Technical Risk Table
Transcript of Technical Risk Table
-
7/30/2019 Technical Risk Table
1/3
Sr.No. Major Activities Technical Risk Observed at Site Mitigation strategy Adopted/Suggested
1 Exavation Safe bearing capacity of soil Minimum S.B.C. should be 45 tonnes / sqm
(FOS = 1.5) or Chemical consolidation of soil
Seepage of water from adjacent land Constructing Drains or Freezing process
Shifting of service lines Shifting of service lines is Hudas responsibility
Damage of water lines/sewage lines/electrical
lines
Damaged to service lines will be equally shared by
contractor
Settlement of foundation
Load cells placed in foundation to check the
settlement & to take suitable preventive measures
Alignment problem because of temple &mosque.
Its an Huda's responsibility
2 Foundation Concreting Quality of materials, Site conditions, Mixing &
Placing Methods
Testing of materials, Concrete should be laid in
layers not exceeding 15 cm in thikness
3 Procurement Inventory of Mac alloy bar used for lifting
operation. Cost Rs. 180/Kg
ABC analysis for major items like Mac alloy bar
which can be used for proper stock maintenance
4 Profiling of tendon bars used
for pre stressing
Used for proper stress distribution. Risk of
collapse of structure due to uneven stress
distribution
Check list should be prepared, followed by engineer
inspection
5 Alignment Change in alignment will cause risk of excessive
cost & completion time of project
Provide detail drawings with checking points
&intermediate levels
6 Crash Barriers Risk of crash barrier fall down due to improper
tieing which may lead to accident
Crash Barrier bars should be welded with the deck
slab reinforcement
7 Faulty design, material &
workmanship
Risk of bad quality, excessive cost &
completion timeClause of liquidity damages & penalty will help to
mitigate such risks
Observed Technical Risks & its Mitigation Process in PVN Elevated Expressway
-
7/30/2019 Technical Risk Table
2/3
8 Bearings Damages during installationRisk: Excessive cost & time
Poor bedding & Inaccurate positions
Risk: Improper load distribution
9 Creep Creep increase the deflection with the time and
may be critical consideration in design.
Creep can cause to cracking to interior of
surface lead to failure of elevated structure
10 Shrinkage
Risk of reduction in volume which may
developed cracks at the surface
Preventing the rapid loss of water from the surface.
Thus it can be done by covering the surface with
polyethylene sheeting.
Affecting the strength of the structure
Carbonation of concrete also results in increasing
the strength of concrete and reduces permeability.
Used expansive cement or shrinkage compensating
cement
11 Temperature variations Temperature variation may lead to deveopment
of cracks in the structure
Fixing of expansion joint to absorb expasion and
contraction
12 Live load and Dead load Live load and dead load lead to various type ofmovement in the elevated expressway.
Provide damping of vibrations and minimize effectsof impact loading
14 Equipment Risk
Launching Girder Risk of derailing of launching girder
Risk of tiliting of launching girder
Risk of collapse of segment due to improper
support
Steel shims method: Bearing is correctlypositioned and leveled on steel shims and the
remaining space filled with a grouting material.
Proper mix design of concrete & use of lesser water
cement ratio
The 300 tonne launching girder can be stabilised by
giving support to it. Barricade area & movement of
people should be banned in case of emergency.
-
7/30/2019 Technical Risk Table
3/3