Tendering and Estimating Assignment 2

download Tendering and Estimating Assignment 2

of 26

Transcript of Tendering and Estimating Assignment 2

  • 7/28/2019 Tendering and Estimating Assignment 2

    1/26

    Tendering and Estimating

    Assignment 2

    Lecturer U. I. B. Daswatta

    Dr. Nirodha fernando

    CSCT2011214

  • 7/28/2019 Tendering and Estimating Assignment 2

    2/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 2

    Content

    Content ................................................................................................................................... 2

    Acknowledgement ................................................................................................................. 3

    Introduction ............................................................................................................................ 4

    Scenario.............................................................................................................................. 5

    Task 01 ....................................................................................................................................... 5

    Three major factors related to build up unit cost ............................................................... 5

    Material .......................................................................................................................... 5

    Labour ............................................................................................................................ 6

    Plant ............................................................................................................................... 6

    Overhead ........................................................................................................................ 7

    Task 02 ....................................................................................................................................... 8

    Material cost................................................................................................................... 8

    Plant and Equipments .................................................................................................... 9

    Labour ............................................................................................................................ 9

    Method Statement ............................................................................................................ 12

    Task 3 ....................................................................................................................................... 15

    Trench Excavation ........................................................................................................... 15

    Labour .......................................................................................................................... 16

    Reinforcement Beam ....................................................................................................... 16

    Material cost................................................................................................................. 17

    Labour .......................................................................................................................... 18

    Cement lime and sand plaster .......................................................................................... 19

    Material ........................................................................................................................ 20

    Labour .......................................................................................................................... 21

    PVC Gutter....................................................................................................................... 22

    Materials ...................................................................................................................... 22

    Labour .......................................................................................................................... 23

    Conclusion ........................................................................................................................... 25

    References ............................................................................................................................ 26

  • 7/28/2019 Tendering and Estimating Assignment 2

    3/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 3

    Acknowledgement

    To become a professional Quantity Surveyor we need theoretical knowledge as well asbetter knowledge on practical applications. Therefore, I would like to offer my sincere

    thanks to Colombo School of Construction Technology staff and grateful to all those who

    supported us in any respect during the completion of this assignment. I would like to offer

    my grateful thanks to our lecture Dr. Nirodha Fernando, and all the lectures guiding me

    toward valuable Assignment report. My special regards with very great attitude to my

    parents.

  • 7/28/2019 Tendering and Estimating Assignment 2

    4/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 4

    Introduction

    In this assignment, calculate the unit cost using operational method pricing and unit rate

    pricing. In the first task, describe the factor that related with the build up unit cost in the

    BOQ. The material, plant and labour are a main three factors according with unit cost.

    In the second task there are calculation unit rate for the work item using the operational

    method. In this task, use Building Schedule of Rates for pricing.

    In the third task describe the how to build up unit rate several work items using the Building

    Schedule of Rates.

  • 7/28/2019 Tendering and Estimating Assignment 2

    5/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 5

    Scenario

    The Government of Sri Lanka has proposed to implement an industrial zone in Northern

    Province as a part of rehabilitation program. The project includes infrastructure

    development (land development, water supply and drainage, electricity,

    telecommunication, road network, etc) and buildings such as factories, accommodation

    buildings, offices, stores, etc by different investors.

    Task 01

    In order to build up tender for the given project, collect data required to build up unit costs.

    (P4)

    Tender is a main document of new proposed project. To order to build up tender firstly

    client want make up the BOQ. To prepare BOQ for entire project the Quantity surveyor must

    need source of many data. Whoever prepare a BOQ they need gathered accurate data for

    prepare accurate BOQ. The overestimated and underestimated cost should bad result for

    contractor, rejecting tender or loses from the project. To built up unit price in BOQ based on

    several factors. In those factors material, labour and plant is became three major factors.

    Every unit rate in BOQ based on these three factors. When these factors changed the unit

    rate is also changed.

