TGEPL_20MW_DPR_24.07.2014

download TGEPL_20MW_DPR_24.07.2014

of 111

Transcript of TGEPL_20MW_DPR_24.07.2014

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    1/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 1of 111

    Detailed Project Report

    20 MW (AC) SOLAR PV POWER PROJECT

    VillageThat, Tehsil-Pokharan, Distt- Jaisalmer, Rajasthan

    Date: 24.07.2014

    Prepared by:

    Gensol Consultants Pvt Ltd,

    108, Pinnacle Business Park,

    Corporate Road, Prahaladnagar,

    Ahmedabad, Gujarat-380015

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    2/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 2of 111

    Copyrigh t Protect ion Statement

    Copyright Gensol Consultants Pvt. Ltd. The reproduction or transmission of all or part of this

    work, whether by photocopying or storing in any medium by electronic means or otherwise

    without the written permission of Gensol Consultants Pvt. Ltd is prohibited, and the commission

    of any unauthorized acts in relation to the work may result in civil or criminal actions. The author

    asserts its moral right to be identified as the author of the work.

    Disclaimer Notice

    This document has been prepared for M/S Today Green Energy Pvt . Ltd . (the Client) only and

    solely for the purpose stated in the contract (the Contract) between Gensol Consultants Pvt Ltd

    (the Consultant) and the Client.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    3/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 3of 111

    Contents

    GLOSSARY .......................................................... ................................................................... .................................. 8

    ABBREVIATIONS .......................................................... .................................................................... .................... 10

    EXECUTIVE SUMMARY.................................................................... .................................................................. 12

    PROJECT AT A GLANCE .......... ................................................................... ....................................................... 16

    1. INTRODUCTION ................................................................ .................................................................. 18

    1.1ABOUT TODAY GREEN ENERGY PRIVATE LIMITED ORGANIZATION................................................................ 18

    1.2ABOUT PROJECT CONSULTANT.................................................................. ...................................................... 19

    1.3SCOPE OF SERVICES FOR DPR .............................................. ................................................................. .......... 20

    2. INDUSTRY OUTLOOK ........................................... ................................................................. ........... 21

    2.1BACKGROUND OF THE PROJECT....................................................... ................................................................ 21

    2.2OBJECTIVE AND BENEFITS OF THE PROJECT.................................... ................................................................. 21

    2.3GLOBAL AND INDIAN ENERGY SCENARIO............................ ................................................................... ........ 21

    2.4RAJASTHAN STATE ELECTRICITY SCENARIO............. .................................................................... ................... 23

    2.5RENEWABLE ENERGY POTENTIAL IN THE STATE.................................................................................... .......... 24

    2.6GROWTH IN DEMAND........................................................... ................................................................... ........ 25

    2.7SOLAR PVREACHING TOWARDS GRID PARITY.................... ................................................................. .......... 26

    3. INDIAN MARKET FOR SOLAR POWER ............................................................................. ........... 27

    3.1THENATIONAL SOLAR MISSION AND STATE POLICIES.................................................................................... 27

    4. JUSTIFICATION FOR THE PROJECT ............................................................ ................................ 32

    5. PROJECT SITE .......................................................................................... ........................................... 32

    5.1LOCATION AND ACCESSIBILITY........................................................................................ ............................... 32

    5.2RAINFALL AND CLIMATE................................................................................................ ................................. 35

    5.3LAND REQUIREMENT AND LAYOUT OF THE PROPOSED PROJECT..................................................................... 36

    6. SOLAR RESOURCE ASSESSMENT ................................................................ ................................. 38

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    4/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 4of 111

    6.1INTRODUCTION...................................................................................................... .......................................... 38

    6.2INDIAS SOLAR RADIATION PROFILE..................................................................... .......................................... 38

    6.3RADIATION PROFILE OF THE SITE.............................................................. ...................................................... 39

    7. SELECTION OF TECHNOLOGY ........................................................... ........................................... 41

    7.1PHOTOVOLTAIC TECHNOLOGIES...................................................... ................................................................ 42

    7.1.1CRYSTALLINE TECHNOLOGY.............................................................................. .......................................... 42

    7.1.2THIN FILM TECHNOLOGY.................................................. ................................................................. .......... 43

    7.1.3COMPARISON OF MAJOR PVTECHNOLOGIES: .............................. ................................................................ 44

    7.2PVTECHNOLOGY RECOMMENDATION........................................... ................................................................. 46

    7.3BALANCE OF PLANT SYSTEMS (BOS) ........................................................ ...................................................... 46

    7.4INVERTER TECHNOLOGIES......................................................................................................... ...................... 46

    7.5CABLING........................................................ ................................................................... ............................... 49

    7.6MODULE MOUNTING SYSTEM.............................................. ................................................................. .......... 50

    8. PROJECT REGISTRATION AND CLEARANCES ................................................................ ......... 52

    8.1PROJECT REGISTRATION/CLEARANCES........................................................................................................... 52

    9. POWER PLANT DESIGN CRITERIA .................................................................................... ........... 54

    9.1DESIGN AND SIMULATION PROJECTIONS BY PVSYST ........................................................................... .......... 54

    9.2PVPOWER PLANT ENERGY PRODUCTION............................ ................................................................... ........ 54

    9.3PVPOWER PLANT CAPACITY UTILIZATION FACTOR (CUF) ............................................... ............................... 55

    9.4SELECTION OF INVERTER AND COMPONENTS................................. ................................................................. 55

    9.5SELECTION OF MONITORING SYSTEM........................................................................................... ................... 55

    9.6DESIGN CRITERIA FOR CABLES AND JUNCTION BOXES................................................................ .................... 56

    10. MAJOR COMPONENTS OF THE POWER PLANT .............................................................. ......... 57

    10.1INTRODUCTION.................................................................................................... .......................................... 57

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    5/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 5of 111

    10.2SOLAR PVMODULES.......................................................... ................................................................... ........ 58

    10.3INVERTER........................................................................... ................................................................. .......... 59

    10.4MODULE MOUNTING SYSTEM............................................ ................................................................. .......... 61

    10.5MONITORING SYSTEM........................................................ ................................................................... ........ 62

    10.6CABLES AND CONNECTORS................................................ ................................................................. .......... 63

    10.7BUILDINGS FOR PLANT EQUIPMENT (INVERTER ROOMS AND CONTROL ROOM) ............................................ 64

    10.8OTHER FACILITIES INCLUDING WATER.............................. .................................................................. ......... 65

    11. POWER EVACUATION AND INTERFACING WITH GRID ........................................................ 66

    11.1POWER EVACUATION PLAN................................................................................. .......................................... 66

    11.2TRANSFORMERS.......................................... ................................................................... ............................... 66

    11.3132KVSWITCHYARD..................................................................................................... ............................... 67

    11.4HT,LV,33KVAND 132KVMETERING EQUIPMENT................................ ..................................................... 69

    11.5CABLES............................................ ................................................................... .......................................... 70

    11.6GRID SYNCHRONIZATION SCHEME.......................................................... ...................................................... 71

    12. ESTIMATION OF ANNUAL ENERGY YIELD ............................................................ .................... 72

    12.1INTRODUCTION.................................................................................................... .......................................... 72

    12.2ENERGY GENERATION ASSESSMENT................................ ................................................................... .......... 73

    13. OPERATION AND MAINTENANCE REQUIREMENTS ............................................................... 78

    13.1BASIC PLANT OPERATION........................... ................................................................... ............................... 78

    13.2MAINTENANCE REQUIREMENTS....................................... ................................................................... .......... 79

    13.3SPARE PARTS MANAGEMENT SYSTEM................................................................. .......................................... 80

    13.4O&MMANUALS................................................................................................ .......................................... 80

    13.5OPERATION &MAINTENANCE ORGANIZATION OF THE PLANT....................................... ............................... 81

    14. PROJECT IMPLEMENTATION STRATEGY .......................... ....................................................... 83

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    6/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 6of 111

    14.1PROJECT PHASES................................................................ ................................................................. .......... 83

    14.2PROJECT REGISTRATION AND FINANCING............................................................ .......................................... 83

    14.3FINALIZATION OF THE EQUIPMENT AND CONTRACTS.......................................... .......................................... 83

    14.4PROCUREMENT AND CONSTRUCTION............................................................................................................. 84

    14.5ERECTION AND COMMISSIONING PHASE................................................................................................ ........ 84

