Tehri Dam

Introduction

The Tehri Dam is a multi-purpose rock and earth-fill embankment dam on the Bhagirathi River

near Tehri in Uttarakhand, India. It is the primary dam of the Tehri Hydro Development

Corporation Ltd. and the Tehri hydroelectric complex.

Tehri Dam Project is one of the important storage cum hydro energy generation complex is in the

Himalayan region of the country. After Bhakara it is the biggest water storage dam and may

provide benefits to the water starved areas of Western U.P., Uttaranchal and Delhi. The hydro-

energy may add to the peaking capacity of the Northern Grid and may help in stabilizing it.

History

A preliminary investigation for the Tehri Dam Project was completed in 1961 and its design was

completed in 1972 with a 600 MW capacity power plant based on the study. Construction began

in 1978 after feasibility studies but was delayed due to financial, environmental and social

impacts. In 1986, technical and financial assistance was provided by the USSR but this was

interrupted years later with political instability. India was forced to take control of the project

and at first it was placed under the direction of the Irrigation Department of Uttar Pradesh.

However, in 1988 the Tehri Hydro Development Corporation was formed to manage the dam

and 75% of the funding would be provide by the federal government, 25% by the state. Uttar

Pradesh would finance the entire irrigation portion of the project. In 1990, the project was

reconsidered and the design changed to its current multi-purpose. Construction of the Tehri Dam

was complete in 2006.

Location

Tehri Dam is the primary dam of the Tehri Development Project, a major hydroelectric project

centered near Tehri Town in the state of Uttarakhand in India.It is located on the Bhagirathi

River, the principal tributary of the sacred River Ganga

Page 3: Tehri dam

Technical description

1. Earth & Rock Fill Dam :

Type : Rock and Earth Fill Height : 260.5 m

Base : 1128 m Width at top : 25.5 m

Length at the top : 592 m

2. Tehri Reservoir:

Water Spread : 42 SQ KM Gross Storage : 3540 Miliion Cum

Live Storage : 2615 Million Cum

3. Power House:

Power House : Under ground Cavern

Size : 197mx24mx63m

Type of Turbines : Francis

Rated Head : 188 M Speed : 214.3 RPM

Installed Capacity : 4x250MW

Annual Energy : 3568 MUs

Page 4: Tehri dam

Time Line for Tehri Dam

1949 Tehri dam conceived

1961 Tehri chosen as a tentative site for the dam

1972 Planning Commission gives its nod to the dam

1978 Actual construction of the dam begins under police protection; Protests gather momentum

1980 Environmental Appraisal Committee appointed by the government, refuses environmental

clearance

1986 Diversion tunnels start operating; Protestors storm the site and stall construction work

1990 Environmental Appraisal Committee, the D R Bhumbla committee, rejects the dam again

1991 Earthquake measuring 6.6 on Richter scale rocks Uttarkashi. Renewed concerns about the

seismic safety of the dam.

1992 Sunderlal Bahuguna goes on a fast unto death. Work on the dam temporarily stopped. Gain

in 1995

1996 Government sets up the V K Gaur committee to look into seismic safety

1997 Hanumantha Rao committee on rehabilitation submits its report. Recommends major

changes in rehabilitation policy

1998 Gaur committee submits its report. Asks for detailed analysis

1999 Chamoli earthquake, measuring 6.8, brings large scale destruction. Anti-dam activists up in

arms about safety

1999 Committee of secretaries of the Union government clears dam

January 2001 Bhuj Earthquake Again Raises Concerns

April 2001 Government Forms another Committee under the S&T Minister Murli Manohar

Joshi

November 2002 M M Joshi Committee Submits Its Report. Says The Dam Is Safe To Withstand

An Earthquake Of High Magnitude

September 2003 In A Divided Verdict, The Supreme Court Clears The Legal Hurdles For Dam

Construction

March 2004 Tunnel T2 Closed. Water Level Rises To 648 Metres Submerging Many Parts Of

Old Tehri Town

July 29, 2004 Water Level Rises To 655 Metres Submerging The Remaining Parts Of The Tehri

Town. Residents Flee For Their Lives

August 2004 Internal Landslide at The Dam Site. 29 Workers Dead

2006 Tehri Town Fully Submerges. First Stage Of Project Completes. (Total Production 1000

Mw)

Page 5: Tehri dam

Components of Tehri Hydro Power Complex

Tehri Hydro Power Complex (2400 MW), comprises the following components:

1. Tehri Dam & Hydro Power Plant (1000 MW)

2. Koteshwar Hydro Electric Project (400 MW)

3. Tehri Pumped Storage Plant (PSP) (1000 MW)

The Govt. in March, 1994 approved the implementation of Tehri Dam & HPP (1000 MW) along

with committed works of Koteshwar HEP and essential works of Tehri PSP, as Stage-I of Tehri

Power Complex. With the synchronization 4th unit of 250 MW in March-07, Tehri Power

Station has become fully operation with installed capacity of 1000 MW.

The 400 MW Koteshwar HEP, was approved by Govt. in April,2000 and the work has

progressed in right earnest and after completion of major excavation work in Dam & Spillway,

Stiling Basin and Power Intake area, the concreting was started and is progressing in full swing.

Investment approval for Tehri PSP (1000 MW) has been accorded by the Govt. in July’06 at an

estimated project cost of Rs. 1657.60 Cr. (at Dec’05 Price Level) with Debt Equity ratio of

70:30. The essential works of Tehri PSP have already been completed with Tehri Dam & HPP

Stage-I.

