Technical Memorandum - nps.acgov.orgnps.acgov.org/nps-assets/docs/npstrh.pdf · other party except...
-
Upload
truonghanh -
Category
Documents
-
view
217 -
download
5
Transcript of Technical Memorandum - nps.acgov.orgnps.acgov.org/nps-assets/docs/npstrh.pdf · other party except...
Technical Memorandum
Limitations:
This document was prepared solely for CEMEX Construction Materials, Inc. in accordance with professional standards at the time the services were
performed and in accordance with the contract between CEMEX Construction Materials, Inc. and Brown and Caldwell dated September 13, 2013.
This document is governed by the specific scope of work authorized by CEMEX Construction Materials, Inc.; it is not intended to be relied upon by any
other party except for regulatory authorities contemplated by the scope of work. We have relied on information or instructions provided by CEMEX
Construction Materials, Inc. and other parties and, unless otherwise expressly indicated, have made no independent investigation as to the validity,
completeness, or accuracy of such information.
701 Pike Street, Suite 1200 Seattle, WA 98101 Phone: 206-624-0100 Fax: 206-749-2200
Prepared for: CEMEX Construction Materials, Inc.
Project Title: Eliot Facility Reclamation Plan Amendment, Surface Mining Permit 23, CA Mine 91-01-0009
Project No.: 144718
Technical Memorandum 2
Subject: Arroyo del Valle Diversion and Conveyance Feasibility
Date: March 7, 2014
To: Ronald D. Wilson, Manager, Land Use Permits: Pacific Region
From: Nathan Foged, Supervising Engineer
Copy to: Andrew Kopania, EMKO Environmental Karen Spinardi, Spinardi and Associates
Prepared by: Nathan Foged, Supervising Engineer California Civil Engineer C66395, Exp. June 2014
Prepared by: Aren Hansen, Principal Engineer California Civil Engineer C78259, Exp. June 2014
Reviewed by: William K. Faisst, Vice President California Civil Engineer C29146, Exp. March 2015
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
ii
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
This page intentionally left blank.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
iii
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Table of Contents
List of Figures ........................................................................................................................................................... iv
List of Tables .............................................................................................................................................................. v
List of Abbreviations ................................................................................................................................................. vi
Section 1: Introduction ............................................................................................................................................. 1
Section 2: Background ............................................................................................................................................. 2
2.1 Site Description ........................................................................................................................................ 2
2.1.1 Livermore-Amador Valley ............................................................................................................ 2
2.1.2 Arroyo del Valle ............................................................................................................................ 3
2.2 Reclamation Planning .............................................................................................................................. 4
Section 3: Design Requirements ............................................................................................................................. 5
3.1 Diversion Criteria ...................................................................................................................................... 5
3.2 Fish Passage and Exclusion .................................................................................................................... 6
3.3 Diversion Location .................................................................................................................................... 7
3.4 Additional Design Considerations ........................................................................................................... 8
Section 4: Options Investigation .............................................................................................................................. 9
4.1 Intake and Fish Exclusion Devices .......................................................................................................... 9
4.1.1 Fish Screening ........................................................................................................................... 10
4.1.2 Infiltration and Seepage ........................................................................................................... 16
4.1.3 Selection of Options for Further Evaluation ............................................................................ 18
4.2 Hydraulic Grade Control Structure ........................................................................................................ 18
4.2.1 Design Options .......................................................................................................................... 18
4.2.2 Options Screening ..................................................................................................................... 21
4.3 Fish Passage or Bypass Structures ....................................................................................................... 23
4.3.1 Design Options .......................................................................................................................... 23
4.3.2 Options Screening ..................................................................................................................... 25
4.3.3 Provision for Controlled Bypass Flows ..................................................................................... 26
Section 5: Evaluation of Conceptual Design Alternatives .................................................................................... 27
5.1 Formulation of Alternatives ................................................................................................................... 27
5.1.1 Alternative 1: Infiltration Bed.................................................................................................... 28
5.1.2 Alternative 2: Linear Screen ..................................................................................................... 29
5.1.3 Alternative 3: Two Cone Screens ............................................................................................. 30
5.1.4 Alternative 4: Nine Cone Screens ............................................................................................ 31
5.2 Evaluation of Alternatives ...................................................................................................................... 32
Section 6: Recommendations for Preferred Alternative ...................................................................................... 36
6.1 Conceptual Layout and Conveyance into Lake A ................................................................................. 37
6.2 Concept-Level Plans and Cost Estimate ............................................................................................... 37
6.3 Potential Downstream Location ............................................................................................................ 38
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
iv
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
6.4 Recommendations for Further Study .................................................................................................... 40
References .............................................................................................................................................................. 41
Attachment A: Conceptual Design Figures ........................................................................................................... A-1
Attachment B: Construction Cost Estimate .......................................................................................................... B-1
List of Figures
Figure 1. Location of CEMEX’s Eliot Facility ............................................................................................................ 2
Figure 2. Surface flows related to Arroyo del Valle and the Chain of Lakes ......................................................... 5
Figure 3. Schematic representation of diversion system ...................................................................................... 9
Figure 4. Decision flow chart for selecting fish screen options ........................................................................... 10
Figure 5. Example of an on-stream fish screen (USBR, 2006) ............................................................................ 11
Figure 6. Examples of an in-canal fish screen (USBR, 2006) .............................................................................. 11
Figure 7. Example of inclined linear fish screens (USBR, 2009) ........................................................................ 12
Figure 8. Example of cylindrical fish screens ........................................................................................................ 12
Figure 9. Example of conical screens.................................................................................................................... 13
Figure 10. Hydraulic depth relationships in Arroyo del Valle near east end of Lake A ...................................... 14
Figure 11. Existing Arroyo del Valle channel geometry near east end of Lake A ............................................... 14
Figure 12. Example of a 500 cfs diversion using conical screens ...................................................................... 15
Figure 13. Conceptual sketch of a lateral infiltration gallery ............................................................................... 16
Figure 14. Conceptual sketch of a permeable berm ........................................................................................... 17
Figure 15. Definition sketch for calculating berm seepage (USACE, 1986) ....................................................... 17
Figure 16. Examples of in-channel rock structures that could pool water upstream ........................................ 19
Figure 17. Example of a flashboard weir used to impound water on a stream ................................................. 19
Figure 18. Example of an inflatable rubber dam .................................................................................................. 20
Figure 19. Examples of pneumatically actuated (Obermeyer) gates .................................................................. 20
Figure 20. Examples of low-head concrete diversion dams ................................................................................ 21
Figure 21. Examples of fish bypass channels ...................................................................................................... 23
Figure 22. Conceptual layout of a partial-width rock ramp fishway .................................................................... 24
Figure 23. Sketch of a vertical-slot fish ladder (NMFS, 2011) ............................................................................ 24
Figure 24. Example of vertical-slot fish ladder ..................................................................................................... 25
Figure 25. Dimensions of a cutthroat flume ......................................................................................................... 26
Figure 26. Schematic sketch of Alternative 1 (plan view) ................................................................................... 28
Figure 27. Schematic sketch of Alternative 2 (plan view) ................................................................................... 29
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
v
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Figure 28. Schematic sketch of Alternative 3 (plan view) ................................................................................... 30
Figure 29. Schematic sketch of Alternative 4 (plan view) ................................................................................... 31
Figure 30. Overall ratings based on weighted evaluation criteria ....................................................................... 36
Figure 31. Dimensional sketch of Parshall flume (FOA, 1993) ....................................................................... 37
Figure 32. Comparison of required diversion head differential with Lake A water surface .............................. 39
List of Tables
Table 1. Water Agencies Served by the South Bay Aqueduct ................................................................................ 3
Table 2. Preliminary Sizing for On-Stream Fish Screen Options .......................................................................... 15
Table 3. Comparison of Hydraulic Grade Control Options ................................................................................... 21
Table 4. Comparison of Fish Passage and Bypass Options ................................................................................. 25
Table 5. Ratings for Evaluation of Design Criteria ................................................................................................ 33
Table 6. Evaluation of Design Alternatives based on Design Criteria ................................................................. 34
Table 7. Summary of Pipe Sizing ........................................................................................................................... 38
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
vi
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
List of Abbreviations
ACCDA Alameda County Community Development Agency
Amendment SMP-23 Reclamation Plan Amendment
BC Brown and Caldwell
CDFW California Department of Fish and Wildlife
CEMEX CEMEX Construction Materials, Inc.
cfs cubic foot/feet per second
County Alameda County, California
ft foot/feet
ft2 square foot/feet
ft/s foot/feet per second
gpd/ft2 gallon(s) per day per square foot
LAVQAR Livermore-Amador Valley Quarry Area Reclamation
NMFS National Marine Fisheries Service
NOAA National Oceanic and Atmospheric Administration
O&M operations and maintenance
PVC polyvinyl chloride
Q-1 Alameda County Quarry Permit 1
Q-76 Alameda County Quarry Permit 76
RCP reinforced concrete pipe
SFEI San Francisco Estuary Institute
SFHA Special Flood Hazard Area
SFPUC San Francisco Public Utilities Commission
Site authorized mining area
SMP-23 Surface Mining Permit 23
Specific Plan LAVQAR Specific Plan
Spinardi Spinardi Associates
Study analysis of hydraulic impacts and evaluation of design options for the Arroyo del Valle diversion to Lake A
USACE U.S. Army Corps of Engineers
USBR U.S. Bureau of Reclamation
Valley Livermore-Amador Valley
Zone 7 Zone 7 of the Alameda County Flood Control and Water Conservation District
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
1
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Section 1: Introduction CEMEX Construction Materials, Inc. (CEMEX) owns and operates the Eliot Facility, a sand-and-gravel mining
operation located between the cities of Pleasanton and Livermore within the unincorporated area of
Alameda County (County), California. CEMEX is seeking the approval of an amendment to its existing
Reclamation Plan, which was originally approved in 1987 under Surface Mining Permit 23 (SMP-23).
In June 2013, Spinardi Associates (Spinardi) prepared the SMP-23 Reclamation Plan Amendment
(Amendment) and submitted it to the Alameda County Community Development Agency (ACCDA). ACCDA
provided comments on the Amendment in a July 8, 2013, letter from James Gilford to Ron Wilson, titled
“Completeness Review of Application to Amend Surface Mining Permit and Reclamation Plan No. 23.” The
letter requested additional technical evaluations, including the following two comments (summarized here):
• Hydraulic impacts: Conduct technical analyses (e.g., hydraulic modeling) to demonstrate that the
restored channel will remain stable, and that neither the channel modifications nor the diversion struc-
ture will increase flood risk to neighboring properties and infrastructure.
• Design feasibility: Present a complete design concept (e.g., schematic plans) and demonstrate that the
elements of the reclamation plan designed to address diversion and conveyance into the Chain of
Lakes1 can be feasibly constructed in compliance with known regulatory requirements.
In response to these comments, CEMEX retained Brown and Caldwell (BC) to analyze hydraulic impacts
along affected reaches of Arroyo del Valle to evaluate design alternatives for the Chain of Lakes diversion
(Study). This document, Technical Memorandum 2, addresses design feasibility as described in the above
comment. A separate document, Technical Memorandum 1, addresses hydraulic impacts.
This document addresses the following Study objectives assigned to BC:
• Investigate design requirements and performance criteria for diversion and conveyance facilities,
including pertinent design criteria requested by the Alameda County Flood Control and Water Conserva-
tion District Zone 7, also known as the Zone 7 Water Agency (“Zone 7”).
• Investigate options for key project components (e.g., fish exclusion, hydraulic grade controls, and fish
passage), perform an initial screening of options, and then formulate up to four conceptual design alter-
natives.
• Evaluate each alternative with respect to key design criteria and identify a preferred alternative.
• Develop conceptual design sketches and prepare a preliminary construction cost estimate for the
preferred alternative.
Technical Memorandum 2 includes the following six sections:
1. Introduction: This section provides a brief introduction to the Reclamation Plan Amendment, describes
the purpose of the Study, and lists specific objectives addressed by this document.
2. Background: This section provides background information regarding the project site, Arroyo del Valle,
and the development of the Amendment.
3. Design Requirements: This section discusses diversion criteria and key design considerations, as well as
regulatory requirements that are likely to influence design options and project feasibility.
1 The original SMP-23 Reclamation Plan was developed in accordance with the Specific Plan for Livermore-Amador Valley Quarry
Area Reclamation (LAVQAR Specific Plan), adopted by the County in November 1981. The LAVQAR Specific Plan describes a “Chain of Lakes” reclamation concept that calls for the creation of a series of excavated lakes to be used for storage and groundwater recharge. See Section 2.2 for more information.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
2
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
4. Options Investigation: This section provides information on design options for key project components
including an initial screening of hydraulic grade control and fish bypass options.
5. Evaluation of Conceptual Design Alternatives: This section describes each of the conceptual design
alternatives and evaluates those alternatives with respect to the specified design criteria.
6. Recommendations: This section draws conclusions from the alternatives evaluation and provides
specific recommendations for a preferred conceptual design alternative.
Section 2: Background This section provides background information regarding the project site (Section 2.1) and the development
of the Amendment (Section 2.2).
2.1 Site Description
The CEMEX Eliot Facility is located in the
Livermore-Amador Valley (Valley) between
the cities of Pleasanton and Livermore,
California (see Figure 1). Mining
operations at the Eliot Facility are vested
under Alameda County Quarry Permit 1 (Q-
1) and Quarry Permit 76 (Q-76) granted in
1957 and 1969, respectively. The
authorized mining area (Site) covers
approximately 975 acres of land between
Stanley Boulevard and Vineyard Avenue.
The Shadow Cliffs Regional Recreation
Area is located directly west of the Site,
Vulcan’s sand and gravel operation is
located to the north and east, and the
Ruby Hill subdivision is located across
Vineyard Avenue to the south. The
evaluations presented in this technical
memorandum address the diversion of
water from Arroyo del Valle into Lake A,
near the east end of the Eliot Facility.
