KINGDOM OF THAILAND ROYAL IRRIGATION DEPARTMENT MINISTRY OF AGLICULTURE AND COOPERATIVES TENDER AND CONTRACTING DOCUMENTS FOR THE FLOOD PREVENTION PROJECT OF EAST SIDE OF THE PASAK RIVER IN AYUTTHAYA VOLUME II TENDER DRAWINGS OCTOBER 2012 CTI ENGINEERING INTERNATIONAL CO., LTD. TOKYO, JAPAN

Transcript of TENDER AND CONTRACTING DOCUMENTS FOR THE ...BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 9/18) KM-FG-036...

  • KINGDOM OF THAILAND

    ROYAL IRRIGATION DEPARTMENT MINISTRY OF AGLICULTURE AND COOPERATIVES

    TENDER AND CONTRACTING DOCUMENTS FOR

    THE FLOOD PREVENTION PROJECT OF EAST SIDE OF THE PASAK RIVER IN AYUTTHAYA

    VOLUME II

    TENDER DRAWINGS

    OCTOBER 2012

    CTI ENGINEERING INTERNATIONAL CO., LTD. TOKYO, JAPAN

  • TITLE DWG NO. TITLE DWG NO.

    GENERAL PLAN BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL LEFT 1/4) KM-FG-049

    GENERAL MAP GP-001 BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL LEFT 2/4) KM-FG-050

    GENERAL NOTE GP-002 BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL LEFT 3/4) KM-FG-051

    KRA MANG FLOODGATE BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL LEFT 4/4) KM-FG-052

    OVERALL LAYOUT (1/2) KM-FG-001 BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL RIGHT 1/4) KM-FG-053

    OVERALL LAYOUT (2/2) KM-FG-002 BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL RIGHT 2/4) KM-FG-054

    PLAN KM-FG-003 BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL RIGHT 3/4) KM-FG-055

