Technical Services Branch (TSB) Addendum Form...2019/07/03 · Technical Services Branch (TSB)...
Transcript of Technical Services Branch (TSB) Addendum Form...2019/07/03 · Technical Services Branch (TSB)...
Technical Services Branch (TSB) Addendum Form
2019 07 11 Page 1 of 1
Addendum for:
TECHNICAL DESIGN REQUIREMENTS FOR ALBERTA INFRASTRUCTURE FACILITIES, MARCH 2019
Addendum No.:
3
Contents:
Update to include: “Appendix J”
Contact:
Troy Holloway [email protected] 780-422-7620
Issued Date:
2019-07-11
Appendix J – new appendix to the Technical Design Requirements (TDR), includes:
1 - “Design Review Deliverable Summary and Checklist” 2 – “Sample Design Report Table of Contents”
1 Design Review Deliverable Summary and Checklist, July 2019
Deliverable Summary:
Please include details on project progress, major changes or decision etc…
Design Review Deliverable Summary and Checklist
This document is to be completed by the consultant for Alberta Infrastructure projects that require a Design
Review by the Technical Services Branch.
Date Workspace Size
Project Name
Project Manager
Prime Consultant
Design Phase
Design Review Deliverable Summary and Checklist, July 2019 2
Schematic Design Deliverable Checklist
Discipline Deliverable Included in
Submission?
Roofing
Description of proposed roofing composition ☐
Warranty requirements (ARCA, Manufacturer’s, etc.) ☐
PV attachment method (if applicable; affects warranty) ☐
Building
Envelope
Description of proposed building envelope assemblies ☐
Compliance with PERSIST requirements ☐
Design strategy for any unconventional or complex envelope
elements ☐
Sustainability
Confirmation of project Tier and LEED Silver target ☐
Sustainability/LEED strategy (narrative) ☐
Preliminary LEED checklist ☐
Hazmat
Information related to hazardous building materials, including
survey report
☐
Preliminary detailed drawing of radon mitigation system ☐
Architecture
Refer to Canadian Handbook of Practice for Architects ☐
Refer to Sample Design Report Table of Contents and
Design Development Expectations (TDR Appendix J) for
additional guidance
☐
Description of functional requirements of interior spaces ☐
3 Design Review Deliverable Summary and Checklist, July 2019
Interior
Design
Proposed interior finishes ☐
Life safety and universal design requirements ☐
Preliminary floor plans ☐
Mechanical See Item 5.1.3 of TDR ☐
Controls Not applicable. ☐
Electrical See Item 6.1.10 of TDR ☐
Structural Structural Schematic Design Report with a narrative
describing information per Item 4.8 of TDR ☐
Acoustics See Item 7.5 of TDR ☐
Civil
Provide a narrative outlining:
1. Referenced codes and standards ☐
2. Site investigation report ☐
3. Site services: water, sanitary sewer, and storm sewer ☐
4. Stormwater management and drainage design ☐
5. Site grading ☐
Design Review Deliverable Summary and Checklist, July 2019 4
Design Development Deliverable Checklist
Discipline Deliverable Included in
Submission?
Roofing
Roofing composition is determined and clearly listed ☐
Preliminary detail drawings including roof plans with drainage
plans (defined slopes, drain locations, etc.), section details
showing proposed roof to wall connections
☐
Building
Envelope
All envelope assemblies determined and identified ☐
Major sections showing relevant conditions, plus sections
showing peculiar geometry (canopies, clerestories, projecting
elements)
☐
Typical details identifying the lines of air barrier, thermal
barrier, and moisture barrier ☐
Preliminary details for coordination of structure and building
envelope ☐
Outline specifications for significant envelope elements ☐
Sustainability
Confirmation of project Tier and LEED Silver target ☐
Sustainability/LEED strategy (narrative) ☐
Preliminary LEED checklist ☐
Hazmat
Detailed specification for Hazmat removal ☐
Detailed specification for proposed radon mitigation system ☐
Architecture Refer to Canadian Handbook of Practice for Architects ☐
5 Design Review Deliverable Summary and Checklist, July 2019
Refer to Sample Design Report Table of Contents and
Design Development Expectations (TDR Appendix J) for
additional guidance
☐
Interior
Design
All floor plans are required ☐
Functional relationships identified ☐
All rooms identified ☐
Moveable or operable partitions identified ☐
Interior partition construction identified ☐
Preliminary elevations, sections, and details ☐
Preliminary millwork identified ☐
Mechanical See Item 5.1.4 of TDR ☐
Controls See Item 5.1.4 of TDR ☐
Electrical See Item 6.1.10 of TDR ☐
Structural
Structural Design Development Report with contents as
described below ☐
A narrative describing updated information per Item 4.8 of
TDR ☐
Drawings per Item 4.9 of TDR ☐
Acoustics See Item 7.5 of TDR ☐
Civil The Design Development Report shall contain a civil section
and drawings that includes the information listed above and ☐
Design Review Deliverable Summary and Checklist, July 2019 6
provide details on the site services (existing locations and
capacities, the sizes of new utilities, and connections).
