The Experience of Nautilus Minerals with regard to ...€¦ · March 2007 Workshop: April 2008 Sept...

45
1 November 10 1 November 2010 © Nautilus 2010 TSX : NUS AIM : NUS The Experience of Nautilus Minerals with regard to Environmental Management for a New Offshore Industry Samantha Smith INTERNATIONAL SEABED AUTHORITY 9 November 2010

Transcript of The Experience of Nautilus Minerals with regard to ...€¦ · March 2007 Workshop: April 2008 Sept...

  • 1November 101November 2010© Nautilus 2010

    TSX : NUS

    AIM : NUS

    The Experience of Nautilus Minerals with regard to

    Environmental Management for a New Offshore Industry

    Samantha Smith

    INTERNATIONAL SEABED AUTHORITY

    9 November 2010

  • 2November 102November 2010© Nautilus 2010

    Forward Looking Information and Disclaimer

    This Presentation may contain forward-looking statements within the meaning of the United States Securities Exchange Act

    of 1934 and forward-looking information within the meaning of applicable Canadian securities law.

    Material forward-looking statements and forward-looking information include, but are not limited to statements or information

    with respect to the Company’s ability to locate, mine and transport ore from the seafloor; estimates of future production; the

    method of transport and amount of ore from the Company’s Solwara project; estimates of anticipated costs and

    expenditures; and development and production timelines.

    We have made numerous assumptions about the material forward-looking statements and information contained herein,

    including those relating to: the future price of copper, gold, silver and zinc; anticipated costs and expenditures; and our ability

    to achieve our goals. Even though our management believes that the assumptions made and the expectations represented

    by such statements or information are reasonable, there can be no assurance that the forward-looking statement or

    information will prove to be accurate. Accordingly you should not place undue reliance on forward-looking statements or

    information.

    Forward-looking statements and information by their nature involve known and unknown risks, uncertainties and other

    factors which may cause the actual results to differ materially from those described in forward-looking statements or

    information. "Risk Factors" are presented in the Company's most recent Annual Information Form, available on SEDAR

    (www.sedar.com). Except as required by law, we undertake no obligation to update forward-looking statements and

    information as conditions change.

    No information in this presentation shall constitute an invitation to invest in Nautilus or any entities of the Nautilus Group.

    Neither Nautilus, nor any entities of the Nautilus Group, nor their respective officers, employees or agents, shall be liable for

    any loss, damage or expense however caused (including through negligence) which you may directly or indirectly suffer in

    connection with this presentation including, without limitation, any loss of profit, indirect, incidental or consequential loss.

    This information is not intended to take the place of professional advice and you should not take action on specific issues in

    reliance on this information.

    While efforts are made to keep the information in this presentation accurate and timely, neither Nautilus nor any of the

    entities of the Nautilus Group guarantee or endorse the content, accuracy or completeness of the information herein. You are

    referred to the Company's documents filed on SEDAR.

    All graphics, effects, processes, information and data in this Presentation are owned or used under license by Nautilus. Any

    reproduction or dissemination, in whole or in part, is strictly prohibited.

    http://www.sedar.com/

  • 3November 103November 2010© Nautilus 2010

    Outline

    Introduction: The Nautilus Experience

    Approvals Process

    EIS Process and Approach to EIA

    Learnings and Next Steps

  • 4November 104November 2010© Nautilus 2010

    THE NAUTILUS EXPERIENCE

  • 5November 105November 2010© Nautilus 2010

    World’s demand for metals continues to rise

    Every human activity impacts on the environment

    Land resources are stretched

    A “new” concept

    Why Go to the Sea?

    Land-based mine Deep sea production

    High tech, high grade, low volume,

    low waste, small footprint

  • 6November 106November 2010© Nautilus 2010

    Nautilus is the first company to commercially explore for Seafloor

    Massive Sulphide (SMS) deposits – HIGH GRADES of copper, gold,

    zinc & silver

    Minimal overburden

    Smaller physical footprint than land-based counterparts

    Minimal social disturbance

    Seafloor Production Makes Sense

  • 7November 107November 2010© Nautilus 2010

    Introduction

    First project: Solwara 1

    Bismarck Sea

    1600 m depth

    30 km from nearest

    coast

    Small extraction area:

    0.11 km20 20 40km

    Konos

    Namatanai

    Rabaul

    Kokopo

    NEW BRITAIN

    NEW IRELAND

    SOLWARA 1 MLA 154

    EL 1374

    EL 1196EL 1196

    EL 1374

    BISMARCK SEA

    PAPUA NEW GUINEA

    BISMARCK SEA

    LOCALITY MAP

    NEW IRELAND PROVINCE

    EAST NEW BRITAIN PROVINCE

  • 8November 108November 2010© Nautilus 2010

    Project Stages

    Exploration

    • What’s there? (Resource, Environment)