    FRONT VIEW AT PASAK RIVER SIDE (1/3) KM-FG-004 BAR ARRANGEMENT (PART - U-SHAPED FLOODWALL RIGHT 4/4) KM-FG-056

    FRONT VIEW AT PASAK RIVER SIDE (2/3) KM-FG-005 BAR ARRANGEMENT (PART - DRAINAGE GATE 1/3) KM-FG-057

    FRONT VIEW AT PASAK RIVER SIDE (3/3) KM-FG-006 BAR ARRANGEMENT (PART - DRAINAGE GATE 2/3) KM-FG-058

    FRONT VIEW AT KRA MANG CANAL SIDE (1/2) KM-FG-007 BAR ARRANGEMENT (PART - DRAINAGE GATE 3/3) KM-FG-059

    FRONT VIEW AT KRA MANG CANAL SIDE (2/2) KM-FG-008 BAR ARRANGEMENT (PART - WING WALL LEFT) KM-FG-060

    LONGITUDINAL SECTION (1/2) KM-FG-009 BAR ARRANGEMENT (PART - WING WALL RIGHT) KM-FG-061

    LONGITUDINAL SECTION (2/2) KM-FG-010 BAR ARRANGEMENT (PART - UPSTREAM APRON 1/3) KM-FG-062

    MAIN STRUCTURE PLAN AND SECTIONS (1/5) KM-FG-011 BAR ARRANGEMENT (PART - UPSTREAM APRON 2/3) KM-FG-063

    MAIN STRUCTURE PLAN AND SECTIONS (2/5) KM-FG-012 BAR ARRANGEMENT (PART - UPSTREAM APRON 3/3) KM-FG-064

    MAIN STRUCTURE PLAN AND SECTIONS (3/5) KM-FG-013 BAR ARRANGEMENT (PART - DOWNSTREAM APRON 1/4) KM-FG-065

    MAIN STRUCTURE PLAN AND SECTIONS (4/5) KM-FG-014 BAR ARRANGEMENT (PART - DOWNSTREAM APRON 2/4) KM-FG-066

    MAIN STRUCTURE PLAN AND SECTIONS (5/5) KM-FG-015 BAR ARRANGEMENT (PART - DOWNSTREAM APRON 3/4) KM-FG-067

    DRAINAGE GATE (1/2) KM-FG-016 BAR ARRANGEMENT (PART - DOWNSTREAM APRON 4/4) KM-FG-068

    DRAINAGE GATE (2/2) KM-FG-017 TEMPORARY WORKS OF KRA MANG FLOODGATE

    CONFIGURATION OF FOUNDATION PILES AND IMPERVIOUS STEEL SHEET PILES KM-FG-018 LAYOUT PLAN KM-TW-001

    BOREHOLE LOGS KM-FG-018A DETAIL OF TEMPORARY DAM 2 KM-TW-002

    STAIRCASE (1/4) KM-FG-019 PLAN OF TEMPORARY EXCAVATION WORKS KM-TW-003

    STAIRCASE (2/4) KM-FG-020 DETAIL OF TEMPORARY WORKS (1/2) KM-TW-004

    STAIRCASE (3/4) KM-FG-021 DETAIL OF TEMPORARY WORKS (2/2) KM-TW-005

    STAIRCASE (4/4) KM-FG-022 HAN TRA FLOODGATE AND CANAL

    FLOODWALL (1/4) KM-FG-023 OVERALL LAYOUT HT-FG&BP-001

    FLOODWALL (2/4) KM-FG-024 LAYOUT (1/3) HT-FG&BP-002

    FLOODWALL (3/4) KM-FG-025 LAYOUT (2/3) HT-FG&BP-003

    FLOODWALL (4/4) KM-FG-026 LAYOUT (3/3) HT-FG&BP-004

    SLOPE PROTECTION OF APPROACH WAY KM-FG-027 HAN TRA FLOODGATE

    FLOOR PROTECTION CONCRETE (1/2) KM-FG-027A PLAN HT-FG-001

    FLOOR PROTECTION CONCRETE (2/2) KM-FG-027B FRONT VIEW AT PASAK RIVER SIDE (1/2) HT-FG-002

    CONFIGURATION OF HANDRAILS AND FENCES KM-FG-027C FRONT VIEW AT PASAK RIVER SIDE (2/2) HT-FG-003

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 1/18) KM-FG-028 FRONT VIEW AT HAN TRA CANAL SIDE (1/2) HT-FG-004

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 2/18) KM-FG-029 FRONT VIEW AT HAN TRA CANAL SIDE (2/2) HT-FG-005

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 3/18) KM-FG-030 LONGITUDINAL SECTION (1/2) HT-FG-006

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 4/18) KM-FG-031 LONGITUDINAL SECTION (2/2) HT-FG-007

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 5/18) KM-FG-032 MAIN STRUCTURE PLAN AND SECTIONS (1/5) HT-FG-008

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 6/18) KM-FG-033 MAIN STRUCTURE PLAN AND SECTIONS (2/5) HT-FG-009

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 7/18) KM-FG-034 MAIN STRUCTURE PLAN AND SECTIONS (3/5) HT-FG-010

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 8/18) KM-FG-035 MAIN STRUCTURE PLAN AND SECTIONS (4/5) HT-FG-011

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 9/18) KM-FG-036 MAIN STRUCTURE PLAN AND SECTIONS (5/5) HT-FG-012

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 10/18) KM-FG-037 CONFIGURATION OF FOUNDATION PILES AND IMPERVIOUS STEEL SHEET PILES HT-FG-013

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 11/18) KM-FG-038 BOREHOLE LOGS HT-FG-013A

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 12/18) KM-FG-039 STAIRCASE (1/4) HT-FG-014

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 13/18) KM-FG-040 STAIRCASE (2/4) HT-FG-015

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 14/18) KM-FG-041 STAIRCASE (3/4) HT-FG-016

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 15/18) KM-FG-042 STAIRCASE (4/4) HT-FG-017

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 16/18) KM-FG-043 FLOODWALL (1/4) HT-FG-018

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 17/18) KM-FG-044 FLOODWALL (2/4) HT-FG-019

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 18/18) KM-FG-045 FLOODWALL (3/4) HT-FG-020

    BAR ARRANGEMENT (SERVICE BRIDGES) KM-FG-046 FLOODWALL (4/4) HT-FG-021

    BAR ARRANGEMENT (CURTAIN WALL & SLAB) KM-FG-047 FLOOR PROTECTION CONCRETE (1/2) HT-FG-021A

    BAR ARRANGEMENT (STAIRCASE) KM-FG-048 FLOOR PROTECTION CONCRETE (2/2) HT-FG-021B

    THE FLOOD PREVENTION PROJECT OF EAST SIDE OF THE PASAK RIVER IN AYUTTHAYALIST OF DRAWINGS

  • TITLE DWG NO. TITLE DWG NO.

