The Engine Design Statement

download The Engine Design Statement

of 30

Transcript of The Engine Design Statement

  • 8/13/2019 The Engine Design Statement

    1/30

    The Engine

    New DockDesign Statement

    December 2013

  • 8/13/2019 The Engine Design Statement

    2/30

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    ContentsIntroduction 01

    The Engine .......................................................................................01Site Plan 02

    New Dock ........................................................................................02

    Existing Building 03

    Facade Study ..................................................................................02

    i + 04

    Cotton Building .............................................................................. 03

    Concept ...........................................................................................04

    Precedent Images 05

    Internal Fit-out .................................................................................06

    Floor Plans 06

    Ground Floor | Existing / Proposed ............................07 / 08

    First Floor | Existing / Proposed ...........................0 9 / 10

    Second Floor | Existing / Proposed .............................11 / 12

    Third Floor | Existing / Proposed ............................13 / 14

    Roof | Existing / Proposed .............................15 / 16

    Environmental | Services 07

    As Proposed ....................................................................................17

    Perspectives 08

    External Strategy ............................................................................ 18

    Elevations 09

    North | Existing / Proposed ........................................................19

    East | Existing / Proposed ........................................................ 20

    South | Existing / Proposed .........................................................21

    West | Existing / Proposed ......................................................... 22

    Sketch Perspectives......................................................................23

    External Views 10

    External Strategy 11

    As Proposed / Precedence .........................................................24

    As Proposed ...................................................................................25

    As Proposed 1:50 ......................................................................... 25

    Sustainability Statement 12

    Change of Use of Ground Floor Commercial Units............... 26

    Additional Information 13

    Drawing List .....................................................................................27

    Cartwright Pickard Architects ......................................................27

  • 8/13/2019 The Engine Design Statement

    3/30

    01

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    New Dock - Existing Infrastructure

    1.0

    INTRODUCTIONThe Engine

    INTRODUCTION

    This Document has been prepared by Cartwright PIckard

    Architects in support of a Planning Application for the proposedconversion of an existing casino (use class Sui Generis) intooffice accomodationon ( use class B1) within New Dock onbehalf of Clarence Dock Estates LLP.

    New Dock is just a 15 minute walk, south east of Leeds CityRailway Station and home to the Royal Armouries Museum,New Dock is a stuning waterfront development with an ethoscentred around creativity, culture and energy.

    The proposed office accommodation named, the Engine is tobe a hub for emerging industries seeking innovative workspacein an unrivalled setting. Open, bright space to think, networkand innovate. A new, flexible workplace that will appeal to abrand - conscious and an expanding sector creating a vibrantand creative community.

    This report sets out to demonstrate key design principlesproposed as part of the conversion work comprising of internalchanges to floor plans and to the external envelope to meet therequirments of theoffice concept.

  • 8/13/2019 The Engine Design Statement

    4/30

    02

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    2.0

    Site PlanNew Dock

    Existing Site

    The existing building was previoiusly used as a Casino whichbecame vacant in 2013. There is an existing Food Retailer on

    some of the ground floor accomodation. The building sits along

    side the existing primarily residential accomodation.

    New Dock

    Acquired by Clarence Dock Estates in 2012, New Dock

    comprises of a unique vision, bringing forward a range of

    proposals as part of a comprehensive vision for the future

    of the area. Including contemporary workspaces for modern

    industry, leisure space, a new gym, waterside rest aurants and

    bars, retail and cafe street and a new arcade which will create

    a mix of uses.

    Sun Path

    The existing building has a predominant North/South axis,

    slightly offset, providing a predominant West and South

    elevation exposed to direct sunlight.

    Routes

    Vehicular

    Immediate public transport links

    Immediate access off Armouries Drive

    Plentiful adjacent public car parking with direct building

    access

    New Generation Transport (NGT) is the citys key

    transformational project connecting the North and South

    of Leeds including a stop at New Dock.

    Pedestrian

    Key pedestrian route, with controlled vehicular access,

    along the key west elevation

    Pedestrian route along Armouries Drive

    Predominant permeability from the central New Dock

    promenade.

    Pedestrian Route

    Vehicular Route

    Service Access

    CAR PARK(1, 600 SPACES)

    ArmouriesDrive

  • 8/13/2019 The Engine Design Statement

    5/30

  • 8/13/2019 The Engine Design Statement

    6/30

  • 8/13/2019 The Engine Design Statement

    7/30

    05

    cartwright pickardarchitects

    The Engine, Leeds Dock

    Design Report | Rev - | December 2013

    05

    cartwright pickardarchitects

    Design Report | Rev - | December 2013

    The i+ concept

    Agile

    Adaptable

    Flexible

    Diverse

    Central

    Control

    Choice

    Culture

    Investable

    Innovative flexible workspace building

    Flexible fit out options

    Adaptable

    High level of natural daylight

    Raised floors

    Exposed high level services

    Raw finishes

    1. 2. 3.

