Test on installed RPCs with the gas mixture. Preliminary results.

24
Test on installed RPCs with the gas mixture. Preliminary results. Alessandro Paoloni on behalf of the OPERA RPC Group (Bologna, LNF, LNGS, Napoli, Padova, Zagreb) OPERA collaboration meeting Hamburg 3-5 June 2004

description

Test on installed RPCs with the gas mixture. Preliminary results. Alessandro Paoloni on behalf of the OPERA RPC Group (Bologna, LNF, LNGS, Napoli, Padova, Zagreb) OPERA collaboration meeting Hamburg 3-5 June 2004. The first spectrometer in the Hall C. Environment parameters: - PowerPoint PPT Presentation

Transcript of Test on installed RPCs with the gas mixture. Preliminary results.

Page 1: Test on installed RPCs with  the gas mixture. Preliminary results.

Test on installed RPCs with the gas mixture.

Preliminary results.

Alessandro Paoloni

on behalf of the OPERA RPC Group

(Bologna, LNF, LNGS, Napoli, Padova, Zagreb)

OPERA collaboration meeting

Hamburg

3-5 June 2004

Page 2: Test on installed RPCs with  the gas mixture. Preliminary results.

The first spectrometer in the Hall C

Environment parameters:• T=16 oC (at the base of the spectrometer)• P~900 mbar (few mbar higher wrt external lab)• Dry=50-60% (wetter wrt external lab)

RPC layers1 11

RPC layers12 22

Easternside

Row 1

Row 7

Hall C lateral wall

To compare experimental results with data from ext. lab, rescale applied voltages to fixed T0=293 K and P0=900 mbar:

V=Vapplied*(T/T0)*(P0/P)

Page 3: Test on installed RPCs with  the gas mixture. Preliminary results.

Tests with nitrogen

For the installed RPCs validation, we kept the detector at 6.5 kV, below the discharge region, but above the operating voltage with the gas mixture:• Test the HV system found that an additional PET layer is needed for the insulation of HV electrodes from the strips• Test mechanical stresses by comparing the currents before and after the iron slab installation in case reduction of the filling material thickness

N2 Test

Page 4: Test on installed RPCs with  the gas mixture. Preliminary results.

Test with gas mixture

• We have the permission to use small quantities of the mixture Ar/C2H2F4/i-C4H10/SF6=75/20/4/1 in premixed bottles

•Test a RPC row (~9 m2) at a time, flushed at 5 refills/day

• The row is covered by a panel of 32 horizontal strips, served by 2 IC boards

Up to now tested the row n.1 of layers n.9,18 and 19

Page 5: Test on installed RPCs with  the gas mixture. Preliminary results.

Test set-up

• The strip panel is self-triggered using two Timing boards installed on the InterConnection boards • Each timing board is endowed with a double threshold discriminator acting on the analog sum of 16 strips• Threshold low = ~20 mV• Threshold high = 25 mV (40 mV in the first measurements)• 32 ADC channels used for measuring the charge induced in each strip• Also counting rates and currents are measured

Page 6: Test on installed RPCs with  the gas mixture. Preliminary results.

Test of the set-up in Frascati

• Used a small size old RPC prototype• Higher Pressure wrt GS lab expected operating voltages below 6 kV in Hall C

Counting rate

Induced charge

Page 7: Test on installed RPCs with  the gas mixture. Preliminary results.

Reference plots at the external lab

• RPC BES1451 under test at Ciocco facility for ‘‘ageing’’ studies at cosmic rays rate• MACRO FE boards used

Effect due to fast increase of the current with high resistivity ?

Chosen operating point:5.5 kV

Page 8: Test on installed RPCs with  the gas mixture. Preliminary results.

Operating currents in Hall CLayer n.9

Layer n.18 Layer n.19

• The currents at the operating point are below 350 nA, lower wrt to QC tests at external GS lab• Their increase is faster for the eastern RPC (near the lateral wall of Hall C)

Page 9: Test on installed RPCs with  the gas mixture. Preliminary results.

Counting rates in Hall C

Layer n.9

Layer n.19Layer n.18

• The counting rates at the operating point are of the order of few Hz/m2 (to be compared with 200-400 Hz/m2 at cosmic rays rate)• The counting rates are higher for the eastern RPC (near the lateral wall of Hall C)• There is not a plateau, but an exponential dependence on the operating voltage

Page 10: Test on installed RPCs with  the gas mixture. Preliminary results.

