The Case for the Federal Hopper Dredge Fleet On the Pacific Coast.
-
Upload
jason-black -
Category
Documents
-
view
217 -
download
0
Transcript of The Case for the Federal Hopper Dredge Fleet On the Pacific Coast.
The Case for the Federal Hopper Dredge Fleet
On the Pacific Coast
Issue Areas:
Goals of Public Law 95-269
Importance of hopper dredging to West Coast ports
Cost of the federal dredge fleet
Competitiveness in the hopper dredge industry
Impact of operating limitations on cost effectiveness
The cost of the ready reserve
Data gaps
Key Findings and Conclusions
Goals: Develop a domestic commercial hopper
capability
Reasonable prices in a timely manner
Emergency and national response capability
The Goals of PL 95-269
05
10152025
1970
1980
1990
2000
Curr
ent
Commercial Fleet Corps Fleet
Num
ber
of
Vess
els
Findings: Corps hopper dredges
decreased from 14 to 4
Industry hopper dredges increased from 0 to 17
Industry now owns over 80% of the national
hopper fleet.
Key Findings and Conclusions
The Goals of PL 95-262(continued)
Industry: Performs 83% of federal
dredging (volume)
Accounts for 89% of program (expenditures)
Performs about 75% of all hopper dredging
Hopper contracts average $135 million per year
Key Findings and Conclusions
The Goals of PL 95-262(continued)
Distribution of Work
(Volume)
I ndustry Non-
hopper 65%
I ndustry Hopper
18%
Corps Non-
hopper11%
Corps Hopper
6%
Conclusions:
The goal to establish a commercial hopper dredge industry has been met.
No further restrictions on the Corps fleet are necessary.
Key Findings and Conclusions
The Goals of PL 95-262(continued)
Can the program be more responsive Can the program be more responsive and cost effective?and cost effective?
Key Findings and Conclusions
The Importance of Hopper Dredging to West Coast Ports
Key Findings and Conclusions
Findings: Hopper dredging:
50-60% of all West Coast dredging85% of Oregon dredgingCorps dredges = 60%
Unique conditions:High proportion of small projectsHigh incidence of adverse weatherOnly one private firm on West Coast5 to 12 weeks to move dredge from East Coast...
The Importance of Hopper Dredging to West Coast Ports
MobilizationTimes and Distances to West Coast
Florida to Texas1400 Miles, 1 Week
6
East Coast N-S2100 Miles, 1-2 Weeks
Portland to Alaska1500 Miles, 1 Week
Between East andWest Coast via Panama Canal8400 Miles, 5 Weeks
Between East an dWest Coast via Cape Horn20000 Miles, 12 Weeks
Portland to Hawaii2000 Miles, 1 ½ Weeks
Great Lakes to East Coast, 2000-3000miles, 1-2 Weeks
Key Findings and Conclusions
= Corps
= Industry
Key Findings and Conclusions
The Cost of the Federal Dredge Fleet
Hopper Fleet Cost ComparisonsAverage cost per cubic yard - current policy
FiscalYear
Private HopperDreges
Corps HopperDredges
1996 $2.31 $2.33
1997 $2.18 $1.93
1998 $2.61 $2.65
1999 $3.02 $3.14
2000 $2.59 $3.03
5 Year Avg $2.54 $2.62
On average, Corps hopper dredges cost$.08 per yard more (3%) than private hopper dredges
Key Findings and Conclusions
Key Findings and Conclusions
The Cost of the Federal Dredge Fleet(continued)
Comparison of Operating Cost
Small Class Vessels - West Coast Projects
$4.65$4.45
$-
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
$14.00
CHR COQ ROG SI U YAQ GRH Total
Projects 1997-2001
Cos
t ($
per
Cub
ic Y
d)
Yaquina
Westport
CHR = Chetco RiverCOQ = Coquille RiverROG = Rogue RiverSIU = Siuslaw RiverYAQ = Yaquina RiverGRH = Grays Harbor
Impact of Removing Operating Limits
Corps rates can be reduced 12%-16% by increasing Corps rates can be reduced 12%-16% by increasing the number of days in the operating yearthe number of days in the operating year
Key Findings and Conclusions
Yaquina Annual Operating Cost and Rental Rate
$8.8 $9.5 $9.7 $9.9
$49.5$41.5 $38.9
$36.1
$8,000
$8,500
$9,000
$9,500
$10,000
$10,500
178 230 250 275Operating Days per Year
Ann
ual C
ost
($ 0
00)
$-
$10.0
$20.0
$30.0
$40.0
$50.0
$60.0
Dai
ly R
enta
l Rat
e ($
000)
Annual Operating Cost Cost per day
Key Findings and Conclusions
Competitiveness in the Hopper Dredge Industry
Key Findings and Conclusions
Competitiveness in the Hopper Dredge Industry (continued)
Bidders per Contract vs.