    Three major factors related to build up unit cost

    Material

    A material is something used to make things. When we speak about material, we mean

    physical substances. In a construction industry we used different types of materials. cement,

    sand, metal, steel and bricks normally used construction industry. The prices of material is

    based on its purchase price with allowances for delivery, offloading, storage and placing and

    wastage.

  • 7/28/2019 Tendering and Estimating Assignment 2

    6/26

  • 7/28/2019 Tendering and Estimating Assignment 2

    7/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 7

    Another factor is when they purchase or hire some plants can that plant and equipment

    transport to the site in safely of with out any barriers. Because the project is in ruler area,

    sometimes there road network is not in good condition. Therefore, the plant and machinery

    can damage or brake down within transport to the site.

    Overhead

    Every contractor looking for cover their overheads and get more profits from the project.

    Overhead and profit added to the cost of all work items to cover. The amount added for

    overheads and profit is normally given as a percentage and the percentage decided by the

    contractor. They want to look above factors and difficulties they can face during the project.

  • 7/28/2019 Tendering and Estimating Assignment 2

    8/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 8

    Task 02

    Build up unit rate for following work item using operational pricing method. Answer shall

    include method statement for the work item. (P6)

    Description Qty Unit

    Concrete, G20, in 150mm thick ground slab, poured against earth 90 m

    Assume that for concreting ground slab use ready mix concrete and placing with the pump

    machine and labours.

    According to the ICC Ready mix concrete rates, cost of1m3

    is Rs. 11,000/=.

    Pumping rate is Rs. 600/= for 1m3. (All transportation and other cost including above rates).

    Material cost

    Total Concrete volume = 90 m3

    Cost for 1m3

    of ready mix concrete = Rs. 11,000

    Cost for total concrete volume = 90 m3

    x Rs. 11,000

    = Rs. 990,000

    Water (Curing)

    90 gal for 1.42 m3

    Total gal = 90/1.42 x 90 m3

    = 5704.23 gal

    Cost for 1 gal = Rs. 0.50

    Total cost for vibrator = Rs. 0.50 x 5704.23 gal

    = Rs. 2852.11

    Total cost for material = Rs. 990,000 + Rs. 2852.11= Rs. 992,852.11

  • 7/28/2019 Tendering and Estimating Assignment 2

    9/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 9

    Plant and Equipments

    Pumping rate for 1m3

    = Rs. 600

    Total cost for pumping = Rs. 600 x 90 m3

    = Rs. 54,000

    According to BSR 0.5 day for 1.42 m3

    Total days = 0.5/1.42 x 90 m3

    = 31.69 days

    Cost for 1 day = Rs. 1500

    Total cost for vibrator = Rs. 1500 x 31.69 days

    = Rs. 47,535

    Total cost for plant = Rs. 54,000 + Rs. 47,535

    = Rs. 101,535

    Labour

    Labour for placing concrete (SK labour)

