TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
Transcript of TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
1/112
Appendix 1 - Technical Specification Feb 2012
TECHNICAL SPECIFICATION
FOR
RUBBER TYRED GANTRY CRANES
FEBRUARY 2012
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
2/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 2
Appendix 1 - Technical Specification Feb 2012
INDEX
TECHNICAL SPECIFICATION
C (I) Functional requirement for the Crane
1. General ........................................................... ............................................................ ...........................................8 1-1. Project Description ..................................................... ........................................................... ........................8 1-2. Terminal Site .................................................... ........................................................... ..................................8 1-3. Overriding Requirement of the Purchaser .......................................................... ...........................................8
2. Overall Design Criteria..........................................................................................................................................9 2-1. Type of Crane ................................................... ........................................................... ..................................9 2-2. Type of Cargo................................................... ........................................................... ..................................9 2-3. Operating Environment and Design Aim.......................................................................................................9 2-4. Mode of Operation and Performance Target (MMBF)................................................................................10 2-5. Statutory Requirements and Minimum Design Standard.............................................................................10
2-6. Minimum Class of Crane.............................................................................................................................11 2-7. General Design Criteria ........................................................ ........................................................... ............11
2-7.1. Crane Particulars..................................................................................................................................11 2-7.2. Dimensional Restrictions.....................................................................................................................13 2-7.3. Yard Interface ..................................................... ........................................................... ......................13 2-7.4. Electrical Facility Interface (Shore Power)..........................................................................................13 2-7.5. Communication Facility Interface (Radio) .......................................................... ................................15 2-7.6. Climatic Conditions ...................................................... ........................................................... ............15 2-7.7. Wind Conditions..................................................................................................................................15 2-7.8. Lifting Loads and Stability ..................................................... ........................................................... ..15
2-8. NOT USED..................................................................................................................................................16 2-9. Noise Control...............................................................................................................................................17 2-10. Operationally Critical Components ...................................................... ...................................................17
3. Crane Structural Specification.............................................................................................................................17 3-1. General Requirement .................................................. ........................................................... ......................17 3-2. Material........................................................................................................................................................18 3-3. Calculations ...................................................... ........................................................... ................................19 3-4. Loads ...................................................... ............................................................ .........................................19 3-5. Members Subject To Buckling ....................................................... ........................................................... ..20 3-6. Fatigue Design Criteria................................................................................................................................20 3-7. Connection Designs .................................................... ........................................................... ......................20 3-8. Gantry Structure Stiffness............................................................................................................................21 3-9. Camber.........................................................................................................................................................21 3-10. Trolley Rails & Rail Fixing ........................................................ ........................................................... ..21 3-11. Workmanship...........................................................................................................................................21 3-12. Quality Control of Structure Fabrication........................................................ .........................................23
3-13. Temporary Structures ....................................................... ........................................................... ............24 4. Functional Systems Devices & Equipment..........................................................................................................24
4-1. Main Hoist ........................................................ ........................................................... ................................24 4-1.1. Main Hoist Drive .......................................................... ........................................................... ............24 4-1.3. Skew Control ...................................................... ........................................................... ......................26
4-2. Trolley, Trolley Drive..................................................................................................................................26 4-2.1. Trolley Frame ..................................................... ........................................................... ......................26 4-2.2. Trolley Drive ...................................................... ........................................................... ......................27 4-2.3. Sway and Position Control ..................................................... ........................................................... ..27 4-2.4. Power Feeder (Power Chain System) ......................................................... .........................................27
4-3. Gantry Drive ..................................................... ........................................................... ................................28 4-3.1. Gantry Drive ....................................................... ........................................................... ......................28 4-3.2. Steering................................................................................................................................................29 4-3.3. Right Angle & Pivot Turn ...................................................... ........................................................... ..29 4-3.4. Gantry Skew Control .................................................... ........................................................... ............29
4-4. NOT USED..................................................................................................................................................29 4-5. Electrical House, Control Panel, Regenerative E.M.F. Absorbing Resistors..............................................29
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
3/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 3
Appendix 1 - Technical Specification Feb 2012
4-5.1. General Construction .................................................... ........................................................... ............29 4-5.2. E-House Temperature Control.............................................................................................................30 4-5.3. Emergency Lights and Fire Control.....................................................................................................30 4-5.4. Back Power Absorbing Resistors.........................................................................................................30 4-5.5. Provision for Future Installation ....................................................... ...................................................30 4-5.6. Control Panel (in the Electrical house) ....................................................... .........................................30
4-6. Operator’s Cab, Checker’s Cab ...................................................... ........................................................... ..30 4-6.1. Construction General .................................................... ........................................................... ............30 4-6.2. Cab Access...........................................................................................................................................31 4-6.3. Window Visibility ........................................................ ........................................................... ............31 4-6.4. Cab Dimension ................................................... ........................................................... ......................31 4-6.5. Cab Fittings..........................................................................................................................................32 4-6.6. Checker’s Cab......................................................................................................................................33
4-7. Personnel Lift ................................................... ........................................................... ................................33 4-8. Headblock....................................................................................................................................................33
4-8.1. Headblock............................................................................................................................................33 4-8.2. Two Wire (Bus) System ......................................................... ........................................................... ..34 4-8.3. Baloney Cable......................................................................................................................................34
4-9.
