Technical Memorandum Barrel Only Alternative … a smaller total footprint. In both cases, the...
Transcript of Technical Memorandum Barrel Only Alternative … a smaller total footprint. In both cases, the...
Tucson Office 3031 West Ina Road
Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724
www.tetratech.com
Technical Memorandum Barrel Only Alternative
Noise Analysis
To: Kathy Arnold From: Robert Sculley
Company: Rosemont Copper Company Date: January 15, 2010
CC: Jamie Sturgess (Rosemont); David Krizek; Michael Dieckhaus (Tt)
Doc #: 025/10-320871-5.3
1.0 Introduction This Technical Memorandum was prepared by Tetra Tech and presents a Noise Analysis for the Barrel Only Alternative being considered in the US Forest Service Environmental Impact Statement (EIS) for the proposed Rosemont Copper Project (Project). This analysis assesses the potential impacts that the Barrel Only Alternative will have on noise conditions.
Tetra Tech published a comprehensive Supplemental Noise Study Report in April of 2009 that was based on the facility layouts in the Mine Plan of Operations (MPO). The Noise Study provided data on existing noise levels in the vicinity of the Project and noise levels measured at an active copper mine such as blasting and other operational activities. Modeling of the blasting vibrations was also performed. Noise effect contouring in the April 2009 study was based on the MPO facility layouts.
The following provides a comparison between the MPO and the Barrel Only Alternative facility layouts:
The top surface of the Dry Stack Tailings Facility would be about 5,250 feet above mean sea level (amsl) for the MPO, and about 5,300 feet amsl for the Barrel Only Alternative. The Dry Stack Tailings Facility for Barrel Only Alternative would have a footprint of 987 acres compared to 870 acres under the MPO.
The top surface of the Waste Rock Storage Area would be about 5,450 feet amsl for the MPO. The Barrel Only Alternative would have two (2) sections to the Waste Rock Storage Facility, with the larger south section having a top elevation of 5,700 feet amsl and the smaller east section having a top elevation of 5,200 feet amsl. The footprint of the Waste Rock Storage Area would be 1,460 acres under the Barrel Only Alternative, compared to 2,000 acres for the MPO.
The Heap Leach Pad for the MPO would be constructed in two (2) phases. The leach pad for the Barrel Only Alternative would be constructed in one (1) phase with
2
a smaller total footprint. In both cases, the closed heaps would eventually be covered with waste rock.
Under the Barrel Only Alternative, the combined footprints of the Waste Rock Storage Area and Dry Stack Tailings Facility (about 2,450 acres) would be somewhat smaller than the combined footprints under the MPO (about 2,870 acres). Under the Barrel Only Alternative, the Dry Stack Tailings Facility would not extend as far to the northeast as it would under the MPO and the Waste Rock Storage Area would extend further to the east than it would under the MPO.
The location and size of the Open Pit would be the same under both the MPO and the Barrel Only Alternative.
Under the Barrel Only Alternative, the Plant Site facilities would have a slightly different configuration and footprint than under the MPO. Under the Barrel Only Alternative, the Waste Rock Storage Area and the Dry Stack Tailings Facility would shield the Plant Site from State Route 83 (SR 83) only for SR 83 segments a mile or more south of the Primary Access Road.
The Primary Access Road would be in the same location under both the MPO and the Barrel Only Alternative.
The differences between the Barrel Only Alternative and the MPO are mostly matters of small details, not major features that would affect noise impacts. Consequently, most of the noise and vibration impact discussions, and the associated noise contour figures in the April 2009 Noise Study, are applicable to the Barrel Only Alternative. Differences in the shape of the combined Waste Rock Storage Area and Dry Stack Tailings Facility would, however, result in some changes in the potential locations for operation equipment under the Barrel Only Alternative.
The following sections of this Technical Memorandum explain which results of the April 2009 Noise Study are still applicable to the Barrel Only Alternative and which results would change under this alternative.
2.0 Blast Noise and Blast Vibration Impacts The Open Pit would be in the same location and operated in the same manner under both the MPO and the Barrel Only Alternative. Blasting events would be limited to one (1) event per day. Daily explosives usage is also expected to be the same under both scenarios.
In addition, differences in the maximum height and shape of the combined footprints of the Waste Rock Storage Area and the Dry Stack Tailings Facility would produce only minor localized shielding differences for blast noise under the MPO and the Barrel Only Alternative. Blast noise effects at the closest noise-sensitive receptor locations would not be affected by differences in the combined footprints of the Waste Rock Storage Area and the Dry Stack Tailings Facility under the MPO and the Barrel Only Alternative.