    CONFIGURATION OF HANDRAILS AND FENCES HT-FG-021C SLUICE PIPE (3/3) HT-BP-019

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 1/24) HT-FG-022 CONCRETE PAVEMENT (1/2) HT-BP-020

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 2/24) HT-FG-023 CONCRETE PAVEMENT (2/2) HT-BP-021

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 3/24) HT-FG-024 COMMON WORK FOR FLOODGATES

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 4/24) HT-FG-025 SHED (1/4) FG-A-001

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 5/24) HT-FG-026 SHED (2/4) FG-A-002

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 6/24) HT-FG-027 SHED (3/4) FG-A-003

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 7/24) HT-FG-028 SHED (4/4) FG-A-004

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 8/24) HT-FG-029 HANDRAIL FG-A-005

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 9/24) HT-FG-030

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 10/24) HT-FG-031

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 11/24) HT-FG-032

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 12/24) HT-FG-033

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 13/24) HT-FG-034

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 14/24) HT-FG-035

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 15/24) HT-FG-036

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 16/24) HT-FG-037

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 17/24) HT-FG-038

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 18/24) HT-FG-039

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 19/24) HT-FG-040

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 20/24) HT-FG-041

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 21/24) HT-FG-042

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 22/24) HT-FG-043

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 23/24) HT-FG-044

    BAR ARRANGEMENT (MAIN BODY OF FLOODGATE 24/24) HT-FG-045

    BAR ARRANGEMENT (SERVICE BRIDGES) HT-FG-046

    BAR ARRANGEMENT (CURTAIN WALL & SLAB) HT-FG-047

    BAR ARRANGEMENT (STAIRCASE) HT-FG-048

    BAR ARRANGEMENT (PART - WING WALL 1/3) HT-FG-049

    BAR ARRANGEMENT (PART - WING WALL 2/3) HT-FG-050

    BAR ARRANGEMENT (PART - WING WALL 3/3) HT-FG-051

    BAR ARRANGEMENT (PART - APRON 1/3) HT-FG-052

    BAR ARRANGEMENT (PART - APRON 2/3) HT-FG-053

    BAR ARRANGEMENT (PART - APRON 3/3) HT-FG-054

    TEMPORARY WORKS OF HAN TRA FLOODGATE

    LAYOUT PLAN HT-TW-001

    PLAN OF TEMPORARY EXCAVATION WORKS HT-TW-002

    DETAIL OF TEMPORARY WORKS (1/2) HT-TW-003

    DETAIL OF TEMPORARY WORKS (2/2) HT-TW-004

    BANK PROTECTION OF HAN TRA CANAL

    TYPICAL CROSS SECTION HT-BP-001

    TRANSVERSE SECTIONS (1/8) NO.0 TO NO.0+20.00 HT-BP-002

    TRANSVERSE SECTIONS (2/8) NO.0+40.00 TO NO.0+60.00 HT-BP-003

    TRANSVERSE SECTIONS (3/8) NO.0+80.00 TO NO.1 HT-BP-004

    TRANSVERSE SECTIONS (4/8) NO.1+20.00 TO NO.1+40.00 HT-BP-005

    TRANSVERSE SECTIONS (5/8) NO.1+60.00 TO NO.1+80.00 HT-BP-006

    TRANSVERSE SECTIONS (6/8) NO.2 TO NO.2+20.00 HT-BP-007

    TRANSVERSE SECTIONS (7/8) NO.2+40.00 TO NO.2+60.00 HT-BP-008

    TRANSVERSE SECTIONS (8/8) NO.2+80.00 TO NO.3 HT-BP-009

    DETAILS (1/2) HT-BP-010

    DETAILS (2/2) HT-BP-011

    U-SHAPED DITCH HT-BP-012

    STAIRS AT REVETMENT (1/4) HT-BP-013

    STAIRS AT REVETMENT (2/4) HT-BP-014

    STAIRS AT REVETMENT (3/4) HT-BP-015