    • Low Impact, similar to MSR activities

    Feasibility

    • EIS and Project Feasibility stages

    • More detail Define Project, impacts and benefits

    Extraction• High impact activities

  • 9November 109November 2010© Nautilus 2010

    Exploration

    CTD/ Hydrocast

    BLACK SMOKER

    PLUM

    Ship

    Tow Yo

    ~20m asf

    MAPRs x 3

    PLUME

    CTD, Neph, Eh,

    Niskin bottles

    SMS

    MBES

    Phase A: Target

    Generation: Detailed

    mapping, look for

    chemical signatures

    Phase B: Target Testing:

    Remotely Operated

    Vehicle (ROV): visual

    survey of the seafloor and

    rock sampling

  • 10November 1010November 2010© Nautilus 2010

    Define the Project

    1. Cut up ore on the seafloor.

    2. Ore and seawater go up the pipe to the

    ship.

    3. Ore is separated from seawater on

    board the ship.

    4. Seawater is filtered and discharged back

    to the deep sea (where it came from).

    5. Ore is put onto a barge and taken to the

    Port of Rabaul for temporary storage.

    6. When there is enough ore, the ore is

    picked up from the PoR by a bulk carrier

    and taken to a pre-existing processing

    plant overseas.

    Seafloor Production Tools (SPTs)

    Riser and Lifting System (RALS)

    Production Support Vessel (PSV)

  • 11November 1011November 2010© Nautilus 2010

    APPROVALS PROCESS

  • 12November 1012November 2010© Nautilus 2010

    Legal Process

    Mining Act 1992

    Governs the exploration,

    development, processing

    and transportation of

    minerals

    Environment Act 2000

    Outlines environmental

    requirements of an activity

    EIS takes into account

    social considerations

  • 13November 1013November 2010© Nautilus 2010

    EMP must be submitted and approved before operations can commence

    http://www.clipartguide.com/_small/0808-0710-2914-4641.jpghttp://www.clipartguide.com/_small/0808-0710-2914-4641.jpghttp://www.clipartguide.com/_small/0808-0710-2914-4641.jpghttp://www.clipartguide.com/_small/0808-0710-2914-4641.jpghttp://www.clipartguide.com/_small/0808-0710-2914-4641.jpghttp://www.clipartguide.com/_small/0808-0710-2914-4641.jpg

  • 14November 1014November 2010© Nautilus 2010

    Environmental Management

    APPROVALS KEY ENVIRONMENTAL WORK

    ELAEL

    MLA

    ML

    EIREISEPAEP

    EMP

    MRA DEC

    PRODUCTION

    EIA

    BASELINE

    ONGOING MONITORING

    POST-CLOSURE MONITORING/REPORTING

    TIME

    CLOSURE

    RELINQUISH LEASE

    STAK

    EHO

    LDER

    ENG

    AG

    ENM

    ENT

    EXP

    LOR

    ATIO

    N

  • 15November 1015November 2010© Nautilus 2010

    Environmental Management

    APPROVALS KEY ENVIRONMENTAL WORK

    ELAEL

    MLA

    ML

    EIREISEPAEP

    EMP

    MRA DEC

    PRODUCTION

    EIA

    BASELINE

    ONGOING MONITORING

    POST-CLOSURE MONITORING/REPORTING

    TIME

    CLOSURE

    RELINQUISH LEASE

    STAK

    EHO

    LDER

    ENG

    AG

    ENM

    ENT

    EXP

    LOR

    ATIO

    N

  • 16November 1016November 2010© Nautilus 2010

    EIS PROCESS

  • 17November 1017November 2010© Nautilus 2010

    EIS Objectives

    Define the existing environment

    Estimate impacts of the project to the environment

    Develop strategies to minimise impacts

  • 18November 1018November 2010© Nautilus 2010

    Early, transparent and

    inclusive stakeholder

    engagement

    Inclusive multi-stakeholder

    workshops Communities

    World-renowned experts

    Government

    NGOs

    Ongoing Community

    Awareness and Consultations

    Established CARES

    www.cares.nautilusminerals.com

    Nautilus Approach

  • 19November 1019November 2010© Nautilus 2010

    EIS Process

    Define Project

    ID Potential Impacts

    ID Studies for EIA and Baseline

    Conduct & Write-up Studies

    Recommendations for impact mitigation

    strategies and monitoring

    Review and Submit EIS

    Complete EIS

    ID Potential Stakeholders

    Workshop: March 2007

    Workshop: April 2008

    Sept 2008

    2007 – 2008

    Workshop: Nov 2008

    Marine scientists (incl deep sea), environmentalists, students, social

    scientists, anthropologists, international and local NGOs, government, other

    industry reps, etc.

