The Eternity Power Thermal Harvesting™ Project · 2019. 9. 2. · •Smelting •The Smelters...
Transcript of The Eternity Power Thermal Harvesting™ Project · 2019. 9. 2. · •Smelting •The Smelters...
The Eternity Power Thermal Harvesting™ Project
• Jacques Malan
• Director
• Vuselela Energy (Pty) Ltd
• South Africa
Introduction To Vuselela Energy
• Vuselela Energy (Pty) Ltd was conceived in 2009 when the effect of Electricity Supply Shortages on the Metallurgical Industry in South Africa became critical.
• Vuselela acts as a Project Developer and/or Owners’ Engineer for Clean Energy Projects based on Waste Heat and Waste Gas from Industrial Facilities.
• Vuselela works with its Consortium Partners to Design Engineer, Construct and Commission these projects with a Cradle to Grave approach.
• Vuselela offers a number of different implementation models such as EPCM, BOOT, LtO and ECA, depending on client preference.
Introduction To Eternity Power
• Eternity Power (RF) (Pty) Ltd • It is the contracting party with Anglo • Ring Fenced Special Purpose Vehicle • Originally set up by Investec and Vuselela • 80% owned by H1 Holdings (Pty) Ltd • 20% owned by Vuselela Energy (Pty) Ltd
• Claim To Fame • First ORC In South Africa • First ORC on Metallurgical Converter in the World
Waterval Smelting Complex
•“Anglo Platinum” •Rustenburg Platinum Mines Ltd.
•Consists Of: •Concentrator – Mills & Flotation
•Smelting Furnaces
•Anglo Converting Process (ACP)
•Energy Recovery Plant
•Acid Plant
•Base Metals Refinery
Waterval – ACP Section
ERP (Eternity Power) Location
Platinum 101 - From Mining to Metals
•Mining •Ore is Mined at various Anglo Platinum mines.
•Concentrating •Milling & Flotation produce a Concentrate.
•Smelting •The Smelters produce a “Furnace Matte”.
•Converting •The Converters produce a “Converter Matte”.
•Acid Plant •Treats Sulfur-Rich Offgas from Converters
•Refining •Base Metals Refinery produces Nickel, Copper & a “Dirty” PGM.
•Precious Metal Refinery Splits PGMs into Valuable Components
Smelting 101
•What is a Smelter? •Metallurgical Process To Extract Metals From Ore
•Iron & Steel, FeCr, FeMn are “Oxide” Smelting Processes Produces a Metal
•Platinum Smelting is a “Sulfide” Smelting Process Produces a “Furnace Matte”
•Not a Metal yet…. •Furnace Matte needs to be Converted to Metal
•Oxygen Blown Converter Produce “Converter Matte”
Exothermic Reaction Produce Heat
Produce SO2 as Offgas (Source of Energy)
Smelting 101 – Inside a Furnace
Smelting 101 – A Converter In Action
Smelting 101 – Tapping The Metal
Smelting 101 – Tapping The Slag
Smelter Complex Energy Balance • Rough Thumbsuck Figures ONLY!
• Concentrator • Mills & Flotation Major Consumers – Circa 20MW
• No Recoverable Waste Energy Release
• Smelting • Primary Smelting Six-In-Line Furnaces – Circa 60MW
• Secondary Slag Cleaning Furnace – Circa 30MW
• Waste Energy Present in Slag, Matte and Offgas
• Recoverable Waste Energy Estimate at >10MW
• Converters • Small Overall Consumption – Circa 5MW
• Exothermic Reaction with Oxygen
• Recoverable Waste Energy >5MW
• Other Sources Ignored for Simplicity
Thermal Harvesting™ Solutions Primary Heat Exchanger (s)
• Parallel to Existing Cooling System for Redundancy. • High Efficiency Exchange Design. • Innovative Solutions for High Dust Loads. • Abrasion, Erosion and Blanking Prevention. • Process Guarantees by Supplier.
Existing Un-cooled Ducting (Patented) • High Heat Loads Causing Deformation. • Frequent Replacement Requirements. • Potential Source of Low-quality Heat. • Harvesting with Thermal Medium.
Liquid Metal and Slags (Patented) • Most Dangerous Operation at any Smelter • Challenging Environment to Harvest Effectively • Demonstration Plant Under Development
Organic Rankine Cycle System
Mature Technology • Proven Technology • >30years in Operation • >96% Availability Guaranteed • >17% Nett Conversion Efficiency • Highly Flexible Operation • >97% Turndown Ratio • Direct Feed to On-Site Grid • Black Start and Island Mode Capability
Plant Design Capacity • Depending on Available Heat Load. • Additional Harvesting Points. • Single Unit vs Modular Units.