2.1.1 Livermore-Amador Valley
The Valley is a wide depression in the
Diablo Range, bounded by the East Bay
Hills to the west and the Altamont Hills to
the east. The Valley’s western portion is the Amador Valley; it includes the city of Pleasanton. The Valley’s
eastern portion is the Livermore Valley; it includes the city of Livermore. The two valleys together form the
Valley. According to the San Francisco Estuary Institute (SFEI, 2013), the Valley was formed by geological
processes and provides a wide space for streams to spread and sink.
Numerous streams that drain out of the surrounding hills have deposited sediments over thousands of years
and filled the Valley (SFEI, 2013). Arroyo Mocho and Arroyo del Valle are two major streams draining into the
Figure 1. Location of CEMEX’s Eliot Facility
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
3
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
southern portion of the Valley. Historically, these were wide and braided streams that deposited large
amounts of coarse sediment transported from their headwaters in the Diablo Range (SFEI, 2013).
Sand and gravel mining has occurred along the Arroyo Mocho and Arroyo del Valle alluvial formations since
the late 1800s, including the areas around the Eliot Facility. Over the years, mining and development
activities have rerouted and channelized much of the lower reaches of Arroyo Mocho and Arroyo del Valle.
Arroyo del Valle’s existing channel flows along the southern portion of the Site. Section 2.2 discusses
proposed mining and reclamation activities and potential impacts to Arroyo del Valle. Section 2.1.2 provides
an overview of the Arroyo del Valle hydrology and geomorphology.
2.1.2 Arroyo del Valle
Arroyo del Valle is located in the upper Alameda Creek watershed. The arroyo drains an area of
approximately 172 square miles before it discharges to Arroyo de la Laguna, west of Pleasanton. Arroyo de
la Laguna flows south and discharges into Alameda Creek, near the town of Sunol. Alameda Creek then
flows west through the East Bay Hills before discharging into San Francisco Bay.
Approximately 85 percent (146 square miles) of the Arroyo
del Valle basin is located upstream of Del Valle Reservoir,
constructed in 1968 to serve as off-channel storage for
water delivered through the South Bay Aqueduct (part of
the California State Water project) and for flood control.
Zone 7 is one of three water agencies served by the South
Bay Aqueduct; Table 1 shows the annual entitlements for
each agency. Zone 7 also uses a small portion of Del Valle
Reservoir capacity to store runoff from the local
watershed2. Although Del Valle Reservoir serves primarily
as water supply storage, a portion of its 77,100-acre-foot
capacity is normally reserved for flood control.
Del Valle Reservoir has altered the hydrologic flow regime in the lower reaches of Arroyo del Valle (Kamman,
2009). Peak flows have decreased and large-magnitude flood flows have been virtually eliminated. Managed
releases during the dry season have resulted in perennial flow conditions along the valley floor rather than
the historical intermittent flow conditions when the arroyo would become dry in the summertime (Kamman,
2009; LSA, 2013). Altered flows have also contributed to changes in Arroyo del Valle channel; the once
actively braided channel network along the valley floor now has shifted to a more defined central channel
system (Kamman, 2009).
Directly downstream of the dam, Arroyo del Valle flows through a narrow, sinuous canyon until it reaches the
valley floor about 1 mile downstream, near the Veterans Administration hospital. At this point, the channel
and floodplain become wider and, in the past, became more active and braided. Sycamore Grove Park is an
important community park that preserves mature Western Sycamore trees along this reach of the historical
Arroyo del Valle floodplain. This park stretches approximately 2 miles from the hospital to Vallecitos Road.
The Eliot Facility Site is located just downstream of Sycamore Grove Park. Arroyo del Valle flows along the
southern portion of the Site adjacent to Lakes A and B (see Section 2.2, Reclamation Planning). The arroyo
flows through two small lakes along the south side of the Shadow Cliffs Regional Recreation Area and then
continues west through the city of Pleasanton. Several small streams drain into Arroyo del Valle between the
dam and its confluence with Arroyo de la Laguna ).
2 Del Valle Reservoir data are available on the Zone 7 Web site: http://www.zone7water.com/water-supply/48-del-valle-reservoir.
Table 1. Water Agencies Served by the South Bay
Aqueduct
Water agency Annual entitlement
(acre-feet)
Zone 7 46,000
Alameda County Water District 42,000
Santa Clara Valley Water District 100,000
Total 188,000
Source: California Department of Water Resources (1968,
2001).
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
4
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
2.2 Reclamation Planning
The SMP-23 Reclamation Plan (1987) was developed in accordance with the Specific Plan for Livermore-
Amador Valley Quarry Area Reclamation (LAVQAR Specific Plan, or Specific Plan), adopted by the County in
November 1981. The LAVQAR Specific Plan describes a “Chain of Lakes” reclamation concept, where mining
operators would convert excavated gravel quarries into a series of open lakes that use them for storage and
groundwater recharge. After mining is completed and quarry sites are reclaimed, the Chain of Lakes are to
be dedicated to Zone 7 of the Alameda County Flood Control and Water Conservation District (Zone 7) for
use in managing the groundwater basin. According to the SMP-23 Reclamation Plan (1987), and consistent
with the LAVQAR Specific Plan, mining at the Site will result in the formation of two lakes:
• Lake A will be located north of Vineyard Avenue, between Isabel Avenue (State Route 84) and Vallecitos
Road.
• Lake B will be located north of Vineyard Avenue, between Isabel Avenue (State Route 84) and the
Shadow Cliffs Regional Recreation Area.
The SMP-23 Reclamation Plan (1987) indicates that excavation at Lakes A and B will extend as far south as
Vineyard Avenue, and that Arroyo del Valle will flow into and through the pits during active mining operations.
Two large concrete spillways would be constructed to control flows into each pit, one at Vallecitos Road and
one at Isabel Avenue. Outflow from Lake B would occur over a rock-lined overflow weir at Lake B’s west end,
returning to Arroyo del Valle. The SMP-23 Reclamation Plan (1987) does not include provision for the
restoration or reconstruction of the channel for Arroyo del Valle, indicating that the arroyo would be routed
through Lakes A and B and the spillways would remain in place after mining was completed.
The proposed SMP-23 Reclamation Plan Amendment (June 2013) reconfigures the footprints of both Lakes
A and B to maintain the channel for Arroyo del Valle separate from Lakes A and B. CEMEX would no longer
excavate Lake A as far south as Vineyard Avenue such that the existing Arroyo del Valle channel could
remain intact. Lake B still would extend south through the currently disturbed Arroyo del Valle channel
alignment, but CEMEX would construct a new channel alignment closer to Vineyard Avenue, to restore the
initial hydraulic and biological function of the arroyo. Given that the channel would no longer flow through
Lakes A and B, the reclamation plan would no longer need to include large concrete spillways at Vallecitos
Road and Isabel Avenue, or the large rock-lined overflow weir at the west end of Lake B.
After reviewing the Amendment submitted to the County in June 2013, ACCDA sent a letter to CEMEX dated
July 8, 2013, with several comments that focused on the following two issues related to the water diversion
and conveyance facilities:
• Hydraulic impacts: Conduct technical analyses (e.g., hydraulic modeling) to demonstrate that the
restored channel will remain stable, and that neither the channel modifications nor the diversion
structure will increase flood hazards.
• Design feasibility: Present a complete design concept (e.g., schematic plans) and demonstrate that the
elements of the reclamation plan designed to address diversion and conveyance into the Chain of Lakes
can be feasibly constructed in compliance with known regulatory requirements. For example, the
proposed diversion structure would require a bypass flow feature (e.g., fish ladder) and a screen
cleaning system (or equivalent fish protection provisions) to be in compliance with current fish habitat
requirements.
The remainder of this document addresses the “design feasibility” comment. A separate technical memo-
randum, TM 1, addresses the “hydraulic impacts” comment.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
5
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Section 3: Design Requirements As described in the previous section, the Amendment calls for Arroyo del Valle to be separated from Lakes A
and B under reclaimed conditions. Therefore, the Amendment includes a diversion structure and conduits
between Lakes A, B, and C to facilitate water transfer from Arroyo del Valle into the Chain of Lakes. BC
reviewed existing documents for information provided by Zone 7 to identify key design requirements for the
diversion and conveyance structures, including diversion criteria (Section 3.1), fish passage and exclusion
requirements (Section 3.2), diversion locations (Section 3.3), and additional design considerations (Section
3.4).
3.1 Diversion Criteria
After the Site is reclaimed, Lake A, Lake B, and all appurtenant diversion and conveyance structures will be
dedicated to Zone 7 for use in water management. According to a memorandum provided by Zone 7 (August
16, 2013), Zone 7 plans to use these facilities to divert water from Arroyo del Valle into the Chain of Lakes to
“replace loss of water through evaporation, mitigate the concentrations of salts in the water due to evapora-
tion, recharge the groundwater basin, and enhance regional flood protection,” consistent with the objectives
of the Specific Plan.
The Specific Plan (1981) states that “the diversion structure from Arroyo del Valle within Lake A into Lake C
will be capable of diverting at least the first 500 cubic feet per second of flow from the Arroyo.” The Specific
Plan does not explicitly discuss water diversion from Arroyo del Valle to Lake A. This lack of clarity was not an
issue for the 1987 Reclamation Plan because Arroyo del Valle was to continue to flow directly into Lake A
after the site was reclaimed. However, the Amendment (June 2013) calls for the Arroyo del Valle channel to
remain intact adjacent to Lake A and to be restored adjacent to Lake B. Therefore, direct transfer of surface
flow from Arroyo del Valle to the Chain of Lakes would require a diversion structure (see Figure 2).
Figure 2. Surface flows related to Arroyo del Valle and the Chain of Lakes
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
6
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
The existing agreement between Zone 7 and RMC Lonestar (a predecessor to CEMEX) dated March 29,
1988 (Agreement) was developed based on the 1987 Reclamation Plan, which assumed that Arroyo del
Valle would flow through Lake A and called for a diversion structure from Lake A to Lake C that would be
capable of diverting at least the first 500 cubic feet per second (cfs). Given the changes described in the
previous paragraph, CEMEX has been discussing new design criteria with Zone 7 assuming that the diver-
sion will now be located on the Arroyo del Valle channel. In an e-mail from Zone 7 to BC dated August 16,
2013, Zone 7 provided a document containing draft design criteria for the new diversion structure. The
document included the following specific criteria relating to diversion and bypass flow rates:
• Divert the first 500 cfs of water from Arroyo del Valle into the Chain of Lakes in an environmentally
sensitive manner. More specifically:
− Provide the ability to control diverted flow rates in increments of 20 to 25 cfs up to the first 250 cfs
− Provide the ability to control diverted flow rates in increments of 50 to 100 cfs between 250 and
500 cfs
− Divert up to 500 cfs during flood releases greater than 1,000 cfs from Del Valle Reservoir, without
any dams or other obstructions in place
• Provide for controlled bypass flows as follows:
− 1 cfs to 40 cfs in winter/spring
− 6 cfs to 15 cfs in summer/fall
While CEMEX’s actual requirements and obligations are defined by the Agreement, BC investigated the
feasibility of various diversion design options in light of the above-described performance criteria. Section 4
below provides a summary of BC’s findings.
3.2 Fish Passage and Exclusion
The California Department of Fish and Wildlife (CDFW) requires fish passage and fish screening for diver-
sions located within salmon- or steelhead-bearing waters of the state. The National Oceanic and Atmospher-
ic Administration (NOAA) also consults on projects impacting fish habitat where federally listed species such
as steelhead are present.
Arroyo del Valle is a tributary stream to Alameda Creek, which has historically been a spawning area for fish
species including central California coastal rainbow trout/steelhead (Oncorhynchus mykiss) and coho
salmon (Oncorhynchus kisutch) (SFEI, 2013). Fish barriers currently exist on Arroyo del Valle downstream of
the Site; however, in recent years numerous fish passage projects have been constructed on Alameda Creek
and its tributaries to remove barriers to and encourage anadromous fish migration into the upper creek
system. For example, San Francisco Public Utilities Commission (SFPUC) has worked on fish passage and
screening improvements for its diversion dam on upper Alameda Creek, a channel reach identified as having
suitable habitat for steelhead.
Hanson et al. (2004) investigated the current and historical occurrence of steelhead in the Valley for Zone 7.
The report provided the following findings:
• Historically, steelhead passage in Arroyo del Valle occurred infrequently, in response to high flow events
that provided suitable surface water connectivity between Arroyo del Valle and lower Alameda Creek.
• It is unlikely that the Arroyo del Valle watershed historically provided consistent suitable habitat condi-
tions for steelhead passage, spawning, and/or juvenile rearing to support self-sustaining populations.
• Suitable habitat exists for steelhead spawning and rearing in the reach immediately downstream of Del
Valle Reservoir; however, management actions would be required to achieve these benefits.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
7
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
BC contacted CDFW regarding permitting requirements for a water diversion structure on Arroyo del Valle.
Based on a conversation with Michelle Lester of CDFW (January 23, 2014), it is too early at this point to
conclude that fish screens or passage will be required given the uncertainties regarding the quantity and
size of the diversion, as well as uncertainty regarding the suitability of the habitat.
Fish habitat studies are ongoing, and new information will become available in the coming years. According
to CDFW, Zone 7 recently commissioned a study titled “Arroyo del Valle and Arroyo de la Laguna Steelhead
Habitat Assessment”; however, this study has not yet been finalized. In a related effort, the Alameda Creek
Alliance is working with Zone 7 and several other agencies to assess instream flows for migratory fish in
Arroyo del Valle. According to the Alameda Creek Alliance Web site:
The Alameda Creek Alliance is working with 16 agencies conducting studies and modeling to determine the range, timing, duration, frequency, and location of the water flows needed to restore the steelhead fishery in Alameda Creek. The Alameda County Water District is nego-tiating with regulatory agencies to determine appropriate bypass flows for future fish ladders in the lower watershed. In the northern watershed, the Alameda Creek Alliance has prompt-ed Zone 7 Water Agency to begin assessing instream flows for migratory fish in Arroyo Mo-cho, Arroyo del Valle and Arroyo de la Laguna through Livermore and Pleasanton.3
Notwithstanding the uncertainties discussed above, for this feasibility study, BC will assume that a diversion
structure on Arroyo del Valle will need to meet requirements for anadromous fish passage and screening.
