The Annual Audit Letter for Salford City Council City Council.pdftested revaluations made during the...
Transcript of The Annual Audit Letter for Salford City Council City Council.pdftested revaluations made during the...
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016
The Annual Audit Letter
for Salford City Council
Year ended 31 March 2016
24 October 2016
Cover page
Mike Thomas
Director
T 0161 214 6368
Tommy Rooney
Manager
T 0161 214 6359 E [email protected]
Daniel Watson
In Charge Auditor
T 0161 234 6344
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 2
Contents
Section Page
1. Executive summary 3
2. Audit of the accounts 5
3. Value for Money conclusion 9
4. Working with the Council 14
Appendices
A Reports issued and fees
B Recommendations
Contents
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 3
Executive summary
Overall review of
financial
statements
Purpose of this letter
Our Annual Audit Letter (Letter) summarises the key findings arising from the
work that we have carried out at Salford City Council (the Council) for the year
ended 31 March 2016.
This Letter is intended to provide a commentary on the results of our work to the
Council and its external stakeholders, and to highlight issues that we wish to draw
to the attention of the public. In preparing this letter, we have followed the
National Audit Office (NAO)'s Code of Audit Practice (the Code) and Auditor
Guidance Note (AGN) 07 – 'Auditor Reporting'.
We reported the detailed findings from our audit work to the Council's Audit and
Accounts Committee as those charged with governance in our Audit Findings
Report on 24 August 2016.
Our responsibilities
We have carried out our audit in accordance with the NAO's Code of Audit
Practice, which reflects the requirements of the Local Audit and Accountability
Act 2014 (the Act). Our key responsibilities are to:
• give an opinion on the Council's financial statements (section two)
• assess the Council's arrangements for securing economy, efficiency and
effectiveness in its use of resources (the value for money conclusion) (section
three).
In our audit of the Council's financial statements, we comply with International
Standards on Auditing (UK and Ireland) (ISAs) and other guidance issued by the
NAO.
Our work
Financial statements opinion
We gave an unqualified opinion on the Council's financial statements on 24 August
2016.
Value for money conclusion
We were satisfied that the Council put in place proper arrangements to ensure
economy, efficiency and effectiveness in its use of resources during the year ended
31 March 2016. We reflected this in our audit opinion on 24 August 2016.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 4
Overall review of
financial
statements
Whole of government accounts
We completed work on the Council's consolidation return following guidance
issued by the NAO and issued an unqualified report on 21 October 2016
Certificate
We certified that we had completed the audit of the accounts of Salford City
Council in accordance with the requirements of the Code on 21 October 2016.
Certification of grants
We also carry out work to certify the Council's Housing Benefit subsidy claim on
behalf of the Department for Work and Pensions. Our work on this claim is not
yet complete and will be finalised by 30 November 2016. We will report the results
of this work to the Audit and Accounts Committee in our Annual Certification
Letter.
Other work completed
Council Finance staff attended a workshop we provided in November 2015 on the
early closure of local authority accounts, and a workshop we provided jointly with
CIPFA in February 2016 covering changes to accounting standards and the Code
of Practice, and emerging issues and future developments.
Working with the Council
We would like to record our appreciation for the assistance and co-operation
provided to us during our audit by the Council's staff.
Grant Thornton UK LLP
October 2016
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 5
Audit of the accounts
Overall review of
financial
statements
Our audit approach
Materiality
In our audit of the Council's accounts, we use the concept of materiality to
determine the nature, timing and extent of our work, and in evaluating the results
of our work. We define materiality as the size of the misstatement in the financial
statements that would lead a reasonably knowledgeable person to change or
influence their economic decisions.
We determined materiality for our audit of the Council's accounts to be £14.89m,
which is 2% of the Council's gross revenue expenditure. We used this benchmark,
as in our view, users of the Council's accounts are most interested in how it has
spent the income it has raised from taxation and grants during the year.
We also identified the following items as sensitive items that were material by
nature rather than size for which any errors identified would be discussed with a
view to requesting amendment depending on their nature and individual
significance:
• cash and cash equivalents
• officers' remuneration, salary bandings and exit packages
• auditor remuneration
• related party transactions
• members' allowances
We set a lower threshold of £0.745m, above which we reported errors to the Audit
and Accounts Committee in our Audit Findings Report.