    STAIRS AT REVETMENT (4/4) HT-BP-016

    SLUICE PIPE (1/3) HT-BP-017

    SLUICE PIPE (2/3) HT-BP-018

  • APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    GP-001

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    GENERAL PLAN

    GENERAL MAP

    0 0.5 1.0 1.5 2.0SCALE

    KILOMETERS

    RAIL W

    AY

    PASAK RIVER

    CHAO PRAYA RIVER

    EXISTINGCHANNEL

    KHA MAOCHANNEL

    HAN TRAFLOODGATE SITE

    KRA MANGFLOODGATE SITE

    EXISTINGKHA MAO FLOODGATE

    ROUTE 32

    ROUTE 309

    AYUTTHAYAHISTORICAL AREA

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    CONSULTING FIRMS :

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    DATE

    NO.

    The Flood Prevention Project of

    Akio SHICHIJUGARI

    East Side of the Pasak River in Ayutthaya

    T. MISHINA

    in the Kingdom of Thailand

    GENERAL PLAN

    GP-002

    Masaki ISHII

    GENERAL NOTE

    Masaki ISHII P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • X

    X X X X

    X

    X

    X X

    XX

    X

    X

    X X

    // //

    9697

    99

    100

    101

    102

    103105

    104

    106

    107

    108

    109

    110

    111

    112

    113

    114

    115

    116

    117

    118

    119

    120

    121

    122

    123

    124

    125

    126

    127

    128

    129

    130

    131

    132

    133

    134

    135

    136

    137

    138

    139

    140

    141

    103

    104

    106

    107

    108 109

    110 111

    112

    144

    145

    146158

    159

    160

    161162

    163

    157

    156155154

    153

    152

    151

    150

    149

    147

    148

    213

    Public Gutter

    Public Road

    Public Gutter

    26m30m

    22.5m

    27m

    14m27m

    21.14m

    14m

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-001

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    OVERALL LAYOUT (1/2)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • X

    X X X X

    X

    X

    104108 109

    144

    145

    146158

    159

    160

    161162

    155154

    153

    152

    151

    26m30m

    22.5m

    27m

    14m

    27m

    21.14m

    14m

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-002

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    OVERALL LAYOUT (2/2)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • SLOPESLO

    PE

    SLOPE SLO

    PE

    SLO

    PE

    SLO

    PE

    Slope 10%

    UP

    Pasak River side

    PLAN OF KRA MANG FLOOD GATE

    Kra Mang Canal side

    27000

    100026000 1000

    28000

    100026000 1000

    28000

    1500

    060

    00

    5000

    6000

    1000

    1300

    010

    00

    1500

    060

    00

    5000

    6000

    1000

    1300

    010

    00

    7000 6000 50006000

    2250

    0

    5600

    800 4000900

    9000

    3600

    3400

    7500

    1450

    0

    30000

    21@1000=21000

    6@1000

    =6000

    10@

    1000

    =100

    00

    4000

    6230

    9@1000=9000

    8@1000=8000

    715012150

    26200 4600

    8003000

    800

    4000

    5000260005000

    8000

    14@

    1000

    =140

    0065

    0

    120

    14@

    1000

    =140

    0065

    012

    0

    800

    800

    800

    800

    800800

    150

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    PC corrugated sheet piles SW500AL=15m