    15. RISK ASSESSMENT AND MITIGATION ........................................................................................ 86

    15.1 PROJECT COMPLETION RISK MEDIUM/LOW......................................................................... ...................... 86

    15.2TECHNOLOGY RISK

    LOW............................................................ ................................................................ 86

    15.3COST OVER-RUN RISK -LOW.................................. ................................................................. ...................... 87

    15.4GENERATION ASSURANCE MEDIUM............................................................................. ............................... 88

    15.5FORCE MAJEURE RISK LOW.............................................................................. .......................................... 88

    15.6OPERATING RISK LOW.......................................................................................................... ...................... 88

    15.7PLANT PERFORMANCE RISK MEDIUM................................................................................................ ......... 89

    16. PROJECT COST ESTIMATE AND FINANCIAL ANALYSIS ....................................................... 90

    16.1PROJECT COST..................................................................................................... .......................................... 90

    16.2SALEABLE ELECTRICITY.......................................................................................................... ...................... 91

    17. LIST OF SUPPLIERS .......................................................... ................................................................. 92

    ANNEXURE-I : ENERGY SIMULATION REPORT (10 MW BLOCK) .............. ........................................... 94

    ANNEXURE-II: MODULE DATASHEET ................................................................ ........................................... 97

    ANNEXURE-III: INVERTER DATASHEET ............................................................................................. ......... 99

    ANNEXURE-IV: PROJECT SCHEDULE ........ ................................................................... .............................. 105

    ANNEXURE-V: SLD- 20 MW PLANT ................................................................................. .............................. 110

    ANNEXURE-VI: SLD- 50 MW PLANT ......................................................... ..................................................... 111

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    7/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 7of 111

    List of Figures

    Figure 1: Seismic zone of India.................................................................................................................. ........... 33

    Figure 2 Location of site.............................................................................................. ........................................... 34

    Figure 3 Solar Resource Map of India............................................... .................................................................. 39

    Figure 4 Typical solar PV system components................................................................................................... 41

    Figure 5 Mono-Crystalline Silicon Module....................................................................................... .................... 43

    Figure 6 Multi-Crystalline Silicon Module................................ ................................................................. ........... 43

    Figure 7 Thin film PV module......................................................................... ....................................................... 44

    Figure 8 Block diagram showing interconnection of various systems............................................................. 58

    Figure 9 Typical photovoltaic solar module ..................................................................................... .................... 59

    Figure 10 Typical Solar Inverter............................................................................................ ................................ 60

    Figure 11 Typical Fixed tilt module mounting structure..................................................................................... 61

    Figure 12 Typical Control Room Section............................................................................. ................................ 65

    Figure 13 Tilt angle optimization snapshot from PVsyst............................ ....................................................... 73

    Figure 14 Sun path for the proposed location..................................................................................................... 74

    Figure 15: Organizational Chart............................................................................................ ................................ 82

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    8/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 8of 111

    GLOSSARY

    Photovoltaic The physical effect of direct Conversion of light (sunlight)to electrical energy

    PV CellThe smallest photovoltaic (PV) element that generateselectricity from light

    PV Module

    A collection of interconnected PV cells, encapsulatedbetween protective materials such as glass and backsheet (Poly Vinyl Fluoride) or glass and glass, andmounted in an aluminum frame. This is a hermeticallysealed unit

    ArraySeveral strings of modules with the same orientation andtilt angle, located together

    InverterAn electronic device that converts direct current electricityinto alternating current electricity suitable for feedingdirectly to the electrical grid or to normal AC loads

    Insolation

    It is a measure of solar radiation energy received on agiven surface area in a given time. It is commonlyexpressed as average irradiance in watts per square

    meter (W/m) or kilowatt-hours per square meter per day(kWh/ (mday)) (or hours/day)

    Mounting StructureDevice used to hold modules in place, at desired angle &direction

    Power EvacuationPower generated from Solar PV Power Plant istransmitted to a point (sub-station) where it is distributedfor consumer use

    Sub-station

    The place where the generated power from solar is

    synchronized with utility grid and metered

    Control Room Room housing control equipment

    CableA conductor with one or more strands bound together,used for transmitting electrical energy

    Junction BoxInputs of several strings are connected to this box andtaken as single output

    CurrentA flow of electricity through a conductor measured in

    Amps

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    9/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 9of 111

    Voltage

    The rate at which energy is drawn from a source thatproduces a flow of electricity in a circuit; expressed in volts.It is the difference of electrical potential between twopoints of an electrical or electronic circuit, expressed in

    volts. It is the measurement of the potential for an electricfield to cause an electric current in an electrical conductor

    Lightning ArrestorDevice used to protect all the components from lightningstrikes

    TransformerAn electrical device by which alternating current of onevoltage is changed to another voltage

    GridA system of high/low tension cables by which electricalpower is distributed throughout a region

    SCADA

    Instrumentation & Control system for the solar power plantused to detect malfunctions and give information at a giventime interval about the availability and performance of theplant

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    10/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 10of 111

    ABBREVIATIONS

    General

    ACB Air Circuit Breaker

    AC Alternate current

    ACSR Aluminum Conductors Steel Reinforced

    BOS Balance of the System

    CO2 Carbon Dioxide

    CT Current Transformer

    DC Direct Current

    DP Double Pole

    DPR Detailed Project Report

    HT High Tension

    LT Low Tension

    LV Low Voltage

    MNRE Ministry of New and Renewable Energy

    SECI Solar Energy Corporation Of India

    KWh Kilo Watt Hour

    MCB Main Combiner Box / Miniature Circuit Breaker

    PLF/ CUF Plant Load Factor/ Capacity utilization factor

    PPA Power Purchase Agreement

    PV Photo Voltaic

    PT Power Transformer

    VCB Vacuum Circuit Breaker

    XLPE Cross Linked Polyethylene

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    11/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 11of 111

    Units

    % Percentage

    C Degree Centigrade

    Kg Kilogram

    kV Kilo-Volt

    kW kilo Watt

    kWp kilo Watt peak

    Lt Liter

    M Meter

    m2 Square meter

    m3 Cubic meter

    Tons Tons

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    12/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 12of 111

    EXECUTIVE SUMMARY

    Today Green Energy Private Limited (TGEPL) is a SPV company promoted by Today

    Homes & Infrastructure Private Limited (THIPL), a Group Today Company planning toput up large scale Solar power projects at strategic locations suitable for Solar power

    generation across India.

    THIPL, is a well-established enterprise in the field of Real Estate Development with a

    number of Residential, Retail and Commercial projects Delivered and Under

    Development. Apart from real estate the THIPL is also in the business of Hospitality.

    Over a period of next 5 years, the Company is committed to set up facilities to generatemore than 5000 MW of power, coal-based and renewable sources. The expansion will

    be fuelled by setting up Greenfield projects as well as expansion in existing power plants.

    THIPL has been declared as a successful bidder in the bid process against the Rfs No

    SECI/JNNSM/SPV/P-2/B-1/Rfs/102013 issued by Solar Energy Corporation of India

    (SECI) and had been issued Letter of Intents.

    THIPL has formed a Project Company TGEPL for the development of Solar PowerProjects. In this regards, TGEPL is going to install a 20 MW (2x10MW) solar PV plant,

    under the Open Category, at village That, situated in Jaisalmer district of Rajasthan state.

    The geographical location of the project site is 26.840544 N and 71.818534 E. For the

    proposed project approx. 115 acres of the land will be required.

    Radiation profile of the location has been assessed using the industry standard

    Meteonorm software and the electricity generation has been estimated. 255 Wp (or

    higher) capacity poly-crystalline technology based PV modules are suggested for the

    proposed solar plant. The basis of selection of poly-crystalline technology is its financial

    competitiveness, long term stability and easy availability. Further, on the basis of basic

    design engineering, 1000 kW solar inverter units are proposed and 20 nos. of inverters

    shall be required for the plant. This project shall be using fixed tilt module mounting

    structures for the installation of PV modules. With such arrangement, it is projected that

    the proposed 20 MW project will operate at a CUF around 22.29% and will be generating

    around 39, 048,487 kWh units per year. Probability analysis has also been presented inthe DPR at the P50, P75 and P90 probability level.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    13/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 13of 111

    The generated electricity from the solar PV plant will be evacuated in the dedicated 132

    kV grid substation situated 12 kms from the project site. TGEPL has signed a PPA at flat

    rate of Rs. 5.45/ kWh for life time of the project, which is considered as 25 years, with

    Solar Energy Corporation of India (SECI).