Spreader, Hook Beam..................................................................................................................................34 4-9.1. Single Lift Telescopic Spreader...........................................................................................................35
4-9.2. Reeve in Spreader ......................................................... ........................................................... ............38 5. Inter-Functional Systems & Components...... ............................................................ .........................................38
5-1. Mechanical System/Components.................................................................................................................38 5-1.1. Bearing, Seals ..................................................... ........................................................... ......................38 5-1.2. Gearing ..................................................... ........................................................... ................................38 5-1.3. Gear Reducers......................................................................................................................................39 5-1.4. Wire Rope Winch Drums ....................................................... ........................................................... ..39 5-1.5. Wire Rope Sheaves..............................................................................................................................40 5-1.6. Wire Ropes ......................................................... ........................................................... ......................41 5-1.7. Shafts, Axles ....................................................... ........................................................... ......................41 5-1.9. Metal Wheels ...................................................... ........................................................... ......................42
5-1.10. Pins, Pin Brackets ..................................................... ........................................................... ............42 5-1.11. Bolts.................................................................................................................................................42 5-1.12. Lubrication.......................................................................................................................................43 5-1.13. Bumper, Buffer ......................................................... ........................................................... ............43 5-1.14. Rubber Tyres .................................................. ........................................................... ......................43
5-2. Hydraulically System/Components .......................................................... ...................................................43 5-2.1. Standards .................................................. ........................................................... ................................43 5-2.2. Components Sources............................................................................................................................43 5-2.3. Operating Condition ..................................................... ........................................................... ............43 5-2.4. Hydraulic Fluid Reservoir ...................................................... ........................................................... ..44 5-2.5. Power Unit...........................................................................................................................................44 5-2.6. Valve Mounting .................................................. ........................................................... ......................44 5-2.7. Relief Valve ........................................................ ........................................................... ......................44
5-2.8. Flow Control Valve ...................................................... ........................................................... ............45 5-2.9. Check valves........................................................................................................................................45 5-2.10. Servo Valves....................................................................................................................................45 5-2.11. Control Valve...................................................................................................................................45 5-2.12. Solenoid Valves ........................................................ ........................................................... ............45 5-2.13. Piping...............................................................................................................................................46 5-2.14. Hoses .................................................... ........................................................... ................................46 5-2.15. Assembly Test .......................................................... ........................................................... ............46 5-2.16. Catch Basins ................................................... ........................................................... ......................46 5-2.17. Filters .................................................... ........................................................... ................................46 5-2.18. Heat Exchangers ....................................................... ........................................................... ............47 5-2.19. Actuator .......................................................... ........................................................... ......................47 5-2.20. Application for Spreader..................................................................................................................47
5-2.21. Couplings.........................................................................................................................................47 5-2.22. Gauges .................................................. ........................................................... ................................47 5-2.23. Covers..............................................................................................................................................47 5-2.24. Hydraulic Fluid ......................................................... ........................................................... ............47 5-2.25. Load Sensing System.......................................................................................................................48
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
4/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 4
Appendix 1 - Technical Specification Feb 2012
5-3. Electrical & Electronic System/Components...............................................................................................48 5-3.1. General.................................................................................................................................................48 5-3.2. Main Power Supply ...................................................... ........................................................... ............48 5-3.3. Power Factor Correction......................................................................................................................48 5-3.4. Protection Against Power Surge ....................................................... ...................................................48 5-3.5. Protection against voltage dip/loss of power supply............................................................................49 5-3.6. Wiring..................................................................................................................................................49 5-3.7. Marking and Identification ..................................................... ........................................................... ..50 5-3.8. Conduit and Cable Tray.......................................................................................................................51 5-3.9. Electrical Trunking ....................................................... ........................................................... ............51 5-3.10. Motor .................................................... ........................................................... ................................52 5-3.11. Brakes ................................................... ........................................................... ................................52 5-3.12. Transformers....................................................................................................................................53 5-3.13. Resistors...........................................................................................................................................53 5-3.14. Enclosures........................................................................................................................................53 5-3.15. Meters, Counters..............................................................................................................................53 5-3.16. Limit Switches .......................................................... ........................................................... ............54 5-3.18. Name Plate.......................................................................................................................................55 5-3.19.
D. C. Power Supply ............................................................ ........................................................... ..55
5-3.20. Encoders ......................................................... ........................................................... ......................55 5-3.21. Sensors.............................................................................................................................................55 5-3.22. Circuit Breakers ........................................................ ........................................................... ............55 5-3.23. Auxiliary Power Socket ...................................................... ........................................................... ..56
5-4. Crane Motion Controls ......................................................... ........................................................... ............56 5-4.1. Control System General.......................................................................................................................56 5-4.2. Programmable Logical Controllers (PLC)...........................................................................................57 5-4.3. Power Supply.......................................................................................................................................58 5-4.4. Discrete I/O Modules...........................................................................................................................58 5-4.5. Real Time Clock Module.....................................................................................................................59 5-4.6. Motion Control Switches in Operator’s Cab........................................................................................59 5-4.7. Motion Control Panels ............................................................ ........................................................... ..61
5-4.8. Remote Motion Controls ........................................................ ........................................................... ..61 5-5. Operational Safety Interlocks ......................................................... ........................................................... ..61 5-5.1. Main Motions Interlocks......................................................................................................................61 5-5.2. For Trolley Operation ................................................... ........................................................... ............62 5-5.3. For Gantry Travel Operation ............................................................ ...................................................63 5-5.4. Spreader Functional Interlock..............................................................................................................63 5-5.5. Cab Entrance Door/Gate Interlock.......................................................................................................64
5-6. Communications..........................................................................................................................................64 5-6.1. Intercom System ........................................................... ........................................................... ............64 5-6.2. Radio Communication System ......................................................... ...................................................64 5-6.3. Data Communication System ........................................................... ...................................................64 5-6.4. Public Address System ........................................................... ........................................................... ..64 5-6.5. Operation Centre / Maintenance Office Station...................................................................................64
5-7. Crane Condition Monitoring System (CCMS) ................................................... .........................................65 5-7.1. General.................................................................................................................................................65 5-7.2. CCMS Description...............................................................................................................................65 5-7.3. On-Board Crane Condition Monitoring System (On-Board CCMS)...................................................66 5-7.4. On-Board CCMS Software Requirements...........................................................................................66 5-7.5. On-Board CCMS Hardware Requirements..........................................................................................68 5-7.6. Condition Monitoring ................................................... ........................................................... ............68 5-7.7. Fault Diagnosis ................................................... ........................................................... ......................72 5-7.8. Preventive Maintenance.......................................................................................................................73 5-7.9. Equipment Performance Data and Operation Log......................................................... ......................73 5-7.10. Remote Crane Condition Monitoring System (RCCMS) .................................................... ............73 5-7.11. RCCMS Software Requirements ............................................................ .........................................74 5-7.12. RCCMS Hardware requirements ............................................................ .........................................74
5-7.13. Server(s)...........................................................................................................................................75 5-7.15. CCMS Data Communication ........................................................ ...................................................75 6. Common Items ......................................................... ........................................................... ................................75
6-1. Walkways, Stairs, Ladders and Platforms .......................................................... .........................................75 6-1.1. Applicable Code/Std. .................................................... ........................................................... ............75
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
5/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 5
Appendix 1 - Technical Specification Feb 2012
6-1.2. Stairway Requirements ........................................................... ........................................................... ..76 6-1.3. Ladder Requirements...........................................................................................................................76 6-1.4. Platforms Requirements.......................................................................................................................77 6-1.5. Walkway Handrail Requirements ..................................................... ...................................................77 6-1.6. Cab Access Platforms ................................................... ........................................................... ............78 6-1.7. Walkway Requirements.......................................................................................................................78
6-2. Illumination and Lighting ..................................................... ........................................................... ............78 6-2.1. Walkways, Stairs, Ladders, Cab Access..............................................................................................78 6-2.2. Work Area Floodlights ........................................................... ........................................................... ..78 6-2.3. Floodlights on Trolley ............................................................ ........................................................... ..79 6-2.4. Emergency Lighting for Escape Routes...............................................................................................79 6-2.5. Lighting Control Switches ...................................................... ........................................................... ..79 6-2.6. High Pressure Sodium Lamp and Ballast ................................................... .........................................79 6-2.7. Fluorescent Lamps...............................................................................................................................80 6-2.8. Access for Lights Maintenance............................................................................................................80
6-3. Painting and Protective Coating ..................................................... ........................................................... ..80 6-3.1. Paint System General...........................................................................................................................80 6-3.2. Surface Preparation..............................................................................................................................81 6-3.3.
