All the numbers are represented are masked considering business confidentiality
Copyright of this project belongs to HCCBPL as per IPR
THE COCA-COLA COMPANY (TCCC)
• Coca-Cola was formulated in 1886 by John F Pemberton• We Operate In more countries than UN• “Coke” is the most Recognized word after “OK”• One of the Most valued Brands in the world
To Refresh the World Inspire moments of optimism and happiness Create value and make a differenceM
issi
on
2
2
HCCBPL is the largest bottling partner of The Coca-Cola Company in India. It is a part of The Coca-Cola
Company’s Bottling Investments Group (BIG) and responsible for the manufacturing, packaging, sales and
distribution of beverages under the trademarks of The Coca-Cola Company.
Introduction…Introduction
3
• To be the best Sales & Distribution Company for consumer products in India connecting people and the product of their choice
Vision
• Enriching lives across the country by building a consumer-driven, customer-focused, employee-friendly, profitable, sustainable and socially responsible business in India
Mission
• PASSION
• LEADERSHIP
• ACCOUNTABILITY
• CITIZENSHIP
• EMPOWERMENT
• INTEGRITY
• TEAMWORK
Values
Vision, Mission and Values
4
All the numbers are represented are masked considering business confidentiality
3
Packs
Returnable Glass Bottles
PET Bottles
Tetra Pack
Cans
Products
Carbonated Soft Drink
Juice
Water
Life Style Beverages
Product : Packs and Brands
5
Concentrate
Sugar & Pulp
Preform Supplier
Coke Depot
Glass Bottle Lines
PET lines
Tetra Pack Lines
Cans line
RGB
PET
Coke
Distributor
DSD
Distribution
Retail Outlet
Key Accounts
Coke Supplier Coke Bottling Plants Coke Depot Route to Market Customers
Coke Value Chain : How do we Serve our Customers?
6
4
7
HCCB - OE Strategic Roadmap – Picture of Success
8
5
Operation Excellence – Strategic Blocks
9
Section : 1
Project & Team Selection
10
All the numbers are represented are masked considering business confidentiality
6
1.1.1 Who was responsible for selecting the Project ? (1/2)
HCCBPL - National Steering Committee
Global Vision 2020
Business Diagnostic
Improvement Opportunities Identification
Project Execution –Training and
OE tool usage
Leadership Report Out
Certification, R&R
Voice of Customer
Voice of Business
Profit & Loss Analysis
KPI Trend & Benchmarking
Project selection Committee
Supply Chain TransformationDefining the Performance Gaps – Big “Y’s”
Idea Generation workshop
SCOR Model
PlanPlan PlanCustomer Channel &
Product Line Reqm’tsComponentsComponents
Components
Laurel, MS
Components
Laurel, MS
Interior Doors:
Haleyville, AL
Interior Doors:
Haleyville, AL
Specialty:
Brampton, Ont.
Specialty:
Brampton, Ont.
Exterior Doors
Dickson, TN
Exterior Doors
Dickson, TN
DorFab:
Lawrenceville, GA
DorFab:
Lawrenceville, GA
Door GroupDoor GroupSuppliersSuppliers CustomersCustomers
Cohesive Supply Chain View Eliminates Disconnects
Retail• Home Depot
• Lowes
Competitors• ??
• ??
Distribution: 1-Stepper• ??
• ??
Distribution: 2-Stepper• ??
• ??
Internal
Suppliers• ??
• ??
External
Suppliers• ??
• ??
11
1.1.1What Background Information on the Company or those who selected the
project was provided to better Understand the context of the project? (2/2)
Fuel – 35%Driver 25%EMI – 25%
Insurance, Registration & Permit – 15%
Approx 65% Cost is Fixed Cost. Only
TAT can reduce this cost
Indian Freight Industry is operating at 50% of Efficiency of global Benchmark
12
7
1.2.1How was the Gap or Opportunity brought to the attention of the project
Identification group? (1/3)
13
x
4xThroughput per location [PC MM]
Yr 2015 Yr 2019-20
UPSIZE
- Leverage 100K above 38% volume contributing customers to upsize from 9MT to 16 MT
- Maximize IU movements from 16MT manual to 40” trailer Palletized
PALLETIZE
- Cover untapped areas like ROM, East, Karnataka, Rajasthan, MP
- Move to 100% in key locations like Mumbai
- Transform IU movements from manual to Palletized through automation / 2-Way
IMPROVIZE TAT
- Reduce Distributor delivery TAT from 46 hours to 24 hours
- Move to staging at all locations with single-piece-flow loading
- Maximize transport visibility to have better controls
1.2.1What is the Gap ( Problem Solving ) or Opportunity? ( 2/3 )
Business Case:
Our freight costline consists of ~72% two-way dispatch volume which has
Fixed & Variable cost components. If we want to impact our freight cost,
reducing fixed component becomes paramount. Hence reducing Fixed component
by reducing TAT of vehicles is important
14
Opportunity:Vehicles TAT of ~2.5 to 3 days
6067
42
72
44
7262
G U J A R A T O R I S S A W U P D E L H I H Y D W A D A B A N G A L O R E
G U J A R A T E A S T N O R T H A P M A H K T K
TAT
IN H
RS
VEHICLE TAT HISTORY
2015
8
1.2.1What area of the organization had the gap or the opportunity? ( 3/3 )
15
Manufacturing Excellence – Engineering & Packaging Innovations to drive competitive advantage
Planning – Nimble Supply Chain nurturing Emerging product categories
Logistics & Distribution – Single Touch, Scale Logistics in a GST environment
Stewardship – Anticipate & act ahead of time to evolving Regulatory & Environmental framework
Leverage Technology – Digitization to drive Visibility, Productivity & Efficiencies
A Future Ready Supply Chain Architectures - Consolidation with reduced Complexity
Lean Supply Chain Cost Structure that remains ‘Flat-to-Prior’
1.2.2What data was generated to help select the project? ( 1/3 )
16
15 1514 14
13
11
7
9
11
13
15
17
2010 2011 2012 2013 2014 2015
NO OF TRIPS IN A MONTH
74
39
0
5
10
15
20
25
30
35
40
45
Plant TAT Depot TAT DistributorTAT
TAT at Three stages in Hrs
4 2.5
58.5
0
10
20
30
40
50
60
70
Plant TAT Depot TAT Distributor TAT
2015 Situation
Huge Trip reduction in last 2 years due to
Distribution Model change
From 2010 to 2015 it has been observed that pan India Distributor and Enroute TAT was increasing resulting in detention at various points and thus
huge Total TAT
9
1.2.2What method and /or tool were used to assess or prioritize the need for
the Project? ( 2/3 )
Kaizen JDI Workshop Six Sigma method
Strategic Criteria Methods / tools
Brainstorming
Project selection matric
Complexity Analysis
Quick win / Replications Simple in nature Complicated 3-4 months
17
Attribute
Criteria
Weight
Percent of Total
Criteria
Is the project aligned with business
priorities? (Aligned with Finance,
business impact, key measures,
KPIs, RPN? A must-do projecr not a
nice-to-do)
1.0 0.2 1.0 0.2 0.1 2.50 3.5%
Can benefits be credibly quantified?
