The BNL National Synchrotron Light Sourceshpschapters.org/sections/accelerator/casey-the bnl light...
Transcript of The BNL National Synchrotron Light Sourceshpschapters.org/sections/accelerator/casey-the bnl light...
1 BROOKHAVEN SCIENCE ASSOCIATES
The BNL National Synchrotron Light Sources
Bob CaseySenior Health Physicist
NSLS-II ESH StaffJune 29, 2010
2 BROOKHAVEN SCIENCE ASSOCIATES
BNL Site
3 BROOKHAVEN SCIENCE ASSOCIATES
BNL Site in 1947
4 BROOKHAVEN SCIENCE ASSOCIATES
5 BROOKHAVEN SCIENCE ASSOCIATES
“At the beginning of the last decade (1950) the shielding ofa high-energy accelerator was quite often considered as an afterthought or last-minute addition to the early experimental-program requirements.” – “S. Lindenbaum”
6 BROOKHAVEN SCIENCE ASSOCIATES
AGS Under Construction
7 BROOKHAVEN SCIENCE ASSOCIATES
AGS – 10 years later
8 BROOKHAVEN SCIENCE ASSOCIATES
Brief AGS History
• Construction started ~ 1956
• Achieved design energy 33 GeV – July, 1960
• Nobel prizes• Muon neutrino – 1962 experiment (Awarded in 1988)• CP Violation – 1963 experiment (Awarded in 1980)• J/Psi particle – 1974 experiment (awarded in 1976)
• Upgraded in intensity many times• Designed for 1 x 1010 p/p• Eventually 7.5 x 1013 p/p
9 BROOKHAVEN SCIENCE ASSOCIATES
10 BROOKHAVEN SCIENCE ASSOCIATES
Enough of proton machines
Lets talk about synchrotron radiation sources
11 BROOKHAVEN SCIENCE ASSOCIATES
Synchrotron Radiation• It had been recognized from laws of electrodynamics that
charged particles will emit radiation when direction or velocity is altered.
• A letter to the Physical Review in 1944 predicted that radiation emitted by electrons would establish a “limitation for maximally energy attainable” in synchrotrons.
• An electron synchrotron built by GE in 1946 observed the emitted and the term “synchrotron radiation” was developed.
12 BROOKHAVEN SCIENCE ASSOCIATES
Synchrotron Radiation (cont.)
• Considered a “nuisance” because of the limitations it imposed on maximum energies for circular machines
• However, scientists began to study the radiation and noted quickly the potential uses for research in absorption spectroscopy and fields.
• “Tantalus” began operation in 1968 as a synchrotron radiation source. It was a 12.5 GeV proton storage ring converted into a 240 MeV electron ring - first dedicated device.
13 BROOKHAVEN SCIENCE ASSOCIATES
Synchrotron Radiation (cont.)
• Other facilities (e.g. 540 MeV ring at Orsay, 250 MeV ring (SURF II) at NBS) adapted facilities for synchrotron radiation research
• Within the U.S., demand for synchrotron radiation research time at electron storage rings often conflicted with high energy physics demands.
• Solid state physicists at BNL recognized the importance of SR research and began an effort to develop wider support for the building of a dedicated synchrotron radiation source.
14 BROOKHAVEN SCIENCE ASSOCIATES
15 BROOKHAVEN SCIENCE ASSOCIATES
16 BROOKHAVEN SCIENCE ASSOCIATES
17 BROOKHAVEN SCIENCE ASSOCIATES
18 BROOKHAVEN SCIENCE ASSOCIATES
19 BROOKHAVEN SCIENCE ASSOCIATES
20 BROOKHAVEN SCIENCE ASSOCIATES
Chasman Green Lattice
• Chasman-Greene developed the first electron synchrotron magnet lattice that was intended to minimize the emittance of the beam – the double-bend achromat
• the Chasman-Greene lattice and its variation are the basis for most of today’s synchrotron sources
• An important figure of merit for a light source is its brilliance. The Chasman – Green lattice was very important in achieving high brilliance in SR beams.