Specific criteria are described as follows:
• Fish passage: Cross-channel structures should include a passable flow bypass structure, and off-channel
flow diversions should include return flow channels to avoid trapping.
• Bypass flows: In the draft design criteria document cited previously, Zone 7 requested that the Arroyo del
Valle diversion allow for controlled diversion bypass flows of up to 40 cfs in winter/spring and 15 cfs in
summer/fall (e-mail correspondence on August 16, 2013).
• Fish screening: CDFW criteria require fish screens to be sized such that the approach velocity entering
the screen does not exceed 0.33 feet per second (ft/s) for all self-cleaning screens located in on-stream
installations. For screens without automatic cleaning, the approach velocity is limited to one-fourth of the
self-cleaning screens. Fish screens are typically sized by dividing the desired diversion flow (e.g., 500 cfs)
and the limiting approach velocity (e.g., 0.33 ft/s), which results in the minimum area of fish screen re-
quired. For example, a 500 cfs diversion limited to 0.33 ft/s approach velocity would require at least
1,515 square feet (ft2) of fish screen. The U.S. Bureau of Reclamation (USBR) (2006) recommends the
use of a 10 percent safety factor, which would increase the required area in this example to 1,667 ft2.
These criteria should be revisited during detailed design as part of consultation with CDFW. It may be
feasible to request a variance from CDFW for the approach velocity restrictions during certain times of year
when fish fry are not present. For example, with such a variance, a diversion structure designed to screen
210 cfs at 0.33 ft/s approach velocity during periods when fry may be present could also be used to screen
500 cfs at 0.8 ft/s (maximum velocity allowed by CDFW) during periods of the year when anadromous fish
fry are not present (likely during summer and fall).
3.3 Diversion Location
Locating the diversion structure at the east end of Lake A (i.e., the most upstream location along Arroyo del
Valle) would provide the most design flexibility in terms of elevations and hydraulic head. However, in
3 Discussion of “Key Accomplishments, Stream Flows for Native Fish” on the Alameda Creek Alliance Web site at:
http://www.alamedacreek.org/about-us/key-accomplishments.php.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
8
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
conversations with Zone 7, and in the August 2013 draft design criteria document, Zone 7 has requested
that the diversion be located “as close to Isabel Avenue/[Highway] 84 as possible” and that any impound-
ments at the diversion would “avoid [creating] large pools that stretch under Vallecitos Bridge and into
Sycamore Grove Park.” BC addressed the latter concern with preliminary hydraulic modeling of the Arroyo
del Valle channel, which found that “an in-channel diversion with an obstruction as high as 10 feet at the
upstream end of Lake A [approximately 1,100 feet downstream of Vallecitos Road] would increase water
surface elevations in the vicinity immediately upstream of the diversion; however, those increases diminish
rapidly and are negligible beyond Vallecitos Avenue.” (BC, February 2014). Therefore, flooding impacts
upstream of Vallecitos Road are not considered to be a constraint as long as the proposed diversion struc-
ture does not include an in-channel obstruction greater than 10 feet in height.
For the purposes of this feasibility study, BC initially assumed that the diversion would be located at the east
end of Lake A because it provides the most design flexibility. However, after the preferred alternative was
selected (see Section 5), BC compared elevations along Arroyo del Valle to Lake A water levels to determine
if there is potential for moving the structure downstream (see Section 6).
3.4 Additional Design Considerations
BC identified additional design considerations based on discussions with Zone 7 and Alameda County. The
following conditions should be considered when screening options and comparing alternatives:
• The proposed diversion project should avoid increased flooding risks to nearby residences and infra-
structure, such as Vallecitos Road, and including Sycamore Grove Park.
• The proposed diversion project should minimize channel disturbance and visual impacts, and preserve
the riparian nature of the area for future park and trail access.
• The proposed diversion project should minimize both capital and long-term maintenance costs.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
9
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Section 4: Options Investigation The Arroyo del Valle diversion system will consist of several interrelated components. The schematic repre-
sentation shown in Figure 3 identifies six major components as follows:
1. Intake and fish exclusion: Water is diverted
away from the Arroyo del Valle channel
through an intake structure that incorpo-
rates a device (e.g., screen) to prevent fish
from being captured or trapped by the di-
version. Section 4.1 describes several op-
tions, discusses preliminary sizing, and
identifies up to three options for further
evaluation as alternatives (Section 5).
2. Hydraulic grade control: Upstream water
levels are raised to create controlled hy-
draulic head for diversions and bypass
flows. Section 4.2 describes several op-
tions and then identifies a preferred option
based on an initial screening assessment.
3. Fish passage and/or bypass: This compo-
nent allows fish to pass any physical barri-
ers created by the hydraulic grade control
structure. Section 4.3 describes several
options and then identifies a preferred op-
tion based on an initial screening assessment.
4. Diverted flow control structure: This structure is used to control flow through the intake, and should
include a device to adjust release rates (e.g., gate or valve) and a device to measure the discharge (e.g.,
a weir or flume). BC develops recommendations for these devices as part of the description of the pre-
ferred alternative (Section 6). Specific equipment should be evaluated as part of the detailed design.
5. Conduit into Lake A: This component consists of a pipeline and/or open channel to convey diverted
water into Lake A. BC develops recommendations for this conveyance structure as part of the description
of the preferred alternative (Section 6).
6. Conduit from Lake A to Lake C: This component consists of a pipeline to convey water from Lake A to
Lake C. Evaluations and recommendations for this component are not included as part of the conceptual
design presented in this document, but will be addressed in a subsequent document.
Sections 4.1 through 4.3 below discuss options for components 1 through 3 described above.
4.1 Intake and Fish Exclusion Devices
A variety of methods and devices have been used to exclude fish from diversions on anadromous fisheries.
The USBR Water Resources Technical Manual, Fish Protection at Water Diversions (USBR, 2006) presents a
summary of typical options. Selection of an appropriate method depends on many factors such as diversion
discharge, stream channel characteristics, fish species present, anticipated operational scenarios, and
hydraulic grade and control capabilities.
BC identified two basic approaches to diverting flow while excluding fish:
• Fish screening: This commonly used approach uses barriers to prevent fish from entering into diversion
channels or intakes.
Figure 3. Schematic representation of diversion system
Although not part of the Arroyo del Valle diversion system, a conveyance
connection is shown between Lake B and Lake C; this represents the planned
installation of a 30-inch-diameter pipe, consistent with the Specific Plan and
the 1988 Agreement between Zone 7 and RMC Lonestar.
23
1 54
6
LAKE B LAKE C
LAKE A
AR
RO
YO D
EL V
ALL
E
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
10
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• Infiltration and seepage: This approach precludes the need for fish screens by transmitting water
through gravel or other permeable media.
These approaches are described in more detail in the following sections.
4.1.1 Fish Screening
Figure 4 illustrates the process BC used to select fish screening options based on our understanding of
CDFW’s preferences and the flow conditions in Arroyo del Valle.
Figure 4. Decision flow chart for selecting fish screen options
Text shaded in gray indicates options that were eliminated from further consideration.
Two general types of fish protection are typically employed at water diversions: positive barrier screens (e.g.,
fish screens) and behavioral barriers (e.g., lights, bubble curtains, sound, etc.). Because behavioral barriers
are less proven, less effective, and less favored by regulatory agencies, we eliminated them from further
consideration. Alternatives for fish protection presented herein include only positive barrier screens.
Positive barrier screens can be further divided based on their location relative to the main channel:
• On-stream barriers are located within the main channel of the watercourse and are typically along the
channel bank (see Figure 5).
• Off-stream or in-canal barriers are located within a side channel or canal; fish that enter the diversion
channel/canal are screened and then directed back into the main channel through a return channel or
bypass pipe (see Figure 6).
The CDFW fish screen criteria specifically state that CDFW prefers on-stream fish screen placement where
feasible. On-stream systems typically create fewer disturbances to the fish species of concern because they
do not remove fish (even temporarily) from the existing stream. Although off-stream placement may be
feasible for the Arroyo del Valle diversion, BC selected on-stream placement as the preferred configuration
for this evaluation due to CDFW’s preference.
Positive Barriers (physical screen barriers)Provides proven protection.
Behavioral Barriers (Lights, bubble curtains, sounds)
Less proven, generally not favored by CDFW.
On-streamKeeps fish in the stream.
Preferred by CDFW.
Off-stream/In-canalRequires fish bypass into downstream
area to avoid trapping. CDFW calls for on-
stream barriers to be used where feasible.
Linear Inclined ScreenRequires more bank length, but less
footprint in channel. Diversion amount
depends on screen submergence.
Submerged ScreenRequires greater footprint in channel, but can be
somewhat modular. Once submerged, diversion rate
does not vary. More expensive than linear screen.
Fish Screen Selection
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
11
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Figure 5. Example of an on-stream fish screen (USBR, 2006)
Wilkens Slough fish screen system on the Sacramento River has a screen length of 225 feet and was designed to divert 700 cfs (capable of diverting
up to a maximum of 830 cfs) given substantial flow depths in the range of 11 to 25 feet (USBR, 2006).
Figure 6. Examples of an in-canal fish screen (USBR, 2006)
Schematic (left) shows typical in-canal fish screen, including bypass pipe
to direct fish back to river. Highline Canal on right uses two V-shaped fish screens.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
12
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
4.1.1.1 Options for On-Stream Screening
Fish screens can be constructed as flat-plate linear screens or modular submerged screens. Figure 7 shows
an example of a linear screen designed for Savage Rapids Diversion Dam near Grants Pass, Oregon. Figure
8 shows cylindrical submerged screens that have been installed by Alameda County Water District in lower
Alameda Creek. Figure 9 shows conical submerged screens installed by Santa Clara Valley Water District.
Both linear and submerged screens are typically equipped with automated screen cleaning systems that
require electrical power at the site.
Figure 7. Example of inclined linear fish screens (USBR, 2009)
Savage Rapids Diversion Dam near Grants Pass, Oregon.
Figure 8. Example of cylindrical fish screens
Lower Alameda Creek diversion for Alameda County Water District; four 42-inch-diameter by 200-inch-long cylindrical screens used to divert up to
150 cfs when fully submerged.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
13
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Figure 9. Example of conical screens
Kirk Diversion Dam for Santa Clara Valley Water District; two 10-foot conical screens used to divert up to 85 cfs when fully submerged at a depth
of approximately 3 feet above the base of the cone. Images and detail drawing courtesy of Intake Screens, Inc.
4.1.1.2 Preliminary Sizing
Fish screening requirements are often the limiting factor in diversion capacity design due to the screen area
needed to pass the diverted flow without exceeding maximum approach velocities. Screen area depends on
water depth. BC used a HEC-RAS hydraulic model to calculate water surface profiles over a full range of
flows observed in Arroyo del Valle since the construction of Del Valle Reservoir4. Figure 10 shows discharge-
depth and frequency-depth relationships based on the modeling results.
4 The reader should refer to Technical Memorandum 1 (BC, February 2014) for details on hydraulic model development and flow
frequency analyses.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
14
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
(a) Discharge-depth rating curve (b) Frequency-depth
Figure 10. Hydraulic depth relationships in Arroyo del Valle near east end of Lake A
Hydraulic depth data based on HEC-RAS modeling results at Station 246+03.
Refer to Technical Memorandum 1 (BC, February 2014) for details on hydraulic model development.
The data shown in Figure 10(b) suggest that, historically, flow depths in Arroyo del Valle are less than 1 foot
about 90 percent of the time and rarely get above 2 feet. If larger flows such as 500 or 1,000 cfs are
released from Del Valle Reservoir for the purposes of diversion, then flow depths increase to approximately
2.5 or 3.3 feet, respectively (see Figure 11).
Figure 11. Existing Arroyo del Valle channel geometry near east end of Lake A
Water surface elevations for 500 and 1,000 cfs based on HEC-RAS modeling results at Station 246+03.
Refer to Technical Memorandum 1 (BC, February 2014) for details on hydraulic model development.
0
1
2
3
4
5
6
0 1,000 2,000 3,000 4,000
Flo
w D
ep
th (
ft)
Discharge (cfs)
0
1
2
3
4
5
6
0% 20% 40% 60% 80% 100%
Flo
w D
ep
th (
ft)
Percent Time Exceeded
400 450 500
432
434
436
438
440
442
Station (ft)
Ele
vation
(ft)
500 cfs
1000 cfs
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
15
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Zone 7 requested that the proposed diversion structure “divert up to 500 cfs during flood releases greater
than 1,000 cfs from Del Valle Reservoir, without any dams or other obstructions in place.” BC used the
depth associated with a 1,000 cfs flow condition (3.3 feet) to do a preliminary fish screen sizing calculation
(see Table 2). However, it should be noted that this calculation assumes a constant depth of 3.3 feet over
the fish screen(s). In reality, the flow depth would decrease as water is drawn from the channel unless a
hydraulic grade control structure is in place. Nevertheless, the calculation in Table 2 provides insight regard-
ing sizing feasibility. Additional discussion regarding the need for hydraulic grade control is provided in
Section 4.2.
Table 2. Preliminary Sizing for On-Stream Fish Screen Options
Screen option
Maximum
approach
velocity
Unit diversion
capacity at a depth of
3.3 feet
Size needed to
divert 500 cfs
Approximate
length of stream
bank needed for
installation
Notes
Linear/flat-panel 0.33 ft/s 1.1 cfs per linear foot 459 linear feet 460 feet Assume vertical screen panel, an inclined
screen could provide additional capacity
Cylindrical 0.33 ft/s 28 cfs per 36-inch unit 18 cylinder
screens 264 feet
36-inch unit is 13 feet 8 inches long; assume
minimum of 1 foot of space between units
Conical 0.33 ft/s 56 cfs per 14-foot unit 9 conical screens 144 feet Assume minimum of 2 feet of space between
units
Notes: 1. Velocity criterion based on CDFW requirements for a fish screen with automated cleaning; no safety factor applied.
