The Analytical Design Planning Technique (ADePT)
-
Upload
paulwaskett -
Category
Business
-
view
1.668 -
download
10
description
Transcript of The Analytical Design Planning Technique (ADePT)
© Adept Management Ltd, 2009
An overview of
Planning & controlling design & engineering projects
The TechnoCentrePuma Way
Coventry CV1 2TWUnited Kingdom
Tel: +44(0)24 7623 6929Fax: +44(0)24 7623 6930
E-mail: [email protected]: www.adeptmanagement.com
© Adept Management Ltd, 2009
Adept Management
ADePTServices
Design Management
ADePT DesignSoftware Suite
Integrated Design Planning
Process Control
Design Team Performance Reporting
ADePT Design Builder
ADePT Design Manager
Software Training
Design & Bid Management
Interim Design Managers
Strategic Planning & Monitoring
Process & Procedure Development
© Adept Management Ltd, 2009
Characteristics of Design
o Iterative
o Driven by information
o Highly complex
o Not well understood
o Broken into sub-problems
o Involving many people
o Undertaken in stages
© Adept Management Ltd, 2009
Poorly Managed Engineering - The Effect
o Fact – design / engineering projects overspend
• 35% of design commissions overspend
o Fact - design / engineering projects over-run
• 42% of design commissions are late
o Severe knock on effects in construction
• 52% of construction projects overspend
• 42% of construction work is late
2008 Construction Performance
Source: Office for National Statistics’ Construction Statistics Annual, 2008
© Adept Management Ltd, 2009
Overview of the methodology
© Adept Management Ltd, 2009
Current & Recent Implementations of ADePT
© Adept Management Ltd, 2009
ADePT - Benefits Identified
o Identification and removal of “turbulence”
o Greater certainty of design co-ordination
o Ability to better prioritise design work
o Focus on task completion
o Effective integration of sub-contractor design
o Better change management
o Improved team collaboration
o Self-policing design team
o Design fee validation
© Adept Management Ltd, 2009
Generating an Integrated Design Plan
© Adept Management Ltd, 2009
Overview of the methodology
© Adept Management Ltd, 2009
A Typical Design Processes
© Adept Management Ltd, 2009
A Typical Design Processes
© Adept Management Ltd, 2009
A Typical Design Processes
Deliverable
Deliverable
Deliverable.
Deliverable
DeliverableDeliverable
External Constraints
External Constraints
External Constraints
External Constraints
External Constraints
© Adept Management Ltd, 2009
Taking a Hierarchical View
© Adept Management Ltd, 2009
Taking a Hierarchical View
© Adept Management Ltd, 2009
Taking a Hierarchical View
© Adept Management Ltd, 2009
Information exchanges
© Adept Management Ltd, 2009
Information exchanges
Activity properties
© Adept Management Ltd, 2009
Information exchanges
Activity properties
Information requirements
Information outputs
© Adept Management Ltd, 2009
Information exchanges
Activity properties
Information requirements
Information outputs
Predecessor activities
Successor activities
© Adept Management Ltd, 2009
Setting up a matrix of the design process
1. List design activities in the matrix rows in any arbitrary order, and repeat the list across the columns of the matrix.
© Adept Management Ltd, 2009
Representing dependencies
2. Mark the matrix to indicate where the activity in the row depends on the activity in the column (e.g. requires information produced by, or requires a decision made from, the activity in the column).
3. Classify the dependencies the show the strength of the requirement: A = vital (should have); B = important (would like to have); or C = nice to have.
© Adept Management Ltd, 2009
Identifying design assumptionsD
esig
n p
roce
ss s
equ
ence
4. Assume the activities are to be undertaken in the order shown and identify any assumptions to be made. For example: activity 3 depends on activities 1, 2, 4 & 13. In the order shown activities 1 & 2 have been undertaken but 4 & 13 have not. So, to undertake activity 3 assumptions about the outputs from 4 & 13 must be made.
© Adept Management Ltd, 2009
Identifying iteration in the design process
Dependency classificationA = vital; B = important; C = nice to have
5. Identify all assumptions and scale of iteration in the design process. For example: activity 3 can only be undertaken if an assumption is made about the output from activity 13 and activity 13 itself requires assumptions to be made about the outputs from 15, 16 & 19. So, only when activity 19 has been undertaken can all assumptions be checked and any rework be undertaken. Therefore all activities from 3 to 19 are in an iterative rework loop.
