Test Pack Flow Chart

1
PO UNIT-TEST PACK FLOW CHART e MMG Engineering MMG Construction MMG QA/QC MESAR QA/QC After Change Revised Drwgs in TP MESAR Const. SCEC Engg. Latest Drwg. Confirmation TP Book Preparation by system wise Yes " HT" Punch Items Latest Drwgs to be change in TP With Transmittal / Without Punch List Punch List Punch List Line Check with PMT No " HT" Punch Items With "HT" Punch Items (2) No " HT" Punch Items " HTA" Punch Item Clearance ( Only Copy) Line Check with PMT for "HTA" FIN & Test Confirmation With "HT" Punch Items (1) "HT" Punch item Clearance Line Check with PMT "HT Items" FIN & Test Confirmation Re-instatement Original Test Pack With "HTA" Punch Items ( Only Copy) No "HTA" Punch items Green File MESAR TP Const. MESAR TP Contrl. QA/QC MESAR TP Const. MESAR TP Const. MESAR TP Const. MMG TP Contrl. QA/QC 2 MESAR TP Const. MESAR TP Const. MMG TP Contrl. QA/QC Release for Painting & Insulation Sign off Sign Off MESAR TP Contrl. QA/QC Copy to PMT MESAR QA/QC PDF File. Yellow File MESAR TP Const. LINE CHECK MMG TP Contrl. QA/QC MMG TP Contrl. QA/QC 1 LINE CHECK LINE CHECK "HT" Punch List "HT" Punch List MESAR TP Contrl. QA/QC MMG TP Contrl. QA/QC MMG TP Contrl. QA/QC Sign off MMG Contsruction Immediately send to MESAR Const. Welding Summary Sheets Immediately send to MESAR QA/QC "HTA" Punch List

description

Hydrotest

Transcript of Test Pack Flow Chart

PO UNIT-TEST PACK FLOW CHART

e

MMG Engineering MMG Construction MMG QA/QC MESAR QA/QC

After Change Revised Drwgs in TP

MESAR Const. SCEC Engg.

Latest Drwg. ConfirmationTP Book Preparationby system wise

Yes " HT" Punch Items

Latest Drwgs to be change in TP

With Transmittal / Without Punch List

Punch List Punch List

Line Check with PMT

No " HT" Punch Items

With "HT" Punch Items (2)

No " HT" Punch Items

" HTA" Punch Item Clearance (Only Copy)

Line Check with PMT for "HTA"

FIN & Test Confirmation

With "HT" Punch Items (1)

"HT" Punch item Clearance

Line Check with PMT "HT Items"

FIN & Test Confirmation

Re-instatement

Original Test Pack

With "HTA" Punch Items (Only Copy)

No "HTA" Punch items

GreenFile

MESAR TP

Const.

MESAR TP

Contrl.QA/QC

MESAR TP

Const.

MESAR TP

Const.

MESAR TP

Const.

MMG TP

Contrl.QA/QC

2

MESAR TP

Const.

MESAR TP

Const.

MMG TP

Contrl.QA/QC

Release for

Painting &

Insulation

Sign off

Sign Off

MESAR TP

Contrl.QA/QC

Copy to PMT

MESAR QA/QC PDF

File.

YellowFile

MESAR TP

Const.

LINE CHECK

MMG TP

Contrl.QA/QC

MMG TP

Contrl.QA/QC

1

LINE

CHECK

LINE CHECK

"HT" Punch List "HT" Punch List

MESAR TP

Contrl.QA/QC

MMG TP

Contrl.QA/QC

MMG TP

Contrl.QA/QC

Sign off

MMG

Contsruction

Immediately send toMESAR Const.

WeldingSummarySheets

Immediately send toMESAR QA/QC

"HTA" Punch

List