Technical Monitoring Procedures
Transcript of Technical Monitoring Procedures
-
8/12/2019 Technical Monitoring Procedures
1/58
Monitoring ProceduresInformation for Teams
March 2012
-
8/12/2019 Technical Monitoring Procedures
2/58
SOLAR DECAHTLONEUROPE
Monitoring Procedures
Information for Teams
Monitoring Team Organization
Abstract
This document describes the monitoring procedures to be taken into account by every Team
in Solar Decahtlon Europe 2012.
1
-
8/12/2019 Technical Monitoring Procedures
3/58
SOLAR DECAHTLONEUROPE Contents
Contents
Contents 2
1 Introduction 3
2 Summary 3
3 Monitoring Architecture 5
4 Sensors 6
5 Monitoring 8
6 Scoring 11
7 Location and dimensions 20
8 Wiring 25
9 Monitoring Drawings 27
10 Instrumentation Plan and Approval 27
A Monitoring CheckList 29
B Monitoring Plans Examples 30
C Datasheets 35
C.1 Twido PLCdatasheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
C.2 TJ MONITORdatasheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
C.3 Domotax datasheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
C.4 STR100 datahseet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
C.5 SCR110-H datasheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
C.6 LLS datasheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
C.7 EN40P datasheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
2
-
8/12/2019 Technical Monitoring Procedures
4/58
Introduction SOLAR DECAHTLONEUROPE
1. Introduction
A significant part of the scoring of the competition consists on the measurement of different items
and the correct performance of several tasks. The Monitoring system is responsible for controlling
these measurements. This document describes, in an exhaustive way, the monitoring procedures
to be carried out by the Organization and the Teams. Moreover, this document has been designed
taking into account different factors, such as the conversations carried out in the October 2011
workshop, pros and cons found in previous Solar Decathlon editions and information obtained
from Teams by private conversations, SDE WAT, deliverables, etc.
Due to the aforementioned factors, some important constraints have been decided by the
Organization with the sole purpose of implementing a robust monitoring system that plays on
the benefit of the Teams and the Organization. The most important modification is related
to the monitoring datalogger location (monitoring panel from now on). The Organization has
decided that Teams must provide enough space to locate the monitoring panel inside the house
(see Section 7 for detailed information). This fact together with some minor modifications will
increase robustness in the system and the Organization expects that Teams agree on the monitoring
description improvement. Moreover, in order to achieve a correct Monitoring Plan and Approval
(see Section 10), a Monitoring Procedures Checklist has been designed and it is presented in
Appendix A. Finally, the number of drawings related to the monitoring procedures has been
increased and they are explained in Section9 and examples are presented in AppendixB.
In case that minor adjustments or modifications to this document are made, they will be
notified and updated through the SDE WAT. Nonetheless, the SDE 2012 Organization will be
accessible to clarify any procedure with the Teams at any time.
2. Summary
This section provides a summary of the present document where the sensors brand and model,
their locations, the variables to be monitored and the acquisition and scored period1are presented.
Table1 gives an overview of the complete monitoring system, although an exhaustive description
is presented in the rest of the document.
1Within the scored period defined in SDE 2012 Rules
3
-
8/12/2019 Technical Monitoring Procedures
5/58
SOLAR DECAHTLONEUROPE Summary
Contest
Brand
Model
Location
Acquisitiontime
Scoringtime
Variables
4.
ElectricalEnergyBalance
Orbis
Domotax
Monit
oringPanel
Everyminute
Endofcompetition
EG,EL,EB
5.1Temperature
Schneid
erElectric
SCR110-H
Living
Room
Everyminute
Every15minutes1
Troom1
Schneid
erElectric
STR100
Bedro
om
Everyminute
Every15minutes1
Troom2
5.2Humidity
Schneid
erElectric
SCR110-H
Living
Room
Everyminute
Every15minutes1
Hroom1
5.3AirQuality
Schneid
erElectric
SCR110-H
Living
Room
Everyminute
Every15minutes1
Qroom1
5.4WorkstationLighting
Trend
LLS
Workstationtable
Everyminute
Endofperiods
Lwork
5.5AcousticPerformance
Tobed
efined
Laboratory
Tobe
defined
Onceincompetition
Onceincompetition
Dhouse
6.1Refrigerator
Tobed
efined
Thermocouple
Refrig
erator
Everyminute
Every15minutes
Tfridge
6.2Freezer
Tobed
efined
Thermocouple
Freeze
r
Everyminute
Every15minutes
Tfreezer
6.3ClothesWasher
Tobed
efined
Thermocouple
WashingMachine
Everyminute
Everytask
TWM
6.4ClothesDryer
Tobed
efined
Scale
Tobe
defined
Endofperiods
Everytask
Wdryer
6.5Dishwasher
Tobed
efined
Thermocouple
Dishw
asher
Everyminute
Everytask
TDW
6.6HomeElectronics
Schneid
erElectric
EN40P
Electr
icBox
Everyminute
Endofperiods
EHE
6.7Oven
Tobed
efined
Thermocouple
Oven
Everyminute
Everytask
Toven
6.8Cooking
Tobed
efined
Scale
Tobe
defined
Endofperiods
Everytask
Wcook
6.9HotWaterDraws
Tobed
efined
Thermocouple
Tobe
defined
Endofperiods
Everytask
Thw
Table1:MonitoringPro
ceduresDocumentsummary
4
-
8/12/2019 Technical Monitoring Procedures
6/58
Monitoring Architecture SOLAR DECAHTLONEUROPE
3. Monitoring Architecture
This section provides an schematic view of the monitoring devices to be installed in every house
in the SDE 2012 competition. The monitoring architecture for the Villa Solar is presented in
Figure 1. Two different power lines will be connected to each house: the first one will connect
the house to the grid while the second one will be used to power the monitoring devices, whose
consumption is not taken into account in the energy related contests. Moreover, three different
Ethernet lines will be connected to the house. The first one will be used by the Teams, while the
other two will be used by the monitoring system.
Figure 1: Monitoring architecture for the Villa Solar.
Every team should provide detailed information about the wiring procedures in order to allow
the power and data lines arrive correctly to their houses (see Section 8 and Section10).
The monitoring architecture for every house is based on two main elements:
Twido PLC: An industrial Twido PLC with extension boards from Schneider-Electric 2
(see AppendixC.1).
TJ MONITOR : An ad-hoc designed board based on the SAM9G20 module from RBZ
Robot Design 3 (see AppendixC.2).
TJ MONITORwill be in charge of acquiring the electricity meters variables related to Contest
4. On the other hand, the Twido PLCwill be in charge of getting all the automated monitoring
variables related to Contest 5 and Contest 6. Moreover, TJ MONITORwill retrieve the informa-
tion from the Twido PLCand send all measurements (i.e. its own acquired data and the data
provided by the PLC) to the monitoring server. The monitoring architecture for one house is de-
picted in Figure2. Notice that both TJ MONITORand Twido PLCwill have their own Ethernet
connection.
Variables not acquired by the automated monitoring system will be obtained and sent to the
monitoring server by observers (see Figure2).
2
http://www.schneider-electric.com3http://www.rbz.es
5
http://www.schneider-electric.com/http://www.rbz.es/http://www.rbz.es/http://www.schneider-electric.com/ -
8/12/2019 Technical Monitoring Procedures
7/58
SOLAR DECAHTLONEUROPE Sensors
TJ MONITOR
TWIDO PLC Air Quality
Temperature
Humidity
ElectronicsHome
Oven
Lighting
RefrigeratorMachineWashing
Freezer Dishwasher
PVMeter Meter
LOADsMeter
BATTERY
MONITORING
SERVER
Acoustic
Hot Water
Cook
Dryer
Ethernet 1
Ethernet 2
Power
Data Acquisitionover Ethernet
RS485 RS485 RS485
OBSERVERS
Figure 2: Monitoring architecture for a house.
4. Sensors
In this section, the sensors used to monitor the different contests are described. A summary of
these sensors have been shown in Section 2.
Contest 4: Electrical Energy Balance. This contest will be scored based on the mea-surements obtained from two or three AC electricity meters installed in each house 4. The
meters selected are the single phase multi-function energy and tariffDomotaxmeters from
ORBIS 5 (see AppendixC.3 6). Notice that these meters (and their configuration) are based
on typical photovoltaic configurations discussed in the last workshop (see Figure3). Special
configurations will be discussed individually with each team.
Sub-Contest 5.1: Temperature. This contest will be scored based on the measurements
obtained from two NTC sensors. One sensor will be located in the main room while the
second will be located in a secondary room. The NTC sensor located in the secondary room
is theSTR100sensor fromSchneider Electric7(see AppendixC.4). The NTC sensor located
in the main room is the SCR110-H sensor from Schneider Electric7, which integrates ahumidity, a CO2 and a temperature sensor (see Appendix C.5).
Sub-Contest 5.2: Humidity. This contest will be scored based on the measurements
obtained from a thin-film capacitive sensor located in the main room. The sensor to be used
is theSCR110-Hsensor from Schneider Electric7, which integrates a humidity, a CO2 and
a temperature sensor (see AppendixC.5).
