The Apprentice_Abhrajit Sett_KJ SIMSR

download The Apprentice_Abhrajit Sett_KJ SIMSR

of 24

Transcript of The Apprentice_Abhrajit Sett_KJ SIMSR

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    1/24

    GOODYEARBallabgarh

    REDUCTION OF WASTE FROM EXTRUSION IN TIREMANUFACTURING PROCESS

    Summer Project Presentation

    At

    GOODYEAR INDIA LIMITED,BALLABHGARH

    By

    Abhrajit Sett

    [email protected]

    K J Somaiya Institute of Management Studies and ResearchMumbai

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    2/24

    #1North America

    #1Latin America

    #1

    EasternEurope, MiddleEast, & Africa

    Asia one of the fastestgrowing markets. Goodyear

    holds a # 2 pos ition in market

    #2

    RegionalRank

    A Global Company

    Asia

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    3/24

    Plant Location : 28 km South of Delhi in Haryanastate on National Highway No.2.

    Major Industries in Area : Escorts, Maruti (Gurgaon), JCB, Yamaha,

    Honda (Greater Noida)

    Area : 67 acre with 654,000 sq.ft of floor space

    Manufacturing : Automotive tires started in 1961,presently producing 4100 Tires per day.

    Products : Farm, Truck, LCV tires.

    Goodyear Ballabhgarh

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    4/24

    Natural Rubber

    Banbury - Mixer

    Extrusion

    Calendering

    Tire Building

    Curing

    InspectionDispatch

    OEMRetail

    Tire Building Process

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    5/24

    Plant Layout

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    6/24

    Project Definition

    Data collection

    Root Cause Analysis Actions suggested based on identified root

    causes

    Cost Benefit Analysis Key Learnings

    Project Approach

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    7/24

    DEFINITION

    The main objective of doing the project is to reduce the waste from extruder machinewhich produces tire treads so as to reduce scrap/rework costs and improve theproductivity of the plant.

    SCOPE

    The scope of the project includes study of extrusion waste that occurs in different

    processes during tire making. Reduction of waste in other processes(particularly curing)was beyond the scope.

    The scope is limited till the recommendation phase. The actual implementations of therecommendations are under the purview of the organization.

    ASSUMPTION

    The waste reduction was limited to material waste because the extrusion process bearsslack.

    The bottleneck lies at the curing process so extrusion doesnt work at full capacity.

    The defect data collected was only limited to 7 days in Shift A. The defects in other shiftsare expected to be of same pattern.

    Project Objective

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    8/24

    Compoundstorage area

    Capbreakd

    ownmill

    Basebreakd

    ownmill

    Capfeedmill

    Basefeedmill

    EXTRUDER

    Takeaway

    conveyor

    Gravityrollers

    Inclinedconvey

    or

    CoolingConvey

    or

    DecliningConveyo

    r

    Skiver

    Weighing

    Conveyor

    ScrapMarker

    CementStation

    Extrusion Process

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    9/24

    51.3%

    22.5%

    16%

    7.8%

    54, 3%

    Types of defects in treads

    LOW WEIGHT

    HIGH WEIGHT

    LUMPS

    TORNEDGE

    OTHERS

    Treads produced-12207Treads rejected-1674

    Defect Data

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    10/24

    Defect Data (sample for 24.5.2011)

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    11/24

    Pareto Analysis

    FINDINGS

    More than 50% of the

    rejections are caused to

    low weight. High weight

    and lumps add up to

    almost 90% of therejections. In our analysis

    lump rejection is being

    considered because lump

    rejections are completely

    controllable up to 40%

    whereas weight rejections

    can be only be removed

    up to 20% or below.

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    12/24

    Low weight

    MAN MATERIAL

    MACHINE METHOD

    Feed break (M) Low Viscosity (M)

    Die setting not proper Low specific gravity (M)

    Low weight Running weight not properly set

    Line synchronization not proper Waiting for compound

    Mechanical/Electrical Operating skillsstoppage (M)

    Root Cause Analysis for Low Weight rejects

    (M) Major reasons

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    13/24

    Why-Why Analysis for Low weight rejects

    Why #6

    Why #5

    Why #4

    Why #3

    Why #2

    Why #1 Lowweight

    Lowviscosity

    Compound

    milled for along time atB.D. mill.

    Mill operatordid not keeptrack of time

    Operatornegligence

    Temperature

    at extruderheadincreased

    No watercirculation at

    extruderhead

    Water valveclosed

    Non-conformanc

    e ofprocedure

    Lowspecificgravity

    Compoundin

    g not OKfromBanbury

    Chemicalsnot mixed in

    properquantity

    Scaling error

    in autoloading

    Calibrationnot done.

    Lack of audit

    Electricalstoppage

    s

    Feedbreak

    Compound

    stuck at millguard of feedmill

    Materialaccumulated

    at top ofmillguard

    Operator filed

    to noticeaccumulation

    No line ofsight less

    visibility

    Compoundslipped frombite rollers

    Adequatedistance from

    bite rollersnot kept

    Bite-rollers

    notmaintained

    Audit notperformed

    Root Causes

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    14/24

    High weight

    MAN MATERIAL

    MACHINE METHOD

    Operating skills High viscosity variation (M)(Die setting)

    Line synchronization Improper breakdown ofnot proper compound at B.D. Mill (M)

    Wrong die tuning

    Root Cause Analysis for High Weight rejects

    (M) Major reasons

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    15/24

    Why-Why Analysis for High weight rejects

    Why #6

    Why #5

    Why #4

    Why #3

    Why #2

    Why #1 Highweight

    Improperbreakdown

    of compound

    Compoundmilled for alesser time

    Compoundurgently

    needed atfeed mill

    Feed millrunning shortof compoundat extruder.

