Technical Assistance Layout with Instructions

84
Resettlement Plan December 2017 Georgia: Urban Services Improvement Investment Program (Tranche 6) GEO: CHI - 01 Chiatura Water Supply System Construction Project PR: 43405-ICB-CHI-01 Urban Services Improvement Investment Program (USIIP Tranche 6) Prepared by the United Water Supply Company of Georgia LLC of the Ministry of Regional Development and Infrastructure for the Asian Development Bank.

Transcript of Technical Assistance Layout with Instructions

Resettlement Plan

December 2017

Georgia: Urban Services Improvement Investment Program (Tranche 6) GEO: CHI - 01 Chiatura Water Supply System Construction Project

PR: 43405-ICB-CHI-01 – Urban Services Improvement Investment Program

(USIIP Tranche 6)

Prepared by the United Water Supply Company of Georgia LLC of the Ministry of Regional

Development and Infrastructure for the Asian Development Bank.

This resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Table of Contents

EXECUTIVE SUMMARY .......................................................................................................................................... 3

CHAPTER 1. PROJECT BACKGROUND AND OBJECTIVES ......................................................................................... 7

CHAPTER 2: SOCIOECONOMIC PROFILE OF PROJECT AFFECTED PERSONS ........................................................... 13

CHAPTER 3: COMPENSATION ENTITLEMENTS ................................................... ERROR! BOOKMARK NOT DEFINED.

CHAPTER 4: LEGAL-REGULATORY FRAMEWORK ................................................................................................. 29

CHAPTER 5: INSTITUTIONAL ARRANGEMENTS .................................................................................................... 35

CHAPTER 6: PUBLIC CONSULTATIONS AND LARP DISCLOSURE ............................................................................ 36

CHAPTER 7: GRIEVANCE REDRESS MECHANISM .................................................................................................. 38

CHAPTER 8: MONITORING AND REPORTING REQUIREMENTS............................................................................. 42

CHAPTER 9: LARP IMPLEMENTATION SCHEDULE ................................................................................................ 43

CHAPTER 10: COMPENSATION UNIT RATES AND LARP BUDGET ......................................................................... 44

APPENDIXES ....................................................................................................................................................... 46

ABBREVIATIONS

ADB Asian Development Bank

AH Affected Household

AP Affected Person

DMS Detailed Measurement Survey

DP Displaced Person

EA Executing Agency

GRC Grievance Redress Commission

GRM Grievance Redress Mechanism

IPMO Investment Program Management Office

IP Indigenous People

IVS International Valuation Standards

LARP Land Acquisition and Resettlement Plan

MFF Multi-tranche Financial Facility

NAPR National Agency of Public Register

NGO Non-Governmental Organization

MLARO Municipality Land Acquisition and Resettlement Office

MOISD Ministry of Infrastructure and Sustainable Development

PMU Project Management Unit

ROW Right of Way

SPS Safeguards Policy Statement

USIIP Urban Service Improvement Investment Program

UWSCG United Water Supply Company of Georgia (LLC)

i

Definition of Terms

Affected Persons Please see below definition for Displaced Persons.

Compensation Payment in cash or in-kind for an asset to be acquired or affected by a

Project at replacement cost at current market value.

Cut-off-date The completion date of census1 of project affected persons2.

Detailed

measurement

Survey

The detailed survey of project affected land parcels and inventory of

affected assets.

Displaced Person

(DP) / Affected

Household (AH)

All the people affected by the Project through land acquisition,

relocation, or loss of incomes and includes any person, household

(sometimes referred to as Project affected family), firm, or public or

private institution. DPs therefore include: (i) persons affected directly by

the project corridor, right-of-way, or construction work area; (ii) persons

losing privately owned or used buildings and structures (residential

dwellings and supplementary structures); (iii) persons whose agricultural

land or other productive assets such as trees or crops are affected; (iv)

persons whose businesses are affected and who might experience loss of

income due to the Project impact; (v) persons who lose

work/employment as a result of Project impact; and (vi) people who lose

access to community resources/property as a result of the Project. For

the purposes of this LARP, displaced person (DP) and affected person (AP)

may be considered synonymous.

Encroachers People who move into the Project area after the cut-off date and are

therefore not eligible for compensation or other rehabilitation measures

provided by the Project.

Entitlement The range of measures comprising cash or in-kind compensation,

relocation cost, income rehabilitation assistance, transfer assistance,

income substitution/business restoration, which are due to AHs,

depending on the type, extent and nature of their losses, and sufficient

to restore their social and economic base.

Inventory of losses Pre-appraisal inventory of assets as a preliminary record of assets to be

affected or lost as a result of the Project

1 June 22, 2017 for the proposed project. 2 2 p. ii; Involuntary Resettlement Safeguards A Planning and Implementation Good Practice Sourcebook (ADB 2012)

https://www.adb.org/sites/default/files/institutional-document/32827/files/ir-good-practices-sourcebook-

draft.pdf

ii

Livelihood Means of support; subsistence (source of income)

APs with no formal

rights

Physical persons who have no recognizable rights or claims to the land

that they are occupying and includes people using private or state land

without permission, permit or grant.

Replacement cost The replacement cost is the amount enough to replace an affected asset

in its existing condition, without deduction of transaction costs or for any

material salvaged and depreciation for age. The Calculation of

compensation amount at full replacement cost will be based on the

following elements: (i) fair market value of construction materials;

(ii) transaction costs; (iii) interest accrued, (iv) transitional and restoration

costs; and (v) other applicable payments, if any.

Sharecropper Same as tenant cultivator or tenant farmer, i.e., a person who cultivates

land they do not own for an agreed proportion of the crop or harvest.

Severely affected

Ahs

Those physically displaced or economically displaced losing 10% or more

of income generating assets.

Vulnerable Any person who might suffer disproportionately or face the risk of being

marginalized from the effects of resettlement and includes; (i) female-

headed households with dependents; (ii) disabled household member;

(iii) poor households (below poverty line); (iv) landless; (v) elderly

households with no means of support; (vi) households without security

of tenure; (vii) ethnic minorities.

3

Executive Summary

1. The Government of Georgia applied to the Asian Development Bank (ADB) for the financing of the construction

and completion of water supply system for Chiatura within the framework of the Loan 3441-GEO: Urban Services

Investment Program – Project 6: titled CHI-01, Water Supply System, Chiatura3.

2. The water supply system of Chiatura – constructed 40-50 years ago, with minor monitoring, maintenance and

replacement of pipes and electro-mechanical installations - is in urgent need of upgrading and rehabilitation. In

addition, the water sources are affected by mountain ore and turbidity during rainfall periods, thus creating a

threat to the health of local population.

3. For the above reasons, following the request of UWSCG, the present design considers a new water source

located along the left bank of the Kvirila River in Sachkhere Municipality.

4. The results of hydrological investigation conducted during preparation of Chiatura Water Supply System

rehabilitation design, confirmed that the most suitable area for drilling the exploration boreholes for Chiatura

water supply is the studied area located parallel to the river Kvirila on the terrace, at the distance of 150 meters

from the river. To supply the city with 75 l/sec of water extraction, it is sufficient to drill seven (7) boreholes at

50 m distance from each other. The document, in accordance with appropriate standards and norms, requires

installation of security-sanitary zone around the boreholes.

5. According to the final design, the total area of land allocated within the ROW of the proposed project will

comprise 3.94 hectares.

6. Currently, the project territory is owned by the residents of village of Chikha in Sachkhere rayon and used

exclusively for agricultural purposes. Therefore, allocation of territory for project purposes will require

acquisition of some privately owned arable agricultural land parcels. The territory allocated for project purposes

will be fenced and no trespassing allowed to aliens. In addition, new access roads will be constructed to allow

owners releasing portion of their land parcels, to maintain uninterrupted use of remaining agricultural land

parcels.

7. To adequately address land acquisition and related economic and social impacts, compensation entitlements

and maintenance of livelihood of project affected people, the UWSCG has prepared a draft LARP in compliance

with the applicable laws of Georgia and ADB Safeguards Policy Statement (SPS 2009) on Involuntary

Resettlement.

3 The proposed project considers construction and completion of water supply system in Chiatura, in particular the arrangement

for 7 water supply wellfields (boreholes), rehabilitation of 4 raw water pumping stations, including civil works and provision of

new pump sets, construction of two reservoirs (1400 and 500 m³), rehabilitation of existing 8 reservoirs (4 of them with less

than 520 m3 volume, remaining 4 of 850, 1190,1340 and 2720 m3), installation of about 16 km long main transmission line (400

and 500 mm diameter pipes), about 10 km long transmission lines (114 to 355 mm diameter pipes), and about 68 km of

distribution network pipe works. The estimated construction period for the completion of works is 540 days.

4

8. The LARP sets out the project goals and project implementation schedule, defines the project affected persons

(APs), eligibility criteria for compensation and cut-off date, grievance redress mechanism, legal framework and

institutional involvement, procedures for AP participation and public consultation, determines compensation

unit rates based on the elaborated valuation methodology, defines compensation entitlements and additional

rehabilitation and mitigation measures which will be employed to compensate, and restore the livelihoods and

living standards of project affected persons and households.

9. The water supply system construction activities will be carried out within the identified ROW occupying the

agricultural land parcels located in vicinity of the regional road to Sachkhere. Most landowners are residents of

the village of Chikha which is almost contiguous with the town of Sachkhere4. According to the proposed project

design, the suggested ROW will require permanent acquisition of seventy-seven (77) land parcels. Out of these

77 land parcels, 74 land parcels with total affected area of 34,570 sq.m.) are privately owned and three (3) land

parcels composing 4,784 square meters of arable land are under legitimate possession of local residents. In total

seventy-seven land parcels to be acquired for project purposes will compose 39,354 sq.m. of rain fed, arable

agricultural land mainly used for growing corn, beans, wheat and even pumpkin. Some of the land parcels have

not been cultivated for a couple of years due to diverse reasons5.

10. These land parcels were distributed to the residents of village Chikha during 1994-1996 under the land reform

launched in Georgia following the break-up of the Soviet Era. In early 2000s systematic registration was

undertaken within the framework of the International donor funded projects to support title registration.

11. The total area of project affected seventy-seven (77) land parcels equals 39,354 sq.m. Among these 77 only

sixteen (16) project affected land parcels (19,147 sq.m.) will subject to full acquisition. The remaining sixty-one

(61) land parcels (with total area of 122,045 sq.m.) will subject to partial acquisition of 20,207 sq.m.) with major

portion of these land parcels remaining outside of the project ROW. The owners of these 61 land parcels will be

able to continue agricultural activities as the remaining portion (101,838 sq.m.) of these land parcels will still

maintain economic viability. Thus, the total affected area of land to be acquired will equal to 39,354 sq.m. The

table below scopes the project impact within the ROW.

Table 1. The summary of project affected land parcels and area of land acquisition

12. Overall, the APs with the residual land, meaning that remaining piece of land which as a result of land take has

lost previous designation and became economically unviable will be eligible to claim full cash compensation for

the entire area of such land parcel.

4 Some landowners have moved to other towns including the capital city, Tbilisi; however they retain land and real property in

their village to visit in the summer time. 5 Some landowners mentioned a lack of cash to cover land cultivation costs, while for others it was related to paid jobs located

outside of the rayon.

Scope of Impact

No of parcels

Total area

(sq.m.)