Estimated Project Cost

Item Cost in Crores Rupees

Major Civil works including Hydro

Mechanical works

1325.76

Electro Mechanical Equipment 543.03

Infrastructure 152.02

Rehabilitation & resettlement 412.22

Environment 66.00

Establishment 249.53

Others 180.24

Sub total 2963.66

Interest During Construction(IDC) and

Financing Charges

427.74

Total Rs. 3357.04

Page 6: Tehri dam

Actual Project Cost

Due to some agitations lot of valuable construction time was lost and there was delay in the

startup work. The project revised cost estimates as per March 2002-03 is as follows.

Item Cost in Crores Rupees

Major Civil works including Hydro

Mechanical works

3034.59

Electro Mechanical Equipment 1107.85

Infrastructure 159.67

Rehabilitation & resettlement 983.14

Environment 141.74

Establishment 346.93

Others 287.40

Sub total 6061.32

Interest During Construction(IDC) and

Financing Charges

560.00

Total 6621.32

Project Cost Escalation and Completion Time through the Year

S.

No.

Description Amount in Rs. Crores

1 Total Cost of Project March 93 Price

level to be completed in 1999

2963.66

2 March 2003 Price level To be

commissioned by 2005 (March)

6621.32 crores

3 Feb. 2005, (Expenditure to date) To be

completed by March 2006

6896.84 crores

Type of Contract The contract bidding was as per the International Contract Bidding procedures (ICB) and bids

were undertaken for various packages constituting the total work. It is a normal item rate

contract. These procedures are prevalent in the construction industry in India and were

acceptable to the THDC and Govt. of India.

Page 7: Tehri dam

Contractors

1. Dam:

The tenders for dam were invited in 1993. The bidders gave wide ranging cost estimates and

programmes. This necessitated rebidding. The important details of rebid are given below.

1

2 Date of tender floated – 8th May 1996

3 Date of bid opening – 9th Aug. 1996

4 Date of Letter of intent – 10th Jan. 1997

5 Date of agreement – 27th Jan. 1997

6 Date start of work – 1st Feb. 1997

7 Value of contract – Rs. 898.45 crores

The following were the bidders for the Dam.

1 M/S Jaiprakash Industries

2 Hindustan Construction Company

3 Continental Construction Company

The contract was awarded to Jaiprakash Industries

2. Spill way:

The bids for spillway were invited as per the following details.

1) Date of tender initiated – 18th Sept. 1998

2) Date of opening of bids – 11th Nov. 1998

3) Date of issue of Letter of Intent – 15th Dec. 1998

4) Date of agreement – 28th 1998

5) Date of start of work – 1st Feb. 1998

6) Value of contract – Rs. 474.81

The bidders were as follows

1) Jaiprakash Industries

2) Karamchand Thapar

3) Hindustan Construction Company

4) Lanco

5) Gammons

6) Bhagirathi

The contract was awarded to Jaiprakash Industries

Page 8: Tehri dam

3. Power House:

The tenders for Power House (Package I, II, III) were floated in 1995. The following are the

important acts.

(1) Tenders floated on 10.05.93

(2) Tenders opened on 15.12.93

(3) Amendments issued on 19.08.93

(4) Price bid opened on 03.01.95

(5) Contract awarded on 09.11.95

(6) Value of contract for the packages Rs. 210.84 crores

Following were the bidders

(1) M/S Thapars

(2) Hindustan Construction Ltd.

The contract was awarded to M/S Thapars

4. Tehri Pumped Storage Plant:

Major works of the Project have been planned to be executed through a single EPC contract.

Agreement for EPC/Turnkey execution of the Project has been signed with the consortium of

M/S Alstom Hydro France and Hindustan Construction Company on 23rd June-2011. Work

on the project has commenced w.e.f. 27th Jul-11.

Problems of the project

Major projects done in far flung and inhospitable terrain with seismic risk, executed in younger

Himalayan rocks may have many problems. Any project is normally executed with activities in

the following chronology.

(1) Site identification, pre feasibility

(2) Detailed investigation

(3) Planning of the project and preparation of detailed feasibility report with realistic cost

estimates.

(4) Designing of different components

(5) Arranging finances

(6) Rehabilitation and resettlement and land acquisition

(7) Infrastructure development

(8) Setting up base facilities for construction

(9) Construction

(10) Testing the system and operation

Page 9: Tehri dam

Dam safety

Safety of Tehri Dam had always been an issue with the local people and the knowledgeable

persons in the scientific field. In Feb. 1967, Mr. N.N.Yakovlov, UN Expert, recommended

rockfill Dam to be the best solution. Mr. J.B. Cook, of USA in1972 also concluded that a high

Dam at Tehri was feasible. In the year 1990 a high level committee was also constituted to look

into it further. This committee also considered the Dam safe. After Utterakashi earthquake in

October, 1991 the matter was once again looked into in depth. The Russians also studied the

earthquake safety and declared it to be the gentle Dam to with stand severe earthquake shocks up

to 8.5 magnitude.

Benefits

The main benefits from the Project when completed would be:

Addition to the installed capacity in Northern Region: 1000 MW (2400 MW on completion

of entire Complex)

Annual energy availability peaking: 3568 Million Units (6200 MU on completion of entire

Complex)

Additional irrigation in 2.7 lakh hectares area besides stabilization in existing 6.04 lakh

hectares area.

162 Million Gallons of water per day (300 Cusecs) for drinking water supply to Delhi to

cater to a population of 40 lac.

108 Million Gallons of water per day (200 Cusecs) for drinking water supply to the towns

and villages of Uttar Pradesh.

Integrated development of Garhwal Region, including construction of a new hill stations viz.

New Tehri Town (NTT) with provision of all possible facility, improved communication,

education, health, tourist traffic, setting up of non- polluting industries, development of

horticulture, fisheries, afforestation of the region etc. much to the advantage of the people of

the region.