(intangible benefits = 1, INR 50MM =
2, 100MM = 3, 150MM = 4,
200MM=5)
1.0 0.1 1.0 0.2 1.0 3.30 4.6%
Can t
he p
roje
ct
transfe
rable
to o
ther
are
as,
functions o
r busin
ess u
nits?
Can w
e involv
e t
he n
ecessary
span o
f
sta
kehold
ers
needed t
o g
ain
accepta
nce a
s w
e c
onduct
the p
roje
ct?
Will
the a
ppro
pro
ate
level of
managem
ent
invest
its t
ime &
budget
on r
evie
win
g,
support
ing &
ensuring t
he
success o
f th
is p
roje
ct?
Is t
he p
roje
ct
alig
ned w
ith b
usin
ess
priorities? (
Alig
ned w
ith F
inance,
busin
ess im
pact,
key m
easure
s,
KP
Is,
RP
N? A
must-
do p
roje
cr
not
a n
ice-t
o-
do)
Can b
enefits
be c
redib
ly q
uantified?
(inta
ngib
le b
enefits
= 1
, IN
R 5
0M
M =
2,
100M
M =
3,
150M
M =
4,
200M
M=
5)
Is a
data
& m
easure
ment
syste
m
availa
ble
, and if
no,
would
gett
ing it
be
cost-
eff
ective?
Prioritization Matrix
Priority Bubble chart
ACTION ITEM CODE DATA BENEFIT (Rev. Order)
COMPLEXITY
Reduce TAT of Vehicle A 20 3,200,000 50
Reduce Detention B 20 1,048,576 50
BBD Reduction C 31 759,375 5
Blow ing P2 pressure reduction D 1 1,419,857 20
Yield Improvement E 31 2,476,099 50
SLE Improvement F 1 1,889,568 20
Checker Reduction G 31 537,824 20
1.2.2Why these methods / tools are used to select the project? ( 3/3 )
Methods / tools
Brainstorming
Complexity Analysis
▪ Understand the internal/external Customer pain area
▪ Indirect impact on our own people & customer may be much higher than cost impact
Why?
▪ Based on the impact on Business▪ Replicable across the organization quickly
▪ Understand the future Risk & requirements▪ Proactive actions to be more competitive
Project selection matric
18
ACTION ITEM CODE DATA BENEFIT (Rev. Order)
COMPLEXITY
Reduce TAT of Vehicle A 20 3,200,000 50
Reduce Detention B 20 1,048,576 50
BBD Reduction C 31 759,375 5
Blow ing P2 pressure reduction D 1 1,419,857 20
Yield Improvement E 31 2,476,099 50
SLE Improvement F 1 1,889,568 20
Checker Reduction G 31 537,824 20
10
1.2.3What Goals ( organizational and / or local) , performance measures, and
/or strategies were the project expected to impact ? ( 1/3 )
•Identify and build vendor base to help migrate to the destination
•Upsize to the right truck type for the right movement type
•Increase Palletized Transportation to multiply dock productivity & throughput
•Loading & Unloading Solutions to minimize casual labor
Handling Productivi
ty
Increase Throughp
ut
Build Capable Vendors
Reduce Transactio
ns
Destination Truck Type for Customer
Destination Truck Type for IU
Supply Chain Strategy - Scale Logistics
Consumer Centric Supply Chain
19
1.2.3What was the relationship between the stated measure & perceived gap
in 1.2.1 ? ( 2/3 )
Where we are? What we are working on? Future Plan ~ Destination
48 hours
36 hours
30 hours
Track & Trace
Slot Planning
Day+1
Order Staging,
Pool Sizing
RFID
Dynamic Scheduling
Double Drivers
Reduced
Demand
Variability
Reduced Unloading Detention
Night Unloading
110-120 INR MM 25-30 INR MM50 -60 INR MM
20
11
1.2.3What was the problem / project objective statement that express where
the organization want to be at the end of the project ( 3/3 )
21
Project Name: Project #: Project Start/End Dates:
Vehicle TAT Reduction
Project Lead: Umesh Madhyan Executive Sponsor: Dinesh Jadhav
Team Members: Project Costs: (include required capital, expenses)
BN Sarkar, Shivanana Prabhu, B Sriram, Rajeev Singh, Tarun Sawhney, Sanjay Sahai, Kunal Sharma, Prashant Sinha, Akansha Tyagi, North Team, KTK Team, AP Team,
Gujarat Team, East Team
- Capital:Novire software
- Expenses:Maintenance Charges
Mission/Project Overview:
Total Freight consists of 80% two-way volume out of which variable freight consists of
And Fixed cost consists of fixed vehicles. If we are able to impact the Fixed cost of Freight costline, then reducing TAT of vehicles is paramount
- KPI's:Vehicle TAT – Gate Exit to Trip End
P&L Line Impact
Freight Cost
Objectives: (include beginning & ending KPI's) Net Benefits:Beginning TAT – 72 hrs
Target TAT – 24 hrs for <150km36 hrs for >150km
Saving Opportunity2017 - ~ 3-4 Cr
In Scope: OE Tools to be used: Out of Scope:Transportation, Warehouse, Distributor Model, Finance
processes
KPI measurement, Process Mapping
Control Chart, Pareto,
Assumptions: Risks & Constraints:Seasonality
Project Milestones: Dependencies:Phase 1: 2016Phase 2: 2017
Define : Feb 2017-Mar 2017Measure : Mar 2017 – Apr - 2017Analyse: Apr 2017 – May 2017Improve: May 2017 – Jun 2017Control : Jul 2017- Aug 2017
Order Cut off time Novire
Project Lead Time: (Total time required to implement would be one full financial year
) Other Key Stakeholders & Areas Affected:6 months Sales
1.3.1How were the stakeholder groups identified? ( 1/2 )
Stakeholder Group
Core Team
Supply Chain
Transportation
Shipping
OE
Corporate OE
Capability Developm
ent
Team
OEM
Zonal Leadership
Team
22
S I P O CSupplier Input Process Output Customer
RTM Team Novire integration Report Dynamic time slot planning TAT Reduction HCCB
Transportation Team FMS data Vehicle Pool Size optimitation Freight Cost Reduction RTM Team
Shipping Team Distributor unloading time Detention reduction Detention Reduction Supply Chain
Operations Team No Entry Exit time Order Staging
RFID
Day+1
Night Unloading
12
1.3.1What or who were the stakeholder group? ( 2/2 )
Supply Chain HeadBack End management
Team
Core Execution Team
Steering Committee
