_The Design of Subways_ (1918)

download _The Design of Subways_ (1918)

of 6

Transcript of _The Design of Subways_ (1918)

  • 8/13/2019 _The Design of Subways_ (1918)

    1/6

    Search

    Return to: Home> The Dual Contracts> DualContracts News (1910-1918)

    "The Design of Subways" (1918)

    THE DESIGN OF SUBWAYS

    PUBLIC SERVICE RECORD VOL. V, NO. 10/11, OCTOBER/NOVEMBER, 1918

    By Julius Glaser

    Designing Engineer, Division of Designs

    Why do we build subways? They're expensive. They cost several times as much,

    mile for mile, as elevated railroads, and their construction entails more inconvenience

    to the public and to business, and for a longer time. They interfere with and endanger

    the sewers, gas pipes, water mains, electric conduits, and other subsurface

    structures, for an extended period, and then, when finally completed, many people

    dislike to ride in them.

    Yet we build subways, because, when finished, unlike elevated railroads, so far

    as street conditions are concerned, they are noiseless, invisible and do not obstruct

    light, air or traffic. Train operation is never interfered with by weather conditions, and

    real estate along the route is enhanced in value. The permanent advantages ofunderground railroads far outweigh the temporary inconveniences during the

    construction period.

    A rapid transit system, however, would be too expensive if it consisted entirely

    of subways. A well-balanced system should consist of subways for the congested

    parts of a city, with elevated extensions and feeders for the outlying and more open

    portions. Development of the open portions and a corresponding rise in realty values

    soon follow the construction of the elevated extensions.

    Profile of Line.Once the route of the subway has been decided upon, the first

    consideration in its design is the determination of its profile. The greatest single

    determining factor in the cost of subways is excavation, with the exception, perhaps,

    of underpinning in narrow streets flanked by tall buildings. Both items should be

    minimized by keeping the structure as close to the street surface as possible. In fact,

    it should follow the contour of the surface, unless excessive grades result thereby.

    Only enough room should be left between the street surface and the roof of the

    structure to allow proper restoration of the usual subsurface structures. Special

    attention must be paid to trunk sewers, and other existing or proposed subways

    passing under or over the subway under consideration.

    In narrow streets the width of the structure can be reduced by double-decked

    construction. This leaves sufficient room on the sides for restoration of pipes which

    would otherwise have to be placed on top of the structure. In this way the amount of

    excavation is reduced, because the structure does not need to be depressed on

    account of the largest pipes. In the case of double-deck subways, the express tracks

    are usually placed on the lower level and can be tunneled so as to avoid heavy

    grades, while the local tracks should preferably follow the street surface contour, on

    account of the stations.

    Near Surface at Stations.At stations, the structure should be very close to

    the street surface, so as to reduce to a minimum the number of steps at the

    entrances. The use of elevators and escalators should be avoided as much as

    possible, because of the enormous increase in the cost of operation which they

    involve. At the stations where island platforms are called for, the structure must be

    depressed to allow for mezzanines. The necessity for future mezzanines should be

    carefully studied, and proper provision made in the determination of the profile that

    they may be constructed later if desired. In this connection, special attention should

    be called to terminal stations where the island platforms are connected at one end bya passage at the same level as the platforms. If no provision were made for a

    mezzanine, an extension of the line would necessitate a resort to sub-passages.

    These should be avoided, because they involve extra stair climbing by the traveling

    public.

    Navigate the Site History Stations Maps Cars Behind the Scenes

    Transfer Station

    9/29/2010 "The Design of Subways" (1918)

    nycsubway.org//psr_design.html 1/6

  • 8/13/2019 _The Design of Subways_ (1918)

    2/6

    Typical express station, four track structure.(Click image to enlarge.)

    As to Grades.Where the subway passes under private property, it should be

    depressed sufficiently to allow for a basement to the building, unless the property

    value does not warrant it.

    In order to obtain proper drainage, the grades of the profile should not be made

    less than 0.3 per cent, preferably not less than 0.75 per cent, but the latter is not

    always desirable for other reasons.

    The profile might be affected also in some localities where there is rock or good

    soil under soft material, in that the structure might be depressed sufficiently to gain

    the advantage of a good bottom.

