TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter...

18
TENDER NOTICE Sealed tenders affixed with revenue stamp of Rs. 5/- are invited for and on behalf of Vice Chancellor, Islamic University of Science & Technology(IUST), Awantipora from OEM/Authorized Dealers/Distributors of OEM, who have been in the said business for at least three (3) years, for the supply of Laboratory Equipment’s for Department of Mechanical Engineering. The Tender document along with the detailed specification can be downloaded from University website (www.Islamicuniversity.edu.in). The last date for the submission of the tender document is 20 th of July 2017 before 1400 hrs in the Office of Estates, IUST campus Awantipora. Sd/- Member Secretary (CPC) No. IUST/CPC/Tender-Adv/17/42 Dated: 04-07-2017

Transcript of TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter...

Page 1: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

TENDER NOTICE Sealed tenders affixed with revenue stamp of Rs. 5/- are invited for and on behalf of Vice Chancellor, Islamic University of Science & Technology(IUST), Awantipora from OEM/Authorized Dealers/Distributors of OEM, who have been in the said business for at least three (3) years, for the supply of Laboratory Equipment’s for Department of Mechanical Engineering. The Tender document along with the detailed specification can be downloaded from University website (www.Islamicuniversity.edu.in). The last date for the submission of the tender document is 20th of July 2017 before 1400 hrs in the Office of Estates, IUST campus Awantipora.

Sd/- Member Secretary (CPC)

No. IUST/CPC/Tender-Adv/17/42 Dated: 04-07-2017

Page 2: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

TENDER DOCUMENT FOR SUPPLY OF EQUIPMENTS/ ITEMS FOR DEPARTMENT

OF MECHANICAL ENGINEERING.

TERMS AND CONDITIONS:

1. The sealed envelope superscripted as “TENDER FOR DEPARTMENT OF MECHANICAL ENGINEERING” should be addressed to Assistant

Registrar (Estates), Islamic University of Science and Technology, Awantipora, Kashmir.

2. The last date of receipt of tender is 20th July 2017 at 1400 hrs.

3. The tenderer should be Original Equipment Manufacturer (OEM) / Authorized Dealer /Distributor of OEM who have been in the said business for at

least three (3) years. Tenderers quoting as Authorized Dealer/Distributors of the manufacturer will be considered provided the tenderer furnishes

Authorization from the Manufacturer.

4. The tenderer must be in satisfactory operation for at least 3 (three) years as on 31st March 2017 and must be providing annual maintenance services for

the equipments where ever required.

5. The tenderer should submit a copy of the latest VAT / Sales tax clearance certificate.

6. Prices quoted by the tenderers should include all local taxes, VAT, duties, levies, transportation costs, insurance costs, etc.

7. The University reserves the right to accept or reject any or all Tenders without assigning any reasons there for. Any attempt of negotiation on the part

of Tenderer to influence by any means will render the tender liable for exclusion from consideration.

8. The Tender should be accompanied with Earnest Money Deposit (EMD) of 2% of the tendered value in the shape of CDR of any nationalised Bank

drawn in favour of “Islamic University of Science and Technology”, payable at Awantipora, Pulwama (J&K). Tender without EMD will not be entertained.

9. The tenderer should quote the rates both in figures and words without cuttings and over writing on the prescribed format and the rate should be inclusive

of all taxes and charges. No fluctuation in the rates is permitted during the currency of the tender.

10. Delivery should be FOR Islamic University of Science and Technology, Awantipora Pulwama (J&K).

11 The equipments / items should be supplied within 01 (One) month from the date on which the order is given.

12. The University reserves the right to reduce or increase the quantity of item at any time.

13. Tender notice and tender document can be downloaded from University website (www.islamicuniversity.edu.in).

14. The tender should be submitted on the format provided by the university.

15. The Validity of tender should be 90 days.

16. Tenders without the following shall not be entertained:

a. EMD of 2% of the tendered value in the shape of CDR of any nationalised Bank in favour of “Islamic University of Science and Technology” payable

at Awantipora, Pulwama (J&K).

b. Copy of the latest VAT / sales tax clearance certificate.

c. Copy of being Authorized distributor / dealer from the OEM / Manufacturer.

d. Proof of being in satisfactory operation for at least 3 (three) years as on 31st March 2017.

e. Tender document downloaded from the University website should be accompanied by a demand draft (non – refundable) of Rs. 1000/- (one thousand)

in favour of “Islamic University of Science and Technology” payable at Awantipora, Pulwama (J&K).

f. Tender document should be duly signed and stamped by the supplier.