Area to be acquired

(sq.m.)

Area remaining

with AHs (sq.m.)

Full acquisition 16 19,147 19,147 0

Partial acquisition 61 122,045 20,207 101,838

Total 77 141,192 39,354 101,838

5

13. Importantly, land acquisition for project purposes will not cause any need for physical resettlement of affected

households as there are no residential dwellings on these land parcels. The project affected land parcels are

exclusively used for farming, producing agricultural produce and sometimes local people allow seasonal grazing

before the start of the plowing and sowing season.

14. The project impact will require demolition of one almost completely ruined structure located on privately owned

land parcel of 400 sq.m. The land parcel is registered in the NAPR as non-agricultural. In 2002 the AP acquired

this land parcel and attached deteriorated structure from the state through privatization. This parcel is located

right next to other project affected land parcels designated as agricultural and being used for growing seasonal

crops.

15. There are no metal fences or stone walls to be affected by the proposed project.

16. The project will most likely affect seasonal crops as a result of project construction activities that might cause

so e disruptio to APs’ atte pti g to gro seaso al rops o the re ai i g portio of la d par els.

17. Eleven perennials, in particular nine (9) fruit bearing trees and two (2) non-fruit bearing perennials are standing

within the ROW on one (1) project affected land parcels. These perennials, instead of being felled, will be

preserved within the sanitary zone of water reservoir. Since the APs will lose access and right to use these

perennials, the APs will be cash compensated as described in the Entitlement Matrix of this LARP.

18. The LARP provides detailed information on the volume of project impact, such as the number of all project

affected land parcels, full names of landowner(s), grown annual and seasonal crops, and perennials (including

fruit bearing and non-fruit trees).

19. During the LARP preparation, the following activities were undertaken:

a. Review of officially available data at the NAPR on land parcels registered under systematic and

sporadic registration;

b. Preparation of the initial list of project affected land parcels and their owners / possessors;

c. Onsite identification and enumeration of project affected land parcels;

d. Census and collection of socio-economic data on each located project affected household;

e. Demarcation and survey of all project affected land parcels in the presence of owner, or owner's

legitimate representative, owners of the adjacent land parcels, representatives of local government

and municipality;

f. Inventory of project affected assets being determined during demarcation and land survey in the

presence of the owner, or owner's legitimate representative and representatives of local

government and municipality;

g. Additional inventory of project affected assets conducted by the licensed valuator who also

conducted market research on secondary land sales6 prior to preparation of valuation report and

determination of compensation unit rates for affected land and assets;

h. Preparation of cash compensation package separately per each project affected land parcel and

broken down per type and volume of impacts subject to cash compensation.

6 Secondary land sales is the term often used in Georgia to describe sales transaction when a private person is willing to sell

land/real property acquired from the State through the privatization process.

6

20. According to the results of these surveys the entire project impact has been clearly defined and all steps and

legal procedures required for land acquisition, registration sales transactions and payment of cash compensation

were identified, scheduled and presented to APs and project stakeholders.

21. The project will impact 77 land parcels owned by 70 affected households.

22. Below is the summary of impact for the given project:

a. The total number of project affected land parcels: 77 / affected area 39,354 sq.m.

b. The total of number affected households: 70 (persons: 158 persons; among them 89 male and 69

female)

c. Physical resettlement 0:

d. Economic Displacement: 70 AH

e. Affected agricultural land parcels: 76 / affected area 38,954 sq.m.

f. Affected non-agricultural land parcels: 1 / affected area 400 sq.m.

g. Land parcels subject to full acquisition: 16 / 19,147 sq.m.

h. Land parcels subject to partial acquisition: 61 / 20,207 sq.m.

i. Land parcel attached with affected structure-building: 1 /100 sq.m.

j. Land parcel attached with structure (residential and /or commercial) used by the AP: 0

k. Land parcels with annual crops /hey: 76/38,954 sq.m.

l. Land parcels attached with affected perennials: 1/400 sq.m

m. Project affected fruit-bearing perennials: 9

n. Project affected non-fruit bearing trees: 2

o. Permanent /temporary stoppage of business: 0

p. Loss of wages/salary from business employer: 0

q. Affected supplementary structures, fences, walls, etc.: 0

r. Total of severely affected land parcels: 747

s. Total of Vulnerable: 13 AHs.

7 In total 74 land parcels will lose more than 10 % of income generating land.

7

Chapter 1. Project Background and Objectives

Project Overview

23. Water supply system of Chiatura – constructed 40-50 years ago, with minor monitoring, maintenance and

replacement of pipes and electro-mechanical installations - is in urgent need of upgrading and rehabilitation. In

addition, the water sources are affected by mountain ore and turbidity during rainfall periods, thus creating a

threat to the health of local population.

24. According to the Detailed Design Report of Rehabilitation of Chiatura water supply system prepared by Eptisa in

December 2016, the water sources in Chiatura have similar characteristics, high values of hardness, conductivity

and nitrate concentration. In addition during rainy periods there are also high levels of MN content. During some

periods of the year, pollution interrupts the supply of water. According to Chiatura-UWSCG, customers complain

about the turbidity of water, in particular during rainy periods.

25. For the above reasons, following the request of UWSCG, the present design considers a new water source in

Sachkhere, along the left bank of the Kvirila River, near the site where the water is drained /extracted to supply

the town of Sachkhere.

26. The proposed project will: (i) provide potable water to Chiatura residents, and (ii) help stimulate livelihood

standards and improve health and safety of local residents as final recipients of the project. The expected

outcome of the proposed project is improved efficiency of water supply, and the installation of meters

supporting collection of fees for the consumed potable water within the project area. Project will benefit

Chiatura population of approximately 15,400 persons.

Methodological Introduction

27. During LARP preparation, several activities were undertaken. On April 7, 2017, at the starting phase of LARP

preparation, the UWSCG organized an extended public orientation meeting in the village Chikha of Sahckhere

rayon. The meeting was held in the Municipality building and attended by 65 persons: local population, project

affected persons, representatives of Sachkhere and Chikha Municipalities, Design Engineer Company - EPTISA

and UWSCG. The attendees were provided with information on project objectives, outcomes and expected

outputs, scope of impact including the need for land acquisition, expected cash compensation and mitigation

measures.

28. Later the LARP Consultant accompanied by the UWSCG Resettlement Team conducted several more public

orientation meetings with local population and potential APs. The objective of these meetings was to inform

the public on pending activities and surveys required for LARP preparation aiming to ensure that livelihood of

project affected persons, if not improved, would at least be maintained at pre-project levels. The sufficient

amount of adequate information shared with local population through face-to-face meetings, discussions and

question-answer sessions oti ated APs’ illi g ess to parti ipate i the sur e s u dertake et ee May –

June 2017.

8

29. During the seven (7) public orientation meetings held in Chiatura (one meeting), Sachkhere (one meeting) and

five (5) public orientation meetings in village Chikha, during the time period from April 7, 2017 through June 22,

20178. The Consultant, together with the UWSCG Resettlement Team, interacted with the majority of APs (in

total 70 AHs) and shared general information on project objectives, the goals of the pending surveys, and

introduced the general principles of valuation methodology, compensation entitlements, cut-off date, and

eligibility criteria. Additionally, APs were informed about the pending surveys (census, socio-economic and

inventory of project affected assets), and the survey date and time was scheduled at APs' convenience and

availability. The summary table of the Public Orientation meetings held during LARP preparation period is

presented in the Annex 1 in the Section of Appendixes.

30. The Consultant together with UWSCG Project Team conducted a desk review and initial examination of available

data. After transposing project design drawings with NAPR Cadaster maps, the team walked through the entire

project ROW and identified each project affected land parcel in situ. NAPR public records on land tenure and

copies of Receive–Delivery Acts available at the local Municipality have been collected and analyzed.

31. Based on this information, the initial data on APs was developed. The data contained: full names of project

affected land parcels owners, ID numbers and contact details, area of project affected land parcel, and title

registration status.

32. After all project affected land parcels were physically identified and their owners determined, the Consultant

commenced the remaining surveys: census, socio-economic survey, demarcation, and detailed inventory of

project affected assets and valuation; in addition, a thorough title search was conducted for assessment of land

tenure status, deter i atio of APs’ eligi ilit for ash o pe satio , earl ide tifi atio of any absent and

deceased APs.

33. This information has been revised, checked for accuracy and later fulfilled according the findings of census, socio-

economic survey (SES), demarcation, land surveys and title search undertaken during LARP development period.

34. In parallel, qualitative study was undertaken at the project initial phase to gain an understanding of

livelihood patterns of project affected community. The obtained information and insights were used to

design questionnaire for socio-economic survey. The Consultant used open-ended and semi-structured

questionnaires to collect qualitative data. Besides, information was collected through individual in-depth

interviews, focus group discussions with APs and other local residents, to not be affected by the

proposed project. To preserve homogeneity focus group discussions were conducted individually in

each category (directly and indirectly affected) through face-to-face interviews. In-depth interviews

(KIIs) were conducted with the representatives of (i) local municipality, (ii) local executive power, (iii)

NAPR (Tbilisi and Sachkhere), (iv) local business people (male and female) trading in Sachkhere

agricultural market, teachers, and youth.

35. On May 2-3, 2017 the Consultant field tested the form of semi-structures questionnaire to be used for census

and socio-economic data collection. In Chikha village ten (10) randomly selected APs have been interviewed to

test time required for filling in the questionnaire and be confirmed the APs would not be reluctant to answer

the questions and provide the information requested under the questionnaire to be used during census and SES.

8 The detailed information on the public orientation meetings conducted during LARP development period is presented in

Chapter 6 and Annex 1.

9

All ten APs willingly answered the questions. The field testing confirmed that questionnaire was suitable for the

assignment.

36. The Data collected through semi-structured questionnaire with number of open questions equipped the

Consultant with information on lifestyle, cultural and social issues, income and wage patterns, general trends

and current prices at the commodity and real property markets.

37. Based on the qualitative survey findings the Consultant developed initial understanding and sound base for

further planning and undertaking the required studies and surveys.

38. The Census and SES has been conducted during June 1-22, 2017. The objective of the SES, similar to census, was

to cover all project affected households. Privacy policy was followed while interviewing the APs permitting them

to feel comfortable sharing information during the surveys. The Consultant used face-to-face interviews (68 AHs)

and telephone interviews (2 AHs) for AHs being away from their permanent residence during the census/ SES

period.

39. Inventory of project affected assets was undertaken by the Consultant together with the UWSCG Resettlement

Team and independent licensed valuator. Valuation methodology and compensation unit rates were developed

by the valuator and revised by the Consultant. The unit rates and LARP Budget was prepared according to the

inventory results and based on the valuation principles in compliance with IVS, best international practice,

country legislation, and ADB SPS 2009.

Title Search conducted during LARP preparation

40. In the process of LARP preparation during census and title search the legal status of project affected land parcels

have been defined. Thirty-one (31) APs presented updated registration documents, while Thirty-nine (39) APs

presented the title documents registered under the systematic registration undertaken in Georgia in early 2000s.

Noteworthy, under the current legislation prior to land acquisition owner of a land parcel registered during

systematic registration is required to first update the registration based on the Receive - Delivery Acts issued in

90s or Title Certificate issued during Land Reform, whichever is available, to confirm the origination of ownership

status9.