    0.5 days for 1.42 m3

    Total days for concreting = 0.5/ 1.42 x 90

    = 31.69 days

    Rate foe 1 day = Rs. 1200

    Total cost for mason = Rs.1200 x 31.69 days

    = Rs. 38,028.17

  • 7/28/2019 Tendering and Estimating Assignment 2

    10/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 10

    U/SK Labour

    1 days for 1.42 m3

    Total days for concreting = 1.5/ 1.42 x 90

    = 95.07 days

    Rate foe 1 day = Rs. 800

    Total cost for mason = Rs.800 x 95.07 days

    = Rs. 76,056.34

    SK Labour for Vibrator0.5 days for 1.42 m

    3

    Total days for concreting = 0.5/1.42 x 90

    = 31.69 days

    Rate foe 1 day = Rs. 1200

    Total cost for mason = Rs.1200 x 31.69 days

    = Rs. 38,028

    U/SK Labour for Curing

    0.5 day for 1.42 m3

    Total days for concreting = 0.5/1.42 x 90

    = 31.69 days

    Rate foe 1 day = Rs. 800

    Total cost for mason = Rs. 800 x 31.69 days

    = Rs. 25,352

    Total cost for Labour = Rs.38,028.17 + Rs.76,056.34 + Rs.38,028 + Rs.25,352

    = Rs. 177,464.51

  • 7/28/2019 Tendering and Estimating Assignment 2

    11/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 11

    Cost for Concreting = Rs. 992,852.11 + Rs. 101,535 + Rs. 177,464.51

    = Rs. 1,271,851.62

    Add 30% for overhead and profit = 30/100 x Rs. 1,271,851.62

    = Rs. 381,555.49

    Total cost for concreting slab = Rs. 1,271,851.62 + Rs. 381,555.49

    = Rs. 1,653,407.11

  • 7/28/2019 Tendering and Estimating Assignment 2

    12/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 12

    Method Statement

    Purpose:-

    The purpose of this method statement is to describe the construction procedures for theconcreting ground slab.

    Scope:-

    The works will incorporate the procedures necessary to execute the following items.

    Responsibilities of client and Contractor Attending personals Health and safety Plant, Machinery and equipment Preparing of work Work Methodology

    Project Detail:-

    Contractor : ICC (Pvt) Ltd

    Project Name and Address : Concreting Ground slab at Dental institute

    Client : Ministry of Health and Nutrition

    Responsibilities of client and contractors Provide and maintain access roads, hard standing for the machineries (a,level hard standing, capable of carrying the outrigger loads as specified in the Lifting

    Plan) and stacking area / off-loading area.

    Provide and maintain scaffolding of the working area, together withhandrails, guardrails, platforms or staging required for safe access and to preventoperatives from falling.

    Welfare facilities shall be made available to the flooring sub-contractor.

    Attending personals Appointed person: Name the appointed person to control of the lifting

    operations.

  • 7/28/2019 Tendering and Estimating Assignment 2

    13/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 13

    Safety Officer: Appointed person who will be control and inspect the safety atsite.

    QA / QC Engineer: person who appointed check the performance of theworks in relation to the method statement, approved drawings and material

    specifications. Site Engineer: Responsible for all activities carried on site and inspection all of

    works.

    Foreman: The foreman, will identify himself to the site management onarrival at site.

    Health and Safety Personal protective equipment: All workers will wear the following: - safety

    helmet, high visibility vest, gloves and safety footwear.

    Safety glasses/goggles; ear defenders; dust mask. All operatives and workerswill comply with any other specific site requirements.

    Site rules: All operatives and workers will be informed of the contractors siterules and obey with them.

    Specific site hazards: Any specific site hazards must be identified and dealwith prior to placing operations commencing on site. E.g., provide suitable

    protection to up-standing steel reinforcing starter bars or provide adequate

    bearing for props.

    Access to the work area: Access to the work area is the responsibility of thecontractor / client.

    Work at heights: The contractor / client must provide and maintainscaffolding of the working area, together with handrails, guardrails, platforms

    or staging required for safe access and to prevent operatives from falling.

    Welfare facilities: The contractor / client must provide access to welfarefacilities. The flooring subcontractor will make a first aid box available.

    Plant, Machinery and Equipment Tower crane / Mobile Crane Concrete Pumps Concreting Buckets Vibrators Wheelbarrows, etc. as applicable

  • 7/28/2019 Tendering and Estimating Assignment 2

    14/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 14

    Preparing for Works Request for design mix based the concrete grades specified on structural

    drawings from the Ready Mixed Concrete Supplier.

    Submit the proposed design mix to client / clients representative forapproval.

    Before the ending all setting out works and excavations, formwork and layingpolythene works are not commence.

    Compacting ground slab bottom using 10-ton vibrating rammer. Laying gauge 1200 polythene on the concreting surface clearly. Arrange the formwork around the edge of ground slab area using 15mm thk

    plywood and 2x2 timbers.