2. A constant flow depth of 3.3 feet was assumed; a hydraulic grade control structure may be necessary to maintain this condition.
The results shown in Table 2 indicate that fish screens designed to divert up to 500 cfs will require a sub-
stantially large structure stretching from at least 144 feet to as much as 460 feet along the stream bank.
For reference, the diversion shown in Figure 8 has a 150 cfs capacity, and the diversion in Figure 9 has an
85 cfs capacity. Diversions as large as 500 cfs are typically located on considerably larger watercourses. For
example, the 500 cfs Red Bluff diversion is located on the Sacramento River (see Figure 12).
Figure 12. Example of a 500 cfs diversion using conical screens
Red Bluff Pumping Plant on the Sacramento River; images courtesy of Intake Screens, Inc.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
16
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
4.1.2 Infiltration and Seepage
A second approach to diverting water away from Arroyo del Valle would be to collect water through infiltra-
tion, percolation, and/or seepage. Two basic methods were investigated as described below.
4.1.2.1 Infiltration Gallery
An infiltration gallery uses perforated conduits that are buried in gravel to facilitate rapid infiltration and sub-
surface drainage through a permeable gravel layer along the stream bottom and/or bank (see Figure 13).
Although infiltration rates would need to be relatively high, they would still be well below the approach
velocity criterion for fish screening, thereby replacing the need for a fish screen.
Figure 13. Conceptual sketch of a lateral infiltration gallery
Sizing and Feasibility Considerations. Infiltration galleries are commonly used for low flow applications, but
could be expanded beyond typical applications by adding more laterals. Preliminary sizing calculations were
performed using an equation from USBR (1995):
� = ��� �2� 2��
where:
L is the computed length of screen to yield desired discharge (ft) Q is the desired discharge (cfs)
r is the radius of the drainage pipe
K is the permeability coefficient for the gravel fill (ft/s)
H is the depth of water over the gravel fill (ft)
d is the distance from the ground surface to the center of the drain pipe (ft)
Assuming a desired flow rate of 500 cfs, permeability coefficient of 0.04 ft/s, 1-foot diameter pipe, 3-foot
depth of pipe, and 1-foot depth of water, the required screen length comes out to be approximately 3,565
feet. This could be accomplished using many parallel drainage pipes; for example, thirty-six 100-foot pipes. If
the pipes are placed approximately 5 feet apart, the length of the infiltration bed along the stream bank
would be 200 feet. Thus, the infiltration bed would have a surface area of 20,000 ft2. A diversion rate of 500
cfs over an area of 20,000 ft2 would result in an inflow velocity of approximately 0.025 ft/s across the
surface of the infiltration bed and a pore velocity of 0.08 ft/s, assuming a porosity of 0.3 for the gravel in the
bed. Thus, the inflow velocity would be much less than what would occur for the fish screens evaluated in
Section 4.1.1.2, above.
Infiltration galleries are commonly used in conjunction with pumps to convey water to higher elevations.
However, at the selected diversion site, elevation drop from the Arroyo del Valle channel to Lake A is ade-
quate for drainage and conveyance pipes to be sloped to allow for gravity flow, substantially reducing
operation and maintenance (O&M) requirements.
INFILTRATION
OUTFLOW
GRAVEL
PERFORATED PIPE
STREAM CHANNEL
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
17
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
4.1.2.2 Permeable Berm
A berm (i.e., levee or dike) could be constructed along the stream bank using high-permeability gravel or rock
to facilitate seepage from Arroyo del Valle into Lake A (see Figure 14). The flow on the down-gradient side
would need to be collected and conveyed to the lake using a collector channel or drainage piping. As with
the infiltration gallery, flow into and through the berm would likely be well below the approach velocity
criterion for fish screening.
Figure 14. Conceptual sketch of a permeable berm
Sizing and Feasibility Considerations. Preliminary sizing calculations were performed by estimating seepage
through a gravel berm using the Schaffernak-Van Iterson method as described in the U.S. Army Corps of
Engineers Seepage Analysis and Control for Dams manual (USACE, 1986). The following equations were
used:
� = �cos� − � ��cos� � − ℎ�sin� �
� = �� sin� tan�
where:
q is the seepage discharge per unit width (cfs)
k is the permeability of the berm (ft/s)
all other parameters are defined by the sketch shown in Figure 15
Figure 15. Definition sketch for calculating berm seepage (USACE, 1986)
OUTFLOW SEEPAGE
STREAM CHANNEL
GRAVEL/ROCK BERM
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
18
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
A variety of berm configurations, water depths, and permeability coefficients were evaluated, and all resulted
in unit discharge rates in the range of 0.05 to 0.20 cfs per foot of berm. These values result in berm lengths
of 2,500 to 10,000 feet to attain diversion rates of as high as 500 cfs. Based on these results, the permea-
ble berm option is considered to be infeasible.
4.1.3 Selection of Options for Further Evaluation
BC selected three options for further evaluation based on the preliminary sizing and feasibility findings
described in the previous sections. Selected options and justification are as follows:
• Linear screen: This option was selected because of its simplicity and flexibility in design. For example,
the screen area can be increased indefinitely with hydraulic depth, while cylindrical screens or conical
screens are limited once submerged.
• Conical screens: This option was selected because it is a widely used, proven technology and is available
in modular manufactured units. Conical screens were selected over cylindrical screens because they
provide more screen area at shallow depths and require less bank area for installation.
• Infiltration gallery: This option was selected because it precludes the need for fish screens and has the
potential to divert 500 cfs with relatively low hydraulic head.
Design alternatives based on each of these options are evaluated in Section 5.
4.2 Hydraulic Grade Control Structure
Hydraulic grade control structures are typically used to impound water and provide controlled hydraulic head
at open-channel diversions. This is particularly important in streams like Arroyo del Valle with low base flows
and shallow ordinary water depths. As discussed in Section 4.1.1.2, even if 1,000 cfs is flowing in Arroyo del
Valle, a hydraulic grade control structure would be necessary to maintain a constant depth across the
intake/fish screening structure. Furthermore, both the Specific Plan and the 1988 Agreement between Zone
7 and RMC Lonestar, a predecessor to CEMEX, state that the diversion structure should have the capability
to divert the first 500 cfs from Arroyo del Valle. Subsequent correspondence from Zone 7 also includes the
need to provide controlled bypass flows in the range of 6 to 40 cfs (see Section 3.1.1). To achieve both the
diversion and bypass flow criteria, a hydraulic grade control structure would be needed to provide sufficient
hydraulic head to divert 500 cfs while discharging only a small bypass flow downstream.
The following subsections describe several potential options for providing hydraulic grade control, followed
by a discussion of sizing and feasibility.
4.2.1 Design Options
The following paragraphs describe several options for hydraulic grade control structures, ranging from simple
to complex. The reader should note that the options presented below were selected based on hydraulic
needs and spatial constraints; however, focused geotechnical investigations regarding site suitability have
not been conducted at this time. Geotechnical investigations are necessary for the design of any structure
that impounds water and will need to be conducted prior to detailed design.
Rock Weir
Although not commonly used for this purpose, large rock structures placed within the channel can create
backwater conditions that form pools upstream. Rocks can be placed in various configurations such as U-
shaped weirs or cross-vanes, which funnel water toward the middle or one side of the channel. At low flows
water would be concentrated into one or more narrow flow paths through the rock structure to maintain fish
passage. The reader should note that the increases in upstream water surface elevations are relatively small
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
19
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
and have relatively little effect during large flows. Figure 16 shows two examples of in-channel rock struc-
tures that pool water upstream.
Figure 16. Examples of in-channel rock structures that could pool water upstream
Left: Big Springs 3 Diversion Enhancement Project (image and information obtained from http://www.usbr.gov/river/pahsimeroi.html).
Right: image from USBR and obtained from an online presentation by NOAA titled “Fish Passage Design for Boulder Weirs”
(http://www.cbfwa.org/Committees/FSOC/meetings/2010_0913/PresentationFSOC_2010_BoulderWeirs.pdf).
Flashboard Weir
Flashboard weirs have long been used to impound and divert water, providing a simple and adjustable way
to control flows. Upstream water levels are manually adjusted in board-size increments by adding or remov-
ing boards from slotted sections. Although simple and cost-effective, the need for manual adjustments can
be a problem when changes need to be made quickly; for example, if boards need to be removed on short
notice prior to a flood event or large flow release. In addition, flashboard weirs often create fish barriers and
necessitate the addition of a side channel or fish ladder. Figure 17 shows an example of a flashboard weir.
Figure 17. Example of a flashboard weir used to impound water on a stream
(Images obtained from: http://www.oart.org.uk/projects/morph-buxted.htm)
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
20
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Inflatable Rubber Dam
Inflatable rubber dams are used at numerous locations by Alameda County Water District in lower Alameda
Creek and other sites throughout the Bay Area. They are able to deflate and collapse to a low profile when
not in use. Operators can inflate or deflate the bladder to control water levels; however, these dams do not
provide precise controls and water releases cannot be controlled laterally across the dam. A level concrete
foundation is typically required within the channel and on the channel bank. A side channel or fish ladder is
likely necessary to allow for fish passage during periods when the dam is inflated. Figure 17 shows an
example of an inflatable dam from an installation on Alameda Creek.
Figure 18. Example of an inflatable rubber dam
Lower Alameda Creek diversion for Alameda County Water District; the dam spans the entire channel, which is roughly 400 feet wide.
(Images obtained from: http://mrbill.homeip.net/albums/mt_hamilton.2011.04.16/pages/page_64.html)
Pneumatic Gates
Pneumatically actuated gates, such as the ones manufactured by Obermeyer Hydro, can be raised to control
upstream water levels when needed, and collapsed to a low profile when not in use. The gates can be
installed in modular sections to allow operators to laterally adjust gate heights and release flow at various
locations along the structure. Substantial channel disturbance, including concrete foundations and the
pneumatic gates (which cannot easily be removed during low flow periods), are necessary. A side channel or
fish ladder is likely necessary to allow for fish passage during periods when the gates are raised.
Figure 19. Examples of pneumatically actuated (Obermeyer) gates
(Images from Obermeyer Hydro, information can be obtained at http://www.obermeyerhydro.com/)
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
21
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Low-Head Concrete Diversion Dam
Low-head concrete dams have been used for river and stream diversions for many years. According to USBR
(1987), a low concrete gravity dam can be founded on alluvial foundations if adequate cutoffs are provided.
Therefore, this option is considered viable for conceptual design purposes; however, additional geotechnical
investigations will need to be conducted as part of the detailed design to confirm site suitability. Figure 20
shows two examples of low-head concrete diversion dams.
Figure 20. Examples of low-head concrete diversion dams
Left: Youngs Creek hydropower facility constructed for Snohomish County Public Utility District in 2011 (photo used with permission).
Right: Kyburz Diversion Dam and fish bypass (left in photo) owned by the El Dorado Irrigation District (photo used with permission).
Historically, low-head concrete diversion dams have created barriers to fish; however, under current regula-
tions, a side channel or fish ladder would typically be required. Concrete dams can be used in conjunction
with weirs, gates, and flumes to provide precise controls of water surface elevations and diversion flow rates,
as well as bypass flows and overflow rates. Natural earth materials, such as boulders or riprap, can also be
incorporated into the dam surface to visually blend into the streambed and riparian environment.
4.2.2 Options Screening
The options described in the previous section cover a wide range of structures with the potential for numer-
ous design variations. Selection of the best option will depend on site suitability, operational flexibility,
potential impacts to fish and riparian habitat, and cost. Table 3 provides a general summary of some of
these key design considerations for each type of hydraulic grade control structure.
Table 3. Comparison of Hydraulic Grade Control Options
Type
Design considerations
Sizing and spatial constraints Operational flexibility Fish habitat/riparian impacts Cost
Rock weir • Typically used for small to medium streams
• Rock placed in channel to create pool, but height is limited and upstream water surface increases are relatively small
• Highly scalable; size and number of rocks can be adjusted to channel dimensions
• Passive structure that does not provide precise control of water levels
• Minimal head difference provides limited diversion capacity
• Natural materials reduce visual impacts
• Does not require large founda-tions or cutoff walls
• Rock structures are typically low head and placed such that water is funneled into a narrow channel that is fish-passable at low flows
Low to moderate
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
22
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Table 3. Comparison of Hydraulic Grade Control Options
Type
Design considerations
Sizing and spatial constraints Operational flexibility Fish habitat/riparian impacts Cost
Flashboard weirs
• Typically used for small to medium streams with relatively low head differentials
• Flashboard weirs are installed in slotted segments allowing the structure to span wide channels if necessary
• Upstream water levels are manually adjusted in board-size increments
• Manual removal can be difficult under significant head pressure and could require equipment
• Boards can be difficult to seal and often result in leakage
• Requires foundation and frames to hold flashboards
• A fish passage structure is likely necessary if flashboards cross entire channel
Moderate
Inflatable rubber dam
• Manufactured in various sizes, but most often used in medium to large streams
• Upstream water depths can range from a few feet to greater than 10 feet
• Operators have some/limited adjustment of water levels by inflating/deflating the bladder
• Overflow discharge location cannot be adjusted laterally across channel
• Bladder can be deflated or removed to minimize obstruction when not in use
• Requires concrete foundation
• Must be deflated and/or removed when not in use
• Fish passage structure is required for periods when dam is inflated
• Fish passage structure may also be needed to bypass foundation given the potential for very low seasonal flows
High
Pneumatic gates
• Gate systems are modular, which allows for installations of various widths
• Typically used for medium to large streams that are several hundred feet wide
• Upstream water depths can range from a few feet to greater than 10 feet
• Operator can control heights of specific gate sections to vary ponded water levels
• Gates can also be adjusted laterally to direct overflow dis-charges to one side of channel or the other
• Bladders can be deflated and gates can be lowered to low profile to minimize obstruction when not in use
• Requires concrete foundation and substantial channel disturbance for installation
• A fish passage structure is likely necessary for periods when gates are up
• Fish passage structure may also be needed to bypass foundation given the potential for very low seasonal flows
Very high
Low-head concrete diversion dam
• Diversion dams can be construct-ed with concrete, providing a high degree of flexibility in terms of size, shape, and configuration
• Can be engineered to provide precise controls of water surface elevations and diversion flow rate
• Often used in conjunction with weirs, gates, and/or flumes
• Likely to be constructed with concrete foundation, sill, and cutoff walls; however, natural features such as rocks could be incorporated into the design
• Cross-channel structure likely to be a fish barrier, thus requiring a fish passage structure
Moderate to very high
Based on the above design considerations, a low-head concrete diversion dam was selected as the pre-
ferred option, given the flexibility of the design, low operation and maintenance, potential for incorporating
natural rock features, and moderate cost. The other options were eliminated based on the following consid-
erations:
• Rock weir: Although a rock weir would be a good option from a cost and fish habitat standpoint, it
provides only a minimal head increase for the upstream diversion intake. More importantly, it would not
allow for precise control and measurement of low flows for controlled bypass.