    The grades between stations should generally be not greater than about 3 per

    cent. More than that seriously affects the cost of operation. But at times it is

    necessary to make the grades at least 4 and sometimes 5 per cent. At stations and

    station approaches, grades should not be more than 0.75 per cent so that trains will

    not creep when the brakes are off. Grades in excess might be used when they are

    balanced about a high point. At all breaks in grade, vertical curves should be used

    with a maximum rate of change of 4 per cent. This maximum is generally employed at

    the ends of stations where it is desired to change the grade as quickly as possible so

    as to avoid excavation, and, for the same reason, also at points where the structure

    passes under other subways and especially below water. Vertical curves should be

    kept off stations entirely, if possible, so that the platforms can be built straight.Crossings at grade should be avoided.

    Alignment of Subways. In working out the alignment for subways the object

    of prime importance is to get a good operating track. This is obviously obtained by

    keeping the line as straight as possible and by using large radii.

    In justice to the owners of abutting property, it is ordinarily endeavored to keep

    the structure centered on the street so that the interference to the building vaults

    under the sidewalks will be a minimum and will affect both sides of the street alike.

    This is, however, not always possible, especially where the line runs through a narrow

    and winding thoroughfare. In such cases, it often becomes necessary to disregard the

    center line of the street and run out a series of tangents in such a way as to reduce

    the number of curves and enable the use of large radii.

    Where Curves Occur. Curves occur either at changes in the direction of the

    street or of the line itself. Where the line turns off, curves become necessary and the

    structure must generally pass under private property. The radii then depend on

    property values in the particular locality. At all curves in the line, care must be taken

    that the tracks are spaced far enough apart to allow for end and center excesses, as

    well as excess due to super-elevation, in addition to the standard clearances and

    construction. At stations located on curves, center and end excesses make the

    platform construction such that the gap between the car body and the platform edge

    is a possible source of danger to passengers. For this reason, curves at stations

    should be avoided if possible. At ends of island platforms, however, it is generally

    necessary to use curves, so as to narrow the structure quickly. In such cases, care

    must be taken that the gap is not large enough to be dangerous.

    9/29/2010 "The Design of Subways" (1918)

    nycsubway.org//psr_design.html 2/6

  • 8/13/2019 _The Design of Subways_ (1918)

    3/6

    Typical four track double deck subway.(Click image to enlarge.)

    Curves also occur where loops are used. The advantage of loops is that trains

    are enabled to reverse direction without holding up traffic behind them. When used,

    they are located either at terminals or at points from where it is desirable to return

    some but not all of the trains in operation.

    Location of Storage Yards. Storage yards are generally built near the

    terminals of the elevated railroad extensions. It is necessary, however, to provide

    emergency storage tracks at convenient points along the line, so that disabled trains

    can be switched off quickly and not hold up traffic. Emergency storage tracks are also

    useful for the purpose of adding extra trains to the service during rush hours.

    In order to obtain good and economical operating conditions, no curve of less

    than 150 feet radius should be used, and all curves of less than 2,000 feet radius

    should be transitioned. Reverse curves should be separated by a tangent as long, at

    least, as the distance between car trucks, so as to give the train a chance to

    straighten out before reversing.

    Placing of Crossovers.In addition to providing for full interchange between all

    tracks, by means of crossovers at terminals, crossovers should also be located at all

    points where a change in heavy traffic is expected, so that trains can be reversed

    from these points. Besides these crossovers, others allowing for full interchange

    should he placed about a mile apart for emergency purposes, so as to make operationof a part of the line possible in case of accident. Crossovers on running tracks should

    not have a smaller frog than number eight, while for emergency a number six frog is

    sufficient. Larger frogs are, of course, desirable, but, in subways, owing to the length

    of crossovers, large frogs mean a more expensive structure. In this connection, it

    should also be pointed out that for the sake of economy crossovers should be so

    located that if possible not more than two tracks need to be spanned by the roof

    beams. From an operating point of view, special frogs should be avoided and the

    number of different kinds be a minimum, so that only a small stock is necessary for

    renewal.