    After finishing all polythene, laying and forming formwork clear the surface. Arrange the all reinforced according to the drawing and maintain the cover

    blocks correctly. Inspection of structural members must do with client /

    clients representative.

    Work Methodology Take concrete cube samples from the truck for quantity specified. Mark the location of pour for concrete received on the site as reference and

    identification.

    Provide sufficient equipment, machinery and labour to carry out theconcreting works.

    Place concrete on selected locations using concrete pumps and / or craneassisted concrete buckets.

    Start concreting from a fresh location and continue continuous tocompletion.

    Place concrete from the lowest point to the final concrete level in oneoperation in horizontal layers.

    Compact concrete by mechanical vibrators. Certify that concrete is workedinto the corners of the structural members.

    After the concrete has set, carry out curing works by applying curingcompound.

  • 7/28/2019 Tendering and Estimating Assignment 2

    15/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 15

    Task 3

    Build up unit rates for following work items. (P7)

    Item Description Unit Rate

    2.A.2 Trench excavation depth exc. 1.0m and n.e. 2.0 m m

    3.B.5 Tor steel bar reinforcement, 16mm dia in beams at roof level Tonne

    3.G.2 16mm thick 1:1:5 cement, lime and sand plaster finish smooth with lime

    putty on internal walls

    m

    3.E.5 150mm dia half round PVC eaves gutter fixed o timber valance boardincluding gutter joiner, brackets, gutter head, mitres and end caps m

    Trench Excavation

    Assumptions;

    Firm soil excavation

    100% hand excavation

    Excavation quantity = 1.5 m x 0.6 m x 1 m

    = 0.90 m3

  • 7/28/2019 Tendering and Estimating Assignment 2

    16/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 16

    Labour

    According to BSR labour out put 0.71 m3

    per day

    Excavation quantity = 0.90 m3

    Total days for excavation = 1 / 0.71 m3x 0.90 m

    3

    = 1.27 days

    Rate for U/SK labour = Rs. 800 per day

    Cost for excavation = Rs. 800 x 1.27 day

    = Rs. 1014.08

    Allow 4% for tools = 4/100 x Rs. 1014.08

    = Rs. 40.56

    Total cost for excavation = Rs. 1014.08 + Rs. 40.56

    = Rs. 1054.64

    Add 30% for overhead and profit = 30/100 x Rs.1054.64

    = Rs. 316.39

    Unit rate for 1m3

    = Rs. 1054.64 + Rs. 316.39

    = Rs. 1371.03

    Reinforcement Beam

    Assumptions;

    10 m long beam Transport and unloading cost include the reinforcement rate Binding and bending cost include the labour rate