4See Section5 to check the use of two or three electricity meters.5http://www.orbis.es6
Datasheet in English is found in http://www.orbis.es/ficha.aspx?id=1097http://www.schneider-electric.com
6
http://www.orbis.es/http://www.orbis.es/ficha.aspx?id=109http://www.schneider-electric.com/http://www.schneider-electric.com/http://www.orbis.es/ficha.aspx?id=109http://www.orbis.es/ -
8/12/2019 Technical Monitoring Procedures
8/58
Sensors SOLAR DECAHTLONEUROPE
(a)
(b)
Figure 3: Standard photovoltaic configurations (a) with and (b) without electrical storage.
Sub-Contest 5.3: Air quality. This contest will be scored based on the measurements
obtained from a non-dispersive infrared sensor located in the main room. The sensor to be
used is theSCR110-Hsensor fromSchneider Electric7, which integrates a humidity, a CO2and a temperature sensor (see AppendixC.5).
Sub-Contest 5.4: Workstation Lighting. This contest will be scored based on the
measurements obtained from a light level sensor. The sensor to be used is the LLS sensor
from Trend 8 (see AppendixC.6).
Sub-Contest 5.5: Acoustic performance. This contest will be scored based on the
8https://www.trendcontrols.com
7
https://www.trendcontrols.com/https://www.trendcontrols.com/ -
8/12/2019 Technical Monitoring Procedures
9/58
SOLAR DECAHTLONEUROPE Monitoring
measurements obtained according to the ISO 140-5:1998. This measurement will be carried
out once during the competition by a specific acoustic laboratory.
Sub-Contest 6.1: Refrigerator. This contest will be scored based on the measurements
obtained from a type K or Tthermocouple(75Cto +250C). The sensor will be located
inside the refrigerator.
Sub-Contest 6.2: Freezer. This contest will be scored based on the measurements ob-
tained from a type K or T thermocouple(75Cto +250C). The sensor will be located
inside the freezer.
Sub-Contest 6.3: Clothes Washer. This contest will be scored based on the measure-
ments obtained from a type K or T thermocouple (75C to +250C). The sensor will
be located inside the washing machine.
Sub-Contest 6.4: Clothes Dryer. This contest will be scored based on the measurementsobtained from a precision scale. The scale to be used will have a resolution of grams.
Sub-Contest 6.5: Dishwasher. This contest will be scored based on the measurements
obtained from a type K or Tthermocouple(75Cto +250C). The sensor will be located
inside the dishwasher.
Sub-Contest 6.6: Home Electronics. This contest will be scored based on the mea-
surements obtained from an electricity meter attached to the home electronics power line.
The meter to be used is the EN40Pfrom Schneider Electric7 with a 10 Wh resolution (see
AppendixC.7).
Sub-Contest 6.7: Oven. This contest will be scored based on the measurements obtainedfrom a type K or T thermocouple(75Cto +250C). The sensor will be located inside
the oven.
Sub-Contest 6.8: Cooking. This contest will be scored based on the ratings assigned
by the observers at the time of cooking. Therefore, no specific sensor will be used in this
sub-contest.
Sub-Contest 6.9: Hot water draws: This contest will be scored based on the measure-
ments obtained from a type K or T thermocouple(75Cto +250C).
5. Monitoring
Most of the variables to be monitored will be acquired every minute. However, in some cases
the measurements will be averaged (see Section6). In what follows, the monitoring procedures to
be carried out by the Organization are presented for each contest. Notice that this information is
only related to the monitoring process, while the scoring process is presented in Section 6.
Contest 4: Electrical Energy Balance. Three Sub-Contests are included in Contest 4:
Sub-Contest 4.1: Electricity Autonomy.
Sub-Contest 4.2: Temporary Generation-Consumption Correlation.
Sub-Contest 4.3: Load Consumption per Measurable Area.
8
-
8/12/2019 Technical Monitoring Procedures
10/58
Monitoring SOLAR DECAHTLONEUROPE
All the information needed for the three sub-contest is obtained from the electricity meters
(see Section4). As aforementioned, the number of electricity meters to be installed depends
on each house configuration. Houses with a hard-wired battery bank, configured as Figure3a,will have three electricity meters (PV, Loads and Bat) and houses without it only two (PV
and Loads). The meter in charge of measuring the energy imported or exported to the
batteries will be a bidirectional meter, while the other two will be unidirectional meters.
Therefore, the monitoring system will get a total of 4 variables:
Energy generated by the PV system (EG).
Energy consumed by the Loads (EL).
Energy imported to the batteries (EBin optional).
Energy exported from the batteries (EBout optional)
These variables will be acquired every minuteby TJ MONITOR, regardless of the scored
period, and uploaded to the monitoring server to calculate the sub-contests scoring (see
Section6). Moreover, power variables (PG, PL and PB) associated to the energy variables
will be shown in the monitoring web site.
Remember that batteries can only be charged with PV energy during the shadows free
period. The SDE Organization will handle the measurements in order to subtract the energy
that enters from the grid to the batteries. Notice that special topologies will be treated
individually and special actions can be implemented in order to allow equanimity between
the Teams.
Sub-Contest 5.1: Temperature. The monitoring system will get a total of 2 variables
for this sub-contest:
Temperature in the main room (Troom1).
Temperature in the secondary bedroom (Troom2).
Sub-Contest 5.2: Humidity. The monitoring system will get one variable for this sub-
contest:
Humidity in the main room (Hroom1).
Sub-Contest 5.3: Air quality. The monitoring system will get one variable for this
sub-contest:
Indoor air quality in the main room (Qroom1).
Sub-Contest 5.4: Workstation Lighting. The monitoring system will get one variable
for this sub-contest:
Workstation lighting (Lwork).
Sub-Contest 5.5: Acoustic p erformance.
This sub-contest will not be connected to the automatic monitoring system and will be
evaluated only once during the SDE 2012 competition. An acoustic laboratory will carry
out the measurement and obtain the following variables:
Sound insulation (Dhouse).
9
-
8/12/2019 Technical Monitoring Procedures
11/58
SOLAR DECAHTLONEUROPE Monitoring
Due to the final configuration of the house and all the Villa Solar components, the Orga-
nization will decide on-site, during Contest Week, the facade that will be evaluated for the
measurement.
Sub-Contest 6.1: Refrigerator. The monitoring system will get one variable for this
sub-contest:
Refrigerator temperature (Tfridge).
Sub-Contest 6.2: Freezer. The monitoring system will get one variable for this sub-
contest:
Freezer temperature (Tfreezer).
Sub-Contest 6.3: Clothes Washer. The monitoring system will get one variable for this
sub-contest: Washing machine temperature (TW M).
Teams must call the observer, before starting the task, to check everything is ready for its
accomplishment and to annotate the time at which the task starts and ends.
Sub-Contest 6.4: Clothes Dryer. This sub-contest will not be connected to the auto-
matic monitoring system. An observer from the Organization will carry out the measurement
and obtain the following variables:
Towels total weight before washing (Wi).
Towels total weight after drying (Wo).
Sub-Contest 6.5: Dishwasher. The monitoring system will get one variable for this
sub-contest:
Dishwasher temperature (TDW).
Teams must call the observer, before starting the task, to check everything is ready for its
accomplishment and to annotate the time at which the task starts and ends.
Sub-Contest 6.6: Home Electronics. The monitoring system will get one variable for
this sub-contest:
Home electronics consumption (EHE ).
Sub-Contest 6.7: Oven. The monitoring system will get one variable for this sub-contest:
Oven temperature (Toven).
Teams must call the observer, before starting the task, to check everything is ready for its
accomplishment and to annotate the time at which the task starts and ends.
Sub-Contest 6.8: Cooking. This sub-contest will not be connected to the automatic
monitoring system. An observer from the Organization will carry out the measurement and
obtain the following variables:
Pot weight before starting the task (Wi).
Pot weight once the task is considered completed (Wo).
10
-
8/12/2019 Technical Monitoring Procedures
12/58
Scoring SOLAR DECAHTLONEUROPE
Sub-Contest 6.9: Hot water draws: This sub-contest will not be attached to the auto-
matic monitoring system. An observer from the Organization will carry out the measurement
and obtain the following variable: Water temperature (Thw).
6. Scoring
As aforementioned, the monitoring scoring depends on the scored periods defined in the SDE
2012 Competition Calendar. Therefore, the information presented in this section is related to the
current version of the SDE 2012 Rules. Any change done to the calendar may modify some of the
information provided in this section.
In what follows we present information about the monitoring scoring for every sub-contest
based on the last existing version of the Rules, SDE 2012 Rules.
Sub-Contest 4.1: Electricity Autonomy.
Figure 4: Contest 4.1 point distribution.
This sub-contest evaluates the electrical energy balance of the competition; hence two dif-
ferent variables are used:
Energy generated by the PV system (EG).
Energy consumed by the Loads (EL).