    As stated before, all curves of less than 2,000 feet radius should be transitioned

    on account of super-elevation. A length of 150 feet is generally sufficient to gain this

    result, although shorter ones, even curves half that length, are giving satisfaction.

    This, of course, is not possible at crossovers and at points of reverse curves.

    Type of Structure. The determination of the standard type of structure to be

    used between stations, except at fan chambers, duct manholes and pump chambers,

    is subject to the nature of the ground, the depth of the subway, the width of the

    street, the relation of the structure to mean high water or to ground-water, thenumber of subsurface structures to be maintained and the general traffic conditions.

    When the subway is near the street surface, in earth and above water, the

    most economical structure has been found to be one composed of steel bents, 5-foot

    centers, connected by concrete arches. Each steel bent consists of roof beams,

    sidewall columns, interior columns and knee braces. Should the subgrade be below

    water and in earth, steel beams are added to the bents just described in the track

    floor of the structure.

    Where the roof of the proposed structure is to be at least 10 feet below the t op

    of rock, or where the subway is to be in earth and far from the street surface, the

    best type of structure has proved to be a concrete tunnel, with an arched roof and

    reinforced flat invert. This type reduces the amount of excavation and does not

    require the erection of cumbersome steel members which an open cut steel bent

    structure at t his depth would necessitate.

    In narrow streets, a steel bent double-deck structure might be used, and, if

    tunneling be more economical, a combination of steel bent and concrete tunnel is

    possible.

    If the line is to be built in open cut without cover through undeveloped territory,

    where few subsurface structures have to be maintained, and the room occupied by

    the finished structure is not a governing factor, reinforced concrete design might be

    advantageous.

    Structural Steel versus Concrete.The question of whether structural steel or

    reinforced concrete should be used in subway construction is an interesting one. The

    9/29/2010 "The Design of Subways" (1918)

    nycsubway.org//psr_design.html 3/6

  • 8/13/2019 _The Design of Subways_ (1918)

    4/6

    opinions of contractors differ radically as to the ease and facility with which a

    reinforced concrete job can be carried out, and the careful designer will prepare

    alternative designs for bids where it seems that reinforced concrete would he more

    economical than steel construction. The advantages of reinforced concrete are the

    ease and promptness with which the various materials can be procured; the smaller

    cost of the reinforcing rods as compared with steel beams and riveted sections; the

    cheapness with which it can be placed; its adaptability to any form, and the fact that

    it does not need painting.

    Steel is advantageous for subway work, because it permits the cover load to be

    shifted to it immediately after erection and adapts itself readily to the restoration of

    subsurface structures. It also reduces to a minimum the amount of excavation.

    Typical local station on four track structure.(Click image to enlarge.)

    As stated above, reinforced concrete might be employed in open cut

    construction where decking is not necessary, where few subsurface structures need

    to be maintained, and where the room occupied by the finished structure is not a

    governing factor. The unit bid for excavation would probably be low, because, insubway contracts, where construction is by cut-and-cover method, the price for

    excavation includes decking and the maintenance of many subsurface structures. The

    contractor would not be delayed on account of the fabrication of steel and would

    prosecute the work with c heaper labor than that necessary for steel c onstruction.

    Where Steel is Imperative. In narrow streets, however, bearing a heavy

    traffic and congested with many pipes, ducts, and other subsurface structures, steel

    bent construction is practically imperative. On account of its superior strength, the

    roof, sidewalls, and invert of the subway can be made much thinner with steel than

    with reinforced concrete. Where pipes and ducts cross the structure, a very thin

    construction can be employed, over which longitudinal pipes and street railroad

    construction can pass with a minimum depression of the subway, thereby reducing the

    amount of excavation. On the sides where the streets are very narrow, similar

    depressions afford room for sewer manholes. In steel bent construction the contractor

    can place his timber bracing between the steel bents without greatly interfering with

    its erection. After the steel is erected, the cover load Can be shifted to it at

    convenient points, allowing greater freedom for the restoration of subsurface

    structures and c oncreting.

    With reinforced concrete this is difficult, because the forms and bracing cannot

    be removed until the concrete has set. Furthermore, the timber bracing prevents the

    desirable continuous laying of concrete and makes it difficult to get a close spacing of

    rods, besides necessitating patchwork in the waterproofing after the removal of the

    bracing.