Bid Amounts as % of Gov Estimate
60%
70%
80%
90%
100%
110%
1.5 2.0 2.5 3.0 3.5
Average No. Bidders per Contract
Bid
% o
f G
ov't
Est
Impact of Competition on Bid Price
90%
43%
25% 26% 28%
42%
0%
20%
40%
60%
80%
100%
1 2 3 4 5+ All
Number of Bidders Per Contract
% o
f Con
trac
ts E
xce
edin
g
Gov
Est
Competitiveness in the Hopper Dredge Industry (continued)
} ~ 17% of contracts exceed estimate dueto limitedcompetition
Key Findings and Conclusions
Key Findings and Conclusions
Volume Advertised vs.
Average No. of Bidders
1.0
1.5
2.0
2.5
3.0
3.5
4.0
25.0 35.0 45.0 55.0 65.0
Material (MCY) Advertised Per Year
Avg
No.
of
Bid
ders
per
Con
trac
t
Competitiveness in the Hopper Dredge Industry (continued)
Criterion for an Open Competitive Market
Large number of independent buyers and sellers
Freedom to enter or leave the market
Substitutability of product
All participants have equal access to information
Key Findings and Conclusions
Commercial Hopper Fleet Industry Consolidations
1980s
GLDD / NATCO
Manson / Osberg Co.
C.F. Bean Co.
Williams - McWilliams
American Dredging
T.L. James (Gulf Coast Tr.)
Roger J. Au Co.
1990s
GLDD / NATCO
Manson Construction Co.
Bean - Stuyvesant LLC
Weeks Marine Inc.
B+B Dredging Corp.
Key Findings and Conclusions
Increased capability Decreased competition
Private Hopper Dredge Ownership
Great LakesDock & Dredge 40%
Bean Stuyvesant13%
Weeks 13%
B+B 13%Manson 20%
17 total vessels 15 available for
routine maintenance 1 firm owns 40% of
private capability Awarded 37% of work
1 firm on West Coast Awarded 60% of work
Key Findings and Conclusions
Consolidation in ownership of small and large class vessels….
Hopper Dredge OwnershipBy Class of Vessel
VesselClass
(Capacity)
Corps GLDD/NATCO
Manson Weeks B+B Bean/Stuyv
Small(up to 2000 cy)
1(875 CY)
1(1800 CY)
(West Coast)
1(1300 CY)
(Gulf Coast)
1(2160 CY)(For sale)
Medium(2000-6000 cy)
1(3140 CY)
4(ea 3600 CY)
1*(5100)
2(4000 CY)(4800 CY)
2(ea 4000 CY)
1(4425 CY)
1(6000 CY)
1(6000 CY)
Large(over 6000 cy)
1(8000 CY)
(Ready Res)
3*(6350 CY)(6540 CY)
(16,000 CY)
1**(11,000)
* Three GLDD vessels have not participated in federal maintenance dredging:2 for sand mining1 for out-of-country dredging
** Note effort to repeal Jones Act grandfather clause for Stuyvesant
Key Findings and Conclusions
Criterion for an Open Competitive MarketAssessment:
Large number of independent buyers and sellers Only five firms have hopper dredge capability 40% of fleet in one firm Consolidation of large and small dredges One firm on West Coast
Freedom to enter or leave the market Cost of new dredge = $30-$60 Million Relatively fixed demand (average 68 mcy / year) Uncertainty of annual funding
Substitutability of product Limited, due to specialized nature of equipment
All participants have equal access to information
Key Findings and Conclusions
If not an open competitive market, then what is it?If not an open competitive market, then what is it?