    1000

    1000

    800

    8@10

    00=8

    000

    350

    150

    18@

    1000

    =180

    008@

    1000

    =800

    0

    800 2000 800

    PC corrugated sheet piles SW500AL=15m

    4620

    1627

    0

    1000 1000

    2880

    800

    800

    1502@1000=2000

    150120

    8@1000=8000150

    2@1000=2000

    15012010960

    1000150

    650

    1000150

    650 65

    09@1000=9000

    150

    20@

    1000

    =200

    0065

    0

    150 16@1000=16000

    2000

    2000

    150

    24@1000=24000

    150

    270

    150

    150

    650

    6@10

    00=6

    000

    150

    3@1000=3000

    150650

    20 20

    2020

    2020

    2020

    7@1000=7000

    270150

    2200

    7@1000=7000

    130

    2020

    7@1000=3000

    2020

    350

    150 150

    20 20

    1400

    014

    000

    2000

    6000

    3@1000=3000270

    162°

    153°

    135°

    135°

    135°

    150

    Resin-coated stepsW350 x L150 @30cm

    Resin-coated stepsW350 x L150 @30cm

    Resin-coated stepsW350 x L150 @30cm

    Resin-coated stepsW350 x L150 @30cm 60

    0

    600

    600

    600

    Radar level gauge in2m mounting frame

    Radar level gauge in2m mounting frame

    2700

    2700

    DN

    4500

    4100

    0 2 4 6 8 10 15 20SCALE

    METERS

    55

    44

    6

    3

    22

    11

    6

    77

    3

    +3.00mMSL

    +2.00mMSL

    +1.50mMSL

    +1.00mMSL

    +0.50mMSL

    ±0mMSL

    -0.50mMSL

    +3.00mMSL

    +2.00mMSL

    +1.50mMSL

    +1.00mMSL

    +0.50mMSL

    ±0mMSL

    -0.50mMSL

    -0.50mMSL

    -0.50mMSL

    +3.00mMSL

    +3.00mMSL

    +3.00mMSL

    +2.00mMSL

    +1.00mMSL

    ±0mMSL

    +2.00mMSL

    +1.00mMSL

    ±0mMSL

    -0.50mMSL

    -0.50mMSL

    -0.50mMSL

    -0.50mMSL

    1000

    2000

    1000 2000

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or moreNon-woven geotextile of 2mm or more in thickness to be placed back and below all bottom gabions

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or moreNon-woven geotextile of 2mm or more in thickness to be placed back and below all bottom gabions

    26000

    5980

    190

    120010

    00 120

    01000 12

    0019

    0

    500 25@1000=25000 500

    500 500

    26000500

    25@1000=25000500

    Baffle piers

    Baffle piers

    26000

    25@1000=25000

    1000

    1500

    2600059

    80

    190

    120010

    00 120

    01000 12

    0019

    0

    500 25@1000=25000 500

    500 500

    26000500

    25@1000=25000500

    190 200

    100010001000

    190200

    1000

    2001000

    1000

    150020

    00

    BAFFLE PIERS

    See PLAN 1

    See PLAN 2

    PLAN 1

    PLAN 2

    SECTION A-A4

    B B

    SECTION C-CSECTION D-D

    CC

    DD

    A A

    SECTION B-B

    5980

    DETAIL OF BAFFLE PIER

    200

    4@20

    0=80

    0

    1000

    100

    100

    1004@215=860240

    400

    1200

    59 10041

    1000

    4@200=800 100100

    4@20

    0=80

    0

    1000

    100

    100

    400

    DB12

    DB12

    DB12

    0SCALE

    METERS

    0.5 1 1.5 2

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    PLAN

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-003

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 26000

    4603

    2000 6000 2000 6000 2000 6000 2000

    Right Bank of Canal Left Bank of Canal

    8000

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    +13.00m MSL

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    MSL

    1450 550 6000 550 900 550 6000 550 900 550 6000 550 1450

    100

    5000

    100

    5000

    +15.60m MSL

    +16.65m MSL

    CL

    Staircase

    650

    +7.50m MSL

    5000 6000 700060002000

    22000 2000

    1000

    5000

    5000

    1000

    500

    Wing wall

    500

    1500

    500

    20

    2010

    00MSL

    150

    8000

    -0.50m MSL

    4000 800800

    1500

    500

    2000

    500

    7500

    1000

    500

    7500

    3000800 800

    -0.50mMSL

    95@400=38000 14@400=640012@400=4800

    +4.60m MSL

    L=15mPC corrugated sheet piles SW 500A

    32500

    4600

    250

    650

    900

    7000

    2300

    1200 1100

    6875

    Impervious steel sheet piles SP-III, L=3mSP-III, L=6.5m SP-III, L=6.5m

    L=15mPC corrugated sheet piles SW 500A

    6000

    6000

    600

    150

    200

    -0.50m MSL

    500

    500

    600

    500

    600

    500

    800

    800

    800

    800

    +7.50m

    +7.50m

    Radar level gauge in2m mounting frame

    105

    105

    0 2 4 6 8 10 15SCALE

    METERS

    1600900

    1500900

    2600 1500

    200

    200

    SECTION 1-1

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or more

    26000

    1000

    Non-woven geotextile of 2mm or more in thickness to be placed back and below all bottom gabions