  • 7/28/2019 Tendering and Estimating Assignment 2

    17/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 17

    Length of bars

    10000Ddt 2/30 60

    9940

    Add hook 2/12/16 384

    10324

    Add lap 40/16 640

    10964

    Material cost

    Length of bar = 10.96 m

    Nr of bars in beam = 6

    Total length of bars = 65.78 m

    Unit weight of 16 mm bar = 1.58 kg

    Total weight of bars = 65.78 m x 1.58 kg

    = 103.94 kg

    16 mm dia reinforcement 1tonne is Rs. 130,000

    Cost of bars = Rs. 130,000/ 1000 kg x 103.94 kg

    = Rs. 13512.20

    Add 1.5% spaces = 1.5/100 x 13512.20= Rs. 202.68

    Add 3% tools = 3/100 x 13512.20

    = Rs. 405.37

    = Rs. 13512.20 + Rs. 202.68 + Rs. 405.37

    = Rs. 14120.25

  • 7/28/2019 Tendering and Estimating Assignment 2

    18/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 18

    According BSR binding wire 1.5 kg per 50 kg

    Total weight of binding wire = 1.5 kg/50 kg x 103.94 kg

    = 3.12 kg

    Cost for binding wire = Rs. 185 x 3.12 kg

    = Rs. 577.20

    Total material cost = Rs. 14,120.25 + Rs. 577.20

    = Rs.14,697.45

    Labour

    SK labour, binding and bending 50 kg per day

    Total days work = 1/50 kg x 103.94 kg

    = 2.08 days

    Rate for SK labour = Rs. 1500

    Cost for SK labour = Rs. 1500 x 2.08 days

    = Rs. 3118.20

    U/SK labour, binding and bending 50 kg per day

    Total days work = 1/50 kg x 103.94 kg

    = 2.08 days

    Rate for SK labour = Rs. 1100

    Cost for SK labour = Rs. 1100 x 2.08 days

    = Rs. 2288

    Total labour cost = Rs. 3118.20 + Rs. 2288

    = Rs. 5406.20

  • 7/28/2019 Tendering and Estimating Assignment 2

    19/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 19

    Cost for 16mm dia reinforcement beam = Rs. 14,697.45 + Rs. 5406.20

    = Rs. 20,103.65

    Add 30% over head and profit = 30/100 x Rs. 20,103.65

    = Rs. 6031.10

    Add 10% wastage = 10/100 x Rs. 14,697.45

    = Rs.1,469.75

    Total cost foe beam = Rs.20,103.65 + Rs.6031.10 + Rs.14469.75

    = Rs. 27,604.50

    Unit rate for 1 tonne = Rs. 27,604.50/ 103.94 kg x 1000 kg

    = Rs. 265,581.10

    Cement lime and sand plaster

    Assumptions;