Moreover, to be equanimous with all Teams, EG will be truncated. EG is the truncatedenergy generated by the PV system (generation period being the one in which all houses arefree of shadows). Therefore, this sub-contest will be evaluated according to the following
equation: EG EL (1)Notice that the shadows free period has been established as the time interval between 10:00
and 16:00 in SDE 2012 Rules 9. If this period is modified, the variable truncation will be
adjusted to it.
Equation1will be calculated every minute, usingEG and EL as the energy generatedand consumed from the beginning of the competition. However, only its final value (i.e. at
the end of the competition) will provide Sub-Contest 4.1 scoring.
9Notice that energy consumption (EL) will not be truncated.
11
-
8/12/2019 Technical Monitoring Procedures
13/58
SOLAR DECAHTLONEUROPE Scoring
Figure4 shows point distribution according to SDE 2012 Rules.
Sub-Contest 4.2: Temporary Generation-Consumption Correlation.
All electric variables are used in this sub-contest.
EGL is calculated as the electricity generated and simultaneously consumed by the loadswithin the predefined scored period (i.e. 10:00-16:00, defined in SDE 2012 Rules).
Moreover, in the case that a house embodies a hard-wired battery bank,EBLis calculatedas the electricity exported from the batteries to the loads within the predefined scored period
(i.e. 10:00-16:00, defined in SDE 2012 Rules) 10.
Finally, the temporary generation-consumption correlation is calculated as follows:
=EGL+EBL
EL
(2)
whereEL is the energy consumed by the loads truncated to the predefined scored period(i.e. 10:00-16:00, defined in SDE 2012 Rules) andEBL = 0 if there is not hard-wiredbattery bank.
Equation 2 will be calculated every minute, using theEGL,EBL andEL valuesfrom the beginning of the competition. However, only itsfinal value(i.e. at the end of the
competition) will provide Sub-Contest 4.2 scoring.
Sub-Contest 4.3: Load Consumption per Measurable Area.
Only the EL electric variable will be used in this sub-contest.
To accomplish the sub-contest requirements,EL value is calculated as the daily average ofthe electrical loads consumption during the competition. This average takes into account
a complete day period (i.e. 24h) for every day during the contest. For each house (i), the
load consumption per measurable area is calculated as:
EiLS=EiLAi
(3)
where Ai represents the measurable area of house i.
Figure 5: Contest 4.3 point distribution.
10
Remember that the energy stored in the batteries can only come from the house PV sources during the shadowsfree period.
12
-
8/12/2019 Technical Monitoring Procedures
14/58
Scoring SOLAR DECAHTLONEUROPE
Finally, the scoring distribution will be normalized to the minimum consumption performed
by all Teams as:
Ei
LS=EiLSELSmin (4)
whereELSmin =min{ EiLS}; iEquation4 will becalculated only once, at the end of the competition.
Figure5 shows point distribution according to SDE 2012 Rules.
Sub-Contest 5.1: Temperature.
Figure 6: Contest 5.1 point distribution.
Both temperature variables (Troom1 and Troom2) will be truncated to the scored time
periods provided inSDE 2012 Rules(Troom1 andTroom2). Moreover, the truncated valueswill be averaged in intervals of15 minutes( Troom1 andTroom2).Finally, the monitoring system will score Sub-Contest 5.1 according to the worst temperature
reading (S5.1):
S5.1= minS( Troom1),S( Troom2)
(5)
where S() is the temperature scoring based on Figure 6 points distribution according to
SDE 2012 Rules.
The competition scored period will be divided in 15 minutes intervals(N15). Total points
available (pT) will be divided in N15 intervals. Equation 5 will be calculated every 15
minutes, and pTN15
points will be assigned according to the sub-contest points distribution.
13
-
8/12/2019 Technical Monitoring Procedures
15/58
SOLAR DECAHTLONEUROPE Scoring
Sub-Contest 5.2: Humidity.
Figure 7: Contest 5.2 point distribution.
Humidity values will be truncated to the predefined scored p eriod in SDE 2012 Rules
(Hroom1), and averaged every 15 minutes(Hroom1).The competition scored period will be divided in 15 minutes intervals (N15). Total
points available (pT) will be divided in N15 intervals.Hroom1 will becalculatedevery15minutes, and pT
N15points will be assigned according to the sub-contest points distribution.
Figure7 shows point distribution according to SDE 2012 Rules.
Sub-Contest 5.3: Air quality.
Figure 8: Contest 5.3 point distribution.
Air quality values will be truncated to the predefined scored period in SDE 2012 Rules
(Qroom1), and averaged every 15 minutes( Qroom1).The competition scored period will be divided in 15 minutes intervals (N15). Total
points available (pT) will be divided in N15 intervals.Qroom1 will becalculatedevery15minutes, and pT
N15points will be assigned according to the sub-contest points distribution.
Figure8 shows point distribution according to SDE 2012 Rules.
14
-
8/12/2019 Technical Monitoring Procedures
16/58
Scoring SOLAR DECAHTLONEUROPE
Sub-Contest 5.4: Workstation Lighting.
Figure 9: Contest 5.4 point distribution.
For every scored period (tSp), defined inSDE 2012 Rules, the minimum workstation lighting
value will be calculated:
Lperiod= min{Lwork(t)} ; t tSp (6)
Total points available (pT) will be divided in Np intervals of tSp . Equation 6 will be
calculated every tSp and pT
Nppoints will be assigned according to the sub-contest points
distribution.
Figure9 shows point distribution according to SDE 2012 Rules.
Sub-Contest 5.5: Acoustic p erformance.
Figure 10: Contest 5.5 point distribution.
The sub-contest scoring will be manually assigned to the sole measurement carried out in
this contest on Dhouseand the points distribution, according to SDE 2012 Rules, shown in
Figure10.
15
-
8/12/2019 Technical Monitoring Procedures
17/58
SOLAR DECAHTLONEUROPE Scoring
Sub-Contest 6.1: Refrigerator.
Figure 11: Contest 6.1 point distribution.
This sub-contest will be continuously evaluated. Tfridgewill be averaged every15 minutes
( Tfridge).The competition scored period will be divided in 15 minutes intervals (N15). Total
points available (pT) will be divided in N15 intervals.Tfridgewill be calculated every15minutes, and pT
N15points will be assigned according to the sub-contest points distribution.
Figure11 shows point distribution according to SDE 2012 Rules.
Sub-Contest 6.2: Freezer.
Figure 12: Contest 6.2 point distribution.
This sub-contest will be continuously evaluated.Tfreezerwill be averaged every 15 minutes
( Tfreezer).The competition scored period will be divided in 15 minutes intervals (N15). Total
points available (pT) will be divided in N15 intervals.Tfreezerwill becalculatedevery15minutes, and pT
N15points will be assigned according to the sub-contest points distribution.
Figure12 shows point distribution according to SDE 2012 Rules.
16
-
8/12/2019 Technical Monitoring Procedures
18/58
Scoring SOLAR DECAHTLONEUROPE
Sub-Contest 6.3: Clothes Washer.
Figure 13: Contest 6.3 point distribution.
For every scored period (tSp), defined in SDE 2012 Rules, the maximum washing machine
temperature value will be calculated:
Tperiod= max{TW M(t)} ; t tSp (7)
Total points available (pT) will be divided in Np intervals of tSp . Equation 7 will be
calculated every tSp and pT
Nppoints will be assigned according to the sub-contest points
distribution.
Figure13 shows point distribution according to SDE 2012 Rules.
Sub-Contest 6.4: Clothes Dryer.
Figure 14: Contest 6.4 point distribution.
The sub-contest scoring will be manually assigned for every task achievement. An observer
will insert Wi and Wo to the monitoring system, which will calculate the towels relative
weight as:
Wdryer =Wo
Wi100 (8)
Total points available (pT) will be divided in Np intervals of tSp . Equation 8 will be
calculated every tSp
and pTNp
points will be assigned according to the sub-contest points
distribution shown in Figure14.
17
-
8/12/2019 Technical Monitoring Procedures
19/58
SOLAR DECAHTLONEUROPE Scoring
Sub-Contest 6.5: Dishwasher.
Figure 15: Contest 6.5 point distribution.
For every scored period (tSp), defined in SDE 2012 Rules, the maximum dishwasher tem-
perature value will be calculated:
Tperiod= max{TDW(t)} ; t tSp (9)
Total points available (pT) will be divided in Np intervals of tSp . Equation 9 will be
calculated every tSp and pT
Nppoints will be assigned according to the sub-contest points
distribution.
Figure15 shows point distribution according to SDE 2012 Rules.
Sub-Contest 6.6: Home Electronics. During the assembly period, the energy consumedby the home electronics line (EHE o) will be measured during a 30 minute period (To).
EHE will be calculated for every scored period (tSp) defined in SDE 2012 Rules.
Total points available (pT) will be divided in Np intervals oftSp . pT
Nppoints will be assigned
to every scored period if
EHE 0.9EHE otSp
To(10)
Sub-Contest 6.7: Oven.
Figure 16: Contest 6.7 point distribution.
