TGEPL_20MW_DPR_24.07.2014
-
Upload
lokesh-kuppili -
Category
Documents
-
view
215 -
download
0
Transcript of TGEPL_20MW_DPR_24.07.2014
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
1/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 1of 111
Detailed Project Report
20 MW (AC) SOLAR PV POWER PROJECT
VillageThat, Tehsil-Pokharan, Distt- Jaisalmer, Rajasthan
Date: 24.07.2014
Prepared by:
Gensol Consultants Pvt Ltd,
108, Pinnacle Business Park,
Corporate Road, Prahaladnagar,
Ahmedabad, Gujarat-380015
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
2/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 2of 111
Copyrigh t Protect ion Statement
Copyright Gensol Consultants Pvt. Ltd. The reproduction or transmission of all or part of this
work, whether by photocopying or storing in any medium by electronic means or otherwise
without the written permission of Gensol Consultants Pvt. Ltd is prohibited, and the commission
of any unauthorized acts in relation to the work may result in civil or criminal actions. The author
asserts its moral right to be identified as the author of the work.
Disclaimer Notice
This document has been prepared for M/S Today Green Energy Pvt . Ltd . (the Client) only and
solely for the purpose stated in the contract (the Contract) between Gensol Consultants Pvt Ltd
(the Consultant) and the Client.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
3/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 3of 111
Contents
GLOSSARY .......................................................... ................................................................... .................................. 8
ABBREVIATIONS .......................................................... .................................................................... .................... 10
EXECUTIVE SUMMARY.................................................................... .................................................................. 12
PROJECT AT A GLANCE .......... ................................................................... ....................................................... 16
1. INTRODUCTION ................................................................ .................................................................. 18
1.1ABOUT TODAY GREEN ENERGY PRIVATE LIMITED ORGANIZATION................................................................ 18
1.2ABOUT PROJECT CONSULTANT.................................................................. ...................................................... 19
1.3SCOPE OF SERVICES FOR DPR .............................................. ................................................................. .......... 20
2. INDUSTRY OUTLOOK ........................................... ................................................................. ........... 21
2.1BACKGROUND OF THE PROJECT....................................................... ................................................................ 21
2.2OBJECTIVE AND BENEFITS OF THE PROJECT.................................... ................................................................. 21
2.3GLOBAL AND INDIAN ENERGY SCENARIO............................ ................................................................... ........ 21
2.4RAJASTHAN STATE ELECTRICITY SCENARIO............. .................................................................... ................... 23
2.5RENEWABLE ENERGY POTENTIAL IN THE STATE.................................................................................... .......... 24
2.6GROWTH IN DEMAND........................................................... ................................................................... ........ 25
2.7SOLAR PVREACHING TOWARDS GRID PARITY.................... ................................................................. .......... 26
3. INDIAN MARKET FOR SOLAR POWER ............................................................................. ........... 27
3.1THENATIONAL SOLAR MISSION AND STATE POLICIES.................................................................................... 27
4. JUSTIFICATION FOR THE PROJECT ............................................................ ................................ 32
5. PROJECT SITE .......................................................................................... ........................................... 32
5.1LOCATION AND ACCESSIBILITY........................................................................................ ............................... 32
5.2RAINFALL AND CLIMATE................................................................................................ ................................. 35
5.3LAND REQUIREMENT AND LAYOUT OF THE PROPOSED PROJECT..................................................................... 36
6. SOLAR RESOURCE ASSESSMENT ................................................................ ................................. 38
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
4/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 4of 111
6.1INTRODUCTION...................................................................................................... .......................................... 38
6.2INDIAS SOLAR RADIATION PROFILE..................................................................... .......................................... 38
6.3RADIATION PROFILE OF THE SITE.............................................................. ...................................................... 39
7. SELECTION OF TECHNOLOGY ........................................................... ........................................... 41
7.1PHOTOVOLTAIC TECHNOLOGIES...................................................... ................................................................ 42
7.1.1CRYSTALLINE TECHNOLOGY.............................................................................. .......................................... 42
7.1.2THIN FILM TECHNOLOGY.................................................. ................................................................. .......... 43
7.1.3COMPARISON OF MAJOR PVTECHNOLOGIES: .............................. ................................................................ 44
7.2PVTECHNOLOGY RECOMMENDATION........................................... ................................................................. 46
7.3BALANCE OF PLANT SYSTEMS (BOS) ........................................................ ...................................................... 46
7.4INVERTER TECHNOLOGIES......................................................................................................... ...................... 46
7.5CABLING........................................................ ................................................................... ............................... 49
7.6MODULE MOUNTING SYSTEM.............................................. ................................................................. .......... 50
8. PROJECT REGISTRATION AND CLEARANCES ................................................................ ......... 52
8.1PROJECT REGISTRATION/CLEARANCES........................................................................................................... 52
9. POWER PLANT DESIGN CRITERIA .................................................................................... ........... 54
9.1DESIGN AND SIMULATION PROJECTIONS BY PVSYST ........................................................................... .......... 54
9.2PVPOWER PLANT ENERGY PRODUCTION............................ ................................................................... ........ 54
9.3PVPOWER PLANT CAPACITY UTILIZATION FACTOR (CUF) ............................................... ............................... 55
9.4SELECTION OF INVERTER AND COMPONENTS................................. ................................................................. 55
9.5SELECTION OF MONITORING SYSTEM........................................................................................... ................... 55
9.6DESIGN CRITERIA FOR CABLES AND JUNCTION BOXES................................................................ .................... 56
10. MAJOR COMPONENTS OF THE POWER PLANT .............................................................. ......... 57
10.1INTRODUCTION.................................................................................................... .......................................... 57
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
5/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 5of 111
10.2SOLAR PVMODULES.......................................................... ................................................................... ........ 58
10.3INVERTER........................................................................... ................................................................. .......... 59
10.4MODULE MOUNTING SYSTEM............................................ ................................................................. .......... 61
10.5MONITORING SYSTEM........................................................ ................................................................... ........ 62
10.6CABLES AND CONNECTORS................................................ ................................................................. .......... 63
10.7BUILDINGS FOR PLANT EQUIPMENT (INVERTER ROOMS AND CONTROL ROOM) ............................................ 64
10.8OTHER FACILITIES INCLUDING WATER.............................. .................................................................. ......... 65
11. POWER EVACUATION AND INTERFACING WITH GRID ........................................................ 66
11.1POWER EVACUATION PLAN................................................................................. .......................................... 66
11.2TRANSFORMERS.......................................... ................................................................... ............................... 66
11.3132KVSWITCHYARD..................................................................................................... ............................... 67
11.4HT,LV,33KVAND 132KVMETERING EQUIPMENT................................ ..................................................... 69
11.5CABLES............................................ ................................................................... .......................................... 70
11.6GRID SYNCHRONIZATION SCHEME.......................................................... ...................................................... 71
12. ESTIMATION OF ANNUAL ENERGY YIELD ............................................................ .................... 72
12.1INTRODUCTION.................................................................................................... .......................................... 72
12.2ENERGY GENERATION ASSESSMENT................................ ................................................................... .......... 73
13. OPERATION AND MAINTENANCE REQUIREMENTS ............................................................... 78
13.1BASIC PLANT OPERATION........................... ................................................................... ............................... 78
13.2MAINTENANCE REQUIREMENTS....................................... ................................................................... .......... 79
13.3SPARE PARTS MANAGEMENT SYSTEM................................................................. .......................................... 80
13.4O&MMANUALS................................................................................................ .......................................... 80
13.5OPERATION &MAINTENANCE ORGANIZATION OF THE PLANT....................................... ............................... 81
14. PROJECT IMPLEMENTATION STRATEGY .......................... ....................................................... 83
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
