Technical Eng Challenge for Malampaya Pipeline

13
Copyright 2002, Offshore Technology Conference This paper was prepared for presentation at the 2002 Offshore Technology Conference held in Houston, Texas U.S.A., 6–9 May 2002. This paper was selected for presentation by the OTC Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the Offshore Technology Conference and are subject t o correction by the author(s). The material, as presented, does not necessarily reflect any position of the Offshore Technology Conference or its officers. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Abstract The Malampaya field development comprises subsea wells in 850 metres water-depth producing via a subsea manifold and two 16 inch diameter inconel clad flowlines to a shallow water  platform 30 km distant. Condensate is removed on the  platform and the dry gas is then transported via a 504 km long 24 inch export pipeline to an onshore gas plant at Tabangao (Batangas, Luzon Island) for extraction of H 2 S. The condensate is stored in the platform CGS caisson prior to export via a short 3 km long 24 inch diameter pipeline and CALM buoy. The field flowlines and export pipeline route selection, design and installation are at the forefront of deep-water technology. The pipelines traverse structurally complex terrain with varied seabed characteristics and sections of high bottom relief. The Philippines archipelago is recognised as being one of the most seismically active areas in the world. The gas export pipeline crosses active faults, an extensive system of submarine channels and areas susceptible to mass gravity flow and other soil instabilities . This paper addresses the pipeline route selection, design  process and some of the specialist techniques employed in the seismic design of the Malampaya pipeline. The paper also addresses some of the novel installation techniques employed and challenges encountered in the execution phase of the project. In particular the deepwater PLES installation, deepwater span rectification and the removal of ordnance in 460 metres water depth will  be addressed. Introduction Following detailed reviews of competing concepts for the Malampaya field, the gas only development, comprising a deep water subsea tieback to a shallow water platform was selected in June 1996 as the preferred option for the development of the field (Fig. 1). Common to all of the concepts under consideration however was the provision of a subsea trunk export pipeline from the Malampaya field to the gas markets situated on the island of Luzon. Of the technical challenges to be faced in the engineering of the Project, it was recognised the feasibility of the export a pipeline in the structurally complex and seismically active terrain was critical. Early survey and data gathering work was essential to resolve the feasibility question. Offshore survey field work was therefore kicked off in December 1996 and continued throughout 1997 in one of the most comprehensive offshore data gathering campaigns  performed in the industry. In addition to the pipeline routing and design challenge the deep waters of Malampaya were to throw-up a number of additional technical and engineering challenges in the installation of the pipelines. These included: Installation of 16 inch PLES units in 820 metres depth; Rock dump optimisation (for span correction) in water depths down to 600 metres depth; These and other challenges were successfully overcome and in doing so the boundaries of existing pipeline design and installation experience extended. The Malampaya export pipeline and flowlines as part of the overall Malampaya Development Project were put into service and supplying gas to the customer on time on 1 st  October 2001. Route Selection. The route selection process adopted for the Malampaya  pipeline emphasised the avoidance of hazards while minimising the length of the pipeline and the water depth. The major tectonic feature between the Malampaya field and a  pipeline landfall in Southern Luzon is the Manila-Mindor o-  Negros subduction-collisi on zone (Fig. 2). A pipeline route  passing to the West of Mindoro Island would have needed to cross the Manila trench with water depths in excess of 2000 metres. Instead, a routing passing to the East of Mindoro was selected. As a fallback option, the Project considered OTC 14040 Malampaya Deep Water Gas Pipeline and Flowlines: Technical and Engineering Challenges faced in the Execution of the Malampaya Pipeline Scope J.C. Macara - Shell Philippines Exploration B.V.

Transcript of Technical Eng Challenge for Malampaya Pipeline

Page 1: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 1/13

Page 2: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 2/13

Page 3: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 3/13

Page 4: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 4/13

Page 5: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 5/13

Page 6: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 6/13

Page 7: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 7/13

Page 8: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 8/13

Page 9: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 9/13

Page 10: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 10/13

Page 11: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 11/13

Page 12: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 12/13

Page 13: Technical Eng Challenge for Malampaya Pipeline

8/10/2019 Technical Eng Challenge for Malampaya Pipeline

http://slidepdf.com/reader/full/technical-eng-challenge-for-malampaya-pipeline 13/13