For every scored period (tSp) defined inSDE 2012 Rules, the oven will be turned on duringa maximum period of 1 hour (Ton). Within this time, the oven must keep a temperature of
18
-
8/12/2019 Technical Monitoring Procedures
20/58
Scoring SOLAR DECAHTLONEUROPE
220 C during at least 45 minutes to get all the available points. An observer will check the
oven power on and off. At the end of the scored period the system will calculate the points
obtained.Total points available (pT) will be divided in Np intervals oftSp . Points will becalculated
every scored period and pTNp
points will be assigned according to the sub-contest points
distribution.
Figure16 shows point distribution according to SDE 2012 Rules.
Sub-Contest 6.8: Cooking.
Figure 17: Contest 6.8 point distribution.
The sub-contest scoring will be manually assigned for every task achievement. An observer
will insert Wi and Wo to the monitoring system, which will calculate the vaporized water
weight as:
Wcook= WoWi (11)
Total points available (pT) will be divided in Np intervals of tSp . Equation 11 will be
calculated every tSp and pT
Nppoints will be assigned according to the sub-contest points
distribution shown in Figure17.
Sub-Contest 6.9: Hot water draws:
Figure 18: Contest 6.9 point distribution.
The sub-contest scoring will be manually assigned for every task achievement. An observer
will insert Thw to the monitoring system. Total points available (pT) will be divided in
Np
intervals of tSp
. Scoring will becalculated every tSp
and pTNp
points will be assigned
according to the sub-contest points distribution shown in Figure18.
19
-
8/12/2019 Technical Monitoring Procedures
21/58
SOLAR DECAHTLONEUROPE Location and dimensions
7. Location and dimensions
In this section we provide information about the monitoring system dimensions and the needs for
space and location. Firstly we explain the monitoring panel constraints, the need for space and
location and its dimensions. After the monitoring panel description, the different sub-contests
needs are explained.
Monitoring panel. The monitoring system core will be placed in a 65 cm (height) x
45 cm (width) x 15 cm (depth)panel. This monitoring panel will hold the Twido PLC
and TJ MONITOR together with the AC electricity meters, power supplies and terminal
blocks needed for its correct working. Teams must provide the wall, to which the monitoring
panel will be attached, with two spikes of 0.5 mm. maximum at 3 cm length and 3 cm width
from the left and right top corners with the capacity of holding the weight of the monitoring
panel (i.e. 6 Kg).
Figure19shows a picture of the monitoring panel 11. The first line shows an electric circuit
breaker, the power supplies and the TJ MONITOR . In the second line the Twido PLC
and extension boards are located together with some terminal blocks which simplify the
structured wiring. Finally, at the bottom of the panel, the three AC electricity meters are
located. Remember, special photovoltaic topologies will be handled individually.
Figure 19: Monitoring system core over the 65 cm (height) x 45 cm (width) x 15 cm (depth) panel.
11Notice that small modifications can arise in the final panel design.
20
-
8/12/2019 Technical Monitoring Procedures
22/58
Location and dimensions SOLAR DECAHTLONEUROPE
All the sensors defined in Section 4 will be wired to this monitoring panel (see Section 8 for
the monitoring wiring requirements).
For the seek of simplicity and robustness during the assembly period and competition, it ismandatory that all Teams provide a free space for the inclusion of the monitoring panel. The
location of the monitoring panel is preferred to be near the inverters (i.e. inverters room), so
it will simplify the connection to the electricity meters and avoid monitoring errors. Notice
that the panel location as well as the sensors location will be discussed between each team
and the SDE 2012 Organization and must be validated by the Organization. No team will
be monitored if the monitoring has not been validated.
In order to prepare the monitoring panel room, it is important to understand how the
different connections will be made between the panel and the exterior.
Figure 20: Schema of the connections to be made to the monitoring panel.
Monitoring power line: As aforementioned (see Section3), the monitoring system
will have its own independent power line. This line will be connected by means of
a 3x6mm2 section cable entering to the left-top corner of the monitoring panel (see
Figure20).
Monitoring Ethernet lines: As aforementioned (see Section3), two different Ether-
net lines will be wired from the left side of the monitoring panel (see Figure20).
Home electronics meter: The two wires coming from the home electronics meterwill connect to the left side of the monitoring panel (see Figure 20). Notice, that as
21
-
8/12/2019 Technical Monitoring Procedures
23/58
SOLAR DECAHTLONEUROPE Location and dimensions
already stated in SDE 2012 Rules, the home electronics meter will be located in the
house electricity panel where a 7 cm free space should be left for its inclusion in the
DIN rail close to the home electronics independent line. Energy readings: The cables for the PV, Batteries and Load system will connect to
the bottom side of the monitoring panel (see Figure 20).
Sensors: The rest of the sensors will connect to the right side of the monitoring panel
to the Twido PLC (see Figure20).
Contest 4: Electrical Energy Balance. The AC electricity meters will be located in
the monitoring panel. Therefore, no other special requirements are needed for standard
topologies. Special topologies and their requirements will be handled individually with
Teams.
(a) (b)
(c) (d)
Figure 21: (a,b) Temperature, (c) air quality and (d) light sensors location. Sensors on the figure
may not correspond to the finally selected sensors (see Section 4).
Sub-Contest 5.1: Temperature. Temperature sensors must be placed in the location
agreed between the Teams and the Organization over a tripod (see Figure 21a,b). The
tripod must be in the placement agreed during all the scored periods.
Sub-Contest 5.2: Humidity. Humidity sensor must be placed in the location agreed
between the Teams and the Organization over a tripod (see Figure21b). The tripod must
be in the placement agreed during all the scored periods.
Sub-Contest 5.3: Air quality. Air quality sensor must be placed in the location agreed
22
-
8/12/2019 Technical Monitoring Procedures
24/58
Location and dimensions SOLAR DECAHTLONEUROPE
between the Teams and the Organization over a tripod (see Figure 21c). The tripod must
be in the placement agreed during all the scored periods.
Sub-Contest 5.4: Workstation Lighting. Light sensor must be placed in the location
agreed between the Teams and the Organization over a tripod (see Figure 21d). The tripod
must be in the placement agreed during all the scored periods.
Sub-Contest 5.5: Acoustic performance. No reserved locations are needed for this
sub-contest.
Sub-Contest 6.1: Refrigerator. Fridge thermocouple must be located inside the refrig-
erator during all the SDE 2012 competition (see Figure 22a).
Sub-Contest 6.2: Freezer. Freezer thermocouple must be located inside the freezer during
all the SDE 2012 competition (see Figure22b).
Sub-Contest 6.3: Clothes Washer. Clothes washer thermocouple must be located inside
the washing machine during all the SDE 2012 competition (see Figure 22c).
Sub-Contest 6.4: Clothes Dryer. No reserved locations are needed for this sub-contest.
Sub-Contest 6.5: Dishwasher. Dishwasher thermocouple must be located inside the
washing machine during all the SDE 2012 competition (see Figure22d).
Sub-Contest 6.6: Home Electronics. A minimum of a 7 cm DIN rail space is need to
be left in the Teams electrical box (see Figure22e).
Sub-Contest 6.7: Oven. Oven thermocouple must be located inside the washing machine
during all the SDE 2012 competition (see Figure22f).
Sub-Contest 6.8: Cooking. No reserved locations are needed for this sub-contest.
Sub-Contest 6.9: Hot water draws: No reserved locations are needed for this sub-contest.
23
-
8/12/2019 Technical Monitoring Procedures
25/58
SOLAR DECAHTLONEUROPE Location and dimensions
(a) (b)
(c) (d)
(e) (f)
Figure 22: (a) Fridge, (b) freezer, (c) washing machine, (d) dishwasher, (e) home electronics and
(f) oven sensors location. Sensors on the figure may not correspond to the finally selected sensors
(see Section4).
24
-
8/12/2019 Technical Monitoring Procedures
26/58
Wiring SOLAR DECAHTLONEUROPE
8. Wiring
For a correct success of the monitorization during the competition, it is necessary that a correct
wiring is designed. An exhaustive revision during the assembly period and a coordination between
the Teams and the SDE 2012 Organization are required in order to schedule the monitoring
installations. In this section, we provide information about how the sensors wiring should be
carried out.
As a preamble, notice the importance of having all the wires protected to the maximum to
prevent possible failures during the public tours or typical house activities. Therefore, this section
aims at clarifying the mandatory wiring protections.
Power connection: All Teams must provide a 3x2.5 mm2 entrance for the monitoring
power line to the place where the monitoring panel is located. Contrary to the connection
between the house and the grid, the SDE 2012 Organization will provide the wires.
Network connection: All Teams must provide an entrance to the place where the moni-
toring panel is located to allow the connection of the two monitoring Ethernet cables to the
monitoring system. The SDE 2012 Organization will provide those wires.