6/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 6of 111
14.1PROJECT PHASES................................................................ ................................................................. .......... 83
14.2PROJECT REGISTRATION AND FINANCING............................................................ .......................................... 83
14.3FINALIZATION OF THE EQUIPMENT AND CONTRACTS.......................................... .......................................... 83
14.4PROCUREMENT AND CONSTRUCTION............................................................................................................. 84
14.5ERECTION AND COMMISSIONING PHASE................................................................................................ ........ 84
15. RISK ASSESSMENT AND MITIGATION ........................................................................................ 86
15.1 PROJECT COMPLETION RISK MEDIUM/LOW......................................................................... ...................... 86
15.2TECHNOLOGY RISK
LOW............................................................ ................................................................ 86
15.3COST OVER-RUN RISK -LOW.................................. ................................................................. ...................... 87
15.4GENERATION ASSURANCE MEDIUM............................................................................. ............................... 88
15.5FORCE MAJEURE RISK LOW.............................................................................. .......................................... 88
15.6OPERATING RISK LOW.......................................................................................................... ...................... 88
15.7PLANT PERFORMANCE RISK MEDIUM................................................................................................ ......... 89
16. PROJECT COST ESTIMATE AND FINANCIAL ANALYSIS ....................................................... 90
16.1PROJECT COST..................................................................................................... .......................................... 90
16.2SALEABLE ELECTRICITY.......................................................................................................... ...................... 91
17. LIST OF SUPPLIERS .......................................................... ................................................................. 92
ANNEXURE-I : ENERGY SIMULATION REPORT (10 MW BLOCK) .............. ........................................... 94
ANNEXURE-II: MODULE DATASHEET ................................................................ ........................................... 97
ANNEXURE-III: INVERTER DATASHEET ............................................................................................. ......... 99
ANNEXURE-IV: PROJECT SCHEDULE ........ ................................................................... .............................. 105
ANNEXURE-V: SLD- 20 MW PLANT ................................................................................. .............................. 110
ANNEXURE-VI: SLD- 50 MW PLANT ......................................................... ..................................................... 111
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
7/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 7of 111
List of Figures
Figure 1: Seismic zone of India.................................................................................................................. ........... 33
Figure 2 Location of site.............................................................................................. ........................................... 34
Figure 3 Solar Resource Map of India............................................... .................................................................. 39
Figure 4 Typical solar PV system components................................................................................................... 41
Figure 5 Mono-Crystalline Silicon Module....................................................................................... .................... 43
Figure 6 Multi-Crystalline Silicon Module................................ ................................................................. ........... 43
Figure 7 Thin film PV module......................................................................... ....................................................... 44
Figure 8 Block diagram showing interconnection of various systems............................................................. 58
Figure 9 Typical photovoltaic solar module ..................................................................................... .................... 59
Figure 10 Typical Solar Inverter............................................................................................ ................................ 60
Figure 11 Typical Fixed tilt module mounting structure..................................................................................... 61
Figure 12 Typical Control Room Section............................................................................. ................................ 65
Figure 13 Tilt angle optimization snapshot from PVsyst............................ ....................................................... 73
Figure 14 Sun path for the proposed location..................................................................................................... 74
Figure 15: Organizational Chart............................................................................................ ................................ 82
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
8/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 8of 111
GLOSSARY
Photovoltaic The physical effect of direct Conversion of light (sunlight)to electrical energy
PV CellThe smallest photovoltaic (PV) element that generateselectricity from light
PV Module
A collection of interconnected PV cells, encapsulatedbetween protective materials such as glass and backsheet (Poly Vinyl Fluoride) or glass and glass, andmounted in an aluminum frame. This is a hermeticallysealed unit
ArraySeveral strings of modules with the same orientation andtilt angle, located together
InverterAn electronic device that converts direct current electricityinto alternating current electricity suitable for feedingdirectly to the electrical grid or to normal AC loads
Insolation
It is a measure of solar radiation energy received on agiven surface area in a given time. It is commonlyexpressed as average irradiance in watts per square
meter (W/m) or kilowatt-hours per square meter per day(kWh/ (mday)) (or hours/day)
Mounting StructureDevice used to hold modules in place, at desired angle &direction
Power EvacuationPower generated from Solar PV Power Plant istransmitted to a point (sub-station) where it is distributedfor consumer use
Sub-station
The place where the generated power from solar is
synchronized with utility grid and metered
Control Room Room housing control equipment
CableA conductor with one or more strands bound together,used for transmitting electrical energy
Junction BoxInputs of several strings are connected to this box andtaken as single output
CurrentA flow of electricity through a conductor measured in
Amps
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
9/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 9of 111
Voltage
The rate at which energy is drawn from a source thatproduces a flow of electricity in a circuit; expressed in volts.It is the difference of electrical potential between twopoints of an electrical or electronic circuit, expressed in
volts. It is the measurement of the potential for an electricfield to cause an electric current in an electrical conductor
Lightning ArrestorDevice used to protect all the components from lightningstrikes
TransformerAn electrical device by which alternating current of onevoltage is changed to another voltage
GridA system of high/low tension cables by which electricalpower is distributed throughout a region
SCADA
Instrumentation & Control system for the solar power plantused to detect malfunctions and give information at a giventime interval about the availability and performance of theplant
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
10/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 10of 111
ABBREVIATIONS
General
ACB Air Circuit Breaker
AC Alternate current
ACSR Aluminum Conductors Steel Reinforced
BOS Balance of the System
CO2 Carbon Dioxide
CT Current Transformer
DC Direct Current
DP Double Pole
DPR Detailed Project Report
HT High Tension
LT Low Tension
LV Low Voltage
MNRE Ministry of New and Renewable Energy
SECI Solar Energy Corporation Of India
KWh Kilo Watt Hour
MCB Main Combiner Box / Miniature Circuit Breaker
PLF/ CUF Plant Load Factor/ Capacity utilization factor
PPA Power Purchase Agreement
PV Photo Voltaic
PT Power Transformer
VCB Vacuum Circuit Breaker
XLPE Cross Linked Polyethylene
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
11/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 11of 111
Units
% Percentage
C Degree Centigrade
Kg Kilogram
kV Kilo-Volt
kW kilo Watt
kWp kilo Watt peak
Lt Liter
M Meter
m2 Square meter
m3 Cubic meter
Tons Tons
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
12/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 12of 111
EXECUTIVE SUMMARY
Today Green Energy Private Limited (TGEPL) is a SPV company promoted by Today
Homes & Infrastructure Private Limited (THIPL), a Group Today Company planning toput up large scale Solar power projects at strategic locations suitable for Solar power
generation across India.
THIPL, is a well-established enterprise in the field of Real Estate Development with a
number of Residential, Retail and Commercial projects Delivered and Under
Development. Apart from real estate the THIPL is also in the business of Hospitality.
Over a period of next 5 years, the Company is committed to set up facilities to generatemore than 5000 MW of power, coal-based and renewable sources. The expansion will
be fuelled by setting up Greenfield projects as well as expansion in existing power plants.
THIPL has been declared as a successful bidder in the bid process against the Rfs No
SECI/JNNSM/SPV/P-2/B-1/Rfs/102013 issued by Solar Energy Corporation of India
(SECI) and had been issued Letter of Intents.
THIPL has formed a Project Company TGEPL for the development of Solar PowerProjects. In this regards, TGEPL is going to install a 20 MW (2x10MW) solar PV plant,
under the Open Category, at village That, situated in Jaisalmer district of Rajasthan state.
The geographical location of the project site is 26.840544 N and 71.818534 E. For the
proposed project approx. 115 acres of the land will be required.
Radiation profile of the location has been assessed using the industry standard
Meteonorm software and the electricity generation has been estimated. 255 Wp (or
higher) capacity poly-crystalline technology based PV modules are suggested for the
proposed solar plant. The basis of selection of poly-crystalline technology is its financial
competitiveness, long term stability and easy availability. Further, on the basis of basic
design engineering, 1000 kW solar inverter units are proposed and 20 nos. of inverters
shall be required for the plant. This project shall be using fixed tilt module mounting
structures for the installation of PV modules. With such arrangement, it is projected that
the proposed 20 MW project will operate at a CUF around 22.29% and will be generating
around 39, 048,487 kWh units per year. Probability analysis has also been presented inthe DPR at the P50, P75 and P90 probability level.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
13/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 13of 111
The generated electricity from the solar PV plant will be evacuated in the dedicated 132
kV grid substation situated 12 kms from the project site. TGEPL has signed a PPA at flat
rate of Rs. 5.45/ kWh for life time of the project, which is considered as 25 years, with
Solar Energy Corporation of India (SECI).