Abrasive Blast Cleaning ......................................................... ........................................................... ..82
6-3.4. Painting Generally ........................................................ ........................................................... ............83 6-3.5. Paint Systems.......................................................................................................................................85 6-3.6. Galvanising......................................................... ........................................................... ......................87 6-3.7. Reinstatement of Protective Coatings at Site....................................................... ................................87 6-3.8. Inspection and Sample Panels..............................................................................................................88
6-4. Purchaser’s Logo, Crane Numbers, Signs .......................................................... .........................................89 6-4.1. Purchaser’s Logo .......................................................... ........................................................... ............89 6-4.2. Crane Numbers ................................................... ........................................................... ......................89 6-4.3. Crane Capacity Signs...........................................................................................................................89 6-4.4. Manufacturer’s Name Plates................................................................................................................90 6-4.5. Other Signs ......................................................... ........................................................... ......................90
6-5. Alarm, Warning Signals ....................................................... ........................................................... ............90
6-5.1. Gantry Travel Warning........................................................................................................................90 6-5.2. Main Hoist Overload Warning.............................................................................................................91 6-5.3. Premature Twistlock Operation Warning ................................................... .........................................91 6-5.4. By-Pass Switch Abuse Warning ....................................................... ...................................................91 6-5.5. Electrical Control House A/C Warning ...................................................... .........................................92 6-5.6. Public Address/Warning......................................................... ........................................................... ..92
6-6. Emergency Stop Push Buttons.....................................................................................................................93 6-6.1. Locations .................................................. ........................................................... ................................93 6-6.2. Type .......................................................... ........................................................... ................................93 6-6.3. Emergency Stop Signs ............................................................ ........................................................... ..93
6-7. Service Outlets.............................................................................................................................................93 6-7.1. Location .................................................... ........................................................... ................................93 6-7.2. Type Model..........................................................................................................................................93
6-8. Fire Extinguishers........................................................................................................................................94 6-8.1. Locations .................................................. ........................................................... ................................94 6-8.2. Type-Model ........................................................ ........................................................... ......................94
6-9. Maintenance Tools and Equipment .......................................................... ...................................................94 6-9.1. Mechanical Maintenance Tools ........................................................ ...................................................94 6-9.2. Electrical/Electronic Maintenance Tools.............................................................................................94 6-9.3. Hydraulic Maintenance Tools..............................................................................................................94 6-9.4. Special Tools and Equipment ........................................................... ...................................................94 6-9.5. Wear Gauges........................................................................................................................................95
7. Project Q.A. and Administrative Requirements...................................................................................................95 7-1. Document Submission (Project) ..................................................... ........................................................... ..95
7-1.1. Project Organisation Chart (Shop & Site)............................................................................................95 7-1.2. Project Schedule (Shop & Site) ........................................................ ...................................................95
7-1.3. Project Progress Report .......................................................... ........................................................... ..96 7-1.4. Quality Assurance Programme/ Manuals ................................................... .........................................96 7-1.5. Daily Plan and Report (Site Work) ............................................................ .........................................96
7-2. Document Submission (Technical)..............................................................................................................97 7-2.1. Submission Schedule .................................................... ........................................................... ............97
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
6/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 6
Appendix 1 - Technical Specification Feb 2012
7-2.2. Conceptual Design...............................................................................................................................97 7-2.3. Drawings and Calculations for the Purchaser's Review.......................................................................97 7-2.4. Lubricant List.......................................................................................................................................98 7-2.5. Crane Delivery Method Statement.......................................................................................................98 7-2.6. Site Work Method Statement...............................................................................................................98 7-2.7. Commissioning Test Procedure. ....................................................... ...................................................99 7-2.8. Up-Dated Drawings ...................................................... ........................................................... ............99 7-2.9. Training Programme..................................................... ........................................................... ..........100 7-2.10. Structural maintenance Program....................................................................................................100 7-2.11. Operation Manuals.........................................................................................................................101 7-2.12. Maintenance Manuals ......................................................... ...........................................................101 7-2.13. As-Built Drawings .................................................... ........................................................... ..........102
7-3. Shop Inspection & Tests............................................................................................................................103 7-3.1. Shop Inspection and Verification.......................................................................................................103 7-3.2. Pre-Shipment Inspection and Test .................................................... .................................................104
7-4. Shipment, Delivery and Site Work........................................................... .................................................105 7-4.1. Clearance for Shipment .......................................................... ...........................................................106 7-4.2. Notification of ETA Site....................................................................................................................106 7-4.3.
Navigation Requirement ......................................................... ...........................................................106
7-4.4. Berthing and Roll-off Requirements..................................................................................................106 7-4.5. Customs Clearance ....................................................... ........................................................... ..........107 7-4.6. Work Permits ...................................................... ........................................................... ....................107 7-4.7. Site Safety and Security.....................................................................................................................107 7-4.8. Site Erection Area and Access...........................................................................................................107 7-4.9. Site Office Communication .................................................... ...........................................................107 7-4.10. Test Weight....................................................................................................................................108 7-4.11. Water, Electricity Supply...............................................................................................................108 7-4.12. Contractor’s Representatives. ....................................................... .................................................108
7-5. Site Inspection and Tests, Certification .................................................... .................................................108 7-5.1. Commissioning Tests Application.....................................................................................................108 7-5.2. Defects List........................................................................................................................................108
7-5.3. Rectification Report...........................................................................................................................109 7-5.4. Commissioning Test ..................................................... ........................................................... ..........109 7-5.5. Endurance Test. .................................................. ........................................................... ....................109 7-5.6. Acceptance Certification....................................................................................................................110 7-5.7. Access for Remedial Work ..................................................... ...........................................................110
7-6. Training .................................................. ............................................................ .......................................110 7-6.1. Training Off-Site. ......................................................... ........................................................... ..........110 7-6.2. Training On-Site (Operators).............................................................................................................110 7-6.3. Training On-Site (Maintenance) ....................................................... .................................................111 7-6.4. Special Training on the Operationally Critical Components Maintenance........................................112 7-6.5. Spare Parts .......................................................... ........................................................... ....................112 7-6.6. Ordered Spare Parts ...................................................... ........................................................... ..........112 7-6.7. Spare parts for Commissioning Work................................................................................................112
8. APPENDICES
I. Structural Limit of the Crane
II. Inspection Control Sheets
III. Crane Interface Drawings
1. Container Stack General Layout
2. Typical Cross Sections-Container Stack Blocks and Crane
Runways
IV. Reference Drawings and Data
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
7/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 7
Appendix 1 - Technical Specification Feb 2012
1. Crane Numbers at Ground Level
2. Circuit Diagram for Net Handling House Logic
3. Control Console Switches Layout
4. Locations of Floodlights on the Trolley
5. Operator’s Cab
6. GCT Logo, Approved Colours, Warning Signs, Name Plates etc
7. Type and Model of Labels and Cable Routing for AGSS and
PDS
8. Overview and Configuration of Crane Condition Monitoring
System (CCMS)
V. List of Drawings / Calculations to be reviewed by the Purchaser
(Minimum Requirements)
VI. List of Operation/ Maintenance Manuals and As Built Drawings
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
8/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 8
Appendix 1 - Technical Specification Feb 2012
Section C. TECHNICAL SPECIFICATION
C (I) Functional Requirement for the Crane
1. General
1-1. Project Description
To carry out the design, construction, delivery, installation, testing and commissioning of
Two (2) units of 41 tonnes capacity electrical Rubber Tyred Gantry Cranes. The cranes
shall be delivered to Gdynia Container Terminal S.A., Gdynia, Poland in a fully
assembled and tested condition.