    These various advantages and disadvantages of the materials have practically

    standardized the design of subways. In general, steel bent construction is used

    except where changes in the design have to be made, due to the discovery, in the

    progress of excavation, of bad soil, surface water, or the absence of expected rock.

    Here reinforced concrete, for which rods can quickly be obtained, comes to the

    rescue without delaying the work.

    Ventilating Flue Construction.Reinforced concrete is also made use of in the

    construction of ventilating flues. The flues follow the street surface and are so

    dependent on the location of the subway, with reference to the curb lines, sewers,

    and other subsurface structures, that their shapes are irregular and cannot be entirely

    determined until these are nearly ready to be built. The adaptability of reinforced

    concrete to any form, as well as the promptness with which rods can be obtained, isthus taken advantage of for the c onstruction of these flues.

    It is interesting to note the development of the present standard types of

    subway structures front that of the first subway built in New York City. The original

    structure is of the steel bent type, with plate and bulb angle columns. It is entirely

    enveloped by waterproofing. The ducts carrying the current for operation are of the

    four-way type and are placed outside of the steel for practically the entire height of

    the sidewalls.

    The present types use standard angles instead of bulb angles. Every steel mill

    rolls standard angles, and the delay which might arise through the shutting down or

    other contingencies of mills rolling bulb angle columns is obviated. The ducts in the

    sidewalls of the old type, forming an air space, as well as the continuous

    waterproofing envelope, which is a poor conductor of heat, retain the heat generated

    by train operation and do not allow it to radiate into the surrounding earth. In the

    present structure, the waterproofing on the sides and bottom is omitted, except

    below mean high water, and the ducts are banked inside of the sidewalls, forming,

    with their concrete protection, a walk 2' 1" wide and 4' high, allowing the generated

    heat to be dissipated through the sidewalls above the ducts and through the bottom.

    This in turn reduces the amount of grating necessary to ventilate the structure. The

    type of ducts has also been changed from four-way to one-way. The one-ways are

    laid with broken joints, both horizontally and vertically, so as to prevent an accident

    to one c able affec ting others.

    Clearances.Proper provision for the installation of signals, for the swaying of

    car bodies on their springs, and for the safety of workmen in the subway, requires a

    clearance of 1' 6" from the car body to any wall. This distance may be decreased to a

    9/29/2010 "The Design of Subways" (1918)

    nycsubway.org//psr_design.html 4/6

  • 8/13/2019 _The Design of Subways_ (1918)

    5/6

    tracks where Crossovers occur. This decrease in clearance may obviate the necessity

    of spanning three tracks, by using a deep girder, which would add to the cost and

    interfere with the restoration of subsurface structures. Openings 2' wide by 7' high,

    spaced on about 10' centers, should also be provided in interior walls for the

    protection of workmen. The clearance at duct benches, for a height of 4' above the

    base of rail, should not be less than 5".

    Track Trough. The depth of the track trough, as used in the New York

    subways, for installation of rails, ties, ballast, third rail and for drainage, is 1' 2" below

    base of rail at center line of track, decreasing to a depth of 12" on both sides of the

    center line of track and at distances of 5' 2" from it. Above a point 2" above base of

    rail the clearance from the center line of track to any obstruction must not be less

    than that required for third rail protection and contact shoe clearances. In addition to

    these standard clearances, provision must be made for center and end excesses due

    to horizontal curvature and super-elevation. Excesses due to vertical curves are so

    small that they can be neglected.

    Super-elevation in New York subways is calculated on the basis of a train

    velocity of 30 miles per hour, the formula used being:

    S =G V 2

    32.2 R

    S = Super-elevation in inchesG = Gauge in inchesV = Velocity in feet per secondR = Radius of curve in feet

    At a velocity of 30 miles per hour this formula reduces to:

    S =3397

    R

    The maximum super-elevation used is 6.5 inches which corresponds to a radiusof 523 feet. On curves of smaller radii the speed is reduced accordingly.