Contest 4: Electrical Energy Balance. As already stated in Section 4 two or three
AC electricity meters will be used for this contest. In order to have a correct wiring that
connects the PV, Batteries and Loads lines to the meters, it is mandatory that all Teams
provide electrical terminal blocks in which the Teams will connect the different lines to be
monitored, and the Monitoring Team will connect the wires from the electrical terminal
blocks to the meters. These electrical terminal blocks must allow the connection of wires
with 6mm2
-16mm2
section.It is important to secure all lines with electrical protections, so the Monitoring Team is able
to manipulate the electricity meters safely. Terminal blocks and protections should not be
further than 50 cm from the monitoring panel.
Figure23 shows a diagram about the requirements for the meters connection in a typical
AC bus architecture. Special designs will be discussed individually with the Teams.
Sub-Contest 5.1: Temperature. Teams must provide a routing from the room, where the
monitoring panel is located, to the nearest place where the sensor will be placed. Teams, that
have a dedicated closet to keep the tripod which holds the temperature sensors during the
intervals in which they are not getting data, should provide the routing from the monitoring
panel room to the closet. In the case of the secondary room, the routing must have at leasta 20mm2 section. The routing to the primary room must have at least a 25 mm2 section.
Sub-Contest 5.2: Humidity. Teams must provide a routing from the room, where the
monitoring panel is located, to the nearest place where the sensor will be placed. Teams,
that have a dedicated closet to keep the tripod which holds the humidity sensor during the
intervals in which it is not getting data, should provide the routing from the monitoring
panel room to the closet. The routing to the primary room must have at least a 25 mm2
section.
Sub-Contest 5.3: Air quality. Teams must provide a routing from the room, where the
monitoring panel is located, to the nearest place where the sensor will be placed. Teams,
that have a dedicated closet to keep the tripod which holds the air quality sensor duringthe intervals in which it is not getting data, should provide the routing from the monitoring
25
-
8/12/2019 Technical Monitoring Procedures
27/58
SOLAR DECAHTLONEUROPE Wiring
Figure 23: Wiring connection to the AC electricity meters.
panel room to the closet. The routing to the primary room must have at least a 25 mm2
section.
Sub-Contest 5.4: Workstation Lighting. Teams must provide a routing from the room,where the monitoring panel is located, to the nearest place where the sensor will be placed.
Teams, that have a dedicated closet to keep the light sensor during the intervals in which
it is not getting data, should provide the routing from the monitoring panel room to the
closet. The routing to the primary room must have at least a 20 mm2 section.
Sub-Contest 5.5: Acoustic performance. No special wiring is needed for this sub-
contest.
Sub-Contest 6.1: Refrigerator. Teams must provide a routing from the monitoring
panel room to the nearest place to the refrigerator. This routing must have at least a
20mm2 section.
Sub-Contest 6.2: Freezer. Teams must provide a routing from the monitoring panel
room to the nearest place to the freezer. This routing must have at least a 20 mm2 section.
Sub-Contest 6.3: Clothes Washer. Teams must provide a routing from the monitoring
panel room to the nearest place to the washing machine. This routing must have at least a
20mm2 section.
Sub-Contest 6.4: Clothes Dryer. No special wiring is needed for this sub-contest.
Sub-Contest 6.5: Dishwasher. Teams must provide a routing from the monitoring panel
room to the nearest place to the dishwasher. This routing must have at least a 20 mm2
section.
26
-
8/12/2019 Technical Monitoring Procedures
28/58
Monitoring Drawings SOLAR DECAHTLONEUROPE
Sub-Contest 6.6: Home Electronics. Teams must provide a routing from the monitoring
panel room to the electric box where the home electronics line is located. This routing must
have at least a 20 mm2
section.
Sub-Contest 6.7: Oven. Teams must provide a routing from the monitoring panel room
to the nearest place to the oven. This routing must have at least a 20 mm2 section.
Sub-Contest 6.8: Cooking. No special wiring is needed for this sub-contest.
Sub-Contest 6.9: Hot water draws: No special wiring is needed for this sub-contest.
9. Monitoring Drawings
According to Rule 30.2, all Teams have to submit the following ID-SDE Instrumentation Drawings
to the SDE 2012 Organization. Please see Appendix B for Drawing examples.
ID-001 - General Monitoring: A plan in which the sensors location, wiring, routing,
temporal tripod location and connection to the grid are shown.
ID-002 - Monitoring panel room: A plan in which the monitoring panel is located within
the monitoring panel room. Measurements about the free space left within the room must
be specified.
ID-003 - Electricity meters topology: A plan in which the different lines to be monitored
(i.e. PV, Bat and Loads) are shown. This plan requires a unifilar electricity plan where the
electricity meters are shown.
ID-004 - Electricity meters connection: A plan in which the monitoring panel and the
electric terminal blocks are shown. The distance from the monitoring panel to the terminal
blocks must be specified.
ID-005 - House appliances: A plan which includes the appliance locations must be
provided to the Organization. Moreover, this plan must include, in the legend, the brand
and reference of every appliance. Furthermore, the plan must include the routing between
the monitoring panel and the electric box where the Home Electronics meter will be located
together with the plugs location at which the home electronics are connected.
10. Instrumentation Plan and Approval
As a document summary, hereafter we provide information about the Team requirements. These
requirements will be checked from now on with the Teams by means of the Monitoring Checklist
(see AppendixA). Teams which do not pass all the items in the Monitoring Checklistwill not be
able to be monitored and no points will be obtained in those contests. The actions to be taken
before the competition are the following:
1. Every Team must hand in the preliminary monitoring plan (see Section9).
2. Each Team and the Organization will negotiate the location of the monitoring panel, the
location of the sensors, the sensors wiring and all the routing needed for a correct wiring.
3. Every Team must hand in the Final monitoring plan.
27
-
8/12/2019 Technical Monitoring Procedures
29/58
SOLAR DECAHTLONEUROPE Instrumentation Plan and Approval
4. The Organization must approve the Final monitoring plan.
5. Teams must ensure that the space and routing described in the Final Monitoring plan have
been left.
Once the assembly period of the competition starts, the following items must be accomplished:
1. The Organization will check the spaces destined for the wiring (routing, space, etc.).
2. Teams will make the necessary adjustments so that the instrumentation system can be safely
and robustly installed by the Organization.
3. The Organization will mark the sensors location.
4. The Organization will install the monitoring panel, power it and check everything is correctly
installed.
5. The Organization will wire the sensors to the monitoring panel.
6. The Organization will verify the sensors operation.
7. Teams are responsible for the monitoring system integrity.
28
-
8/12/2019 Technical Monitoring Procedures
30/58
Monitoring CheckList SOLAR DECAHTLONEUROPE
A. Monitoring CheckList
29
-
8/12/2019 Technical Monitoring Procedures
31/58
SOLAR DECAHTLONEUROPE Monitoring Plans Examples
B. Monitoring Plans Examples
30
-
8/12/2019 Technical Monitoring Procedures
32/58
Monitoring Plans Examples SOLAR DECAHTLONEUROPE
31
-
8/12/2019 Technical Monitoring Procedures
33/58
SOLAR DECAHTLONEUROPE Monitoring Plans Examples
32
-
8/12/2019 Technical Monitoring Procedures
34/58
Monitoring Plans Examples SOLAR DECAHTLONEUROPE
33
-
8/12/2019 Technical Monitoring Procedures
35/58
SOLAR DECAHTLONEUROPE Monitoring Plans Examples
34
-
8/12/2019 Technical Monitoring Procedures
36/58
Datasheets SOLAR DECAHTLONEUROPE
C. Datasheets
C.1. Twido PLCdatasheet
35
-
8/12/2019 Technical Monitoring Procedures
37/58
SOLAR DECAHTLONEUROPE C.1 Twido PLCdatasheet
36
-
8/12/2019 Technical Monitoring Procedures
38/58
C.1 Twido PLCdatasheet SOLAR DECAHTLONEUROPE
37
-
8/12/2019 Technical Monitoring Procedures
39/58
SOLAR DECAHTLONEUROPE C.1 Twido PLCdatasheet
38
-
8/12/2019 Technical Monitoring Procedures
40/58
C.1 Twido PLCdatasheet SOLAR DECAHTLONEUROPE
39
-
8/12/2019 Technical Monitoring Procedures
41/58
SOLAR DECAHTLONEUROPE C.2 TJ MONITORdatasheet
C.2. TJ MONITORdatasheet
MOD SAM9G20
RBZ ROBOT DESIGN S.L.