1-2. Terminal Site
The Cranes shall be delivered and installed on Gdynia Container Terminal onEnergetykow 5, Gdynia, Poland (hereinafter referred to as GCT).
1-3. Overriding Requirement of the Purchaser
This Specification forms part of and is subject to the Conditions of Contract. Special
attention of the Contractor is drawn to Clause 3. General Requirements of the Conditions of
Contract for clarification of position of this Specification in relation to the overall and
overriding requirements of the Purchaser.
For the purposes of this Contract (including Clause 3 of the Conditions of Contract and
relevant references within the Specification) acceptable routine maintenance shall bewithin the following general parameters.
(1) For steel structures and related component parts, fittings and fixings, acceptableroutine maintenance shall be limited to the maintaining of the paint system as
stated below. Reinforcing, cutting out and/or replacement of any corroded,
fatigued or defective steel or its fixings, etc. shall be Defects remedial works and
not maintenance.
(2) For the paint system acceptable routine maintenance shall be:
- Preparing and over coating the existing paint system at year 20 after theissuance of the Commissioning Certificate.
- Removing damaged parts of the paint system back to clean steel and
repainting in isolated areas but not exceeding in aggregate more than 1%,
2% and 3% of the total surface area at years 5, 10 and 15 respectively.
- The removal of the paint system back to steel and replacement of the paint
system in areas aggregating more than the above percentages of the total
surface area of the painted part of the Crane shall be Defects remedial
works and not maintenance.
(3) For items of electrical and mechanical equipment, controls, systems, components,
fittings and fixings, acceptable maintenance shall be the periodic and routine
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
9/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 9
Appendix 1 - Technical Specification Feb 2012
maintenance normally carried out on the various parts generally undertaken as
establishment practices of the Purchaser.
(4) The foregoing shall apply notwithstanding any inconsistent requirement or
information in any maintenance instructions provided by the Contractor or
otherwise put forward by the Contractor and any such inconsistent requirement or
information shall not, and shall not be relied on by the Contractor, to relieve, limit
or diminish any obligation or liability of the Contractor under the Agreement or
otherwise including in relation to Defects.
2. Overall Design Criteria
2-1. Type of Crane
The Crane shall be powered by shore power supply system, electrically driven rubber tyred
travelling gantry crane with a self-driven trolley with a cab. The Crane drive and controlshall be full AC inverter drive, with fully digitalised controls with PLC. The proposed drive
and control system shall be a proven system successfully operating on a similar capacity
crane in actual container handling operations.
2-2. Type of Cargo
The type of cargo to be handled by the Crane shall be
1 ISO 20ft, 40 ft and 45ft containers including high-cube, half height, flat rack
containers.
2 Other types of container with ISO corner fittings at 20ft, 40ft, or 45 ft positions.3 Containers with overheight cargoes through an overheight cargo container lifting
frame of the Purchaser.
4 Damaged container with slings and shackles attached to lifting lugs of the spreader.
2-3. Operating Environment and Design Aim
1. The Crane shall be operated and maintained on 24 hours per day basis in all weather
conditions. All electrical, electronic, and mechanical equipment shall be non-
hygroscopic, non-corroding suitable for use in conditions stated in 2-7.6, 2-7.7, 5-4
of this Specification.
The Cranes shall conform to the noise requirements in this Specification.
2. Special considerations shall be given in all aspects of the design for achieving
accurate load spotting ability with quick sway/yaw damping, and ensuring full
operational capability and safety for round the clock operations, including operation
under heavy rain and/or falling snow.
3. The Crane shall be exposed to non-technical personnel specifically at the ground
level and in access to trolley/operator’s cab. The Contractor will provide adequate,
safe and fool-proof protection in and around all equipment and fittings in these areas
of the Crane.
4. Ease of maintenance and safety of the maintenance staff shall be aimed at
throughout the design to minimise total downtime of the Crane.
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
10/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 10
Appendix 1 - Technical Specification Feb 2012
2-4. Mode of Operation and Performance Target (MMBF)
The Crane shall be manually controlled; all functions on the Crane shall be controlled fully
by the operator from the operators cab position.
The MMBF of the Crane will be ascertained by the Purchaser after its Commissioning. For
the purpose of ascertaining MMBF the Crane will be put into operation under such
conditions and circumstances as may exist or be required by the Purchaser from time to time
including if the Purchaser elects operation for the purpose of the Purchaser’s business and/or
for the specific purpose of ascertaining MMBF. No credit or allowance shall be given for
the benefit of the Contractor in respect of conditions, circumstances, and operator’s
performance.
The MMBF is defined as:
Twist Lock Count (TLC) for one week
Number of Breakdowns of a Crane for one week
TLC = One TLC is defined as the operation of twist lock + hoisting + trolley + lowering +
unlock.
The actual MMBF shall be recorded on a weekly basis. Following completion of the Initial
Trial Period, the Intermediate Trial Period and the Final Trial Period for a Crane the MMBF
shall be calculated by dividing the total number of twist lock counts recorded during the
final four-weeks by the total number of breakdowns in the same period.
2-5. Statutory Requirements and Minimum Design Standard
1. The Crane and its mechanism shall be designed and manufactured to comply in all
aspects with the requirements of all latest, applicable state or local Polish and
European Community laws, ordinances, rules, orders, or other legal or regulatory
institutes.