The drawings are expected to have:
a. Existing site grades ☐
b. Site Servicing Plan ☐
c. Stormwater management plan ☐
d. Site grading plan ☐
7 Design Review Deliverable Summary and Checklist, July 2019
Construction Documents 75% Complete Deliverable Checklist
Discipline Deliverable Included in
Submission?
Roofing
Completed roof plans with drainage plans and penetrations ☐
Sufficient section details clearly showing all components
within the assemblies. Provide clearly illustrated wall to roof
tie-ins at parapets and roof to high wall details
☐
Specification to be at or near completion with all proposed
materials and approved manufacturers listed. Warranty and
inspection services should be clearly defined
☐
Building
Envelope
A sufficient quantity of completed envelope plan and section
details to represent the approaches to be used for the
balance of the project
☐
At least preliminary details for all penetrations, interfaces
between differing assemblies, and elements such as
canopies and louvers
☐
Plans and sections sufficiently complete to identify all the
details needed for the balance of the project ☐
Preliminary specifications for significant envelope elements ☐
Sustainability LEED checklist ☐
Hazmat Consultant responses addressing previous hazmat and radon
related feedback from SD and DD stages
☐
Architecture Refer to Canadian Handbook of Practice for Architects ☐
Design Review Deliverable Summary and Checklist, July 2019 8
Interior
Design
Coordinated floor plans with all Engineering disciplines (i.e.
Structural, Mechanical, Electrical, etc.)
☐
Potential conflicts with function of adjacent spaces identified
and mitigation strategies identified
☐
All rooms identified and coordinated with door and hardware
schedule
☐
Moveable or operable partitions identified and details
provided
☐
Interior partition construction identified and details provided ☐
Further developed elevations, sections, and details ☐
Specifications for all interior finishes ☐
Mechanical See Item 5.1.5 of TDR ☐
Controls See Item 5.1.5 of TDR ☐
Electrical See Item 6.1.10 of TDR ☐
Structural
75% complete Contract Drawings with Design Information
per Item 4.10 of TDR ☐
75% complete Book Specification Sections for all structural
items in the scope of work for the project per Item 4.11 of
TDR
☐
Acoustics See Item 7.5 of TDR ☐
Civil
Civil drawings shall include the following:
a. Existing site grades ☐
b. Site Servicing Plan ☐
9 Design Review Deliverable Summary and Checklist, July 2019
c. Stormwater management plan ☐
d. Site grading plan ☐
e. Pavement Plan ☐
f. Fire emergence movement plan ☐
g. Detail drawings ☐
h. Erosion and sediment control plan ☐
Prepare contract document specifications using the Alberta Infrastructure
Technical Specifications as a basis to include, but not to be limited by:
a. Local municipality’s design standards ☐
b. Standards and Guidelines for Municipal
waterworks, wastewater and storm drainage
systems (Alberta Environmental Guidelines)
☐
c. Barrier-Free Design Guidelines ☐
All applicable Master Specifications in Alberta Infrastructure
Technical Specifications ☐
Design Review Deliverable Summary and Checklist, July 2019 10
Pre-Tender Deliverable Checklist
Discipline Deliverable Included in
Submission?