    4.

    4.0

    i+

    Concept Summary

  • 8/13/2019 The Engine Design Statement

    8/30

    06

    cartwright pickardarchitects

    The Engine, Leeds Dock

    Design Report | Rev - | December 2013

    06

    cartwright pickardarchitects

    Design Report | Rev - | December 2013

    1.

    4. 5.

    7.

    6.

    8.

    9.

    2. 3.

    5.0

    Precedent ImagesInternal Fit-out

    TMT - Technology, Media, TelecommunicationsTechnology is constantly evolving and companies aim to

    evolve with it, it follows that buildings must be adaptable toavoid becoming obsolete over time.

    Key Features:

    agile

    adaptable

    flexible

    diverse

    central

    control

    choice

    culture

    investable

  • 8/13/2019 The Engine Design Statement

    9/30

    07

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Ground Floor As Existing - NTS

    6.0

    Floor PlanGround Floor As Existing

    a.

    c.

    d.

    b.

    Accommodation Key

    a.Casino

    b.Retail

    c.Service Yard / Deliveries

    d. Existing Car Park

  • 8/13/2019 The Engine Design Statement

    10/30

    08

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Key Design Proposals

    1. New Main Entrance

    2. Casino entrance removed

    3. External Raised steps removed

    4. External Doors Removed

    5. New male and female WCs

    6. New illuminated signage board

    7. New building signage suspended from steel truss on

    roof

    8. New infill floor structure (shown hatched)

    9. New windows

    10. New glazed curtain wall

    11. New meeting pod balconies

    12. New lantern over stair core

    NIA - Existing NIA - Proposed GEA

    1464 1464 1847

    Accommodation Key

    a. Business Lounge

    b. Feature Stairs

    c. Sky Reception

    d. Cafe / Deli

    e. Meeting Room

    f. Seminar Room

    g. WCs

    h. LiftsGround Floor As Proposed - NTS

    6.0

    Floor PlanGround Floor As Proposed

    i. ii. iii.

    d.b.a.

    e.

    f.

    g.

    h.

    c.

    5.

    2.

    1. 4.

    4. 3.

  • 8/13/2019 The Engine Design Statement

    11/30

    09

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    First Floor As Existing - NTS

    6.0

    Floor PlanFirst Floor As Existing

    Accommodation Key

    a.Casino

    a.

  • 8/13/2019 The Engine Design Statement

    12/30

    10

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Key Design Proposals

    1. New male and female WCs

    2. New illuminated signage board

    3. New building signage suspended from steel truss on

    roof

    4. New infill floor structure (shown hatched)

    5. Opening over entrance area below

    NIA - Existing NIA - Proposed GEA

    1605 1596 1900

    First Floor As Proposed - NTS

    Accommodation Key

    a. Office

    b. Feature Stairs

    c. Meeting Rooms

    d. WCs

    e. Lifts

    6.0

    Floor PlanFirst Floor As Proposed

    3.

    5.

    1.

    4.

    2.

    a. a.

    b.

    c.

    d.

    e.

  • 8/13/2019 The Engine Design Statement

    13/30

    11

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Mezzanine As Existing - NTS

    6.0

    Floor PlanSecondAs Existing

    Accommodation Key

    a.Casino

    a.

  • 8/13/2019 The Engine Design Statement

    14/30

    12

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Mezzanine As Proposed - NTS

    6.0

    Floor PlanSecondAs Proposed

    Key Design Proposals

    1. New male and female WCs

    2. New illuminated signage board

    3. New building signage suspended from steel truss on

    roof

    4. New windows

    5. New meeting pod balconies

    NIA - Existing NIA - Proposed GEA

    914 1281 1900

    - 367 sqm of additional floor space due to the filling in of t he

    void in the floorplate of the existing building.

    3.

    5.

    2.

    8.

    b. b.

    c.

    8.

    8.

    4.

    1.

    4.4.

    a.

    a. e.

    d.

    Accommodation Key

    a. Office

    b. Meeting Pods

    c. Internet Radio Studios

    d. News Desk

    e. Feature Stairs

    f. WCs

    g. Lifts

    g.

    f.

