TetraTech EM Inc. HS™ · 2021. 6. 11. · Contract No. 68-W7-0003, Work Assignment No....
Transcript of TetraTech EM Inc. HS™ · 2021. 6. 11. · Contract No. 68-W7-0003, Work Assignment No....
EPA Region 5 Records Ctr.
TetraTech EM Inc. HS™
200 E. Randolph Drive, Suite 4700 + Chicago, IL 60601 * (312) 856-8700 + FAX (312) 938-01 18
November 17,2000
Mr. Thomas AlcamoWork Assignment Manager (SR-6J)Remedial Response Unit No. 1U.S. Environmental Protection Agency Region 577 West Jackson BoulevardChicago, IL 60604
Subject: Field Oversight Summary for October 23 through November 3,2000Lemon Lane Landfill Site, Bloomington, IndianaContract No. 68-W7-0003, Work Assignment No. 044-RXBF-0529
Dear Mr. Alcamo:
Tetra Tech EM Inc. (Tetra Tech) has prepared the enclosed field oversight summary to document itsremedial action oversight activities at the above-referenced site from October 23 through November 3,2000. CBS Corporation, the responsible party for the site, conducted the remedial action activities.Appendix A of the field oversight summary contains a photographic log of Tetra Tech's field activities,and Appendix B contains a copy of Tetra Tech's oversight field notes.
If you have any questions about the enclosed summary, please call me at (847) 818-7189.
Sincerely,
Raj RajaramSite Manager
Enclosure
cc: Steve Nathan, EPA Project Officer (letter only)David Alberts, EPA Contracting Officer (letter only)Tom Kouris, Tetra Tech Program Manager (letter only)
contains recycled fiber and is recyclable
ENCLOSURE
FIELD OVERSIGHT SUMMARY FOROCTOBER 23 THROUGH NOVEMBER 3, 2000
LEMON LANE LANDFILL SITEBLOOMINGTON, INDIANA
(Four Pages)
FIELD OVERSIGHT SUMMARYLEMON LANE LANDFILL SITE
BLOOMINGTON, INDIANA
Tetra Tech Oversight Personnel: Brian Lenihan and Greg YoungReporting Period: October 23 through November 3, 2000
INTRODUCTION
As requested by the U.S. Environmental Protection Agency (EPA), Tetra Tech EM Inc. (Tetra Tech) is
conducting oversight of remedial action (RA) activities at the Lemon Lane Landfill site in Bloomington,
Indiana, under Contract No. 68-W7-0003, Work Assignment No. 044-RXBF-0529. CBS Corporation
(CBS) is the responsible party for the site. PSARA Technologies (PSARA) is CBS's consultant; WRS
Environment and Infrastructure, Inc. (WRS), is CBS's site remediation contractor; American Drill ing
Services (ADS) is CBS's drilling contractor; Envirocon Systems. Inc. (Envirocon), is CBS's
geomembrane liner contractor; and Colder and Associates (Colder) is PSARA's landfill cap consultant.
This report summarizes Tetra Tech's oversight observations from October 23 through November 3, 2000,
and discusses issues and developments during the reporting period and future activities at the site.
Appendix A contains a photographic log of field activities, and Appendix B contains a copy of Tetra
Tech's oversight field notes for the reporting period.
OVERSIGHT OBSERVATIONS
Tetra Tech's oversight observations of RA activities at the site from October 23 through November 3,
2000, are summarized below.
Monday, October 23,2000
Tetra Tech arrived at the site at 8:00 a.m. WRS was excavating in the southwest retention pond area and
was using the excavated material to backfill locations in the southwest portion of the landfill . At
8:30 a.m., ADS arrived at the site to install four piezometers in the landfill. Two piezometers (PZ) were
E-1
to be placed in the northwest section of the landfill (PZ-BD in grid F6 and PZ-BS in grid G8) and two
more in the southwest section of the landfill (PZ-AD in grid D18 and PZ-AS in grid F16). At 12:00 p.m.,
WRS finished excavating grid CIO. Tetra Tech then inspected this grid and found no problems. WRS
placed protective sand cover over backfilled and consolidated areas of the landfill. Such activities
continued throughout the day. Envirocon received landfill cap materials at the site during the day. Tetra
Tech left the site at 4:30 p.m.
Tuesday, October 24, 2000
Tetra Tech arrived at the site at 6:00 a.m. At 6:45 a.m., WRS began loading Toxic Substances Control
Act (TSCA) material for off-site disposal and continued placing protective sand cover over backfilled and
consolidated areas of the landfi l l . These activities continued throughout the day. At 9:30 a.m., ADS
continued with piezometer installation at the site; piezometer installation was completed at 11:30 a.m.
Envirocon received landfill cap materials at the site during the day. Tetra Tech left the site at 3:00 p.m.
Monday, October 30,2000
Tetra Tech arrived at the site at 12:15 p.m. The geocomposite layer (GCL) and geomembrane had been
placed over about 40 percent of the landfill, mostly on its north side. Envirocon continued installation of
the GCL and geomembrane. WRS graded locations in the southwest corner of the landfill and excavated
the perimeter drainage ditch on the south side of the site. Tetra Tech left the site at 4:30 p.m.
