Thanet Offshore Wind Farm - uni-hamburg.de · 2012. 11. 13. · Thanet History • Crown Estates...
Transcript of Thanet Offshore Wind Farm - uni-hamburg.de · 2012. 11. 13. · Thanet History • Crown Estates...
www.gl-nobledenton.com Applied Intelligence
Thanet Offshore Wind Farm
Thanet History
• Crown Estates Round 2
� 100 x 3MW WTGs to provide 300MW
� 33kV Array to Substation – 132kV to Shore
� Two Export Cables to Richborough Power Station
• July 2005
� GL commenced engineering for Warwick Energy
• September 2007
� CRC acquired TOW
• November 2008
� Vattenfall Wind Power acquired TOW
11/05/2010 2
Thanet Location
11/05/2010 3
Challenge
Financial Closure
through
Project Execution
to
Project Completion
11/05/2010 4
11/05/2010 5
Thanet Offshore Wind Farm
Vattenfall Wind Power - Client
- Principal Contractor
GL Noble Denton - Project Management Services
- CDM Coordinator
- Marine Warranty Surveyor
- Foundations Installation
Management
CDM 2007
• Construction Phase Plan (CPP)
• CPP Supporting Procedures
• Principal Contractor
• CDM Coordinator
• Procedures and Risk Assessments
• Authority to Commence Work
11/05/2010 6
Contract Status
• Form of Contract – e.g. Lump Sum
• HSE
• Document Control
• Planning
• Cost Control
• Interfaces
• Risk Management
• Package management
• QA / QC
11/05/2010 7
Level 1 Schedule
11/05/2010 8
Project Organogram
11/05/2010 9
Steering Group / SponsorTBA
Project Director
Ole Bigum Nielsen
Project Engineer
Gordon Clark
Commercial Manager
Chris Hughes-Rees
Construction Manager
Ray Guy
Cost / Contracts
Engineer
Peter Watson
Legal
VAB / ND Consultants
Insurance
MARSH Brokers
Project Support
Sarah Eastmond
Quality
Steve Mason /
Peter McGrath
Programme
Interfaces
Naval Sondhi/
Andy Reed
Foundation Installation
Management
Garry Blowers
Management of all
Foundation Installation
Management Contracts
Document Control
Karolina Kolacynska
Project Assistant
Hanne Kongstad
HS&E Manager
Peter Butler
CDM Practitioner
Kellie Field
Marine Warranty
Noble Denton
Consultants
Certification
DNV
Economic Control
Thomas Olofsson
O&M Site Manager
Jimmy Hansson
QHSE
Gordon Clark
PR & Communications
Mandy Broughton
Offshore Sub-Station
Martin Rendell
Jacket and Piles
Topsides
Loadout / Transportation
Installation and Hook-Up
Services
Risk Management
Peter Butler
Wind Turbines
Poul-Erik Larsen
WTG Installation
Find V Poulsen
SCADA
Lars Højholt
Power Plant Control
Jesper Runge Kristensen
Consents
Royal Haskoning
Kit Hawkins
Electrical
Stig Holm Sørensen
Cable Installation
Stig Holm Sørensen
Export CablesDavid Smail
Foundations
Naval Sondhi
Ramboll Foundations
Design
Transition
Pieces
Monopiles
Andy ReedHS&E
Andy Walker
Marine Coordination
SeaRoc
Port Technicians
Port of Ramsgate
Stephen Reynolds
Client Project Manager
Gordon Clark
Risk Management
Chris Hughes-Rees /
Peter Watson
Inter Array CablesGlen Evertsen
Site ManagerSøren Thor
Cardiff PowerDafydd Rickard
Garrad HassanTerry Foster
Array Cable Reps
• Polar Prince
• Normand Mermaid
Head of HSE
Kevin Lennon
Diving & Tower Crews
• Osiris
• Subocean
Export Cable Reps
• UR101• Shore End Ops
• Discoverer
SAP
John Harrison
Current Status
11/05/2010 10
Monopiles / TPs 100
Cables 89
WTGs 65
Substations 2
Export Cables 1 of 2