Stakeholder groups Designations Roles
Zonal Vice President Zonal Supply Chain Head HeadFactory ManagerZonal Finance Head
Transportation ManagerShipping ManagerRTM FE/ BE Manager
OE Team Operational Excellence Team
C
R & A
I
R R – ResponsibleA – AccountableC- ConsultI – Inform
23
1.3.2What knowledge or skill sets were determined to be necessary for
successful completion of the project? ( 1/3 )
Skills/ Knowledge/
Abilities
Determined Skills Set
▪ Analytical Skills
▪ Design Thinking
▪ Problem Solving skills
▪ Change management Skills
▪ Functional Knowledge
▪ Product Knowledge
▪ Technical skills
24
13
1.3.2To what extend did the existing stakeholder groups have the required knowledge or skills? ( 2/3 )
What additional knowledge and skills were brought to make the project successful ? ( 3/3 )
Stakeholder Gaps Identified Current Desired Skill Brought
Director Supply Chain None None
Zonal Vice President None None
Zonal Supply Chain Head Design Thinking Low Medium Champion Training
Zonal RTM Head Design Thinking Low Medium Champion Training
Zonal Finance Head Design Thinking Low Medium Champion Training
Transportation Manager Change Management Low High CAP tool Training
Shipping Manager Change Management Low High CAP tool Training
RTM Manager Front End Change Management Low High CAP tool Training
RTM Manager Back End Change Management Low High CAP tool Training
OE MemberDesign Thinking &
Business intelligenceMedium High
LSS & Analytics training
25
1.3.3Before the Project started, what specific training was done? ( 1/2 )
Trai
ning
Lev
el
Peop
le P
artic
ipat
ion
Coac
hing
& M
ento
ring
Cert
ifica
tion
Leve
ls
✓ Change Acceleration process Training
for selected group members
✓ Design thinking module introduced in
champion training and steering
committee member got trained
✓ 5 days LSS and analytics session was
conducted for OE members
26
14
1.3.3Before project started what was done to prepare the team to work
together as a team? ( 2/2 )
Set Engagement
objectives
Identify and assess
stakeholders
Develop engagement
plan and technique
Implement engagement
plan
Assess the engagement
process
Respond to engagement
results
Measure and Report
progress
27
1.3.4What roles & expectations were determined ahead of the project? ( 1/3 )
What Who Purpose When Type
Status Reports Sponsor, Champion,
Members, Leaders,
MBB
Update stakeholders
on progress of the
project.
Bi – Monthly Mail
Team Meetings Leaders and
Members
Internal reviews/Update
on projects/Change
Management Issues
Bi-Weekly Meeting
Project Reviews & Toll
Gate
Leaders, Members,
MBB, Champion
Project Reviews Monthly Meeting
OE Reviews Sponsor, Champion,
Leaders, MBB
Project Review –
Status Update and
direction
Monthly Meeting
OE Tollgate Sponsor, Champion,
Leaders, MBB
Tollgate Monthly Meeting
Presentations to
Special Interest
Groups
Project Leader To update external
groups to promote
communication/create
awareness of project
interdependencies.
As needed As applicable
28
15
1.3.4What deadlines & deliverables did the team have to consider ahead of
actually starting the project? ( 2/3 )
Phase Start date End Date # Days OE ReviewStakeholders
Review
Define 5 – Feb - 17 28-Feb-17 23 Completed Completed
Measure 28-Feb-14 31 - Mar – 17 33 Completed Completed
Analyze 31-Mar-17 30-Apr-17 30 Completed Completed
Improve 30-Apr-17 31-May-17 31 Completed Completed
Control 31-May-17 31-Jul-17 60 Completed Completed
29
1.3.4Before the project started, what team routines, including communications
, were established? ( 3/3 )
Name FunctionMeeting
1Meeting 2 Meeting 3 Meeting 4 Meeting 5 Meeting 6 Meeting 7 Meeting 8 Meeting 9 Meeting 10 Present %
BN Sarkar RTM manager P P P P P P P P P P 100%
Amer Hussain Supply Chain P P P P P P P A P P 90%
RalinsTransportationManager
P P P P A P P P P P 90%
B Sri Ram RTM Manager P P P P P A P P P P 90%
Tarun Sawhney RTM Manager P P P P P A P P P P 90%
SdeveshTransportation Manager
P P P P A P P P P P 90%
Rajeev RTM Manager A P P P P P P P A P 80%
Akansha Tyagi OE Manager P P P P P P P P P P 100%
Kunal Sharma OE AVP P P P P P P P P P P 100%
No of People Present 8 9 9 9 6 7 9 8 8 9 100%
Weekly - Compliance 89% 100% 100% 100% 67% 78% 100% 89% 89% 100%
Overall Compliance (%) 91%
30
16
Section : 2Current situation and root cause / improvement opportunity analysis
31
All the numbers are represented are masked considering business confidentiality
2.1.1What specific goals and / or measures was the team trying to achieve
with the project? ( 1/2 )
Project Deliverables: Reduce the TAT of vehicles
from 2~3 days to ~1day
Key Performance Indicators:
a) Vehiclee Efficiency
b) Vehicle Pool Size
c) TAT <24hrs for <150km
distance
TAT < 36 hrs for distance >150km
32
17
2.1.1What additional potential benefit, other than specific goals and /or
measures, was the project expected to impact? ( 2/2 )
Additional Potential Benefits:
Additional Benefits Metrics
Customer Detention Reduction
% increase delivery time compliance
Vehicle TAT Improvement TAT KPIs
Customer delivery time reduction
% Increase in customer satisfaction
Better transport controls Novire report accuracy
33
Tools:
Process Mapping – SIPOC, Flow Chart, Measurement System Analysis, Brainstorming, Fish Bone Analysis, Customer Surveys
2.2.1What method and /or tools were used to identify possible root causes /
improvement opportunities? ( 1/2 )
Methodology: Six Sigma DMADV