21 BROOKHAVEN SCIENCE ASSOCIATES
NSLS Project Proposal
• Final proposal for the National Synchrotron Light Source submitted to ERDA in Feb. 1977
• Requested $24 million to build 2 rings• Construction to start Oct. 1, 1978• Project to be completed Oct. 1981
• Project was approved for design start Oct. 1, 1977
22 BROOKHAVEN SCIENCE ASSOCIATES
Ground-breaking - September 1978
23 BROOKHAVEN SCIENCE ASSOCIATES
Fall 1980
24 BROOKHAVEN SCIENCE ASSOCIATES
First Light - 1982
25 BROOKHAVEN SCIENCE ASSOCIATES
Early NSLS History
• NSLS was dedicated in fall 1982, but was suffering from a number of compromises imposed by the funding shortfall.• VUV was far from the planned beam current and life time,
but was operating with a limited program• X-ray had beam but required on-going improvements for
two years before able to support an experimental program. • Shielding was added as needed for linac, booster and VUV
• However, they persevered and within several years a very strong research program was established.
26 BROOKHAVEN SCIENCE ASSOCIATES
NSLS Now
27 BROOKHAVEN SCIENCE ASSOCIATES
NSLS
VUV RING• E = 0.8 GeV• εx = 155 nm• C = 51 m• I = 1 Amp
XRAY RING• E = 2.8 GeV• εx = 60 nm• C = 170 m• I = 0.3 Amp
Booster & Linac• E = 0.12 - 0.8 GeV• C = 28 m, 0.7 Hz• I = 0.01 Amp
28 BROOKHAVEN SCIENCE ASSOCIATES
So lets talk Radiation Safety
29 BROOKHAVEN SCIENCE ASSOCIATES
Three Key NSLS Radiation Safety Issues
• How do you handle 2500 users involved in 1200 different experiments each year?
• How do you handle Hutch “Search and Secure” 100,000 times per year?
• How do you operate an accelerator with inadequate shielding?
30 BROOKHAVEN SCIENCE ASSOCIATES
Bill Thomlinson
31 BROOKHAVEN SCIENCE ASSOCIATES
Tom Dickinson
32 BROOKHAVEN SCIENCE ASSOCIATES
The Light Source User Community• Very diverse group
• different fields of research• different experiences
• Often inexperienced with synchrotrons and beam lines (UWOC)
• Often present at the facility for short periods of time, including week-ends and nights
• They arrive with their samples, sometimes with special equipment, & stay a day or two and then leave.
33 BROOKHAVEN SCIENCE ASSOCIATES
How do you handle 2500 Users a year?The NSLS Approach - Research Operations
• NSLS staff assigned full-time responsibility to provide operational ESH support and over-sight of beam lines and users• 9 operations coordinators (opcos) providing coverage 24/7• 5 ESH staff working normal hours
• Responsible for:• Safety review of experiments• Check-in and oversight of user groups at beam lines• Configuration control of shielding components, interlocks &
radiation safety barriers
34 BROOKHAVEN SCIENCE ASSOCIATES
Safety Review
• Details of each experiment must be submitted in advance for review by ESH professional
• Extended review required for complex experiments
• Submissions and reviews addressed through networked database.
• Experiments may not begin without ESH approval.
35 BROOKHAVEN SCIENCE ASSOCIATES
Check-in and Oversight of User Groups at Beam Lines
• Each experiment is enabled at beam line by Operations Coordinator following confirmation of:• ESH approval• Completion of all training (Building, ESH, and beam line specific)• Satisfaction of any other conditions established for the experiment during the safety
review
• All electrical equipment must be inspected for NRTL listing
• Overhead cranes and machine shops locked out – use restricted to authorized persons only.