41. The licensed land survey company demarcated and surveyed all project affected land parcels and issued cadaster

survey maps in compliance with the legal requirement. The APs were provided with free cadaster survey maps,

guided and instructed on how to apply to NAPR for updated registration.

9 Georgia, after gaining independence from the Soviet Union, determined private possession on land through disposition and

management of land par els for erl , i “o iet Era used olle ti e far s Kolkhozes su sidized the “tate. Withi the framework of economic reforms undertaken in the country, large land parcels being under collective farms possession and use,

were subdivided into smaller parcels and alienated among the households that did not any more receive agricultural subsidy

from the State. Land Reform in Georgia has been undertaken through several phases, staring from 1992 through 2005 years.

Presently, land parcels registered within the framework of the Land Reform require specifying the coordinates and registration

of corrections to ensure that these corrections are reflected in the NAPR electronic base that is active since 2006 and cover the

entire country.

10

42. The APs submitted documents to Sachkhere NAPR office to update registration of project affected land parcels.

Similar action was undertaken by APs residing in Tbilisi, who applied for registration update to the NAPR Office

in Tbilisi.

43. The UWSCG Resettlement Team put additional efforts to reach out to the APs with suspended registration and

provided them with new and correct cadaster survey maps issued by the survey company.

44. Significant attention and correct approach was used during determination of project affected land parcels

(including portion of a land parcel subject to partial acquisition for proposed project purposes) through the

demarcation of project affected land parcels. Demarcation was undertaken by a licensed company practicing in

the field of land surveys. The surveyors used professional equipment and in situ identified the factual location

of the boundaries of all project affected land parcels located within the ROW. The initial list of APs was double

checked and data added as collected during the census and SES.

45. Members of the household whose project affected land parcel was registered in the name of a deceased owner

were provided with updated cadaster survey maps, accompanied to the NAPR and instructed on application

procedures to update their titles. Most APs accepted UWCSG assistance with gratitude.

46. Overall, title search allowed timely detection of all procedural gaps and identified necessary legal actions and

bureaucrat steps to be accomplished prior to commencement of LARP implementation, and permitted

successful handling of time consuming legal procedures.

47. During demarcation and land surveys of project affected land parcels, no cases of land capture (encroachment)

was observed. All land parcels are registered either during systematic registration or as a result of sporadic

registration10. Although, according to the current legislation, almost 90 % of project affected land parcels will

need to be re-registered prior to land acquisition as stipulated under the active legislation of Georgia.

Magnitude of Project Impact

48. According to the proposed project design, the project construction activities will be carried out on the territory

used for agricultural activities by the residents of village Chikha and entail permanent acquisition of seventy-

seven (77) privately owned rain fed arable agricultural land parcels being under private possession of 70 AHs.

49. The total area of project affected seventy-seven (77) land parcels equals 39,354 sq.m. Among these 77 only

sixteen (16) project affected land parcels (19,147 sq.m.) will subject to full acquisition. The remaining sixty-one

(61) land parcels (with total area of 122,045 sq.m.) will subject to partial acquisition of 20,207 sq.m.) with major

portion of these land parcels remaining outside of the project ROW. The owners of these 61 land parcels will be

10 Title Certificates and/or Receive – delivery acts are the major legal documents verifying private possession/ownership to rural /arable

agricultural land parcels of the households. In case of the given project, the majority of Chikha residents (APs) presented the valid copies of

Receive-delivery Acts. The information on land possession was confirmed with village Chikha Municipality and compared for accuracy with

the information provided from the local archive. Based on the information retrieved from the receive-delivery acts combined with census

data, additional land surveys were conducted by UWSCG professional land surveys. This was free-of-charge service provided to APs. The land

surveys allowed to specify precise coordinates and update registration data in the NAPR. This procedure was undertaken in compliance with

the NAPR requirements. At the starting phase of LARP development the legal procedures and steps to be undertaken during land acquisition

were informally discussed with the key leads of relevant department of the NAPR.

11

able to continue agricultural activities as the remaining portion (101,838 sq.m.) of these land parcels will still

maintain economic viability.

50. Overall, the APs with the residual land, meaning that remaining piece of land which as a result of land take has

lost previous designation and became economically unviable will be eligible to claim full cash compensation for

the entire area of such land parcel.

51. Importantly, land acquisition for project purposes will not cause any need for physical resettlement of affected

households as there are no residential dwellings on these land parcels.

52. The project affected land parcels are exclusively used for farming, producing agricultural produce and sometimes

local people allow seasonal grazing before the start of the plowing and sowing season.

53. The project impact will require demolition of one almost completely ruined structure located on privately owned

land parcel of 400 sq.m. The land parcel is registered in the NAPR as non-agricultural. In 2002 the AP privatized

from the State this land parcel and attached deteriorated structure. This parcel is located right next to other

project affected agricultural land parcels.

54. There are no metal fences or stone walls to be affected by the proposed project.

55. The project will most likely affect seasonal crops as a result of project construction activities that might cause

so e disruptio to APs’ atte pti g to gro seaso al rops o the re ai i g portio of la d par els.

56. Eleven perennials, nine (9) fruit trees and two (2) non-fruit bearing perennials are standing within the ROW on

one (1) project affected land parcels. These perennials, instead of being felled, will be preserved within the

sanitary zone of water reservoir. Since the AP will lose access and right to use these perennials, the AP will be

cash compensated as described in the Entitlement Matrix of this LARP.

57. In addition, there are more perennials growing on the edge of the river Kvirila bank and along the current access

road. These perennials will not be directly affected by the project as they grow outside of the boundaries of

project affected land parcels. None of the APs have claimed ownership rights to these perennials during

demarcation, cadaster surveys and inventory of affected land and assets. Besides, none of the APs confirmed

using these perennials for collection of firewood or fruits11. Therefore, the trees grown along the river bank but

not on private land parcels will not be subject to any cash compensation.

11 Since none of the APs will experience loss of income by losing access to these perennials, these trees are not included in the

cash compensation package developed separately per each project affected land parcel. The purpose of this information is to

ensure that no unfair claim for compensation is made during construction period by any AP or any interested person.

12

58. During LARP preparation significant attention was given to the needs of the disadvantaged, vulnerable groups12

and severely affected13 AHs. These APs were provided with transportation to the project site to attend land

surveys. Legal advisory was provided to female headed HHs on how to apply for update registration of project

affected land parcels. Two single elderly APs were provided with free of charge land survey services for additional

land parcels rather than project affected ones to proceed registration of titles.

59. The summary table below shows the scope of project impact identified based on the project design drawings,

census, socio-economic survey, title search, and inventory of project affected assets, undertaken on site during

the preparation of this draft LARP.

Table 2. Summary of project impact covered under this LARP

Project Affected Unit Number of Units

Land parcel 77

Household 70

Total of project affected persons 158

Vulnerable AHs 13

Severe impact 74

Land parcels to be fully acquired 16

Land parcels to be partially acquired 61

Structure (deteriorated) 1

Land parcels with annual crops/hey 76

Fruit bearing perennials 9

Decorative/timber perennials 2

60. The UWSCG made a decision to prepare LARP for the proposed project ROW. According to the magnitude and

the level of severity of project impact on affected persons and communities, considering the ADB SPS 200914,

the project is suggested to be classified as Category B.

12 Any person who might suffer disproportionately or face the risk of being marginalized from the effects of resettlement and

includes; (i) female-headed households with dependents; (ii) disabled household heads; (iii) poor households (below poverty

line); (iv) landless; (v) elderly households with no means of support; (vi) households without security of tenure; (vii) ethnic

minorities. 13 Severely Affected AHs are those losing 10 % or more of income generating (producing) land/assets as a result of project related

physical and/or economic displacement 14 http://www.adb.org

13

Chapter 2: Socioeconomic Profile of Project Affected Persons

61. Population of village Chikha counts 800 households. The majority of project affected persons are located in

village Chikha. Some AHs hold the land ownership and also keep the residential house in village Chikha, but

permanently live and work in Tbilisi, the Capital city of Georgia. In terms of the magnitude of land take this

project will impact around 8.75 % of the village households.

Age Composition of AHs

62. The Socio-economic profile of the APs is based on the information obtained during census and the results of

socio-economic survey of all located AHs. The total number of affected households (70 AHs) comprise 158

persons (89 male and 69 female). Out of these 158, the underage persons are 14 (5 boys and 9 girls). The average

size of a household is 2.26 persons. However, several households count from six to seven household members.

63. The table below shows the age composition of the APs disaggregated according to gender and age groups of

adults and underage persons.

Table 3: Breakdown of APs according to Age Groups and Gender

Project Affected

persons

Male Female Total

Number % Number % Number %

Adult 84 94.4 60 86.96 144 91.14

Underage (below

18 years) 5 5.6 9 13.04 14 8.86

Total 89 100 69 100 158 100

Occupation and Main Source of Income of AHs

64. Many of the local population is mainly engaged in horticulture (cattle breading) and agriculture. Main annual

crops grown are wheat and corn. Corn stems are used as the main fodder for cattle; wheat is grown for family

consumption, and they only sell a small share of their produce at the local market. Vegetables, mainly potato,

cabbage, carrot, garlic, and onion is grown in the orchards organized in the backyards of the land parcels assigned

for residential purposes.

65. Some AHs are involved in farming, in the local context being associated with horticulture and utilization

agricultural land mainly for growing annual crops to feed the cattle. Both men and women are pre-occupied with

cattle. Most households keep only one cow and several chicken. Mainly men herd the cattle on rotation

schedules. APs collect grass from their land parcels; plus they purchase some hey for winter and use remnants

of food not consumed in the family to surplus daily ration of the only cow, to collect milk and make cheese for

self-consumption or for sale at the Sachkhere agriculture food market.

14

66. Therefore, one of important element for the proposed project is provision of access roads to the remaining

portions of the land parcels so that APs are able to use agricultural machinery to cultivate and collect yield during

harvest period.

67. During key informant interviews, census and socioeconomic survey, most of the AHs confirmed that arable

agricultural land is of vital importance for their livelihood. Anyhow, during the demarcation and re-survey of

project affected land parcels the inventory of project affected assets confirmed that less than half of land parcels

have been cultivated this year. According to the AHs they cannot cover the cultivation costs since the

government stopped issuance of vouchers they used last couple of years for cultivation these land parcels.

68. Few men have temporary jobs in construction and often leave home to earn for leaving. Few men drive cars and

provide taxi services to the villagers. Many of adult men do not have salary-paid employment, therefore placing

a majority of men into the category of interested in full time employment opportunities.

69. Most of the females are housewives taking care of family and children and they also tend to the fields growing

crops. A few have paid jobs as civil servants or assist their family members to run local shops selling consumer

goods.

70. Worth to be noted that AHs did not properly quantify their annual income gained from agricultural activities,

but indicated that they use grown seasonal crops mostly for personal consumption. In terms of cash inflow, they

found it easier to report monthly salary rates, retirement pension, and/or disability aid and regular costs for

food, consumer goods, utilities, communication and health care.

71. The median source of cash flow is retirement pension (180 GEL/month) and State targeted aid for disability (the

amount varies according to the 1st, 2nd, and 3rd category of disability).

72. Overall livestock remains the main source of making a living, and also a reliable source of cash income for most

of the AHs. Though some interviewed persons did not nominate livestock and farming as their main activity, but

rather confirmed that they were looking for stable and regular paid employment.