• Flashboard weirs: Although flashboard weirs are highly adjustable, special equipment is often required
to remove boards due to hydraulic pressure head and safety concerns. Such equipment could require
additional infrastructure for access.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
23
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• Inflatable dam: Although an inflatable dam can be deflated or removed when it is not needed, the
construction cost and long-term maintenance costs would be substantial. Installation of the concrete
foundation would result in substantial bed and bank disturbance, and unlike a concrete diversion dam,
rocks cannot be incorporated into the design to provide a more natural riparian appearance.
• Pneumatic gates: Although pneumatic gates provide operational flexibility, the construction cost and
long-term maintenance costs would be substantial. Installation of the concrete foundation would result
in substantial bed and bank disturbance, and unlike a concrete diversion dam, rocks cannot be incorpo-
rated into the design to provide a more natural riparian appearance.
4.3 Fish Passage or Bypass Structures
As discussed in the previous section, a cross-channel hydraulic grade control structure such as a low-head
concrete diversion dam would require provisions for fish passage. The following subsections describe some
potential options for fish passage followed by a discussion of sizing and feasibility.
4.3.1 Design Options
Numerous options are available for fish passage structures. A useful summary of options is presented in
Anadromous Salmonids Passage Facility Design, National Marine Fisheries Service, Northwest Region, 2011
(NMFS, 2011) and by Thorncraft and Harris (2000). Three different types are described below, ranging from
simple to complex.
Bypass Channel
Bypass channels are low-gradient earthen or rocky channels that mimic the structure of natural streams to
allow for fish passage. Bypass channels typically include bends and/or meanders to decrease the gradient
and maintain sufficient flow depth for fish passage. Figure 21 shows two examples of rock-lined fish bypass
channels.
Figure 21. Examples of fish bypass channels
(Images obtained from http://www.co.pierce.wa.us/index.aspx?NID=1850 and
http://www.biotactic.com/Northern_Pike_Telemetry_and_Passage.htm)
Rock Fishway
Rock fishways are similar to rock-lined bypass channels, but are typically shorter with a more “ramped” (i.e.,
steeper) gradient. According to Thorncraft and Harris (2000), rock-ramp fishways were developed as a low-
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
24
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
cost alternative to more formally engineered fishway designs, and are particularly well-suited for low barriers.
Figure 22 shows a conceptual sketch of a rock ramp fishway from Thorncraft and Harris (2000).
Figure 22. Conceptual layout of a partial-width rock ramp fishway
(Image obtained from Thorncraft and Harris, 2000)
Vertical-Slot Fish Ladder
Vertical-slot fish ladders are widely used to provide fish passage for salmon and steelhead (NMFS, 2008).
These structures consist of a rectangular concrete channel with a series of narrow vertical slots and pools
(see Figure 23). Structures can be designed to achieve specific velocities depending on the fish species of
interest and can operate under variable headwater and tailwater levels. Figure 24 shows a conceptual
sketch of a vertical-slot fish ladder from Thorncraft and Harris (2000).
(a) 3-dimensional view (b) plan view
Figure 23. Sketch of a vertical-slot fish ladder (NMFS, 2011)
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
25
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Figure 24. Example of vertical-slot fish ladder
(Image obtained from Thorncraft and Harris, 2000)
4.3.2 Options Screening
Selection of the best option for fish passage or bypass depends on spatial constraints, operational flexibility,
fish passage/habitat benefits, and cost. Table 4 provides a general summary of some of these key design
considerations for each type of fish passage or bypass structure.
Table 4. Comparison of Fish Passage and Bypass Options
Type
Design considerations
Sizing and spatial constraints Operational flexibility Fish passage benefits Cost
Bypass channel • Requires space outside the main channel to create a low-gradient bypass channel alignment
• Bypass flows of 40 cfs could require a channel that is roughly 1 to 2 feet deep and10 to 20 feet wide
• Bypass flow rates would need to be controlled using a secondary control structure
• Hydraulic conditions are highly variable with bypass rates
• May require maintenance for erosion and/or sedimentation
• Intended to mimic the structure and function of natural streams
Moderate
Rock fishway • Requires space downstream of dam to accommodate ramp-down at 20:1 slope
• Bypass flows of 40 cfs could require a channel that is roughly 1 to 2 feet deep and 8 to 12 feet wide
• Bypass flow rates would need to be controlled using a secondary control structure
• Hydraulic conditions are highly variable with bypass rates
• Large fish may require relatively high bypass flows to be passable
• Not widely used
Moderate
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
26
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Table 4. Comparison of Fish Passage and Bypass Options
Type
Design considerations
Sizing and spatial constraints Operational flexibility Fish passage benefits Cost
Vertical-slot fish ladder
• Requires space along one of the dam abutments and in the chan-nel just downstream of the dam
• Can accommodate a wide range of dam heights
• Bypass flow rates would need to be controlled using a secondary control structure
• Can be designed to accommodate a wide range of bypass flows
• Can be designed to accommodate a wide range of headwater and tailwater elevations
• Design has been used widely and has proved to be effective
• Structure can be designed to meet specific flow conditions (i.e., velocities) for the fish species of interest
High
Based on the above design considerations, a bypass channel, rock fishway, or similar structure was selected
as the preferred option. Although a vertical-slot fish ladder provides some advantages in terms of operation-
al flexibility and performance reliability, the cost is typically very high due to the need for intricate concrete
form work (NMFS, 2008). Furthermore, a rock-lined bypass channel or fishway would help to preserve the
natural riparian conditions of the stream.
4.3.3 Provision for Controlled Bypass Flows
Zone 7 requested that the Arroyo del Valle diver-
sion system provide for controlled bypass flows of
1 to 40 cfs in winter/spring seasons, and 6 to 15
cfs in summer/fall seasons (see Section 3.1). This
can be accomplished by installing a flow meas-
urement device at the entrance to the fish bypass
channel, which would allow operators to estimate
bypass flow rates and adjust diversion rates
accordingly.
One option would be to install a cutthroat flume
(see Figure 25). A flume is preferable to a weir or
orifice because it requires less vertical drop and
has a free surface, thus making it more amenable
to fish passage. A cutthroat flume may be more
suitable than other flumes because it has a flat
floor and functions well under both free flow and
submerged flow conditions. Furthermore, cutthroat
flumes are simple to construct using concrete
forms, or can be obtained in various prefabricated
sizes.
One disadvantage is that cutthroat flumes are typically not as accurate as other flow measurement flumes
unless entrance conditions are carefully controlled. Nevertheless, cutthroat flumes do offer design flexibility
in that they can be scaled to the desired flow range. In addition, multiple flumes could be installed in either
nested or parallel configurations to increase the depth-to-flow ratios for improved accuracy.
Figure 25. Dimensions of a cutthroat flume
A rectangular cutthroat flume has a flat floor and no throat length; the
inlet converges at a 3:1 ratio and the outlet diverges at a 6:1 ratio.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
27
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Section 5: Evaluation of Conceptual Design Alternatives BC developed conceptual design alternatives for the diversion and conveyance of water from Arroyo del Valle
to Lake A based on the design requirements described in Section 3 and the results of the options investiga-
tion in Section 4. Section 5.1 describes each of the conceptual design alternatives. Section 5.2 evaluates
and compares the alternatives based on weighted design criteria.
5.1 Formulation of Alternatives
As discussed at the beginning of Section 4, complete design alternatives consist of an intake with fish
exclusion, hydraulic grade control structure, fish bypass structure, diverted flow control structure, and
conduit into Lake A. Each intake’s fish exclusion mechanism is the key differentiating feature among the
alternatives because that component is the primary driver for the size, flow capacity, and construction and
maintenance costs of the diversion system. Selected options for the remaining components will be common
to all alternatives, and are described below:
• Hydraulic grade control (i.e., diversion dam): As discussed in Section 4.2.2, BC selected a low-head
concrete diversion dam as the preferred method for hydraulic grade control given the flexibility of the
design, low maintenance, potential for incorporating natural rock features, and moderate cost. Concep-
tual design parameters were determined as follows:
− The length of the dam crest is 140 feet (the approximate width of the channel minus estimated
width of the bypass fishway).
− The height of the dam crest varies depending on the alternative; it is calculated based on the head
required to pass the peak diversion capacity plus the head required to discharge minimum flows
through the fish bypass.
• Fish bypass: As discussed in Section 4.3.2, BC selected a bypass channel/rock fishway at the preferred
method for providing fish passage because it preserves the natural riparian conditions of the stream.
Conceptual design parameters were determined as follows:
− The channel/fishway is roughly 2 feet deep and 10 feet wide, assuming a 2 percent slope on the
channel.
− Two cutthroat flumes installed near the entrance to the channel/fishway would measure bypass
flows. A small flume with a throat width of 2 feet is used to pass up to approximately 8 cfs with 1
foot of head. A larger, parallel flume with a throat width of 6 feet is used in combination with the first
flume to pass a total flow of approximately 40 cfs with 1.2 feet of head.
• Diverted flow control structure and conduit into Lake A: These components will be discussed as part of
the preferred design alternative (see Section 6).
Building on these common elements, four different conceptual design alternatives were developed around
the following intake configurations:
1. 100-by-200-foot infiltration bed
2. 400-foot linear screen
3. Two 14-foot-base conical screens
4. Nine 14-foot-base conical screens
While Alternatives 3 and 4 use the same screen option, both were included to provide a comparison of
diversion rates at two different sizes with different impacts to the creek bank. The following sections de-
scribe each of these alternatives in more detail.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
28
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
5.1.1 Alternative 1: Infiltration Bed
For Alternative 1, a 100-foot deep (i.e., extending in the horizontal direction perpendicular to the stream
bank) by 200-foot-long gravel infiltration bed is constructed on the north bank of Arroyo del Valle. The
infiltration bed consists of approximately 4 feet of gravel with forty 100-foot perforated horizontal drain pipes
(laterals) buried at an average depth of 3 feet. Figure 26 shows a schematic sketch of Alternative 1.
Figure 26. Schematic sketch of Alternative 1 (plan view)
Water impounded behind the diversion dam will create a pool that inundates the infiltration bed. When the
flow control gate is open, impounded water will be allowed to infiltrate through the gravel and into the
drainage laterals, which are sloped away from the arroyo toward a manifold. The manifold then connects to a
main conduit that drains by gravity to Lake A.
Key design parameters for Alternative 1 include the following:
• The lowest elevation of the surface of the infiltration bed is set at an elevation of 434.0 feet, approxi-
mately 1 foot above the channel bottom to allow for sedimentation.
• The approach velocity at the surface of the gravel bed is estimated to be 0.023 ft/s at 500 cfs, which is
well below the CDFW fish screening criterion of 0.33 ft/s.
• Assuming the gravel is capable of infiltrating water at a rate of 30,000 gallons per day per square foot
(gpd/ft2), or 0.046 ft/s (i.e., the hydraulic conductivity of the gravel), the infiltration bed could pass 500
cfs at an estimated depth of 0.64 foot (see equation presented in Section 4.1.2.1). Based on this result,
the head required to reach the 500 cfs peak diversion capacity is conservatively assumed to be 1 foot.
• The invert elevations of the bypass cutthroat flumes are set at an elevation of 435.0 feet; this allows
operators to reach maximum diversion capacity without bypassing any flows and thus providing the
greatest operational flexibility.
• The dual cutthroat flumes described previously require 1.2 feet of head to discharge 40 cfs into the fish
bypass; therefore, the minimum elevation of the dam crest is calculated to be 436.2 feet.
• A flow control gate is installed on the outlet conduit to Lake A to control diversion rates.
• Periodic maintenance of the gravel bed will be required to prevent accumulation of fine sediments and
clogging the drainage laterals, which could reduce system capacity over time.
BYPASS FLOW
ROCK FISHWAY
DIVERTED FLOW
GRAVEL INFILTRATION BED
100 FT x 200 FT
ARROYO DEL
VALLE FLOWOVERFLOW
PERFORATED PIPE LATERALS x 40
GRAVEL BED AT 434.0 FT ELEVATION
DAM CREST ELEVATION AT 436.2 FT
2 CUTTHROAT FLUMES
AT 435.0 FT ELEVATION
2-FT, 6-FT THROAT WIDTHS
CHANNEL BOTTOM AT APPROX.
433.0 FT ELEVATION
Not to scale
FLOW ONTO BED
(INFILTRATED)
FLOW CONTROL GATE
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
29
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• Final design must include provisions for maintenance access and safety equipment in accordance with
applicable standards.
5.1.2 Alternative 2: Linear Screen
For Alternative 2, a linear fish screen and housing structure is installed on the north bank of Arroyo del Valle
with a total of 400 linear feet of screen panels inclined at an angle of 45 degrees. Figure 26 shows a
schematic sketch of the Alternative 2.