• Two operations coordinators are on duty and make routine rounds through-out each shift.
• NSLS Safety Officer and other ESH staff routinely on floor through-out the day.
36 BROOKHAVEN SCIENCE ASSOCIATES
Beam Line Configuration Control
• Shielding & Radiation Safety Components• Any change requires Safety System permit approved by
Safety Officer• Start-up check-list completed by OpCo• Photographs to confirm configuration
• Interlock • Safety system permit required for work on system• Work by authorized personnel only• Re-test of system following any modification
37 BROOKHAVEN SCIENCE ASSOCIATES
38 BROOKHAVEN SCIENCE ASSOCIATES
X-29 Beam Line Configuration Control
39 BROOKHAVEN SCIENCE ASSOCIATES
X-29 beam line
40 BROOKHAVEN SCIENCE ASSOCIATES
Issue 2 - Hutch Search and Secure
• Previously at BNL, only departmental staff were authorized to search and secure a “high hazard” area
• It was very clear early in the research program that another approach was necessary at NSLS – it was simply not practical to require NSLS operations to secure every hutch following entry.
• Solution • Develop and implement hutch interlocks and “search and secure”
hardware that is simple to use and highly reliable• Authorize users and beam line staff to conduct search and secure
41 BROOKHAVEN SCIENCE ASSOCIATES
NSLS Interlock Principles• System should be fail-safe
• Loss of power• Short to ground• Open circuit
• System should be redundant – 2 chains independent of each other
• Redundant branches should be different• PLC on one chain, relay logic in 2nd chain• Different types of switches
• System should be readily testable
• System should be simple
42 BROOKHAVEN SCIENCE ASSOCIATES
Interlock History• System has proved highly reliable and simple to use
• No complete loss of protective function during 25 year history
• All interlocks are tested and recertified on a 6 month frequency. We recently sought extension of test frequency, but were unable to justify it after conducting failure mode analysis.
43 BROOKHAVEN SCIENCE ASSOCIATES
A Few Pictures of the Hutch Search and Secure
44 BROOKHAVEN SCIENCE ASSOCIATES
Hutch Entry
45 BROOKHAVEN SCIENCE ASSOCIATES
Hutch Door Prior to Entry
46 BROOKHAVEN SCIENCE ASSOCIATES
X -28 Hutch Following Entry
47 BROOKHAVEN SCIENCE ASSOCIATES
X-28 Hutch interior
48 BROOKHAVEN SCIENCE ASSOCIATES
Search and Secure History
No instances of improper search or interlock failure resulting in person in hazardous area with hutch “secured”
49 BROOKHAVEN SCIENCE ASSOCIATES
Issue 3 Operating Accelerators with Marginal Shielding
• Booster was assembled with less than optimum components and operated with high injection and extraction losses throughout its history. Near-by areas are subject to elevated radiation fields during booster operation.
• VUV ring was locally shielded with lead bricks. No neutron shields were initially provided. During injections, near-by areas are subject to elevated radiation fields.
50 BROOKHAVEN SCIENCE ASSOCIATES
Booster Enclosure
51 BROOKHAVEN SCIENCE ASSOCIATES
52 BROOKHAVEN SCIENCE ASSOCIATES
VUV Ring
53 BROOKHAVEN SCIENCE ASSOCIATES
54 BROOKHAVEN SCIENCE ASSOCIATES
VUV Ring
55 BROOKHAVEN SCIENCE ASSOCIATES
Shielding Upgrades• Have only been marginally successful
• Radiation exposures have been successfully controlled by:• Limiting times of Booster operations
– VUV fills during normal hours are: 8:00, 12:30, and 5:30– X-ray fills are 7:00 a.m. and 7 p.m.
• VUV floor locked out during commissioning periods following some maintenance periods
• Users on VUV floor are required to stand back from machine and injection line during fills
• Area radiation monitors installed through-out the building, including many offices, with alarms locally and in control room.