I am agreeable to all the terms and conditions mentioned above.

Signature of the tenderer

Page 3: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

1. Theory of Machines Lab

S.No.

Equipment Specifications Qty Total price

1 Mechanism Models 1. Crank and Connecting Rod Model

2. Crank and Slotted Link Model

3. Four Bar Link Mechanism

4. Pantograph

5. Scotch Yoke Mechanism

6. Whitworth Quick Return Mechanism

7. Geneva Mechanism

8. Kinematic Pair models

1 each

2 Gear Models 1. Spur, Helical, Bevel

2. Rack and Pinion

3. Worm and wheel

4. Gear Train (Spur)

5. Epicyclic Gear Train (Sun and Planet Type)

6. Differential Gear

1 each

3 Cam and Follower

Models

1. Plate CAM with flat faced reciprocating follower

2. Tangent CAM with Roller Oscillating Follower

3. Cylindrical CAM with translating follower

4. Translating CAM with reciprocating knife edge follower

5. End CAM with translating follower

6. Harmonic Motion

7. 7. Triangular Eccentric CAM

1 each

Page 4: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

4 Clutch and Brake

Models

1. Clutch (Single Plate)

2. Clutch (Multi Plate)

3. Double Shoe Brake

4. Band and Block Brake

5. Disc Brake (Working)

6. Internally Expansion Brake

7. Hydraulic Brake Unit (two brake

drum)

1 each

5 Drives Models 1. Flat Belt Pulley

2. V-Belt Pulley

3. Chain Drive

4. Friction Wheel Drive

1 each

6 Couplings Models 1. Hooke's Coupling

2. Oldham Coupling

3. Universal Coupling

4. Flanged Coupling

5. Flexible Coupling

1 each

7 Bearings Models 1. Ball bearing

2. Roller bearing

3. Taper bearing

4. Thrust bearing

5. Ball bearing set

6. Swivel bearing

7. Brackets

8. Journal bearing

9. Plummer Block

10. Footstep bearing

1 each

8 Universal Governor

Apparatus

The apparatus should enable

performing following experiments: 1

Page 5: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

1. The effect of varying mass of center sleeve

2. The effect of varying rotating mass

3. The determination of characteristic curves of sleeve

position against the speed of

rotation

4. The effect of varying the

initial spring compression The

apparatus should include four

different types of governor

mechanism with spring and

weights:

a. Watt Governor

b. Porter Governor/Proell

c. Hartnell Governor

Additionally a digital tachometer to

measure - spindle speed should be

included.

9 Motorized

Gyroscope

The Motorized Gyroscope setup should

enable demonstration of relationship

between applied torque and the rate

of direction of rotation. The

apparatus should consist of a rotor

mounted in bearings which should be

free to rotate about

a. Its own axis

b. Axis of precession

c. c. Axis of gyroscopic couple

1

Page 6: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

10 Coriolis Component

of Acceleration The setup should enable study of

Coriolis component of acceleration at

various speeds of rotation and water

flow rates.

The setup should include standard

components including:

1. Main Tank: MS/Fiber Glass Lining

2. Rotating arms: 9mm/6mm orifice dia., 300mm long

3. Rotameter: 300 to 3000 LPH

4. Electric Motor: 0.5HP/1500 RPM

5. Mono-block Pump

6. Control Unit

7. Rigid Support Structures

1

11 Universal

Vibration

Apparatus

The apparatus should enable

conducting of various experiments to

illustrate and verify the principles

and relations involved in the study

of vibrations. List of experiments

that should be enabled with the

apparatus:

1. Simple Pendulum

2. Compound Pendulum

3. Bi-filler Suspension

4. Longitudinal Vibration system

1

Page 7: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

5. Free equivalent spring mass system

6. Forced equivalent spring mass system

7. Torsional vibration of single rotor system

8. Torsional vibration of double rotor system

9. Damped torsional vibration of single rotor system

10. Forced damped torsional

vibrations

11. To study the forced lateral

vibration of beam for different

damping

12 Whirling of Shaft

Apparatus

The apparatus should enable

demonstration of the phenomenon of

whirling of shaft with single rotor.

