Medium Voltage Switchgear Witness Test Procedure General Order Number ____________ Project Name _______________ Page ____of____ Item _________________ !ustomer "esignation_________________________________ Medium Voltage Switchgear Witness Test Procedure The following Procedure #ro$ides %aton&s 'Witness Test Standards( for #erforming factor) witness test* These guidelines do not co$er all details+ $ariations+ or combinations of the e,ui#ment+ its installat o#eration* !are will be e.ercised to com#l) with local+ state+ and national regulations+ as well as sa e,ui#ment* /ll switchgear will be o#erated and tested b) ,ualified %aton #ersonnel as defined b) OS0/ 12!345256 s Supplied Information and Equipment _ Personal Protecti$e %,ui#ment _ Project folder _ !ertified Production Test 4e#ort _ !onstruction "rawings _ Witness Test Procedure _ Product line contacts and #hone numbers Prior to Testing 58 4e$iew9 _ !onstruction drawings associated with the e,ui#ment being tested _ Site safet) rules and emergenc) #rocedures Ins#ection and Test Procedures A FINA !EVIEW "F #"MMENTS$%EFI#IEN#IES WI &E #"N%'#TE% AT #"N#'SI"N "F TESTIN() 58 Visual9 _ The de$ice name#late information is identical with the switchgear drawings* _ Suitabilit) and calibration dates of test sets _ !ircuit brea-ers to ensure the) ha$e the #ro#er am#ere+ $oltage and interru#ting rating* _ Verif) all high $oltage labels+ :; labels and /NSI re,uired labels are $isible* _ /u.iliar) de$ices such as #rotecti$e de$ices+ meters+ control switches are installed and wired* _ That all VT and !T ratios #ro#erl) corres#ond to drawings _ That #rimar) and secondar) fuse ratings or circuit brea-ers match drawings _ Meter scaling and t)#e match drawings _ Verif) Switchgear 0eaters and Thermostat installed <if a##licable8 _ Verit) correct cable entr) #ositions i*e* to# entr)=bottom entr) _ Verif) correct cable lugs <if re,uired8 18 Mechanical9 Verif) >rea-er 4ac-ing Mechanism _ 4ac- out one brea-er in the closed #osition to $erif) cell interloc- _ !hec- brea-er rac-s out freel) without interferences _ /ttem#t to rac- brea-er in closed #osition to $erif) cell interloc- _ 4ac- brea-er to rails to ensure brea-er s#ring is discharged Verif) Mechanical >rea-er O#eration _ O#en and close each brea-er from the brea-er co$er _ O#en and close each brea-er door and chec- for interferences _ O#en and close each Potential Transformer door<s8 chec- for interferences ?8 %lectrical9 The #rotecti$e rela)+ metering+ and control setting su##lied b) the customers& engineer or from a Power Stud) #erformed #rior to commissioning* /##l) !ontrol Power to Switchgear Verif) %lectrical >rea-er O#eration _ O#en and close each brea-er with brea-er control _ O#en and close each brea-er from remote terminal a##licable8 _ !lose brea-er+ tri# circuit brea-er utili@ing #r <if a##licable8 _ %nsure AB ;O4 o#erates <if a##licable8 _ %nsure brea-er Ca& and Cb& contacts o#erate Verif) Metering _ 3unctionall) test metering de$ices b) energi@ing rated $alues D8 O#erational !ontrols _ Test /utomatic Transfer S)stem <if a##licable8 _ Other O#erational Test 78 3inal details after Witness Test are com#lete* _ !om#lete mimic bus* _ /ll remaining name#lates installed* _ "rawers and doors aligned* _ "anger labels and other warning stic-ers* _ Vacuum and #erform final cleaning of gear* _ Touch u# #ainting* _ !hec- Shutter alignment*

Transcript of Test Procedure.doc

Medium Voltage Switchgear Witness Test Procedure

General Order Number ____________ Project Name _______________ Page ____of____

Item #_________________ Customer Designation_________________________________

Medium Voltage SwitchgearWitness Test Procedure

The following Procedure provides Eatons Witness Test Standards for performing factory witness test.

These guidelines do not cover all details, variations, or combinations of the equipment, its installation, checkout, and safe operation. Care will be exercised to comply with local, state, and national regulations, as well as safety practices for this class of equipment.

All switchgear will be operated and tested by qualified Eaton personnel as defined by OSHA 29CFR1910 subpart 5.Supplied Information and Equipment

_ Personal Protective Equipment

_ Project folder

_ Certified Production Test Report

_ Construction Drawings

_ Witness Test Procedure

_ Product line contacts and phone numbers

Prior to Testing

1) Review:

_ Construction drawings associated with the equipment being tested

_ Site safety rules and emergency procedures

Inspection and Test ProceduresA FINAL REVIEW OF COMMENTS/DEFICIENCIES WILL BE CONDUCTED AT CONCLUSION OF TESTING.

1) Visual:

_ The device nameplate information is identical with the switchgear drawings.

_ Suitability and calibration dates of test sets

_ Circuit breakers to ensure they have the proper ampere, voltage and interrupting rating.

_ Verify all high voltage labels, UL labels and ANSI required labels are visible.

_ Auxiliary devices such as protective devices, meters, control switches are installed and wired.

_ That all VT and CT ratios properly correspond to drawings

_ That primary and secondary fuse ratings or circuit breakers match drawings

_ Meter scaling and type match drawings

_ Verify Switchgear Heaters and Thermostat installed (if applicable)

_ Verity correct cable entry positions i.e. top entry/bottom entry

_ Verify correct cable lugs (if required)

2) Mechanical:

Verify Breaker Racking Mechanism

_ Rack out one breaker in the closed position to verify cell interlock

_ Check breaker racks out freely without interferences

_ Attempt to rack breaker in closed position to verify cell interlock

_ Rack breaker to rails to ensure breaker spring is discharged

Verify Mechanical Breaker Operation

_ Open and close each breaker from the breaker cover

_ Open and close each breaker door and check for interferences

_ Open and close each Potential Transformer door(s) check for interferences

3) Electrical:

The protective relay, metering, and control settings must be supplied by the customers engineer or from a Power System Study performed prior to commissioning.