    FRONT VIEW AT PASAK RIVER SIDE (1/3)

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-004

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    FRONT VIEW AT PASAK RIVER SIDE (1/3)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 26000

    4603

    2000 6000 2000 6000 2000 6000 2000

    Right Bank of Canal Left Bank of Canal

    1000

    0

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    +13.00m MSL

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    1450 550 6000 550 900 550 6000 550 900 550 6000 550 1450

    +15.60m MSL

    +16.65m MSL

    CL

    Staircase

    650

    +7.50m MSL

    6500

    6500Wing wall

    20

    500

    1000

    0

    -0.50m MSL

    4000 800800

    7500

    2250500 500

    -0.50mMSL

    +4.60m MSL

    L=15mPC corrugated sheet piles SW 500A

    32500

    4600

    250

    650

    900

    7000

    2300

    1100 1100

    6875

    L=15mPC corrugated sheet piles SW 500A

    1000

    Wing wall

    4800

    -0.50m MSL

    500

    1200

    600

    850

    2800

    350

    4400

    3850

    5150

    9000

    2200

    2000

    800

    1500

    700

    1875

    350

    500

    150

    150

    500

    150

    5000 6000 70006000

    2000

    22000 2000

    500

    20MSL

    +7.50mMSL

    +7.50m

    100

    105

    105

    0 2 4 6 8 10 15SCALE

    METERS

    2000 200020001150

    900

    500

    200

    600900

    2600 1500RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    SECTION 2-2

    26000

    1500

    5000

    1500

    5000

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or moreNon-woven geotextile of 2mm or more in thickness to be placed back and below all bottom gabions

    FRONT VIEW AT PASAK RIVER SIDE (2/3)

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-005

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    FRONT VIEW AT PASAK RIVER SIDE (2/3)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 26000

    4603

    2000 6000 2000 6000 2000 6000 2000

    Right Bank of Canal Left Bank of Canal

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    +13.00m MSL

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    1450 550 6000 550 900 550 6000 550 900 550 6000 550 1450

    +15.60m MSL

    +16.65m MSL

    CL

    Staircase

    5000 6000 700060002000

    22000 2000

    800

    20 20

    150

    500

    -0.50m MSL -0.50m MSL

    500

    +4.60m MSLSand fill t=1m

    650

    32500

    7000

    4600

    650

    250

    900

    2300

    1100 1100

    6875

    L=15mPC corrugated sheet piles SW 500A

    L=15mPC corrugated sheet piles SW 500A

    RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    800

    MSL+7.50m

    MSL+7.50m

    MSL+7.50m

    100

    105

    105

    0 2 4 6 8 10 15SCALE

    METERS

    +3.00m MSL10005

    00

    1000 500

    ±0.00m MSL

    -0.50m MSL

    +3.00m MSL

    ±0.00m MSL

    SECTION 3-3

    1000

    FRONT VIEW AT PASAK RIVER SIDE (3/3)

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-006

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    FRONT VIEW AT PASAK RIVER SIDE (3/3)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 4600