2. Where items are not covered by Poland / European Community Statutory
requirements, the Crane and other Goods shall be designed and manufactured to at
least the standards as specified in this Specification. For items which are not
specified above, then to at least to the current applicable recommendations of thefollowing organisations: -
AWS American Welding Society – Bridges and Dynamically Loaded Structures
BSI British Standards Institute
DIN Deutsche Industrie Normen
FEM Federation European de la Manutention
GB Chinese Standard Institute
IEC International Electro Technical Commission
MMBF =
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
11/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 11
Appendix 1 - Technical Specification Feb 2012
IEEE Institute of Electrical and Electronic Engineers
ISO International Standards Organisation
JIS Japanese Industrial Standards
UL Underwriters Laboratory
The Contractor shall be required to submit to the Purchaser a full list of applicable
standards used in the design of the Crane.
2-6. Minimum Class of Crane
Structures:
Class of Utilisation U7
State of Loading Q2
Group Classification A7
Impact Factor 1.4
Duty Factor 0.9
Normal Load Spectrum factor 0.80 of rated capacity.
Mechanisms
Mechanisms Class ofUtilisation
State ofLoading
GroupClassification
Hoist T7 L3 M8
Trolley Travel T7 L3 M8
Gantry Travel T7 L3 M8
2-7. General Design Criteria
2-7.1. Crane Particulars
Major dimensions, clearances and performance requirements:
(1) Rated Load
Under Spreader 41 tonnes.
(2) Test load for overload test 51.25 tonnes under spreader.
(3) Container type ISO 20’, 40’, and up to 53’ containers with ISO
corner fittings at 20’, 40’ or 45’ position.
(4) Spreader 20’/40’/45’ telescopic type
with power-operated retractable end flippers andmoving side guides capable of handling 8’ and
8’ 6” wide containers.
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
12/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 12
Appendix 1 - Technical Specification Feb 2012
(5) Span (Gantry) 23.470mm (77’) centres of wheels.
(6) Lift above ground 20,750 mmminimum to the lowest point of spreader (side
guides/ lowered end flipper).
Emergency hoist limit at 20,850mm to the
lowest point of spreader.
For the lowering, the headblock (spreader
removed condition) must be able to be lowered
onto the ground.
(7) Overall Crane
Length
Not more than 12,200 (40’).
(8) Speed – Main Hoist 25m/min. minimum with 41 tonne load under
spreader.
60m/min. minimum with empty spreader.
Acceleration or deceleration time max. 6.0 s for
empty spreader and 3s for rated load.
- Trolley 70m/min. minimum.
Acceleration time max. 4.0 s.
Deceleration time max. 3.0 s.
- Gantry 90m/min. minimum.
Acceleration/Deceleration time max. 8.0s.
The above speeds must be achieved for crane operation under a sustained 20
meter/sec. wind condition.
(9) Skew adjustment (*) ±5 degrees
Speed: 0.5 degree/second minimum
(*) Note 1 Skew adjustment systems shall be capable ofchanging attitude of a 41 Te container with 1.6
meter eccentricity.
(10) Anti-sway/yaw The Crane shall be provided with anti-sway
dampening.
The anti-sway system shall be capable of
damping the spreader after the trolley has
stopped with full deceleration at any operational
speed with any operational load, to within
50mm of lateral displacement after 2 cycles of
sway. The same criteria will apply to theyawing motion following the trolley stopping
from any operational speed with full
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
13/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 13
Appendix 1 - Technical Specification Feb 2012
deceleration, or after the end of the skew motion
command. The system shall meet the above
criteria measured at the spreader end beams
expanded to the 45’ position between 3.0 meters
above the ground level and the maximum lift.
(11) Number of gantry wheels Eight (8) (Two in line per corner).
(12) Gantry Wheels Steering A hydraulic wheel jack up system shall be
installed between each pair of wheels to allow
free turning of the wheel pairs through 90
degrees. The complete cycle from activation of
the wheel jack system, turning of the wheels
through 90 degrees to raising the jacks shall be
no more than 70 seconds.
The gantry system shall also be designed to
allow the wheels to adopt intermediate turning
angles to allow pivot turning of the Crane. See
4-3.3.
2-7.2. Dimensional Restrictions
(1) The Crane profile shall be within the structures limit as defined in the drawing no.
GCT-RTG-01 in Appendix I, to ensure safe operation of the Crane at any lane.
(2) The spreader width must be kept within 2800mm when handling 8’-0” widecontainers, and 2900mm when handling 8’-6” wide containers.
2-7.3. Yard Interface
(1) The Crane runway path is part of the reinforced concrete terminal pavement.
Typical layout of runways is shown on the attached drawing in Appendix. III. The
design should allow for cranes to safely pass other Cranes operating on adjacent
runways, taking into account 1% cross grades and certain amount of drift of the
Cranes.
(2) NOT USED
2-7.4. Electrical Facility Interface (Shore Power)
(1) A shore power supply system shall be installed on the crane through H.V. cable reel
system that shall permit the normal container operation. The power supply to the
crane shall be 15 KV (±15%) 3 phase, 50Hz±5%, a suitable transformer shall be
provided to convert the in-coming HV power supply down to match the crane
electrical system circuitry.
(2) The high tension trailing cable connection on the yard shall be terminated into
specially designed HV junction boxes. Termination of the cable conductors and fibre
waveguide in the plugs at the junction box shall be done by the Contractor.
Termination of the Purchaser’s power supply cable and optics fibre cables into the
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
14/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 14
Appendix 1 - Technical Specification Feb 2012
socket shall also be the scope of the Contractor. The high tension cable shall be
supplied by contractor with a suitable cable reeling device. A sufficient length of
cable to cover minimum 200 meters gantry travel range from the junction box shall
be provided by the Contractor. The Contractor shall bring the Crane trailing cable
end to the junction box and shall complete the cable connecting work with an
approved cable joint kit. The supply and installation of the H.V. junction box shall
be by others. The cable joints made at Site and high tension wiring shall be subject
to the inspection requirements of the local power supply authority
(3) The high tension trailing cable shall be 15 KV ethylene propylene rubber insulated
polychloroprene jacketed round type flexible power cable based on IECA Pub. S68 -
516 or the equivalent approved by the Purchaser.
The conductor shall be stranded flexible conductor consisting of tinned annealed
copper wires. The cable shall also carry the fibre- optic cable for the remote CCMS
(refer to 5-7).
(4) The HV cable reel shall be installed opposite to the operator cabin, the transformer
on the electrical house side. The cable reel shall be installed within the restricted
dimensions as set out in 2-7. The drive control system of the cable reel shall be
designed to minimise abrupt starting, braking and excessive slack / tension in the
cable when the Crane passes the cable feed point. Sensors to detect the above
conditions shall be provided.
(5) Cable guide wheels shall be installed near the gantry trucks to keep the high tension
cable close to the ground level. The cable shall be laid inside the cable slot within a
total wheel base of gantry trucks in one corner.