Understanding and analyzing current & future state VSM
Identification of possible root cause
34
S I P O CSupplier Input Process Output Customer
RTM Team Novire integration Report Dynamic time slot planning TAT Reduction HCCB
Transportation Team FMS data Vehicle Pool Size optimitation Freight Cost Reduction RTM Team
Shipping Team Distributor unloading time Detention reduction Detention Reduction Supply Chain
Operations Team No Entry Exit time Order Staging
RFID
Day+1
Night Unloading
2 31
18
2.2.1Why were these methods and /or tools selected
How was the team prepared to use these methods and/or tools ( 2/2 )
Tools Used Why How
Process MappingCommon understanding
of process by teamCross functional team
and process walkthrough
Brainstorming Generating Ideas Cross functional meeting
Fish Bone Analysis Idea generationIdentifying factors
impacting Big Y with project team members
Customer SurveysUnderstanding Voice of
customer
Interaction with customer through
market survey
35
2.2.2What data was generated and how was the data analyzed to identify the
possible root cause/improvement opportunities? ( 1/2 )
Data was generated through Fish bone and market research for secondary data collection
36
19
2.2.2What were possible root cause/improvement opportunities? ( 2/2 )
S. N Root Cause
1 Insufficient space at Distributor/ CFA/ WH
2 Stock not available
3 Insufficient forklift/ manpower at distributor point
4 Detention
5 Delay at checkpoints
6 Temporary closed
7 Vehicle Breakdown
8 No Entry exit timings
9 Distributor preferable unloading time
10 Absence of transport coordinator
11 No night unloading
12 Driver behavior
13 Unavailability of driver
14 Delay in Plant
15 Multiple touch points
16 Volume skew
17 Low visibility of truck movement
18No proper time slot planning & allocation
process
19 Credit not available
20 No order cut off point
Classification of X’s
Geographical / population related
Process / Policy Related
Freight Related
Track & trace
Customer delivery
Consumer Related
All identified reasons are classified in broad 6 categories
37
2.3.1What methods and /or tools were used to identify the final root cause(s)/
improvement opportunity (ies)? ( 1/3 )
14 were identified as potential root cause Method: Six Sigma
Cause & Effect
ANOVA
FMEA
38
S. N Potential Causes
1 Insufficient space at Distributor/ CFA/ WH
2 Stock not available
3Insufficient forklift/ manpower at distributor
point
4 Detention
5 Delay at checkpoints
6 No Entry exit timings
7 Distributor preferable unloading time
8 Absence of transport coordinator
9 No night unloading
10 Delay in Plant
11 Multiple touch points
12 Volume skew
13 Low visibility of truck movement
14No proper time slot planning & allocation
process
20
2.3.1Why were these methods and /or tools selected
How was the team prepared to use these methods and /or tools ( 2/2 )
Tools
Cause & Effect
Scatter Plots/ Summary/ ANOVA/
Mann Whitney Test
& CI
Factors Validation &
FMEA
Why How
• To prioritize vital few from trivialmany
• Training on OE
tools and
methodology to
team members
• Weekly team
meetings &
working sessions
• Monthly review
with Champion/
sponsor
• To identify the specific factor impacting BIG Y
• To Filter the potential causes using high RPN no
39
2.3.2What data was generated and how was the data analyzed in order to
identify the final root cause(s) / Opportunity ( ies)? ( 1/3 )
14 were identified as potential root cause
Brainstorming Fishbone
FMEA Mann Whitney Test & CI
Regression Multi voting
40
S. N Potential Causes
1 Insufficient space at Distributor/ CFA/ WH
2 Stock not available
3Insufficient forklift/ manpower at distributor
point
4 Detention
5 Delay at checkpoints
6 No Entry exit timings
7 Distributor preferable unloading time
8 Absence of transport coordinator
9 No night unloading
10 Delay in Plant
11 Multiple touch points
12 Volume skew
13 Low visibility of truck movement
14No proper time slot planning & allocation
process
Nu
mb
er
of
tou
che
s
95% Bonferroni Confidence Intervals for StDevs
3
1
5045403530252015
Nu
mb
er
of
tou
che
s
TAT
3
1
350300250200150100500
F-Test
0.000
Test Statistic 0.14
P-Value 0.000
Levene's Test
Test Statistic 37.99
P-Value
Test for Equal Variances for TAT
21
2.3.2What are specific examples of data analysis that led to the final root
causes? ( 2/3 )
All the numbers are represented are masked considering business confidentiality
41
Num
ber
of t
ouch
es
95% Bonferroni Confidence Intervals for StDevs
3
1
5045403530252015
Num
ber
of t
ouch
es
TAT
3
1
350300250200150100500
F-Test
0.000
Test Statistic 0.14
P-Value 0.000
Levene's Test
Test Statistic 37.99
P-Value
Test for Equal Variances for TAT
Mann Whitney Test & CI
1501209060300
Median
Mean
15.012.510.07.55.0
A nderson-Darling Normality Test
V ariance 401.658
Skewness 4.0196
Kurtosis 21.5835
N 629
Minimum 0.040
A -Squared
1st Q uartile 2.165
Median 6.090
3rd Q uartile 14.850
Maximum 167.420
95% C onfidence Interv al for Mean
11.148
73.20
14.287
95% C onfidence Interv al for Median
5.224 7.030
95% C onfidence Interv al for StDev
18.992 21.215
P-V alue < 0.005
Mean 12.717
StDev 20.041
95% Confidence Intervals
Summary for DC TAT in hours
Mean (TAT) 14
hours
Median (TAT) 7 hours
TAT
Pe
rce
nt
4003002001000-100
99.99
99
95
80
50
20
5
1
0.01
Mean
<0.005
60.07
StDev 43.70
N 993
AD 57.955
P-Value
Probability Plot of TATNormal
2.3.2What was (were) the final root cause(s) / improvement opportunity (ies) ?