The scope of our audit
Our audit involves obtaining enough evidence about the amounts and
disclosures in the financial statements to give reasonable assurance that they are
free from material misstatement, whether caused by fraud or error.
This includes assessing whether:
• the Council's accounting policies are appropriate, have been consistently
applied and adequately disclosed;
• significant accounting estimates made by management are reasonable; and
• the overall presentation of the financial statements gives a true and fair view.
We also read the narrative report and annual governance statement to check
they are consistent with our understanding of the Council and with the accounts
on which we give our opinion.
We carry out our audit in line with ISAs (UK and Ireland) and the NAO Code
of Audit Practice. We believe the audit evidence we have obtained is sufficient
and appropriate to provide a basis for our opinion.
Our audit approach was based on a thorough understanding of the Council's
business and is risk based.
We identified key risks and set out overleaf the work we performed in response
to these risks and the results of this work.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 6
Audit of the accounts – Salford City Council
Overall review of
financial
statements
Risks identified in our audit plan How we responded to the risk
Management over-ride of controls
Under ISA (UK&I) 240 it is presumed that the risk of
management over-ride of controls is present in all
entities.
As part of our audit work we:
reviewed entity controls in relation to journal transactions
tested journal entries
reviewed accounting estimates, judgements and decisions made by management
reviewed unusual significant transactions
We did not identify any issues to report
Valuation of property, plant and equipment
The Council re-values its assets on a rolling basis over
a four year period. The Code requires that the Council
ensures that the carrying value at the balance sheet
date is not materially different from current value.
This represents a significant estimate by management
in the financial statements.
As part of our audit work we:
reviewed management's processes and assumptions for the calculation of the estimate
• held discussions with the Valuer about the basis on which the valuation is carried out and challenged key assumptions
• reviewed and challenged the information used by the Valuer to ensure it is robust and consistent with our
understanding
• reviewed the instructions issued to valuation experts and the scope of their work
• reviewed the competence, expertise and objectivity of the valuer used by management
• tested revaluations made during the year to ensure they were input correctly into the Council's asset register
• evaluated the assumptions made by management for those assets not revalued during the year and how
management has satisfied themselves that these are not materially different to current value.
We did not identify any issues to report
Valuation of pension fund net liability
The Council's pension fund asset and liability as
reflected in its balance sheet represent significant
estimates in the financial statements.
As part of our audit work we:
identified the controls put in place by management to ensure that the pension fund liability is not materially misstated
assessed whether these controls were implemented as expected and are sufficient to mitigate the risk of material
misstatement
reviewed the competence, expertise and objectivity of the actuary who carried out your pension fund valuation and
gained an understanding of the basis on which the valuation is carried out
completed procedures to confirm the reasonableness of the actuarial assumptions made
reviewed the consistency of the pension fund asset and liability and disclosures in notes to the financial statements
with the actuarial report from your actuary.
We did not identify any issues to report
These are the risks which had the greatest impact on our overall strategy and where we focused more of our work.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 7
Audit of the accounts – Salford City Council (continued)
Overall review of
financial
statements
Risks identified in our audit plan How we responded to the risk
Valuation of surplus assets and investment property
The CIPFA Code of Practice implemented International
Financial Reporting Standard (IFRS) 13 for the 2015/16 financial
statements. The Council is required to include surplus assets
within property, plant and equipment in its financial statements
at fair value, as defined by IFRS13.
The basis on which fair value is defined for investment property
is also different to that used in previous years.
This represents a significant change in the basis for estimation
of these balances in the financial statements.
There are also extensive disclosure requirements under IFRS
13 which the Council needs to comply with.
As part of our audit work we:
reviewed management's processes and assumptions for the calculation of the estimate
reviewed the competence, expertise and objectivity of the management experts used
reviewed the instructions issued to valuation experts and the scope of their work
discussed with the valuer the basis on which the valuation is carried out and challenged the key assumptions
reviewed and challenged the information used by the valuer to ensure it is robust and consistent with our
understanding
tested revaluations made during the year to ensure they were input correctly into the Council's asset register
reviewed the disclosures made by the Council in its financial statements to ensure they are in accordance
with the requirements of the CIPFA Code of Practice and IFRS 13.
