THE CHANNEL TUNNEL Geological Problems Encountered and Solutions Implemented.
-
Upload
cornelia-scott -
Category
Documents
-
view
259 -
download
4
Transcript of THE CHANNEL TUNNEL Geological Problems Encountered and Solutions Implemented.
THE CHANNEL TUNNELGeological Problems Encountered and Solutions
Implemented
Introduction Geology Problems Summary
Overview
Contents of Presentation Description Geology Conditions Encountered Solutions End Result
Description of tunnel Cost Length Duration of Construction
Location
Introduction
Introduction Geology Problems Summary
Site Investigation
Boreholes
Probing
Seismic Surveys
Geology
Introduction Geology Problems Summary
Geology
Description of Geology Upper Chalk (Coniacian layer) Middle Chalk (Turonian layer) Lower Chalk (Cenomanian layer) Gault Clay (Albian layer)
Location of planned excavation Depth and layer Favourable properties
Geology
Introduction Geology Problems Summary
GeologyGeology
Introduction Geology Problems Summary
Detailed Solutions
Combination of measures implemented
TBM design resists 11 bar pressure Flexible hood controls
broken ground
Tunnel Lining Spheroidal graphite cast-
iron lining (SGI)
Problems
Introduction Geology Problems Summary
Detailed Solutions
Ground treatment Grouting from MST Tube a Machete forces
grout into rock Reduces permeability Eliminates water-bearing
fissures
Problems
Introduction Geology Problems Summary
Summary
Boring & probing establishes potential hazards
Chalk marl strata ideal
Solutions in unfavourable conditions
Importance of geology in civil engineering
Thank you for listening - Any questions?
Summary