( 3/3 )
Cause Validated Cause Validated
Customer Detention Insufficient space
Distributor Preferable unloading timing
Stock not available
No Entry exit timing Delay at checkpoints
Order availability Absence of Transport cordinator
Night Unloading Delay in plant
Truck pool size Multiple touch points
No Slot planning Volume skew
Final
root
cause
42
22
2.3.3How was (were) the final root cause(s) / improvement opportunity (ies)
validated? ( 1/2 )
14 were identified as potential root cause How – Tools used
Mann Whitney Test & CI
ANOVA/ Summary
FMEA
Cause
Detention
No time slot planning
No night unloading
Volume skew
4 were validatedroot cause
Brainstorming
Multi voting
Fish Bone Analysis
43
S. N Potential Causes
1 Insufficient space at Distributor/ CFA/ WH
2 Stock not available
3Insufficient forklift/ manpower at distributor
point
4 Detention
5 Delay at checkpoints
6 No Entry exit timings
7 Distributor preferable unloading time
8 Absence of transport coordinator
9 No night unloading
10 Delay in Plant
11 Multiple touch points
12 Volume skew
13 Low visibility of truck movement
14No proper time slot planning & allocation
process
2.3.3What evidence showed that the final root cause(s) / Opportunity (ies)
were validated prior to solution development ? ( 2/2 )
14 were identified as potential root cause Validation of Root cause as
pilot
4 were validatedroot cause
44
50 71 10514947 63 87 103145119
0
200
May 1st WeekMay 2nd WeekMay 3rd WeekMay 4th WeekJune 1st WeekJune 2nd WeekJune 3rd WeekJune 4th WeekJune 5th Week
Avg Vehicle Requirement vs Regular vehicle
Avg Vehicle Requirement
Vehicle in the system
S. N Potential Causes
1 Insufficient space at Distributor/ CFA/ WH
2 Stock not available
3Insufficient forklift/ manpower at distributor
point
4 Detention
5 Delay at checkpoints
6 No Entry exit timings
7 Distributor preferable unloading time
8 Absence of transport coordinator
9 No night unloading
10 Delay in Plant
11 Multiple touch points
12 Volume skew
13 Low visibility of truck movement
14No proper time slot planning & allocation
process
Cause
Detention
No time slot planning
No night unloading
Volume skew
23
2.4.1How was the correctness of the initial project scope, deliverables, and
Training Confirmed (or what changes were made )? ( 1/4)
45
Financial Impact
uScope:
nIn-Scope/Out-of-Scope - GPS
Vehicles/ Non- GPS Vehicles
n(Process Start/Stop)
uState financial impact of project -
24Cr in 3yrs
nExpenses
nInvestments (inventory, capital, A/R) -
GPS
nRevenues
Team
uPES Shipping Project Executive Sponsor (if different
from PS)
uPS Supply Chain Head Project Sponsor/Process Owner Toll Gate Review Schedule
uDC RTM Deployment Champion Tollgate ScheduledRevised Complete
uGB/BB Akansha Tyagi Green Belt/Black Belt Define : Feb 2017-Mar 2017 15/02/17 - 15/02/17
uMBB Kunal Sharma Master Black Belt Measure : Mar 2017 – Apr - 2017 20/03/17 20/03/17
Core Team Role % Contrib. LSS Training Analyse: Apr 2017 – May 2017 17/04/17 19/04/17 19/04/17
uDevesh Malik Transportation
Manager
SME XX Improve: May 2017 – Jun 2017 29/05/17 30/05/17 30/05/17
uTarun Sawhney RTM Manager 20% GB Control : Jul 2017- Aug 2017 13/06/17 13/06/17
uB SriRam RTM Manager 25% PS
Extended Team uReview high-level schedule
milestones here:
uMohit RTM 15% Not Trained nPhase Completions
uRalins RTM 15% Not Trained nTollgate Reviews
Problem/ Goal Statement
Problem: Reduce the Vehicle TAT to 24hrs for <150km & <36hrs for <36hrs
Goal: Before Overall TAT - 60hrs, Target - 36hrs overall
nShift mean, variance, or both
nShould impact cost, time, quality dimensions
uExpress goals using SMART criteria
nSpecific, Measurable, Attainable, Resource Requirements, Time Boundaries
uExplain leverage and strategic implications - Vehicle Pool Reduction
2.4.1How were stakeholder involved and /or communicated with during the
root cause / improvement opportunity phase of the project? ( 2/4)
Obtain the Voice of CustomerBE Management Team
Core Execution Team
Steering Committee
Stakeholder groups How
Monthly review with National & Zonal Committee
Help Prepare the selection criteriaMonitoring and validating the pilot test results
OE Team Mentor project team with DMADV approachDrive the project time lines and project meeting
One on One meeting, Email & Con Calls
Communication Mechanism
Review Meetings and Regular emails
Weekly/Fortnightly, Monthly reviewSharing the status of validated resultsParticipating in project toll gates
Toll Gates Publishing MIS & progress Reports
46
24
2.4.1
01
What stakeholder resistance was identified and/or addressed in this
phase of the project? ( 3/4)
NoneFE Management Team
Core Execution Team
Steering Committee
Stakeholder groups Resistance
None
Why do I need to collect data on the causesI need to focus on my current business
OE Team The longevity of the retained & new outlets
Impact
H
M
None
None
Initial data collection reveals some of the mythsTeam alignment was done before initiating the projectNecessary R&R was put in place
Tracking mechanism put in place
Communication Mechanism
47
2.4.1How was the appropriateness of the initial team membership and
management routines confirmed ( or what changes were made)? ( 4/4)
Expectation establishmentCommon GoalTeam ContactTrust
Achieving resultsFinding solutionsCaringEstablishing unique identity
Agreement on roles & ideasDuring projectNegotiationsConsensus building
Roles & ResponsibilityExpressing IdeasInterdependentReacting
Skill set Mapping+Training+Engagement
Forming PerformingNormingStorming
ManagementSupply Chain TeamRTM TransportationShippingFinance
C
o
r
e
T
e
a
m
Management Routine Confirmation
SC Head
Steering Committee
Sales &Ops Head
Monthly Review
Monthly to Fortnightly
Weekly
✓
✓
✓
48
25
Section : 3Solution / Improvement Development
49
All the numbers are represented are masked considering business confidentiality
3.1.1What methods and /or tools were used to identify the possible solutions / improvements? How was the
team prepared to use these methods and / or tools (to identify the possible solutions / improvements)?
Why were these methods and/ or tools selected ( to identify possible solutions / improvements )?
Method:- DMADV Methodology
Candidate X'sInsufficient space at Distributor/
CFA/ WH
Stock not available
Insufficient forklift/ manpower
at distributor point
Detention
Delay at checkpoints
No Entry exit timings
Distributor preferable unloading
time
Absence of transport
coordinator
No night unloading
Delay in Plant
Multiple touch points
Volume skew
Low visibility of truck
movement
No proper time slot planning &
allocation process
Tool Used Why Who How
Brainstorming Develop the list of solution P
r
o
j
e
c
t
T
e
a
m
Team Review
FMEA To identify preventive measures
Team Meeting
Solution selection Matrix
To select the possible solution
Team Meeting/review
Pilot Testing To gauge the results in controlled environment
Team Work
HypothesisTesting
To validate the results Minitab
P
o
s
s
i
b
l
e
S
o
l
u
t
i
o
n
s
Step 1
Step 2
Step 3
Generation of possible solution
Prioritization of possible solution
Validation of possible solution
50
26
3.1.2What data was generated and how was the data analyzed to determine
the possible solutions / improvements? ( 1/3)
Analysis
DATA Door Analysis
Process Door Analysis
51
__________
Process
Number
__________Observer
1
2
3
4
5
8
(Gate in
at Dasna)
Average Time
TAT Process
2
(Gate In
At
3
(Gate out
at Jhilmil
4
(Gate In
at
5
(Gate out
at
6
(Vehicle
reporting
7
(Vehicle
out
Truck No. Vehicle No
Transport
er
Name
Truck
Type
(Two
Vehicle
Rounds(1
st/2nd)
1
(Gate
Out
Time Measurement Sheet
Analysis Date
Analysis Time
__________
Analysis Shift __________
VEHICLE NO.