56 BROOKHAVEN SCIENCE ASSOCIATES
57 BROOKHAVEN SCIENCE ASSOCIATES
Brief NSLS Summary
• First light source designed and dedicated as a light source for research
• Slow and challenging start, but eventually extremely successful as a research facility.
• 2 Nobel prizes have been won based on research conducted at NSLS
• Excellent safety record – ESH program regarded as one of the best
• Many new synchrotron radiation facilities have been built since the mid 80s with improved performance and NSLS is no longer state of the art.
• Upgrade efforts started in early 2000’s in order to provide state of the art capability for it users.
58 BROOKHAVEN SCIENCE ASSOCIATES
Which Brings Us to NSLS-II
59 BROOKHAVEN SCIENCE ASSOCIATES
1
Light Source Emittance
60 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Project ScopeAccelerator Systems
• Storage Ring (~ ½ mile in circumference),200 MeV linac, and 3 GeV booster• 3 hour life-time • 3 GeV, 500 mA, top-off injection• Ultra-low emittance: εx, εy = 0.6, 0.008 nm-rad• Small beam size: σy = 2.9 µm, σx = 33 µm, σ’y = 2.7 µrad, σ’x = 17 µrad
Conventional Facilities• Ring Building and Service Buildings (~ 400,000 gsf)• Laboratory/Office Buildings (LOBs) (190,000 gsf)
Beam Lines• Initial six insertion device beam lines• Capable of hosting at least 58 beam lines
Total Project Cost: $912M
61 BROOKHAVEN SCIENCE ASSOCIATES
101 102 103 104 1051012
1013
1014
1015
1016
1017
1018
1019
1020
1021
W60U100
U13U5
VBM
X17
XBM
MGUX25X1
BM
U40
Br
ight
ness
[Pho
t/(se
c-0.
1%bw
-mm
2 -mra
d2 )]
Photon Energy (eV)
U14
Average BrightnessNSLS-II vs. NSLS
62 BROOKHAVEN SCIENCE ASSOCIATES
Start of Construction Celebration
From left to right: BHSO Manager Mike Holland, Stony Brook President Shirley Strum Kenny, NSLS-II Federal Project Director FrankCrescenzo, NSLS-II Project Director Steve Dierker, DOE Deputy Director for Science Pat Dehmer, Senator Kirsten Gillibrand, Senator Charles Schumer, BNL Director Sam Aronson, Battelle Executive Vice President Ron Townsend
June 15, 2009
63 BROOKHAVEN SCIENCE ASSOCIATES
Construction ProgressJune 2009
April 2010
64 BROOKHAVEN SCIENCE ASSOCIATES
Construction Progress
Vehicle Tunnel
Structural Steel SR TunnelSR Roof
SR Ratchet WallEntrance Lobby
May 2010
65 BROOKHAVEN SCIENCE ASSOCIATES
Status of NSLS-II Project• Excellent progress
• Project is 30% complete as of end of May 2010
• On schedule and on budget• All major procurements, totaling $214M to date, were awarded within 1% of planned cost
• Key Project MilestonesJuly 2012 Start Linac CommissioningOctober 2012 Start Booster CommissioningOct 2013 Start Accelerator Commissioning Jun 2014 Early Project Completion; Beam Available to Beam linesJun 2015 CD-4, Approve Start of Operations
66 BROOKHAVEN SCIENCE ASSOCIATES
Important Radiation Safety Issues
• Build on NSLS strengths• Include ESH in all engineering design reviews• Adopt beam line safety review process• Adopt training and work planning programs• Adopt Research Operations model
• Make sure that we get the shielding right
• Examine interlock design for improvements
67 BROOKHAVEN SCIENCE ASSOCIATES
Make Sure the Shielding is Right
• Get experienced people – PK Job and Casey
• Document and present all analyses
• Conduct frequent peer review
68 BROOKHAVEN SCIENCE ASSOCIATES
Document and Present all Analyses
• Linac Shields, NSLS II- TN 12• Booster & Storage Ring Shields, NSLS II – TN 13• Storage Ring Supplemental Shielding – NSLS TN 21• Beam lines and Front Ends, NSLS II – TN 14• Activation Analysis, NSLS II – TN 15 & 1• Preliminary Material Requirement for Supplemental Shields
–TN 31• Shielding Estimates for First Optics Enclosures,
Monochromatic Stations, and Monochromatic Beam Transports for the NSLSII Beam lines – TN 33
• Revised Shielding Estimates for the NSLS-II Beam lines at 3.0 GeV Beam Energy – TN 40
69 BROOKHAVEN SCIENCE ASSOCIATES
Document and Present all Analyses (cont.)