    Generally, the full super-elevation is obtained at the point of curvature and the

    rate of decrease on curves not transitioned is one-half inch in 33 feet. On transition

    curves the approach should extend over the entire transition except when a rate of 1

    inch in 33 feet is exceeded, in which case it may extend into the tangent track. No

    approach to a curve, transitioned or otherwise, should be longer than 330 feet.

    The clearance from the top of an unloaded car, in its normal position, to the

    under side of the subway roof should be 6 inches if possible. This is sufficient when

    the top of the car monitor is curved and super-elevation is obtained by raising one rail

    and depressing the other, each one-half of the total amount, it also permits the

    raising of a car to clear the wheel flanges in case of accident.

    Stations.Typical local stations are generally provided with side platforms and

    accommodate trains of less cars than the trains required for express service. Those

    local stations, however, at which express trains stop, occurring on lines having only a

    partial express service, must be as long as express stations. The width of the side

    platforms should not be less than 10 feet. This sometimes necessitates relocating thestreet sewer underneath the platforms. The height of all platforms is generally about 4

    feet above base of rail.

    The length of platforms depends upon the number of cars to each train required

    by the probable traffic. In New York City the original subway station platforms were

    built 200 feet and 350 feet long to accommodate five and eight-car local and express

    trains, respectively. The increase in traffic required their lengthening to 225 feet and

    480 feet for six and ten-car trains. The new platforms for the Dual Subway System in

    New York are 405 feet and 480 feet long for the I. R. T. lines, and 495 feet and 530

    feet long for the N. Y. M. R. R. lines.

    Typical express stations have island platforms, generally reached by mezzanines

    over the tracks. Sub-passages, because they increase stair climbing, should be

    avoided, but in some cases local conditions make their use imperative. Since express

    stations must be depressed to allow for mezzanine construction, that part of the

    station not occupied by mezzanines should be built with a high roof. This adds to the

    appearance, besides being economical, because the roof is required to carry less

    backfill.

    Stations in Narrow Streets. In narrow streets and deep structures even local

    stations are constructed with island platforms and mezzanines. In the case of narrow

    streets this is done because one island platform accommodating traffic in both

    directions takes up less room than two side platforms and in the case of deep

    structures advantage is taken of the available room for a mezzanine. This, besides

    affording a natural rest in stair climbing, eliminates one control and balances to some

    extent the extra expense of a deep structure, by the saving in the cost of operation.

    In very narrow streets it is possible to design a station where the roof over one track

    is the platform for the other track. The station could of course be constructed on two

    levels, but the above method saves a considerable amount of excavation and reduces

    stair climbing.

    Station entrance stairs are sometimes built on the sidewalks next to the curb.

    This practice, however, has been largely abandoned and is resorted to where the

    entrances are built under existing elevated railroad stairs. Generally the practice is

    followed of endeavoring to convince abutting property owners of the fact that a

    subway approach through their property will enhance its value. Where this can be

    accomplished it removes the station entrances entirely from the street, leaving the

    sidewalk clear for the use of pedestrians. When an owner cannot see his way clear tomake the alterations to his building necessitated by the above procedure, he can

    often be persuaded to exchange window display space, or an entrance to his building

    from a stair platform, for beam rights. This saves the construction of a supporting wall

    adjacent to the building line, thereby reducing cost and saving sidewalk area.

    Escalators Considered.Where the distance from the surface of the street to

    the platform level exceeds 32 feet, the installation of escalators is considered, and

    where this distance exceeds 50 feet elevators must be used. Ramps, not exceeding a

    9/29/2010 "The Design of Subways" (1918)

    nycsubway.org//psr_design.html 5/6

  • 8/13/2019 _The Design of Subways_ (1918)

    6/6

    levels to be connected would require only a few steps, and also at all other places

    where possible, the difference between their cost and stair construction not being

    prohibitive. They should not be used instead of stairs where the large opening they

    require on account of head room would monopolize valuable areas, as at sidewalk

    levels and island platforms.

    htt p:/ / www. nycsubway.or g/ar t i cl es/ psr_desi gn. htmlThi s si t e i s not af f i l i at ed wi t h any t r ansi tagency or provi der.

    9/29/2010 "The Design of Subways" (1918)

    nycsubway.org//psr_design.html 6/6