DASNA TO DEPOT TRAVEL
TIME
WAITING TIME AT DEPOT
DEPOT TO DISTRIBUTOR TIME
TOTAL TIME
SPENT AT DISTRIBUT
OR
TIME FROM DIST. TO DEPOT
DIST./DEPOT TO DASNA
TAT
Hours
Days Hours
Days Hours
Days Hours
Days Hours Days Hours Days Hours
HR38M6479
11:21
0.47 1:23 0.06 1:12 0.05 02:20
0.097
15:09:00
0.63 64:00:00
UP86B9810
11:29
1.48 1:19 0.05 2:21 0.10 01:05
0.045
5:50 0.24 57:28:00
2.39 109:27:00
HR38H2183
9:09 0.38 1:40 0.07 2:20 0.10 02:00
0.083
4:28 0.19 56:00:00
2.33 82:47:00
HR55Q6813
6:50 0.28 5:03 0.21 2:36 0.11 01:35
0.066
2:57 0.12 153:14:00
6.38 181:51:00
HR38N5687
23:36
0.98 13:54
0.58 9:06 0.38 02:59
0.124
61:42:00
2.57 161:04:00
Collected DATA
DATA Collection Plan
3.1.2What are the possible solutions / improvements? ( 2/3)
Possible Solutions
Day+1dispatch/ delivery compliance
Dynamic Scheduling & Time slot Planning
Right vehicle pool sizing
GPS Implementation & correct reporting
Novire GPS reports utilization
Reducing distributor detention
Initiate night unloading
Reduce Volume skew-ness
Bar on Order cut off time
Install RFID
Order staging at bay locations in Plant
52
27
3.1.2What evidence showed that the solutions / improvements identified were
possible instead of final? ( 3/3)
Each of possible solution was identified through data door or process analysis
Brainstorming Session
Brainstorming Session
53
3.2.1
01
What method and / or tools were used to identify the final solution(s) /
improvement(s)? ( 1/3)
• Day+1dispatch/ delivery compliance
• Dynamic Scheduling & Time slot Planning
• Right vehicle pool sizing • GPS Implementation & correct
reporting • Novire GPS reports utilization • Reducing distributor detention• Initiate night unloading • Reduce Volume skew-ness• Bar on Order cut off time • Install RFID• Order staging at bay locations in
Plant
Selection Criteria
CTQ ImpactProject Performance Indicators
Time ImpactImplementation time
Cost ImpactImplementation Cost
EaseSimplicity of Implementation
Top 11 Possible Solution
HIGH ImpactMedium Impact
Low Impact
HML
54
28
3.2.1Why were these method and / or tools were selected (to identify the final solution(s) /
improvement(s)? ( 2/3) How was the team prepared to use these method and / or tools (to identify
the final solution(s) / improvement(s)? ( 3/3)
13 Possible Solutions How
Refresher Training on the tool utilizationHighlighting benefit of the tool in identifying the root causeTeam meeting and brainstorming sessionAnalysis of stakeholders MatrixExpert opinion of champion & SponsorWar room setup for free flow discussion
Sigma Impact
Maximum Impact on CTQ
Time Impact
Cost Impact
Ease Implementation &
replication
To meet budges
To meet deadlines
Why
55
3.2.2How were the methods and / or tools used to determine the final
solution(s) / Improvement(s)? ( 1/2)
11 Possible Solutions
Step 2 Prioritization of possible solution
CTQ Impact
Ease Cost
ImpactTime
Impact
Solution Selection Priority Number
Final Solutions
All the numbers are represented are masked considering business confidentiality
56
Possible Solutions Before AfterTAT
improvementDay+1dispatch/ delivery compliance 0.85 0.9 Medium
Dynamic Scheduling & Time slot Planning 0 0.6 High
Right vehicle pool sizing x
50%
reductio
n
High
GPS Implementation & correct reporting 0 850 high
Novire GPS reports utilization 0 0.6 medium
Reducing distributor detention 15hrs 7-8 hrs medium
Initiate night unloading 0
5%
distribut
ors
medium
Reduce Volume skew-ness 65% medium
Bar on Order cut off time no time8pm
timemedium
Install RFID 0 1 medium
Order staging at bay locations in Plant 0 5 medium
29
3.2.2What was (were) the final solution(s) / Improvement(s)? ( 2/2)
57
Final Solutions
Right Pool Sizing
Dynamic Time slot planning
GPS Installation & tracking
Night Unloading
Distributor Detention Reduction
Improvement
3.2.3How were the final solution(s) / Improvement(s) validated ? ( 1/2)
Final Solution validated through pilot testing
How
13 Possible Solutions
Brainstor
ming
Solution
Selectio
n Matric
Motivating
PotentialSolution
Prioritized Solutions
Pilot & Implemented
6 Final Solutions
PotentialSolution
Prioritized Solutions
Pilot & Implemented
Result
Validated
Non Validated
RCAModified Solutions
Validation Process
We need to Put some
evidence
58
30
3.2.3What evidence showed that the validation was performed prior to
implementation ? ( 2/2)
A pilot run was conducted in natural environment to gauge the actual out put of suggested change in process. After pilot team observed a downward trend in vehicle requirement
59
50
71
105
149
47
63
87
103
145
119
95
0
20
40
60
80
100
120
140
160
May 1st Week May 2nd Week May 3rd Week May 4th Week June 1st Week June 2nd Week June 3rd Week June 4th Week June 5th Week
Avg Vehicle Requirement vs Regular vehicle
Avg Vehicle Requirement Earlier Veh pool Current Vehicle Pool
3.2.4What additional potential benefits were anticipated from the final
solution(s) / improvement(s) ? ( 1/2)
Monthly Availability Index
Customer satisfaction Index
Novire reports waiting time
Weekly TAT Report
Product Availability
Customer Satisfaction
Reduction in detention
Improvement in TAT
MetricsPotential Benefits
60
31
3.2.4Were the additional potential benefit anticipated prior to implementation ?
( 2/2)
Additional Benefits Metrics
Increase Day+1 Compliance % increase in next day dispatches
Dynamic Time slot planning Gate Exit to Gate In time
Night Unloading Night dispatches
Reduce Distributor Detention Vehicle no.