    The project cost of the envisaged 20 MW (AC) PV Plant is estimated to be Rs. 15070

    Lakhs. Debt equity ratio of the investment is 70:30 and debt equity amount for this ratio

    is Rs. 10549 lakhs and Rs. 4521 lakhs respectively. The project will receive VGF funding

    to the tune of Rs. 2190 lakhs. Furthermore, considering the financial analysis, it is

    projected that investment in the proposed project will give a project IRR of 11.81%.

    Average Debt Service Coverage Ratio (ADSCR) of the proposed investment is worked

    out to be 1.45.

    Apart from the financial benefits the solar power plant also helps to reduce the release

    of carbondioxide produced by fossil fuel generation. The project converts solar radiation

    into useful electricity, adding to sustainability of the project and the local environment.

    Besides all these concerns, this report highlights the details of the proposed power

    generation scheme, site facilities, solar radiation in the proposed site location and water,

    evacuation of generated power, features of main plant and equipment including the

    inverter system, electrical systems, environmental aspects, estimate of capital cost and

    the financial analysis and the schedule for project implementation.

    Group Company Today Homes & Infrastructure Pvt. Ltd. (THIPL) located at Delhi is

    a well established enterprise in the field of Real Estate Development and Hospitality with

    numbers ofResidential, Retail and Commercialprojects already developed and the rest

    are under development.

    Further in 2007 Today Homes & Infrastructure Pvt. Ltd. (THIPL) has diversified in

    the Power Sector and form a company Today Energy (MP) Pvt Ltd.(TEMPPL)

    promoted by Today Homes & Infrastructure Pvt Ltd.(THIPL) to set up 1320 MW

    (2x660 MW) coal based Thermal Power Plant (IPP) at village Silari, Tehsil Gotegaon,

    Dist. Narsinghpur, Madhya Pradesh. The details of the project is given below:

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    14/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 14of 111

    I) Land: Total land acquired is appox. 750 acres at Distt Narsinghpur in the State

    of Madhya Pradesh (M.P.), which is sufficient, as per CEA norms for 1320

    (2x660) MW coal based thermal Power Project with Supercritical technology.

    a) Private Landappox685.54 Acres of land in continuous stretch for the project

    has been purchased directly from the land owners through consent route and is

    in our possession.

    b) Government landof 64.15 Acres has been allocated vide GoMP Revenue

    Deptt. Order No. F16-41/2008/7/2A Bhopal dated 31.03.2011.

    No forest land is involved.

    II) Firm allocation of 40 cusec of waterhas been granted by Water Resource Dept.

    (WRD), GoMP.

    III) Coal:

    (A) Coal linkage for one unit of 660 MW has been tied up with the State of Madhya

    Pradesh.

    (B) In addition, Central Electricity Authority (CEA) Standing Committee hasrecommended the name of project company i.e. Today Energy (M.P.) Pvt Ltd

    (TEMPPL) with maximum marks i.e. 90 (ninety) to Ministry of Power (MoP)

    which has further recommended to Ministry of Coal (MoC). It is expected that

    long term coal linkage shall be allocated to TEMPPL by Long Term Linkage

    Committee shortly.

    IV) Environment Clearance: TOR was accorded by MOEF in September 2007.

    Public hearing committee meeting was conducted on 19.06.2009 by M.P.

    Pollution Control Board. EIA report was submitted through M.P. Pollution Control

    Board to Expert Appraisal Committee (EAC) of MOEF and put up in their 65 th

    meeting on 13.02.2010. In absence of firm fuel linkage to the project, proposal

    was deferred till fuel tie up. Long term coal linkage for one unit of 660 MW has

    been tied up with the State of Madhya Pradesh. We have again taken up the

    proposal with EAC of MOEF for issuance of EC to the project.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    15/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 15of 111

    V) International Competitive BiddingCorrigendum issued on 11.05.2011 to earlier

    International Competitive Bidding (ICB) Notice Inviting Tender NIT-ICB wherein

    leading international/national manufacturer of BTG participated in the bid. Initial

    round of technical discussion have completed and final techno commercial

    negotiations are in progress.

    VI) Rail Transport Clearance from Ministry of Railway (Railway Board) was

    accorded for establishing railway siding at the Project Site.

    VII) Open AccessThe Bulk Power Transmission Agreement for 800 MW entered

    into with Power Grid Corporation of India Ltd.

    VIII) Chimney Height Clearance fromAirports Authority of India has been accorded.

    IX) Defence Clearance has been obtained from Defence Estate Office, Jabalpur

    Circle.

    X) Fly Ash Utilization

    a) MOU already signed with M/s ACC Ltd. for collection of 2000 MT of fly ash perday.

    b) MOU signed with M/s Vikas Concrete Industries, Jabalpur for collection of 1000

    MT of fly ash per day.

    XI) Power Evacuation:In the past few years there was no procurement inspite of big

    demand supply gap from various State Utilities because of the financial

    constraints. The Central Government has approved a big financial package to

    carry out the financial restructuring of the State Utilities. This has resulted into the

    starting of the power procurement by such Utilities to meet their deficiency in

    power. Recent bids have been in the range of Rs. 4/-kWh to Rs. 5/-kWh. Since

    the fuel has been tied up, we are contemplating to participate in the various power

    purchase bids being invited by various state Utilities. Some of them are already in

    pipeline.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    16/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 16of 111

    PROJECT AT A GLANCE

    Project Developer Today Green Energy Pvt Ltd.

    (TGEPL)

    Project Installed Capacity 23 MWp (DC), 20 MW (AC) SolarPhotovoltaic Power Plant

    Selected Location Village: That ; Tehsil: Pokharan;District-Jaisalmer, Rajasthan

    Site Co-ordinates 26.840544 N and 71.818534 E

    Global Horizontal Irradiation 1974.7 kWh/m2

    Tariff details Rs. 5.45 for 25 years

    Annual degradation 1%

    Nearest Major Towns Pokharan, Phalodi, Jaisalmer,Jodhpur

    Solar module type Poly Crystalline

    Capacity of each module 255 Wp

    No. of modules 90,192 (2x10 MWacplant)

    PV System Mounting Structure type MS Galvanised

    Power conditioning Unit (Inverters)capacity

    1000 kW

    Power conditioning Unit specifications Input voltage range 600850 V

    No. of inverters 20 Nos.

    Inverters make ABB

    Capacity Utilisation Factor 22.29 %

    Expected Generation(after 1styear ofoperation)

    39,048,487 kWh

    Total Project cost (Rs in lakhs) 15070

    Equity from Promoters (Rs. in lakhs) 4521

    Term loan from Financial Institutions (Rs.in lacs) 10549

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    17/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 17of 111

    VGF Funding (Rs. in lacs) 2190

    Project IRR 11.81%

    Equity IRR 14.01%

    Land 115 acres approx

    Power Evacuation 132 kV Grid substation at Pokharan

    Mode of Implementation By EPC (Engineering, Procurementand Construction)

    Project Time Frame Seven (7) months

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    18/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 18of 111

    1. INTRODUCTION

    This report is referred to as the Detailed Project Report for installation of 20 MW (AC)

    Photovoltaic (PV) Plant at village That, Tehsil Pokharan, District Jaisalmer, Rajasthan(Project Site or Site). The report is prepared by Gensol Consultants Private Limited

    having been appointed as the Project Consultant for the client with the intention to

    provide a detailed project pre-feasibility analysis and advisory. This report includes the

    feasibility studies, system design and techno-commercial analysis for installation of the

    PV plant.

    1.1 About Today Green Energy Private Limited Organization

    Today Green Energy Private Limited. (TGEPL) is a company promoted by Today Homes

    & Infrastructure Private Limited, a Group Today Company planning to increase its energy

    portfolio in the renewable energy sector in India.

    Today Homes & Infrastructure Pvt Ltd.is a well established enterprise in the field of Real

    Estate Development with a number of Residential, Retail and Commercial projects

    Delivered and Under Development. Apart from real estate the Group Today is also in the

    business of Hospitality.

    Over a period of next 5 years, the Company is committed to set up facilities to generate

    more than 5000 MW of power, largely coal-based. The expansion will be fuelled by

    setting up Greenfield projects as well as extension in existing power plants. Discussions

    at various levels with concerned authorities are already in progress.