73. As composed in the table below, the major source of income of AHs is based on the information obtained during

census and socioeconomic survey of 100% of located AHs.

Table 4: Breakdown of PAPs according to their Occupation Disaggregated by Gender

Occupation

Male Female Total

Number

of

Persons

% Number of

Persons %

Number of

Persons %

Farmer 16 17.98 0 0.00 16 10.13

Housewife 0 0.00 29 42.03 29 18.35

Pensioner 17 19.10 26 37.68 43 27.22

Civil Servant 5 5.62 5 7.25 10 6.33

Unemployed 18 20.22 0 0.00 18 11.39

Schoolies 5 5.62 9 13.04 14 8.86

15

Expenses of AHs

74. The biggest share of expenses relates to clothing, health care, purchase of consumption goods and food, plowing

and sowing costs, keeping livestock, and interest rates for swift loans.

Table 5: Breakdown of Percentage Ratio of Average Annual Expenditures of the AHs

AH expenditures Percentage Ratio of AH expenses

Food 32.84

Health care 14.53

Vehicle maintenance 11.08

Utilities 7.27

Clothing 6.17

Bank loan Interests 5.49

Farming & Livestock 4.09

Housing repairs 3.40

Transportation costs 3.36

Education /University 3.07

Telecommunication 2.50

Agriculture activity costs 2.05

Cigarettes /Alcohol 1.64

Consumer Goods 1.33

Internet 0.68

Business Operational costs 0.00

Travel/leisure 0.50

Total 100

Possessions of AHs

75. People in project affected area live in residential dwellings built of bricks and blocks. The houses are mainly two-

storied, 3 to 4 bedrooms, and kitchen, storage and living room on the first level. Besides, all households have

supplementary structures being used as storage facilities, summer kitchens, cattle barns, and bathrooms. Usually

these structures, including latrines, baths and kitchens are built separately with external access. The roofs of the

residential dwellings are mainly newly covered by green or purple metal sheets. For several years the

businessman originally coming from this rayon of Georgia has been providing significant technical and financial

Business/Self-

employed 11 12.36 0 0.00 11 6.96

Hired labor 16 17.98 0 0.00 16 10.13

Working

abroad/out of

region

1 1.12 0 0.00 1 0.63

Total 89 100 69 100 158 100

16

aid to local people. The support included new roof covers, gas heaters, free gas and electricity supply and free

health care in local hospital meeting international standards.

76. Local people possess several land parcels, aside to residential land plots often attached with smaller land plots

used as orchards where they often grow small gardens of vegetables (cabbage, carrots, garlic, onion, beans and

etc.). Majority of AHs have about 2000-4000 sq.m. of agricultural land parcels received during the land reform.

These land parcels are located further from the village settlement but still on the walking distance. The AHs use

them for agricultural activities to grow annual crops and fodder for their cattle.

77. The level of possessed durable goods varied. All AHs have Color TVs and Satellite Dishes. Many AHs have more

than one mobile phone. 52 % of AHs have washing machines. 12 AHs out of 85 keep automobiles. Internet is

only available to 8 AHs. WCs are mainly outside of the residential houses. Hot water is available to most AHs

operating on electricity or wood file. Natural gas and electricity is provided to all AHs. Potable water is provided

from private wells built decades ago by grandparents. Besides, many families receive water through rubber pipes

downstream from the mountain springs. Such self-organized water supply systems are traditional to rural areas,

especially in the villages located in the bottom of the hills. Only limited number of AHs managed to organize

inside the house WCs.

Table 6: Breakdown of the Possession of Durable Assets of AHs

Item Number of AHs %

Color TV & Satellite Dish 70 100.00

Mobile phone 107 152.86

Landline telephone 20 28.57

PC and/or Laptop 10 14.29

Internet 6 8.57

Well in private yard 4 5.71

Gas Heater (being used) 43 61.43

Electric heater 10 14.29

Wood Stove 54 77.14

Washing machine 38 54.29

Refrigerator 65 92.86

Motor cycle 4 5.71

Automobile 11 15.71

Mini tractor 3 4.29

Mini Bus 6 8.57

TOTAL of AHs 70 100

Education and Literacy of AHs

17

78. The level of literacy of AHs is reported to be 100%. The adults (89 male and 69 female) attended secondary

school. Ten (10) females have higher education degrees, while twenty (20) men are University graduates. Six (6)

men managed to obtain technical education and /or /vocational trainings.

Table 7: Sex-disaggregated Education and Literacy Level of Adults Members of AHs

Education/Literacy Male Female Total

Number

of

Persons

% Number

of

Persons

% Number

of

Persons

%

Primary 0 0.00 0 0.00 0 0.00

Secondary 67 75.28 61 88.41 128 81.01

Technical 5 5.62 0 0.00 5 3.16

Higher (university) 17 19.10 8 11.59 25 15.82

Total 89 100 69 100 158 100

Vulnerability among AHs

79. The total of thirteen (13) persons composing thirteen (13) vulnerable AHs have been identified during the census

and socio-economic survey. Five (5) AHs are below poverty line and receive State targeted aid. Six (6) households

are headed by females. Besides, two (2) persons are registered as disabled and receive State aid. Since

vulnerability category is assigned to the household. In total thirteen (13) project affected households are

qualified as vulnerable according to their socio-economic status.

Table 8: Breakdown of Vulnerable APs per AHs

Female Headed

Household

HH Below

Poverty Line APs with disability Vulnerability Index

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

6 5 2 13

18

Indebtedness

80. Several AHs reported bank loan liability and shared the amount of monthly interest rate they are liable to pay to

the lending institution.

Infrastructure

81. Major health care center – newly built clinic with qualified medical personnel and modern equipment is located

in town of Sachkhere, the administrative center of the rayon with the similar name. The secondary school

offering full educational program (12 grades) is located in village Chikha. Sport facilities are easily accessible to

local teenagers. Several Banks, ATMs are provided in the rayon center. Agricultural market, several restaurants,

number of pharmacies, small supermarkets and other trade facilities are organized in the center of Sachkhere,

in close vicinity to Regional Bus Station.

82. Population of Chikha is provided with natural gas supply and electricity. However, in winter time most

households prefer to use firewood for heating and cooking rather and attempt to minimize natural gas and

electivity consumption to keep the utility costs relatively low.

83. Local municipality issues spe ial so alled passes to ea h household allo i g the to olle t fire ood i the designated forest areas.

Women in the Local Context

84. Women are mainly involved in household activities such as horticulture, animal husbandry, and general

household works. Women participate in household decision-making processes and organizing family matters.

During census and socioeconomic survey, female respondents were active and willing interviewees.

85. The majority of affected households are headed by men. The Receive-Delivery Acts are issued on the name of

Household Head. However, during the registration of land parcels distributed and allocated to the HHs, all family

members including parents, spouses and children born before 2006 are recorded at the NARP as the co-owners.

Impact on Minorities

86. No ethnic minorities are among the Project Affected Persons. The APs are primarily Georgian. No group of local

residents showed any specific or unique features that could be identified as a distinct minority group. No impact

on Indigenous People is expected from the Project. The investment program area does not include communities

that may be defined as indigenous peoples under ADB's Safeguard Policy Statement (2009). Consequently, the

indigenous peoples' impact classification for the proposed project is C.

19

87. The project at the construction phase will include appropriate measures to mitigate the potential risk of

HIV/AIDS and other sexually transmitted diseases, as well as drugs and human trafficking. These measures

include raising public awareness and shall be undertaken by Construction Contractor and/or Supervision

Consultant as requested according to the specific contractual agreements.

Chapter 3: Compensation Entitlements

Objectives of Compensation Policy

88. The implementation of resettlement activities is linked to the implementation of the investment component of

the project to ensure that displacement or restriction of access does not occur before necessary measures for

resettlement have been fully implemented and confirmed.

89. As stipulated in SPS 2009 and described in this LARP all project related impacts identified during the relevant

studies should be addressed accordingly, meaning that all project affected persons will be provided with relevant

compensation and other assistance required for relocation, prior to displacement, and preparation and provision

of resettlement sites with adequate facilities, where required. In particular, taking of land and related assets

may take place only after compensation has been paid and, where applicable, resettlement sites and moving

allowances have been provided to the displaced persons.

Compensation Eligibility Criteria and Cut-Off Date

90. Compensation eligibility is limited to AHs by the cut-off date, June 22, 2017. The APs have been informed about

the essence and meaning of the cut-off date and communicated that this is the completion date of the census,

demarcation and land surveys, title search, socioeconomic survey and inventory of project affected assets

undertaken by the Consultant from May 2 to June 22 of the year 2017 in close cooperation with licensed survey

company, UWSCG Resettlement Team, APs and the representatives of local Municipality.

91. All project affected land parcels within the ROW have been surveyed. The results of land parcel survey was

printed out on a large format and displayed in the meeting hall of Chikha Municipality. The cadaster drawing

showed all 77 land parcels. The land parcels were enumerated, the name of landowner and area of the land

parcels was applied on each plot and in the separate table provided on the margin of the same printout.

92. The APs were introduced to the displayed drawing - Cadaster Survey Map - and explained how to identify their

own land parcel. They were invited to identify their land parcels, double check the accuracy and confirm with

personal signature, or report any discrepancy if revealed with regard to the area, location, names of owners of

adjacent land parcels etc.

Photo 1. Cadaster design map displayed in the Meeting Hall of Chikha Municipality

20

Photo 2. APs checking the accuracy of presented data and provide their feedback

93. After all signatures have been applied to the disclosed drawing and all comments and feedback of APs

considered, the relevant corrections have been made to finalize the sequence and area of affected land parcels.

Then the closure date – June 22, 2017 was applied to the drawing and the same date was established as the cut-

off-date for the given project.

94. The cut-off date for the project has been established as June 22, 2017.

95. AHs who settle in the affected areas after the cut-off date will not be eligible for compensation, as they will be

classified as illegal encroachers. These AHs, if any detected within the project ROW, will be given three months

advance notice to vacate premises and dismantle structures, if any prior to project implementation. Their

dismantled structures will not be confiscated and they will not be penalized or sanctioned. Indeed, forced

eviction will only be considered following exhaustion of all other efforts.

96. The LARP determines eligibility criteria of affected households (AHs) and provisions for compensating all types

of impact expected as result of the proposed project. In particular:

a. Loss of entire agricultural land parcel

b. Loss of portion of agricultural land parcel

c. Loss of entire non-agricultural land parcel attached with condemned structure

d. Loss of income from growing seasonal crops

e. Loss of some perennials15

15 There are a number of perennials including fruit trees standing between the land parcels or even outside of land parcel

boundaries. None of the APs claimed ownership or possession of these perennials, or confirmed receiving any income from

21

97. Loss of land will be cash compensated at full replacement cost16 according to current market value as determined

under the Valuation Report17 prepared by the independent licensed Valuator specifically for the given project.

98. The criteria for eligibility to compensation are based on AHs belonging to one of three groups:

a. those who have certified and/or formal rights of use of the occupied land;

b. those who do not have formal legal rights (i.e. legitimate possession) to land at the time of the

census and SES accomplishes but have a legal basis to claim for such land or assets—provided that

such claims are recognized and/or become recognized in accordance with the effective legislation

of Georgia;

c. those who have no recognizable legal right or claim to the land they are occupying (i.e. land users

without registered certificate and informal settlers) eligible for compensation of income and assets

lost but not land18.