Optimize Vehicle Pool size Volume based vehicle pool size
61
3.2.5What data was generated and how was the data analyzed to justify why the
chosen final solution(s) / improvement(s) should be implemented?( 1/2)
20 Possible Solutions
5 Justified Solutions
5 Validated Solutions
11 Shortlisted Solutions
Solution Selection Metrics, Brainstorming & Multi-Voting
Validation CriteriaPilot Run
market feasibility
Stakeholders approvals
Customer centricity
Data Analysis output
Process Analysis output
Justification Criteria
Implementation Feasibility
Cost Benefit analysis
Market acceptability
62
32
3.2.5What evidence showed that justification was performed prior to
implementation ?( 2/2)
Pilot Run
Management Buy-in
63
5071
105
149
4763
87103
145119
0
20
40
60
80
100
120
140
160
May 1stWeek
May 2ndWeek
May 3rdWeek
May 4thWeek
June 1stWeek
June2nd
Week
June 3rdWeek
June 4thWeek
June 5thWeek
Avg Vehicle Requirement vs Regular vehicle
Avg Vehicle Requirement Vehicle in the system
3.3.1How was the correctness of the initial or updated project scope,
deliverables, and timing confirmed (or what changes were made)?( 1/4)
64
Financial Impact
uScope:
nIn-Scope/Out-of-Scope - GPS
Vehicles/ Non- GPS Vehicles
n(Process Start/Stop)
uState financial impact of project -
24Cr in 3yrs
nExpenses
nInvestments (inventory, capital, A/R) -
GPS
nRevenues
Team
uPES Shipping Project Executive Sponsor (if different
from PS)
uPS Supply Chain Head Project Sponsor/Process Owner Toll Gate Review Schedule
uDC RTM Deployment Champion Tollgate ScheduledRevised Complete
uGB/BB Akansha Tyagi Green Belt/Black Belt Define : Feb 2017-Mar 2017 15/02/17 - 15/02/17
uMBB Kunal Sharma Master Black Belt Measure : Mar 2017 – Apr - 2017 20/03/17 20/03/17
Core Team Role % Contrib. LSS Training Analyse: Apr 2017 – May 2017 17/04/17 19/04/17 19/04/17
uDevesh Malik Transportation
Manager
SME XX Improve: May 2017 – Jun 2017 29/05/17 30/05/17 30/05/17
uTarun Sawhney RTM Manager 20% GB Control : Jul 2017- Aug 2017 13/06/17 13/06/17
uB SriRam RTM Manager 25% PS
Extended Team uReview high-level schedule
milestones here:
uMohit RTM 15% Not Trained nPhase Completions
uRalins RTM 15% Not Trained nTollgate Reviews
Problem/ Goal Statement
Problem: Reduce the Vehicle TAT to 24hrs for <150km & <36hrs for <36hrs
Goal: Before Overall TAT - 60hrs, Target - 36hrs overall
nShift mean, variance, or both
nShould impact cost, time, quality dimensions
uExpress goals using SMART criteria
nSpecific, Measurable, Attainable, Resource Requirements, Time Boundaries
uExplain leverage and strategic implications - Vehicle Pool Reduction
33
3.3.1How were stakeholders involved and /or communicated with during the
solution / improvement phase of the project ?( 2/4 )
Obtain the Voice of CustomerBE Management Team
Core Execution Team
Steering Committee
Stakeholder groups How
Monthly review with National & Zonal Committee
Help Prepare the selection criteriaMonitoring and validating the pilot test results
OE Team Mentor project team with DMADV approachDrive the project time lines and project meeting
One on One meeting, Email & Con Calls
Communication Mechanism
Review Meetings and Regular emails
Weekly/Fortnightly, Monthly reviewSharing the status of validated resultsParticipating in project toll gates
Toll Gates Publishing MIS & progress Reports
65
3.3.1What stakeholder resistance was identified and /or addressed in this phase
of the project ? ( 3/4 )
01
NoneBE Management Team
Core Execution Team
Steering Committee
Stakeholder groups Resistance
None
Why do I need to collect data on the causesI need to focus on my current business
OE Team The longevity of the retained & new outlets
Impact
H
M
None
None
Initial data collection reveals some of the mythsTeam alignment was done before initiating the projectNecessary R&R was put in place
Tracking mechanism put in place
Communication Mechanism
66
34
3.3.1How was the appropriateness of the initial or updated team membership
and management routines confirmed (or what changes were made)? ( 4/4 )
Expectation establishmentCommon GoalTeam ContactTrust
Achieving resultsFinding solutionsCaringEstablishing unique identity
Agreement on roles & ideasDuring projectNegotiationsConsensus building
Roles & ResponsibilityExpressing IdeasInterdependentReacting
Skill set Mapping+Training+Engagement
Forming PerformingNormingStorming
ManagementSales & Operations TeamCapability DevelopmentDistributionMarketingLegal
C
o
r
e
T
e
a
m
Management Routine Confirmation
SC Head
Steering Committee
Sales &Ops Head
Monthly Review
Monthly to Fortnightly
Weekly
✓
✓
✓
67
Section : 4Implementation and Result Verification
68
All the numbers are represented are masked considering business confidentiality
35
4.1.1How were stakeholder involved in planning the solution / improvement
implementation ? ( 1/2 )
SC - DirectorSC Management Team
Core Execution Team
Steering Committee
Stakeholder groups who How
Zonal Vice PresidentZonal Supply Chain HeadZonal Operation HeadZonal RTM Head Zonal Finance Head
Sales ManagerArea Sales ManagerCapability Development Manager
BU Team Operational Excellence Team
Obtaining Customer Voice
Approving solution, involving in strategic decisionReview solution implementation progressLeading change management
Providing expert adviseResolving cross functional inter linkageAligning team with their functionsImplementing new processes
SWOT analysis of the solutionsImplementation of solutionsProject Plan and internal reviewBusiness Analytics & Improvement validation
69
4.1.1How were stakeholder involved in implementing the solution / improvement
implementation ? ( 2/2 )
Stakeholder groups Approved CommunicateImplementati
on PlanDevelopment
Resource Allocation
SOP Development
Training Validate Results
SC Management Team
Steering Committee
Core Execution Team
BU Team
✓
✓ ✓✓✓✓
✓ ✓
✓✓
✓
✓
✓✓
Stakeholders Involvement
70
36
4.1.2What was done to anticipate resistance before it occurred ? ( 1/3 )
What types of resistance were actually encountered during the course of solution /
improvement implementation? ( 2/3 )
Stakeholders WHO Allegiance ImpactResistance
Encountered
SC Management Team
SC - Director
None None
Steering Committee
Zonal Vice PresidentZonal Supply Chain HeadZonal Operation HeadZonal Commercial HeadZonal Finance Head
None None
Core Execution Team
Sales ManagerArea Sales ManagerCapability Development Manager
Will cost benefit analysis justifyI need to focus on my current business
OE Team Operational Excellence TeamThe longevity of the retained & new outlets
H
M
Happy
Neutral
Puzzled
71
4.1.2What types of resistance were actually encountered during the course of
solution / improvement implementation? ( 2/3 )
01
NoneBE Management Team
Core Execution Team
Steering Committee
Stakeholder groups Resistance
None
What are the benefits from thisI need to focus on my current business
OE Team The longevity of the retained & new outlets
Impact
H
M
None
None
Pilot implementation helped in taking care of identified resistanceTeam alignment was done before initiating the projectNecessary R&R was put in place
Tracking mechanism put in place
Communication Mechanism
72
37
4.1.2How was the actual resistance identified? ( 3/3 )
Stakeholders WHOResistance
Encountered
SC Management Team
SC - Director
Steering Committee
Zonal Vice PresidentZonal Supply Chain HeadZonal Operation HeadZonal Commercial HeadZonal Finance Head
Core Execution Team
Sales ManagerArea Sales ManagerCapability Development Manager
Will cost benefit analysis justifyI need to focus on my current business
BU Team Operational Excellence TeamThe longevity of the retained & new outlets
Stakeholder Analysis
Meeting with StakeholdersMeeting with
teamCommunicate
with Core team members
73
4.1.3How was the actual resistance addressed? ( 1/2 )
Aligning the team with Big Y and TCCC vision 2020Group discussion with stakeholderOne on One Meeting
One on One meeting conducted with the cross functional SME and SPOC to make them understand the benefit of the project.Splash BAR SME sent a mailer across the org stating the potential of the splash bar business.Zone wise capability development managers met with the zonal management team members for the smooth implementation of the project.