Elements of “Natural” Monopoly
High level of initial capital investment
Decrease in marginal cost as output increases Capital costs greatly outweigh operating costs Economy of scale exists over entire demand range
Example: Utilities
Typical Government Responses: Regulated pricing Direct Ownership
Key Findings and Conclusions
Key Findings and Conclusions
The Impact of Corps Operating Year Limitations on Program Cost Effectiveness
Key Findings and Conclusions
The Impact of Corps Operating Year Limitations on Program Cost Effectiveness (continued)
Nationwide:
ChangeChangeFromFrom
FY 90-92FY 90-92toto
FY 93-01FY 93-01
Average No. Private Average AverageAverage No. Private Average AverageVolume Industry Bidders Bid as %Volume Industry Bidders Bid as %Advertised FirmsAdvertised Firms per Contract of Gov Est per Contract of Gov EstINCREASED! DECREASED! DECREASED! INCREASED!INCREASED! DECREASED! DECREASED! INCREASED!
37.2 MCY37.2 MCY
3.03.077
84%84%
51.1 MCY51.1 MCY 95%95%
2.42.455
Key Findings and Conclusions
The Impact of Corps Operating Year Limitations on Program Cost Effectiveness (continued)
Impacts of 1993 - West Coast:
4.3 MCY4.3 MCY
2.92.911
89%89%
5.6 MCY5.6 MCY 98%98%
2.42.411
ChangeFrom
FY 90-92to
FY 93-01
Average No. Private Average AverageAverage No. Private Average AverageVolume Industry Bidders Bid as %Volume Industry Bidders Bid as %Advertised FirmsAdvertised Firms per Contract of Gov Est per Contract of Gov EstINCREASED! NO CHANGE! DECREASED! INCREASED!INCREASED! NO CHANGE! DECREASED! INCREASED!
Trends in Demand
Dredging demand fairly stable since 1996 Total demand ~ 270 mcy per year Hopper demand ~ 68 mcy per year
Expansion of existing ports Deeper harbors and channels Operating constraints due to environmental
windows
Trend: An increasing amount of work chasing a limited number of dredge firms
over a decreasing amount of time
Key Findings and Conclusions
Conclusions: New restrictions on McFarland + increased
demand will result in more work for industry More work for industry will result in fewer bidders
per project and increased bid prices unless… More work results in additional competing firms
Key Findings and Conclusions
The Impact of Corps Operating Year Limitations on Program Cost Effectiveness (continued)
Allocating more work to Corps vessels will result in:- More competitive bidding- Increased efficiency of Corps fleet- Lower program cost
Recommendations
Impose no further operating restrictions on the Corps hopper dredge fleet.
Repeal the restrictions on the number of days the Yaquina and Essayons are allowed to operate each year.
Ensure the Yaquina and Essayons are maintained to a level consistent with the safe and efficient performance of their missions.
Closing Thought:
““As in the case of public power, a limited government As in the case of public power, a limited government role in a predominately private industry can generate role in a predominately private industry can generate benefits that flow in both directions.benefits that flow in both directions.
The public company is constrained and tested by the The public company is constrained and tested by the record of the private companies, while the private record of the private companies, while the private ones are obliged to measure up to the yardstick ones are obliged to measure up to the yardstick established by the public activity.”established by the public activity.”
From A.K. Okun, Equality and Efficiency, Brookings Institute, 1975.
Questions?
The Case for the Federal Hopper Dredge Fleet
On the Pacific Coast