Terminal Expansion Project Phase Overview Level 0...L02 • Virgin Australia Lounge Relocation •...

2
INTERNATIONAL ARRIVALS BAG RECLAIM OFFICE DOMESTIC BAG RECLAIM INTERNATIONAL ARRIVALS WASTE GATE 19 GATE 18 GATE 16 GATE 15 GATE 14 GATE 13 GATE 12 GATE 20 GATE 21 SERVICE YARD FORECOURT D C G UNDERCROFT STORE OFFICE SECONDARY BAG INSPECTION STAFF & GOODS SCREENING Terminal Expansion Project Phase Overview EMIGRATION INTERNATIONAL SECURITY SCREENING WASTE INTERNATIONAL ARRIVALS GATE 19 GATE 18 GATE 16 GATE 15 GATE 14 GATE 13 GATE 12 GATE 20 GATE 21 INTERNATIONAL ARRIVALS TRANSIT IMMIGRATION VIP INTERNATIONAL LOUNGE OFFICE DUTY FREE ARRIVAL VIP DEPARTURES DUTY FREE RETAIL SOUTHPRECINCT PROVIDORE RETAIL FOOD KIOSK RETAIL FASHION ATURA HOTEL CHECK-IN HALL TERMINAL ENTRY ACCESS TO INTERNATIONAL DEPARTURES DEPARTURES DUTY FREE FAMILY DINING PREMIUM F&B DEDICATED INTERNATIONAL GATE 18 GATE 16 GATE 15 GATE 14 GATE 19 GATE 20 GATE 21 INTERNATIONAL RETAIL INTERNATIONAL F & B ACCESS TO INTERNATIONAL GATE LOUNGES THE INTERNATIONAL F & B AND RETAIL AREAS ARE EXPANDING INTERNATIONAL F & B VIRGIN LOUNGE RELOCATION INTERNATIONAL RETAIL Level 0 Level 1 Level 2 Timeline CURRENT BUILDING FOOTPRINT DETAILS OVERLEAF Q1 Q2 Q3 Q4 Q3 Q4 2018 2019 2020 2021 Q1 Q2 Q3 Q4 Phase 4 Phase 3 Phase 5 Q1 Q2 Q3 Q4 Phase 1 & 2

Transcript of Terminal Expansion Project Phase Overview Level 0...L02 • Virgin Australia Lounge Relocation •...

Page 1: Terminal Expansion Project Phase Overview Level 0...L02 • Virgin Australia Lounge Relocation • Northern Retail Concourse areas and associated Retail tenancies (base building) •

