ASME Section VIII, Div.1
Pressure Test ingand
Code Stamp ing
-
8/10/2019 Testing and Stamping
2/32
Topics
Requirements for Pressure Testing
Hydrostatic Testing
Pneumatic Testing
Test Gauge
Stamping
-
8/10/2019 Testing and Stamping
3/32
Requirements
forPressure Testing
-
8/10/2019 Testing and Stamping
4/32
Why Test?
Detect gross defects in
design and fabrication
-
8/10/2019 Testing and Stamping
5/32
What Must Be Pressure Tested?
Completed vessels, fabricated to the
ASME Code, at the required pressureand temperature
-
8/10/2019 Testing and Stamping
6/32
Hydrostatic Testing
-
8/10/2019 Testing and Stamping
7/32
Test Temperature
The recommended minimum metal
temperature of 30 oF above the
design minimum design metal
temperature (MDMT) and not over
120
o
F
-
8/10/2019 Testing and Stamping
8/32
HydroTest Pressure
d
tp
S
SMAWPT )3.1(
Tp = Test Pressure
MAWP= Maximum Allowable Working Pressure
St = Material stress value at test temperature
Sd = Material stress value at design temperature
-
8/10/2019 Testing and Stamping
9/32
Exceptions
Vacuum Service
Combination Units
Enameled VesselsCast Iron Vessels
-
8/10/2019 Testing and Stamping
10/32
-
8/10/2019 Testing and Stamping
11/32
Combination Units
When operated independently test
as separate vessel
Example: Heat Exchangers
-
8/10/2019 Testing and Stamping
12/32
Enameled Vessels
Test pressure shall be equal to
but need not be above the
vessel MAWP
-
8/10/2019 Testing and Stamping
13/32
Cast Iron Vessels
MAWP < 30 psi:
Test pressure must be 2.5 x MAWP
and 30 psi:
Test pressure must be 2 x MAWP
-
8/10/2019 Testing and Stamping
14/32
Pneumatic Test Pressure
d
tp
S
Sx10.1MAWPxT
Tp = Test Pressure
MAWP= Maximum Allowable Working Pressure
St = Material stress value at test temperature
Sd = Material Stress value at Design temperature
-
8/10/2019 Testing and Stamping
15/32
Test Procedure
1. Gradually increase pressure to
about test pressure
2. Thereafter, increase the pressure atan interval equal to 1/10 of the test
pressure until the test pressure has
been reached
Assure that UW-50 has been compliedpriorto
pneumatic testing
-
8/10/2019 Testing and Stamping
16/32
-
8/10/2019 Testing and Stamping
17/32
Witness Pressure Test
Authorized Inspector shall
witness pressure tests for all
vessels being U stamped,except multiple vessels
fabricated to UG-90(c)(2)
-
8/10/2019 Testing and Stamping
18/32
UG-102: Test Gauges
Connected directly to the vessel
Visible to the Operator
Graduated at a range double thetest pressure, but in no case morethan 4 times or less than 1-1/2 timesthe test pressure
Calibrated against a deadweighttester or master gauge
-
8/10/2019 Testing and Stamping
19/32
Stamping
-
8/10/2019 Testing and Stamping
20/32
UG-118: Methods of Marking
Marking may be directly on the vessel
or on a nameplate
Minimum letter size requirements for
either direct stamping or nameplate
A nameplate is required on
Ferrous materials less than 1/4 thick
Non-ferrous materials less than thick
-
8/10/2019 Testing and Stamping
21/32
Symbol Stamping
Code stamps may be applied on the
vessel or on a nameplate attached to
the vessel, prior to hydrostatic testTest procedure must be documented
in the Manufacturers program
The Authorized Inspector must haveaccepted the test procedure
-
8/10/2019 Testing and Stamping
22/32
-
8/10/2019 Testing and Stamping
23/32
Type of Construction
Arc/Gas Welded - W
Brazed - B
Pressure Welded - PResistance Welded - RES
-
8/10/2019 Testing and Stamping
24/32
Special Services
Lethal Services L
Unfired Steam Boiler UB
Direct Fired Vessels DFNon-stationary NPV
Pressure Vessels
Letters are located under the U Codesymbol stamp
-
8/10/2019 Testing and Stamping
25/32
Degree of Radiography
Full Radiography RT-1
UW-11 (a)(5)(b) RT-2
Spot Radiography RT-3When RT-1, RT-2 RT-4
or RT-3 does not apply
-
8/10/2019 Testing and Stamping
26/32
Postweld Heat Treatment
Entire vessel heat treated HT
Partial heat treatment PHT
-
8/10/2019 Testing and Stamping
27/32
Vessel Parts
The word part must be stamped
under the U Code stamp symbol
The Manufacturers name, precededby Certified by, and the serial
numbers are the only identification
required
-
8/10/2019 Testing and Stamping
28/32
Code Stamp
Code Symbol
The U symbol stamp is for
a Manufacturer who
fabricates complete
pressure vessels in the shop
or field
The holder of a U stampmay also make vessel parts
U
-
8/10/2019 Testing and Stamping
29/32
Code Stamping
-
8/10/2019 Testing and Stamping
30/32
Code Stamp
The UM Code
Symbol is applied to
pressure vessels thatare built to the
requirements of U-1(j)
UM
-
8/10/2019 Testing and Stamping
31/32
Code Stamp
The UV symbol is
used for pressure
relief devices thatmeet Section VIII,
Div. 1 requirements.
UV
-
8/10/2019 Testing and Stamping
32/32
Questions?
Pressure Testing & CodeStamping