  • 8/13/2019 The Engine Design Statement

    15/30

    13

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Second Floor As Existing - NTS

    6.0

    Floor PlanThird Floor As Existing

    Accommodation Key

    a.Casino

    a.

  • 8/13/2019 The Engine Design Statement

    16/30

    14

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Second Floor As Proposed - NTS

    2.

    3.

    4.

    10.

    1.

    6.0

    Floor PlanThird Floor As Proposed

    Key Design Proposals

    1. New male and female WCs

    2. New building signage suspended from steel truss on

    roof

    3. New glazed curtain wall

    4. Void to office below

    NIA - Existing NIA - Proposed GEA

    1562 1545 1860

    Accommodation Key

    a. Office

    b. Screening Room

    c. Meeting Rooms

    d. Feature Stairs

    e. WCs

    f. Lifts

    a.

    a.

    b.

    d.

    e.

    f.

    c.

  • 8/13/2019 The Engine Design Statement

    17/30

    15

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Roof As Existing - NTS

    6.0

    Floor PlanRoof As Existing

  • 8/13/2019 The Engine Design Statement

    18/30

    16

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Roof As Proposed - NTS

    6.0

    Floor PlanRoof As Proposed

    1.

    2.

    Key Design Proposals

    1. New building signage suspended from steel truss on

    roof

    2. New lantern over stair core

    NIA - Existing NIA - Proposed GEA

    Ground 1464 1464 1847

    First 1605 1596 1900

    Second 914 1281 1900

    Third 1562 1545 1860

    In summary there is 341 sqm of additional floor space due

    to the filling in of the void in the f loor plate of the existing

    building.

  • 8/13/2019 The Engine Design Statement

    19/30

    17

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Typical Section as Proposed - NTS

    Environmental Strategy as Proposed Services Calculation

    Net Internal Areas

    Level NIA sqm Workplaces @ 1:6

    Ground 1,464 244

    First 1,596 266

    Second 1281 213

    Third 1,545 257.5

    Total 5,886 981

    WC Calculation (from BS 465-1:2006)

    Option 1: Seperate sex facilities

    120% occupancy provision, i.e 60% men and 60% women

    Therefore 588 men + 588 women

    Women: 27 WCs and washbasins (7 per floor)

    Men: 14 WCs, urinals and washbasins (4 per floor)

    Option 2: Unisex facilities

    Assume100% provisionTherefore 981 men & women

    42 WCs and basins in self contained cubicles with full

    height walls and doors (11 per floor)

    Toilets for disabled people

    Within the total WC provision given above:

    At least one wheelchair-accessible unisex toilet at each floor

    At least one ambulent disabled WC cubicle in both male and

    female seperate sex toilets

    One larger WC cubicle 1200mm wide in b oth male and

    female seperate sex toilets

    Existing ductwork and nozzles to be

    retained where possible.

    Existing Steel structure exposed and re

    finished where required.

    Existing plasterboard ceiling removed to

    expose services.

    New linear pendant lighting to Office

    specification.

    Existing raised access floor tested and

    retained where possible

    New small power, data and floorboards.

    7.0

    Environmental | ServicesAs Proposed

  • 8/13/2019 The Engine Design Statement

    20/30

    18

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    8.0

    PerspectivesExternal Appearance

    01. 02.

    03. 04.

    Strategy Development

    We have looked at the facade designed for use as a casino

    and believe additional glazing is required to meet daylighting

    levels in the office. Some of the solid panels of cladding on

    the west facade need to be substituted for glazing.

    Also the amount of glazing needs to be considered with the

    impact of solar gain and heat loss. The strategies below show

    an option on how this could be developed.

    01. All existing transparent glazing replaced by glass with

    a relatively low light transmittance (circa 40%). This

    will be visible as a tint to the glass.

    02. Proportion of opaque glazing increased on facades to

    reduce light transmittance internally.

    03. Existing glazing retained and external shading

    introduced. Eg. metal mesh screens suspended from

    roof overhang.

    04. Sketch perspective showing additional brise soleil

    which is to be the option to be progressed with.

    Design Response

    The proposed external appearance is in response to

    the conversion of the existing casino into new office

    accomodation. Situated due east of the site is Clarence Dock

    Car Park which features an external mesh cladding over the

    south facing elevation. We are proposing to use a similar

    material over the south and west facades of the existing

    casino to help the office environment and reduce the solar

    gain to the building.

  • 8/13/2019 The Engine Design Statement

    21/30

    19

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    North Elevation As Proposed - NTS

    North Elevation As Existing - NTS

    2.