Apply Control Power to Switchgear

Verify Electrical Breaker Operation

_ Open and close each breaker with breaker control switch

_ Open and close each breaker from remote terminals (if applicable)

_ Close breaker, trip circuit breaker utilizing protective relay (if applicable)

_ Ensure 86 LOR operates (if applicable)

_ Ensure breaker a and b contacts operate

Verify Metering

_ Functionally test metering devices by energizing circuits to rated values

4) Operational Controls

_ Test Automatic Transfer System (if applicable)

_ Other Operational Test

5) Final details after Witness Test are complete.

_ Complete mimic bus.

_ All remaining nameplates installed.

_ Drawers and doors aligned.

_ Danger labels and other warning stickers.

_ Vacuum and perform final cleaning of gear.

_ Touch up painting.

_ Check Shutter alignment.Voltaje elemento que Switchgear da testimonio de Procedimiento de la Prueba

Nmero del Orden general que ____________ Proyecta Nombre que _______________ Compagina ____of____

Artculo# _________________ Cliente Designation_________________________________

Voltaje elemento Switchgear

Procedimiento de la Prueba del testigo

El Procedimiento siguiente provee Eaton "Normas de la Prueba del Testigo" por ejecutar fbrica da testimonio de prueba.

Estos [guidelines] no cubren todo detalles, variaciones, o combinaciones del equipo, su instalacin, [checkout], y funcionamiento seguro. Se ejercer condescender afliccin con local, estado, y regulaciones nacionales, tan satisfactorio como prcticas de la seguridad por esta clase de equipo.

Se operar todo [switchgear] y prob por Eaton calificado personal como defini por OSHA 29CFR1910 [subpart] 5.

Suministr Informacin y Equipo

_ Equipo Personal Proteccionista

_ Proyecta plegador

_ Produccin Certificada Prueba Informe

_ Dibujos de la Construccin

_ da testimonio de Procedimiento de la Prueba

_ Producto linea contactos y nmeros del telfono

Prior a Comprobacin

1) Repaso:

_ dibujos de la Construccin asociaron con el ser del equipo prob

_ reglas de la seguridad del Sitio y procedimientos de la emergencia

Inspeccin y Procedimientos de la Prueba

Un FINAL REPASO De COMENTARIOS/ se CONDUCIRAN DEFICIENCIAS A CONCLUSION De COMPROBACION.1) Visual:

_ El informacin del placa de nombre del aparato es idntico con los dibujos del [switchgear].

_ Conveniencia y calibracin fecha de juegos de la prueba

_ ola grande del Circuito asegurarlos tiene el amperio propio, voltaje e interrumpe valuacin.

_ Verifica todo etiquetas del voltaje altas, UL etiqueta y ANSI requiri etiquetas es visible.

_ aparatos Auxiliares aparatos tal como proteccionistas, metros, se instalan interruptores del mando y alambraron.

_ Ese todo VT y CT proporciones propiamente corresponden a dibujos

_ Ese primero y valuaciones de la espoleta secundarias U ola grande del circuito se casan dibujos

_ escamadura del Metro y dibujos del fsforo del tipo

_ Verifica Switchgear Calentadores y Thermostat instal (si aplicable)

_ Verdad entrada del cable correcta posiciona [i.e]. entrada de la cima/ entrada del fondo

_ Verifica cable correcto lleva (si requiri)

2) Mecnico:

Verifique ola grande Atormenta Mecanismo

_ Atormenta ausente un ola grande en la posicin cerrada verificar [interlock] de la celda

_ ola grande en jaque atormenta fuera libremente sin interferencias

_ intenta atormentar ola grande en posicin cerrada verificar [interlock] de la celda

_ Atormenta ola grande a barras asegurar ola grande salta se descarga

Verifique Funcionamiento del ola grande Mecnico

_ Abre y cierra cada ola grande del ola grande cubre

_ Abre y cierra cada puerta del ola grande y cheque por interferencias

_ Abre y cierra cada puerta del Transformador Potencial (s) cheque por interferencias3) Elctrico:

La parada de la proteccin, [metering], y escenas del mando deben ser suministradas por el ingeniero del clientes o de un Sistema del Poder Estudia ejecut prior a comisionar.

Aplique Poder del Mando a Switchgear

Verifique Funcionamiento del ola grande Elctrico

_ Abre y cierra cada ola grande con ola grande controla interruptor

_ Abre y cierra cada ola grande de trminos remotos (si aplicable)

_ ola grande Estrecho, ola grande del circuito del viaje utiliza parada de la proteccin (si aplicable)

_ Asegura 86 LOR opera (si aplicable)

_ Asegura ola grande 'a' y 'b' se pone en contacto con opera

Verifique Metering

_ Functionally prueba aparatos del [metering] por dar energa a circuitos a tas valores

4) Operational Mandos

_ Prueba Automtico Transfiere Sistema (si aplicable)

_ Otro Operational Prueba

5) Final detalles despus de Prueba del Testigo son completos.

_ Completa autobs mmico.

_ Todo queda placa de nombre instalaron.

_ Cajones y puertas alinearon.

_ Peligro etiqueta y otro pegatinas de la advertencia.

_ Vaco y ejecuta limpieza conclusiva de vestido.

_ Toca pintura despierta.

_ alineacin de la contraventana en jaque.