(6) The system especially the high tension slip ring components shall be well protected
from weather, having an IP rating of not less than 55.
(7) The cable reel drive machinery and slip ring area shall be isolated by fencing or
other means and to permit to access of authorised persons only. High tension
warning signs shall be provided and fitted to the entrance of the fenced area.
(8) A suitably sized space heater shall be provided for the slip ring enclosure. An
indicator light indicating functioning or malfunction of the space heater shall be
installed near the cable reel machinery and shall clearly visible from ground level.The slip ring enclosure shall have hinged, sealed and lockable access panels on
both sides to provide for easy access for servicing and maintenance.
(9) Limit switches to control gantry motion near the travelling limit (limited by cable
length) shall be provided.
(10) An override switch shall be provided to allow operation of the cable reel drive. This
switch shall be enclosed in a lockable and weatherproof box mounted at groundlevel in the proximity of the cable plough arrangement.
(11) The composite HT trailing cable shall incorporate not less than eight (8) numbers of
low loss silica glass optical fibre waveguides. The cable reel mechanisms shall
incorporate low loss connecting devices that allow the use of all waveguide
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
15/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 15
Appendix 1 - Technical Specification Feb 2012
simultaneously linking the equipment on the crane to external devices. The standard
for the waveguide shall be 60/125 micron.
(12) The optical waveguide shall be terminated with Avaya ST-2 type standard
connectors unless otherwise specified. The composite cable shall be separated into
power and optical fibre cables for termination work in the junction boxes on yard as
well as the cable reel on the Crane.
(13) The source of power supply shall be connected to CMS system (refer to 5-7) and
also indicator in operator cabin.
2-7.5. Communication Facility Interface (Radio)
NOT USED.
2-7.6. Climatic Conditions
The Crane and other Goods shall be designed and constructed to be fully capable of
operating safely and withstanding the following climatic conditions.
(1) Ambient temperature -20oC to 40
oC
(2) Relative humidity Max. 100%
(3) Dew point Max. 3oC
(4) Wind up to 25m/sec. without special warning during operation.
More stringent and specific requirements shall apply for individual crane and other Goods
subsystems and components, which are separately specified in each relevant clause of thisSpecification.
2-7.7. Wind Conditions
The entire Crane structure with all of its machineries, components, fittings, or accessories,
and all tie-down equipment shall be designed and constructed to withstand following wind
loading conditions.
(1) Allow for wind loading of sustained wind speed of 25m/sec. for safe load handling
operation of the Crane.
(2) For the stowed condition of the Crane:
A wind loading of wind speed up to 43m/sec. shall be allowed for the condition that
the Crane is out of service and stationary without any gantry tie downs, but trolley
anchored.
2-7.8. Lifting Loads and Stability
(1) One side landing
i) A normal operating condition shall include the case of one side landing of a
45ft - concentric 41 tonnes weight container, in which case a set of main
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
16/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 16
Appendix 1 - Technical Specification Feb 2012
hoist wire ropes on the landed side is assumed slack and not carrying the
load.
ii) The calculations of the structural and mechanical components shall include
calculation for this criterion.
(2) Eccentric container handling
i) All structural, mechanical and electrical systems or system components shall
be designed to be capable of handling continuously 28 Te gross weight
containers with eccentricity of 1.2m in longitudinal (gantry) direction and
0.25m in transverse (trolley) direction. The eccentricity of container shall
not cause any horizontal drift of the container during hoisting/lowering
motion.
ii) The Contractor shall submit for the Purchasers review, a design method tocompletely eliminate the possibility of lifting one end of a container by two
twistlocks. The design shall incorporate a system to immediately detect this
condition and to render the hoist motion inoperable. The spreader which
stops with one end locked inside a container shall allow lowering only with
attendance of maintenance personnel.
(3) Fatigue condition
All structural fatigue calculations shall include the case of continuous handling of a
28 Te gross weight container with 1.2m eccentricity in longitudinal direction.
Minimum loading cycle to be 2 million cycle.
(4) Dynamic snag load (catch load)
The Crane shall not sustain any damage due to dynamic snag load. The Contractor
shall submit structural calculations to prove that structures are safe under dynamic
snag load.
(5) Stability
(i) The Crane shall be stable with a reasonable safety margin and shall not
sustain damages when a dynamic snag load is applied at any trolley andhoisting position.
(ii) The Crane shall be stable and shall not sustain any damage in the case when
emergency push button is pressed during gantry travel with a rated speed
with a 41 tonnes rated load suspended at the maximum lift height position in
an operational gantry gradient of not more than two percent.
(6) All other loading conditions forming the design criteria other than specified in this
Specification shall be submitted to the Purchaser for review.
2-8. NOT USED
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
17/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 17
Appendix 1 - Technical Specification Feb 2012
2-9. Noise Control
The Crane’s noise level shall conform to the following requirements: -
(1) The noise level inside the operator’s cab shall be below 75dB during
operation, with air conditioner on, and doors and windows closed condition.
(2) The noise level measured at a distance of 1 meter from any corner of the
machinery house shall be below 85 dB
2-10. Operationally Critical Components
(1) The Contractor shall submit the inspection and replacement schedule for the
operationally critical components to the Purchaser.
(2) The objective is to assist the Purchaser to establish a standard for maintenanceand inspection of operationally critical components (i.e. those components and
structural joints where failure could have catastrophic consequences).
3. Crane Structural Specification
3-1. General Requirement
3-1.1. Deflection or oscillation of the structure shall not affect the Crane capacity and operating
efficiency (particularly spreader positioning ability).
3-1.2. The main structure shall be designed so as not to sustain damage in the event of puncture ofany one tyre.
3-1.3. The girder shall be designed to allow operator to escape from the operator’s cab to the
walkway of the girder at any point of trolley travel range, in an emergency.
The walkways along the full length of the girder members shall be mounted off the side
of the girder members and not less than 800mm below the top flange of the girder. The
“Power Chain” may also be mounted between the side of the girder and the walkway to
afford protection against falling from the walkway to the inside of the crane.
3-1.4. Trolley rails shall comprise a standard rail section and be fitted to the girder through railclips and a proven fastening system. The rail joints shall be welded and ground smooth.
3-1.5. The following equipment/machinery shall be fitted to the main structure.
(1) Gantry drive machineries including 90 degree and an intermediate angle (for spin
turn) steering mechanisms.
(2) Control panels and panel house.
(3) Starting equipment and control panel.
(4) Trolley power feeding system.
3-1.6. The following fittings shall be fitted to the main structure.
(1) Walkway, stairs, ladders and platforms (refer to 6-1).
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
18/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 18
Appendix 1 - Technical Specification Feb 2012
(2) Lighting for operation and for walkway, stairs, ladders and platforms (refer to 6-2)
(3) Intercom telephones (refer to 5-6.1).