Figure 27. Schematic sketch of Alternative 2 (plan view)
The diversion dam will impound water to provide up to 3 feet of depth on the screens. When the flow control
gate is open, water will flow through the screen panels into a manifold chamber, then transition to a main
conduit that flows by gravity to Lake A.
Key design parameters for Alternative 2 include the following:
• The screens’ bottoms are set at an elevation of 434.0 feet, approximately 1 foot above the channel
bottom to allow for sedimentation.
• Screens were sized based on the CDFW approach velocity criterion of 0.33 ft/s and a safety factor of 1.1
as follows:
�0.33#$/&1.1 ( )√2+,3#$-,400#$- = 509#$1/&
• The invert elevations of the bypass cutthroat flumes are set at an elevation of 437.0 feet; this configura-
tion allows operators to reach maximum diversion capacity without bypassing any flows and thus provid-
ing the greatest operational flexibility.
• The dual cutthroat flumes described previously require 1.2 feet of head to discharge 40 cfs into the fish
bypass; therefore, the minimum elevation of the dam crest is calculated to be 438.2 feet.
• A flow control gate installed on the outlet conduit to Lake A controls diversion rates.
• An automated screen cleaning mechanism must be included as part of the detailed design to allow the
use of the 0.33 ft/s approach velocity criterion. Operation of the automated cleaning system will require
power at the site.
BYPASS FLOW
ROCK FISHWAY
DIVERTED FLOW
ARROYO DEL
VALLE FLOW
OVERFLOW
BOTTOM OF SCREEN
AT 434.0 FT
ELEVATION
DAM ELEVATION AT 438.2 FT
CHANNEL BOTTOM AT APPROX.
433.0 FT ELEVATION
Not to scale
SCREENED FLOW
SCREEN PANELS (400 LINEAR FEET)
INCLINED AT 45o ANGLE
FLOW CONTROL GATE2 CUTTHROAT FLUMES
AT 437.0 FT ELEVATION
2-FT, 6-FT THROAT WIDTHS
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
30
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• A trash rack or series of bollards and a debris boom are installed to protect the screens from trash and
floating debris.
• Final design must include provisions for maintenance access and safety equipment in accordance with
applicable standards.
5.1.3 Alternative 3: Two Cone Screens
For Alternative 3, two conical fish screens and housing are installed on the north bank of Arroyo del Valle.
The screens have a 14-foot base width and a maximum discharge of 60 cfs per screen (assuming a 0.33
ft/s approach velocity). Figure 28 shows a schematic sketch of Alternative 3.
Figure 28. Schematic sketch of Alternative 3 (plan view)
The diversion dam will impound water to create up to 4 feet of depth over the screens. When the flow control
gate is open, water will flow through both screens into a lateral pipe that flows to a header pipe or manifold
chamber, and then will transition to a main conduit that flows by gravity to Lake A.
Key design parameters for Alternative 3 include the following:
• The bottoms of the screens are set at an elevation of 434.0 feet, approximately 1 foot above the chan-
nel bottom to allow for sedimentation.
• Screens were sized based on the Intake Screens, Inc. specification, which assumes an approach velocity
criterion of 0.33 ft/s, consistent with CDFW requirements.
• The invert elevations of the bypass cutthroat flumes are set at an elevation of 438.0 feet; this allows
operators to reach maximum diversion capacity without bypassing any flows and thus providing the
greatest operational flexibility.
• The dual cutthroat flumes described previously require 1.2 feet of head to discharge 40 cfs into the fish
bypass; therefore, the minimum elevation of the dam crest is calculated to be 439.2 feet.
• A flow control gate installed on the outlet conduit to Lake A controls diversion rates.
• Brushed cone screens, such as the ones manufactured by Intake Screens, Inc., include automated
screen cleaning systems, allowing for the use of the 0.33 ft/s approach velocity criterion. Operation of
the automated cleaning system will require power at the site.
BYPASS
FLOW
ROCK FISHWAY
DIVERTED
FLOW2 x 14-FT CONE SCREENS
ARROYO DEL
VALLE FLOW
OVERFLOW
BOTTOM OF SCREENS AT
434.0 FT ELEVATION
DAM ELEVATION AT 439.2 FT
CHANNEL BOTTOM AT APPROX.
433.0 FT ELEVATION
Not to scale
SCREENED
FLOW
FLOW CONTROL GATE2 CUTTHROAT FLUMES
AT 438.0 FT ELEVATION
2-FT, 6-FT THROAT WIDTHS
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
31
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• A trash rack or series of bollards and a debris boom are installed to protect the screens from trash and
floating debris.
• Final design must include provisions for maintenance access and safety equipment in accordance with
applicable standards.
5.1.4 Alternative 4: Nine Cone Screens
For Alternative 4, nine conical fish screens and housing are installed on the north bank of Arroyo del Valle.
The screens have a 14-foot base width and a maximum discharge of 60 cfs per screen (assuming a 0.33
ft/s approach velocity). Figure 29 shows a schematic sketch of Alternative 4.
Figure 29. Schematic sketch of Alternative 4 (plan view)
The diversion dam will impound water to create up to 4 feet of depth over the screens. When the flow control
gate is open, water will flow through all nine screens into a lateral pipe that flows to a header pipe or mani-
fold chamber, then transitions to a main conduit that flows by gravity to Lake A.
Key design parameters for Alternative 4 include the following:
• The bottoms of the screens are set at an elevation of 434.0 feet, approximately 1 foot above the chan-
nel bottom to allow for sedimentation.
• Screens were sized based on the Intake Screens, Inc. specification, which assumes an approach velocity
criterion of 0.33 ft/s, consistent with CDFW requirements.
• The invert elevations of the bypass cutthroat flumes are set at an elevation of 438.0 feet; this allows
operators to reach maximum diversion capacity without bypassing any flows and thus providing the
greatest operational flexibility.
• The dual cutthroat flumes described previously require 1.2 feet of head to discharge 40 cfs into the fish
bypass; therefore, the minimum elevation of the dam crest is calculated to be 439.2 feet.
• A flow control gate installed on the outlet conduit to Lake A controls diversion rates.
• Brushed cone screens, such as the ones manufactured by Intake Screens, Inc., include automated
screen cleaning systems, allowing for the use of the 0.33 ft/s approach velocity criterion. Operation of
the automated cleaning system will require power at the site.
BYPASS
FLOW
ROCK FISHWAY
9 x 14-FT CONE SCREENS
ARROYO DEL
VALLE FLOW
OVERFLOW
BOTTOM OF SCREENS AT
434.0 FT ELEVATION
DAM ELEVATION AT 439.2 FT
CHANNEL BOTTOM AT APPROX.
433.0 FT ELEVATION
Not to scale
SCREENED FLOW
DIVERTED
FLOW
FLOW CONTROL GATE2 CUTTHROAT FLUMES
AT 438.0 FT ELEVATION
2-FT, 6-FT THROAT WIDTHS
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
32
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• A trash rack or series of bollards and a debris boom are installed to protect the screens from trash and
floating debris.
• Final design must include provisions for maintenance access and safety equipment in accordance with
applicable standards.
5.2 Evaluation of Alternatives
BC compared each of the conceptual design alternatives using a design criteria matrix and a simple
weighted rating system as described in the USACE Institute for Water Resources’ Planning Manual (Yoe and
Orth, 1996). This method allocates point values to selected evaluation criteria, and then scores each
alternative relative to those criteria. This method provides a transparent way to assess qualitative as well as
quantitative criteria, while reflecting value judgments. BC defined the evaluation criteria for the Arroyo del
Valle diversion project as follows:
• Achieve diversion capacity: The proposed diversion system should divert the first 500 cfs of water from
Arroyo del Valle into the Chain of Lakes. In other words, the proposed diversion system should have
enough capacity to divert 500 cfs without letting any flow downstream. Note that the requirement to “di-
vert up to 500 cfs during flood releases greater than 1,000 cfs from Del Valle reservoir, without any
dams or other obstructions in place” was determined to be infeasible because sufficient head depth
could not be maintained across a large diversion structure without hydraulic grade control in place (see
Section 4.1.1.2). Therefore, it was not considered necessary to meet this “diversion capacity” require-
ment.
• Provide operational flexibility: Given the uncertainty surrounding future operating scenarios, operational
flexibility will be important for efficient water management. Therefore, the proposed diversion system
should include an adjustable diversion control structure that will allow operators to divert as much water
as possible while discharging only the minimum required bypass flows downstream. More specifically,
the proposed diversion system should:
− Provide the ability to control diverted flow rates in increments of 20 to 25 cfs up to the first 250 cfs
− Provide the ability to control diverted flow rates in increments of 50 to 100 cfs between 250 and
500 cfs
− Provide the ability to control bypass up to 40 cfs
• Meet fish screening and fish passage requirements: The proposed diversion system should avoid
impacts to fish. CDFW requirements include:
− The intake structure for the proposed diversion system should meet CDFW fish screening criteria by
not exceeding approach velocities of 0.33 ft/s.
− A fish bypass structure should be included to provide passage past the proposed diversion dam.
• Minimize potential for increased flood risk: In TM 1 (February 2014), BC found that “an in-channel
diversion with an obstruction as high as 10 feet at the upstream end of Lake A [approximately 1,100
feet downstream of Vallecitos Road] would increase water surface elevations in the vicinity immediately
upstream of the diversion; however, those increases diminish rapidly and are negligible beyond Valleci-
tos Avenue.” Because all of the proposed dam heights are less than 10 feet, none of the proposed alter-
natives are expected to cause substantial increases in flood risk. Nevertheless, low dam heights are
considered preferable from a relative risk standpoint. Therefore, the alternatives were evaluated based
on their required dam heights.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
33
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• Minimize disturbance and visual impacts: The proposed diversion system should minimize potential
disturbance areas along the channel bed and banks to avoid impacts to riparian areas. Alternatives that
preserve the riparian nature of the area are preferred over ones with larger, more conspicuous features.
• Minimize capital and long-term maintenance costs: The preferred alternative should be cost-effective in
terms of construction cost and long-term O&M costs.
BC evaluated each conceptual design alternative with respect to the above design criteria, and then as-
signed ratings based on the weighted scoring system explained in Table 5. The results of the evaluations are
presented in Table 6, and the composite score for each alternative is graphed in Figure 30.
Table 5. Ratings for Evaluation of Design Criteria
Category Criterion Points available
(out of 100)
Scoring
Rating choices Percentage of points
awarded
Diversion criteria Achieve diversion capacity 20 Yes 100
No 0
Provide operational flexibility 20 Yes 100
No 0
Meet fish screening and fish passage requirements
15 Yes 100
No 0
Additional
considerations
Minimize potential for increased flood risk—based on dam height
15 Less than 4 feet 100
Less than 5 feet 75
Less than 6 feet 50
Less than 7 feet 25
Minimize disturbance and visual impacts 15 Excellent 100
Good 67
Moderate 33
Poor 0
Minimize capital and long-term maintenance costs
15 Excellent 100
Good 67
Moderate 33
Poor 0
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
34
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Table 6. Evaluation of Design Alternatives based on Design Criteria
Alternative Evaluation criteria
Diversion criteria Additional considerations
No. Description
Achieve
diversion
capacity
(20 points)
Provide
operational
flexibility
(20 points)
Meet fish
screening and
fish passage
requirements
(15 points)
Minimize
potential for
increased
flood risk
(15 points)
Minimize disturbance
and visual impacts
(15 points)
Minimize capital and
long-term maintenance costs
(15 points)
1 Infiltration bed
Yes Yes Yes Dam height = 3.2 feet
Rating: Good
• Approximately 200 linear feet of bank would be disturbed for construction of the infiltration bed
• Graded to match surrounding topography; gravel bed consists of natural earth materials
• Visual impacts less than more intrustive screening structures
• Does not require trash rack, bollards, or debris boom
Rating: Good
• Low construction cost relative to other alternatives
• Would require annual cleaning to remove debris and plant growth
• Would require periodic maintenance due to potential for fine sediment to accumulate and cause clogging
2 Linear screen
Yes Yes Yes Dam height = 5.2 feet
Rating: Poor
• Approximately 400 linear feet of bank would be disturbed for construction of the screen system
• Significant bank disturbance and visual impact
• Might require extensive fencing to avoid safety issues and/or vandalism
• Requires trash rack, bollards, and debris boom in streambed
Rating: Poor
• High construction cost relative to other alternatives
• Screens and cleaning system would require significant operation and maintenance
• Would require periodic inspection of and maintenance for mechanical, electrical, and control equipment
• Screen, trash rack, and debris boom would require periodic cleaning
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
35
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Table 6. Evaluation of Design Alternatives based on Design Criteria
Alternative Evaluation criteria
Diversion criteria Additional considerations
No. Description
Achieve
diversion
capacity
(20 points)
Provide
operational
flexibility
(20 points)
Meet fish
screening and
fish passage
requirements
(15 points)
Minimize
potential for
increased
flood risk
(15 points)
Minimize disturbance
and visual impacts
(15 points)
Minimize capital and
long-term maintenance costs
(15 points)
3 Two conical screens
No Yes Yes Dam height = 6.2 feet
Rating: Good
• Approximately 50 linear feet of bank would be disturbed for construction of the screen system
• Somewhat reduced bed/bank and visual impact
• Might require extensive fencing to avoid safety issues and/or vandalism
• Requires trash rack, bollards, and debris boom in streambed
Rating: Moderate
• Moderate to high construction cost relative to other alternatives
• Screens and cleaning system would require significant operation and maintenance
• Would require periodic inspection of and maintenance for mechanical, electrical, and control equipment
• Screen, trash rack, and debris boom would require periodic cleaning
4 Nine conical screens
Yes Yes Yes Dam height = 6.2 feet
Rating: Moderate
• Approximately 150 linear feet of bank would be disturbed for construction of the screen system
• Significant bank disturbance and visual impact
• Might require extensive fencing to avoid safety issues and/or vandalism
• Requires trash rack, bollards, and debris boom in streambed
Rating: Poor
• High construction cost relative to other alternatives
• Screens and cleaning system would require significant operation and maintenance
• Would require periodic inspection of and maintenance for mechanical, electrical, and control equipment
• Screen, trash rack, and debris boom would require periodic cleaning
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
36
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Figure 30. Overall ratings based on weighted evaluation criteria
The results shown in Figure 30 indicate that Alternative 1 is the preferred alternative based on the weighted
scoring system described in Table 5 and the evaluation results summarized in Table 6. Alternative 1 also has
another distinct advantage over the other options, in that the diversion capacity is linearly proportional to the
water depth (or head) above the bed surface (see equation in Section 4.1.2.1). Therefore, as flow rates and
water surface elevations increase in Arroyo del Valle, additional discharge capacity beyond 500 cfs is
available because the approach velocity is well below the CDFW criteria. In contrast, the linear and cone
screen options are limited to a maximum diversion rate of 500 cfs independent of any increase in head
during higher flow events because they are already sized at the approach velocity limit.