Tuesday, October 31,2000
Tetra Tech arrived at the site at 8:30 a.m. At 8:40 a.m., WRS began excavating the perimeter drainage
ditch in the southeast corner of the landfill. A hoe-ram was used to dislodge a bedrock knob at the base
of the drainage ditch (see Photograph No. 1). At 9:15 a.m., Envirocon started laying the GCL in the east-
central portion of the site (see Photograph No. 2). At 10:00 a.m., WRS watered the haul road as a dust
control measure. At 10:25 a.m., Envirocon started placing geotextile material across the perimeter
drainage ditch on the east side of the landfill (see Photograph No. 3). At 10:45 a.m., Envirocon installed
the geomembrane above the GCL used for the drainage ditch (see Photograph No. 4). Tetra Tech
E-2
observed the welding of geomembrane seams (see Photograph No. 5). Landfill cap installation and
various drainage ditch excavation and grading continued throughout the day. Tetra Tech left the site at
4:30 p.m.
Wednesday, November 1,2000
Tetra Tech arrived at the site at 7:30 a.m. WRS continued drainage ditch excavation on the south and
west sides of the landfill, and Envirocon continued installing the GCL and geomembrane. These activities
continued throughout the day. At 2:00 p.m., Tetra Tech observed destructive and nondestructive seam
testing of the geomembrane welds (see Photograph No. 6). During destructive seam testing, the tensile
and shear strength of a weld is tested by attempting to pull the weld apart. Nondestructive seam testing
involves injecting air into a welded seam and then measuring the drop in air pressure over a 5-minute
period. This test is used to evaluate the continuity of the weld. Colder reported that all welds tested to
date had passed both destructive and nondestructive seam testing. Tetra Tech left the site at 4:30 p.m.
Thursday, November 2,2000
Tetra Tech arrived at the site at 7:30 a.m. At 8:00 a.m., WRS began excavating the drainage ditch on the
west and northwest sides of the landfill, and Envirocon continued installing the GCL. These activities
continued throughout the day. At 11:15 a.m., Tetra Tech observed destructive seam testing of
geomembrane welds (see Photograph No. 7). The welds observed passed the minimum requirements for
tensile and shear strength. Tetra Tech left the site at 4:30 p.m.
Friday, November 3, 2000
Tetra Tech arrived at the site at 7:30 a.m. At 8:00 a.m., WRS started excavating in the retention pond
area on the southwest side of the site and started grading the protective cover on the southwest side of
the site. At 9:00 a.m., Envirocon began installing the geonet layer above the geomembrane. These
activities continued throughout the day. At 1:00 p.m., WRS began installing a length of concrete drainage
pipe in the drainage ditch on the southeast side of the site (see Photograph No. 8). By mid-afternoon, the
GCL and geomembrane had been installed over about 75 percent of the landfill (see Photographs No. 9
E-3
and 10), and the geonet had been installed over about 60 percent of the landfill. Tetra Tech left the site at
3:00 p.m.
ISSUES AND DEVELOPMENTS
By the end of the reporting period, all TSCA material had been excavated and removed from the site.
Installation of the landfill cap commenced during the week of October 23, 2000. All landfill cap
installation and testing activities observed by Tetra Tech during the reporting period were conducted in
accordance with specification in the landfill cap installation work plan.
FUTURE ACTIVITIES
Tetra Tech will continue to provide RA oversight at the site as directed by EPA. The RA activities at the
site are scheduled to be completed by December 8, 2000.
E-4
APPENDIX A
PHOTOGRAPHIC LOGLEMON LANE LANDFILL SITE
(Five Pages)
IIIIIIIIIIIIIIIIIII
Photograph No. 1 Location: Lemon Lane LandfillOrientation: South Date: October 31, 2000Description: WRS removing bedrock obstruction from southeast drainage ditch
Photograph No. 2Orientation: EastDescription: Envirocon installing GCL on east side of landfill
A-l
Location: Lemon Lane LandfillDate: October 31,2000
IIIIIIIIIIIIIIIIIII
Photograph No. 3 Location: Lemon Lane LandfillOrientation: Northeast Date: October 31, 2000Description: Envirocon installing geotextile across perimeter drainage ditch
\Photograph No. 4Orientation: NorthDescription: Envirocon installing geomembrane over GCL
A-2
Location: Lemon Lane LandfillDate: October 31,2000
IIIIIIIIIIIIIIIIIII
Photograph No. 5 Location: Lemon Lane LandfillOrientation: Northeast Date: October 31, 2000Description: Envirocon welding seam between two panels of geomembrane
Photograph No. 6 Location: Lemon Lane LandfillOrientation: East Date: November 1, 2000Description: Envirocon conducting nondestructive seam testing of geomembrane weld
A-3
IIIIIIIIIIIIIIIIIII
Photograph No. 7 Location: Lemon Lane LandfillOrientation: North Date: November 2, 2000Description: Envirocon conducting destructive seam testing of geomembrane weld
Photograph No. 8 Location: Lemon Lane LandfillOrientation: Southeast Date: November 3, 2000Description: WRS installing concrete pipe in southeast drainage ditch
A-4
IIIIIIIIIIIIIIIIIII
Photograph No. 9Orientation: NortheastDescription: Southwest side of landfill
Location: Lemon Lane LandfillDate: November 3, 2000
Photograph No. 10Orientation: EastDescription: North side of landfill
Location: Lemon Lane LandfillDate: November 3, 2000
A-5
APPENDIX B
OVERSIGHT FIELD NOTESLEMON LANE LANDFILL SITE
(Eight Sheets)
ocoCO
ooo00
CO03TJ
Tltt)
Di-jO.
33
COi-*roCOroCO
COCO
TJ
ro
. Field Logbook No.
0C
oCO
oD
OCO
U)TJ
33
COh-»
ro
roCOh-*(-*CO
TJ
CO
Oc
0CD
OQ
OCO
COCDTJ
IDi—ia
3D
CDi-*roCOroCO
uCO
CP Date <Q/30/00