    Academics and consultants

    Holistic approach with Academics and consultants

    Academics and consultants, Nautilus held workshop, DEC engaged int’l consultant

  • 20November 1020November 2010© Nautilus 2010

    Define the Project

    1. Cut up ore on the seafloor.

    2. Ore and seawater go up the pipe to the

    ship.

    3. Ore is separated from seawater on

    board the ship.

    4. Seawater is filtered and discharged back

    to the deep sea (where it came from).

    5. Ore is put onto a barge and taken to the

    Port of Rabaul for temporary storage.

    6. When there is enough ore, the ore is

    picked up from the PoR by a bulk carrier

    and taken to a pre-existing processing

    plant overseas.

    Seafloor Production Tools (SPTs)

    Riser and Lifting System (RALS)

    Production Support Vessel (PSV)

  • 21November 1021November 2010© Nautilus 2010

    Identify Potential Impacts (note: cartoon only)

  • 22November 1022November 2010© Nautilus 2010

    Identify Studies Needed

    Biology Studies:

    Macrofauna (incl., DNA/genetic studies)

    Benthic Habitat Assessment

    Bioaccumulation

    Bioluminescence

    Existing Resource Utilisation

    Hazard and Risk Assessment

    Hydrodynamic Modelling:

    Cutting

    Dewatering

    Noise and Light

    Oceanography (12 mo, full column)

    Sedimentation Rates (36 mo, ongoing)

    Sediment Chemistry

    Video Survey (>100,000 obs)

    Water Quality

    Additional objective: science will also benefit from additional deep sea

    studies conducted to obtain data for the EIS

    Time Lapse

    Camera

    Sediment

    Trap

    Hard Substrate

    Sampling

    Soft Substrate

    Sampling

  • 23November 1023November 2010© Nautilus 2010

    Achieving Independence

    Independent

    researchers

    Freedom to publish

    Independent reviewers

    Transparency EIS on website

    • Duke University

    • Scripps Institution of Oceanography

    • University of Toronto, Canada

    • WHOI

    • CSIRO, Australia

    • Hydrobiology, Australia

    • University of Papua New Guinea

    • Coffey Natural Systems, Australia

    • Rabaul Volcano Observatory, PNG

    • Asia Pacific Applied Science

    Associates (APASA), Australia

    • Australian National University

    • Curtin University of Technology,

    Australia

    • James Cook University, Australia

    • Charles Darwin University, Australia

  • 24November 1024November 2010© Nautilus 2010

    Report Facts

    Provide expertise (in their area of expertise)

    Decide studies with other stakeholders including government

    Design and Conduct Studies

    Review EIA

    Suggest Management Strategies

    Role of Scientists

  • 25November 1025November 2010© Nautilus 2010

    Limiting the Impacts

    Reference Site

    (S Su)

    Temporary Refuge

    Areas

    Animal relocation

    Artificial substrates*

    EL 1196

    MLA 154

    SOLWARA 1

    Solwara 5

    North Su

    South SuSolwara 9a

    Solwara 9b

    Mining Lease Application

    Existing Exploration Licence

  • 26November 1026November 2010© Nautilus 2010

    Community Awareness

    Major focus

  • 27November 1027November 2010© Nautilus 2010

    Coastal, Shallow- and Mid-Water Environment

    Issues raised during previous

    community consultations:

    Protect marine environments:

    • Reefs and fisheries

    • Whales, sharks and turtles

    Nautilus response:

    “Engineer out” impacts to surface waters:

    • No extraction impact shallower than

    1300 m water depth at Solwara 1

    (below where tuna, etc live)

    Only impact to surface waters:

    presence of vessel, supporting

    vessels and riser pipe

  • 28November 1028November 2010© Nautilus 2010

    Limiting the Impacts

    Filter water prior to

    discharge

    Dewatering discharge –

    25 to 50 m above

    seafloor

    Fast turn-around time

    (limit changes to water)

    500 m exclusion zone

    (no collisions)

    Fully enclosed ore delivery

    system (riser pipe)

    Filter water prior to

    discharge (no chemicals)

    Dewatering discharge – 25

    to 50 m above seafloor

    500 m exclusion zone

    recommended

    (no collisions)

    Mineralised area

    Legend

  • 29November 1029November 2010© Nautilus 2010

    Supporting Education

    Since 2007, three PNG Nationals have

    been awarded the opportunity to study

    at Duke University (USA)

    Learn state-of-the-art techniques under

    supervision of world renowned deep

    sea biologist Dr Cindy Lee Van Dover

    Deep Sea Marine Science seminar at

    the University of PNG

    Initiative short-listed for Asia Mining

    Congress Sustainability Award

  • 30November 1030November 2010© Nautilus 2010

    Concluding Remarks

    Our Measure of Success

    EIS reviewed, with

    commendation

    EIS approved

    Environment Permit granted

    Continue to have positive

    relationships with local

    communities, governments and

    scientific community

  • 31November 1031November 2010© Nautilus 2010

    NEXT STEPS:

    ENVIRONMETNAL

    MANAGEMENT AND

    MONITORING PLAN(S)

  • 32November 1032November 2010© Nautilus 2010

    EMP

    Required under Papua New Guinea legislation

    Identified impacts, brought in external experts to ID

    studies, carry out studies and recommend mitigation

    strategies, monitoring programs, etc.