    The power projects are planned to be diverse in geographic location, fuel type, fuel

    source & off take, and each project is planned to be strategically located near an

    available fuel supply load center.

    Power generated from these units will be sold under the combination of long term and

    short term PPAs to state owned/private distribution companies and industrial consumers.

    Discussions are already in progress.

    http://www.todayhomes.co.in/http://www.todayhomes.co.in/
  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    19/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 19of 111

    1.2 About Project Consultant

    Gensol Consultants Pvt. Ltd. founded in March 2007 was setup as a 360o Carbon

    Solution Provider having expertise in generation, registration and trading of Certified as

    well as Verified Emission Reductions (CERs and VERs), better known as carbon credits.

    In the past 4 years, Gensol has spread its area of expertise from providing consultancy

    for Clean Development Mechanism (CDM) to technical-commercial advisory services for

    the setup and expansion of energy infrastructure, thus providing them with a complete

    package to grow and benefit from our expertise and assistance. Having an early entry

    advantage along with a creative and dedicated team, Gensol Consultants Pvt. Ltd. is

    built on one of the most innovative, client friendly and revenue boosting models.

    Consequently, the company boasts of handling numerous projects across the length and

    breadth of the country with over 10 million Emission Reductions in the first commitment

    period and more than 800MW of solar PV advisory projects already under its wing.

    Gensol Solar Division, set up in early months of 2009 is dedicated to using technology,

    engineering and innovation to give its clients the best returns on their capital. It is with

    this view that we strive to provide support and engineering expertise to clients and

    investors in Solar Power Sector through our offerings of complete concept to

    commissioning advisory services for MW scale grid-connected and off grid standalone

    solar power projects. Gensol Solar Team boasts of years of on-ground experience in

    setting up of Solar Power Plants. Comprising of Electrical, Civil and Mechanical

    Engineers on one hand and Financial and Regulatory Consultants on the other, Gensol

    Solar team presents a unique blend of technological expertise with market intelligence,

    thus, helping us provide a 360operspective to clients.

    Gensol Consultants is empanelled with various lending institutions and Ministry of New

    and Renewable Energy. Gensol also hold the distinction of representing Ministry of

    Environment and Forestry (MoEF) at International Forums.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    20/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 20of 111

    1.3 Scope of Services for DPR

    The scope of work for the DPR includes all details concerning the feasibility, design, and

    financial viability of the project.

    The Report has the following main contents:

    Site assessment

    Solar radiation resource assessment

    Solar PV technology assessmentand evaluation

    Annual Yield estimation

    SPV Plant layout

    Overall System description

    Power evacuation arrangements and single line diagram (SLD)

    Clearances and permits

    Financial analysis

    Risk Assessment

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    21/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 21of 111

    2. INDUSTRY OUTLOOK

    2.1 Background of the project

    THIPL had participated in the JNNSM Phase II Batch I solar bid conducted by Solar

    Energy Corporation of India (SECI). In the bid results THIPL has been allotted a total of

    5 PV projects of 10 MW capacity each. Out of this, 2 PV projects of 10 MW each i.e.

    20MW are under open category and 3 PV projects of 10 MW each i.e. 30MW are under

    the DCR category. THIPL has formed a Project Company TGEPL for the development

    of Solar Power Projects. This DPR is meant for Open category i.e. 20MW.TGEPL board

    has decided to install 2 x10 MW project capacity, near village That, Pokharan. Electricity

    sale arrangement has already been done by signing a long term PPA with SECI at Rs.

    5.45/ kWh for the 25 years.

    This project will be executed with an EPC (Engineering, Procurement and Construction)

    partner. TGEPL will invest 30% of the total project cost as equity investment and rest of

    the money which is 70% of the project cost shall be arranged from a financial institution

    as debt.

    2.2 Objective and benefits of the project

    The objective of the proposed solar power plant is to generate clean energy from the

    solar radiation using photovoltaic phenomenon. This energy will be evacuated to the

    nearby grid and further distributed in the electricity network. Solar energy is a clean

    source of electricity and produces no pollution. Hence, there are many social economic

    benefits are associate with the development of this project.

    2.3 Global and Indian Energy Scenario

    Electricity is one of the world's fastest-growing form of end-use energy consumption. Net

    electricity generation worldwide will rise by 2.3 percent per year on average from 2007

    to 2035 as compared to 1.4 percent per year growth for total world energy demand. The

    growth in electricity generation for non-OECD countries increases by an average annual

    rate of 3.3 percent, as rising standards of living increases the demand. In OECD nations,

    where infrastructures are more mature and population growth is relatively slow, growth

    in generation is much slower, averaging 1.1 percent per year from 2007 to 2035.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    22/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 22of 111

    Graph 1: World Electricity Consumption Projections

    The Indian government has set ambitious goals in the 11th plan for power sector owing

    to which the power sector is poised for significant expansion. It has been estimated that

    need-based capacity addition of more than 100,000 MW would be required. This has

    resulted in massive addition plans being proposed in the sub-sectors of Generation

    Transmission and Distribution.

    Graph 2: Indian Energy Scenario

    Thermal

    68%Nuclear

    2%

    Hydro 17%

    Solar

    13%

    Indian Energy Scenario

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    23/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 23of 111

    2.4 Rajasthan state electricity scenario

    Rajasthan state has total installed capacity or the order of 14059.12 MW. Thermal is

    leading source of energy with total installed capacity of 8454.75 MW. It is approximately

    60.13% of the total installed capacity. Second highest installed capacity is of Renewable

    energy source which is of the order of 3483.05 MW and hydro is of 1548.32 MW and

    remaining is from the nuclear is 573 MW.1

    Graph 3: Rajasthan Energy Scenario

    Furthermore, contribution of renewable energy sources in the total installed capacity is

    really astonishing and also generates hope for the renewable energy investors. Including

    Hydro capacity, total renewable energy capacity in the state is about 36% of the overall

    installed capacity.

    Now looking at energy demand and supply picture, in 2012-2013, energy requirement of

    Rajasthan state was 55538 MU and energy availability was only 53868 MU. There was

    around 3 % energy deficiency. Monthly records further showing the picture of the energy

    deficiency condition of the state. Maximum deficiency was 8.9 % in the month of June

    2012.2

    1http://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdf2http://www.cea.nic.in/reports/yearly/lgbr_report.pdf

    Thermal

    60%

    Nuclear

    4%

    Hydro

    11%

    RES 25%

    Energy Scenario of Rajasthan State

    http://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdfhttp://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdfhttp://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/yearly/lgbr_report.pdfhttp://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdf
  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    24/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 24of 111

    Graph 4: Energy Demand Vs Supply in Rajasthan

    Anticipated power deficit in the state is 15.1 %. This data clearly indicates that there is a

    huge demand of energy and electricity generated from solar PV plant can surly be

    consumed.

    2.5 Renewable Energy potential in the state

    Rajasthan is the state having almost all commercial renewable energy technology

    installed, whether it is wind mills, solar PV, Hydro, bio-mass etc. Moreover, the potential

    of the renewable energy generation is also promising. State has 35% renewable power

    installation out of total power. Major renewable energy sources in the state are wind and

    solar. Considering the data of Indian Wind Energy Association, Rajasthan has wind

    potential of the order of 5005 MW3.

    Sun is the most abundant natural source of energy available on the earth. Solar energycan either be used for the generation of electricity (photovoltaic energy) or for heating

    purposes (solar thermal energy). As solar electricity generation and other use of solar

    energy do not emit any GHG emission, it is treated as renewable energy source.

    3Centre for Wind Energy Technology (CWET): http://www.cwet.tn.nic.in/html/departments_wra.html

    3500

    3750

    4000

    4250

    4500

    4750

    5000

    5250

    5500

    5750

    6000

    EnergyinM

    U

    Energy Demand Vs Supply in Rajasthan StateRequirement (MU) Availability (MU)

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    25/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 25of 111

    2.6 Growth in Demand

    Despite the rapid growth in this decade, solar photovoltaic is a young market. Thus the

    different industry forecasters have different sizes even for the existing market, let alone

    their forecasts in the longer term. The European Photovoltaic Industry Association

    (EPIA) has comprehensive long-term forecasts for the photovoltaic industry. Its forecasts

    have been much more cautious than the break-neck speed of industry growth in the last

    2-3 years; however, there is every possibility that the much higher results in comparison

    to forecasts over the last few years will result in over-estimation of the market.