99. Where land is to be acquired, land possessors (APs) with registered Certificate and/or AHs not holding Title

Certificates but are eligible to claim for Certificate will be assisted in the process of title registration and receive

full compensation at replacement cost for acquired land.

100. The APs that are not eligible to register ownership title to land pursuant to the rules, laws or any regulations

being in force in Georgia are not eligible for compensation for land but will receive compensation for assets

attached to land and other assistance as described in the Entitlement Matrix.

101. Households headed by single women with dependents and all other vulnerable households will be eligible

for further assistance19 to fully mitigate project impacts.

102. Considering the volume of impact on separate land parcels, all 70 AHs owners of 74 land parcels are severely

affected, as the percentage of land take is more than 10 % in case of partial acquisition and 100 % when entire

land parcel subject to land acquisition for project construction purposes.

103. In compliance with ADB SPS 2009 and this LARP special care20 will be given to vulnerable and severely

affected AHs.

these wildly grown plum trees. However, cash compensation package contains cash compensation for the perennials standing

along the two project affected land parcels. 16 No additional resources of similar land are available to exercise land-for-land compensation (provision of land of equal size

and productive value). 17 Calculation of cash compensation at income capitalization rates was not required due to the fact that real property market

proved to be sufficiently active in the project influence area. 18 According to ADB SPS 2009, AHs falling to the 3rd category beside the cash compensation for loss of assets and income will

receive one-time allowance as additional rehabilitation measure to assist them maintenance of their livelihoods at least to

the pre-project levels.

19 The specific description of further assistance for vulnerable people is described in the Entitlement Matrix provided below in

this chapter. 20 Vulnerable APs will be provided with transportation to the NAPR office to sign Sales Agreement. Besides, UWSCG

will provide necessary technical assistance as needed in the process of LARP implementation and beyond.

22

Compensation Entitlements and Mitigation Measures

104. Entitlement provisions are defined specifically for this project and applicable to APs facing loss of land, assets

and income, incorporate cash compensation at full replacement cost at the current market values in compliance

with the ADB SPS 2009 and active legislation of Georgia.

105. The entitlements are detailed below:

106. Agricultural arable land will be cash compensated at full replacement cost in the amount sufficient to

purchase replacement land of equal in value and productivity in vicinity to the project affected land parcel.

Method for calculation of full replacement cost will include cost of preparation of land to levels similar to those

of the affected land. The taxes and fee related to processing transaction registration will be covered by the

Executing Agency.

107. Non-Agricultural land will be cash compensated at replacement cost in the amount sufficient to purchase

land of equal in value, designation and location in vicinity to the project affected land parcel. Method for

calculation of full replacement cost will include cost of preparation of the land to levels similar to those of the

affected land. The taxes and fee related to processing transaction registration will be covered by the Executing

Agency.

108. "Orphan land": remaining piece of land which as a result of land take has lost previous designation and

became economically unviable. In such case, landowner is eligible to claim full cash compensation for the entire

area of such land parcel.

109. Structures: Structure-buildings (including condemned one) will be compensated in cash at full replacement

cost, i.e. construction cost without any deductions for depreciation, salvaged materials, or transaction costs. The

compensation for houses/buildings will include the cost of lost utility (water, electricity, sewerage, gas)

connections. Construction cost calculation considers market cost of the materials to build a replacement

structure with an area and quality similar to or better than those of the affected structure, or to repair a partially

affected structure, plus the cost of transporting building materials to the construction site, plus the cost of any

la or a d o tra tor’s fees. A appli a le ta es a d fees for tra sa tio registratio ill e o ered the Executing Agency.

110. Deteriorated structure: cash compensation for deteriorated structure was determined based on the

salvaged materials. The ruined remnant of the structure, fragments of remaining walls composed by old

construction blocks and bricks can hardly be used for further construction purposes. Therefore, in given case

evaluation was conducted according to the current market value of the salvaged materials.

111. Fruit bearing perennials: Cash compensation shall reflect income replacement. Cash compensation will be

calculated at current market value and according to type, age, and productive value of project affected fruit tree.

Annual yield capacity of a mature fruit bearing tree multiplied to market price of a fruit (kg/GEL) and multiplied

to the number of years required to grow a new tree to same productivity age.

23

112. Decorative /non fruit bearing perennials: Compensation will be calculated for timber value of decorative

trees and perennials not bearing fruits at current market value and according to type and age of affected tree.

113. Besides, eligible APs will receive additional cash for purchase of seedlings per each project affected tree

including fruit bearing, decorative and timber trees.

114. NOTE: Construction of water supply system does not require any trees to be cut. However several dozen

perennials are standing on the portion of land to be acquired for project purposes to arrange sanitary zone of

the reservoir. Therefore, although these trees will not be logged, the APs will not have access to these perennials.

The loss of access to these perennials will be cash compensated as described above.

115. Annual Crops: Default payment of cash compensation at current market rates for annual crops per entire

area of project affected land parcel. Compensation will be issued even in case the APs have managed to collect

the yield. Crop compensation will be paid to landowners. In case of tenancy agreement, cash compensation will

be paid to owner/tenant based on the specific sharecropping agreements (written/verbal) being made between

these two parties.

116. Community Structures and Public Utilities: If affected, assets will be fully relocated or rehabilitated to meet

their pre-project functions and utilities.

117. Contractor's Temporary Requirements: The civil works contract will require the contractor to be responsible

for the temporary acquisition and reinstatement of all land required outside the road reserve for construction

camps, offices, borrow pits, materials storage sites, materials processing sites, and haul roads. The contractor

will select the land parcels they require and they will be responsible for negotiating agreements directly with

land owners to occupy the land. In the event that a contractor fails to obtain the agreement of a landowner, the

contractor would be required to select an alternative site and negotiate a new agreement. No involuntary

occupation of land for temporary construction purposes would occur. Provision will be made in the civil works

contract for the contractor to be responsible for providing adequate measures to cater for existing traffic while

the construction works are in progress. The contractors shall be required to obtain the approval of the executing

agency for all proposals for traffic management during the construction of the civil works contracts and also they

shall be required to maintain all temporary diversion roads and existing roads used to carry diverted traffic from

the main road.

Additional Rehabilitation Measures

118. The LARP considers additional rehabilitation measures to be provided to AHs that qualify as vulnerable and

severely affected.

119. One-time allowance for vulnerability: In addition to the compensation of lost land and crops, vulnerable

AHs will be provided with additional rehabilitation measures; in particular, one-time allowance set to cash

compensation calculated based on the minimum subsistence monthly income level for the household of five (5)

persons multiplied to 3 months per AH. The amount (1036 GEL per affected household) of compensation are

calculated based on the data retrieved from official website of the National Statistics Office of Georgia –

24

GEOSTAT21. Additionally, the members of vulnerable families will be given priority in employment in project-

related jobs.

120. One-time allowance for severe impact: APs losing more than 10 % of income generating land, in addition

to the compensation of lost land and crops, will be provided with additional rehabilitation measures; in

particular, one-time allowance set to cash compensation calculated based on the minimum subsistence monthly

income level for the household of five (5) persons multiplied to 3 months per AH. The amount (1036 GEL per

severely affected land parcel) of compensation is calculated based on the data retrieved from official website of

the National Statistics Office of Georgia – GEOSTAT22. Additionally, the members of vulnerable families will be

given priority in employment in project-related jobs.

Taxation and Bank Service Fees

121. In no case will the AHs be liable for any taxes and eventual transaction fees; these will be paid by the UWSCG.

Deposit/Escrow Accounts

122. Amount of cash compensation will be deposited on the special account with the UWSCG if during LARP

implementation process any AP is missing, absent, or deceased and issuance of compensation is postponed due

to legal procedures.

Entitlement Matrix

123. The table below describes the Entitlements and additional allowances to compensate all type of income and

assets loss identified in the context of this specific project.

Table 9: Entitlement Matrix

Project

/Affected

Asset

Specification Affected

People

Compensation Entitlements

Permanent

Loss of land

(agricultural

/ non-

agricultural)

All AHs as

owners/legitima

te possessors of

all project

affected land

parcels

independent

from impact

severity

AHs with

registered

/recognizabl

e title

Cash compensation calculated at full

replacement cost at current market

value to be sufficient to purchase

land parcel of equal size, location, soil

productivity /designation to project

affected land parcel.

Method for calculation of full

replacement cost besides the value of

affected asset will also include cost of

preparation of the land to levels

21 http://www.geostat.ge/index.php?action=page&p_id=179&lang=eng. Minimum monthly income subsistence level for the

household of 5 members is 345/30 GEL. In particular: 345.30 X 3= 1035.90 GEL; rounded to 1036 GEL per affected household. 22 Same as above.

25

Project

/Affected

Asset

Specification Affected

People

Compensation Entitlements

similar to those of the affected land.

AHs will be free of taxes, land parcel

sub-division and transaction

registration costs.

The taxes and fee related to

processing transaction registration

will be covered by the Executing

Agency.

All AHs holding

excess (surplus)

land23

AHs who

use more

area then

allocated

under title

documents

Captured land will not be cash

compensated, unless registered in

the NAPR according to the decision of

land legalization commission.

However, any loss of annual crops

and other improvements will be cash

compensated in cash at full market

rate for annual harvest to be paid to

land-user.

Orphan land Any privately

owned land that

will lose previous

designation and

economic

viability as a

result of project

related land

acquisition

All AHs

facing the

risk of

keeping

"Orphan

land"

If proven the loss of economic

viability of remaining portion of land,

AP is eligible to claim full cash

compensation and alienation of the

entire area of such land parcel.

APs interested in full acquisition will

apply to UWSCG (GRC)24. The GRC will

involve local agricultural expert to assess

and determine whether the residual land

is economically viable or not. The

decision of GRC will be provided to AP.

Cash compensation will be calculated

as usual at full replacement cost at

current market value as applicable to

the cases of permanent loss of land

for title holders /legitimate

possessors.

23 Excess (surplus) land refers to the cases when AP uses more area of land than as shown in documents originating land

ownership rights. Such cases will be transferred for the review and approval /rejection of local land legalization commission

prior to updating the registration. 24 If such need arise, UWSCG /GRC may invite agricultural specialist who will assess whether the residual land is or is not economically viable. In

general terms this depends on the size, access, configuration of land parcel and etc.

26

Project

/Affected

Asset

Specification Affected

People

Compensation Entitlements

Agricultural

Sharecroppers

Agricultural

Sharecropp

ers/APs

without

valid

contract

Agricultural sharecroppers will

receive cash compensation in the

amount equal to their share of

harvest at market rates.

Structures Any structure

subject to

demolition for

project purposes

Owners/use

rs of such

structures

(including

squatters)

Cash compensation at replacement

rates for affected structure and other

fixed assets without deduction for

salvageable materials, depreciation,

and transaction costs.

Deteriorated structure: cash

compensation for deteriorated

structure was determined based on

current market value of the salvaged

materials.

Crops

Entire area of all

project affected

land parcels of

agricultural

designation

All AHs

(including

squatters)

Crop compensation in cash at full

market rate for annual harvest to be

paid to land-user or tenant will be

determined based on specific

sharecropping agreements made

between these parties.