Threshold studies

The rates have been measured at 5.5 kV with the lower threshold at 20 mV

Good higher threshold stability till 60 mV

Page 11: Test on installed RPCs with  the gas mixture. Preliminary results.

Induced charge

The average induced charge at 5.5 kV is about 20 pC

Page 12: Test on installed RPCs with  the gas mixture. Preliminary results.

Induced charge: layer 9

Entire row Middle + western RPCs

Page 13: Test on installed RPCs with  the gas mixture. Preliminary results.

Induced charge: layer 18

Western RPC Middle RPC Eastern RPC

Page 14: Test on installed RPCs with  the gas mixture. Preliminary results.

Conclusions

Up to now we have tested 9 installed RPCs with the gas mixture Ar/C2H2F4/i-C4H10/SF6=75/20/4/1, observing:

1. Very low operating currents and counting rates

2. No plateau for the counting rate vs the voltage (reference to external lab. measurements essential for determining the operating point)

3. Current and rate higher for RPCs near the lateral side of Hall C

These results are a first indication of the goodness of the RPC installation procedure

More statistics needed (first installed rows, rows with filling material substituted)

Page 15: Test on installed RPCs with  the gas mixture. Preliminary results.

What from QC tests ? BE1074

7.9 ± 0.3

2.8 ± 0.4

2.021 ; 2.099

386 ; II

BIM1331

2.5 ± 0.6

0.92 ± 0.01

1.911 ; 1.988

464 ; II

BE1136

8.7 ± 0.2

0.45 ± 0.01

1.917 ; 1.973

568 ; OK

BES1710

1.7 ± 0.1

0.70 ± 0.01

1.965 ; 2.043

472 ; II

BI1653

3.8 ± 0.3

1.34 ± 0.04

1.864 ; 1.903

388 ; II

BES1698

5.7 ± 0.2

1.27 ± 0.02

1.950 ; 1.999

377 ; II

BES1551

2.7 ± 0.3

4.0 ± 0.3

2.004 ; 2.047

372 ; II

BI1220

14.1 ± 0.4

0.90 ± 0.02

2.031 ; 2.070

450 ; OK

BES1680

19.7 ± 0.2

0.94 ± 0.01

1.914 ; 1.977

530 ; II

Eastern side

Layer 9

Layer 18

Layer 19

RPC name di/dv (nA/kV)cm)V100 ; V500 (kV)Iop(nA); C.R. Q.R.

RPC name:Red=high temperature testGreen=low temperature test

Page 16: Test on installed RPCs with  the gas mixture. Preliminary results.

Strip signals (I)Strip

Ground

1 M pick-up

Page 17: Test on installed RPCs with  the gas mixture. Preliminary results.

Strip signals (II)

Adjacent strips

50 pick-up

Page 18: Test on installed RPCs with  the gas mixture. Preliminary results.

Strip signals (III)Central strip1 M pick-up

Ground1 M pick-up

Central strip differential read-out

Far strips50 pick-up

Page 19: Test on installed RPCs with  the gas mixture. Preliminary results.

Strip signals (IV)

Noise

Strip1 Mpick-up

Ground1 Mpick-up

Strip with differential read-out

Page 20: Test on installed RPCs with  the gas mixture. Preliminary results.

Induced charge: layer 9

Total induced charge

Reconstructed hit position

Entire rowMiddle + western RPCs

Up Down

Page 21: Test on installed RPCs with  the gas mixture. Preliminary results.

Induced charge: layer 18

UpDown

Western RPC Middle RPC Eastern RPC

Page 22: Test on installed RPCs with  the gas mixture. Preliminary results.

P = 1000 mbar

P = 900 mbar

Lower operating voltages expected at GS because of the lower pressure

Frascati test of the set-up

6.25 kV

5.65 kV

T = 20 oC

Page 23: Test on installed RPCs with  the gas mixture. Preliminary results.

Strip panel not covering the entire RPC and picking up signals outside its area (more signals at the edge of the panel)

Frascati test of the set-up

Page 24: Test on installed RPCs with  the gas mixture. Preliminary results.

Found a miscalibration of the nanoamperometers used in hall C (not OPERA standard): the currents are lower by a factor of about 2

Current on the negative electrode from nanoamperometers

Current on the positive electrode from power supply

Further investigations needed to understand and solve the problem