Roofing
Complete and coordinated detail drawings and specification
documents
☐
75% (and prior) requirements are complete ☐
Building
Envelope
Complete all the 75% requirements ☐
Clear coordination between specialties (e.g. envelope,
structural, mechanical, electrical details at canopies for
support, roof drainage, lighting)
☐
Complete specification using terms consistent with drawings ☐
Sustainability LEED checklist ☐
Hazmat All comments previously identified must be reflected and
included at this stage with no further comments from our unit
☐
Architecture Refer to Canadian Handbook of Practice for Architects ☐
Interior
Design
Final floor plans, elevations, sections, and details fully
coordinated with all disciplines
☐
Final specifications ☐
Mechanical See Item 5.1.5 of TDR ☐
Controls See Item 5.1.5 of TDR ☐
11 Design Review Deliverable Summary and Checklist, July 2019
Electrical See Item 6.1.10 of TDR ☐
Structural
100% complete Contract Drawings with Design Information
per Item 4.10 of TDR ☐
100% complete Book Specification Sections for all structural
items in the scope of work for the project per Item 4.11 of
TDR
☐
100% complete Book Specification Sections for construction
inspection and materials testing per Item 4.12 of TDR ☐
Acoustics See Item 7.5 of TDR ☐
Civil
Civil drawings shall include the following:
a. Existing site grades ☐
b. Site Servicing Plan ☐
c. Stormwater management plan ☐
d. Site grading plan ☐
e. Pavement Plan ☐
f. Fire emergence movement plan ☐
g. Detail drawings ☐
h. Erosion and sediment control plan ☐
Prepare contract document specifications using the Alberta Infrastructure
Technical Specifications as a basis to include, but not to be limited by:
a. Local municipality’s design standards ☐
b. Standards and Guidelines for Municipal
waterworks, wastewater and storm drainage
systems (Alberta Environmental Guidelines)
☐
c. Barrier-Free Design Guidelines ☐
All applicable Master Specifications in Alberta Infrastructure
Technical Specifications ☐
1 July 2019
Sample Design Report Table of Contents
Purpose
This document consolidates the major elements that comprise a typical Schematic Design and
Design Development report. The Schematic Design report summarizes and synthesizes background
information and client requirements into architectural design options, and proposes a recommended
design solution based on an analysis of the pros and cons of each. During Design Development,
architectural, engineering, and specialist consultants apply their skills to refine the design concept so
that it can progress to the Construction Documents phase.
While the sample described below is intended for a school project, it can be adapted to suit any other
building typology. Following the Sample Table of Contents, a list of Design Development Drawing
Expectations is provided. This document presents the information typically expected in the Design
Development drawing submission (although it cannot capture every element of every project).
The Sample Table of Contents and Design Development Drawing Expectations are offered as a
reference for the information of Project Managers, Design Teams, and other stakeholders, and do not
replace the requirements or obligations in the Owner’s Consultant Agreement, documents such as
the Canadian Handbook of Practice for Architects, or those found elsewhere in the Technical Design
Requirements for Alberta Infrastructure Projects (TDR).
0.0 Executive Summary ................................................................................................. -
1.1 Areas Summary ..................................................................................................... -
1.2 Cost Summary ....................................................................................................... -
1.3 Schedule Summary ................................................................................................ -
2.0 Response to Functional Program ................................................................................ -
2.1 Instructional Areas ..................................................................................................... -
Classrooms ............................................................................................................................. -
Ancillary Rooms (Art, Music, Band) ........................................................................................ -
Gymnasium & Gymnasium Storage ....................................................................................... -
Library/Resource Centre ......................................................................................................... -
Science Rooms ....................................................................................................................... -
Fine Arts .................................................................................................................................. -
Career & Technology Studies (CTS) ...................................................................................... -
2 July 2019
Wrap-Around Services ............................................................................................................ -
Technology ............................................................................................................................. -
Special Education ................................................................................................................... -
Instructional Flex Space ......................................................................................................... -
2.2 Non – Instructional Areas ........................................................................................... -
Administration & Staff ............................................................................................................. -
Physical Education Flex Space .............................................................................................. -
Non-Instructional Flex Space .................................................................................................. -
Circulation ............................................................................................................................... -
Storage ................................................................................................................................... -
Washrooms ............................................................................................................................. -
Wiring Network & Server ........................................................................................................ -
Mechanical & Electrical ........................................................................................................... -
Cafeteria & Food Services ...................................................................................................... -
2.3 Functional Relationships ............................................................................................ -
Circulation ............................................................................................................................... -
Zoning ..................................................................................................................................... -
Site Planning ........................................................................................................................... -
Area Redevelopment Plan, Urban Design Review Panel, Overlays, Integration of Sports
Fields & Other Neighbourhood Amenities .............................................................................. -
Land Use Analysis .................................................................................................................. -
Civil Design (Watershed Controls, Riparian Developments/Ponds) ..... Error! Bookmark not
defined.