© Adept Management Ltd, 2009
Optimizing the design sequence
6. Optimize the sequence of the activities to minimize the number of assumptions which need to be made and ensure that assumptions which cannot be made with a high level of confidence (classified A & B) are included within iterative rework loops whilst assumptions which can be made with confidence (C) are not.
© Adept Management Ltd, 2009
Breaking down iterative rework loops
7. If necessary (i.e. if the scale of iteration is greater than can be managed in the time available) identify assumptions which can reduce the scale of iteration further if made in such a way that the designers have confidence in them e.g. by over-estimating structural loadings or fixing a typical interface detail.
© Adept Management Ltd, 2009
Re-optimizing the design sequence
8. Re-optimize the sequence of the activities and record any new assumptions which are now not included in iterative rework loops.
© Adept Management Ltd, 2009
Detailed Locker Room Co-ordination
Envelope / Structure Interface
Ceiling Voids & RCP Co-ordination
Sub-structure Co-ordination
In practice: clusters represent systems
© Adept Management Ltd, 2009
A view of all clusters / systems
© Adept Management Ltd, 2009
Create the Programme
© Adept Management Ltd, 2009
Co-ordination loops identified in ADePT and shown in the
design programme
© Adept Management Ltd, 2009
-100 -80 -60 -40 -20 0 20 40 60 80 100Procurement Packages Target Tender
Date
Bicycle Enclosures 13/07/2009Vehicle Barriers 13/07/2009Soft Landscaping 19/01/2009Internal Signage 06/04/2009Floor Screed 09/02/2009External Signage 23/03/2009Decorations 06/04/2009External Render 05/01/2009Floor & Wall Tiling 23/03/2009Soft Flooring 23/03/2009Lifts 09/02/2009Internal Glazed Screening 10/11/2008FF&E inc. White Goods 02/03/2009Catering / Kitchen Equipment 15/12/2008Small Kitchen Fitout 16/02/2009Fixed Furniture inc. Reception Desk 03/11/2008Security Fencing 06/10/2008Floor Painting / Epoxy Flooring 19/01/2009Hard Landscaping 04/08/2008Internal Joinery 15/12/2008Plumberwork / Sanitary / Toilet Fitout 17/10/2008BWIC 24/11/2008Toilet & Kitchen Pods 17/10/2008Internal Doors & Ironmongery 17/11/2008Roof Mansafe 18/08/2008Brick & Blockwork inc. Windposts 28/07/2008RainWater System 11/08/2008Dry Lining / Plasterboard / Fire Stopping 25/08/2008Flat Roof Coverings 23/06/2008Raised Flooring 04/08/2008Roof Cladding / Finishes 26/05/2008Roller Shutter Doors 02/06/2008Suspended Ceilings 22/09/2008Sports Pitches 07/04/2008Architectural & General Metalwork 18/08/2008Sliding / Folding Partitions 10/11/2008Curtain Walling 28/04/2008Insitu Concrete Frames 30/06/2008External Windows / Doors / Glazing 19/05/2008M&E Building Services 11/02/2008Retaining walls / Structures 05/11/2007Precast Cladding 17/03/2008Site enabling / Ground works 05/11/2007Drainage SW / FW 02/11/2007Substructures inc. Ground Slabs 14/04/2008Structural Steelwork / Decking / Purlings 31/03/2008Precast Concrete: Slabs, Stairs, Column 28/04/2008External Crib Walling 05/11/2007External Services 21/10/2007External CIS Pit & Ducting 02/11/2007
Variance: construction vs. design dates
© Adept Management Ltd, 2009
Imposing Constraints
© Adept Management Ltd, 2009
Understanding the impact
Impact understood and a managed decision can be made to resolve
this issue
© Adept Management Ltd, 2009
-100 -80 -60 -40 -20 0 20 40 60 80 100 -100 -80 -60 -40 -20 0 20Procurement Packages Target Tender
Date
Bicycle Enclosures 13/07/2009Vehicle Barriers 13/07/2009Soft Landscaping 19/01/2009Internal Signage 06/04/2009Floor Screed 09/02/2009External Signage 23/03/2009Decorations 06/04/2009External Render 05/01/2009Floor & Wall Tiling 23/03/2009Soft Flooring 23/03/2009Lifts 09/02/2009Internal Glazed Screening 10/11/2008FF&E inc. White Goods 02/03/2009Catering / Kitchen Equipment 15/12/2008Small Kitchen Fitout 16/02/2009Fixed Furniture inc. Reception Desk 03/11/2008Security Fencing 06/10/2008Floor Painting / Epoxy Flooring 19/01/2009Hard Landscaping 04/08/2008Internal Joinery 15/12/2008Plumberwork / Sanitary / Toilet Fitout 17/10/2008BWIC 24/11/2008Toilet & Kitchen Pods 17/10/2008Internal Doors & Ironmongery 17/11/2008Roof Mansafe 18/08/2008Brick & Blockwork inc. Windposts 28/07/2008RainWater System 11/08/2008Dry Lining / Plasterboard / Fire Stopping 25/08/2008Flat Roof Coverings 23/06/2008Raised Flooring 04/08/2008Roof Cladding / Finishes 26/05/2008Roller Shutter Doors 02/06/2008Suspended Ceilings 22/09/2008Sports Pitches 07/04/2008Architectural & General Metalwork 18/08/2008Sliding / Folding Partitions 10/11/2008Curtain Walling 28/04/2008Insitu Concrete Frames 30/06/2008External Windows / Doors / Glazing 19/05/2008M&E Building Services 11/02/2008Retaining walls / Structures 05/11/2007Precast Cladding 17/03/2008Site enabling / Ground works 05/11/2007Drainage SW / FW 02/11/2007Substructures inc. Ground Slabs 14/04/2008Structural Steelwork / Decking / Purlings 31/03/2008Precast Concrete: Slabs, Stairs, Column 28/04/2008External Crib Walling 05/11/2007External Services 21/10/2007External CIS Pit & Ducting 02/11/2007
Result: aligned construction & design dates
© Adept Management Ltd, 2009
Key decisions required to integrate design & procurement
© Adept Management Ltd, 2009
Programme for one design discipline
© Adept Management Ltd, 2009
Programme for one project stage
© Adept Management Ltd, 2009
Controlling a Design Project
© Adept Management Ltd, 2009
Overview of the methodology
© Adept Management Ltd, 2009
Select tasks to add to the work plan for this period0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Task Priorities
Due to be completed
Due to be progressed
Current Date
End of Focus Period
Late
Focus Period
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
End of Look-Ahead
Period
Due to be completed in the next period
Due to be progressed in the next period
Look-Ahead Period
Task Priorities
Due to be completed
Due to be progressed
Current Date
End of Focus Period
Late
Focus Period
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Select tasks to add to the work plan for this period
Due to be progressed
Due to be completed
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Select tasks to add to the work plan for this period
Due to be progressed
Due to be completed in the next period
Due to be completed
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Publish the work plan to the design team0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Output for Designers to Complete0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Manage any constraints identified by the team0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Validate the progress given by the design team0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Write progress back to the design programme so that it can be rescheduled 0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Workflow process in practice
1. Generate Workplan
2. Publish Workplan to design team
3. Update Workplan with
team’s progress & constraints
4. Update programme &
archive Workplan
Reschedule programme
Star
t of
Foc
us p
erio
dEn
d of
Foc
us p
erio
d
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Update the programme and report performance 0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Understand and report trends0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Report overall progress:activities, information or documents
• Activities completed• Information produced• Documentation issued
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Overall Reporting
o What did we plan to achieve?o What did we complete?o What did we fail?o Why did we fail?o Fix problem and re-plan!
o What do we need to start / complete the activity in the future?
o What could stop us?
o How can we mitigate the risks?
o Ensure that we plan to deliver?
Looking Back
Looking Forward
0%
10%20%
30%40%50%
60%
70%80%
Aug Sep Oct Nov Dec
% P
lan
Com
plet
e
© Adept Management Ltd, 2009
Managing change (emerging need for re-design)
© Adept Management Ltd, 2009
Understanding the impact
Impact understood and an evidence-based decision made to resolve this by all parties
© Adept Management Ltd, 2009
An overview of
Planning & controlling design & engineering projects
The TechnoCentrePuma Way
Coventry CV1 2TWUnited Kingdom
Tel: +44(0)24 7623 6929Fax: +44(0)24 7623 6930
E-mail: [email protected]: www.adeptmanagement.com