Trees Trees affected:

Fruit bearing

perennials

All APs

(including

squatters)

Cash compensation at market value

on the basis of type, age, and

productive value of fruit tree;

Each fruit bearing tree in addition

shall be compensated for purchase of

saplings.

AHs will be eligible to dispose logged

trees themselves. Construction

company ensures free delivery of

timber to the residence of AHs.

Trees affected:

Non-fruit

bearing

perennials

Cash Compensation will be calculated

for timber value of decorative trees

and perennials not bearing fruits. APs

will receive additional cash for

purchase of seedlings per each

project affected tree including fruit

bearing, decorative and timber trees.

Community

Resources

Access shall be maintained or

reinstated;

Rehabilitation/substitution of the

27

Project

/Affected

Asset

Specification Affected

People

Compensation Entitlements

affected structures/utilities (i.e.

bridges, roads, schools, health-

centers, water pipes, irrigation

channels, etc.).

Vulnerable

AHs

AHs below

poverty

line;

disabled

people;

pensioners;

widows;

female

headed

households;

In addition to land and crops

compensation, one-time allowance

set to cash compensation calculated

based on the minimum subsistence

monthly income level for the

household of 5 members multiplied

to 3 months per AH. The amount of

compensation is calculated based on

the data retrieved from official

website of the National Statistics

Office of Georgia – GEOSTAT25.

Besides, the members of vulnerable

families will be given priority in

employment in project-related jobs.

Severe

Impact

Additional

provisions for

severe impacts

(loss of 10% or

more of income

generating land

/assets)

AHs

(titleholders

and/or

without title

but eligible

to claim title

registration,

Leaseholder

,

Squatters

In addition to land and crops

compensation, one-time allowance

set to cash compensation calculated

based on the minimum subsistence

monthly income level for the

household of 5 members multiplied

to 3 months per AH. The amount of

compensation is calculated based on

the data retrieved from official

website of the National Statistics

Office of Georgia – GEOSTAT26.

Besides, the members of severely

impacted households will be given

priority in employment in project-

related jobs.

Temporary

impact

Loss of access to

land parcel

Owners

/Users

Temporary access will be set up by

Construction Company.

Income loss due

to lack of

temporary

Business

units

Temporary access will be set up by

Construction Company.

25 http://www.geostat.ge/index.php?action=page&p_id=179&lang=eng 26 http://www.geostat.ge/index.php?action=page&p_id=179&lang=eng

28

Project

/Affected

Asset

Specification Affected

People

Compensation Entitlements

access road to

the business

activity

Temporary loss

of income

caused by

occupying land

parcels for the

camps and

quarries

Owners/use

rs

During camps' site selection process,

Construction Company should

coordinate with relevant state

agencies and give priority to vacant

lands not used for agricultural

/residential purposes. But in case the

land parcels selected for camps and

quarries will have private land-users,

all losses, and amount of due

compensation shall be determined

according to the principles of

compensation entitlements provided

under this LARP.

Any other

unforeseen

Impacts

As required Any As required, according to the

requirements and principles of SPS

2009 and guided by the approved

LARF and MFF.

29

Chapter 4: Legal-Regulatory Framework

Legislation of Georgia

124. The following laws and Normative Acts regulate land/real property ownership rights, rules and procedures

for land acquisition, and obtaining State ownership right to privately owned land parcels based on the necessary

public needs for infrastructure rehabilitation project purposes.

a. The Constitution of Georgia, August 24, 2995

b. The Law of Georgia on ownership rights to agricultural land, March 22, 1996

c. The Civil Code of Georgia, June 26, 1997

d. The Procedural Civil Code of Georgia, November 14, 1997

e. The Law of Georgian on the Rules for Expropriation of Ownership for Necessary Public Need, July 23, 1999

f. Tax Code of Georgia, 2005

g. Labor Coode of Georgia, May 25, 2006

h. The Law of Georgia on Protection of Cultural Heritage, May 8, 2007

i. The Law of Georgia on Public Health, June 27, 2007

j. The Law of Georgia on Declaration private ownership rights to land parcels under possession (use)

of physical and persons and legal persons of private law, July 11, 2007

k. The Law of Georgia on Public Register, December 19, 2008

l. The Law of Georgia on Notary Activity, December 4, 2009

m. The Law of Georgia on State Property, July 21, 2010

n. The Law of Georgian on Entrepreneurs, October 28, 1994

125. Overall, the above listed laws and normative acts consider compensation of resettlement costs at the market

values. Legislation determines the types of loss subject to compensation and define that compensation should

be issued for damaged assets as well as lost income. Pursuant to the legislation consultations and notifications

are important to ensure participatory involvement of project affected persons in the process of project

preparation and implementation.

126. Under the active legislation, during the implementation of resettlement action plan the following

mechanism are to be undertaken:

a. Acquisition of project affected land and assets located within the ROW through the negotiation and

issuance of defined compensation prior to the commencement of civil works;

b. Exercising the right of expropriation based on the Court decision and after issuance of defined

compensation in case the negotiations fail.

Expropriation

127. Expropriation of project affected land and assets takes place only in case if negotiations fail.

30

128. Process of expropriation is undertaken in accordance to the procedures defined under the law and is

implemented on the basis of the order of the Minister of Economy and Sustainable Development of Georgia and

relevant court decision.

129. The order of the Minister defines the case of public need and grants the Expropriator with the right to occupy

the land. The Court defines the State agency, or legal person public/private law to be granted with the right of

expropriation. Court decision shall also contain detailed inventory of property/assets subject to expropriation

and statement on amount of compensation to be paid to a landowner.

130. Project affected land cannot be occupied until the following is being implemented:

a. Court proceeding is accomplished;

b. Relevant communication with project affected persons after the obtainment of Court restriction

c. Compensation amount is deposited on the relevant account27.

ADB Safeguard Policy Statement

131. The Safeguard Policy Statement on Involuntary Resettlement describes common objectives of ADB's

safeguards, lays out policy principles, and outlines the delivery process for ADB's safeguard policy.

132. The objectives of the IR policy are as follows:

a. To avoid involuntary resettlement, wherever possible;

b. To minimize involuntary resettlement by exploring Sub-Project and design alternatives;

c. To enhance, or at least restore, the livelihoods of all displaced persons in real terms, relative to pre-

Sub-Project levels; and

d. To improve the standards of living of the displaced poor and other vulnerable groups.

133. Scope and Triggers: The involuntary resettlement safeguards covers physical displacement (relocation, loss

of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income

sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions

on land use or on access to legally designated parks and protected areas. It covers them whether such losses

and involuntary restrictions are full or partial, permanent or temporary.

134. ADB Policy Principles:

1. Screen the project early on to identify past, present, and future involuntary resettlement impacts and

risks. Determine the scope of resettlement planning through a survey and/or census of displaced

persons, including a gender analysis, specifically related to resettlement impacts and risks.

2. Carry out meaningful consultations with affected persons, host communities, and concerned

nongovernment organizations. Inform all displaced persons of their entitlements and resettlement

options. Ensure their participation in planning, implementation, and monitoring and evaluation of

27 Treasury escrow account, UWSCG project account or bank account of project affected person.

31

resettlement programs. Pay particular attention to the needs of vulnerable groups, especially those

below the poverty line, the landless, the elderly, women and children, and Indigenous Peoples, and

those without legal title to land, and ensure their participation in consultations. Establish a grievance

redress e ha is to re ei e a d fa ilitate resolutio of the affe ted perso s’ o er s. Support the

social and cultural institutions of displaced persons and their host population. Where involuntary

resettlement impacts and risks are highly complex and sensitive, compensation and resettlement

decisions should be preceded by a social preparation phase.

3. Improve, or at least restore, the livelihoods of all displaced persons through (i) land-based resettlement

strategies when affected livelihoods are land based where possible or cash compensation at

replacement value for land when the loss of land does not undermine livelihoods, (ii) prompt

replacement of assets with access to assets of equal or higher value, (iii) prompt compensation at full

replacement cost for assets that cannot be restored, and (iv) additional revenues and services through

benefit sharing schemes where possible.

4. Provide physically and economically displaced persons with needed assistance, including the following:

(i) if there is relocation, secured tenure to relocation land, better housing at resettlement sites with

comparable access to employment and production opportunities, integration of resettled persons

economically and socially into their host communities, and extension of project benefits to host

communities; (ii) transitional support and development assistance, such as land development, credit

facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as

required.

5. Improve the standards of living of the displaced poor and other vulnerable groups, including women, to

at least national minimum standards. In rural areas provide them with legal and affordable access to

land and resources, and in urban areas provide them with appropriate income sources and legal and

affordable access to adequate housing.

6. Develop procedures in a transparent, consistent, and equitable manner if land acquisition is through

negotiated settlement to ensure that those people who enter into negotiated settlements will maintain

the same or better income and livelihood status.

7. Ensure that displaced persons without titles to land or any recognizable legal rights to land are eligible

for resettlement assistance and compensation for loss of non-land assets.

8. Prepare a resettle e t pla ela orati g o displa ed perso s’ e title e ts, the i o e a d li elihood

restoration strategy, institutional arrangements, monitoring and reporting framework, budget, and

time-bound implementation schedule.

9. Disclose a draft resettlement plan, including documentation of the consultation process in a timely

manner, before project appraisal, in an accessible place and a form and language(s) understandable to

affected persons and other stakeholders. Disclose the final resettlement plan and its updates to affected

persons and other stakeholders.

32

10. Conceive and execute involuntary resettlement as part of a development project or program. Include

the full osts of resettle e t i the prese tatio of proje t’s osts a d e efits. For a proje t ith significant involuntary resettlement impacts, consider implementing the involuntary resettlement

component of the project as a stand-alone operation.

11. Pay compensation and provide other resettlement entitlements before physical or economic

displacement. Implement the resettlement plan under close supervision throughout project

implementation.

12. Monitor and assess resettlement outcomes, their impacts on the standards of living of displaced

persons, and whether the objectives of the resettlement plan have been achieved by taking into account

the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

LARP Principles Adopted for the Project

135. The UWSCG has prepared draft LARP in compliance with the laws and regulations of Georgia and ADB SPS

to serve as the tool to ensure that project implementation process meets the core principles of involuntary

resettlement as listed below:

a. Land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring

all viable alternative project designs;

b. Where unavoidable, a time-bound RP will be prepared and AHs will be assisted in improving or at

least regaining their pre-project standard of living;

c. Meaningful Consultation with AHs on compensation, disclosure of resettlement information to AHs,

and participation of AHs in planning and implementing sub-projects will be ensured;

d. Vulnerable and severely affected AHs will be provided special assistance;

e. Non-titled AHs (informal dwellers or squatters) will receive a livelihood allowance in lieu of land

compensation and will be fully compensated for losses other than land;

f. Legalizable AHs will be legalized and fully compensated for land losses;

g. Provision of income restoration and rehabilitation to all AHs;

h. The RP will be disclosed to the AHs in the local language;

i. Payment of compensation, and rehabilitation measures will be completed prior to the contractor

taking physical acquisition of the land and prior to the commencement of any construction activities

on a particular package; and

j. Establishment of appropriate grievance redress mechanism to solve AHs grievance if it occurs.

k. Internal monitoring and disclosure of reports.28

136. Notice to contractors cannot be given until the UWSCG officially has confirmed in writing, stating that:

Payment has been fully disbursed to the displaced persons and rehabilitation measures are in place; Already-

compensated/assisted displaced persons have cleared the area in a timely manner; and area is free from any

encumbrances.