Because blasting events would be similar under both the MPO and the Barrel Only Alternative, groundborne vibrations would be the same. Thus, the discussions and associated noise contour
3
figures for blast noise and blast-related vibrations, as presented in the April 2009 Noise Study, would be applicable to the Barrel Only Alternative.
3.0 Construction Noise Impacts Although the Plant Site would still be in the same general area under the Barrel Only Alternative, the Plant Site facilities would have a slightly different configuration and footprint than that of the MPO. However, there would be little if any difference in the construction activity noise levels between the MPO and the Barrel Only Alternative. As noted in the April 2009 Noise Study, construction noise levels would attenuate to background noise levels over a relatively short distance and would not create any noise impacts at the nearest existing residences. Therefore, the discussions and associated noise contour figure for construction noise impacts presented in the April 2009 Noise Study would be applicable to the Barrel Only Alternative.
4.0 Equipment Operation Noise Impacts As discussed in the April 2009 Noise Study, operational noise levels from the Plant Site area would be similar to the maximum construction noise levels. Operational noise levels are expected to attenuate to background noise levels over a distance of about two (2) miles and would therefore not create any noise impacts at the nearest existing residences or along SR 83.
As indicated in Section 1.0, the combined footprints of the Waste Rock Storage Area and Dry Stack Tailings Facility under the Barrel Only Alternative (about 2,450 acres) would be somewhat smaller than the combined footprints under the MPO (about 2,870 acres). Maximum elevations of these facilities would be somewhat higher under the Barrel Only Alternative than under the MPO. Under the Barrel Only Alternative, the Dry Stack Tailings Facility would not extend as far to the northeast as it would under the MPO and the Waste Rock Storage Area would extend further to the east than it would under the MPO.
Figure 1 presents operational equipment noise contours for the Barrel Only Alternative. Actual noise generation by equipment working on the Waste Rock Storage Area and the Dry Stack Tailings Facility would be the same as for the MPO, but potential equipment locations would be somewhat different due to differences in the shapes of facility footprints.
Haul trucks and other equipment working at the south end of the Waste Rock Storage Area would be in a location very similar to that under the MPO. Consequently, the equipment operation noise contours shown in the April 2009 Noise Study for the south end of the Waste Rock Storage Area would still be applicable to the Barrel Only Alternative for equipment operations in the southernmost portion of the Waste Rock Storage Area. The eastern extension of the Waste Rock Storage Area under the Barrel Only Alternative would result in haul truck and other equipment operations being about 0.3 miles closer to homes along Singing Valley Road than would be the case under the MPO. Figure 1 shows the noise contours for equipment operating at the southeastern corner of the Waste Rock Storage Area. Intermittent equipment operations at the southeastern corner of the Waste Rock Storage Area would increase noise levels at the closest residences along Singing Valley Road by about 2 dBA compared to MPO operations at the south end of the Waste Rock Storage Area (from about 39 dBA to about 41
4
dBA). Most people cannot distinguish a change in noise level that is less than about 1.5 to 2 dBA. In addition, as noted in the April 2009 Noise Study, existing minimum noise levels in the Project area are estimated to be about 30 to 40 dBA, and average noise levels were generally 37 to 45 dBA. Because intermittent equipment operation noise levels would be comparable to existing background noise levels, the change to the Waste Rock Storage Area footprint for the Barrel Only Alternative would not result in a significant noise impact at the nearest noise-sensitive locations.
Equipment working at the north end of the Dry Stack Tailings Facility would be further from homes located along Highway 83 northeast of the Project site than would be the case under the MPO. Figure 1 shows noise contours for equipment operating at the north end of the Dry Stack Tailings Facility. Noise from such equipment operations would not result in any significant noise impacts at the nearest noise-sensitive locations.
5.0 Traffic Noise Impacts The Barrel Only Alternative would not alter the basic employment level or operating material requirements for the Project as described in the MPO. In addition, this alternative would not alter the routing of the proposed Primary Access Road. Consequently, the MPO and the Barrel Only Alternative would be expected to have the same traffic generation, and thus the same resulting traffic noise impacts. Therefore, the discussions and noise contour figures, as presented in the April 2009 Noise Study, would be applicable to this alternative.
6.0 Conclusion A review of operational and facility changes was performed between the MPO and the Barrel Only Alternative being considered in the EIS process. Because the facilities, operations, and anticipated traffic patterns are generally the same for both scenarios, most of the discussions, noise contour figures, and analysis results presented in the April 2009 Noise Study are applicable to the Barrel Only Alternative. Revised noise contours (Figure 1) were prepared to illustrate maximum equipment operation noise conditions under the Barrel Only Alternative. Compared to the MPO, maximum equipment operation noise levels under the Barrel Only Alternative would increase by about 2 dBA at the closest noise sensitive receptor location. Intermittent equipment operation noise levels under this alternative would be comparable to existing background noise levels, and would not cause significant noise impacts at the nearest noise-sensitive receptors.