Expansion (Classrooms, Parking) .......................................................................................... -
Parking & Vehicular Circulation (cars/buses, bicycles, loading, shipping, handling, waste)
Error! Bookmark not defined.
3.0 Project Principles ..................................................................................................... -
3.1 Methodology .......................................................................................................... -
Structure of Meetings .............................................................................................................. -
Key Stakeholders .................................................................................................................... -
Public Process ........................................................................................................................ -
3.2 Implementation ...................................................................................................... -
Procurement & Tendering Strategy ........................................................................................ -
3 July 2019
3.3 Research ............................................................................................................... -
Benchmarking Analysis .......................................................................................................... -
Typologies ............................................................................................................................... -
Systems & Materials ............................................................................................................... -
3.4 Concepts ................................................................................................................ -
Approach & Parti ..................................................................................................................... -
Analysis of Options (Circulation, Zoning, Functional Relationships) ...................................... -
Materiality ................................................................................................................................ -
Organizational Principles .........................................................................................................
Building Envelope Approach (Roof, Fenestration/Clerestory, Wall Systems)………..……….-
3.5 Mature Buildings (>40 years) ................................................................................. -
Modernism .............................................................................................................................. -
3.6 Historic Places ........................................................................................................ -
Designation & Character Defining Elements .......................................................................... -
Scope & Standards ................................................................................................................. -
Guidelines for Conservation ................................................................................................... -
3.7 Sustainability .......................................................................................................... -
District Planning & Integration ................................................................................................ -
Social Sustainability: Purposeful/Meaningful & Adaptable/Flexible ........................................ -
Green Building Standards…………………………………………………………………………..-
Commissioning……………………………………………………………………………………….-
4.0 Architecture, Planning, & Interior Design ............................................................... -
4.1 Principles of Urban Design: A: Urbanism ................................................................... -
A1: The City ............................................................................................................................ -
A2: The Neighbourhood, District, & Corridor .......................................................................... -
A3: The Block, Street, & Building ............................................................................................ -
4.2 Principles of Urban design: B: Design Excellence ...................................................... -
B1: Sustainability .................................................................................................................... -
B2: Public Arts & Culture ........................................................................................................ -
B3: Celebrate the Weather & Climate..................................................................................... -
B4: Durable, Permanent & Timeless Materials ....................................................................... -
B5: Appropriate Use of Innovation .......................................................................................... -
4 July 2019
4.3 Principles of Universal Design ................................................................................... -
Equitable Use .......................................................................................................................... -
Flexibility in Use ...................................................................................................................... -
Simple & Intuitive Use ............................................................................................................. -
Perceptible Information ........................................................................................................... -
Tolerance for Error .................................................................................................................. -
Low Physical Effort ................................................................................................................. -
Size & Space for Approach & Use .......................................................................................... -
5.0 Landscape Architecture ........................................................................................... -
Landscape Design Overview .................................................................................................. -
Soft & Hard Landscaping ........................................................................................................ -
LEED ....................................................................................................................................... -
Special Considerations ........................................................................................................... -
6.0 Geotechnical ................................................................................................................. -
7.0 Civil ................................................................................................................................ -
8.0 Structural ....................................................................................................................... -
Structural Overview................................................................................................................. -
Foundations ............................................................................................................................ -
Structural Systems & Framing ................................................................................................ -