http://www.rbzrobotdesign.com
Module RBZ SAM9G20
M
M
o
o
d
d
u
u
l
l
e
e
b
b
a
a
s
s
e
e
d
d
i
i
n
n
A
A
T
T
9
9
1
1
S
S
A
A
M
M
9
9
G
G
2
2
0
0
m
m
i
i
c
c
r
r
o
o
c
c
o
o
n
n
t
t
r
r
o
o
l
l
l
l
e
e
r
r
f
f
r
r
o
o
m
m
A
A
t
t
m
m
e
e
l
l
C
C
o
o
m
m
p
p
a
a
t
t
i
i
b
b
l
l
e
e
w
w
i
i
t
t
h
h
R
R
B
B
Z
Z
M
M
o
o
d
d
u
u
l
l
a
a
r
r
S
S
y
y
s
s
t
t
e
e
m
m
3
3
D
D
m
m
o
o
d
d
e
e
l
l
a
a
v
v
a
a
i
i
l
l
a
a
b
b
l
l
e
e
f
f
o
o
r
r
d
d
i
i
r
r
e
e
c
c
t
t
i
i
n
n
t
t
e
e
g
g
r
r
a
a
t
t
i
i
o
o
n
n
i
i
n
n
t
t
o
o
m
m
e
e
c
c
h
h
a
a
n
n
i
i
c
c
a
a
l
l
C
C
A
A
D
D
HARDWARE
M
M
a
a
i
i
n
n
p
p
r
r
o
o
c
c
e
e
s
s
s
s
o
o
r
r
A
A
R
R
M
M
9
9
@
@
4
4
0
0
0
0
M
M
H
H
z
z
A
A
T
T
9
9
1
1
S
S
A
A
M
M
9
9
G
G
2
2
0
0
f
f
r
r
o
o
m
m
A
A
t
t
m
m
e
e
l
l
6
6
4
4
M
M
B
B
@
@
3
3
2
2
b
b
i
i
t
t
s
s
R
R
A
A
M
M
m
m
e
e
m
m
o
o
r
r
y
y
*
*
2
2
5
5
6
6
M
M
B
B
S
S
L
L
C
C
N
N
A
A
N
N
D
D
m
m
e
e
m
m
o
o
r
r
y
y
*
*
2
2
S
S
P
P
I
I
p
p
o
o
r
r
t
t
s
s
3
3
S
S
e
e
r
r
i
i
a
a
l
l
p
p
o
o
r
r
t
t
s
s
1
1
I
I
2
2
C
C
*
*
*
*
2
2
U
U
S
S
B
B
H
H
O
O
S
S
T
T
a
a
n
n
d
d
1
1
S
S
l
l
a
a
v
v
e
e
11SSDDIIOOwwiitthhssuuppppoorrttffoorrSSDD//SSDDIIOO//SSDDHHCC 11DDiiggiittaa llaauudd iiooppoorrtt 11EEtthhee rrnnee tt1100//110000 88DDiissccrreetteeII//OOssiiggnnaa llss 111166bb iittppaa rraallllee llbbuuss 88AAu
ux
xi
il
li
ia
ar
ry
yssi
ig
gn
na
al
ls
s******
C
C
o
o
m
m
e
e
r
r
c
c
i
i
a
a
l
l
(
(
0
0
/
/
6
6
0
0
C
C
)
)
a
a
n
n
d
d
i
i
n
n
d
d
u
u
s
s
t
t
r
r
i
i
a
a
l
l
(
(
-
-
4
4
0
0
/
/
8
8
5
5
C
C
)
)
t
t
e
e
m
m
p
p
e
e
r
r
a
a
t
t
u
u
r
r
a
a
r
r
a
a
n
n
g
g
e
e
a
a
v
v
a
a
i
i
l
l
a
a
b
b
l
l
e
e
5
5
V
V
i
i
n
n
p
p
u
u
t
t
s
s
u
u
p
p
p
p
l
l
y
y
40
-
8/12/2019 Technical Monitoring Procedures
42/58
C.2 TJ MONITORdatasheet SOLAR DECAHTLONEUROPE
MOD SAM9G20
RBZ ROBOT DESIGN S.L.
http://www.rbzrobotdesign.com
AATT9911SSAAMM99GG2200
6
64
4MMBB RRAAMM
225566MMBB
FFLLAASSHH
EETTHH 1100//110000
S
SPPIIOO00
UUAARRTT00
S
SDDIIOO
UUSSBB HHOOSSTT 00
U
UAARRTT11
U
U
A
A
R
R
T
T
2
2
U
U
S
S
B
B
H
H
O
O
S
S
T
T
1
1
U
US
SBB SSLLAAVVEE
SSPPIIOO11
I
I
2
2
C
C
0
0
DDIIGGIITTAALL
AAUUDDIIOO
G
G
P
P
I
I
O
O
0
0
.
.
.
.
8
8
MMEEMMOORRYYEESSTTAANNDDAARR
C
CO
ONNNNEECCTTIIVVIITTYY
DDIISSCCRREETTEE II //OO
S
S
E
E
R
R
I
I
A
A
L
L
C
CO
ON
NN
NE
EC
CT
TI
IV
VI
IT
TY
Y
1
16
6BB IITT
PPAARRAALLLLEELL
B
B
U
U
S
S
A
AU
UX
X0
0.
.
.
.
8
8
**BBaass iiccccoonnffiigguurraattiioonn..CCoonnssuu llttffoorrootthhee rrppoossss iibb iilliittiieess ****MMoorreeII22CCccaann bbee aaddddeedd rreedduucciinnggtthhee nnuummbbee rrooffdd iissccrreetteeII//OO******TThheessee ss iiggnnaa llssddeeppeenndd oonntthhee mmoodduu llee..CCoonnssuu llttRRBBZZffoorrtthhee iirrffuunnccttiioonnaa lliittyy
41
-
8/12/2019 Technical Monitoring Procedures
43/58
SOLAR DECAHTLONEUROPE C.2 TJ MONITORdatasheet
MOD SAM9G20
RBZ ROBOT DESIGN S.L.
http://www.rbzrobotdesign.com
SOFTWARE
L
L
i
i
n
n
u
u
x
x
b
b
a
a
s
s
e
e
d
d
d
d
e
e
v
v
e
e
l
l
o
o
p
p
m
m
e
e
n
n
t
t
s
s
y
y
s
s
t
t
e
e
m
m
R
R
B
B
Z
Z
p
p
r
r
o
o
v
v
i
i
d
d
e
e
s
s
p
p
a
a
t
t
c
c
h
h
e
e
s
s
b
b
a
a
s
s
e
e
d
d
i
i
n
n
l
l
u
u
n
n
u
u
x
x
4
4
s
s
a
a
m
m
p
p
r
r
o
o
j
j
e
e
c
c
t
t
s
s
o
o
u
u
r
r
c
c
e
e
s
s
B
Bu
ui
il
ld
dr
ro
oo
ot
t
b
ba
as
se
ed
d
r
ro
oo
ot
tf
fs
s
OOtthhee rrrroooottffssoorrkkee rrnnee llssaarreeaavvaa iillaabb lleeoonn ddeemmaanndd
DOCUMENTACIN
C
C
o
o
n
n
N
N
e
e
c
c
t
t
i
i
v
v
i
i
t
t
y
y
d
d
i
i
a
a
g
g
r
r
a
a
m
m
s
s
S
S
o
o
f
f
t
t
w
w
a
a
r
r
e
e
r
r
e
e
g
g
e
e
n
n
e
e
r
r
a
a
t
t
i
i
o
o
n
n
d
d
o
o
c
c
u
u
m
m
e
e
n
n
t
t
S
S
o
o
f
f
t
t
w
w
a
a
r
r
e
e
s
s
i
i
m
m
p
p
l
l
e
e
s
s
o
o
u
u
r
r
c
c
e
e
s
s
S
S
o
o
f
f
t
t
w
w
a
a
r
r
e
e
l
l
o
o
a
a
d
d
i
i
n
n
g
g
S
S
o
o
u
u
r
r
c
c
e
e
s
s
f
f
o
o
r
r
k
k
e
e
r
r
n
n
e
e
l
l
,
,
b
b
o
o
o
o
t
t
l
l
o
o
a
a
d
d
e
e
r
r
a
a
n
n
d
d
r
r
o
o
o
o
t
t
f
f
s
s
IDENTIFICADORES DE PRODUCTO
C
C
d
d
i
i
g
g
o
o
D
D
e
e
s
s
c
c
r
r
i
i
p
p
c
c
i
i
n
n
MMOODD__SSAAMM99GG2200__SSTTDDCC EEssttaannddaa rrmmoodduu lleewwiitthhccoommee rrcciiaa lltteemmppee rraattuurraaggrraaddee MMOODD__SSAAMM99GG2200__SSTTDDII EEssttaannddaa rrmmoodduu lleewwiitthhiinndduuss ttrriiaa lltteemmppee rraattuurraaggrraaddee
M
M
O
O
D
D
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
C
C
X
X
X
X
X
X
C
C
u
u
s
s
t
t
o
o
m
m
m
m
o
o
d
d
u
u
l
l
e
e
M
M
O
O
D
D
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
P
P
L
L
M
M
a
a
n
n
u
u
f
f
a
a
c
c
t
t
u
u
r
r
i
i
n
n
g
g
l
l
i
i
c
c
e
e
n
n
s
s
e
e
M
M
O
O
D
D
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
D
D
L
L
F
F
u
u
l
l
l
l
d
d
e
e
s
s
i
i
g
g
n
n
d
d
o
o
c
c
u
u
m
m
e
e
n
n
t
t
a
a
t
t
i
i
o
o
n
n
i
i
n
n
e
e
d
d
i
i
t
t
a
a
b
b
l
l
e
e
C
C
A
A
D
D
f
f
o
o
r
r
m
m
a
a
t
t
w
w
i
i
t
t
h
h
m
m
a
a
n
n
u
u
f
f
a
a
c
c
t
t
u
u
r
r
i
i
n
n
g
g
l
l
i
i
c
c
e
e
n
n
s
s
e
e
C
C
R
R
_
_
G
G
S
S
M
M
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
C
C
a
a
r
r
r
r
i
i
e
e
r
r
w
w
i
i
t
t
h
h
G
G
P
P
R
R
S
S
c
c
o
o
n
n
n
n
e
e
c
c
t
t
i
i
v
v
i
i
t
t
y
y
42
-
8/12/2019 Technical Monitoring Procedures
44/58
C.2 TJ MONITORdatasheet SOLAR DECAHTLONEUROPE
MOD SAM9G20
RBZ ROBOT DESIGN S.L.