    900

    2000 6000 2000 6000 2000 6000 2000

    1500

    Right Bank of CanalLeft Bank of Canal

    HWL + 3.50m MSL

    LWL + 0.50m MSL

    +13.00m MSL

    HWL + 3.50m MSL

    LWL + 0.50m MSL-0.50m MSL

    1450 550 6000 550 900 550 6000 550 900 550 6000 550 1450

    100

    5000

    100

    5000

    +15.60m MSL

    +16.65m MSL

    CL

    Staircase

    500

    13150 81502000 220002000

    +4.50m MSL

    Impervious steel sheet piles SP-IIIL=3m

    1500

    500

    650

    L=15m

    800 800

    150

    8000

    69@400=27600

    1:2.0

    Sodding

    Earth fill

    4000

    PC corrugated sheet piles SW 500A

    27000

    L=15mPC corrugated sheet piles SW 500A

    +4.50m MSL +4.50m MSL

    2300

    1100 1200

    650

    250

    32500

    7000

    6875

    Impervious steel sheet piles SP-III, L=3m

    3000

    8000

    4603

    800

    800

    MSL+7.50m

    MSL+7.50m

    150

    MSL+7.50m

    Radar level gauge in2m mounting frame

    26000

    105

    105

    0 2 4 6 8 10 15SCALE

    METERS

    SECTION 4-4

    4000

    1500

    4000

    1500

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or moreNon-woven geotextile of 2mm or more in thickness to be placed back and below all bottom gabions

    Natural ground

    FRONT VIEW AT KRA MANG CANAL SIDE (1/2)

    Natural ground

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-007

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 26000

    4600

    900

    2000 6000 2000 6000 2000 6000 2000

    Right Bank of CanalLeft Bank of Canal

    HWL + 3.50m MSL

    LWL + 0.50m MSL

    +13.00m MSL

    HWL + 3.50m MSL

    LWL + 0.50m MSL-0.50m MSL

    1450 550 6000 550 900 550 6000 550 900 550 6000 550 1450

    +15.60m MSL

    +16.65m MSL

    CL

    Staircase

    13150 81502000 220002000

    +4.50m MSL

    800

    1:2.0

    Gabion mattress

    Earth fill

    4000

    27000

    L=15mPC corrugated sheet piles SW 500A

    +4.50m MSL +4.50m MSL46

    03

    7000

    2300

    1100 1200

    650

    250

    32500

    6875

    300080

    0

    800

    RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    L=15mPC corrugated sheet piles SW 500A

    MSL+7.50m

    MSL+7.50m

    MSL+7.50m

    105

    105

    0 2 4 6 8 10 15mSCALE

    METERS

    +3.00m MSL 1000500

    1000

    ±0.00m MSL

    500

    +3.00m MSL

    ±0.00m MSL

    SECTION 5-5

    1000

    Natural groundNatural ground

    FRONT VIEW AT KRA MANG CANAL SIDE (2/2)

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-008

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 4500

    15000

    Pasak River side Kra Mang Canal side

    4600

    900

    2600

    2000

    10005001000 500

    500

    500

    8000

    3000

    1500

    500

    1000500

    3000

    500

    2500

    500

    1500

    10001000

    Impervious steel sheet piles SP-III

    -0.50m MSL

    +13.00m MSL

    2000

    2000

    1000

    4600

    100

    PC spun piles Ø600

    7502100210021002100210075010

    50

    6000 3000 6000

    +4.50m MSL

    6000 13990

    20

    600

    6000

    5000

    -0.50m MSL

    800

    20

    5000

    500

    1000

    1000 4000

    8000

    1500

    2000

    500

    1500

    500600 600

    PC corrugated sheet piles SW 500AL=15m

    1200

    20

    3400

    2700 35035045

    5012

    0075

    0

    8300

    800

    2200

    Curtain wall

    Stainless steel fixed wheel gateClear span 2.0m x Height 1.5m

    36004620

    20 20

    U type wall

    Coping concrete

    7500

    1000

    500

    Impervious steel sheet piles SP-III

    150

    150

    +7.50m MSLMSL

    +7.50m

    14500

    7500

    L=6.5m

    PC spun piles Ø600 L=8.5m

    1500 15001500

    3000 1500150015001500

    15001500 2000 1500

    PC corrugated sheet piles SW 500AL=15m

    RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    750

    1000

    900

    750

    650

    250

    5501050

    650

    250

    1490 990

    -0.50m MSL

    480SP-III, L=3m35@400=14000

    320

    2500

    1500

    450

    800

    150

    800

    HWL + 3.50m MSL

    LWL + 0.50m MSL

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    L=3m

    L=5m

    450

    450

    Pressure

    25@

    300=

    7500

    350

    Resin-coated steps350W x 150L @30cm

    25@

    300=

    7500

    350

    Resin-coated steps350W x 150L @30cm

    600

    MSL+7.50mMSL

    +7.00mMSL

    +7.00m

    105

    105

    3900

    +15.60m MSL

    +16.65m MSL

    0 2 4 6 8 10 15SCALE

    METERS

    SECTION 6-6

    +3.00mMSL

    +3.00m MSL

    1400014000

    1000

    1000

    1000

    500

    1000

    500

    500

    500

    500

    500

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or more

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or more

    1000

    LONGITUDINAL SECTION (1/2)