    Will continue inclusive, multi-stakeholder, proactive,

    transparent approach

  • 33November 1033November 2010© Nautilus 2010

    Learnings/Reminders

    Not a “one size fits all” solution to EMP design

    (Site Specific? Project specific?)

    Impacts will depend on: extraction rate, mode

    of extraction

    Need provision for (realistic) adaptive

    management

    Reference area needs to have same/similar

    conditions as impacted area (biota, nat.

    variations)

  • 34November 1034November 2010© Nautilus 2010

    Experts need to work within their area of

    expertise but...

    There needs to be a holistic understanding of

    the environment and issues

    Efforts to minimise impacts (eg plumes,

    greenhouse gas emissions)

  • 35November 1035November 2010© Nautilus 2010

    Exploration area ≠ Extraction area –

    • There’s a chance plume won’t go outside claim area

    (should this be taken into account when

    selecting/sizing APEIs? Also currents?)

    APEI area relative to the size of impact?

    What if APEI is:

    not representative of area that is impacted?

    the most prospective ground?

  • 36November 1036November 2010© Nautilus 2010

    Solwara 1: Proposed

    Extraction Site

    North Su: Active

    Subsea Volcano

    South Su: Proposed

    Reference Site (not to

    be extracted)

    EL 1196

    MLA 154

    SOLWARA 1

    Solwara 5

    North Su

    South SuSolwara 9a

    Solwara 9b

    Mining Lease Application

    Existing Exploration Licence

  • 37November 1037November 2010© Nautilus 2010

    Non-representative

    area set aside

    EL 1196

    MLA 154

    SOLWARA 1

    Solwara 5

    North Su

    South SuSolwara 9a

    Solwara 9b

    Mining Lease Application

    Existing Exploration Licence

    Reserve Area

  • 38November 1038November 2010© Nautilus 2010

    No commercially-

    viable areas left

    EL 1196

    MLA 154

    SOLWARA 1

    Solwara 5

    North Su

    South SuSolwara 9a

    Solwara 9b

    Mining Lease Application

    Existing Exploration Licence

    Reserve Area

  • 39November 1039November 2010© Nautilus 2010

    Monitoring

    Developed several testable

    hypotheses with international

    experts

    Monitoring requirements as

    required by government

    Monitoring requiring ROV will

    occur during scheduled

    maintenance rotations no

    loss to production

    Will work commitments into

    mine plan

  • 40November 1040November 2010© Nautilus 2010

    THIS FORUM

  • 41November 1041November 2010© Nautilus 2010

    What are the Goals?

    Support development of resources

    Commercially viable*

    Technologically achievable

    Ensure responsible environmental management

    Minimise impacts to the environment

    Maintain biodiversity and overall ecosystem health

    and function

    What do we need to achieve this?

    A Single Environmental Management Plan? – or –

    Over-arching Guidelines and Principles?

  • 42November 1042November 2010© Nautilus 2010

    Questions

    Who will do the work on the APEIs to find out what

    is there and if they are representative?

    Is a contractor likely to go into (spend money in) an

    area that has been “sterilised”?

    “Adaptive APEIs” – does this increase or decrease

    risk? For the contractor? For the environment?

    “Nice to Haves” vs “Need to Haves”?

    Continual Improvement?

    Artificial substrates?

    What proportion of lease area is typically covered in

    nodules?

    Can APEIs be established sequentially?

  • 43November 1043November 2010© Nautilus 2010

    What has been done before?

    ISA guidelines

    IMMS code

    Gorda Ridge EIS

    Solwara 1 EIS

    DSTP Guidelines

    InterRidge Guidelines

    International Maritime

    Legislation

    etc.

    What do we know?

    What are the gaps?

    Seek independent

    expert advice to help

    fill gaps

  • 44November 1044November 2010© Nautilus 2010

    What Makes Good Minerals Policy Framework?

    Clear guidelines, timelines

    Transparency

    Consistency

    Efficiency

    Benefits justify risk(s)

    Environmentally and Socially

    responsible

    Economically viable

    Independence of reviewers

    Agreement from governing body/ies and

    affected stakeholders

    Provision for Adaptive Management

  • 45November 1045November 2010© Nautilus 2010

    nautilusminerals.com

    TSX & AIM : NUS

    A New Industry, Not Just a Project

    p

    www.cares.nautilusminerals.com

    Dr. Samantha Smith

    [email protected]