Section 6: Recommendations for Preferred Alternative For diverting water from Arroyo del Valle into the Chain of Lakes, BC selected Alternative 1, the infiltration
bed alternative, as the preferred alternative, based on Section 5.2 comparison. Some of the key advantages
of this method include:
• High diversion rates at low hydraulic head
• Lower hydraulic grade control/dam height
• Relatively minor visual impacts
• Relatively low construction cost
• No mechanical or electrical components present in the streambed
• Substantially lower O&M costs
• Significantly reduced potential for safety and vandalism issues
Some of the key disadvantages include:
• Potential for fine sediments to permeate the gravel layer and result in clogging
60
50
63
90
0.0 20.0 40.0 60.0 80.0 100.0
Alternative 4(9 Cone Screens)
Alternative 3(2 Cone Screens)
Alternative 2(Linear Screen)
Alternative 1(Infiltration Bed)
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
37
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
• Sediment, debris, and vegetative growth on top of the gravel bed could reduce permeability requiring
annual maintenance
• Bed covers a large area
These disadvantages are considered to be less significant than those for the other alternatives. Annual
maintenance to remove sediment, debris, and vegetative growth is fairly simple and straightforward. In
addition, even though the bed covers a large area, it will consist of natural earth materials similar in color
and texture to those that exist in the streambed and the bed can be screened with native vegetation around
the perimeter.
Building on the concept presented in Section 5.1.1, BC developed a site layout and additional conveyance
features (Section 6.1), performed preliminary sizing of project elements and prepared a concept-level cost
estimate (Section 6.2), and investigated the potential for moving the diversion structure downstream
(Section 6.3). These sections are followed by recommendations for further study (Section 6.4).
6.1 Conceptual Layout and Conveyance into Lake A
A conceptual site layout of the proposed diversion system with locations of major features is provided in
Figure A-1 (Attachment A). As described previously, the infiltration bed contains forty 100-foot lateral pipes
draining into a header pipe/manifold that then joins into a main conduit. Additional features are specified for
conveyance into Lake A as follows:
• The main conduit begins as an 84-inch-diameter
pipeline, then discharges through an 8-by-8-foot
headgate into an open channel. The headgate
functions as a diversion control structure and can
be raised or lowered to different levels to control
diversion discharge rates.
• From the headgate water discharges into a 10-
foot-wide by 12-foot-deep concrete rectangular
channel, consisting of four sections:
− Stilling basin: dissipates energy and controls
turbulent discharges from the headgate
− Tranquil flow section: develops suitable ap-
proach conditions for the Parshall flume
− Parshall flume section: for flow measurement
(see Figure 31)
− Downstream transition: leads to riprap chute
• The riprap chute downstream of the concrete
channel is a trapezoidal riprap-lined channel that
slopes down steeply into Lake A. A riprap pad con-
tinues below the typical water surface elevation of
412 feet.
6.2 Concept-Level Plans and Cost Estimate
BC developed the conceptual design and performed preliminary sizing calculations to estimate dimensions
and quantities for use in developing a concept-level cost estimate. Figure A-2 (Attachment A) shows a
Figure 31. Dimensional sketch of Parshall flume
(FOA, 1993)
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
38
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
conceptual design plan and Figure A-3 (Attachment A) shows three sections. Conceptual design features and
assumptions (in addition to those discussed in previous sections) are described below:
• The gravel infiltration bed top surface will slope down toward the Arroyo del Valle channel at 0.5 percent
to direct fish toward the channel during times when water levels drop.
• A clay cutoff wall is installed along the edge of the infiltration bed closest to the stream to prevent
horizontal subsurface flow from the channel from draining into the laterals at elevations less than 434.0
feet.
• A geotextile filter fabric should be used to limit the transport of fine sediments and reduce clogging.
• The infiltration bed transitions back to existing grade at a 2:1 slope; use erosion control practices on
exposed slopes and revegetate to stabilize soils.
• Electrical power is required for the sluice gate, which will need to be motorized due to the size.
• A flow meter is installed at the Parshall flume to record diversion rates and potentially provide feedback
to modulate the control gate to achieve the required discharge rate.
• For costing purposes, assume that the low-head dam is formed with a concrete core (e.g., crest, base,
and cutoff walls) and 4:1 sloped rock fill at the upstream and downstream faces.
• Assume 6-foot chain-link fencing installed around the open channel for safety.
• Lateral, manifold, and main pipes were sized using Manning’s equation (see summary of pipe sizes,
Table 7).
Table 7. Summary of Pipe Sizing
Component Material Slope
(percent)
Sizing
Number Diameter
(inches)
Total length
(ft)
Laterals PVC 1 40 12 1,200
PVC 1 40 18 2,800
Manifold PVC 1 2 36 60
RCP 1 2 48 80
RCP 1 2 60 60
Main RCP 2 1 84 30
PVC: polyvinyl chloride; RCP: reinforced concrete pipe. Note that high density polyethylene pipe might be a
suitable substitute for PVC.
Table B-1 (Attachment B) summarizes the concept-level cost estimates for Alternative 1. The total estimated
construction cost is $3.3 million.
6.3 Potential Downstream Location
A substantial ephemeral tributary stream enters Arroyo del Valle about 2,450 feet upstream of Isabel
Avenue. This tributary drains the watershed located south of Lake A and west of Del Valle Reservoir. Zone 7
staff have previously expressed interest in the potential to capture storm flows from this tributary after they
enter Arroyo del Valle and have requested that the diversion be located “as close to Isabel Avenue/[Highway]
84 as possible” (see Section 3.3).
BC investigated the potential for moving the Arroyo del Valle diversion downstream toward Isabel Avenue by
taking the streambed profile and subtracting the head differential needed to convey water and measure
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
39
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
discharge through the diversion system. This differential was conservatively estimated to be approximately 9
feet. The elevation profile was then plotted with the future anticipated average water level in Lake A of 412
feet mean sea level (personal communication between Andrew Kopania, EMKO Environmental, Inc., and
Colleen Winey, Zone 7) to identify where the two lines crossed (see Figure 32). Using this comparison, BC
estimated that diversion locations closer than about 2,970 feet upstream of Isabel Avenue may not provide
enough elevation difference to meet the head requirements.
The results of this assessment indicate that the diversion structure could not be located far enough down-
stream to capture the tributary inflow without substantial modifications to the diversion system to reduce the
hydraulic profile or increase the head behind the grade control structure.
Figure 32. Comparison of required diversion head differential with Lake A water surface
390
400
410
420
430
440
450
460
19000 20000 21000 22000 23000 24000 25000 26000
ELE
VAT
ION
(F
T)
CENTERLINE STATION (FT)
Existing Channel Bottom
Channel minus 9 feet
Lake A Water Surface
Vallecitos Rd Bridge
Isabel Ave Bridge
2,970 FT
ISA
BE
L A
VE
VA
LLE
CIT
OS
RD
TR
IBU
TA
RY
IN
FLO
W
CU
RR
EN
TLO
CA
TIO
N
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
40
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
6.4 Recommendations for Further Study
Detailed analyses of project components were beyond the scope of this study; however, the following studies
should be considered for supporting final design:
• Detailed hydraulic analyses of conduits and open channels, including analyses of pressurized flow and
minor losses, peak flow velocities, rapidly varied flow transitions in the rectangular channel, and en-
trance/submergence conditions related to flow measurement devices
• Geotechnical investigations and dam foundation design
• Stable riprap sizing for rock-lined chute and at the dam face
• Gravel filter design and considerations for reverse flow/flushing system
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
41
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
References Alameda County Community Development Agency (ACCDA), June 2013. Letter from James Gifford to Ron Wilson titled
“Completeness Review of Application to Amend Surface Mining Permit and Reclamation Plan No. 23.”
California Department of Fish and Wildlife, Fish Screening Criteria: http://www.dfg.ca.gov/fish/Resources/Projects/Engin/Engin_ScreenCriteria.asp
California Department of Fish and Wildlife (CDFW), January 2014. Verbal communication between Aren Hanson (Brown and Caldwell) and Michelle Lester of CDFW on January 23, 2014.
California Department of Water Resources, 2001. South Bay Aqueduct (Bethany Reservoir and Lake Del Valle) 4/01. http://www.water.ca.gov/pubs/swp/south_bay_aqueduct__lake_del_valle_and_bethany_reservoir_/south-bay-aque.pdf
EMKO Environmental, 2013. Hydrology and Water Quality Analysis Report, Lake A And Lake B Expansion, CEMEX Eliot Quarry – SMP-23, Pleasanton, California. Prepared by: EMKO Environmental, Inc. 551 Lakecrest Drive, El Dorado Hills, California 95762, June 7, 2013.
Food and Agriculture Organization of the United Nations (FAO), 1993. Field measurement of soil erosion and runoff by N. W. Hudson Silsoe Associates, Ampthill, Bedford United Kingdom Rome. http://www.fao.org/docrep/T0848E/T0848E00.htm
Hanson, Dr. Charles H., August 2004. Evaluation of the Potential Historical and Current Occurrence of Steelhead within the Livermore-Amador Valley. Prepared for Zone 7 Water Agency 5997 Parkside Dr. Pleasanton, CA 94588. Prepared by Hanson Environmental, Inc. 132 Cottage Lane Walnut Creek, CA 94595. http://www.alamedacreek.org/reports-educational/pdf/Zone%207%202004.pdf
Kamman Hydrology & Environmental Engineering, Inc. (Kamman), 2009. Phase 2 Technical Report, Sycamore Grove Recovery Program, Sycamore Grove Park, Livermore, California. Prepared for Livermore Area Recreation and Park District 4444 East Avenue, Livermore, California 94550 and the Zone 7 Water Agency 100 North Canyons Parkway, Livermore, California 94551. Edited by Kamman Hydrology & Engineering, Inc., 7 Mt. Lassen Drive, Suite B250, San Rafael, California 94903.
LSA Associates, 2013. “Results of Biological Surveys, CEMEX Eliot Quarry, Alameda County, California.” Letter to Ron Wilson, CEMEX, 5180 Golden Foothills Parkway, El Dorado Hills, California 95762 from Malcolm J. Sproul, LSA Associates, Inc., 157 Park Place Point, Richmond, California, 94801.
National Marine Fisheries Service (NMFS), February 2011. Anadromous Salmonids Passage Facility Design. National Marine Fisheries Service Northwest Region.
San Francisco Estuary Institute (SFEI), February 2013. Alameda Creek Watershed Historical Ecology Study.
Santa Clara Valley Water District, 2011. Kirk Diversion Dam Replacement and Fish Screen Project, Engineer’s Report.
Spinardi Associates (Spinardi), June 2013. Reclamation Plan Amendment, CEMEX SMP-23, 1544 Stanley Boulevard, Pleasanton, California 94566, Unincorporated Alameda County, Submitted to: Alameda County Community Development Agency Neighborhood Preservation and Sustainability Department, 224 W. Winton Ave, Suite 205, Hayward, California 94544, Prepared by: Spinardi Associates, 265 Sea View Avenue, Piedmont, California 94610
Thorncraft and John H. Harris, May 2000. Fish Passage and Fishways in New South Wales: A Status Report Garry Office of Conservation NSW Fisheries. Sydney Cooperative Research Centre for Freshwater Ecology Technical Report 1/2000
U.S. Army Corps of Engineers (USACE), September 1986. Seepage Analysis and Control For Dams Engineer Manual 1110-2-1901. Department of the Army, U.S. Army Corps of Engineer, Washington, DC 20314-1000.
U.S. Bureau of Reclamation (USBR), 1987. Design of Small Dams, 3rd Edition. 860 pp.
U.S. Bureau of Reclamation (USBR), 1995. Ground Water Manual. Water Resources Technical Publication. U.S. Department of the Interior, Bureau of Reclamation.
U.S. Bureau of Reclamation (USBR), April 2006. Water Resources Technical Publication "Fish Protection at Water Diversions" A Guide for Planning and Designing Fish Exclusion Facilities. U.S. Department of the Interior, Bureau of Reclamation. http://www.usbr.gov/pmts/hydraulics_lab/pubs/manuals/fishprotection/
U.S. Bureau of Reclamation (USBR), April 2009. Water Resources Technical Publication “Guidelines for Performing Hydraulic Field Evaluations at Fish Screening Facilities.” U.S. Department of the Interior, Bureau of Reclamation.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
42
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Yoe, Charles E., and Kenneth D Orth, November 1996. Planning Manual. U.S. Army Corps of Engineers (USACE), Water Resources Support Center Institute for Water Resources, IWR Report 96-R-21.
Zone 7, August 2013. E-mail correspondence from Colleen Winey to Nathan Foged. August 16, 2013. “RE: CEMEX Eliot Facility Rec Plan -- Data needs for Arroyo del Valle hydraulic study.” Attachment: “Z7 Diversion Criteria.docx” [Draft Design Criteria for the Arroyo Del Valle Diversion Structure.]