5
REFERENCES Tetra Tech (2009) Supplemental Noise Study, Rosemont Copper Project. Prepared for
Rosemont Copper Company. Report Dated April, 2009 WestLand (2007) Rosemont Project Mine Plan of Operations. Prepared for Rosemont Copper
Company. Report Dated June, 2007
!(
!(
l
l
×
×
×
× ×
×
×
×× ××××
×
×××× ×
×
×
×
×
î
T 18 S
T 18 ST 19 S
T 17 S
T 18 S
T 18 ST 19 S
R 1
6
R 1
5
R 1
6 E
R 1
7 E
R 1
6 E
R 1
5 E
R 1
6 E
R 1
7 E
!(83
!(83
40 d
BA
50 d
BA
30 d
BA
80 dBA
70 dBA
60 dBA
40 d
BA
50 d
BA
30 d
BA
SINGING VALLEY RD
E GREATERVILLE RD
OLD
SO
NO
ITA
HW
Y
BIG
THU
ND
ER R
D
BIG THUNDER RD
GHOST DANCE RD MES
QU
ITE M
ESA P
L
35 dB
A
55 dBA45 dBA
55 dBA
45 dBA
35 dBA
80 dBA
70 dBA
60 dBA
SON
OITA H
Y
S HELVETIA RD
GR
EAT
ERVI
LLE
RD
E FISH CANYON RD
E EMPIRE RANCH RD
BOX C
ANYO
N R
D
S H
OU
GH
TON
RD
E YUCCA ASH FARM RD
E SINGING HILLS TR
S O
LD S
ON
OIT
A H
Y
HILTON RANCH RD
E BEATTY RANCH RD
W CAMINO AURELIA
YON EDG
E TR
E GARDNER CANYON RD
HIDDEN VALLEY RD
T 17 S
House Y
House X
House W
House V
House UHouse T
House S
House R
House Q
House P
House OHouse N
House L
House K
House JHouse I
House H
House D
House C
House B
House A
House E
Building F
Building G
Center of Open Pit
Plant SiteLocation
Santa Rita Abbey
North End of Dry Stack Tailings Facility
Southeast Corner of Waste Rock Storage Area
!(
!(
!(
!(
l
l
×
×
×
× ×
×
×
×× ××××
×
×××× ×
×
×
×
×
î
4100
4500
4400
4200
4700
4300
4000
4600
4800
4900
5000
5100
39003800
5200
5300
5400
5500
5600
3700
3600
5700
5800
3500
5900
6000
3400
6100
6300
6200
4300
4800
6000
5800
4600
4800
5300
4300
4100
5500
4900
4800
4700
5000
5100
5100
5500
5100
6200
4400
5100
520056
00
5400
5300
4500
6000
5000
6100
4500
4900
4900
5200
4200
4600
5600
4900
4900
4300
4000
4500
4000
4700
5300
4300
4800
4400
5900
5900
4900
5000
5100
4600
5100
4400
4600
4500
4100
4500
5400
4600
4200
4600
4600
4600
5000
5500
61006200
5100
5200
5200
4400
4400
5900
5900
4200
4400
4900
50004900
46004000
5300
4600
5400
6100
4800
4700
4000
4600
5300
4400
5300
4300
5000
4200
5500
4600
4600
5200
4500
4000
5400
5600
5300
5300
5000
5800
4200
5100
4600
4900
4700
4000
4700
5200
5400
5500
4600
4700
4600
5700
5300
5500
4300
5200
5400
4900
4200
5800
4100
5000
5700
6000
4700
5900
4600
4200
6100
5800
4400
5900
4000
4800
5300
4300
5200
5200
4800
5900
5200
4300
5000
5700
4800
5300
6200
4600
4400
5000
4300
5600
4100
5500
4700
4400
4700
50006000
4800
6000
5000
4700
5500
4800
4500
4500
5300
5100
4000
4700
4600 4000
4300
4500
5400
5200
4700
6000
4600
4800
4500
4300
4000
4200
5800
4200
4300
5900
4200
5400
4500
5400
5400
5700
4700
4600
4900
5700
4600
4500
5100
5800
4900
4700
4700
5000
4600
6000
4400
5100
4200
4600
4400
4600
5900
5000
5500
4600
5300
5400
5400
5300
4600
4900
4500
4300
4500
4500
4500
5300
4600
4100
5600
4900
4600 4700
4900
4100
5400
5700
4800
5200
4100
4900
4400
4600
4500
5000
4300
5400
5300
5400
5100
5600
4800
4500
4600
5900
5000
5300
4600
4200
4000
6200
5500
4000
4600
4500
4200
4600
4000
4300
5000
5000
5200
5300
4700
4000
4800
5000
5300
5000
4800
4100
4600
5200
5800
5000
5900
5800
5800
5000
4900
5700 4600
5400
5000
4400
4900
4900
4600
4600
5500
4200
5000
5300
4400
5400
4600
5400
4300
4300
5100
4500
4100
4800
5700
5100
6100
4800
5100
4700
4100
4200
5700
5500
4600
5400
4500
4700
4900
5300
4700
4800
5300
5700
11
11 11
11
07
01
14 18
17
12
30
04
26
16
29
08
27
32
14
19
35