(4) Travel warning device (refer to 6-5.1). Speakers and flashing strobe light at each
of 4-corners.
(5) Service outlet (refer to 6-7).
(6) Emergency stop buttons (refer to 6-6).
(7) Four fire extinguishers; 5kg CO2 capacity, 1 at outside of panel house, 1 at
trolley platform and one 2 kg at outside the driver’s cab.
3-2. Material
3-2.1 The whole of the materials used in the Crane shall be new, of the best quality and suitable
for the duty intended. Mill certificates shall be obtained and records strictly maintained to
match these to the various Crane sections produced during crane manufacture. The steel
materials for all the stress members shall be selected from the materials which specification
includes the notch toughness requirement at or below -20 deg. Celsius.
3-2.2 The steel used for the manufacture of the Crane shall conform as a minimum to one or more
of the following standards most recent issue.
Deutsche Industrie Norman (DIN)
British Standards (BS)
Japanese Industry Standards (JIS)
American Standards (ASTM/API)
Chinese Standard (GB)
3-2.3 Welded Joints
Stresses at weld throats shall be calculated as the vector sum of the individual stresses
applied to the weld throat. For fatigue design when calculating the stress range, the
vector difference of the greatest and least vector sum stress may be used instead of the
algebraic difference.
Welded joint design shall conform to BS 5400: Part 10, BS 7608, and for static loads
only AWS D1.1 - 2000.
3-2.4 Bolted Joints
Bolted joint design shall conform to BS 5400: Part 10, BS 7608, and to the AISC
Specification using 0.9 times AISC allowable values. Prying action due to distortion of
the connection details shall be considered. Bolts subject to fluctuating tensile stress shall
be checked according to BS 7608. Bolts governed by fatigue strength shall comply with
ASTM A325. Structural bolted joints are not allowed unless approved in writing by
Purchaser.
3-2.5 Pin Joint
An effective lubrication system shall be provided for each pin Joint to prevent its seizure
within the life of the structure.
3-2.6 Machinery bases
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
19/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 19
Appendix 1 - Technical Specification Feb 2012
All main drive machinery bases (Motors, brakes, gearboxes, bearing housings/pedestals, etc.)
shall be machined; after all adjacent welding has been completed.
All machinery mounts shall have adjustable locking screws for horizontal adjustment
(forward and backwards, side to side) for the purposes of the equipment alignment.
3-2.7 Edge Finish
All edges of structures shall be free from sharp edges or burrs.
3-2.8 Surface Finish
(1) All welding spatters shall be removed from structure surfaces.
(2) The metal surfaces shall be cleaned and touched up with primer immediately aftercooling down to prevent oxidation and the formation of rust.
3-2.9 Draining and Inspection Manhole
(1) All the structure shall be designed to drain water effectively. Any draining water
shall not affect safety of operations or maintenance work under heavy rain. No
water trap shall be allowed in any part of the crane structure. Adequate numbers of
inspection manholes shall also be installed.
(3) Appropriately, sized manholes shall be provided in all unsealed members to provide
for internal inspection. The manholes shall be positioned such to allow access fromeach end of any unsealed member and particular attention for safety shall be given to
those areas where manholes directly access onto or from vertical ladders.
3-3. Calculations
3-3.1 Submission to Purchaser
(1) Wheel loads, stability calculations, braking capacity and distance calculations for all
motions, and peak power consumption calculations shall be submitted for
Purchaser's review prior to commencement of detailed design.
(2) Other data or design calculations at various stages of design shall be submitted from
time to time as requested by the Purchaser as part of review process.
3-4. Loads
3-4.1 The design shall incorporate all loads and load combinations pertinent to all in service
and out of service conditions of the crane. The loads due to temperature effects, erection
stresses, and others based on the Contractor's experience shall be included in the analysis
if they cause significant stresses. If rational analysis indicates loads larger than specified,
the larger loads shall be used.
3-4.2 The Contractor shall comply with BS2573: Part 1: 1983, Rules for the Design of Cranes.
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
20/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 20
Appendix 1 - Technical Specification Feb 2012
3-5. Members Subject To Buckling
(1) The design of columns, beam columns, frames and beams subject to lateral buckling
shall be in accordance with the AISC Specification. The design of flat plates, curved
plates, and plate stiffeners shall be in accordance with a recognized method that
considers the combined effect of shear, compression and flexure. The effects of
biaxial stresses shall be included. Criteria given in FEM are acceptable.
(2) For all structural plates, the ratio of the minimum clear dimension, b, to thickness, t,
shall not exceed 60, i.e. 60 ≥ b/t.
(3) The local buckling criteria given in the AISC and AISE standards are unacceptable
because biaxial and combined stress effects are ignored. The choice of a practical
method of calculation is left to the Contractor who shall state the origin of the
method chosen.
(4) Tension field action may be included for evaluating pure shear resistance during
overload and stowed conditions, provided the tension field shear panels are designed
for a factor of safety against collapse of at least 1.25. Tension field panels shall be
assumed to have zero capacity to resist bending, bearing or axial stress.
3-6. Fatigue Design Criteria
3-6.1 Fatigue design shall generally conform to the requirements of BS 5400: Part 10 1980,
except as modified in this section. Modifications to BS 5400 pertain primarily to the
deletion of provisions that apply to bridges only, insertion of design load spectra
applicable to container cranes and the addition of provisions for tubular joints.
3-6.2 When not specified in BS 5400, the requirements and recommendations in BS 7608 shall
be followed.
3-7. Connection Designs
(1) Connections shall be designed to resist artificial local loads imposed by a stress
equal to the average of the allowable and the calculated stress, but they shall be
designed for not less than 75% of the allowable strength of the member. Notice
that whenever the calculated stresses are less than 50% of the allowable stress, the
75% requirement applies.
(2) Stresses at weld throats shall be calculated as the vector sum of the individual
stresses applied to the weld throat. For fatigue design when calculating the stress
range, the vector difference of the greatest and least vector sum stress may be
used instead of the algebraic difference.
(3) Welded joint design shall conform to BS 5400: Part 10, BS 7608, and AWS D1.1,
Section 9, except for Sections 9.2.1, 9.3, 9.4, 9.5 and 9.6 which contain
information that is covered elsewhere in these Specifications.
(4) Bolted joint design shall conform to BS5400: Part 10, BS 7608. Prying action
due to distortion of the connection details shall be considered. Bolts subject to
fluctuating tensile stress shall be checked according to BS 7608.
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
21/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 21
Appendix 1 - Technical Specification Feb 2012
3-8. Gantry Structure Stiffness
3-8.1. Deflection or oscillation of the structure shall not affect the Crane capacity and operating
efficiency (particularly spreader positioning ability).