Special Considerations ........................................................................................................... -
9.0 Mechanical ..................................................................................................................... -
Mechanical Overview .............................................................................................................. -
Site Service Distribution .......................................................................................................... -
Heating Systems ..................................................................................................................... -
Cooling Systems ..................................................................................................................... -
Ventilation Systems ................................................................................................................ -
Plumbing Systems .................................................................................................................. -
Fire Protection ......................................................................................................................... -
Pipe & Duct Insulation ............................................................................................................ -
Acoustics (Active & Passive Attenuation) ............................................................................... -
Energy Management Control Systems ................................................................................... -
Building Start-up & System Verification .................................................................................. -
LEED ....................................................................................................................................... -
5 July 2019
Operating Costs & Energy Consumption ................................................................................ -
10.0 Electrical ...................................................................................................................... -
Electrical Overview ................................................................................................................. -
Exterior & Site Electrical Systems .......................................................................................... -
Building Interior Systems ........................................................................................................ -
Lighting (Artificial & Natural: skylights, clerestory, windows) .................................................. -
Special Considerations ........................................................................................................... -
LEED ....................................................................................................................................... -
Controls ................................................................................................................................... -
Security System ...................................................................................................................... -
11.0 Acoustics ..................................................................................................................... -
Active & Passive Strategies .................................................................................................... -
12.0 Food Services & Kitchen Design ............................................................................... -
13.0 Mechanized Circulation .............................................................................................. -
Elevators, escalators, moving walkways, etc. ........................................................................ -
14.0 Active Design .............................................................................................................. -
15.0 Flexibility and Futureproofing .................................................................................... -
16.0 Code Review ................................................................................................................ -
17.0 Budget/costing ............................................................................................................ -
18.0 Schedule ...................................................................................................................... -
19.0 Safety, Security & CPTED ........................................................................................... -
Exterior & Site Security Technical Description ...................................................................... -
Interior & Occupant Security Technical Description ............................................................. -
Miscellaneous Systems & Special Considerations ............................................................... -
Crime Prevention Through Environmental Design (CPTED) ................................................ -
20.0 Signage & Wayfinding ................................................................................................ -
Heraldry: naming, flagging, etc. ............................................................................................ -
Appendix ............................................................................................................................. -
6 July 2019
Design Development Drawing Expectations
Site Plan
Paving, hard landscaping elements, sidewalks, loading, and parking types (e.g. Barrier-Free,
electric vehicle, loading, etc.) indicated
Identify vehicular and pedestrian circulation and drop-off areas; identify strategies to mitigate
concerns with safety at areas of potential conflict (i.e., increased visibility/no parking areas,
signage, crosswalks, etc.)
Site accessories indicated (bike racks, garbage enclosures, signs, flag poles, etc.)
Provisions for firefighting access shown and dimensioned
Landscape design strategies (not only shown “as per bylaw”)
Grades and grading requirements outlined; establish geodetic elevation
Areas of future expansion
All service connection locations and sizes, gas meter and fire department connection locations
Roof Plan
Roof drainage plan/roof slopes/preliminary roof structure strategy indicated (sloped structure or
sloping insulation on flat roofs, other roof materials, access, slopes, etc.), rainwater collection
(gutters, drains, etc.)
Mechanical equipment, air intake, and exhaust locations
Proposed photovoltaic locations (if applicable)
Floor Plans
All floor plans required, with all rooms identified
Building Code Review completed – all exiting/life safety requirements shown, washroom count,
barrier-free requirements, fire protection requirements, etc. summarized in the report and
integrated into the design drawings
All windows and doors shown
7 July 2019
Area comparison to original program requirements, with explanation of variances (can be on
drawings/model or separately in report)
Moveable walls and/or operable partitions identified
STC ratings for critical spaces and operable walls (identify on drawings and/or in report)
Acoustical wall/ceiling treatment clearly identified with NRC value
Functional relationships integrated into design, with descriptions indicating areas of concern and
mitigation strategies (i.e., noise from adjacent areas, control points, multi-functional spaces, etc.
and the strategies/techniques used to reduce impact to adjacent areas)
Mechanical Plumbing plan - fixtures, floor drains, plumbing and drainage mains.