We agreed some additional disclosures in the accounts for IFRS 13 in respect of financial instruments
but did not identify any other issues to report.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 8
Audit of the accounts
Overall review of
financial
statements
Audit opinion
We gave an unqualified opinion on the Council's accounts on 24 August 2016, in
advance of the 30 September 2016 national deadline.
The Council made the accounts available for audit in line with the agreed
timetable, and provided a good set of working papers to support them, although
some working papers were not received at the start of the audit. The finance team
responded promptly and efficiently to our queries during the course of the audit.
We will continue to work with Finance staff to identify further improvements to
the efficiency of the accounts production and audit processes to enable the earlier
deadlines for 2017/18 to be met, which will require councils to bring forward the
approval and audit of financial statements to 31 May and 31 July respectively.
The draft financial statements recorded total comprehensive income and
expenditure of £(107.239m). This remained unchanged following completion of
our audit, although various amendments were made following our audit in respect
of disclosure and classification changes. These related mainly to disclosures on the
Council's Property, Plant and Equipment assets and Private Finance Initiative
(PFI) schemes, but had no impact on the Council's reported financial position for
2015/16.
Issues arising from the audit of the accounts
We reported the key issues from our audit of the accounts of the Council to the
Council's Audit and Accounts Committee on 24 August 2016.
As a result of our work, we identified some areas for further improvement and
agreed with management recommendations to address them. These are listed at
Appendix B.
Annual Governance Statement and Narrative Report
We are also required to review the Council's Annual Governance Statement and
Narrative Report. It published them on its website with the draft accounts in
line with the national deadlines.
Both documents were prepared in line with the relevant guidance and were
consistent with the supporting evidence provided by the Council and with our
knowledge of the Council. We agreed a small number of amendments and
additions to both documents and have made a recommendation relating to the
narrative report (see Appendix B).
Whole of Government Accounts (WGA)
We carried out work on the Council's consolidation schedule in line with
instructions provided by the NAO . We issued a group assurance certificate
which did not identify any issues for the group auditor to consider.
Other statutory duties
We also have additional powers and duties under the Act, including powers to
issue a public interest report, make written recommendations, apply to the
Court for a declaration that an item of account is contrary to law, and to give
electors the opportunity to raise questions about the Council's accounts and to
raise objections received in relation to the accounts.
We did not identify any issues that required us to apply our statutory powers
and duties under the Act. We did not receive any objections from electors to
the 2015-16 accounts. There were no circumstances that required us to issue a
public interest report in respect of our 2015/16 audit.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 9
Value for Money conclusion
Overall review of
financial
statements
Background
We carried out our review in accordance with the NAO Code of Audit Practice
(the Code), following the guidance issued by the NAO in November 2015 which
specified the criterion for auditors to evaluate:
In all significant respects, the audited body takes properly informed decisions and deploys resources
to achieve planned and sustainable outcomes for taxpayers and local people.
Key findings
Our first step in carrying out our work was to perform a risk assessment and
identify the key risks.
The key risks we identified and the work we performed is set out in table 2
overleaf.
We concluded that:
• The Council had appropriate arrangements in place for monitoring and
reporting the revenue and capital position, managing financial pressures and
identifying and delivering savings measures. There were also effective
arrangements for setting the annual budget and forecasting the medium term
financial strategy. The Council will need to continue to monitor closely and
manage financial risks during 2016/17 if it is to again achieve its financial
targets.
• The Council worked effectively with its partners to implement its two key
projects for integrated care, which were the expansion of the £116m Older
People's pooled budget to a wider pooled budget covering all adults totalling
approximately £236m and the development of an Integrated Care Organisation
(ICO) for the integrated provision of adult social care, community and hospital
mental and physical health services. Associated risks were identified and action
plans put in place to address them and progress and proposals were reported to
the City Mayor and Cabinet.