The project cost of the envisaged 20 MW (AC) PV Plant is estimated to be Rs. 15070
Lakhs. Debt equity ratio of the investment is 70:30 and debt equity amount for this ratio
is Rs. 10549 lakhs and Rs. 4521 lakhs respectively. The project will receive VGF funding
to the tune of Rs. 2190 lakhs. Furthermore, considering the financial analysis, it is
projected that investment in the proposed project will give a project IRR of 11.81%.
Average Debt Service Coverage Ratio (ADSCR) of the proposed investment is worked
out to be 1.45.
Apart from the financial benefits the solar power plant also helps to reduce the release
of carbondioxide produced by fossil fuel generation. The project converts solar radiation
into useful electricity, adding to sustainability of the project and the local environment.
Besides all these concerns, this report highlights the details of the proposed power
generation scheme, site facilities, solar radiation in the proposed site location and water,
evacuation of generated power, features of main plant and equipment including the
inverter system, electrical systems, environmental aspects, estimate of capital cost and
the financial analysis and the schedule for project implementation.
Group Company Today Homes & Infrastructure Pvt. Ltd. (THIPL) located at Delhi is
a well established enterprise in the field of Real Estate Development and Hospitality with
numbers ofResidential, Retail and Commercialprojects already developed and the rest
are under development.
Further in 2007 Today Homes & Infrastructure Pvt. Ltd. (THIPL) has diversified in
the Power Sector and form a company Today Energy (MP) Pvt Ltd.(TEMPPL)
promoted by Today Homes & Infrastructure Pvt Ltd.(THIPL) to set up 1320 MW
(2x660 MW) coal based Thermal Power Plant (IPP) at village Silari, Tehsil Gotegaon,
Dist. Narsinghpur, Madhya Pradesh. The details of the project is given below:
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
14/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 14of 111
I) Land: Total land acquired is appox. 750 acres at Distt Narsinghpur in the State
of Madhya Pradesh (M.P.), which is sufficient, as per CEA norms for 1320
(2x660) MW coal based thermal Power Project with Supercritical technology.
a) Private Landappox685.54 Acres of land in continuous stretch for the project
has been purchased directly from the land owners through consent route and is
in our possession.
b) Government landof 64.15 Acres has been allocated vide GoMP Revenue
Deptt. Order No. F16-41/2008/7/2A Bhopal dated 31.03.2011.
No forest land is involved.
II) Firm allocation of 40 cusec of waterhas been granted by Water Resource Dept.
(WRD), GoMP.
III) Coal:
(A) Coal linkage for one unit of 660 MW has been tied up with the State of Madhya
Pradesh.
(B) In addition, Central Electricity Authority (CEA) Standing Committee hasrecommended the name of project company i.e. Today Energy (M.P.) Pvt Ltd
(TEMPPL) with maximum marks i.e. 90 (ninety) to Ministry of Power (MoP)
which has further recommended to Ministry of Coal (MoC). It is expected that
long term coal linkage shall be allocated to TEMPPL by Long Term Linkage
Committee shortly.
IV) Environment Clearance: TOR was accorded by MOEF in September 2007.
Public hearing committee meeting was conducted on 19.06.2009 by M.P.
Pollution Control Board. EIA report was submitted through M.P. Pollution Control
Board to Expert Appraisal Committee (EAC) of MOEF and put up in their 65 th
meeting on 13.02.2010. In absence of firm fuel linkage to the project, proposal
was deferred till fuel tie up. Long term coal linkage for one unit of 660 MW has
been tied up with the State of Madhya Pradesh. We have again taken up the
proposal with EAC of MOEF for issuance of EC to the project.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
15/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 15of 111
V) International Competitive BiddingCorrigendum issued on 11.05.2011 to earlier
International Competitive Bidding (ICB) Notice Inviting Tender NIT-ICB wherein
leading international/national manufacturer of BTG participated in the bid. Initial
round of technical discussion have completed and final techno commercial
negotiations are in progress.
VI) Rail Transport Clearance from Ministry of Railway (Railway Board) was
accorded for establishing railway siding at the Project Site.
VII) Open AccessThe Bulk Power Transmission Agreement for 800 MW entered
into with Power Grid Corporation of India Ltd.
VIII) Chimney Height Clearance fromAirports Authority of India has been accorded.
IX) Defence Clearance has been obtained from Defence Estate Office, Jabalpur
Circle.
X) Fly Ash Utilization
a) MOU already signed with M/s ACC Ltd. for collection of 2000 MT of fly ash perday.
b) MOU signed with M/s Vikas Concrete Industries, Jabalpur for collection of 1000
MT of fly ash per day.
XI) Power Evacuation:In the past few years there was no procurement inspite of big
demand supply gap from various State Utilities because of the financial
constraints. The Central Government has approved a big financial package to
carry out the financial restructuring of the State Utilities. This has resulted into the
starting of the power procurement by such Utilities to meet their deficiency in
power. Recent bids have been in the range of Rs. 4/-kWh to Rs. 5/-kWh. Since
the fuel has been tied up, we are contemplating to participate in the various power
purchase bids being invited by various state Utilities. Some of them are already in
pipeline.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
16/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 16of 111
PROJECT AT A GLANCE
Project Developer Today Green Energy Pvt Ltd.
(TGEPL)
Project Installed Capacity 23 MWp (DC), 20 MW (AC) SolarPhotovoltaic Power Plant
Selected Location Village: That ; Tehsil: Pokharan;District-Jaisalmer, Rajasthan
Site Co-ordinates 26.840544 N and 71.818534 E
Global Horizontal Irradiation 1974.7 kWh/m2
Tariff details Rs. 5.45 for 25 years
Annual degradation 1%
Nearest Major Towns Pokharan, Phalodi, Jaisalmer,Jodhpur
Solar module type Poly Crystalline
Capacity of each module 255 Wp
No. of modules 90,192 (2x10 MWacplant)
PV System Mounting Structure type MS Galvanised
Power conditioning Unit (Inverters)capacity
1000 kW
Power conditioning Unit specifications Input voltage range 600850 V
No. of inverters 20 Nos.
Inverters make ABB
Capacity Utilisation Factor 22.29 %
Expected Generation(after 1styear ofoperation)
39,048,487 kWh
Total Project cost (Rs in lakhs) 15070
Equity from Promoters (Rs. in lakhs) 4521
Term loan from Financial Institutions (Rs.in lacs) 10549
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
17/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 17of 111
VGF Funding (Rs. in lacs) 2190
Project IRR 11.81%
Equity IRR 14.01%
Land 115 acres approx
Power Evacuation 132 kV Grid substation at Pokharan
Mode of Implementation By EPC (Engineering, Procurementand Construction)
Project Time Frame Seven (7) months
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
18/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 18of 111
1. INTRODUCTION
This report is referred to as the Detailed Project Report for installation of 20 MW (AC)
Photovoltaic (PV) Plant at village That, Tehsil Pokharan, District Jaisalmer, Rajasthan(Project Site or Site). The report is prepared by Gensol Consultants Private Limited
having been appointed as the Project Consultant for the client with the intention to
provide a detailed project pre-feasibility analysis and advisory. This report includes the
feasibility studies, system design and techno-commercial analysis for installation of the
PV plant.
1.1 About Today Green Energy Private Limited Organization
Today Green Energy Private Limited. (TGEPL) is a company promoted by Today Homes
& Infrastructure Private Limited, a Group Today Company planning to increase its energy
portfolio in the renewable energy sector in India.
Today Homes & Infrastructure Pvt Ltd.is a well established enterprise in the field of Real
Estate Development with a number of Residential, Retail and Commercial projects
Delivered and Under Development. Apart from real estate the Group Today is also in the
business of Hospitality.