28
25
26
15
10
09
21
33 3432
22
27
27
31
29
14
05
23
35
20
26
10
33
2223
12
23
15
26
13
20
03
28
13
09
24
29
28
29
20
31
16
31
0602 02
30
14
24
29
35
26 25
21
08
32
2024
1713 18
30
17
34
12
31
07
32
30
25
23
19
18
19
17
36
30
08
02
35
01
07
0503
29
18
26
06
0606
25
04
19
36
0102 05
07
08
30
05
13
36
01
24
25
36
25
12
36 3635
32
31
3532 343331
20
19
2221
2323
2024 19 24
09
16
04
21
33
28
28
33
09
04
16
21
27
34
28
34
27
15
22
10
22
27
15
03
03
10
3334
2122
±
JANUARY 2010
FIGURE 1BARREL ONLY ALTERNATIVE
ROSEMONT COPPER PROJECT NOISE ANALYSIS
4,000 0 4,000 8,0002,000Feet
Note: Equipment operationnoise contours are shown forthe north end of the Dry StackTailings Facility and thesoutheast corner of the WasteRock Storage Area, andrepresent intermittent noiselevels when equipment isoperating in these areas.Traffic noise contours are 24-hour Ldn noise levels for Year20 traffic conditions.
LegendMain Facility Outline
RoadwayAZ State Highway 83
Township/Range Line
Section Lines
Ground Contour
55+ dBA Ldn Zone
45-55 dBA Ldn Zone
35-45 dBA Ldn Zone
Equipment Noise Contour (XX dBA)
Traffic Noise Contour Designations
Transmittal of Technical Memoranda and Pit Lake Report
February 8, 2010
To: Beverly Everson
Cc: Tom Furgason
From: Kathy
Doc #: 003/
Subject:
Date:
OSEMONT COPPER A Bridge to a Sustainable Future.
Memorandum
Rosemont Copper is pleased to transmit the following twenty technical memoranda and one report:
1. Rosemont Hydrology Method Justification, a Tetra Tech memo dated January 7, 2010; 2. Barrel Only alternative —
a. Noise Analysis, a Tetra Tech memo dated January 15, 2010 b. Traffic Analysis, a Tetra Tech memo dated January 8, 2010
c. Geochemical Characterization 'of Facilities, a Tetra Tech memo dated January 10, 2010 d. Lighting, an M3 memo dated December 2009
3. Barrel and McCleary alternative —
a. Noise Analysis, a Tetra Tech memo dated January 9, 2010 b. Traffic Analysis, a Tetra Tech memo dated December 15, 2009
c. Geochemical Characterization of Facilities, a Tetra Tech memo dated December 16, 2009
d. Lighting, an M3 memo dated December 2009
4. Scholefield Tailings and McCleary Waste alternative —
a. Noise Analysis, a Tetra Tech memo dated January 15, 2010
b. Traffic Analysis, a Tetra Tech memo dated January 12, 2010
c. Geochemical Characterization of Facilities, a Tetra Tech memo dated January 10, 2010
d. Lighting, an M3 memo dated January 2010
5. Sycamore Tailings and Barrel Waste alternative —
a. Noise Analysis, a Tetra Tech memo dated January 15, 2010
b. Traffic Analysis, a Tetra Tech memo dated January 9, 2010
c. Geochemical Characterization of Facilities, a Tetra Tech memo dated January 10, 2010
d. Lighting, an M3 memo dated January 2010
6. Partial Backfill alternative —
a. Noise Analysis, a Tetra Tech memo dated January 23, 2010
b. Traffic Analysis, a Tetra Tech memo dated January 9, 2010
c. Geochemical Characterization of Facilities, a Tetra Tech memo dated January 10, 2010
7. Geochemical Pit Lake Predictive Model, prepared by Tetra Tech and dated February 2010
As per your request, I am transmitting three hardcopies and two disks (disks contain tech memos only) directly to the Forest Service and two copies and one disk directly to SWCA. The Pit Lake report includes
a copy of the report on a CD on the inside of the back cover of each report.