    Globally, the solar power industry has been growing rapidly in recent years. In 2010, an

    estimated total capacity of 17,000 MW was installed globally. Germany leads the racewith more than 40 percent of the total global market.

    The three leading countries (Germany, Japan and the US) represent nearly 89% of the

    total worldwide PV installed capacity. Currently, around 84% of solar industry demand is

    located in four countries where governments have actively promoted its development

    through favorable regulation: Germany, Japan, Spain and the US in selected states.

    Spain was one of the fastest growing markets in 2008 owing to very favorable legislation

    and attractive feed-in tariffs. In 2008, Spain accounted for 45% of the new photovoltaic

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    26/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 26of 111

    installments. However in 2009, Spain market reduced considerably due to government

    policy change on the FIT.

    Going forward, the growth in Sunbelt countries is expected to increase considerably dueto the higher demand for power and better solar resource in these countries such as

    India, MENA, China, etc.

    2.7 Solar PV Reaching towards Grid Parity

    Grid parity is the point at which photovoltaic electricity is equal to or cheaper than grid

    power. This is achievable first in areas with abundant sun and high costs for electricity

    such as in California and Japan. For regions with subsidies for solar power generation,

    grid parity can be achieved much sooner. Costs of solar electricity are falling steeply

    through a combination of factors including better cell efficiency and improvements in

    solar manufacturing.

    As the PV system costs decrease, the geographies with higher solar radiation and high

    price of electricity will achieve grid parity at the earliest. For example, in Hawaii where

    the cost of electricity is high and there is also abundant solar radiation, PV has already

    reached grid parity with todays system costs. Italy also is a very prime region where PV

    will be at grid parity shortly.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    27/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 27of 111

    3. INDIAN MARKET FOR SOLAR POWER

    A Solar PV Project Developer can set up a solar power project in India in one of the

    following three ways:

    3.1 The National Solar Mission and State Policies

    The Jawaharlal Nehru National Solar Mission is a major initiative of the Government of

    India with active participation from States to promote ecologically sustainable growth

    while addressing Indias energy security challenge. It will also constitute a major

    contribution by India to the global effort to meet the challenges of climate change. Theobjective of the Mission is to establish India as a global leader in solar energy, by creating

    the policy conditions for its large scale diffusion across the country as quickly as possible.

    The Mission has set a target, amongst others, for deployment of grid connected solar

    power capacity of 20,000 MW by 2022 and is planned to be implemented in three phases

    with phase-1 by 2013, phase-2 by 2017 and phase 3 by 2022. Against the targets for

    phase 1, major achievements include the following:

    National Solar Mission

    Solar Policy of the Central Govt aimed at setting up20,000 MW of Solar Power Plants by 2022

    State Policies

    Individual states like Gujarat, Rajasthan, Karnataka and

    Madhya Pradesh have released their own policies to setup Solar PV Power Plants in the respective states

    Renewable Energy Certificates

    Any Project Developer can set up any size of projectanywhere in India. Unlike preferential tariff under NSMand State Policies, REC's offer a variable tariff over the

    lifetime of project.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    28/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 28of 111

    The entire capacity of 1,100 MW of grid connected solar power has been allocated.

    The sanctioned capacity for off grid applications is over 118 MW.

    No direct financial assistance is provided by the government for setting up solar power

    projects connected to the grid. One scheme of 1000 MW has been implemented through

    a mechanism of bundling of solar power with thermal power from unallocated quota of

    the Government. For projects connected to less than 33 kV grid, a scheme of generation

    based incentive has been implemented under which a total of 98 MW capacity projects

    were allotted.

    To support deployment of off-grid solar applications, the Government provides capitalsubsidy upto 30% of the benchmark cost and / or soft loan at a rate of 5% interest.

    Since launch of the JNNSM, the capacity of grid-connected solar power projects has

    grown from 8 MW in January 2010 to over 2208 MW 4by January 2014 in the country.

    Recently, MNRE has established the Solar Energy Corporation of India (SECI) for

    handling the power procurement from the second batch of the JNNSM. SECI (MNRE)s

    role would be limited to providing a subsidy known as Viability Gap Funding (VGF), whichis basically a part payment, made by SECI to the project developer in order to make the

    project viable. MNRE has recently unveiled guidelines for allocation of solar power

    project worth 750 MW under the VGF route, out of which, half if earmarked for projects

    opting for cells and modules of domestic origin.

    State Policies

    Subsequent to the launch of the JNNSM, many states have acknowledged the

    importance of solar energy and hence formulated their own respective policies regarding

    the same. Solar potential with their installed capacities for the states which have released

    the solar policies have been summarized in the following table:

    4Source : MNRE : http://www.mnre.gov.in/mission-and-vision-2/achievements

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    29/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 29of 111

    Summary of solar potential, state policy targets and installed capacities in the states of India5

    S.No. State Average Annual

    Solar Resource

    (kWh/m2/day)

    Govt. Policy/Target Installed PV

    Capacity (MW)

    1) Rajasthan 5.0-6.3 Solar power of 10000-

    12000 MW capacity by

    2022.

    666.75

    2) Gujarat 5.2-6.0 500 MW by 2014 860.4

    3) Karnataka 4.6-5.8 200 MW by 2016 31

    4) Tamil Nadu 4.8-5.8 3000 MW of power by

    2015

    31.82

    5) Andhra Pradesh 4.8-5.8 97.2 MW sanctioned 92.9

    6) Madhya Pradesh 5.0-5.6 500 MW by 2013 195.32

    7) Chhattisgarh 5.0-5.6 500-1000 MW by March

    2017

    5.1

    8) Maharashtra 4.6-5.6 No declared state-

    specific target other

    than RPO fulfillment

    237.25

    5Source: MNRE. Installed capacity data as on January 31st, 2014.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    30/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 30of 111

    9) Uttar Pradesh 4.6-5.2 1000 MW by 2017 17.38

    10) Punjab 4.6-5.1 300 MW in Phase-I 9.33

    11) Haryana 4.7-5.3 No declared solar

    specific policy

    7.8

    12) Uttarakhand 3.8-5.7 No declared solar

    specific policy

    5.05

    13) Jharkhand 4.7-5.5 No declared solar

    specific policy

    16

    14) West Bengal 4.2-5.1 No declared solar

    specific policy

    7.05

    15) Odisha 5.1-5.5 No declared solar

    specific policy

    15.5

    16) Delhi 4.7-5.1 No declared solar

    specific policy

    3.01

    17) Andaman and

    Nicobar

    4.7-5.1 No declared solar

    specific policy

    5.1

    18) Others No declared solar

    specific policy

    1.62

    Total 2208 MW

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    31/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 31of 111

    The main features of the Rajasthan State policy is discussed as under:

    Rajasthan State Policy:

    The policy aims at developing Rajasthan as a global hub of solar power of 10,000-

    12,000 MW capacity in next 10-12 years to meet energy requirements of Rajasthan

    and India. To achieve grid parity in next 7-8 years, the State will encourage the Solar

    Power Developers to establish manufacturing plant of their technology in Rajasthan.

    The Rajasthan State will promote setting up of solar power projects for direct sale to

    Discoms of Rajasthan. The total capacity under this category will be distributed equally

    between SPV and CSP based power plants. The total maximum capacity under thiscategory for phase-1 (up to 2013) and phase-2 (2013-2017) would be as follows:-

    Phase-1 (up to 2013) Phase-2 (2013 -2017)

    Maximum Capacity to be developed 200 MW 400 MW (Additional)

    Selection of these Solar Power Projects shall be through tariff based competitive

    bidding process. The State Government may undertake the review of targets mentioned

    above as and when the need arises in view of any technological breakthrough resulting

    in substantial decrease in cost of Solar Power generation. The Rajasthan State will also

    promote Solar Power Producers to set up Solar Power Plants of unlimited capacity for

    captive use or sale of power to 3rd party/States other than Rajasthan. The State will

    also promote deployment of Roof Top and Other Small Solar Power Plants connectedto LT/11kV Grid as per guidelines of MNRE under Rooftop PV & Small Solar Generation

    Programme (RPSSGP) of NSM and orders of appropriate Regulatory Commission.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    32/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 32of 111

    4. JUSTIFICATION FOR THE PROJECT

    Average annual solar radiation at the proposed site at horizontal surface is 1975 kWh/m2

    which is potentially adequate for the installation of the PV plant. Annual expectedgeneration from the 10 MW block is 19,524,243 kWh and for the entire 20 MW is

    39,048,487 kWh.