INTERNATIONAL ARRIVALSBAG RECLAIM

OFFICE

DOMESTIC BAG RECLAIM INTERNATIONAL ARRIVALS

WASTE

GATE 19 GATE 18 GATE 16 GATE 15 GATE 14 GATE 13 GATE 12GATE 20GATE 21

SERVICEYARD

FORECOURT

D

C G

UNDERCROFT

STORE

OFFICE

SECONDARY BAG INSPECTION

STAFF & GOODSSCREENING

Terminal Expansion Project Phase Overview

EMIGRATION

INTERNATIONAL SECURITY SCREENING

WASTE

INTERNATIONAL ARRIVALS

GATE 19 GATE 18 GATE 16 GATE 15 GATE 14 GATE 13 GATE 12GATE 20GATE 21

INTERNATIONAL ARRIVALS

TRANSIT

IMMIGRATIONVIP

INTERNATIONALLOUNGE

OFFICE

DUTY FREEARRIVAL

VIP

DEPARTURESDUTY FREE

RETAIL SOUTH PRECINCT

PROVIDORE

RETAIL

FOOD KIOSK

RETAIL

FASHION

ATURA HOTEL

CHECK-IN HALL

TERMINAL ENTRY

ACCESS TO INTERNATIONAL DEPARTURES

DEPARTURESDUTY FREE

FAMILYDINING

PREMIUM F&B

CLEANUP

STATION

DEDICATED INTERNATIONAL GATE 18

GATE 16 GATE 15 GATE 14GATE 19GATE 20GATE 21INTERNATIONAL RETAIL

INTERNATIONAL F & B

ACCESS TO INTERNATIONAL GATE LOUNGES

THE INTERNATIONAL F & B AND RETAIL AREAS ARE EXPANDING

INTERNATIONAL F & B

VIRGIN LOUNGE RELOCATION

INTERNATIONAL RETAIL

Level 0

Level 1

Level 2

Timeline

CURRENT BUILDING FOOTPRINT

DETAILS OVERLEAF

Q1 Q2 Q3 Q4Q3 Q4

2018 2019 2020 2021Q1 Q2 Q3 Q4

Phase 4

Phase 3

Phase 5

Q1 Q2 Q3 Q4

Phase 1 & 2

Page 2: Terminal Expansion Project Phase Overview Level 0...L02 • Virgin Australia Lounge Relocation • Northern Retail Concourse areas and associated Retail tenancies (base building) •

Terminal Expansion Project: Summary of worksPhases Phase

Description:Key Works Summary Description: Impacts: Result:

18/6/2018 to20/7/2020

Site Establishment

Site Mobilisation Traffic via Export Park Site compound established

Phase 1 & 2Q3 2018 toQ1 2020

New expanded building footprint area to north of Terminal

L00• Undercroft (part)• Northern Plant Rooms• Northern Screening• Goods & Staff Screening• Waste Management & Service Yard• Storage / Airside Offices areas• Virgin Australia Engineering

Relocation

L01• Border Agency Offices (part)

Level 01• Commercial Offices

L02• Virgin Australia Lounge Relocation • Northern Retail Concourse areas

and associated Retail tenancies (base building)

• Changes to Terminal concourse access during construction works adjacent to Gate 16 / 15

• Modified external pedestrian access to the Terminal around the construction site

• Modification to the Airside road access at northern end around Gates 16 / 15 / 14

• Virgin Australia Lounge & Engineering relocation

• Border Agency relocation to new L01 Offices (part)

• New Retail precinct open (part) to northern end

• New Northern Screening / Service Yard available

• Decanting of existing Aviation House tenants

Phase 3Q4 2019 toQ4 2020

International Arrival expansion & upgrades to L00 & L01 areas

L00• Existing Baggage belt extension and

second belt addition• Upgrade of Secondary Examination

Area (SEA)

L01• Stairs and vertical transportation

from Immigration to International Baggage claim area at L00

• Expansion of International Arrivals inbound Immigration

• Changes to passenger flows for International Arrivals through Immigration and Baggage claim areas

• Changes to the Border Force operations adjacent Immigration

• Aviation House demolition

• Staged works in discrete zones to enable ongoing International Arrival operations to be maintained

• Progressive relocation of Border Force Offices, Immigration and International Baggage Reclaim

• Improved facilitation for inbound International passengers

Phase 4Q2 2019 toQ1 2021

International Departures ex-pansion includ-ing new LAGS and Emigration

L01• International & VIP Lounges• Border Agency Offices (complete)• Emigration and LAGS expansion• Outbound Duty Free expansion

(partial)

L01• Relocate existing

International Lounge and Border Agency Offices refurbishment

• Relocate existing Emigration and LAGS from L02 to L01

• Staged works in discrete zones to enable ongoing Terminal operation to be maintained

• Complete consolidation of Border Agency Offices

• International Departures process commences from new L01 area

Phase 5Q4 2020 toQ2 2021

Completion of Retail Concourse Refurbishment

• Balance of L02 concourse Retail & amenities

• Outbound & Inbound Duty Free expansion (complete)

• Baggage Service Room• Undercroft (complete)• Forecourt

• PAX flows through to immigration, Emigration and concourse

• Working adjacent international lounge

• Stage works in discrete zones to enable ongoing operation

• Detail coordination of Hoarding plans to mitigate disruption

• Performance of work at night, low PAX times

• Potential for earlier staging to mitigate mobilisations