Project team meeting with champions on fortnightly basisProject team cross functional team meeting with the management team on monthly basis
Aligning the Team with Big Y & Vision 2020
Pan India workshop conducted to cascade vision 2020Zone wise meeting conducted to cascade the benefit of touching the customers in bottom of pyramid
Group Discussion with Stakeholders
One on One Meeting
74
38
4.1.3How did the team know it was successful in addressing the resistance ?
( 2/2 )
7585 81
8895
0
10
20
30
40
50
60
70
80
90
100
Define Measure Analyse Design Validate
GRPI Score
GRPI Score
Continuous improvement in GRPI score from start of the project till end
All the numbers are represented are masked considering business confidentiality
75
4.1.4What was the evidence of stakeholder group buy-in? ( 1/2 )
Stakeholders WHO AcceptanceAcceptance Assurance
SC Management Team
SC - DirectorObtaining Customers Voice
Steering Committee
Zonal Vice PresidentZonal Supply Chain HeadZonal Operation HeadZonal Commercial HeadZonal Finance Head
By obtaining the approval at every stage
Core Execution Team
Sales ManagerArea Sales ManagerCapability Development Manager
By involving them in developing and implementing the solutions
BU Team Operational Excellence TeamDeveloping and implementing solutions
H
M
H
H
All the numbers are represented are masked considering business confidentiality
76
39
4.1.4What evidence showed that buy-in was obtained prior to Implementation?
( 2/2 )
All the numbers are represented are masked considering business confidentiality7777
4.2.1What process (es) or system (s) were changed or created to implement the
solution / improvement? ( 1/2 )
• Day+1dispatch/ delivery compliance tracking
1
• Dynamic Scheduling & Time slot Planning tracking
2
• Right vehicle pool sizing monthly
3
• GPS Implementation & correct reporting continuous
4
• Initiate night unloading ongoing
5
• Order staging at bay locations in Plant
6
78
40
4.2.1What systems were changed or created to measure and manage the
performance of the implementation? ( 2/2 )
PAN INDIA
1. Select only the Following Locations :1. HCCB Plants 2. HCCB Depots3. Distributors 4. Anchors (Could be avoided)5. IU Dispatches (Could be Avoided)
2. Select only the Following Vehicles :1. GPS Installed2. Fixed Vehicles 3. Full body Vehicles 4. Half Body Vehicles
3. Select Zones that have GPS installed vehicles and that use Novire GPS Reports4. The Vehicle owner has agreed for GPS installation
DON’T SELECT VEHICLES THAT HAVE NOT GPS INSTALLED AS THEY ARE OUT OF OUR TRACKING SYSTEM
79
4.3.1What were the result ? ( 1/2 )
The above chart shows that this project delivered a significant improvement in TAT of vehicles from 2015-2016-2017
WUP & AP have shown a significant improvement
All the numbers are represented are masked considering business confidentiality
80
41
4.3.1How did the result compare to the specific project goal / measures from
item 2.1.1 ? ( 2/2 )
All the numbers are represented are masked considering business confidentiality
81
The overall TAT value in 2015 was 72hrs which got reduced to 58hrs in 2016 and 42hrs in 2017The result of KPIs developed are:No. of vehicles doing <24hrs TAT for <150km distance : 75%No. of vehicles doing <36hrs TAT for >150km distamce : 50%
4.3.2What additional benefits were realized from the project? ( 1/3 )
How did the team measure any of the additional benefit that were “soft” ? ( 2/3 )
82
Additional Benefits Metrics
Increase Day+1 Compliance % increase in next day dispatches
Dynamic Time slot planning Gate Exit to Gate In time
Night Unloading Night dispatches
Reduce Distributor Detention Vehicle no.
Optimize Vehicle Pool size Volume based vehicle pool size
42
4.3.2How do the actual additional benefits that were realized compare to
expected additional benefits identified in Item 3.2.4 ? ( 3/3 )
Additional Benefits
Metrics Base Line Expected Achieve
Increase Day+1 Compliance
% increase in next day dispatches
80% 100% 90%
Dynamic Time slot planning
Gate Exit to Gate In time
0 100% 50%
Night Unloading Night dispatches 0% 50% 10%
ReduceDistributor Detention
Vehicle no. 0%
Optimize Vehicle Pool size
Volume based vehicle pool size
0% 50% 30%
All the numbers are represented are masked considering business confidentiality
83
Section : 5Sustaining and Communicating Result
84
All the numbers are represented are masked considering business confidentiality
43
5.1.1What was done make sure the process or system changes made during the
implementation (item 4.2.1) continue to be followed? (1/2 )
Final Solution Systemic / Process Changes
Increase Day+1 Compliance1. Weekly Day+1 compliance report flash2. Formula change for Day0 delivery
Dynamic Time slot planning Planning of vehicles and order mapping in advance
Night Unloading HCCBPL & distributors negotiation for night unloading
Reduce Distributor Detention Vehicle exit from plant basis distributor preferable unloading time
Optimize Vehicle Pool size Revision of fixed pool vehicles basis volume skewness
Business Reviews by steering committee on identified actionsPerformance dashboard release by core team to the stakeholders
All the numbers are represented are masked considering business confidentiality
85
5.1.1What evidence showed that this became part of the Organization’s Culture /
Operating strategy? ( 2/2 )
Day+1 Compliance Report Dynamic Time Slot planning GPS Live Tracking
Culture Change : Key Focus Areas
All the numbers are represented are masked considering business confidentiality
86
44
5.1.2What was done to make sure that the benefits obtained from the
implementation ( Item 4.2.1) will be maintained ? ( 1/2 )
Governance Reviews
Dashboard
Goals/ KRA
Scorecards
How we measured and monitored the results
All the numbers are represented are masked considering business confidentiality
87
5.1.2What evidence showed that this became part of the organization’s culture /
operating strategy? ( 2/2 )
Weekly & monthly Reviews Execution Zonal plans
All the numbers are represented are masked considering business confidentiality
88
45
5.2.1How did the team communicate the results to the various stakeholder
groups? ( 1/1 )
Back End Management Team
Core Execution Team
Steering Committee
Stakeholder groups
Other Stakeholders
Communication Mode
• Business update• Town hall• MIS & Dashboard
• Project Review• Newsletter• MIS & Dashboard