28 Please see for details the Chapter 8.Monitoring and Reporting Requirements

33

Measures to bridge the gaps between country legislation and ADB SPS 2009

137. The Legal Matrix given in table 10 describes the differences between the legislation of Georgia and ADB SPS

2009 and describes the mitigation measures suggested to bridge these gaps.

Table 10. Legal Gap Analyses and Mitigation Measures

Country Legislation ADB SPS 2009 Mitigation measures

suggested for the proposed

project

Only the owners of registered

project affected structures are

eligible to cash compensation

All owners/possessors of

project affected structures are

eligible to full compensation

The only condemned structure

to be affected by the proposed

project will be valued by

Independent Licensed valuator

and relevant compensation

issued as foreseen in the

approved LARP.

Only the owners of registered

project affected land parcels

are eligible to cash

compensation

Lack of registered title does not

deprive project affected

persons right to loss

compensation

Land titles are already being

updated and prior to land

acquisition all APs will free of

charge receive updated titles

prior to commencement LARP

implementation.

Loss of annual crops to be

compensated only to the

owners of registered project

affected land parcels

Loss of annual crops o be

compensated to APs

notwithstanding the title

registration status

Same as above.

No legal requirement on

compensation loss of

salary/wages/profit as a result

of business stoppage

Business

temporary/permanent

stoppage subject to

compensation to cover the loss

of salary/wages/profit

No business stoppage is

expected within the

framework of the proposed

project.

Law does not regulate the

activity of Grievance Redress

Committee

Grievances to be resolved

informally, through Grievance

Redress Committees, at the

level of local self-government

units, NGOs and/or through

participatory involvement of

local CBOs

Grievance Redress Committee

and two-tier Grievance Redress

Mechanism is already being

established under the UWSCG

to handle grievances,

complaints of APs and of any

third parties and run the

Grievance Log for monitoring

and supervision purposes.

Law does not specify the

requirement on provision of

preliminary information of APs

on compensation eligibility

conditions

APs need to be informed on

compensation eligibility for

project affected assets prior to

appraisal

APs were provided information

on valuation methodology to

determine compensation unit

rates per each type of assets,

income loss; besides, APs were

present and actively involved in

34

Country Legislation ADB SPS 2009 Mitigation measures

suggested for the proposed

project

the process of inventory of

project affected assets.

Law does not require provision

of relocation costs or

additional rehabilitation

measures income/livelihood

restoration for vulnerable and

severely affected persons

Resettled APs need to be

provided with rehabilitation

measures and assisted in the

process of income/livelihood

restoration

Within the framework of the

proposed project all vulnerable

and severely affected persons

will be provided with additional

one-time allowances; besides,

capable household members

will be given priority in

employment in project related

jobs.

Georgian legislation does not

require development of

Resettlement Plan

Prior to issuance of

compensations Resettlement

Plan has to be prepared and

endorsed (No Objection issued

by ADB & Client)

Final LARP will be reviewed and

approved (No Objection

issued) by the ADB and GOG,

prior to commencement of

LARP implementation, i.e. land

acquisition and issuance of

cash compensation to APs.

Georgian legislation does not

require holding Official Public

Consultations

Ongoing public communication

and encouragement of

participatory involvement of

APs in project planning,

implementation and

monitoring is the integral part

of the ADB SPS 2009

To achieve participatory

involvement of APs and raising

awareness of rights,

responsibilities of APs, project

objectives, outcome and

output, including land

acquisition and compensation

procedures number of public

orientation meetings have

been hold. APs have been

active involved in each activity

conducted during LARP

preparation, review, public

disclosure and acceptance of

APs’ feed a k to e incorporated in the Final LARP

submitted for ADB/GOG

review and approval.

35

Chapter 5: Institutional Arrangements

138. The Chapter describes the role, authority, and responsibility of state agencies involved in the process of LARP

preparation and implementation. These agencies are: Executing Agency - United Water Supply Company of

Georgia of the Ministry of Regional Development and Infrastructure of Georgia, Municipality Land Acquisition

and Resettlement Office (MLARO), NAPR, Ministry of Regional Development and Infrastructure, Ministry of

Finance, ADB, NGOs, and consultants.

139. Below are described their roles and responsibilities with regard to the proposed project:

140. UWSCG: Carries responsibility to for all LARP related issues on local and National levels. Besides, the UWSCG

is in charge to:

a. Hire and supervise consultant involved in preparation LARP based on the detailed design;

b. Formation of MLARO in relevant Municipality;

c. Coordination all LARP related activities;

d. Presenting all necessary documents to ensure rapid allocation of resettlement budget and undertaking

further payment of defined compensation amounts to project affected persons;

e. Provision of internal monitoring through supervision consultant

f. Deploying independent monitoring agency, in case such is requested by the ADB

141. MLARO: Involvement in LARP preparation and implementation and coordination of LARP implementation

related activities on Municipality level. UWSCG will join the MLARO composition, together with the following

candidates:

a. Representative of local Municipality

b. UWSCG representative responsible for LARP activities

c. UWSCG local representative

d. Representative of project affected community (population

142. Supervision Consultant: Supervision Agency responsible for construction supervision activities, to observe

and monitor completion of all compensation/rehabilitation payment procedures prior to construction

contractor entering the site.

143. Ministry of Finance: Allocates compensation and rehabilitation funds based on the submitted land

acquisition and resettlement plan and relevant budget.

144. UWSCG will supervise the economic displacement of APs, monitor construction and reinstatement process

with support from the supervision consultant. The institutional arrangement for the Project implementation is

presented in the following figure.

36

Chapter 6: Public Consultations and LARP Disclosure

Public Consultation Meetings

145. The public consultation meetings have been conducted since the early phase of LARP preparation. The public

meetings were open to any interested person including population from project affected village, representatives

of local government, municipality of Sachkhere and Chiatura, and NGOs were invited to attend the meetings

too.

Table 11. Brief review of public orientation meetings held during LARP development period

No Date Location Lead No of

Attende

es

Target

Audience

Topics Discussed Meeting

outcome

1 April

7,

2017

Chikha of

Sachkhere

Municipalit

y

UWSCG,

PIU

65 Sachkhere

Municipality

,

Project

Stakeholder

s

Introduction of project

design, output and outcome

Participatory

involvement and

support of the

local

government

2 April

7,

2017

Chiatura UWSCG,

PIU

12 Chiatura

Municipality

,

Project

Stakeholder

s

Introduction of project

design, output and outcome

3 April

16,

2017

Chikha PIU, LARP

Consultan

t

36 Chikha

residents,

potential

APs

Scope and objectives of the

project; expected impact on

APs, importance of surveys

required for LARP

preparation, compensation

eligibility and entitlements

Potential APs

agreed to

participate in

census, SES and

land surveys 4 April

17,

2017

Chikha PIU, LARP

Consultan

t

28 Chikha

residents,

potential

APs

5 May

4,

2017

Chikha PIU, LARP

Consultan

t

32 APs,

Representati

ves of

Chikha

Municipality

Importance of inventory,

demarcation and land

surveys of project affected

parcels in presence of APs

Participatory

involvement of

APs in inventory,

demarcation and

surveys achieved

and scheduled in

agreement with

APs

6 May

5,

2017

Chikha PIU, LARP

Consultan

t

56 APs,

Representati

ves of

Chikha

Municipality

7 June

22,

2017

Chikha PIU, LARP

Consultan

t

70

APs Displaying the Cadaster

Survey Map showing the

actual results of

demarcation/land surveys

and reveled discrepancies

requiring to be corrected in

the records of NAPR.

APs agreed to

accept technical

assistance

offered from

UWSCG and

submit new

survey cadaster

maps free-of

charge provided

to APs together

37

with application

for update

registration data

at the NAPR.

146. All participants were provided with information on pending project and introduced to the safeguards

principles of ADB SPS 2009.

LARP Public Disclosure

147. The Final Draft LARP has been publicized during the LARP Disclosure period for review and comments by

project stakeholders. The draft LARP Public Disclosure meeting was held on January 16, 2018. The Notification

on the location, time and date of Public Disclosure was provided to APs together with the copy of Information

Pamphlet through the local Municipality personnel. Besides, the relevant notifications were displayed on the

Information Desk in the lobby of the Municipality buildings in Sachkhere and village Chikha. The Notification

were made early enough to enhance attendance of any interested person, APs, government agencies and NGOs.

148. The final version of the LARP in English will be disclosed on ADB website29. Georgian versions will be

uploaded on UWSCG website30 and hard copies be made available in Sachkhere and Chikha Municipalities.

149. The Information Booklet summarizes essence of cut-off date, compensation eligibility criteria, brief review

of valuation methodology and compensation entitlements, project schedules and implementation features, and

the rights and responsibilities of APs and other project stakeholders, grievance redress mechanism and

monitoring patterns.

150. The English version of the Information Booklet is presented in the Annex 5 of this LARP.

29 www.adb.org 30 www.water.gov.ge

38

Chapter 7: Grievance Redress Mechanism

Objectives

151. The Grievance Redress Mechanism (GRM) is a process through which the affected people may voice and

seek resolution of concerns throughout the entire project cycle. In this project, the grievance redress mechanism

is in place by which the affected people will be fully informed of their rights and procedures for addressing

complaints whether verbally or in writing during consultation, DMS, and at the time of receiving compensation

and resettlement assistance.

152. The UWSCG has functioning GRC and mechanism for grievance redress established under the UWSCG Order

No 12231, dated April 30, 2014 developed in compliance with the Article 8, paragraph 7 of the UWSCG Charter.

153. Grievance Redress Commission (GRC) is being established, fully functioning and provided with required

administrative support by PIU through the entire project circle including the LARP implementation, construction

and operations period.

154. The role and responsibility of the GRC is to accept claims and complaints, assess its validity, determine the

scope of eventual impacts, and timely resolve the issue, including the claims regarding the compensation and

maintain grievance redress mechanism as flexible and efficient mechanism to address and resolve the claims as

raised during project planning and implementation period.

Mechanism exercised to address grievances within ADB funded projects

155. The UWSCG has establish three-phased (three-tiered) Grievance Redress Mechanism to be applied during

processing the grievances submitted by project affected persons (hereinafter as named in the i terested parties duri g the i ple e tatio for ADB fu ded proje ts.

156. 1st Phase: Subscribers Service Centre32 of the UWSCG Local Office will accept oral and written

claims/complaints submitted by interested person and review within two-week time period.

157. The authorized representative of UWSCG local Service Center of UWSCG is authorized obliged to review

and register a complaint according to the format approved in Annex 1 of the Order No 122 and in order to

resolve the problem raised in a complaint coordinate with the following persons:

a. Head of the local Service Center (Director/Manager);

b. Representative of the Department for International Procurement and Relationship with Donors;

c. Representative of the Department for Environment Protection, Resettlement and Permits;

d. Representative of Construction Contractor

e. Representative of Supervision Company.

158. 2nd Phase: in case the complaint is not resolved at the 1st Phase, complainant, seeking timely and efficient

31 UWSCG Order No 122 on Mechanism for Redress Grievances within the Framework of ADB funded projects. 32 UWSCG runs 50 Service center in various Municipalities of Georgia.