Over a period of next 5 years, the Company is committed to set up facilities to generate
more than 5000 MW of power, largely coal-based. The expansion will be fuelled by
setting up Greenfield projects as well as extension in existing power plants. Discussions
at various levels with concerned authorities are already in progress.
The power projects are planned to be diverse in geographic location, fuel type, fuel
source & off take, and each project is planned to be strategically located near an
available fuel supply load center.
Power generated from these units will be sold under the combination of long term and
short term PPAs to state owned/private distribution companies and industrial consumers.
Discussions are already in progress.
http://www.todayhomes.co.in/http://www.todayhomes.co.in/ -
8/10/2019 TGEPL_20MW_DPR_24.07.2014
19/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 19of 111
1.2 About Project Consultant
Gensol Consultants Pvt. Ltd. founded in March 2007 was setup as a 360o Carbon
Solution Provider having expertise in generation, registration and trading of Certified as
well as Verified Emission Reductions (CERs and VERs), better known as carbon credits.
In the past 4 years, Gensol has spread its area of expertise from providing consultancy
for Clean Development Mechanism (CDM) to technical-commercial advisory services for
the setup and expansion of energy infrastructure, thus providing them with a complete
package to grow and benefit from our expertise and assistance. Having an early entry
advantage along with a creative and dedicated team, Gensol Consultants Pvt. Ltd. is
built on one of the most innovative, client friendly and revenue boosting models.
Consequently, the company boasts of handling numerous projects across the length and
breadth of the country with over 10 million Emission Reductions in the first commitment
period and more than 800MW of solar PV advisory projects already under its wing.
Gensol Solar Division, set up in early months of 2009 is dedicated to using technology,
engineering and innovation to give its clients the best returns on their capital. It is with
this view that we strive to provide support and engineering expertise to clients and
investors in Solar Power Sector through our offerings of complete concept to
commissioning advisory services for MW scale grid-connected and off grid standalone
solar power projects. Gensol Solar Team boasts of years of on-ground experience in
setting up of Solar Power Plants. Comprising of Electrical, Civil and Mechanical
Engineers on one hand and Financial and Regulatory Consultants on the other, Gensol
Solar team presents a unique blend of technological expertise with market intelligence,
thus, helping us provide a 360operspective to clients.
Gensol Consultants is empanelled with various lending institutions and Ministry of New
and Renewable Energy. Gensol also hold the distinction of representing Ministry of
Environment and Forestry (MoEF) at International Forums.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
20/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 20of 111
1.3 Scope of Services for DPR
The scope of work for the DPR includes all details concerning the feasibility, design, and
financial viability of the project.
The Report has the following main contents:
Site assessment
Solar radiation resource assessment
Solar PV technology assessmentand evaluation
Annual Yield estimation
SPV Plant layout
Overall System description
Power evacuation arrangements and single line diagram (SLD)
Clearances and permits
Financial analysis
Risk Assessment
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
21/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 21of 111
2. INDUSTRY OUTLOOK
2.1 Background of the project
THIPL had participated in the JNNSM Phase II Batch I solar bid conducted by Solar
Energy Corporation of India (SECI). In the bid results THIPL has been allotted a total of
5 PV projects of 10 MW capacity each. Out of this, 2 PV projects of 10 MW each i.e.
20MW are under open category and 3 PV projects of 10 MW each i.e. 30MW are under
the DCR category. THIPL has formed a Project Company TGEPL for the development
of Solar Power Projects. This DPR is meant for Open category i.e. 20MW.TGEPL board
has decided to install 2 x10 MW project capacity, near village That, Pokharan. Electricity
sale arrangement has already been done by signing a long term PPA with SECI at Rs.
5.45/ kWh for the 25 years.
This project will be executed with an EPC (Engineering, Procurement and Construction)
partner. TGEPL will invest 30% of the total project cost as equity investment and rest of
the money which is 70% of the project cost shall be arranged from a financial institution
as debt.
2.2 Objective and benefits of the project
The objective of the proposed solar power plant is to generate clean energy from the
solar radiation using photovoltaic phenomenon. This energy will be evacuated to the
nearby grid and further distributed in the electricity network. Solar energy is a clean
source of electricity and produces no pollution. Hence, there are many social economic
benefits are associate with the development of this project.
2.3 Global and Indian Energy Scenario
Electricity is one of the world's fastest-growing form of end-use energy consumption. Net
electricity generation worldwide will rise by 2.3 percent per year on average from 2007
to 2035 as compared to 1.4 percent per year growth for total world energy demand. The
growth in electricity generation for non-OECD countries increases by an average annual
rate of 3.3 percent, as rising standards of living increases the demand. In OECD nations,
where infrastructures are more mature and population growth is relatively slow, growth
in generation is much slower, averaging 1.1 percent per year from 2007 to 2035.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
22/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 22of 111
Graph 1: World Electricity Consumption Projections
The Indian government has set ambitious goals in the 11th plan for power sector owing
to which the power sector is poised for significant expansion. It has been estimated that
need-based capacity addition of more than 100,000 MW would be required. This has
resulted in massive addition plans being proposed in the sub-sectors of Generation
Transmission and Distribution.
Graph 2: Indian Energy Scenario
Thermal
68%Nuclear
2%
Hydro 17%
Solar
13%
Indian Energy Scenario
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
23/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 23of 111
2.4 Rajasthan state electricity scenario
Rajasthan state has total installed capacity or the order of 14059.12 MW. Thermal is
leading source of energy with total installed capacity of 8454.75 MW. It is approximately
60.13% of the total installed capacity. Second highest installed capacity is of Renewable
energy source which is of the order of 3483.05 MW and hydro is of 1548.32 MW and
remaining is from the nuclear is 573 MW.1
Graph 3: Rajasthan Energy Scenario
Furthermore, contribution of renewable energy sources in the total installed capacity is
really astonishing and also generates hope for the renewable energy investors. Including
Hydro capacity, total renewable energy capacity in the state is about 36% of the overall
installed capacity.
Now looking at energy demand and supply picture, in 2012-2013, energy requirement of
Rajasthan state was 55538 MU and energy availability was only 53868 MU. There was
around 3 % energy deficiency. Monthly records further showing the picture of the energy
deficiency condition of the state. Maximum deficiency was 8.9 % in the month of June
2012.2
1http://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdf2http://www.cea.nic.in/reports/yearly/lgbr_report.pdf
Thermal
60%
Nuclear
4%
Hydro
11%
RES 25%
Energy Scenario of Rajasthan State
http://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdfhttp://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdfhttp://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdf -
8/10/2019 TGEPL_20MW_DPR_24.07.2014
24/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 24of 111
Graph 4: Energy Demand Vs Supply in Rajasthan
Anticipated power deficit in the state is 15.1 %. This data clearly indicates that there is a
huge demand of energy and electricity generated from solar PV plant can surly be
consumed.
2.5 Renewable Energy potential in the state
Rajasthan is the state having almost all commercial renewable energy technology
installed, whether it is wind mills, solar PV, Hydro, bio-mass etc. Moreover, the potential
of the renewable energy generation is also promising. State has 35% renewable power
installation out of total power. Major renewable energy sources in the state are wind and
solar. Considering the data of Indian Wind Energy Association, Rajasthan has wind
potential of the order of 5005 MW3.
Sun is the most abundant natural source of energy available on the earth. Solar energycan either be used for the generation of electricity (photovoltaic energy) or for heating
purposes (solar thermal energy). As solar electricity generation and other use of solar
energy do not emit any GHG emission, it is treated as renewable energy source.
3Centre for Wind Energy Technology (CWET): http://www.cwet.tn.nic.in/html/departments_wra.html
3500
3750
4000
4250
4500
4750
5000
5250
5500
5750
6000
EnergyinM
U
Energy Demand Vs Supply in Rajasthan StateRequirement (MU) Availability (MU)
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
25/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 25of 111
2.6 Growth in Demand
Despite the rapid growth in this decade, solar photovoltaic is a young market. Thus the
different industry forecasters have different sizes even for the existing market, let alone
their forecasts in the longer term. The European Photovoltaic Industry Association
(EPIA) has comprehensive long-term forecasts for the photovoltaic industry. Its forecasts
have been much more cautious than the break-neck speed of industry growth in the last
2-3 years; however, there is every possibility that the much higher results in comparison
to forecasts over the last few years will result in over-estimation of the market.