Overall VfM conclusion
We are satisfied that in all significant respects the Council put in place proper
arrangements to secure economy, efficiency and effectiveness in its use of
resources for the year ending 31 March 2016.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 10
Value for Money
Overall review of
financial
statements
Risk identified Work carried out Findings and conclusions
Financial position and future year
savings
The Council is facing a continued period of
austerity. Having made over £118m of
budget savings in the period 2010/11 to
2014/15, the Council has a savings target
of £31m in 2015/16. The current updated
medium term financial strategy forecasts
savings required in 2016/17 of £21.8m and
funding gaps of £14.8m in 2017/18,
£14.8m in 2018/19 and £12.1m in
2019/20.
This requires the redesign and
transformation of services to help deliver
the future savings required.
We reviewed:
• the reasonableness of assumptions in the
updated MTFS
• the Council's arrangements for identifying,
agreeing and delivering savings plans including
implementation of the transformation programme
• financial and budget reporting to Members
• the outturn position for 2015/16 and the budget
plan for 2016/17
We also met with key officers to discuss key
strategic challenges and the Council's proposed
response.
The revenue and capital position are reported to the Corporate Management
Team (CMT), the City Mayor's briefing and then to the Overview and Scrutiny
Board (OS&B). Reports were presented to O&SB in September and December
2015 and February and July 2016, providing the current position, forecasts to
year end, details of risks and pressures in service groups and an assessment of
the risks to the achievement of the savings target.
A forecast adverse variance at year end of £2.652m was reported to O&SB in
December 2015 but improved to a forecast adverse variance of £0.872m in
February 2016. The Council achieved a final outturn position at 31 March 2016
of £1.311m favourable variance against the £207.739m annual budget. All
service groups either underspent or met their service budget.
For 2015/16, the council set a minimum level of general fund reserves of £8.4m,
a desirable target of £14.6m and forecast a balance of £13.6m at 31 March
2016, the same as the previous year. At 31 March 2016 the actual general fund
reserves balance was £14.37m, £0.8m more than the original budget forecast,
but still below the desirable level.
The final capital spend was £78.483m against a final capital programme of
£95.919m. We understand most of the £17.436m underspend will be slippage
into the 2016/17 capital programme subject to review and approval by CMT and
O&SB.
The 2016/17 budget and medium term financial strategy to 2019/20 was
prepared by the Director of Finance and Corporate Business in consultation with
Strategic Directors and Heads of Service. It was considered by Cabinet in
February 2016 before being presented to and approved by full Council on 24
February 2016. This included details of the planned measures to deliver the
£21.8m new transformational savings, efficiencies and additional income
required to balance the 2016/17 budget. The 2016/17 budget includes
appropriate assumptions for key income and expenditure amounts.
Table 2: Value for money risks
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 11
Value for Money (continued)
Overall review of
financial
statements
Risk identified Work carried out Findings and conclusions
Savings measures were developed by the City Mayor, Deputy Mayor, Directors and Executive Lead
Members working with the Budget Strategy Group. The Council has also encouraged engagement
by staff and the public on its savings proposals and service reform and transformation plans through
the weekly 'City Director's update' briefing. This outlines current issues, developments and
challenges for the Council. Staff were asked in January 2016 to comment on the savings proposals
and regular 'Shaping Our City Staff Bulletin' emails on the progress made in developing new digital
customer business models have been issued, inviting staff comments and ideas and providing
details of staff briefing sessions. The Council's 'Shaping our City' public website also provides
further information on the transformation programme and invited the public to get involved.
The Council's savings measures and transformation programme are subject to appropriate review
and approval, with business cases proposing changes and efficiencies in services being taken to
Cabinet for approval. This included the Customer Transformation Service Design and Business
Case which was approved by Cabinet in December 2015 and the Customer Strategy which was
approved by Cabinet in June 2016. Through this transformation work the Council aims to change
the way customers interact with the Council through its 'Customer Business Model' programme to
enable more online interaction by the public with the Council. The Council aims to deliver £7m of
savings over the life of the project.