Specification:

1. Test shaft: Three diameter combinations of 2 No. each.

2. Bearing to provide end conditions: (a) both ends fixed

(b) one end fixed and one end

free

3. Drive motor < 0.5 HP

4. Sturdy base

1

13 Static and Dynamic

Apparatus

The apparatus should enable

performing experiments for balancing

a rotating mass system. The apparatus

1

Page 8: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

should consist of SS shaft fixed in a

rectangular frame. Experimental

abilities:

1. To balance masses statically and dynamically of a single rotating

mass system

2. To observe the effect of unbalance in a rotating mass

system Should include standard attachments

including:

a. Drive motor with speed control

b. Balancing weights: 4No.s, SS

c. Rotating shaft: SS

Page 9: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

2. Applied Thermodynamics Lab

S.No.

Equipment Specifications Qty Total price

1

Separating

Throttling

Calorimeter With

Boiler & Condenser

Separating Throttling Calorimeter with

Boiler & Condenser:

The equipment should enable following

experiments to be performed:

a) Dryness Fraction of steam

b) Efficiency of boiler

c) Heat Balance sheet

The equipment/system should consists

of Base Stand, Steam boiler,

Separating Calorimeter, Throttling

Calorimeter, Float Switch, Steam

Condenser, Measuring jar, Temperature

Controller, Electric heaters, Pressure

relief valve, Pressure gauges,

Temperature Indicator, Temperature

sensors, Wattmeter, Control Panel.

Boiler Specifications:

1

Page 10: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

1. Material: M.S Shell with Glass wool Insulation

2. Min. Capacity: 20 Kg/sec Mass flow rate

3. Min. Pressure: 5 Bar

4. Float Switch: To Prevent Dry Heating of Boiler

5. Water Heaters Min. Capacity: 10 kW

6. Separating Calorimeter Material:

S.S.

7. Throttling Calorimeter Material:

S.S.

8. Steam Condenser Min. Capacity: 20

kg/hr

2

Steam Power Plant

Steam Power Plant Unit should help the

students to understand the complete

system of a Thermal Power Plant. The

Unit should have the following minimum

specifications:

1. Boiler heater capacity: 6 KW

2. Steam generation capacity: 400

kg/hr from and at 100°C

3. Steam turbine capacity: 2.5 hp

output with casing of CI/MS

4. Eddy Current Dynamometer capacity:

2.5 hp, with speed: 3000 rpm

1

Page 11: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

5. Fuel tank capacity: 100

litres, made from MS sheet

with top hinged lid

6. Feed water tank: Overhead

tank –

750 litres (HDPE like sintex)

7. Steam Condenser

8. Water Softner

9. Steam Calorimeter: Separating

& Throttling calorimeter with

insulated separator &

throttling unit gauge glass

for level with valve set.

10. Circulation water pump: Mono

block 2.0 hp,

11. Condensate Extraction cum

Vacuum Pump: Reciprocating type, 0.5 hp

12. Turbine control panel: Made

from square tubes and MS

sheets double coloured powder

coated.

13. Digital RPM indicator with

controller, relay, PNP speed

sensor.

3

Two stage air

compressor test rig

The unit should enable determination of

volumetric efficiency and isothermal

efficiency at various discharge

pressures. The unit should contain:

1. Air compressor - Double cylinder, two-stage type driven by a 2-hp

1

Page 12: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

three-phase motor mounted on air

receiver provided with delivery

valve.

2. Air tank and orifice with water

manometer for air intake

measurement.

3. Pressure gauges at outlet on both

stages.

4. Digital temperature indicator.

5. Energy meter to measure input

power.

4 Digital bomb

calorimeter

Bomb Calorimeter outfit should provide

method for determination of heat of

combustion of organic matter and the

calorific value and Sulphur content of

solid and liquid fuel. The outfit

supplied shall be complete for analysis

as per the method recommended by IS 1360

II or BS 1016.

Specifications:

1. Calorimeter Vessel with bomb

support, Water jacket, Combined

Lid for calorimeter vessel and

water jacket, Stirrer, Connecting

Leads, Connecting tube to connect

bomb & pressure gauge.

1

Page 13: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

2. Connecting tube with fine

adjustment valve, to connect

pressure gauge, pressure gauge on

stand, Spanner for oxygen tube

connection, Ignition Wire, (2

meters) Nichrome, Cotton thread.

3. Stand for bomb lid, Hook for

lifting bomb, stainless steel

Crucible, Gelatine capsules, Gas

release valve, Bomb firing unit,

Vibrator, Timer, Benzonic acids.