    Shortage ofmaterial.Planningimproper.

    Highviscosity

    Compound

    fromBanbury was

    hard

    Impropermixing atBanbury

    Mixing cyclenot followedby operator

    SOP not inplace

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    16/24

    Lumps

    MAN MATERIAL

    MACHINE METHOD

    Absenteeism Lumpy Compound (M)

    Negligence (M) Viscosity variation (M)

    Temp/TCU Waiting for compound

    Line stoppage (M) Operating skills

    Root Cause Analysis for Lump rejects

    (M) Major reasons

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    17/24

    Why-Why Analysis for Lump rejects

    Why #6

    Why #5

    Why #4

    Why #3

    Why #2

    Why #1 Lumps

    Lumpycompound

    Lumpytreads mixedat Banbury

    Lumps notremovedduring

    segregation

    Improperdisposal oflumpy scrap

    Improperdisposal of

    lumpy treads

    Lumpytreads notrecorded

    Compoundgot lumpy infeed mill

    Compoundprocessedfor a long

    time

    Orbitconveyor notused in cap

    side

    Operator nottrained in orbit

    conveyorusage

    Lumps

    formed atBanbury

    mixer

    Mill tailingswaste added

    to mixer

    Mill tailingsformed frommill guides

    Housekeepingat mill guides

    not done

    Viscosityvariation

    LineStoppage

    Safety fromthe coolingtank

    Tread slippedfrom cooling

    tank todancing roller

    Less visibilityfor operator to

    see tread

    Process notstandardized

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    18/24

    Actions / Opportunities

    Ensure Ok compound loaded on B.D. mill free from lumps

    Root Cause - Operator negligence

    Censor installed at declining conveyor so that operator loads treadto roller on time

    Root Cause Less visibility for operator

    Automated entry of lumpy treads count by operator at cementingstation through push button

    Root Cause Lumpy treads not recorded

    Temp monitoring device at mill of Banbury to avoid excess heatingof compound

    Root Cause Lack of visibility in temp control

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    19/24

    Actions / Opportunities

    Implementation of Orbit conveyor at the cap & the base feed mills andtrain operator its function and usage.

    Root Cause Lumps formed due to overheating as operator is not trained on its usage

    Segregate lumps from lumpy treads before sending back to Banburymixer

    Root Cause Improper disposal of lumpy treads

    Scheduling of preventive maintenance at conveyor belt, skiver, motorto prevent untimely breakdown during running of batch

    Root Cause Non conformance to procedure(maintenance)

    Proper scheduling at Banbury to ensure there is enough compound. Ifnot operator should inform supervisor at the starting of batch

    Root Cause Shortage of material at B.D. mill

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    20/24

    Actions / Opportunities

    Censor installed at cap feed mill to indicate accumulation ofmaterial at cap feed mill guard

    Root Cause Less visibility for mill man

    TCU leakages should be monitored frequently by the shift

    supervisor. Root Cause Non-conformance to audits

    Operator counseling to make them aware and responsible towardsthe job they are doing & adhere to SOPs/specifications.

    Root Cause Standard procedures not followed

    Proper distance between the bite rollers should be maintained andits axis straightened so that rollers work properly.

    Root Cause Safety and performance audit not conducted by plant

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    21/24

    Cost Benefit Analysis

    Total no of treads rejected during 7 shifts =

    1658 * 18.6 * 3/7 * 30 = 396498.85 KG

    (No of rejects * Avg wt * No of shifts * No of days)

    Total cost involved for treating one KG of tread

    = Cost of Banbury + Cost of extruder

    = 1.30+0.39=1.69 Rs/kg

    Total cost of re-work per month: =396498.85 * 1.69 = Rs. 670, 083.06

    Cost of rejection in the previous state

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    22/24

    Cost Benefit Analysis

    Treads rejected/day (After changes) =369.34 Nos

    Treads rejected/month= 11080.4 Nos

    Total loss of tread in terms of weight for 1 month

    = 1080.4*18.60 (wt of 1 tread)=206,095.44 KG

    New cost involved for rework oftread/month=206,095.44*1.69= Rs. 348,301

    Therefore this project has potential tosave = Rs.670,083.06 348,301

    = 321,781.86 Rs/Month.

    The rejection achieved after implementing some of the changes was from 13.71 to 7.06 %

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    23/24

    Key Learnings

    Learned in detail about the steps/processes involved in tire manufacturingparticularly producing treads in 10*10 extruder machine.

    Learned about the quality parameters which are responsible for the rejectionof tire treads.

    Learned about the allocation of work, manpower, job scheduling & also

    learned that how manpower is managed & handled on the shop floor. Undertook step-by-step approach using TQM tools to address the problem.

    Practically saw the types of manufacturing waste being generated on theshop floor & how it impacts the productivity of the plant.

    Learned about the interdependencies between various processes for this

    project & how the impact of one process affects the output of anotherprocess.

  • 8/3/2019 The Apprentice_Abhrajit Sett_KJ SIMSR

    24/24

    Thank you