Delivery of savings and the reform and transformation of services are both identified as significant
risks on the Council's Strategic Risk Register. Arrangements are in place to monitor and manage
these risks through monthly monitoring against savings targets and budgets. Savings delivery and
risks are monitored via a 'RAG' (Red, Amber, Green) rating tracker. The current savings tracker
covers savings measures totalling £24m with current ratings of:
• £9.7m Green: low risk - saving achieved or low likelihood of not being achieved
• £10.4m Amber: medium risk - saving assumed as achieved in year end forecast
• £3.9m Red: high risk - the saving is not assumed to be achieved in year end forecast
As at the end of June 2016, the Council's projected position for the year ending 31 March 2017 is an
adverse variance of £3.849m. and an adverse variance of £0.295m on the Dedicated
Schools Grant (DSG) budget. The Council has a track record of achieving savings targets and
identifying alternative measures and mitigating actions where planned savings measures are not
delivering the target savings in order to deliver within budget.
On that basis we concluded that the risk was sufficiently mitigated and the Council has
proper arrangements in place the meet its responsibilities.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 12
Value for Money (continued)
Overall review of
financial
statements
Risk identified Work carried out Findings and conclusions
Health & Social Care Integration
The Council is seeking to deliver wide
ranging changes and greater integration to
ensure the financial sustainability of adult
health and social care services. The
Council aims to expand its Integrated Care
Organisation and pooled budget
arrangements for Older People to cover
health and social care budgets for all
adults. Working with partners from
different organisations and service areas
with potentially conflicting priorities, the
project is complex and high profile.
We reviewed the project management and risk
assurance frameworks established by the
Council to establish how it is identifying,
managing and monitoring these risks.
The Council has worked with its partners to implement two key projects for integrated
care. The first is the expansion of the £116m Older People's pooled budget to a wider
pooled budget covering all adults totalling approximately £236m. The second is the
development of an Integrated Care Organisation (ICO) for the integrated provision of
adult social care, community and hospital mental and physical health services.
Both projects are recognised on the Council's Strategic Risk Register as 'Actively
Managed Risks'. The register provides details of the actions in place to manage and
mitigate the risks. This includes appropriate partnership arrangements to expand the
Integrated Care Programme for Older People to cover the whole adult population of
Salford, and to put in place the required agreements to establish the ICO and the
required commissioning and governance arrangements.
Sufficient arrangements are in place to consult and communicate key decisions on
partnership working within the Council. The City Mayor and Cabinet have received
reports on progress and the proposed agreements and governance arrangements put
in place for the wider pooled budget and the ICO.
The Council and Salford Clinical Commissioning Group (CCG) have operated a
pooled budget for health and social care services for Older People since April 2014.
In March 2016 the Council and the CCG agreed that the pooled budget would be
extended from April 2016 to include health and social care services for all adults. A 5
year Service and Financial Plan is being developed for the wider pooled budget
based on the original one for Older People services and a risk share agreement is in
place.
The Salford Alliance Partnership comprises of the Council, the CCG, Salford Royal
Foundation Trust (SRFT) and Greater Manchester West Mental Health Foundation
Trust. It is supported by an Alliance Agreement between the partners, who have
worked together to establish the ICO. The Alliance Board met regularly during the
year with representatives from all the partners. Discussions included finance and
activity, performance metrics, the risk register and the development of the ICO.
The full business case for the ICO was approved by the Council and its health
partners, which is evidence that the partners have been able to work together to
agree detailed plans for the organisation.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 13
Value for Money (continued)
Overall review of
financial
statements
Risk identified Work carried out Findings and conclusions
The original planned commencement date of 1 April 2016 was deferred to allow
time for due diligence to be completed on both sides. Subsequently 400 Adult
Social Care staff transferred from the Council to SRFT and the ICO was
launched on 1 July 2016, with SRFT as the prime provider of adult social care.
The Alliance Agreement, including the Alliance Board, have been disestablished
and revised governance arrangements put in place for the integrated care
system infrastructure. The Salford Health and Wellbeing Board oversees the
integrated care system and an Integrated Adult Health and Care Commissioning
Joint Committee has been established to oversee the pooled budget
arrangements between the Council and the CCG. An Advisory Board for
Integrated Care has also been established to advise on the development of
service strategy and oversee the Integrated Care Vanguard Programme.
In June 2016 the Council's internal auditors reported on their joint review with
the CCG's internal audit providers of the integrated care service governance
arrangements for commissioning and concluded they were fit for purpose.