'O' Ring Big, 'O' Ring Small, 'O'

Ring for Stirrer Valve for Bomb,

Valve Kay.

4. Complete with Instruction manual.

5 Boiler Models 1. Lancashire Boiler

2. Cornish Boiler

3. Babcock and Wilcox Boiler

4. Locomotive Boiler

5. Cochran Boiler

6. Vertical Water Tube Boiler

7. Sterling Boiler

8. Nestler Boiler

9. Steam Engine with a Boiler

1 each

6 Sectional working

models 1. Gas Turbine or Turbojet Engine

2. Wankel Engine

1 each

Page 14: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

3. Heat Transfer Lab

S.No.

Equipment Specifications Qty Total price

1

Composite walls

apparatus

The apparatus should enable the

measurement of the conductivity and

resistance of composite walls. The

setup should include:

1. Heater Assembly

2. Test specimen/Plates

a) M.S. plates of 2 nos.

b) Bakelite plates 2 nos.

c) Brass Slabs/Wood 2 nos.

3. Set of thermocouples

4. Digital Temp. Indicator

5. Dimmerstat

6. Main On/Off Switch

7. An appropriate Voltmeter and

Ammeter

1

2

Critical radius of

insulating material

The apparatus should enable

measurement of critical radius of the

insulating material. The setup should

include:

1. Cylindrical glass vessel/G.I. Pipe with appropriate heaters and

insulating materials

2. Digital Thermometer

1

Page 15: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

3. Necessary switches and controls

4. Dimmerstat

5. An appropriate Voltmeter and

Ammeter

3

Natural Convection

Heat Transfer

Apparatus

The setup should enable determination

of overall heat transfer coefficient

and local transfer coefficients in

natural convection at various heat

transfer rates. The apparatus should

include:

1. Pipe: Brass/SS with Min. OD 38mm, 500mm long with appropriate

heater

2. Thermocouples fitted along with the length of pipe for

temperature measurement

3. Digital Temperature Indicator

4. Dimmerstat

5. Main On/Off Switch

6. An appropriate Voltmeter and

Ammeter

1

4

Pin Fin Apparatus

The apparatus should enable testing of

pin fin in both natural as well as

forced convection, in addition to the

determination of temperature

distribution along the length and

1

Page 16: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

natural and forced heat transfer

coefficients, etc.

1. Should include three pin fins: MS/Brass/Al

2. Appropriate channel

3. Thermocouple set

4. A band heater (Min. 300W) to heat the pin fin

5. Digital temperature indicator

6. Dimmerstat

7. Main On/Off Switch

8. An appropriate Voltmeter and

Ammeter

5

Emissivity Measurement Apparatus

The apparatus should enable

measurement of emissivity of test

surfaces. The apparatus should

include:

1. Test plate and reference plate with min. 140mm dia.

2. Min. Heater Capacity: 250W

3. Plate material: Aluminum/Brass

4. Thermocouples

5. Voltmeter and Ammeter for input measurement to heaters through a

selector switch

6. Separate dimmers for both the plates

7. Multichannel digital temperature

indicator

1

Page 17: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

6 Concentric tube heat

exchanger

The apparatus should enable

determination of heat exchanged LMTD

and effectiveness of the equipment.

The apparatus should include:

1. Inner copper tube ID: 12.7mm, and outer GI Pipe ID: 15mm and

approx. 1.5m length

2. Thermometers: 4 nos.

3. Measuring flask: 1 Ltr capacity

4. Geyser: 3kW Single phase

1

7 Shell & tube heat

exchanger(water to

water)

Shell & tube heat exchanger (water to

water) should be able to measure

overall heat transfer coefficient and

effectiveness. The apparatus should

include:

1. Shell: At least 200mm dia., 5mm thick and at least 750mm long MS

pipe

2. Tubes: Copper or seamless MS tubes with appropriate diameter

and length

3. Min. water heater capacity: 2kW

4. Thermocouple for temperature measurement and appropriate

digital temperature indicator

5. Valves to control hot and cold water flow

6. Rota meters (may be quoted as

optional)

1

Page 18: TENDER NOTICE - Islamic University of Science & · PDF fileSeparating Throttling Calorimeter with Boiler & Condenser: The equipment should enable following experiments to be performed:

Format for Quoting Prices

S. No Name of the

Experiment/Equipment

Specifications Quantity Price

Quoted

1

2

3

4

5

6

7

8

9

10.

11.

12.

13

14

15

16

17

18

19