http://www.rbzrobotdesign.com
Carrier GPRS RBZ
CCoommppaa ttiibb lleewwiitthhRRBBZZMMoodduu llaarrSSyysstteemm
GGPPRRSS ffoorr ddaa ttaattee lleemmee ttrryy
3
3
D
D
m
m
o
o
d
d
e
e
l
l
a
a
v
v
a
a
i
i
l
l
a
a
b
b
l
l
e
e
f
f
o
o
r
r
d
d
i
i
r
r
e
e
c
c
t
t
i
i
n
n
t
t
e
e
g
g
r
r
a
a
t
t
i
i
o
o
n
n
i
i
n
n
t
t
o
o
m
m
e
e
c
c
h
h
a
a
n
n
i
i
c
c
a
a
l
l
C
C
A
A
D
D
HARDWARE
RRBBZZmmoodduu llaarrssyysstteemm ssoocckkee tt GGPPRRSSmmooddeemm wwiitthhSSIIMMccaa rrddhhoo llddee rr SSMMAAaann tteennnnaa ccoonnnneeccttoorr DDuuaa llUUSSBBhhooss ttccoonnnneeccttoorr
O
O
n
n
e
e
U
U
S
S
B
B
S
S
l
l
a
a
v
v
e
e
c
c
o
o
n
n
n
n
e
e
c
c
t
t
o
o
r
r
1
1
R
R
S
S
2
2
3
3
2
2
s
s
e
e
r
r
i
i
a
a
l
l
p
p
o
o
r
r
t
t
1
1
R
R
S
S
4
4
8
8
5
5
s
s
e
e
r
r
i
i
a
a
l
l
p
p
o
o
r
r
t
t
1
1
S
S
D
D
I
I
O
O
w
w
i
i
t
t
h
h
s
s
u
u
p
p
p
p
o
o
r
r
t
t
f
f
o
o
r
r
S
S
D
D
/
/
S
S
D
D
I
I
O
O
/
/
S
S
D
D
H
H
C
C
1
1
E
E
t
t
h
h
e
e
r
r
n
n
e
e
t
t
1
1
0
0
/
/
1
1
0
0
0
0
8
8
D
D
i
i
s
s
c
c
r
r
e
e
t
t
e
e
I
I
/
/
O
O
s
s
i
i
g
g
n
n
a
a
l
l
s
s
C
C
o
o
m
m
e
e
r
r
c
c
i
i
a
a
l
l
(
(
0
0
/
/
6
6
0
0
C
C
)
)
a
a
n
n
d
d
i
i
n
n
d
d
u
u
s
s
t
t
r
r
i
i
a
a
l
l
(
(
-
-
4
4
0
0
/
/
8
8
5
5
C
C
)
)
t
t
e
e
m
m
p
p
e
e
r
r
a
a
t
t
u
u
r
r
a
a
r
r
a
a
n
n
g
g
e
e
a
a
v
v
a
a
i
i
l
l
a
a
b
b
l
l
e
e
1
1
2
2
V
V
i
i
n
n
p
p
u
u
t
t
s
s
u
u
p
p
p
p
l
l
y
y
,
,
v
v
e
e
r
r
s
s
i
i
o
o
n
n
s
s
w
w
i
i
t
t
h
h
L
L
i
i
P
P
O
O
b
b
a
a
t
t
t
t
e
e
r
r
y
y
b
b
a
a
c
c
k
k
u
u
p
p
a
a
v
v
a
a
i
i
l
l
a
a
b
b
l
l
e
e
D
DI
IN
N
R
Ra
a
i
i
l
l
m
m
o
o
u
u
n
n
t
t
e
e
d
d
43
-
8/12/2019 Technical Monitoring Procedures
45/58
SOLAR DECAHTLONEUROPE C.2 TJ MONITORdatasheet
MOD SAM9G20
RBZ ROBOT DESIGN S.L.
http://www.rbzrobotdesign.com
SOFTWARE
L
L
i
i
n
n
u
u
x
x
b
b
a
a
s
s
e
e
d
d
d
d
e
e
v
v
e
e
l
l
o
o
p
p
m
m
e
e
n
n
t
t
s
s
y
y
s
s
t
t
e
e
m
m
R
R
B
B
Z
Z
p
p
r
r
o
o
v
v
i
i
d
d
e
e
s
s
p
p
a
a
t
t
c
c
h
h
e
e
s
s
b
b
a
a
s
s
e
e
d
d
i
i
n
n
l
l
u
u
n
n
u
u
x
x
4
4
s
s
a
a
m
m
p
p
r
r
o
o
j
j
e
e
c
c
t
t
s
s
o
o
u
u
r
r
c
c
e
e
s
s
B
Bu
ui
il
ld
dr
ro
oo
ot
t
b
ba
as
se
ed
d
r
ro
oo
ot
tf
fs
s
OOtthhee rrrroooottffssoorrkkee rrnnee llssaarreeaavvaa iillaabb lleeoonn ddeemm aanndd
DOCUMENTACIN
C
C
o
o
n
n
n
n
e
e
c
c
t
t
i
i
v
v
i
i
t
t
y
y
d
d
i
i
a
a
g
g
r
r
a
a
m
m
s
s
S
S
o
o
f
f
t
t
w
w
a
a
r
r
e
e
r
r
e
e
g
g
e
e
n
n
e
e
r
r
a
a
t
t
i
i
o
o
n
n
d
d
o
o
c
c
u
u
m
m
e
e
n
n
t
t
S
S
o
o
f
f
t
t
w
w
a
a
r
r
e
e
s
s
i
i
m
m
p
p
l
l
e
e
s
s
o
o
u
u
r
r
c
c
e
e
s
s
S
S
o
o
f
f
t
t
w
w
a
a
r
r
e
e
l
l
o
o
a
a
d
d
i
i
n
n
g
g
S
S
o
o
u
u
r
r
c
c
e
e
s
s
f
f
o
o
r
r
k
k
e
e
r
r
n
n
e
e
l
l
,
,
b
b
o
o
o
o
t
t
l
l
o
o
a
a
d
d
e
e
r
r
a
a
n
n
d
d
r
r
o
o
o
o
t
t
f
f
s
s
IDENTIFICADORES DE PRODUCTO
C
C
d
d
i
i
g
g
o
o
D
D
e
e
s
s
c
c
r
r
i
i
p
p
c
c
i
i
n
n
CCRR__GGSSMM__SSAAMM99GG2200__CCTT CCaarrrriieerr wwiitthh GGPPRRSS ccoonnnneeccttiivviittyy ccoomm ee rrcciiaa ll
tteemm ppee rraattuurree
C
C
R
R
_
_
G
G
S
S
M
M
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
I
I
T
T
C
C
a
a
r
r
r
r
i
i
e
e
r
r
w
w
i
i
t
t
h
h
G
G
P
P
R
R
S
S
c
c
o
o
n
n
n
n
e
e
c
c
t
t
i
i
v
v
i
i
t
t
y
y
i
i
n
n
d
d
u
u
s
s
t
t
r
r
i
i
a
a
l
l
t
t
e
e
m
m
p
p
e
e
r
r
a
a
t
t
u
u
r
r
e
e
C
C
R
R
_
_
G
G
S
S
M
M
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
C
C
X
X
X
X
X
X
C
C
u
u
s
s
t
t
o
o
m
m
c
c
a
a
r
r
r
r
i
i
e
e
r
r
C
C
R
R
_
_
G
G
S
S
M
M
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
P
P
L
L
M
M
a
a
n
n
u
u
f
f
a
a
c
c
t
t
u
u
r
r
i
i
n
n
g
g
l
l
i
i
c
c
e
e
n
n
s
s
e
e
C
C
R
R
_
_
G
G
S
S
M
M
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
D
D
L
L
F
F
u
u
l
l
l
l
d
d
e
e
s
s
i
i
g
g
n
n
d
d
o
o
c
c
u
u
m
m
e
e
n
n
t
t
a
a
t
t
i
i
o
o
n
n
i
i
n
n
e
e
d
d
i
i
t
t
a
a
b
b
l
l
e
e
C
C
A
A
D
D
f
f
o
o
r
r
m
m
a
a
t
t
w
w
i
i
t
t
h
h
m
m
a
a
n
n
u
u
f
f
a
a
c
c
t
t
u
u
r
r
i
i
n
n
g
g
l
l
i
i
c
c
e
e
n
n
s
s
e
e
M
M
O
O
D
D
_
_
S
S
A
A
M
M
9
9
G
G
2
2
0
0
_
_
S
S
T
T
D
D
C
C
A
A
T
T
9
9
1
1
S
S
A
A
M
M
9
9
G
G
2
2
0
0
e
e
s
s
t
t
n
n
d
d
a
a
r
r
m
m
o
o
d
d
u
u
l
l
e
e
C
C
R
R
_
_
G
G
S
S
M
M
_
_
B
B
A
A
T
T
L
L
i
i
P
P
O
O
b
b
a
a
t
t
t
t
e
e
r
r
y
y
b
b
a
a
c
c
k
k
u
u
p
p
44
-
8/12/2019 Technical Monitoring Procedures
46/58
C.3 Domotax datasheet SOLAR DECAHTLONEUROPE
C.3. Domotax datasheet
5
Conexiones
Dimensiones
Caractersticas Tcnicas
Tensin de referencia Un
Intensidad de base
Ib (Imx)
Frecuencia de referencia
Consumo propio
Clase de precisin
Clase de proteccin
Tipo de proteccin
Montaje
Cuadro de Modelos
Modelo Precisin Discriminaciones Caractersticas
DOMOTAX Clase 1 Activa Sin discriminacin horaria Medida directa 10(60) A
DOMOTAX 2 TN Clase 1 Activa Con discriminacin horaria (dh) mas rel Medida directa 10(60) A
DOMOTAX Activa/Reactiva C lase 1 Acti va / C lase 2 React iva S in y con d is cr im inac in hor ar ia (dh) Med ida d ir ec ta 10(60) A
DOMOTAX Bidireccional Clase 1 Activa Importacin y Exportacin Medida directa 10(60) A