The Council will need to ensure it maintains sufficient arrangements with the
CCG for commissioning services from the ICO and monitoring its performance,
managing the associated risks on a longer term basis for the benefit of its own
governance as well as reassuring external stakeholders.
On that basis we concluded that the risk was sufficiently mitigated and the
Council has proper arrangements in place for managing arrangements
with third parties effectively to deliver its strategic priorities.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 14
Working with the Council
Overall review of
financial
statements
Our work with you in 2015/16
We are really pleased to have worked with you over the past year. We
have established a positive and constructive relationship. Together we
have delivered some great outcomes.
An efficient audit – the accounts audit was substantially complete by the
end of July and we issued our audit opinion on 24 August 2016, following
the approval of the accounts that day by the Audit and Accounts
Committee. This was over a month before the deadline of 30 September
and in line with the timescale we agreed with you. Our audit team are
knowledgeable and experienced in your financial accounts and systems.
Our relationship with your team provides you with a financial statements
audit that continues to finish ahead of schedule releasing your finance
team for other important work.
Understanding your operational health – through the value for money
conclusion we provided you with assurance on your operational
effectiveness.
Sharing our insight – we provided regular updates to the Audit and
Accounts Committee covering best practice. Areas we covered included
Innovation in public financial management and Knowing the Ropes –
Audit Committee Effectiveness Review and Reforging local government.
Thought leadership – We have shared with you our publication on
Building a successful joint venture and will continue to support you as you
consider greater use of alternative delivery models for your services.
Providing training – we provided workshops on financial accounts issues
and early closure. The courses were attended by members of your team who
are responsible for the production of the annual financial statement of
accounts. We have also provided briefing sessions for the Audit and
Accounts Committee on the role of external audit.
Providing information – We provided you with information on CFO
insights, our online analysis tool providing you with access to insight on the
financial performance, socio-economy context and service outcomes of
councils across the country.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 15
Working with the Council
Overall review of
financial
statements
Working with you in 2016/17
Highways Network Asset
The Code of Practice on Local Authority Accounting (the Code) requires
authorities to account for Highways Network Asset (HNA) at depreciated
replacement cost (DRC) from 1 April 2016. The Code sets out the key
principles but also requires compliance with the requirements of the
recently published Code of Practice on the Highways Network Asset (the
HNA Code), which defines the assets or components that will comprise the
HNA. This includes roads, footways, structures such as bridges, street
lighting, street furniture and associated land. These assets should always
have been recognised within Infrastructure Assets.
The Code includes transitional arrangements for the change in asset
classification and the basis of measurement from depreciated historic cost
(DHC) to DRC under which these assets will be separated from other
infrastructure assets, which will continue to be measured at DHC.
This is expected to have a significant impact on the Council's 2016/17
accounts, both in values and levels of disclosure, and may require
considerable work to establish the opening inventory and condition of the
HNA as at 1 April 2016.
Under the current basis of accounting values will only have been recorded
against individual assets or components acquired after the inception of
capital accounting for infrastructure assets by local authorities. Authorities
may therefore have to develop new accounting records to support the
change in classification and valuation of the HNA.
The nature of these changes means that Finance officers will need to work closely
with colleagues in the highways department and potentially also to engage other
specialists to support this work.
Some of the calculations are likely to be complex and will involve the use of
external models, a combination of national and locally generated rates and a
number of significant estimates and assumptions.
We have been working with the Council on the accounting, financial reporting
and audit assurance implications arising from these changes. We have issued two
Client Briefings which we have shared with Finance staff. We will issue further
briefings during the coming year to update the Council on key developments and
emerging issues.
This accounting development is likely to be a significant risk for our 2016/17
audit, so we have already had some preliminary discussions with the Council to
assess the progress it is making in this respect. We confirmed that Finance staff
have had on-going discussions with Urban Vision, who maintain the inventory of
Infrastructure Assets, to identify those assets and components that will comprise
the HNA. Work is on-going by Urban Vision and Finance staff to ensure the
required data is input into the modelling tools that will produce the required
balances for the 2016/17 accounts.
We will continue to liaise closely with the senior finance team during 2016/17 on
this important accounting development, with timely feedback on any emerging
issues.