• Guidelines for NSLS-II Beam Lines and Front-end Radiation Shielding Design • Final Design Parameters and Beam Loss Assumptions for Shielding Calculations of
Accelerator Enclosures – Jan. 31, 2008• Bulk Shielding Requirements for Final Design of NSLS-II Accelerator Enclosures – Feb.
19, 2008 • Redundancy Requirements for Critical Devices; Presentation at RadSynch Workshop
IV; 6/08• “Shielding Requirements for NSLS-II” – Presented at Mid-year HP Society; 1/08• “Shielding Requirements for NSLS-II Beam Lines” – Presented at ICRS-11; 4/08• ESH Chapter in NSLS-II Preliminary Design Report• NSLS-II Preliminary Safety Assessment Document• “ALARA Analysis of NSLS-II Shield Designs” presented at RadSynch Workshop, 4/09 • The Effectiveness of Thin Low-Z Scrapers in the Electron Storage Rings, RadSynch
Workshop, 4/09• Activation Analysis of Soil, Air and Water near the NSLS II Accelerator Enclosures,
RadSynch Workshop, 4/09
70 BROOKHAVEN SCIENCE ASSOCIATES
Conduct Frequent Peer Review
• We have hosted 3 radiological safety workshops• March, 2007• April, 2008• June, 2010
• Workshop participants include radiation physicists from SLAC, ALS, and ESRF; and accelerator physicists from APS and ALS
• Workshops have been very valuable and help to examine our assumptions and analysis
• In addition we are subject to DOE project review (Lehman review) 1 – 2 times per year
71 BROOKHAVEN SCIENCE ASSOCIATES
Examination of Interlock Design
72 BROOKHAVEN SCIENCE ASSOCIATES
Evaluation of Safety Interlock Integrity
• Performed by independent contractor specializing in fault tree analysis using ISA 84 principles
• Assumes interlock test interval of one year
• Fault tree analysis with specialized computer software used to evaluate probability of failure
• Generic fault rates used for components where rates are not available ( i.e. solenoids and some switches)
73 BROOKHAVEN SCIENCE ASSOCIATES
Evaluation of Safety Interlock Integrity (cont.)• Examined probability of failure for 3 scenarios
• A person enters an enclosure without using the control system to shut down the beam (breaks a door open to enter the protective enclosure) while beam is present.
• A person follows proper procedures to enter an enclosure, but due to failures within the safety system, beam is present on entry.
• A person has entered an enclosure using proper procedures and the control and safety systems have reacted properly. Then, while the individual is present, malfunction of the safety systems allows the safety shutters to open and exposes the person to beam.
74 BROOKHAVEN SCIENCE ASSOCIATES
Conclusions of study:
• Previous design significantly improved by 4 modifications
– Adding a second critical device
– Separating safety and control functions
– Use of Safety PLC’s logic vs. relay logic
– Use of diverse shutter position sensing
• All scenarios have probability of failure < 10 -05
75 BROOKHAVEN SCIENCE ASSOCIATES
Results of Interlock Failure Analysis
76 BROOKHAVEN SCIENCE ASSOCIATES