230 Vc.a.
10(60) A
50 Hz
Circuitos de tensin:
< 2 VA
Circuitos de intensidad:
< 1 VA
Clase 1 segn EN 62053-21
Clase II segn EN 60335
IP 51 segn EN 60529
Tringulo de fijacin (Ver dimeniones).
Caractersticas
El DOMOTAX es un contador multifuncin de energa elctri-ca monofsico, esttico para medida directa de energa acti-va (clase 1) o activa / reactiva; de conexin directa a doshilos.
Ideal para la discriminacin horaria ya que sustituye al con-
tador de doble tarifa y al interruptor horario. Puede efectuar discriminaciones horarias de hasta cuatroperiodos de tarifacin con sus correspondientes maxmetros.
Permite la posibilidad partiendo de un modelo bsico, deincorporar comunicacin mediante un puerto RS232,RS485, salida SO o emisor de impulsos (libre de potencial).
La comunicacin RS485 se incorpora para aquellas instala-ciones con lectura centralizada.
Se puede suministrar con rel de retardo por mximademanda bajo pedido.
El DOMOTAX es un contador idneo para instalacionesmonofsicas en viviendas que necesiten gestionar sus con-sumos, ya que puede incluir curva de carga de la instala-cin.
Todas estas opciones hacen del DOMOTAX uno de los con-tadores monofsicos de medida directa ms completos delmercado.
45
-
8/12/2019 Technical Monitoring Procedures
47/58
SOLAR DECAHTLONEUROPE C.4 STR100 datahseet
C.4. STR100 datahseet
SPECIFICATIONS
Ambient Conditions
Storage temperature. . . . . . . . . . . 20 C to +70 C
(4 F to +158 F)
Operation temperature . . . . . . . . . .0 C to +50 C(+32 F to +122 F)
Humidity . . . . . . . . . . . . . . . . . . . . . . . . . max. 90%
non-condensing relative humidity
Mechanical
Enclosure material . . . . . . . . . . . . . . . . . . .ABS/PC
Enclosure rat ing . . . . . . . . . . . . . . . . IP 20/NEMA 1
Dimensions. . . . . . . . . . . . . . . . . . . . . . . see Fig. 1
Weight . . . . . . . . . . . . . . . . . . . . . . . .85 g (0.19 lb.)
Agency Compliances
Emission
CE . . . . . . . . . . . . . . . . . . . . . . . . . . EN 61000-6-3
Immunity
CE . . . . . . . . . . . . . . . . . . . . . . . . . . EN 61000-6-1
Safety
CE . . . . . . . . . . . . . . . . . . . . . . . . . . . EN 61010-1
UL . . . . . . . . . . . . . . . . . . . . . C -UL, UL 916 Listed
Flammability
UL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . UL 94 V-0
Energy (STR106-3 only)
eu.bac, certificate no. 020711 . . . . . . . . EN 15500
Sensor Data
Type . . . . . . . . . . . . . . . . . . . . . . 1.8 kW thermistor
Accuracy . . . . . . . . . . . . . . at 1530 C (5986 F),
0.35 C (0.63 F)
STR100 - STR107
Field Devices Europe 01
Wall Modules
The STR is a series of wal l modu les optimized fo r
public facilities such as office buildings, hotels,
hospitals, schools and shopping malls. Their
pleasant appearance and well-designed inter-
face make them suitable for any contemporary
building. They are easy to operate and install.
The STR101 through STR107 are equipped
with a modular jack (RJ-10) that allows the wall
module to be connected to the portable TAC
Xenta OP (Operator Panel ). The STR101 through
STR107 can be used together with the TAC Xen-
ta 100, 200, 300 and 400 series of controllers.
The wall modules are equipped diff erently; the
STR100 is the basic model, while the STR106
and STR107 are fully equipped. The STR wall
modules replace the ZS 100 series and the
EGRL room sensor.
DIMENSIONS mm (in)
58(
2.2
8)
116(
4.6
)
24(
0.9
)
84 (3.3)
82 (3.2)
Fig 1
46
-
8/12/2019 Technical Monitoring Procedures
48/58
C.4 STR100 datahseet SOLAR DECAHTLONEUROPE
Schneider Electric Telephone Europe: Malm, Sweden +46 40 38 68 50 Telephone Asia Pacific: Singapore +65 6776 3166 www.schneider-electric.com/buildings
03-00101-04-en 2007 mf
2
009SchneiderElectric.
Allrightsreserved.
STR100 - STR10703
Field Devices Europe
2
009SchneiderElectric.
Allrightsreserved.
02Field Devices Europe
Part Numbers
STR100 . . . . . . . . . . . . . . . . . . . . . . . . 004600100
STR100-W (White) . . . . . . . . . . . . . . . . 004600110
STR101 . . . . . . . . . . . . . . . . . . . . . . . . 004600200
STR102 . . . . . . . . . . . . . . . . . . . . . . . . 004600300
STR103 . . . . . . . . . . . . . . . . . . . . . . . . 004600700
STR104 . . . . . . . . . . . . . . . . . . . . . . . . 004600400
STR106 . . . . . . . . . . . . . . . . . . . . . . . . 004600500
STR106-B . . . . . . . . . . . . . . . . . . . . . . 004600800
STR106-3. . . . . . . . . . . . . . . . . . . . . . . 004600900
STR107 . . . . . . . . . . . . . . . . . . . . . . . . 004600600
FUNCTIONS
Fig. 2 shows an STR107. The STR100STR106
may have less functionality.
Mode Indicator
A green LED is used on the STR101STR107
to indicate the mode in accordance with the
following:
green light.
flashing green light.
being off.
Bypass Button
A bypass button is provided on models STR103
STR107 to change from standby (economy)
or unoccupied mode to comfort mode. When
entering comfort mode, the symbol on the dis-
play shows a steady light. When the bypass time
expires, the symbol returns to its previous status
again, provided that the feedback mode is con-
nected. Otherwise the symbol returns to the Off
status after two hours.
Setpoint Offset Wheel
A setpoint offset wheel i s provided on models
STR103, STR104, STR106 and STR107 for
adjusting the temperature setpoint offset.
The adjustment range may be set to the
following limits (not applicable to STR106-3):
The adjustment i s done manually using the plas-
tic keys on the back of the core-panel. Increase/
decrease limits are separately adjustable.
Model Temp.
Sensor
Mode
Indicator
Setpoint
Offset
Wheel
Bypass
Button
Fan Speed
Control1
STR100 X
STR101 X X
STR102 X X X
STR103 X X X
STR104 X X X X
STR106
STR106-B
STR106-3
X
X
X2
X3
X4
STR107 X X X X X5
1. In the TAC Xenta 100 series, this is onlyapplicable for the TAC Xenta 101-VF and TAC
Xenta 121-FC.
2. STR106-3 with a fixed range: 3 C
(centigrades only).
3. STR106-B has no icon on t he Bypass button.
4. All three models use a 5-positions control
wheel: A-0-I-II-III.
5. STR107 uses a 3-positions control wheel:
Auto-Off-On.
Wiring
The STR100STR107 uses 210