    1.

    3.

    4.

    5.

    9.0

    ElevationsNorth Facade | Existing / Proposed

    Key Design Proposals

    1. Casino entrance removed

    2. New illuminated signage board

    3. New building signage suspended from steel truss on

    roof

    4. New windows

    5. New solid copper cladding

  • 8/13/2019 The Engine Design Statement

    22/30

  • 8/13/2019 The Engine Design Statement

    23/30

  • 8/13/2019 The Engine Design Statement

    24/30

    22

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    7.

    1.

    1.

    2. 4.

    6.

    3.

    5.

    8.

    West Elevation As Proposed - NTS

    West Elevation As Existing - NTS

    9.0

    ElevationsWest Facade | Existing / Proposed

    Key Design Proposals

    1. New Main Entrance

    2. Casino entrance removed

    3. External Raised steps removed

    4. External Doors Removed

    5. New illuminated signage board

    6. New building signage suspended from steel truss on

    roof

    7. New glazed curtai n wall

    8. New lantern over stair core

  • 8/13/2019 The Engine Design Statement

    25/30

  • 8/13/2019 The Engine Design Statement

    26/30

  • 8/13/2019 The Engine Design Statement

    27/30

  • 8/13/2019 The Engine Design Statement

    28/30

    26

    cartwright pickardarchitects

    The Engine, New Dock

    Design Report | Rev - | December 2013

    Change of Use of Ground Floor Commercial Units.

    BREEAM and Sustainability as Provided.

    Introduction12.1 This Sustainability Statement (the Statementsupports an application made by Clarence Dock Estates LLP(the Applicant) to Leeds City Council for Planning Permissionfor a change of use in relation to the former Casino at NewDock (formerly Clarence Dock) in Leeds City Centre.

    12.2 In accordance with Policies GP11 and GP12 ofthe Leeds Unitary Development Plan Review (UDPR) (2006),the application should be supported by a SustainabilityAssessment that considers the principles of the SustainableDesign and Construction Supplementary Planning Document(2011).

    12.3 This Statement addresses the requirements of Leedsadopted planning policy, and identifies measures that will be

    incorporated into the proposals within the limited scope thatthe nature of the application allows.

    Design Considerations12.4 The proposals seek a change of use the Casino intoOffice works space at New Dock in Leeds. Limited externalalterations are proposed as a result of this application.The application proposals are an essential element of theMasterplan and strategy for revitalising the commercial offer atNew Dock, which will seek to enhance the productive life of anexisting large building which has recently become vacant. Thisrecycling of buildings is considered inherently sustainable.

    Renewable Energy and Energy Efficiency12.5 Due to the restrictions imposed by the existing siteconditions, and the limited benefits they would bring it is notconsidered viable or feasible to incorporate renewable energymeasures at the present time. It is therefore not proposed toinstall any renewables.

    12.6 The application is supported by a Framework TravelPlan, which incorporates measures to encourage the wideruse of bicycles, including through the promotion of the existingshort and long-stay cycle parking spaces at New Dock andthe potential for new cycle racks and shower / locker facilitieswithin the proposed B1 office units.

    Materials12.7 The proposals are for a change of use of the existingCasino building, and the structure is to be retained, with limitedchange in materials. Whilst the retained materials might not be

    the most optimum in terms of environmental performance, theirretention and reuse is vital to the scheme and is the most viable

    and sustainable option.

    Surface Water12.8 No changes to the existing arrangements for surfacewater run-off approved as part of the construction of ClarenceDock are proposed.

    12.9 A separate application relating to a series of publicrealm works is due to be submitted imminently, which willpropose the introduction of soft landscaping components tothe New Dock public realm. As well as enhancing the externalenvironment, these works will reduce the amount of hardstandingand provide a more permeable surface that should aid surfacewater run-off.

    Waste Management12.10 Operational waste management will continue to behandled in the same way as existing and previously approved

    at New Dock. Separate waste and recyclable waste storageis incorporated into the existing development.

    Health and Well-being12.11 Since the change of use supports more daytimeactivities than the previous casino usage, the impact thebuilding makes on surrounding users will reduce.The internal spaces are being carefully reviewed to providemaximum daylighting for office users through introduction ofinternal lightwells and some new windows to the rear, andthrough arranging workspace areas to gain views wherefeasible.

    Existing site-wide security and safety measures will bemaintained to support this change of usage. The surroundingpublic realm is pedestrianised, with good external spacesincluding close proximity to canal and dockside .

