Technical Risk Table

download Technical Risk Table

of 3

Transcript of Technical Risk Table

  • 7/30/2019 Technical Risk Table

    1/3

    Sr.No. Major Activities Technical Risk Observed at Site Mitigation strategy Adopted/Suggested

    1 Exavation Safe bearing capacity of soil Minimum S.B.C. should be 45 tonnes / sqm

    (FOS = 1.5) or Chemical consolidation of soil

    Seepage of water from adjacent land Constructing Drains or Freezing process

    Shifting of service lines Shifting of service lines is Hudas responsibility

    Damage of water lines/sewage lines/electrical

    lines

    Damaged to service lines will be equally shared by

    contractor

    Settlement of foundation

    Load cells placed in foundation to check the

    settlement & to take suitable preventive measures

    Alignment problem because of temple &mosque.

    Its an Huda's responsibility

    2 Foundation Concreting Quality of materials, Site conditions, Mixing &

    Placing Methods

    Testing of materials, Concrete should be laid in

    layers not exceeding 15 cm in thikness

    3 Procurement Inventory of Mac alloy bar used for lifting

    operation. Cost Rs. 180/Kg

    ABC analysis for major items like Mac alloy bar

    which can be used for proper stock maintenance

    4 Profiling of tendon bars used

    for pre stressing

    Used for proper stress distribution. Risk of

    collapse of structure due to uneven stress

    distribution

    Check list should be prepared, followed by engineer

    inspection

    5 Alignment Change in alignment will cause risk of excessive

    cost & completion time of project

    Provide detail drawings with checking points

    &intermediate levels

    6 Crash Barriers Risk of crash barrier fall down due to improper

    tieing which may lead to accident

    Crash Barrier bars should be welded with the deck

    slab reinforcement

    7 Faulty design, material &

    workmanship

    Risk of bad quality, excessive cost &

    completion timeClause of liquidity damages & penalty will help to

    mitigate such risks

    Observed Technical Risks & its Mitigation Process in PVN Elevated Expressway

  • 7/30/2019 Technical Risk Table

    2/3

    8 Bearings Damages during installationRisk: Excessive cost & time

    Poor bedding & Inaccurate positions

    Risk: Improper load distribution

    9 Creep Creep increase the deflection with the time and

    may be critical consideration in design.

    Creep can cause to cracking to interior of

    surface lead to failure of elevated structure

    10 Shrinkage

    Risk of reduction in volume which may

    developed cracks at the surface

    Preventing the rapid loss of water from the surface.

    Thus it can be done by covering the surface with

    polyethylene sheeting.

    Affecting the strength of the structure

    Carbonation of concrete also results in increasing

    the strength of concrete and reduces permeability.

    Used expansive cement or shrinkage compensating

    cement

    11 Temperature variations Temperature variation may lead to deveopment

    of cracks in the structure

    Fixing of expansion joint to absorb expasion and

    contraction

    12 Live load and Dead load Live load and dead load lead to various type ofmovement in the elevated expressway.

    Provide damping of vibrations and minimize effectsof impact loading

    14 Equipment Risk

    Launching Girder Risk of derailing of launching girder

    Risk of tiliting of launching girder

    Risk of collapse of segment due to improper

    support

    Steel shims method: Bearing is correctlypositioned and leveled on steel shims and the

    remaining space filled with a grouting material.

    Proper mix design of concrete & use of lesser water

    cement ratio

    The 300 tonne launching girder can be stabilised by

    giving support to it. Barricade area & movement of

    people should be banned in case of emergency.

  • 7/30/2019 Technical Risk Table

    3/3