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
A-1
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Attachment A: Conceptual Design Figures
Figure A-1. Arroyo del Valle Diversion Infiltration Bed Conceptual Design
Figure A-2. Arroyo del Valle Diversion Infiltration Bed Conceptual Design Plan
Figure A-3. Arroyo del Valle Diversion Infiltration Bed Conceptual Design Sections
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
A-2
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
This page intentionally left blank.
"
RIPRAP
CHUTE
"
PARSH
ALL FL
UME F
ORDIV
ERSION
FLOW
MEAS
UREM
ENT
"
ENERG
Y DISS
IPATOR
(STILLI
NG BA
SIN)
"
8' x 8'
HEAD G
ATE
"
USE E
ROSIO
N CON
TROL B
MPS
AND RE
VEGETA
TE SLO
PE
"
SLOPE
UP FRO
M GRAV
EL BED
AT 2:1
TO MA
TCH GR
ADE
"
2 x CU
THROA
T FLUM
ES FO
RBYP
ASS FL
OW ME
ASUREM
ENTINV
ERT AT
435.0
FT EL
EV."
ROCK-
LINED
FISHW
AYSLO
PED AT
APPRO
X. 2%
RIFFLE
-POOLS
FEATU
RES"
LOW-HE
AD CO
NCRET
EDA
M WITH
SPILLW
AY CR
EST AT
436.2
FT EL
EV.
"
PIPE M
ANIFO
LD (DIA
. VARI
ES)
"
84' DI
A. MA
IN CON
DUIT
"
40 X 1
00' PE
RFORAT
EDDR
AINAG
E PIPE
LATER
ALS5' O
N CENT
ER SPA
CING
"
200' L
ONG X
100' D
EEP
GRAV
EL INF
ILTRATI
ON BE
D43
4.0 FT
ELEV.
AT CH
ANNEL
"
ROCK
FILL SL
OPES
ON UP
STREAM
AND
DOWN
STREAM
FACES
FLOW
"
RECTAN
GULAR
CONC
RETE
CHANN
EL 10
' WIDE
x 12' D
EEP
439
437
438
436
43543
4
433
440
441442
443
444
432431
445
447
44645
045
145
2453
448
449
446
446443
444447
449
446
446
441
440
44544
8
440
444
447
440
448
440
437 43
8
447
440
441
447
442
444
446
446
Sourc
e: Es
ri, Dig
italG
lobe,
GeoE
ye, i-
cube
d, US
DA, U
SGS,
AEX,
Getm
appin
g, Ae
rogrid
, IGN,
IGP,
swiss
topo,
and t
he G
IS U
ser C
ommu
nity
Path: P:\CEMEX\144718 Arroyo del Valle Hydraulic Study\GIS\MXD\CEMEX_AdVHS_AttA1.mxd Author: NFoged3/3/2014
LIMITA
TIONS
: THIS
DRAW
ING OR
FILE
HAS B
EEN P
REPA
RED B
Y BRO
WN
AND C
ALDW
ELL F
OR IT
S CLIE
NT AN
D MAY
NOT B
E COP
IED O
R USE
D WI
THOU
T WRIT
TEN A
UTHO
RIZAT
ION. D
UE TO
THE A
LTERA
BLE N
ATUR
E OF
ELEC
TRON
IC MA
TERIA
LS, R
ECIPI
ENT S
HOUL
D NO
T RELY
ON T
HIS
FOR A
CCUR
ACY O
R CON
TENT
, AND
ACKN
OWLE
DGES
AND A
GREE
S IT
HAS B
EEN P
ROVID
ED SO
LELY
FOR C
ONVE
NIENC
E AND
INFO
RMAT
IONAL
PU
RPOS
ES.
BROW
N AND
CAL
DWEL
L MAK
ES N
O RE
PRES
ENTAT
IONS
REGA
RDING
SUIT
ABILIT
Y OR
FITN
ESS
FOR
A PAR
TICUL
AR P
URPO
SE.
F
400
40Fee
t
1 inc
h = 80
feet
L E G
E N D
Lake
A at
412 f
t elev
.Ch
anne
l Cen
terlin
e1-f
t Con
tour (
2006
LiDA
R)
ARRO
YO DE
L VAL
LE DIV
ERSIO
NINF
ILTRA
TION B
EDCO
NCEP
TUAL
DESIG
NTe
chnic
al Me
moran
dum
2 - At
tachm
ent A
Divers
ion an
d Con
veya
nce F
easib
ility
Eliot
Facil
ity Re
clama
tion P
lanSu
rface
Mini
ng Pe
rmit 2
3 (“S
MP-23
”)
FIGUR
E A-1
BC Pr
oject
Numb
er 14
4718
Path: P:\CEMEX\144718 Arroyo del Valle Hydraulic Study\GIS\MXD\CEMEX_AdVHS_AttA2.mxd Author: NFoged3/3/2014
LIM
ITA
TIO
NS
: T
HIS
DR
AW
ING
OR
FIL
E H
AS
BE
EN
PR
EP
AR
ED
BY
BR
OW
N
AN
D C
ALD
WE
LL F
OR
IT
S C
LIE
NT
AN
D M
AY
NO
T B
E C
OP
IED
OR
US
ED
WIT
HO
UT
WR
ITT
EN
AU
TH
OR
IZA
TIO
N.
DU
E T
O T
HE
ALT
ER
AB
LE
NA
TU
RE
OF
EL
EC
TR
ON
IC M
AT
ER
IAL
S,
RE
CIP
IEN
T S
HO
ULD
NO
T R
ELY
ON
TH
IS
FO
R A
CC
UR
AC
Y O
R C
ON
TE
NT,
AN
D A
CK
NO
WLE
DG
ES
AN
D A
GR
EE
S I
T
HA
S B
EE
N P
RO
VID
ED
SO
LE
LY
FO
R C
ON
VE
NIE
NC
E A
ND
IN
FO
RM
AT
ION
AL
PU
RP
OS
ES
. B
RO
WN
AN
D C
ALD
WE
LL M
AK
ES
NO
RE
PR
ES
EN
TA
TIO
NS
RE
GA
RD
ING
S
UIT
AB
ILIT
Y O
R F
ITN
ES
S
FO
R A
P
AR
TIC
UL
AR
P
UR
PO
SE
.
AR
RO
YO
DE
L V
AL
LE
DIV
ER
SIO
N
INF
ILT
RA
TIO
N B
ED
CO
NC
EP
TU
AL
DE
SIG
N P
LA
N
Tec
hn
ica
l M
em
ora
nd
um
2 -
Att
ac
hm
en
t A
Div
ers
ion
an
d C
on
ve
yan
ce F
ea
sib
ility
Elio
t F
ac
ilit
y R
ec
lam
ati
on
Pla
n
Su
rfa
ce
Min
ing P
erm
it 2
3 (
“SM
P-2
3”)
FIG
UR
E A
-2
BC
Pro
jec
t N
um
be
r 1
44
71
8
Sca
le: 1
” =
50
’
Path: P:\CEMEX\144718 Arroyo del Valle Hydraulic Study\GIS\MXD\CEMEX_AdVHS_AttA3.mxd Author: NFoged3/3/2014
LIM
ITA
TIO
NS
: T
HIS
DR
AW
ING
OR
FIL
E H
AS
BE
EN
PR
EP
AR
ED
BY
BR
OW
N
AN
D C
ALD
WE
LL F
OR
IT
S C
LIE
NT
AN
D M
AY
NO
T B
E C
OP
IED
OR
US
ED
WIT
HO
UT
WR
ITT
EN
AU
TH
OR
IZA
TIO
N.
DU
E T
O T
HE
ALT
ER
AB
LE
NA
TU
RE
OF
EL
EC
TR
ON
IC M
AT
ER
IAL
S,
RE
CIP
IEN
T S
HO
ULD
NO
T R
ELY
ON
TH
IS
FO
R A
CC
UR
AC
Y O
R C
ON
TE
NT,
AN
D A
CK
NO
WLE
DG
ES
AN
D A
GR
EE
S I
T
HA
S B
EE
N P
RO
VID
ED
SO
LE
LY
FO
R C
ON
VE
NIE
NC
E A
ND
IN
FO
RM
AT
ION
AL
PU
RP
OS
ES
. B
RO
WN
AN
D C
ALD
WE
LL M
AK
ES
NO
RE
PR
ES
EN
TA
TIO
NS
RE
GA
RD
ING
S
UIT
AB
ILIT
Y O
R F
ITN
ES
S
FO
R A
P
AR
TIC
UL
AR
P
UR
PO
SE
.
AR
RO
YO
DE
L V
AL
LE
DIV
ER
SIO
N
INF
ILT
RA
TIO
N B
ED
CO
NC
EP
TU
AL
DE
SIG
N S
EC
TIO
NS
Tec
hn
ica
l M
em
ora
nd
um
2 -
Att
ac
hm
en
t A
Div
ers
ion
an
d C
on
ve
yan
ce F
ea
sib
ility
Elio
t F
ac
ilit
y R
ec
lam
ati
on
Pla
n
Su
rfa
ce
Min
ing P
erm
it 2
3 (
“SM
P-2
3”)
FIG
UR
E A
-3
BC
Pro
jec
t N
um
be
r 1
44
71
8
SE
CT
ION
A-A
’
SE
CT
ION
B-B
’S
EC
TIO
N C
-C’
Ho
rizo
nta
l S
ca
le: 1
” =
50
’
Ve
rtic
al S
ca
le:
1”
= 1
0’
This page intentionally left blank.
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
B-1
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
Attachment B: Construction Cost Estimate
Concept-level Cost Estimate for Infiltration Bed Alternative
Eliot Facility Reclamation Plan Amendment Arroyo del Valle Diversion and Conveyance Feasibility
B-2
Use of contents on this sheet is subject to the limitations specified at the beginning of this document. CEMEX AdVHS TM02 20140307.docx
This page intentionally left blank.
Eliot Facility Reclamation Plan Amendment Preliminary Construction
Cost Estimate
Arroyo del Valle Diversion and Conveyance Feasibility
Per unit Total
Excavation CY 14,500 5 72,500 5.5' max gravel depth x 200' x 100' plus 10%
Additional 10,000 CY for bank excavation and 2:1 slopes
Pea Gravel Backfill CY 4,500 45 202,500 5.5' max gravel depth x 200' x 100' plus 10%
Subsurface clay cut-off wall CY 300 30 9,000 8' depth x 5' width x 200' length
Geofabric SF 30,000 2 60,000 220' x 120' plus 10%
Slope erosion protection SF 3,200 5 16,000 For 2:1 side slopes surrounding bed; use 4 ft average rise
12" Dia. Perforated Pipe LF 1,200 60 72,000 Wrapped in geofabric
18" Dia. Perforated Pipe LF 2,800 90 252,000 Wrapped in geofabric
36" Diameter LF 60 180 10,800 C905 PVC
48" Diameter LF 80 240 19,200 C905 PVC
60" Diameter LF 60 255 15,300 RCP
84" Diameter LF 30 610 18,300 RCP
Connections EA 40 840 33,600 Tee connections for laterals into manifold
Junction box EA 1 10,000 10,000 Manifold into 84" main conduit
Concrete Channel CY 250 1,200 300,000 10' wide by 12' deep 1 ft thick walls, formed-in-place
Stilling basin blocks EA 8 100 800 Stilling basin block forms for energy dissipation
Parshall flume EA 1 5,000 5,000 Parshall flume (8-ft throat width) for flow measurement
Gravel bedding for channel CY 100 45 4,500 12' x 2' x 100 plus 10%
8' x 8' Motorized Sluice Gate ea 1 74,000 74,000 Vendor quote for 7'x7' scaled on area, plus $10,000 for installation
Flow Meter (ultrasonic) ea 1 10,000 10,000
Riprap, dumped with bedding CY 267 150 40,050 Chute dimensions of 40' wide x 60' long x 3' thick
Excavation CY 400 5 2,000 140' width x 6' depth x 12' length
Formed Concrete CY 145 1,100 159,500 140' width x (2 x 6' cutoff walls + 4' crest height + 12' cantilever
base)
Rock fill for up/downstream faces CY 450 150 67,500 assume 4:1 slopes
Earthwork cut and fill CY 300 5 1,500 4' x 2% slope = 200' length times 10' width times 4' depth
Wood, planting, riparian features LF 200 50 10,000 4' x 2% slope = 200' length
Rock and cobble, placed CY 75 175 13,125 4' x 2% slope = 200' length times 10' width times 4' depth
Chain link fencing LF 420 30 12,600 6' chain link fencing along drainage channel, to preventfall hazard
Electrical Services ea 1 15,000 15,000
Construction Subtotal 1,506,775
Contractor's Mobilization/Overhead percent 10 --- 150,678
Subtotal 1,657,453
Contractor's Mark Ups percent 10 --- 165,745
Subtotal 1,823,198
Contingency percent 40 --- 729,279
Subtotal 2,552,477
Bonding and Insurance percent 5 --- 127,624
Subtotal 2,680,101
Engineering and Administration percent 20 536,020
Design Engineering, Engineering Asssitance During Construction
and Legal and administrative costs such as Project-Specific CEQA
compliance, permitting, special studies,etc.costs, and
Total 3,216,121
3,300,000 round up to nearest $100,000
Notes:
1. Costs reflect those for a publically bid project in the San Francisco Bay Area Winter 2014.
2. Estimated prepared at AACEI Class 5, Order of Magnitude accuracy level.
Table B-1. Concept-level Cost Estimate for Infiltration Bed AlternativeTable B-1. Concept-level Cost Estimate for Infiltration Bed AlternativeTable B-1. Concept-level Cost Estimate for Infiltration Bed AlternativeTable B-1. Concept-level Cost Estimate for Infiltration Bed Alternative
Design Element
Total Construction Cost
Cost (dollars)Units Quantity Comments
P:\CEMEX\144718 Arroyo del Valle Hydraulic Study\500 Deliverables\TM02 Attachments\superseded\CEMEX_AdVHS_TM02_AttC_20140221.xlsx TM02 | Attachment B
This page intentionally left blank.