Strings Energised 2 of 10
Contracts Placed 77
Operations Building 1
Monopiles in Fabrication
11/05/2010 11
Sea Jack – Used for Monopile and TP Installation
11/05/2010 12
MPs in Installed with Navigation Aids
11/05/2010 13
TPs in Yard
11/05/2010 14
TP Installation
11/05/2010 15
Resolution – Used for TP and WTG Installation
11/05/2010 16
Sea Jack installing TPs
11/05/2010 17
Ramsgate Site
11/05/2010 18
Ramsgate Site Layout
11/05/2010 19
Onshore Substation Richborough
11/05/2010 20
Onshore Export Cable Works - A256
11/05/2010 21
Polar Prince DP Vessel for Cable Lay
11/05/2010 22
Normand Mermaid – Cable Lay
11/05/2010 23
UR101 – Export Cable Lay
11/05/2010 24
Cable Plough
11/05/2010 25
Euro Duct
11/05/2010 26
Offshore Substation Topsides Construction
11/05/2010 27
Offshore Substation Jacket Construction
11/05/2010 28
Stanislav Yudin – Offshore Substation Installation
11/05/2010 29
Installation of Offshore Substation by Yudin
11/05/2010 30
Offshore Substation Installation by Yudin
11/05/2010 31
Vessels working in the Field – things get busy at times
11/05/2010 32
Offshore Substation Installed
11/05/2010 33
Excalibur – Used for Offshore Substation Hook-up
11/05/2010 34
Met Mast Installation on Offshore Substation
11/05/2010 35
Marine Mammal Observation - 11th April 2009
11/05/2010 36
Installation of WTGs by Resolution
11/05/2010 37
WTG Installation by Resolution
11/05/2010 38
Lessons Learnt
• Project Management
• CDM 2007
• Contract Status
• Marine Operations
• Design Optimisation
11/05/2010 39
11/05/2010 40
Project Management
• HSE
• Document Control
• Planning
• Cost Control
• Interfaces
• Risk Management
• Package Management
• QA / QC
Typical Project Management
REDS Diving Support
ABJV Pile Gripper personnel
Dutch Heavy Lift Refurbishment of Pile Gripper
Densit Grouting Services
Fugro Seacore Drilling
IHC Hydrohammer Hammer Rental
IHC Handling Pile Lifting Tool (Rental)
NCS Positioning Base Station
Gardline Marine Mammal Observation
Sea Contractors Harbour Tug Hire
OWPMS Crew Vessel Charter
Gardline Crew Vessel Charter
Subacoustech Noise Monitoring
Envrioserve Guard Vessel
VG Lift Engineering Lift Supervisors
Storm Weather Forecasting
Trinity House Rental of Marker Buoys
Brown and May Herring Survey
Jon Ford Bird Surveyor
Arie Dirk Bird Surveyor
11/05/2010 41
Cost Forecast
• Missing Items
• Accuracy
• Risk Assessment
11/05/2010 42
Marine Operations
• Onshore Site and Marine Support
• CDM-2007 – Safety File
• Construction Vessel Coordination
• Crew Vessel Coordination
• Weather
11/05/2010 43
Design Overview and Optimisation
• String Completion
• Common Monopile Diameters
• Design for Installations
• Cable Installation Methodology
11/05/2010 44
Conclusions
• Plan the Work – Work the Plan
• Plan Early
• Appreciate Project Status
• Do Not Skimp on Project Management
• Identify and Manage Risk
11/05/2010 45
11/05/2010 46
For further information visit www.gl-nobledenton.com
Thank you for your attention!
11/05/2010 47
For further information visit www.gl-nobledenton.com
Thank you for your attention!
11/05/2010 48
For further information visit www.gl-nobledenton.com
Thank you for your attention!
11/05/2010 49
For further information visit www.gl-nobledenton.com
Thank you for your attention!