    Considering power demand for the state, power generated from the proposed power

    plant will be utilized for the state itself. The proposed solar photovoltaic power plant

    (SPV) will contribute to bridge the gap between the demand and availability of power.

    Moreover, it will also help to cut out the dependency on the coal to generate the

    electricity. Furthermore, electricity from the solar power plant will be evacuated to the

    132 kV GSS of RRVPNL situated about 12 kms from the site. Being a higher capacity, it

    is anticipated that grid outage and transmission losses will be considerably low and this

    will help to optimize the electricity feed in the grid. The project - being a renewable energy

    project - leads to sustainable development through efficient utilization of naturally

    available sunlight.

    Financial benefit is an important factor of any investment. Installation of solar PV plant

    seems to be a financially lucrative preposition as it is projected that proposed project will

    have IRR of the order of 11.81 %.

    In other words, the proposed project is a beneficial preposition in term of financial returns,

    environmental aspects and business preposition.

    5. PROJECT SITE

    5.1 Location and Accessibility

    Proposed site location is situated at Latitude 26.840544 N and Longitude 71.818534 E,

    in Village-That, Tehsil-Pokharan, Distt - Jaisalmer, State - Rajasthan. The site is located

    at elevation of approximately 229 m above mean sea level. The project location comes

    under seismic zone-2. Hence, the threat of damage due to an earthquake is also very

    low.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    33/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 33of 111

    Figure 1: Seismic zone of India

    The site is well connected with the intra-state and interstates locations through road,

    railway and airways. Location is situated near to NH-15. Nearest city is Phalodi which is

    about 75 km and nearest railway station is also located in Phalodi city. Nearest airport is

    in Jodhpur which is 182 km from the site. The distance of state capital Jaipur from the

    site is of the order of 478 km.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    34/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 34of 111

    1.1.1.1.1.1

    Figure 2 Satellite map showing the location of the site

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    35/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 35of 111

    The site selection for a solar power plant is pre-dominantly determined by solar insolation

    availability & grid connectivity for exporting power. Equally important are other essentialfactors/considerations such as:

    Availability of adequate land for power plant and green belt development

    Soil condition like soil bearing capacity etc.

    Proximity to state electricity grid enabling economic evacuation of power generated

    Availability of water and power during construction

    Availability of local work force in the proximity

    Availability of load centers (towns) within vicinity Easy accessibility of the site

    5.2 Rainfall and Climate

    The following graph depicts that in the month of January temperature goes below even

    from 8 0C and in the month of May goes high up to 45 0C. The average annual

    temperature at the site is 26 0C.

    Graph 5: Temperature profile of VillageThat

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    36/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 36of 111

    The site receives scanty rainfall annually around 308.5 mm. Rainfall occurs mainly in the

    months of June, July, August and September.

    Graph 6: Rainfall Profile of Village - That

    5.3 Land Requirement and Layout of the Proposed Project

    The total land area required for the project is about 115 acres.

    The power plant layout can be divided in to three main sections as:

    1. Module mounting area

    2. Control room

    3. Inverter Rooms

    The major portion of the site will be used for module mounting. The modules will be

    mounted on a galvanized steel structures which will be installed facing south direction

    for best efficiency & optimal power output. The steel structure will be grouted using RCC

    foundation (or ramming if soil conditions permit). The proposed structure shall be

    designed to hold 20-25 modules per structure and which can withstand wind speed up

    to 170 km/hr. The structure is designed in such a way that it will occupy minimum

    required space without sacrificing the performance.

    4.65 6.16 4.65 5.78.68

    32.7

    115.63

    86.8

    32.1

    8.680.9 1.86

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    37/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 37of 111

    The interconnection cables are routed within the structure and the output cables from

    the modules are taken through proper size conduit to the String Combiner Box (SCB).

    The output cables from the SCBs are routed under the ground through conduits or cable

    trenches. Earthing for the entire module mounting structures will be done using copper

    or GI conductors. The earth pits for module area will be provided as the electrical

    standards. In order to protect the modules from lightning, lightning protection will be

    provided in the module mounting area. Sufficient number of lightning arrestors will be

    provided in this area alone for protection of modules.

    The layout of the array structures shall be so designed that it shall occupy minimum

    space without sacrificing the output of Solar PV modules.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    38/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 38of 111

    6. SOLAR RESOURCE ASSESSMENT

    6.1 Introduction

    The electrical output of a solar power plant is dependent on the incident solar radiation

    it receives. Outside the Earths atmosphere, on a surface normal to the solar beam, the

    power density is 1,365 W/m2, which is known as Solar Constant. As the solar radiation

    passes through the atmosphere, depending on the length of the atmospheric path

    traversed by the solar radiation and the quantity of dust, water vapour, ozone, CO2 and

    other aerosols/gases present, some amount of it is scattered and absorbed. The diffused

    radiation plus the direct irradiance from the sun are together termed as Global

    Irradiance. The diffused sunlight can vary from about 20% on a clear day to 100% in

    heavily overcast conditions. The peak irradiance of 1,000 W/m2 is taken as the standard

    value in the industry by which PV modules are rated. However, the total solar energy

    received in a day over a specific area, called daily solar irradiance or insolation, is more

    important than the instantaneous solar irradiance. The solar resource is not equally

    available in all regions of the world hence a site specific solar resource assessment is

    required for every project.

    6.2 Indias Solar Radiation Profile

    India being a tropical country is blessed with good sunshine over most parts, and the

    number of clear sunny days in a year also being quite high. The country receives solar

    energy equivalent to more than 5,000 trillion kWh per year. Indias equivalent solar

    energy potential is about 6,000 million GWh of energy per year. Being a tropical country,

    India is blessed with good sunshine over most parts, and the number of clear sunny days

    in a year also being quite high.

    The daily average global radiation is around 5.0 kWh/m2in north-eastern and hilly areas

    to about 7.0 kWh/m2in western regions and cold desert areas with the sunshine hours

    ranging between 2300 and 3200 per year. In most parts of India, clear sunny weather is

    experienced for 250 to 300 days a year. The annual global radiation varies from 1600 to

    2200 kWh/m2. Following figure presents the global solar radiation map of India jointly

    developed by MNRE and NREL.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    39/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 39of 111

    Figure 3 Solar Resource Map of India

    6.3 Radiation Profile of the Site

    Solar radiation data can be collected from many sources like NASA-SSE, 3 Tier,

    SolarGIS, and Meteonorm. Meteonorm data is considered for this project since it uses

    both satellite as well as weather station data nearest to the site, while other data sources

    employ only satellite derived data.

    METEONORM database contains the TMY files of solar and climatic parameters for

    several Indian locations based on measured as well as estimated values. The software

    provides a facility to interpolate the solar and meteorological data for any location through

    geographical parameters.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    40/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 40of 111

    Average horizontal solar radiation at the site comes out to be 5.41 kWh/m2/day as per

    meteonorm data. Monthly averages of the same data are given as follows:

    Table 1: Solar Insolation, temperature and wind speed data for the site

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    41/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 41of 111

    7. SELECTION OF TECHNOLOGY

    Photovoltaic comprises the technology to convert sunlight directly into electricity. The

    term photo means light and voltaic, electricity. A photovoltaic (PV) cell, also known assolar cell, is a semiconductor device that generates electricity when light falls on it.

    Since its first commercial use in powering orbital satellites of the US space programs in

    the 1950s, PV has made significant progress with total photovoltaic module industry

    growing at more than 40% in the past decade.

    The PV modules combined with a set of additional application-dependent system

    components (e.g. inverters, batteries, electrical components, and mounting systems),

    form a PV system. These PV systems are highly modular, i.e. modules can be linked

    together to provide power ranging from a few watts to tens of megawatts (MW).

    The solar PV panels typically produce DC electricity that is fed to a grid interactive

    inverter, which in turn converts the DC electricity into AC electricity at a required voltage

    level. In order to achieve a higher system voltage, the output of inverters is fed to step

    up transformers to increase the voltage levels at the desired level. From the transformer,

    the power is routed through the high voltage panel and eventually to other required

    measuring & protection devices before connecting to the grid. The major equipment and

    components of a typical solar plant are shown in the following figure.