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-009

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    LONGITUDINAL SECTION (1/2)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

  • 4500

    15000

    Pasak River sideKra Mang Canal side

    4600

    900

    2600

    2000

    1000 500 1000500 500

    500

    8000

    30001500

    500

    1000500

    3000

    500

    2500

    500

    15001000

    1000

    Impervious steel sheet piles

    HWL + 3.50m MSL

    LWL + 0.50m MSL-0.50m MSL

    +13.00m MSL

    2000

    7502000

    1000

    750

    4600

    100

    PC spun piles Ø600 L=5m750 2100 2100 2100 2100 2100 750

    1050

    600030006000

    +4.50m MSL

    600013990

    20

    6000

    5000

    -0.50m MSL

    5001

    000

    1000

    10004000

    8000

    1500

    2000

    500

    1500

    500

    600

    600

    PC corrugated sheet pilesSW 500A L=15m

    20

    Impervious steel sheet piles SP-III

    Coping concrete

    20

    22500

    7500

    1000

    500

    L=6.5m20

    800

    150

    150

    MSL+7.50m

    5000

    5000

    55@400=22000

    16270

    150030001500 1500 1500 1500 15001500

    PC spun piles Ø600 L=8.5m15002000 1500

    150

    6350

    RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    RC piles Ø150 L=3munder 1m x 2m bed area of each bottom gabion mattress

    650

    250

    990 1490

    1050

    550

    1000

    250

    -0.50m MSL

    Impervious steel sheet piles SP-III, L=3m320Welded fitting SP-IIIL=3m

    2500

    480

    1500

    650

    900

    PC corrugated sheet piles SW 500AL=15m

    450

    800

    800800

    HWL + 6.00m MSL

    LWL + 0.50m MSL

    SP-III L=3m

    800

    450

    450

    Pressure

    25@

    300=

    7500

    350

    600

    Resin-coated steps350W x 150L @30cm

    Resin-coated steps350W x 150L @30cm

    25@

    300=

    7500

    350

    600

    MSL+7.50m MSL

    +7.00m

    105

    105 +15.60m MSL

    +16.65m MSL3900

    LONGITUDINAL SECTION (2/2)

    0 2 4 6 8 10 15SCALE

    METERS

    SECTION 7-7

    +3.00m MSL+3.00m MSL

    1000

    500

    500

    500

    500

    500

    14000

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or more

    1000

    1000

    1000

    500

    10000

    22000

    Zinc-coated gabion mattressL2.0m x W1.0m x H0.5m /pieceMesh wire diameter Ø2.7mm or more

    1000

    4990

    APPROVEDLOCATIONREV.

    DESCRIPTIONCHECKED

    PRESENT APPROVED

    APPROVEDDATE

    OFFICE OF ENGINEERING DESIGN & ARCHITECTUREIRRIGATION SYSTEM DESIGN GROUP

    APPROVED

    DESIGNED

    CHECKED

    DRAWN

    DATE

    PROPOSED

    APPROVED

    VERIFIED

    ROYAL IRRIGATION DEPARTMENT

    CHIEF

    DIRECTOR

    D.G.

    ROYAL IRRIGATION DEPARTMENT

    CONSULTING FIRMS :

    DATE

    NO.

    The Flood Prevention Project ofEast Side of the Pasak River in Ayutthaya

    in the Kingdom of Thailand

    KRA MANG FLOODGATE(CIVIL WORKS)

    CTI ENGINEERING INTERNATIONAL CO., LTD.

    KM-FG-010

    Masaki ISHII

    Masaki ISHII

    Akio SHICHIJUGARI

    T. MISHINA

    LONGITUDINAL SECTION (2/2)

    P. SIRION

    S. INTARAPRACHA

    L. KOWATTANA

    CoverList of drawingsGeneral planKra Mang floodgate