    Transport12.12 The application is supported by a Framework TravelPlan, which sets out a range of measures that could beimplemented at the development and sets out procedures thatwill be introduced to allow the Travel Plan to be implementedand developed.

    12.13 The Framework Travel Plan proposes measures t o: Manage access provision and transport requirements; Reduce travel impact on the locality, and; Encourage more sustainable travel solutions.

    12.14 The Framework Travel Plan includes measures relating

    to walking, cycling, bus, train, car sharing as well as otherinitiatives.

    12.15 The administration of the Travel Plan will initially bethe responsibility of the developer; in this case Clarence DockEstates LLP. The responsibility of the delivery of the TravelPlan will then be t ransferred from the management companyto each respective organisation once operational. In addition,each occupier will be required to designate a Travel Co-ordinator and complete a company travel plan in accordancewith the approved Travel Plan.

    Ecology12.16 At present there are limited ecological features withinthe New Dock development, with the public realm predominantlyconsisting of hard landscaping.

    12.17 The wider Masterplan and proposals for New Dockwill enhance biodiversity on-site within the given constraints.Proposals will include the provision of communal gardens

    incorporating a herb garden, planting sculptured planters andlawns.

    Breeam12.18 It is recognised that BREEAM is predominantly aimedat new buildings and major refurbishments where there isgreater scope to influence the environmental performance andimpact of a building. The opportunities to score highly underBREEAM will therefore be constrained by the existing buildingand site.

    12.19 Major refurbishment is defined by BREEAM asremodelling of both the fabric and primary building servicesto improve the energy performance of a building. Given theage of the building, limited alterations to the fabric and buildingservices are currently proposed. The project will thereforemost likely be assessed under the BREEAM Fit-out criteria.

    12.20 It is acknowledged that within the Leeds City CouncilSustainable Design SPD, a minimum BREEAM rating of VeryGood is recommended. Due to the re-use of materials andurban location, the development will inherently fair well underMaterials and Transport. However, it is noted that the existingbuilding fabric/form and building services will likely hindergood performance under the two key categories of Energyand Health & Wellbeing. As such, further studies will be likelyto gain a better understanding of whether a rating of BREEAMGood or Very Good is to be achieved.

    12.0

    SUSTAINABILITY STATEMENTBuro Happold

  • 8/13/2019 The Engine Design Statement

    29/30

    27

    cartwright pickardarchitects

    The Engine, New DockDesign Report | Rev - | December 2013

    Drawing List697-AP-0001 Location Plan697-AP-0010 Existing Ground Floor Plan697-AP-0011 Existing First Floor Plan697-AP-0012 Existing Second Floor Plan697-AP-0013 Existing Third Floor Plan697-AP-0015 Existing Roof Plan697-AP-0020 Existing North Elevation697-AP-0021 Existing East Elevation697-AP-0022 Existing South Elevation697-AP-0023 Existing West Elevation697-AP-0110 Proposed Ground Floor Plan697-AP-0111 Proposed First Floor Plan697-AP-0112 Proposed Second Floor Plan697-AP-0113 Proposed Third Floor Plan697-AP-0115 Proposed Roof Plan697-AP-0116 Proposed Section AA697-AP-0117 Proposed Section BB697-AP-0120 Proposed North Elevation697-AP-0121 Proposed East Elevation697-AP-0122 Proposed South Elevation697-AP-0123 Proposed West Elevation

    Cartwright Pickard Architects

    Round Foundry Media CentreFoundry StreetLeeds LS11 5QPUnited Kingdom

    T: 0113 394 4380

    E: [email protected]

    1. 2. 3.

    4. 5. 6. 9.

    7. 8.

    1.High Fisher Gate

    2. | 3. | 4. Wakefield

    One

    5. | 7. | 8.London

    Metropolitan University

    6.Cotton Building

    13.0

    Additional InformationDrawings and Programme

  • 8/13/2019 The Engine Design Statement

    30/30

    cartwrightpickardarchitects

    London Office

    1 Canal Side Studios8-14 St Pancras WayLondon NW1 0QGUnited Kingdom

    T: 0207 554 3830F: 0207 388 9312E: [email protected]

    www.cartwrightpickard.com

    Leeds Office

    Round Foundry Media CentreFoundry StreetLeeds LS11 5QPUnited Kingdom

    T: 0113 394 4380

    E: [email protected]

    www.cartwrightpickard.com

    Manchester Office

    23 New Mount StreetManchesterM4 4DEUnited Kingdom

    T: 0161 953 6649F: 0161 953 6649E: [email protected]

    www.cartwrightpickard.com