Fire Protection Plan: fire mains, zones and hazards.
Heating Plan: distribution system and layout of terminal units.
Cooling Plan: distribution system and layout of terminal units.
Ventilation Plan: single line distribution mains and layout of terminal units.
Mechanical Room Plan: equipment layout.
Mechanical Systems Schematics: domestic water, heating, cooling, and ventilation.
Building Sections and Typical Details
Structural, mechanical, and electrical systems determined with preliminary coordination of major
elements (i.e., type of structure, columns/loadbearing walls/cross-bracing coordinated, rooftop
units/mechanical rooms, crawlspaces, roof access, etc.)
Wall, roof, and floor assemblies determined and identified
Acoustical seal details where STC rated walls intersect the base building (exterior walls/windows,
underside of structure/ceiling, heating cabinets) to ensure flanking paths are sealed.
Areas of complex interior spaces (i.e., clerestories, open stairs, interconnected floor spaces)
and/or significant design features should be indicated in section.
Typical details shown (the lines of air barrier, thermal barrier, and moisture barrier graphically
represented and should be able to be “traced” and reviewed for intent) – need to be able to
identify the barriers through the details. Can be three-dimensional or two dimensional – as long
as components can be identified and “traced” for review.
Alberta Infrastructure Technical Requirements shall be incorporated into the drawings. Use of
PERSIST technique clearly shown on drawings.
Building Elevations All exterior elevations required
8 July 2019
All building heights indicated
Grade line clearly shown and identified
All exterior materials shown and identified
All window and doors shown and coordinated with the floor plans
Other penetrations and/or elements shown (louvres, shades, canopies, lighting, building signage,
etc.) if known
Building integrated photovoltaic locations (if applicable)
Other Elements
Three-dimensional Renderings (may be part of Drawing Set or included
in Report)
Building renderings showing materials and colours
Include light/shadow studies
Include acoustic modeling and site studies
Structural
1. General Notes:
o Detailed design criteria for the building
o Key geotechnical design parameters
o Material specifications in abridged form
2. Three Dimensional Renderings - minimum two (2) views from orthogonal directions
3. Typical Structural Details proposed for use in the building
4. Foundation Plan:
o Structural grid with labels and dimensions (applies to all plans and sections)
o Foundation layout including location of spread/strip footings, concrete/steel piles, screw
piles for modular units, grade beams, basement walls and inclined ramps in parkades
o Location of braced bays (LLRS / SFRS)
o Legend and schedules as appropriate
5. Floor Plans:
o Top of floor elevation
o Floor system including slab thickness
o Layout of beams, columns, vertical cores and braced bays
o Major openings in the floor slab
6. Legend and schedules as appropriate
7. Roof Plans:
9 July 2019
o Roof elevation
o Layout of roof framing including metal deck
o Roof slopes and drain locations
8. Building Sections:
o Major sections showing relevant conditions
o Sections showing peculiar geometry (canopies, clerestories, gymnasium)
o Elevation of each level and finished grade
Mechanical Information
Referenced Codes and Standards
Mechanical system detail descriptions
Energy analysis and modeling
System and equipment redundancies and connections to essential electrical system
Major equipment selections with capacities
Vibration and noise control
Energy Management Control System, communication protocol and any interface to subsystems
such as security, fire alarm and lighting
Preliminary plumbing fixtures selections (product data sheets)
Electrical Information
The anticipated electrical load and allowances for future expansion;
Requirements of incoming electrical services and any space requirements for a vault, sub-station,
or main electrical room
The distribution of power and utilization voltages;
Locations for electrical closets, communications rooms, bus-duct risers;
Requirements for embedding conduits;
Light fixture selection and requirements for ceiling systems and ceiling space;
Target illumination levels and power densities for all interior and exterior lit space;
Switching and controls for energy efficiency;
Telecommunications and data systems, fire alarm systems, public address systems, intercom,
security;
Determination of lightning protection system
Outline Specification (at minimum) included in Report