Thermal Harvesting™ Advantages
16
Competitive Effective Electricity Price • Zero Capex Required from Producer.
• Zero Opex or Maintenance from Producer.
• Pricing Competitive with Eskom from Startup.
• Predictable Escalation for 15 years.
• Results in Predictable Pricing Forecast.
Security of Supply • Guaranteed Output Capacity.
• Guaranteed Conversion Efficiency.
• Guaranteed Availability.
Typical ORC Flowsheet
Eternity Power H&M Balance
Plant Parameters
Design Point Max. Min.
ERP Inlet Temperature 255°C 275°C
ERP Outlet Temperature 240°C or higher pending thermal load
Mass Flow Rate 1, 200 t/h 1,450 t/h 810 t/h
Pressure at inlet 62 bara
Thermal Load 23.36 MW 25.7 MW
Power Output (output at generator terminals) 4.29 MWe 4.9 MWe
Design Ambient Temperature (Dry bulb) 17°C 45°C 0°C
Elevation 1,157 masl
Balance Of Plant Flowsheet
PI
TIT
DHP-323-004 – 450-BL4
DHP-323-060-450-BL4
ORC
VENDOR
PACKAGE
PITIT
PI
PIT
YC
PI
PIAL PI
TIC
YC
DHP-000-003– 350-BL4
YC YC
PITIC
PIFIT
YC
PI
FI
PIPIT
PRESSURIZATION LINE
A
FE
INSTRUMENT AIR
PI
PI001 001001
001001001
003 004
EPS
001 E
028
029
030
031
A
010
012
FO
E034
035013
014 015
E017
018
032
033
A
002003
002005
019
FC
021
020
EPS
ATM
027
025
024 026
ATM
016
BL-005
BL-002
BL-001
DHP-000-001– 350-BL4
00-PV-001
IA
M
00-HX-001
G
023
350
450
450
350
EPSBL-004
DH
P-0
00
-00
2–
35
0-B
L4
022
001 FC
005
002
IA
EPSBL-004
PI
FIQ001
061
060
AHHAHAL
M
PI
FIT
PI
FI
YC
002
002
FE002
PI
TIT
PI
TIC
YC
005
005
PI
TIT
PI
TIC
YC
006
006
PITIT
YC
PITIC003
003PITIT
YC
PITIC004
004
062 063
PRESSURIZATION LINE
064 065
10 D CLEARANCE
10 D CLEARANCE
06
60
67
Eternity Power SCADA
Plant Layout – 3D
Graphic Plant Overview
Graphic Plant Overview
Graphic Plant Overview
Graphic Plant Overview
Graphic Plant Overview
Graphic Plant Overview
Graphic Plant Overview
Background Story
• Formed Vuselela Energy in 2009
• Approached Anglo in 2010
• Completed Feasibility in 2011
• Approached Investec in 2011
• Signed HoT with Anglo in 2011
• Bankable Feasibility in 2012
• Signed Contracts in 2012
• Started Construction in 2013
• Many Delays in 2013 and 2014
• Finally Commissioned in 2015
Key Milestones • Project Development
• Feasibility Report (VE) March 2012 • Feasibility review (Anglo) April 2012 • Final Feasibility Report (VE) April 2012 • Feasibility approval (Anglo) August 2012 • Project Documents October 2012 • Financial close December 2012
• Project Implementation • Groundbreaking August 2013 • ORC delivery to site (3 shipments) October 2013
November 2013 January 2014
• Ready for commissioning May 2015 • Commercial Operation Date (COD) June 2015
Construction Challenges • The MHSA Factor – 8 weeks
• Extremely Rigid Requirements • Unfortunate Stoppages
• Rain Delays – 3 weeks • Minimum – Better Than Expected
• Strike Action – 5 weeks • Within Manageable Levels
• Underground Conditions – 4 weeks • 6m Deep Pump Foundations
• Incompetent Contractor – 24 weeks • Be Extremely Careful with Selection Process • At The First Sign Of Trouble – KICK THEM OUT!!!
Construction Challenges
Typical Operational Fluctuation
Operational Results Extract
Month Dec Cummulative (MWh) Gross 8151.48
Nett 7234.48
Production (MWh) Gross 1226.43
Nett 1097.26
MW Peak Gross 4.36
Nett 3.96
Ave Prod (MWh) Gross 2.66
Net 2.37
Ave Efficiency (%) Gross 22.14%
Nett 19.41%
ERP Availability Ave 99.9%
ERP Utilization Ave 56.6%
Ambient Temp [°C] Ave 28.43
Questions ??
Strictly Confidential & Proprietary-
Property of EPS (Pty) Ltd and/or Vuselela Energy (Pty) Ltd
All Rights Reserved