3-8.2 The horizontal displacement at the girder level due to full acceleration or deceleration of
trolley with a rated load, or full acceleration or deceleration of trolley while suspending a
rated load at the maximum upper limit position, shall not exceed 30mm.
3-8.3 The main structure shall be designed so as not to sustain damage in the event of puncture of
any one tyre.
3-9. Camber
The camber of the two main girders should make due allowance for deflection under load.
3-10. Trolley Rails & Rail Fixing
Trolley rails shall comprise a standard rail section and be fitted to the girder through rail
clips and a proven fastening system. The trolley rails shall be supported by the girders with
Gantrex type rail pads and steel plate to reduce vibration of trolley. The rail joints shall be
welded and ground smooth.
3-11. Workmanship
3-11.1 The whole of the structural fabrication and assembly shall be done in a through,workmanlike manner and shall follow the best modern practices in the manufacture of
high-grade structures. The work shall be performed by workmen suitably skilled in their
particular trades.
3-11.2 Welders, welding operators and tackers shall be certified, for the material, processes and
type of welding being performed, by an independent testing laboratory within 6 months
prior to performing such work. The certifying laboratory will be approved by the Purchaser.
3-11.3 Certification of the qualifications of each individual welder shall be submitted by the
Contractor. Welds installed using unqualified procedures or welding performed by non-
certified welders shall be subject to removal by the Contractor at his own expense.
3-11.4 The Contractor’s Quality Assurance team shall be required to keep an accurate log of the
qualified welders on the job. This log will be subjected to examination at any time by the
Purchaser or their site representative.
3-11.5 Welding procedures may be AWS prequalified or they shall be qualified in accordance
with AWS by the approved testing laboratory.
3-11.6 Written procedures for all welded joints shall be submitted to the Purchaser. Procedures
shall identify required inspections that may be critical to the specific welds. Procedures
shall be identified on the drawings and shall be made available to all appropriate shop
personnel. Procedures shall be prepared in a manner such that shop personnel can
understand and use them without referencing the applicable codes.
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
22/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 22
Appendix 1 - Technical Specification Feb 2012
3-11.7 These requirements shall apply to all welding, burning, cutting and grinding on the crane
structure. This includes welds for erection attachment, whether or not they are removed,
and electrical clips and conduit supports.
3-11.8 The Contractor’s Quality Assurance team will ensure that all correct welding procedures
are strictly followed by the welding personnel. Any welding work being seen to not meet
accepted procedures shall be stopped immediately and logged as a non-conformance report.
Continuation of this welding will then be subject to approval by the Purchaser’s
Representative on site.
3-11.9 The Contractor’s Quality Assurance team will ensure that all welding during low
temperatures is carried out under an appropriated welding procedure, as far as practicable,
within an enclosed canopy to provide a controlled environment. The use of correct pre-
heating procedures and welding rod hot boxes is essential and will be closely monitored by
the Purchaser’s Representative.
3-11.10 To facilitate removal / replacement or regular maintenance, all unpainted metal surfaces
shall be treated with an appropriate approved anti-corrosion treatment.
i) Structural Pins-“Copper Kote”, “Copper-slip”, “Moly-slip”, or “Molybonum di
sulphide”
ii) Bearings, housings-grease
iii) Tapped holes-“Never-Seize”
iv) Bolts-“Never-Seize”
3-11.11 A325 and A490 bolts that are 7/8” (22mm) in diameter or less may be tightened to the
required tension by any standard method. A325 and A490 bolts greater than 7/8” (22mm)diameter shall be tightened to the required tension by the calibrated wrench method only.
The following supplemental requirements shall apply in addition to the requirements of the
Specifications to structural joints using ASTM A325 or A490 bolts.
(i) Hardened washers shall be placed under the both the head and the nut.
(ii) The contractor shall notify the Engineer if the highest and lowest torques measured
during wrench calibration varies by more than 10 percent of the lowest torque, so
they may develop the appropriate solution. If the range exceeds this tolerance, filed
tightening may be erratic.
(iii) The “snug tight” tension shall be approximately 50 percent of the specified tension
and shall be achieved using a calibrated wrench.(iv) The sequence of bolt tensioning shall be shown on the drawings.
(v) After the snug tight condition is achieved, an initial tension of 75 percent of the final
tension shall be developed in all the bolts. Only then shall the final tension be
developed
(vi) The final tension shall be verified by testing 10 percent of the bolts after all the bolts
are tensioned. If the verification indicates loss of tension in some bolts, the
Contractor shall notify the Purchaser. The Purchaser and the Contractor will develop
the appropriate action.(vii) The flange contact bearing surfaces shall have at least 75% of the bearing cross-
sectional areas in contact. The outer surface of the flanges shall fit within 0.010in.
(0.25mm) for 75% of the length of the edge and not more than 1/32in. (1mm) for the
remaining 25% of the length.
-
8/20/2019 TECHNICAL SPECIFICATION FOR RUBBER TYRED GANTRY CRANES
23/112
[ GCT - RUBBER TYRED GANTRY CRANES ]
Page: 23
Appendix 1 - Technical Specification Feb 2012
(viii) Bolt tension may be verified at locations selected by the Purchaser’s Representative.
Bolt tension verification shall be performed by the Contractor in the present of the
Purchaser’s Representative and in such a manner that the torque can be wrench gage
read during verification.
3-11.12 Weld Testing and Inspection
All welds shall be subjected to inspection by methods and extent, reflecting the critical
nature of the welded connection.
Welds shall meet the requirements for cyclically loaded structures of AWS D1.1-latest
version. The specific method of weld inspections shall be shown on the drawings. Weld
inspection procedures shall be submitted to the Purchaser.
Testing, which shall be at the Contractors expense is required as follows:-
Weld Type of Testing/Inspection Acceptance Criteria
All Welds 100% Visual AWS D1.1-latest version
Full Penetration Butt Welds
(Compression)
100% UT
1 X Exposure ≈ 400 mm
per weld
AWS D1.1-latest version
Full Penetration Butt Welds
(Tension-as determined by
stress levels due to operating
loads combinations)
100% UT
10% of length RT or
1 X exposure per weld
length ≈ 400 mm which
ever is the greater
AWS D1.1-latest version
Full Penetration Butt Welds inTension Bars (if applicable)
100% UT100% of length RT
AWS D1.1-latest version
Fillet Welds or Partial
Penetration Welds
On FCM
On Non-FCM
100% of length MT
10% of length MT
(as nominated by the
Purchaser’s Representative)
AWS D1.1-latest version
Rejection of any portion of a weld inspected on a less than 100% basis shall require
inspection of 100% of that weld.
Ultrasonic testing of tension welds shall be done by or under the direct supervision of ASNT
Certified LEVEL III personnel.
3-12. Quality Control of Structure Fabrication
3-12.1 Qua