    Figure 4 Typical solar PV system components

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    42/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 42of 111

    7.1 Photovoltaic technologies

    Traditional solar cells are made from silicon, are usually flat-plate, and generally are the

    most efficient. Second-generation solar cells are called thin-film solar cells because they

    are made from amorphous silicon or non-silicon materials such as cadmium telluride.

    Thin film solar cells use layers of semiconductor materials only a few micrometers thick.

    Because of their flexibility, thin film solar cells can double as rooftop shingles and tiles,

    building facades, or the glazing for skylights.

    Third-generation solar cells are being made from variety of new materials besides silicon,

    including solar inks using conventional printing press technologies, solar dyes, and

    conductive plastics. Some new solar cells use plastic lenses or mirrors to concentrate

    sunlight onto a very small piece of high efficiency PV material.

    In spite of availability of all the technology, crystalline technology has maximum number

    of installation world wise and has been demonstrated to perform in the field in excess of

    30 years. In addition to this, the technologies are described concisely as follows:

    7.1.1 Crystalline Technology

    Typically, there are two types of crystalline technology mono-crystalline and multi-

    crystalline. Both the technologies are made up of silicon material and have some pros

    and cons. Basic features of individual technology are as follows.

    Mono-Crystalline Silicon

    Mono-crystalline Silicon has a continuous crystal lattice structure with practically zero

    defects or impurities. Mono-crystalline Silicon is superior to other types of silicon cells in

    terms of higher efficiencies which are typically around 18-23%. However, the mono

    crystalline Si-cell production is an expensive process when compared to other types of

    PV cells. Mono-Crystalline panels are mostly considered where the space is limited as

    in the case of rooftops. The lifespan of mono-crystalline cells is a minimum of 25 years

    and can go more, making them a worthwhile investment for long-term use.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    43/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 43of 111

    Figure 5 Mono-Crystalline Silicon

    Module

    Figure 6 Multi-Crystalline Silicon

    Module

    Multi-Crystalline Silicon

    Multi-crystalline (or poly-crystal) silicon panels are made by using polycrystalline wafers.

    Multi crystalline wafers consists of number of crystallites with different grain sizes will be

    having grain boundaries and several defects. Multi-crystalline Si growth is relatively

    cheaper than the mono crystalline Si and the cells made up of these wafers are relatively

    cheaper. Due to the less pure crystals, the efficiency of these cells reduces and the

    module efficiencies typically range in between 14-16%. The lifetime of these modules is

    also around 25 years or more and these panels are cheaper option where the space is

    not a limitation. These panels are commonly preferred ones for grid connected

    applications.

    7.1.2 Thin Film Technology

    Thin film modules are potentially cheaper to manufacture than crystalline cells have a

    wider customer appeal as design elements due to their homogeneous appearance

    present. Disadvantages include low-conversion efficiencies and requiring larger areas of

    PV arrays and more material (cables, support structures) to produce the same amount

    of electricity.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    44/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 44of 111

    Figure 7 Thin film PV module

    Material costs and manufacturing costs are lower per unit area as compared to those of

    crystalline silicon cells.

    7.1.3 Comparison of Major PV Technologies:

    Table 2 Technology Comparisons

    S. No. Parameter Crystalline Thin Film

    1) Types of Materials Poly-crystalline, mono-

    crystalline silicon

    Amorphous Silicon, CdS, CdTe,

    CIS/ CIGS, etc.

    2) Handling Better protection against

    breakage

    Need extra care

    3) Power Efficiency 13-21.5% 7-13%

    4) Technology Well Developed Well Developed

    5) Module Weight Light weight modules (0.1Kg/W) Slightly heavy modules (0.17

    Kg/W)

    6) Area utilization Higher power generated Less power per unit area

    7) Temperature Effects Highest impact of Temperature

    variations

    Lesser impact of Temperature

    variations

    8) Irradiance Used particularly for Normal

    radiations

    Better performance with Diffuse

    radiations

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    45/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 45of 111

    General Comparison of thin-film technologies

    S. No. a-Si CdTe CIS/CIGS

    1) a-Si suffer significant

    initial degradation in

    power output when

    exposed to the sun

    Lesser degradation Lesser degradation

    9) Module quantity Lesser quantity required Higher quantity required

    10) Output per MW

    installed

    High Higher

    11) Land Requirement Lesser space required per MW Larger space requirement

    12) Cost Comparable cost per Watt Comparable cost per Watt

    13) Environment Effects Less Sensitive Sensitive

    14) Stabilization Stable power output at initial

    stages

    Stability achieved after 1-2

    months

    15) Availability Easily available Easily available

    16) Power Degradation Less degradation Slightly higher degradation

    17) Plant Maintenance Less maintenance required after

    installation so lower cost

    High maintenance required, so

    high maintenance cost

    18) Repair Relatively easy Easy

    19) Cooling Requirement Required Not required

    20) Cabling Easy installation Easy installation

    21) Suitability for Grid

    Tech.

    Good Good

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    46/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 46of 111

    2) Overall efficiency around

    6-8%

    Overall efficiency around

    8-11%

    Overall efficiency 9-13%

    3) a-Si thin film modules

    comprised about 31% ofthin film market and 4.4%

    of global PV market in

    2012

    CdTe comprised 44% of

    thin film market andabout 6.2% of the global

    PV market in 2012

    CIGS comprised 24% of

    thin film market andabout 3.3% of the global

    PV market in 2012

    4) Spectral Sensitivity

    towards short wavelength

    CdTe absorbs medium

    wavelengths

    CIS/CIGS also absorbs

    medium wavelength

    7.2 PV Technology Recommendation

    Each of the above technologies has their own particular strengths and limitations. Multi

    crystalline silicon photovoltaic technology is recommended for the project on the grounds

    of easy availability, cost effectiveness and technological stability.

    7.3 Balance of Plant Systems (BoS)

    On an average, BoS constitutes 40-45 % of the total project cost of a solar PV Project.For a solar PV Plant, the BoS comprises of inverters, cables, mounting structures,

    foundations and power electronics. Often assigned secondary importance irrespective

    of their being a significant cost component, BoS are critical determinants of the actual

    plant life. High technical standards of BoS components should therefore be ensured as

    a matter of standard practice.

    7.4 Inverter Technologies

    Solar inverter is a critical component in the solar energy system. It performs the

    conversion of the variable DC power output of array (string of the Photovoltaic (PV)

    modules) into a utility frequency AC power, which can be fed into the commercial

    electrical grid. There are mainly two category of solar inverters are available central, and

    string. A central inverter is generally for adopted for MW scale plant and string inverter

    can handle comparatively less power.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    47/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 47of 111

    Inverter is the heart of a solar power project. It is also known as Power Conditioning Unit

    (PCU). A PCU consists of an electronic Inverter along with associated control, protection

    and data logging devices. Typically the utility scale inverters are unidirectional and supply

    the power to the grid in the form of AC power conforming to IEC 61727 or equivalent

    standard. The inverter has a feature that it automatically adjusts with the grid conditions

    such as the voltage & frequency levels to suit the Grid. It is advised that following key

    points can be considered while specifying your inverter requirements to various vendors.

    a) Proven Technology: The inverter should be selected based on the proven

    technology and it is advisable that the inverter has completed at least one year

    successful operation in the high temperature weather conditions and fluctuating grid

    conditions.

    b) Grid Compliance:At times you may require changing some of the key parameters

    of the inverters to match with your local grid conditions, hence the inverter should

    have features of changing some of the threshold parameters, and it can be

    programmed accordingly. It should also have features of grid islanding through Air

    Circuit Breakers. Some of the new generation inverters have provision of self

    protective and self diagnostic features so that it can protect itself from the PV array

    faults and adjust with the changing parameters of the solar PV array. The Inverter

    should have provisions of automatically wake up in the morning and begin to export

    power provided there is sufficient solar energy and the grid voltage and frequency is

    in range.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    48/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 48of 111

    The inverter should have MPPT control algorithm in such a way that it adjust itself

    with the voltage of the SPV array to optimize solar energy fed into the grid. The MPPT

    must have provision for constant voltage operation. The inverter MPPT feature

    should comply with EN50530 or Equivalent standard.