    Total internal wall length is 100m and height is 3m

    1 Sq = 9.29 m

    2

    1 kg = 0.02 Cwt

    Total wall area = 100 m x 3 m

    = 300 m2

  • 7/28/2019 Tendering and Estimating Assignment 2

    20/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 20

    Material

    Cement

    According BSR 0.8 bag for 1 sq

    Nr of cement bags = 0.8/ 9.29 m2

    x 300 m2

    = 25.83 bags

    = 26 bags

    Cost for cement = 26 x Rs. 940

    = Rs. 24,440

    SandAccording BSR 0.07 cub per 1 Sq

    Volume of sand = 0.07/9.29 m2

    x 300 m2

    = 2.26 cub

    Cost for sand = 2.26 cub x Rs. 9000

    = Rs. 20,344.46

    Slaked lime

    According BSR 0.66 Cwt per 1 Sq

    = 1 kg/0.02 Cwt x 0.66 Cwt

    = 33 kg

    Volume of slaked lime = 33 kg/ 9.29 m2

    x 300 m2

    = 1065.66 kg

    Cost for slaked lime = Rs. 300/50 kg x 1065.66 kg

    = Rs. 6,393.96

  • 7/28/2019 Tendering and Estimating Assignment 2

    21/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 21

    Water

    According BSR 10 gal per 1 Sq

    Volume of water = 10 gal/ 9.29 m

    2

    x 300 m

    2

    = 322.93 gal

    Cost for water = 322.93 gal x Rs. 5

    = Rs. 1,614.64

    Total cost for material = Rs.24,440 + Rs.20,344.46 + Rs.6393.96 + Rs.1614.64

    = Rs. 52,753.06

    Labour

    According BSR SK labour 1.5 days for 1 Sq

    Total days of SK labour worked = 1.5 days/9.29 m2

    x 300 m2

    = 48.44 days

    Cost for SK labour = 48.44 days x Rs. 1200

    = Rs. 58,127.02

    According BSR U/SK labour 1.5 days per 1 Sq

    Total days of SK labour worked = 1.5 days/9.29 m2

    x 300 m2

    = 48.44 days

    Cost for SK labour = 48.44 days x Rs. 900

    = Rs. 43,596

    labour cost = Rs. 58127.02 + Rs. 43,596

    = Rs. 101,723.02

    Add 4% for tools and scaffoldings = 4/100 x Rs. 101,723.02

  • 7/28/2019 Tendering and Estimating Assignment 2

    22/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 22

    = Rs.4068.92

    Total labour cost = Rs. 101,723.02 + Rs. 4068.92

    = Rs. 105,791.94

    Cost for plastering = Rs. 52,753.06 + Rs. 105,791.94

    = Rs. 158,545

    Add 30% overhead and profit = 30/100 x Rs. 158,545

    = Rs. 47,563.50

    Add 5% wastage = 5/100 x 52,753.06

    = Rs. 2637.65

    Total cost for plastering = Rs.158,545 + Rs.47,563.50 + Rs. 2637.65

    = Rs. 208,746.15

    Unit rate for 1 m2

    = Rs.208,746.15/300 m2

    x 1 m2

    =Rs. 695.82

    PVC Gutter

    Materials

    According BSR all Quantities for 8m length

    150 mm thk gutter (4m length) = 2 Nos

    Cost for gutter = Rs. 800.00 x 2

    = Rs. 1600.00

    Gutter brackets = 17 Nos

    Cost for brackets = Rs.15.00 x 17

    = Rs. 255.00

  • 7/28/2019 Tendering and Estimating Assignment 2

    23/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 23

    Gutter joiner = 1 Nos

    Cost for gutter joiner = Rs. 300.00 x1= Rs.300.00

    End caps = 2 Nos

    Cost for end caps = Rs. 85.00 x 2

    = Rs.170.00

    Gutter head = 1 Nos

    Cost for gutter head = Rs. 650.00 x 1

    = Rs. 650.00

    9mm brass screws = 34 Nos

    Cost for screws = Rs. 2.50 x 34

    = Rs. 85.00

    Solvent cement = 20 gms

    Cost for solvent cement = Rs. 1.50 x 20

    = Rs. 30.00

    Total material cost = Rs.3090.00

    Labour

    SK labour = 0.5 days

    Cost for SK labour = Rs.1000.00 x 0.5

    = Rs.500.00

  • 7/28/2019 Tendering and Estimating Assignment 2

    24/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 24

    U/SK labour = 0.5 days

    Cost for U/SK labour = Rs. 800.00 x 0.5

    = Rs. 400.00

    Labour cost = Rs. 500.00 + Rs. 400.00

    = Rs. 900.00

    Add 5% for plant and scaffolding = 5/100 x Rs. 900.00

    = Rs. 45.00

    Add 3% for tools = 3/100 x Rs. 900.00

    = Rs.27.00

    Total labour cost = Rs. 900.00 + Rs. 45.00 + Rs. 27.00

    = Rs. 972.00

    Cost for gutter fixing = Rs. 3090.00 + Rs. 972.00

    = Rs. 4062.00

    Add 27% overhead and profit = 27/100 x Rs. 4062.00

    = Rs. 1096.74

    Total cost for fixing gutter = Rs. 4062.00 + Rs. 1096.74

    = Rs. 5158.74

    Unit rate for 1m = Rs. 5158.74/8 m

    = Rs. 644.84

  • 7/28/2019 Tendering and Estimating Assignment 2

    25/26

    HND In Quantity Surveying and Construction Economics

    CSCT 2011214 Page 25

    Conclusion

    The project Quantity surveyor is the main character in tender process. He wants to prepare

    BOQ and pricing it. Before the build up unit rate he want gathered several data according

    with the unit rate. Build up unit rate without any information that must harm to contractor.

    Because the overestimated and underestimated cost should, bad result for contractor,

    rejecting tender or loses from the project. To build up unit price in BOQ based on several

    factors. In those factors there are three main factors called material, labour and plant.

    Collecting data above those three factors much needed is in Sri Lanka day by day there are

    price fluctuation in the market. Therefore that directly accordance with unit rate. Building

    Schedule of Rate is suitable for pricing in every workstation.

  • 7/28/2019 Tendering and Estimating Assignment 2

    26/26

    HND In Quantity Surveying and Construction Economics

    References

    Building Schedule of Rates

    www.safetyculture.com.au/...method-statements/.../concrete_preparati.