Globally, the solar power industry has been growing rapidly in recent years. In 2010, an
estimated total capacity of 17,000 MW was installed globally. Germany leads the racewith more than 40 percent of the total global market.
The three leading countries (Germany, Japan and the US) represent nearly 89% of the
total worldwide PV installed capacity. Currently, around 84% of solar industry demand is
located in four countries where governments have actively promoted its development
through favorable regulation: Germany, Japan, Spain and the US in selected states.
Spain was one of the fastest growing markets in 2008 owing to very favorable legislation
and attractive feed-in tariffs. In 2008, Spain accounted for 45% of the new photovoltaic
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
26/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 26of 111
installments. However in 2009, Spain market reduced considerably due to government
policy change on the FIT.
Going forward, the growth in Sunbelt countries is expected to increase considerably dueto the higher demand for power and better solar resource in these countries such as
India, MENA, China, etc.
2.7 Solar PV Reaching towards Grid Parity
Grid parity is the point at which photovoltaic electricity is equal to or cheaper than grid
power. This is achievable first in areas with abundant sun and high costs for electricity
such as in California and Japan. For regions with subsidies for solar power generation,
grid parity can be achieved much sooner. Costs of solar electricity are falling steeply
through a combination of factors including better cell efficiency and improvements in
solar manufacturing.
As the PV system costs decrease, the geographies with higher solar radiation and high
price of electricity will achieve grid parity at the earliest. For example, in Hawaii where
the cost of electricity is high and there is also abundant solar radiation, PV has already
reached grid parity with todays system costs. Italy also is a very prime region where PV
will be at grid parity shortly.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
27/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 27of 111
3. INDIAN MARKET FOR SOLAR POWER
A Solar PV Project Developer can set up a solar power project in India in one of the
following three ways:
3.1 The National Solar Mission and State Policies
The Jawaharlal Nehru National Solar Mission is a major initiative of the Government of
India with active participation from States to promote ecologically sustainable growth
while addressing Indias energy security challenge. It will also constitute a major
contribution by India to the global effort to meet the challenges of climate change. Theobjective of the Mission is to establish India as a global leader in solar energy, by creating
the policy conditions for its large scale diffusion across the country as quickly as possible.
The Mission has set a target, amongst others, for deployment of grid connected solar
power capacity of 20,000 MW by 2022 and is planned to be implemented in three phases
with phase-1 by 2013, phase-2 by 2017 and phase 3 by 2022. Against the targets for
phase 1, major achievements include the following:
National Solar Mission
Solar Policy of the Central Govt aimed at setting up20,000 MW of Solar Power Plants by 2022
State Policies
Individual states like Gujarat, Rajasthan, Karnataka and
Madhya Pradesh have released their own policies to setup Solar PV Power Plants in the respective states
Renewable Energy Certificates
Any Project Developer can set up any size of projectanywhere in India. Unlike preferential tariff under NSMand State Policies, REC's offer a variable tariff over the
lifetime of project.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
28/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 28of 111
The entire capacity of 1,100 MW of grid connected solar power has been allocated.
The sanctioned capacity for off grid applications is over 118 MW.
No direct financial assistance is provided by the government for setting up solar power
projects connected to the grid. One scheme of 1000 MW has been implemented through
a mechanism of bundling of solar power with thermal power from unallocated quota of
the Government. For projects connected to less than 33 kV grid, a scheme of generation
based incentive has been implemented under which a total of 98 MW capacity projects
were allotted.
To support deployment of off-grid solar applications, the Government provides capitalsubsidy upto 30% of the benchmark cost and / or soft loan at a rate of 5% interest.
Since launch of the JNNSM, the capacity of grid-connected solar power projects has
grown from 8 MW in January 2010 to over 2208 MW 4by January 2014 in the country.
Recently, MNRE has established the Solar Energy Corporation of India (SECI) for
handling the power procurement from the second batch of the JNNSM. SECI (MNRE)s
role would be limited to providing a subsidy known as Viability Gap Funding (VGF), whichis basically a part payment, made by SECI to the project developer in order to make the
project viable. MNRE has recently unveiled guidelines for allocation of solar power
project worth 750 MW under the VGF route, out of which, half if earmarked for projects
opting for cells and modules of domestic origin.
State Policies
Subsequent to the launch of the JNNSM, many states have acknowledged the
importance of solar energy and hence formulated their own respective policies regarding
the same. Solar potential with their installed capacities for the states which have released
the solar policies have been summarized in the following table:
4Source : MNRE : http://www.mnre.gov.in/mission-and-vision-2/achievements
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
29/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 29of 111
Summary of solar potential, state policy targets and installed capacities in the states of India5
S.No. State Average Annual
Solar Resource
(kWh/m2/day)
Govt. Policy/Target Installed PV
Capacity (MW)
1) Rajasthan 5.0-6.3 Solar power of 10000-
12000 MW capacity by
2022.
666.75
2) Gujarat 5.2-6.0 500 MW by 2014 860.4
3) Karnataka 4.6-5.8 200 MW by 2016 31
4) Tamil Nadu 4.8-5.8 3000 MW of power by
2015
31.82
5) Andhra Pradesh 4.8-5.8 97.2 MW sanctioned 92.9
6) Madhya Pradesh 5.0-5.6 500 MW by 2013 195.32
7) Chhattisgarh 5.0-5.6 500-1000 MW by March
2017
5.1
8) Maharashtra 4.6-5.6 No declared state-
specific target other
than RPO fulfillment
237.25
5Source: MNRE. Installed capacity data as on January 31st, 2014.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
30/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 30of 111
9) Uttar Pradesh 4.6-5.2 1000 MW by 2017 17.38
10) Punjab 4.6-5.1 300 MW in Phase-I 9.33
11) Haryana 4.7-5.3 No declared solar
specific policy
7.8
12) Uttarakhand 3.8-5.7 No declared solar
specific policy
5.05
13) Jharkhand 4.7-5.5 No declared solar
specific policy
16
14) West Bengal 4.2-5.1 No declared solar
specific policy
7.05
15) Odisha 5.1-5.5 No declared solar
specific policy
15.5
16) Delhi 4.7-5.1 No declared solar
specific policy
3.01
17) Andaman and
Nicobar
4.7-5.1 No declared solar
specific policy
5.1
18) Others No declared solar
specific policy
1.62
Total 2208 MW
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
31/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 31of 111
The main features of the Rajasthan State policy is discussed as under:
Rajasthan State Policy:
The policy aims at developing Rajasthan as a global hub of solar power of 10,000-
12,000 MW capacity in next 10-12 years to meet energy requirements of Rajasthan
and India. To achieve grid parity in next 7-8 years, the State will encourage the Solar
Power Developers to establish manufacturing plant of their technology in Rajasthan.
The Rajasthan State will promote setting up of solar power projects for direct sale to
Discoms of Rajasthan. The total capacity under this category will be distributed equally
between SPV and CSP based power plants. The total maximum capacity under thiscategory for phase-1 (up to 2013) and phase-2 (2013-2017) would be as follows:-
Phase-1 (up to 2013) Phase-2 (2013 -2017)
Maximum Capacity to be developed 200 MW 400 MW (Additional)
Selection of these Solar Power Projects shall be through tariff based competitive
bidding process. The State Government may undertake the review of targets mentioned
above as and when the need arises in view of any technological breakthrough resulting
in substantial decrease in cost of Solar Power generation. The Rajasthan State will also
promote Solar Power Producers to set up Solar Power Plants of unlimited capacity for
captive use or sale of power to 3rd party/States other than Rajasthan. The State will
also promote deployment of Roof Top and Other Small Solar Power Plants connectedto LT/11kV Grid as per guidelines of MNRE under Rooftop PV & Small Solar Generation
Programme (RPSSGP) of NSM and orders of appropriate Regulatory Commission.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
32/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 32of 111
4. JUSTIFICATION FOR THE PROJECT
Average annual solar radiation at the proposed site at horizontal surface is 1975 kWh/m2
which is potentially adequate for the installation of the PV plant. Annual expectedgeneration from the 10 MW block is 19,524,243 kWh and for the entire 20 MW is
39,048,487 kWh.