    The inverter output always follows the grid in terms of voltage and frequency. This

    should be achieved by sensing the grid voltage and phase and feeding this

    information to the feedback loop of the inverter. Thus control variable then controls

    the output voltage and frequency of the inverter, so that inverter is always

    synchronized with the grid.

    c) Inverter Efficiency:The efficiency of the inverter is another key factor, and most of

    the inverters are available in the efficiency range of about 97-98% efficiency levels.

    However it is important to make a note of the inverter efficiency at the part load

    conditions. Typically the part load efficiency levels are more than 97 % at 75% load

    as per IEC 61683 or equivalent standard. It is important to assess the inverter

    efficiency levels at different load say 25%, 50%, 75% and 100% and it should meet

    the IEC 61683 standard.

    d) Control and Protection:The inverter should have internal protection arrangement

    against any sustained fault in the feeder line and against lightning in the feeder line.

    It should also have the required protection arrangements against earth leakage faults.

    The inverter should also have suitable rated DC disconnecting arrangement to allow

    safe start up and shut down of the system. Inverter should also have required

    protection arrangements against reverse polarity of DC Connection. There should be

    suitable surge protection arrangement to pass the fault current to earthingsystem. During the earth fault condition, the inverter should be having provision of

    disconnection.

    e) Operational Flexibility: The inverter should have provision of parallel operation.

    Generally two inverters are connected to a single 3 winding transformer, the inverter

    should have flexibility to work in such combinations. The inverter should have feature

    of ON and OFF automatically based on solar radiation variations during the day.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    49/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 49of 111

    The inverter should have suitable display panels so that all important parameters

    such as DC input voltage, DC input current, all phase to phase AC voltages , all phase

    AC current, AC output power, frequency , apparent power , reactive power etc are

    visible to the plant operators. Some of the inverters come with a suitable PCU with

    display, and can be connected to the SCADA system.

    During the sleep mode the inverter should be having the automatic control provisions

    so that the threshold dc voltage of the inverter can decide the inverter to enter in

    sleep mode and back to standby mode. The inverter must also automatically re-enter

    standby mode when threshold of standby mode.

    The standard warranty of these inverters is 5 to 10 years. However many inverter

    manufacturer offer extended warranty also considering string inverter is a costlier

    proposition as compared to a central inverter, however an apple to apple comparison

    can only be made consideration of not only cost per watt of string versus central, but

    also cost reduction of DC cables and other associated benefits such as reduced down

    time in case of string inverter.

    The central inverter takes input from number of arrays and operates at single MPP.

    Hence the inverter MPP (maximum power point) is governed by the arrays which are

    having partial shading ,mismatch losses , modules with tolerances which may lead to

    reduce output in case of central inverter. However this can be reduced by selection

    of string inverter as different strings have different MPP so that the output is

    maximized.

    7.5 Cabling

    a) DC Cables and Connectors: Working with solar PV arrays can be hazardous since

    Solar panels connected together in an array are often configured to produce high DC

    voltage. Furthermore, DC voltages are constant in nature so, effect of electric shock

    due to DC voltage will surely be severe. Hence, DC Cables should be double

    insulated and polarized and DC connectors should always be used. The minimum

    technical requirements for Cables laid down by MNRE states that they should

    conform to General Test and Measuring Method PVC insulated cables for working

    voltage up to and including 1100 V and UV resistant for outdoor installation

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    50/111

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    51/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 51of 111

    including Module Mounting Structures shall have to be adequately protected from

    atmosphere and weather prevailing in the area.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    52/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 52of 111

    8. PROJECT REGISTRATION AND CLEARANCES

    8.1 Project Registration/ Clearances

    Following clearances would be required for the envisaged project:

    A) Permits and Clearances

    The Government of India at the central level and the state governments at the local level

    have established legal, policy guidelines and regulatory frameworks for setting up of non-

    conventional energy based power projects. Accordingly, certain clearances and

    approvals are required to be obtained from different Government Bodies and Statutory

    Agencies at various stages of development and operation phases of the project. These

    clearances are classified into two broad categories known as statutory and non-statutory

    clearances.

    a) Statutory Clearances

    Statutory Clearances mainly comprise water supply agreement from state government,

    consent for establishment from State Pollution Control Board (SPCB), environmental

    clearances from MOEF, forest clearances from state forest department and MOEF,

    company registration through registrar of company, rehabilitation and resettlement of

    displaced families on account of land acquisition from state/central government etc.

    MOEF clearance is not applicable for the project. Forest clearance is also not applicable

    as forest land is not considered for the project. The land identified for the project is free

    of any inhabitation and is being directly purchased from the owners; hence there are no

    R&R issues. However the agricultural land needs to be converted for non-agricultural

    use.

    b) Non-Statutory Clearances

    The Non-Statutory Clearances mainly comprise land availability from state government

    and clearance for National Monuments from Archaeological Survey of India (ASI) / Govt.

    of India etc. There is no national monument in the identified land for the project.

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    53/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 53of 111

    c) Other Clearances

    Sanction of construction power from the office of Chief Engineer of the respective state

    Electricity Utility and permission to use ground water if applicable.

    Table 3: List of Clearances required for PV Projects in Rajasthan

    S.No. ItemsResponsible

    AgencyTentative

    Date

    1 Nodal Agency registration RRECL Zero

    2 Bid Evaluation Committee RRECL Zero + 10

    3 Registration certificate for plots

    Between Seller

    & Buyer Zero + 20

    4 State Level Screening Committee Approval RRECL Zero + 25

    5

    Consent from local panchayat for development of

    project site Panchayat Zero + 30

    6 Approval for Connectivity Diagram RVPNL Zero + 45

    7

    Distribution Company/ Local agency Supervision

    Application and payment for Sub Station RVPNL Zero + 60

    8 Approval of Approach Route for Transmission Line RVPNL Zero + 75

    9 Transmission line permits Energy Minister Zero + 75

    10 Allotment of Bay RVPNL Zero + 75

    11 Power Purchase Agreement Local Discom Zero + 75

    12 Metering Approval Local Discom Zero + 75

    13 REC Accreditation RRECL Zero + 90

    14 Non Agricultural Certification for land approval

    District Collector

    Office Zero + 90

    15 Meter, CT PT testing and inspection certificates RDPPC Zero + 100

    16 Consent to Establish (Pollution Control Board) PCB Zero + 100

    17

    Chief Electrical Officer visit for approval on the

    electrical layout of plantCEI Zero + 110

    18 Approval for Interconnection RVPNL Zero + 110

    19 Permission for Charging RDPPC Zero + 110

    20 State Level Empowered Committee Approval RRECL Zero + 110

    21 REC Registration NLDC Zero + 110

    22

    Certificate of Commissioning - Nodal Agency/ Local

    Agency RRECL Zero + 120

    23

    Customs & Excise Duty Exemption/ MNRE

    Certificates

    MNRE &

    RRECL

    Ongoing

    Basis

    24 Consent to Operate (Pollution Control Board) PCB Zero + 150

  • 8/10/2019 TGEPL_20MW_DPR_24.07.2014

    54/111

    20 MW (AC) SOLAR PV POWER PROJECT BY TGEPL

    Page 54of 111

    9. POWER PLANT DESIGN CRITERIA

    The Power Plant is sized on the following major criteria:

    Solar Power (average insolation available)

    Power evacuation facility in the vicinity of the proposed site along with grid

    availability on 24 Hours a day basis.

    Details of the design process and are presented in the below sections.

    9.1 Design and Simulation projections by PVSYST

    PVSYST tool is one of the most accepted design tool for the study, sizing, simulation

    and data analysis of complete PV systems. We have used this tool to generate the most

    realistic energy yield simulation results, which are detailed in this report. Main features

    of PVSYST:

    1. Detailed computation of the used components (modules, inverters, etc)

    2. Simulation on hourly basis and detailed evaluation and consideration of different

    loss factors.

    3. Calculation of arbitrary orientated module planes (fixed and tracking systems)

    4. Most accepted and used tool to generate simulation results for PV power plants,

    as the results are based on systematic and refined approach.

    5. Program with the most accurate results and functions available in the market.

    9.2 PV Power Plant Energy Production

    The system lifetime energy production is calculated by determining the first-year energygeneration as expressed in kWh (AC)/kWp (AC), and then degrading output over the

    system life based on an annual performance degradation rate. System degradation

    (largely a function of PV panel type and manufacturing