The audit risks associated with this new development and the work we plan to
carry out to address them will be reflected in our 2016/17 audit plan.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 16
Working with the Council
Overall review of
financial
statements
.
We will also continue to work with you and support you over the next financial
year in other areas.
Locally our focus will be on:
• An efficient audit – continuing to deliver an efficient audit and continuing our
work with the Finance team to ensure the achievement of the earlier accounts
deadline in 2017/18
• Improved financial processes – we will focus our work on the identification
and delivery of actions and measures to maintain revenue spend within the
approved budget, including planned savings measures
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 17
Appendix A: Reports issued and fees
Fees
Planned
£
Actual fees
£
2014/15 fees
£
Statutory audit of the Council 137,030 137,030 182,706
Housing Benefit Grant Certification 20,993 To be
confirmed*
24,870
Total fees (excluding VAT) 158,023 137,030 207,576
We confirm below our final fees charged for the audit and provision of non-audit services
Reports issued
Report Date issued
Audit Plan March 2016
Audit Findings Report August 2016
Annual Audit Letter October 2016
Fees for other services
Service Fees £
Audit related services:
Western Gateway Infrastructure Scheme at Port Salford – Regional Growth
Fund:
• Return 16/1/14-31/3/15
• Additional outputs return 16/1/14-31/3/15
Teachers' Pensions Return 2014/15
Pooling of housing capital receipts return 2014/15
2011-15 Programme Agreement for Affordable Homes grant schemes
Total
5,000
2,500
4,200
2,700
3,000
17,400
Non-audit services Nil
*Work on the Housing Benefit Grant Certification is in progress with a deadline of
30 November 2016 and so the actual fee will be confirmed when this work is
complete.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 18
Appendix B: Recommendations
Rec
No. Issue and recommendation Priority Management response
Implementation date &
responsibility
1. A number of working papers were not received at
the commencement of the audit.
Recommendation: Ensure all supporting working
papers are complete and available at the start of
the audit.
High Working paper check to be included in final accounts
timetable.
November 2016
2. Code paragraph 3.1.5.3 b) requires that the
Narrative Report should "provide an analysis of
the financial and non-financial performance
indicators as relevant to the performance of the
authority". Whilst the Council's core performance
measures are listed in the Narrative Report, no
information is provided on actual performance
against them during the year.
Recommendation: Provide details of actual
performance against the Council's core
performance measures listed in the Narrative
Report.
Medium Performance information is routinely provided on
thematic reports to Scrutiny at their request on an ad
hoc basis. We are currently discussing a performance
framework with the City Mayor including how we make
the information more open and transparently available.
January 2017
Assistant Director Strategy
Change
3. Amendments were made for errors identified in
PFI amounts disclosed in note 43 'payment
periods table'. These were due to errors in
amounts recorded in the supporting working
papers. This indicated a lack of robust
management review of the supporting working
papers and calculated amounts.
Recommendation: Ensure sufficient
management review and checks of material PFI
calculations and supporting working papers.
Medium Validation check formula to be added to working
papers to ensure consolidated costs included in note
43 match individual PFI / LIFT working papers.
Formula errors included in original note 43
consolidation working papers that led to
misstatement of future liabilities have already been
corrected.
Additional management review time will be
incorporated in to final accounts timetable to ensure
accuracy of working paper
Formula errors already corrected.
Validation formula to be added
August 2016
Review time to be included in
16/17 accounts timetable.
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016 19
Appendix B: Recommendations (continued)
Rec
No. Issue and recommendation Priority Management response
Implementation date &
responsibility
4. We identified that the amounts of members'
allowances published on the Council's website did
not reconcile to note 35 in the accounts. The
website amounts were amended to reconcile to
the accounts.
Recommendation: Reconcile members'
allowances details to the amounts disclosed in the
accounts before they are published on the
Council's website. published on the website.
High Members' allowances details were reconciled to the
amounts disclosed in the accounts. The initial version
provided to members services was not the version
uploaded by IT services to the website. In future once
the amounts have been through the review process
with members the finance team will arrange for the
file to be uploaded to the website.
July 2017
© 2016 Grant Thornton UK LLP | The Annual Audit Letter for Salford City Council | October 2016
Back page