Considering power demand for the state, power generated from the proposed power
plant will be utilized for the state itself. The proposed solar photovoltaic power plant
(SPV) will contribute to bridge the gap between the demand and availability of power.
Moreover, it will also help to cut out the dependency on the coal to generate the
electricity. Furthermore, electricity from the solar power plant will be evacuated to the
132 kV GSS of RRVPNL situated about 12 kms from the site. Being a higher capacity, it
is anticipated that grid outage and transmission losses will be considerably low and this
will help to optimize the electricity feed in the grid. The project - being a renewable energy
project - leads to sustainable development through efficient utilization of naturally
available sunlight.
Financial benefit is an important factor of any investment. Installation of solar PV plant
seems to be a financially lucrative preposition as it is projected that proposed project will
have IRR of the order of 11.81 %.
In other words, the proposed project is a beneficial preposition in term of financial returns,
environmental aspects and business preposition.
5. PROJECT SITE
5.1 Location and Accessibility
Proposed site location is situated at Latitude 26.840544 N and Longitude 71.818534 E,
in Village-That, Tehsil-Pokharan, Distt - Jaisalmer, State - Rajasthan. The site is located
at elevation of approximately 229 m above mean sea level. The project location comes
under seismic zone-2. Hence, the threat of damage due to an earthquake is also very
low.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
33/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 33of 111
Figure 1: Seismic zone of India
The site is well connected with the intra-state and interstates locations through road,
railway and airways. Location is situated near to NH-15. Nearest city is Phalodi which is
about 75 km and nearest railway station is also located in Phalodi city. Nearest airport is
in Jodhpur which is 182 km from the site. The distance of state capital Jaipur from the
site is of the order of 478 km.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
34/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 34of 111
1.1.1.1.1.1
Figure 2 Satellite map showing the location of the site
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
35/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 35of 111
The site selection for a solar power plant is pre-dominantly determined by solar insolation
availability & grid connectivity for exporting power. Equally important are other essentialfactors/considerations such as:
Availability of adequate land for power plant and green belt development
Soil condition like soil bearing capacity etc.
Proximity to state electricity grid enabling economic evacuation of power generated
Availability of water and power during construction
Availability of local work force in the proximity
Availability of load centers (towns) within vicinity Easy accessibility of the site
5.2 Rainfall and Climate
The following graph depicts that in the month of January temperature goes below even
from 8 0C and in the month of May goes high up to 45 0C. The average annual
temperature at the site is 26 0C.
Graph 5: Temperature profile of VillageThat
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
36/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 36of 111
The site receives scanty rainfall annually around 308.5 mm. Rainfall occurs mainly in the
months of June, July, August and September.
Graph 6: Rainfall Profile of Village - That
5.3 Land Requirement and Layout of the Proposed Project
The total land area required for the project is about 115 acres.
The power plant layout can be divided in to three main sections as:
1. Module mounting area
2. Control room
3. Inverter Rooms
The major portion of the site will be used for module mounting. The modules will be
mounted on a galvanized steel structures which will be installed facing south direction
for best efficiency & optimal power output. The steel structure will be grouted using RCC
foundation (or ramming if soil conditions permit). The proposed structure shall be
designed to hold 20-25 modules per structure and which can withstand wind speed up
to 170 km/hr. The structure is designed in such a way that it will occupy minimum
required space without sacrificing the performance.
4.65 6.16 4.65 5.78.68
32.7
115.63
86.8
32.1
8.680.9 1.86
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
37/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 37of 111
The interconnection cables are routed within the structure and the output cables from
the modules are taken through proper size conduit to the String Combiner Box (SCB).
The output cables from the SCBs are routed under the ground through conduits or cable
trenches. Earthing for the entire module mounting structures will be done using copper
or GI conductors. The earth pits for module area will be provided as the electrical
standards. In order to protect the modules from lightning, lightning protection will be
provided in the module mounting area. Sufficient number of lightning arrestors will be
provided in this area alone for protection of modules.
The layout of the array structures shall be so designed that it shall occupy minimum
space without sacrificing the output of Solar PV modules.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
38/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 38of 111
6. SOLAR RESOURCE ASSESSMENT
6.1 Introduction
The electrical output of a solar power plant is dependent on the incident solar radiation
it receives. Outside the Earths atmosphere, on a surface normal to the solar beam, the
power density is 1,365 W/m2, which is known as Solar Constant. As the solar radiation
passes through the atmosphere, depending on the length of the atmospheric path
traversed by the solar radiation and the quantity of dust, water vapour, ozone, CO2 and
other aerosols/gases present, some amount of it is scattered and absorbed. The diffused
radiation plus the direct irradiance from the sun are together termed as Global
Irradiance. The diffused sunlight can vary from about 20% on a clear day to 100% in
heavily overcast conditions. The peak irradiance of 1,000 W/m2 is taken as the standard
value in the industry by which PV modules are rated. However, the total solar energy
received in a day over a specific area, called daily solar irradiance or insolation, is more
important than the instantaneous solar irradiance. The solar resource is not equally
available in all regions of the world hence a site specific solar resource assessment is
required for every project.
6.2 Indias Solar Radiation Profile
India being a tropical country is blessed with good sunshine over most parts, and the
number of clear sunny days in a year also being quite high. The country receives solar
energy equivalent to more than 5,000 trillion kWh per year. Indias equivalent solar
energy potential is about 6,000 million GWh of energy per year. Being a tropical country,
India is blessed with good sunshine over most parts, and the number of clear sunny days
in a year also being quite high.
The daily average global radiation is around 5.0 kWh/m2in north-eastern and hilly areas
to about 7.0 kWh/m2in western regions and cold desert areas with the sunshine hours
ranging between 2300 and 3200 per year. In most parts of India, clear sunny weather is
experienced for 250 to 300 days a year. The annual global radiation varies from 1600 to
2200 kWh/m2. Following figure presents the global solar radiation map of India jointly
developed by MNRE and NREL.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
39/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 39of 111
Figure 3 Solar Resource Map of India
6.3 Radiation Profile of the Site
Solar radiation data can be collected from many sources like NASA-SSE, 3 Tier,
SolarGIS, and Meteonorm. Meteonorm data is considered for this project since it uses
both satellite as well as weather station data nearest to the site, while other data sources
employ only satellite derived data.
METEONORM database contains the TMY files of solar and climatic parameters for
several Indian locations based on measured as well as estimated values. The software
provides a facility to interpolate the solar and meteorological data for any location through
geographical parameters.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
40/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 40of 111
Average horizontal solar radiation at the site comes out to be 5.41 kWh/m2/day as per
meteonorm data. Monthly averages of the same data are given as follows:
Table 1: Solar Insolation, temperature and wind speed data for the site
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
41/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 41of 111
7. SELECTION OF TECHNOLOGY
Photovoltaic comprises the technology to convert sunlight directly into electricity. The
term photo means light and voltaic, electricity. A photovoltaic (PV) cell, also known assolar cell, is a semiconductor device that generates electricity when light falls on it.
Since its first commercial use in powering orbital satellites of the US space programs in
the 1950s, PV has made significant progress with total photovoltaic module industry
growing at more than 40% in the past decade.
The PV modules combined with a set of additional application-dependent system
components (e.g. inverters, batteries, electrical components, and mounting systems),
form a PV system. These PV systems are highly modular, i.e. modules can be linked
together to provide power ranging from a few watts to tens of megawatts (MW).
