Term Project
-
Upload
samhita-prajapati -
Category
Documents
-
view
9 -
download
2
Transcript of Term Project
A. STREAMLINING PROGRAM MANAGEMENT TRACKING SYSTEM FOR ORIGINAL EQUIPMENT MANUFACTURERS
B. TIME STUDY OF THE MUFFLER END SPINNING MACHINE
Term Project
By,Samhita K. PrajapatiB.E. Production60012115020
Project Details
Objective: Streamlining Program
Management Tracking System for OEMs
Method: Creating a Dashboard Program
using MS Excel
Aim: To form a centralised Database
containing data of multiple projects.
Problem Statement
The Program Management Department has to manage a large number of projects simultaneously.
Monitoring of various projects becomes time consuming.
A centralised database which would be reviewed and updated monthly was desired.
Method
Dashboard is a single sheet displaying all the compiled data dynamically.
Visual Basic for Applications (VBA) language for MS Excel was used to create codes for dynamic programming of the various sheets.
Sheets
The Sheets designed for the “Project Health Report” are: Manager Input Pilot Paynter Customer Tooling and ED&T TAVA Status Customer Milestones Dashboard
Manager Input Sheet
Pilot Sheet
Paynter Sheet
Customer Tooling Sheet
Customer ED&T Sheet
TAVA Sheet
Status Sheet
Customer Milestones Sheet
Dashboard
Conclusion
The Project Health Report is a handy management tool.
It is user-friendly and can be used by anyone with minimal knowledge of MS Excel.
It is colour coded for quick analysis with financial data represented in the form of tables and charts.
Project Details
Objective: To conduct a time study of the Muffler
End Spinning Machine
Method: Video Time Study
Aim: To compute production target for each shift
of a working day
Introduction
A Time Study is conducted with the aim of boosting productivity rates.
Time study duration varies according to the product being manufactured.
Method study and Time study are usually conducted together.
It is initiated when: Desired productivity rate is not achieved An improvement is desired There is a change in layout/machinery A periodic review is to be conducted
The Process Layout
StorageEmbossin
gSpot
WeldingNotchin
g
Lock-Seaming
Flanging &
Stuffing
Welding (if
required)
End Cap Fitting
(if required)
EndSpinnin
g
Leakage Test
(if required)
FG Trolley
Method
Time and Method study was conducted in the following manner:
1. A video study of each of the individual operations in the defaulting manufacturing cell was conducted
2. The station with operating time much greater than machine cycle time was considered to be the bottleneck operation.
3. A thorough Method and Time Study is then carried out on the bottleneck operation to determine the cause of delay
Note: Always conduct a the study with a highly skilled operator manning the machine
Bottleneck
The Spinning Machine was found to have a much greater operating time.
It was selected for further study.
Machine Cycle Time = 22 seconds
General Operating Time = 39.4
seconds (avg)
Next Step
The End Spinning Machine was further studied.
The actions of the operator were divided into the following elements:- Walk, take muffler and load
on M/C. Take unloaded job and place
on table Press cycle start and observe
1 rotation Walk to LT & right LT value Unload job and put on table,
load new job, initiate test Check unloaded job and put
in FG trolley
The Table of Readings
Microsoft Office Excel Worksheet
Allowances
An operator will not perform his operation with 100% consistency.
The ISO Handbook has specified guidelines regarding allowances for the worker’s safety and welfare.
These allowances are calculated into the machining time.
Calculating Allowance
Microsoft Excel Worksheet
Cycle Time
Load 42Process 81 On Table & FixtureUnload 9Idle Time 0Allowance in seconds 29
Tea time Allowance in seconds 0
If all allowance is considered in Idle time, then only tea time allowance is applicable
Total cycle time in seconds 132Applicable cycle time 161.04
Actual Hourly Output (5% allowance) 57 min hour 21Shift Output 162
Cycle Time
Available Working Time
Time Calculation MinsA Total Shift Time 510Less Lunch Time 30B Available time for work 480
C Personal Need Allowance 5% 24
D Available time for work 456LessE Shift Start, PM, Inspection 10F Shift end Cleaning & Last off 10
GNet Working Time (for calculation of Output) 436
Shift I (7am – 3:30pm)
Time Available Time
Net Time including 5% personal need allowance
Net time (Tea time distributed)
Hourly Output
7-8 am 60 47 48 188-9 am 60 57 58 229-10 am 60 57 58 2210-11 am 60 57 58 2211-12 am 30 28.5 29 1112-1 pm 60 57 58 221-2 pm 60 47 48 182-3 pm 60 57 58 223-3:30 pm 30 18.5 19 7Shift I 480 426 436 162
Shift II (3:30pm – Midnight)
Time Available Time
Net Time including 5% personal need allowance
Net time (Tea time distributed)
Hourly Output
3:30-4 pm 30 18.5 19 74-5 pm 60 57 59 225-6 pm 60 42 43 226-7 pm 60 57 59 227-8 pm 60 57 59 118-9 pm 30 28.5 30 229-10 pm 60 57 59 1810-11 pm 60 57 59 2211-12 am 60 47 49 7Shift II 480 421 436 162
Shift III (Midnight – 7am)
Time Available Time
Net Time including 5% personal need allowance
Net time (Tea time distributed)
Hourly Output
12-1 am 60 47 47 181-2 am 60 57 57 212-3 am 60 57 57 213-4 am 30 28.5 29 114-5 am 30 57 57 215-6 am 60 57 57 216-7 am 60 47 47 18Shift I 390 350.5 350.5 131
Conclusion
A video study of the Muffler End Spinning Machine was conducted. Ideal machining time is 32 seconds
The Cycle Time for the entire Muffler Assembly Cell for Product X was calculated to be 161.04 seconds.
Hourly Output Rate for each shift are: 162 products in Shift I 162 products in Shift II 131 products in Shift III
Thank You