The solar PV panels typically produce DC electricity that is fed to a grid interactive
inverter, which in turn converts the DC electricity into AC electricity at a required voltage
level. In order to achieve a higher system voltage, the output of inverters is fed to step
up transformers to increase the voltage levels at the desired level. From the transformer,
the power is routed through the high voltage panel and eventually to other required
measuring & protection devices before connecting to the grid. The major equipment and
components of a typical solar plant are shown in the following figure.
Figure 4 Typical solar PV system components
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
42/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 42of 111
7.1 Photovoltaic technologies
Traditional solar cells are made from silicon, are usually flat-plate, and generally are the
most efficient. Second-generation solar cells are called thin-film solar cells because they
are made from amorphous silicon or non-silicon materials such as cadmium telluride.
Thin film solar cells use layers of semiconductor materials only a few micrometers thick.
Because of their flexibility, thin film solar cells can double as rooftop shingles and tiles,
building facades, or the glazing for skylights.
Third-generation solar cells are being made from variety of new materials besides silicon,
including solar inks using conventional printing press technologies, solar dyes, and
conductive plastics. Some new solar cells use plastic lenses or mirrors to concentrate
sunlight onto a very small piece of high efficiency PV material.
In spite of availability of all the technology, crystalline technology has maximum number
of installation world wise and has been demonstrated to perform in the field in excess of
30 years. In addition to this, the technologies are described concisely as follows:
7.1.1 Crystalline Technology
Typically, there are two types of crystalline technology mono-crystalline and multi-
crystalline. Both the technologies are made up of silicon material and have some pros
and cons. Basic features of individual technology are as follows.
Mono-Crystalline Silicon
Mono-crystalline Silicon has a continuous crystal lattice structure with practically zero
defects or impurities. Mono-crystalline Silicon is superior to other types of silicon cells in
terms of higher efficiencies which are typically around 18-23%. However, the mono
crystalline Si-cell production is an expensive process when compared to other types of
PV cells. Mono-Crystalline panels are mostly considered where the space is limited as
in the case of rooftops. The lifespan of mono-crystalline cells is a minimum of 25 years
and can go more, making them a worthwhile investment for long-term use.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
43/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 43of 111
Figure 5 Mono-Crystalline Silicon
Module
Figure 6 Multi-Crystalline Silicon
Module
Multi-Crystalline Silicon
Multi-crystalline (or poly-crystal) silicon panels are made by using polycrystalline wafers.
Multi crystalline wafers consists of number of crystallites with different grain sizes will be
having grain boundaries and several defects. Multi-crystalline Si growth is relatively
cheaper than the mono crystalline Si and the cells made up of these wafers are relatively
cheaper. Due to the less pure crystals, the efficiency of these cells reduces and the
module efficiencies typically range in between 14-16%. The lifetime of these modules is
also around 25 years or more and these panels are cheaper option where the space is
not a limitation. These panels are commonly preferred ones for grid connected
applications.
7.1.2 Thin Film Technology
Thin film modules are potentially cheaper to manufacture than crystalline cells have a
wider customer appeal as design elements due to their homogeneous appearance
present. Disadvantages include low-conversion efficiencies and requiring larger areas of
PV arrays and more material (cables, support structures) to produce the same amount
of electricity.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
44/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 44of 111
Figure 7 Thin film PV module
Material costs and manufacturing costs are lower per unit area as compared to those of
crystalline silicon cells.
7.1.3 Comparison of Major PV Technologies:
Table 2 Technology Comparisons
S. No. Parameter Crystalline Thin Film
1) Types of Materials Poly-crystalline, mono-
crystalline silicon
Amorphous Silicon, CdS, CdTe,
CIS/ CIGS, etc.
2) Handling Better protection against
breakage
Need extra care
3) Power Efficiency 13-21.5% 7-13%
4) Technology Well Developed Well Developed
5) Module Weight Light weight modules (0.1Kg/W) Slightly heavy modules (0.17
Kg/W)
6) Area utilization Higher power generated Less power per unit area
7) Temperature Effects Highest impact of Temperature
variations
Lesser impact of Temperature
variations
8) Irradiance Used particularly for Normal
radiations
Better performance with Diffuse
radiations
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
45/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 45of 111
General Comparison of thin-film technologies
S. No. a-Si CdTe CIS/CIGS
1) a-Si suffer significant
initial degradation in
power output when
exposed to the sun
Lesser degradation Lesser degradation
9) Module quantity Lesser quantity required Higher quantity required
10) Output per MW
installed
High Higher
11) Land Requirement Lesser space required per MW Larger space requirement
12) Cost Comparable cost per Watt Comparable cost per Watt
13) Environment Effects Less Sensitive Sensitive
14) Stabilization Stable power output at initial
stages
Stability achieved after 1-2
months
15) Availability Easily available Easily available
16) Power Degradation Less degradation Slightly higher degradation
17) Plant Maintenance Less maintenance required after
installation so lower cost
High maintenance required, so
high maintenance cost
18) Repair Relatively easy Easy
19) Cooling Requirement Required Not required
20) Cabling Easy installation Easy installation
21) Suitability for Grid
Tech.
Good Good
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
46/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 46of 111
2) Overall efficiency around
6-8%
Overall efficiency around
8-11%
Overall efficiency 9-13%
3) a-Si thin film modules
comprised about 31% ofthin film market and 4.4%
of global PV market in
2012
CdTe comprised 44% of
thin film market andabout 6.2% of the global
PV market in 2012
CIGS comprised 24% of
thin film market andabout 3.3% of the global
PV market in 2012
4) Spectral Sensitivity
towards short wavelength
CdTe absorbs medium
wavelengths
CIS/CIGS also absorbs
medium wavelength
7.2 PV Technology Recommendation
Each of the above technologies has their own particular strengths and limitations. Multi
crystalline silicon photovoltaic technology is recommended for the project on the grounds
of easy availability, cost effectiveness and technological stability.
7.3 Balance of Plant Systems (BoS)
On an average, BoS constitutes 40-45 % of the total project cost of a solar PV Project.For a solar PV Plant, the BoS comprises of inverters, cables, mounting structures,
foundations and power electronics. Often assigned secondary importance irrespective
of their being a significant cost component, BoS are critical determinants of the actual
plant life. High technical standards of BoS components should therefore be ensured as
a matter of standard practice.
7.4 Inverter Technologies
Solar inverter is a critical component in the solar energy system. It performs the
conversion of the variable DC power output of array (string of the Photovoltaic (PV)
modules) into a utility frequency AC power, which can be fed into the commercial
electrical grid. There are mainly two category of solar inverters are available central, and
string. A central inverter is generally for adopted for MW scale plant and string inverter
can handle comparatively less power.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
47/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 47of 111
Inverter is the heart of a solar power project. It is also known as Power Conditioning Unit
(PCU). A PCU consists of an electronic Inverter along with associated control, protection
and data logging devices. Typically the utility scale inverters are unidirectional and supply
the power to the grid in the form of AC power conforming to IEC 61727 or equivalent
standard. The inverter has a feature that it automatically adjusts with the grid conditions
such as the voltage & frequency levels to suit the Grid. It is advised that following key
points can be considered while specifying your inverter requirements to various vendors.
a) Proven Technology: The inverter should be selected based on the proven
technology and it is advisable that the inverter has completed at least one year
successful operation in the high temperature weather conditions and fluctuating grid
conditions.
b) Grid Compliance:At times you may require changing some of the key parameters
of the inverters to match with your local grid conditions, hence the inverter should
have features of changing some of the threshold parameters, and it can be
programmed accordingly. It should also have features of grid islanding through Air
Circuit Breakers. Some of the new generation inverters have provision of self
protective and self diagnostic features so that it can protect itself from the PV array
faults and adjust with the changing parameters of the solar PV array. The Inverter
should have provisions of automatically wake up in the morning and begin to export
power provided there is sufficient solar energy and the grid voltage and frequency is
in range.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
48/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 48of 111
The inverter should have MPPT control algorithm in such a way that it adjust itself
with the voltage of the SPV array to optimize solar energy fed into the grid. The MPPT
must have provision for constant voltage operation. The inverter MPPT feature
should comply with EN50530 or Equivalent standard.
The inverter output always follows the grid in terms of voltage and frequency. This
should be achieved by sensing the grid voltage and phase and feeding this
information to the feedback loop of the inverter. Thus control variable then controls
the output voltage and frequency of the inverter, so that inverter is always
synchronized with the grid.
c) Inverter Efficiency:The efficiency of the inverter is another key factor, and most of
the inverters are available in the efficiency range of about 97-98% efficiency levels.
However it is important to make a note of the inverter efficiency at the part load
conditions. Typically the part load efficiency levels are more than 97 % at 75% load
as per IEC 61683 or equivalent standard. It is important to assess the inverter
efficiency levels at different load say 25%, 50%, 75% and 100% and it should meet
the IEC 61683 standard.
d) Control and Protection:The inverter should have internal protection arrangement
against any sustained fault in the feeder line and against lightning in the feeder line.
It should also have the required protection arrangements against earth leakage faults.
The inverter should also have suitable rated DC disconnecting arrangement to allow
safe start up and shut down of the system. Inverter should also have required
protection arrangements against reverse polarity of DC Connection. There should be
suitable surge protection arrangement to pass the fault current to earthingsystem. During the earth fault condition, the inverter should be having provision of
disconnection.
e) Operational Flexibility: The inverter should have provision of parallel operation.
Generally two inverters are connected to a single 3 winding transformer, the inverter
should have flexibility to work in such combinations. The inverter should have feature
of ON and OFF automatically based on solar radiation variations during the day.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
49/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 49of 111
The inverter should have suitable display panels so that all important parameters
such as DC input voltage, DC input current, all phase to phase AC voltages , all phase
AC current, AC output power, frequency , apparent power , reactive power etc are
visible to the plant operators. Some of the inverters come with a suitable PCU with
display, and can be connected to the SCADA system.
During the sleep mode the inverter should be having the automatic control provisions
so that the threshold dc voltage of the inverter can decide the inverter to enter in
sleep mode and back to standby mode. The inverter must also automatically re-enter
standby mode when threshold of standby mode.
The standard warranty of these inverters is 5 to 10 years. However many inverter
manufacturer offer extended warranty also considering string inverter is a costlier
proposition as compared to a central inverter, however an apple to apple comparison
can only be made consideration of not only cost per watt of string versus central, but
also cost reduction of DC cables and other associated benefits such as reduced down
time in case of string inverter.
The central inverter takes input from number of arrays and operates at single MPP.
Hence the inverter MPP (maximum power point) is governed by the arrays which are
having partial shading ,mismatch losses , modules with tolerances which may lead to
reduce output in case of central inverter. However this can be reduced by selection
of string inverter as different strings have different MPP so that the output is
maximized.
7.5 Cabling
a) DC Cables and Connectors: Working with solar PV arrays can be hazardous since
Solar panels connected together in an array are often configured to produce high DC
voltage. Furthermore, DC voltages are constant in nature so, effect of electric shock
due to DC voltage will surely be severe. Hence, DC Cables should be double
insulated and polarized and DC connectors should always be used. The minimum
technical requirements for Cables laid down by MNRE states that they should
conform to General Test and Measuring Method PVC insulated cables for working
voltage up to and including 1100 V and UV resistant for outdoor installation
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
50/111
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
51/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 51of 111
including Module Mounting Structures shall have to be adequately protected from
atmosphere and weather prevailing in the area.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
52/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 52of 111
8. PROJECT REGISTRATION AND CLEARANCES
8.1 Project Registration/ Clearances
Following clearances would be required for the envisaged project:
A) Permits and Clearances
The Government of India at the central level and the state governments at the local level
have established legal, policy guidelines and regulatory frameworks for setting up of non-
conventional energy based power projects. Accordingly, certain clearances and
approvals are required to be obtained from different Government Bodies and Statutory
Agencies at various stages of development and operation phases of the project. These
clearances are classified into two broad categories known as statutory and non-statutory
clearances.
a) Statutory Clearances
Statutory Clearances mainly comprise water supply agreement from state government,
consent for establishment from State Pollution Control Board (SPCB), environmental
clearances from MOEF, forest clearances from state forest department and MOEF,
company registration through registrar of company, rehabilitation and resettlement of
displaced families on account of land acquisition from state/central government etc.
MOEF clearance is not applicable for the project. Forest clearance is also not applicable
as forest land is not considered for the project. The land identified for the project is free
of any inhabitation and is being directly purchased from the owners; hence there are no
R&R issues. However the agricultural land needs to be converted for non-agricultural
use.
b) Non-Statutory Clearances
The Non-Statutory Clearances mainly comprise land availability from state government
and clearance for National Monuments from Archaeological Survey of India (ASI) / Govt.
of India etc. There is no national monument in the identified land for the project.
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
53/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 53of 111
c) Other Clearances
Sanction of construction power from the office of Chief Engineer of the respective state
Electricity Utility and permission to use ground water if applicable.
Table 3: List of Clearances required for PV Projects in Rajasthan
S.No. ItemsResponsible
AgencyTentative
Date
1 Nodal Agency registration RRECL Zero
2 Bid Evaluation Committee RRECL Zero + 10
3 Registration certificate for plots
Between Seller
& Buyer Zero + 20
4 State Level Screening Committee Approval RRECL Zero + 25
5
Consent from local panchayat for development of
project site Panchayat Zero + 30
6 Approval for Connectivity Diagram RVPNL Zero + 45
7
Distribution Company/ Local agency Supervision
Application and payment for Sub Station RVPNL Zero + 60
8 Approval of Approach Route for Transmission Line RVPNL Zero + 75
9 Transmission line permits Energy Minister Zero + 75
10 Allotment of Bay RVPNL Zero + 75
11 Power Purchase Agreement Local Discom Zero + 75
12 Metering Approval Local Discom Zero + 75
13 REC Accreditation RRECL Zero + 90
14 Non Agricultural Certification for land approval
District Collector
Office Zero + 90
15 Meter, CT PT testing and inspection certificates RDPPC Zero + 100
16 Consent to Establish (Pollution Control Board) PCB Zero + 100
17
Chief Electrical Officer visit for approval on the
electrical layout of plantCEI Zero + 110
18 Approval for Interconnection RVPNL Zero + 110
19 Permission for Charging RDPPC Zero + 110
20 State Level Empowered Committee Approval RRECL Zero + 110
21 REC Registration NLDC Zero + 110
22
Certificate of Commissioning - Nodal Agency/ Local
Agency RRECL Zero + 120
23
Customs & Excise Duty Exemption/ MNRE
Certificates
MNRE &
RRECL
Ongoing
Basis
24 Consent to Operate (Pollution Control Board) PCB Zero + 150
-
8/10/2019 TGEPL_20MW_DPR_24.07.2014
54/111
20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL
Page 54of 111
9. POWER PLANT DESIGN CRITERIA
The Power Plant is sized on the following major criteria:
Solar Power (average insolation available)
Power evacuation facility in the vicinity of the proposed site along with grid
availability on 24 Hours a day basis.
Details of the design process and are presented in the below sections.
9.1 Design and Simulation projections by PVSYST
PVSYST tool is one of the most accepted design tool for the study, sizing, simulation
and data analysis of complete PV systems. We have used this tool to generate the most
realistic energy yield simulation results, which are detailed in this report. Main features
of PVSYST:
1. Detailed computation of the used components (modules, inverters, etc)
2. Simulation on hourly basis and detailed evaluation and consideration of different
loss factors.
3. Calculation of arbitrary orientated module planes (fixed and tracking systems)
4. Most accepted and used tool to generate simulation results for PV power plants,
as the results are based on systematic and refined approach.
5. Program with the most accurate results and functions available in the market.
9.2 PV Power Plant Energy Production
The system lifetime energy production is calculated by determining the first-year energygeneration as expressed in kWh (AC)/kWp (AC), and then degrading output over the
system life based on an annual performance degradation rate. System degradation
(largely a function of PV panel type and manufacturing