39

review and resolution of the complaint, is eligible to address the Grievance Redress Commission.

Composition of the Grievance Redress Commission:

159. The Grievance Redress Commission33 (GRC) is formed under the paragraph 5 of Order No. 122 with

following composition:

a. Representative of local municipality - Chairman of the Commission

b. Manager/Director of UWSCG Service Centre

c. Representative of Investment Project Management Department of UWSCG

d. Representative of local respected NGO

e. Female representative of persons affected by the sub-project

f. Informal representative identified by the population affected by the sub-project34

160. The CRC shall meet ad-hoc to review any complaint not resolved at the 1st Phase. The GRC shall review and

resolve the issue raised in the compliant within two-week time period from the date of grievance registration.

161. 3rd Phase: Interested person is eligible to apply to ADB to the address provided below, in case the GRC fails

to resolve problem raised in the complaint and grievance still remains unresolved after two-week time period

since its official submission.

Asian Development Bank Georgia Mission

1, G. Tabidze St; Tbilisi Georgia

Tel: + 9995 32 225 06 19

162. IMPO (Investment Program Management Office) will ensure provision of relevant trainings35 to designated

staff of Local Service Centers of USWCG on how to proceed and address grievances. Representative of the local

service center responsible for GRM has to be acquainted with Environmental Management Plan and mitigation

measures to identify what type of Claims has to be considered under GRM. In addition, Grievance Log36 and

enough supply of blank Grievance Forms37 will also be provided.

163. Responsible person assigned at the local service center will register grievances in the Grievance Log.

Temporary offices located at the construction sites also keep the Grievance Log to allow aggrieved person file

the claim right on spot.

164. Contact Details (telephone numbers and full names of persons in charge) and the daily hours for receiving

phone calls of APs and any interested person is included in the Information Booklet and also displayed on Public

Information Boards in the Local Service Centers and Municipalities within project affected area.

33 In each city there is one Commission and members of the Commission do not change in accordance with the content of the

complaint. 34 A representative of the affected community 35 UWSCG ensures that on-job trainings are provided to every new employee of local service center to be responsible for GRM

operations. These on-job trainings are provided by USIIP and Supervision Company environmental specialists soon after hiring

of a new employee. 36 Sample attached in Annex 4. 37 Sample attached in Annex 3.

40

Grievance Resolution Process Cycle

165. The complaints and grievances from the APs will be addressed through the process described below:

Phase Action

Level

Process Timeline

1st

Phase

UWSCG

Local

Service

Center

The designated person at the UWSCG Local Service

Center will first give hearing to the aggrieved person,

then register the grievance and assign registration

number. Then he/she will inform about the grievance

upper level person to the local service center

responsible for grievances, and circulating the

document exchange intranet the grievance is provided

to UWSCG Department of International Procurement

and Donors Relationship, Department of Environment

Protection, resettlement and Permits; besides he/she

contacts the representatives of the Construction

Contractor and Construction Supervision Company.

2 weeks

2nd

Phase

UWSCG

GRC

In case the complaint is not resolved on the 1st Phase,

AP (complainant), seeking timely and efficient review

and resolution of the complaint, is eligible to address

the Grievance Redress Commission.

After receiving written complaints of AP, the GRC will

review and prepare a Case File for GRG hearing and

resolution. A formal hearing with GRC will be scheduled

in agreement with aggrieved AP. Liaison persons

assigned by the PIU will keep communication with AP to

schedule meetings, advise AP submission of additional

supporting documents or proves to support his/her

claim, collect such documents presented by AP and

present to the GRC during formal hearing. Besides, the

support includes assistance in preparation written

complaint to GRC, if required.

The decisions from majority of the members will be

considered final from the GRC and will be issued to AP

after signed by GRC members. The case record will be

updated and the decision will be communicated to the

complainant within 14 days of submission.

2 weeks

3rd

Phase

ADB

Georgian

Mission

In case the GRC fails to resolve problem raised in the

complaint and grievance still remains unresolved after

two-week time period since its official submission, the

interested person is eligible to apply to Asian

Development Bank Georgia Mission.

41

166. Any physical and legal person, any appellant can communicate his/her concern to the Court at any stage of

grievance redress. The GRC will not influence or restrict the AP from applying to court for legal remedies.

167. If the complaint is found invalid, the GRC formulates a response and sends a written letter to the

complainant, explaining the reasons of rejection. The complainant can appeal the decision and bring the case to

the local Court.

42

Chapter 8: Monitoring and Reporting Requirements

168. The Project will establish systems for internal monitoring and evaluation. The main purpose of the

monitoring and evaluation programme is to ensure that resettlement and acquisition of land and properties

have been implemented in accordance with the pro isio of ADB’s “P“ 2009, the la s of Georgia a d ith this LARP.

169. The objectives of the monitoring and evaluation programme are:

a. To ensure that the standard of living of AHs is restored or improved;

b. To monitor whether or not the time lines are being met;

c. To identify problems or potential problems;

d. To identify immediate/rapid response methods to mitigate problems or potential problems; and

e. To ensure that the GRM is functioning and grievances, if any, are being addressed timely and

effectively.

Internal Monitoring

170. The UWSCG will conduct monitoring and assessment of the given project.

171. To achieve the main purpose and objectives of internal monitoring the UWSCG will ensure to provide

significant attention to the following aspects of project implementation process:

a. Frequency and quality of information campaign and consultations hold for project affected people

b. Status of land acquisition and payments of compensations for project affected assets

c. Status of provision of additional rehabilitation and mitigation measures

d. Close monitoring of complaints and grievance management.

Reporting Requirements

172. The results of internal monitoring during LARP implementation as well as project related construction

activities will be communicated with UWSCG, Ministry of Infrastructure and ADB through the quarterly project

implementation reports.

173. The information on possible social/economic impact incurred during earth works and project construction

activities will be collected directly from the field by the Supervision Consultant and will be reported through the

project Coordinator at the UWSCG HQ on a monthly basis.

174. These monthly reports will then be quarterly consolidated by UWSCG and submitted to Ministry of

Infrastructure and ADB.

43

Chapter 9: LARP Implementation Schedule

175. The LARP preparation and implementation schedule is described in Table 9 below.

Table 12. Implementation Schedule for May, 2017 – March, 2018

Activities/ Months May June July Aug Sept Oct Nov Dec Jan Feb Mar

2017 2017 2017 2017 2017 2017 2017 2017 2018 2018 2018

Preparation of Initial LARP

Public Orientation Meetings

Enumeration, demarcation and

survey of project affected parcels

Census, SES, Inventory

Title Search

Deploying Valuator /Inventory &

appraisal

Data analyses

Developments of initial LARP &

tentative budget

UWSCG & ADB review, provision

comments to initial draft LARP &

Budget

Incorporating comments &

announcement of LARP Public

Disclosure

UWSCG & ADB No Objection for

LARP implementation

commencement

LARP Implementation - Land

Acquisition & Issuance of

Compensations

Technical Assistance to APs

(registration updates, legal

consultancy)

Negotiations & Cash Compensation

of AHs

Processing Sales Agreements &

Issuance of Compensations

Internal Monitoring, .Resolving

outstanding issues & grievances

Construction Contract award

44

Chapter 10: Compensation Unit Rates and LARP Budget

176. The independent licensed valuator has been deployed to prepare Valuation Report and determine compensation unit rates

per each type of affected asset and income loss.

177. The Valuation Report describes the methods used for determination of compensation unit rates as replacement cost at

current market values. The Valuation Report developed in Georgian language is being presented to the UWSCG and is

readily available upon request of interested APs.

178. Besides, the description of approaches exercised during determination compensation unit rates are summarized in the

Information Booklet specifically designated for APs. The Information Booklets will be individually distributed to AH.

Together with Information Booklets, they will received One-page Description document prepared separately for each

project affected land parcel and reflecting the breakdown of cash compensation package individually handed to the AP.

179. The unit rates for assets (land, structure, perennials) and income loss (annual crops) are defined under the Valuation Report

prepared by the independent licensed valuator. Whereas, the amount of one-time allowances, in addition allocated to

severely affected and vulnerable APs, are defined based on the principles of RPF, ADB SPS 2009, and the good practice

examples.

180. Below is presented the summary table of LARP budget calculated based on suggested compensation unit rates.

181. NOTE: The Detailed Compensation Package provides the breakdown of compensation package per types of impact and

compensation items separately for each project affected land parcel. The information presented in this table is designed

for official use only and does not subject to public disclosure38.

Table 13: Budget for Cash Compensation for AHs and LARP Implementation

# Compensation Item Quantity Unit Measure Unit Rate (GEL) Total per Item

(GEL)

1 Agricultural land 38,954 sq.m. 12 467,448

2 Non-agricultural Land 400 sq.m. 12 4,800

3 Sub-total of land replacement 39,354 Sq.m. 12 472,248

4 Replacement cost for deteriorated

structure (100 sq.m.) 1 sq.m. 290 290

5 Sub-total of structure 100 Sq.m. N/A 290

6 Replacement value for fruit bearing

perennials (sour plu , i.e. Tke ali 4 number 143 572

7 Replacement value for hazel nut bushes 5 number 130 650

8 Timber value of project affected perennial

(Hornbeam) 2 number 130 260

9 Purchase of best quality saplings 11 number 15 165

38 Full names, contact phones numbers, and detailed cash compensation package (per AP and compensation items) is provided

as a separate document for internal use during project implementation, monitoring, and assessment process. To protect the

confidentiality of personal information of APs the document will not be subject to public disclosure.

45

# Compensation Item Quantity Unit Measure Unit Rate (GEL) Total per Item

(GEL)

10 Sub-total for compensation for affected

perennials 22 number N/A 1,647

11 Annual Crops (corn) 22,067 sq.m. 0.4 8,827

12 Annual Crops (wheat) 39,948 sq.m. 0.4 15,979

13 Annual Crops (corn and beans) 12,720 sq.m. 0.55 6,996

14 Annual Crops (pumpkin) 65 number 2 130

15 Perennial crops (Lucerne) 1,800 sq.m. 0.14 252

16 Annual crops (hay) 60,064 sq.m. 0.12 7,208

17 Sub-total of crops compensation N/A Sq.m. N/A 39,392

18 Vulnerability 13 AHs 1036 13,468

19 Severe Impact 74 Parcels 1036 76,664

20 Sub-total of one-time allowances N/A 90,132

21 Total of Cash Compensation 603,709

22 Contingency (20%) 120,742

23 TOTAL of LARP Compensations (GEL)

724,450

Additional LARP Implementation Costs

24 Registration of subdivided land parcels 61 number 102 6,222

25 Registration of Sales Transaction 77 number 51 3,927

26 Sub-total of registration costs 10,149

27 Contingencies during registration (20 %)

2,030

28

Income tax (20 %) to be added to

Compensation Amount excluding the

price for land acquisition 39

26,292

29 Total Implementation costs 38,471

30 SUM of Total Expenses GEL 762,921

31 SUM of Total Expenses in USD

281,521 At Exchange Rate 1 USD -2.71 GEL

39 mount of land acquisition is deducted from the total Compensation Amount as sales transactions will not subject to Income Tax

46

Appendixes

47

Annex 1. Review of Conducted Public Consultations

Table 14. Questions raised by the APs during public orientation meetings and the answers provided

# Name of AP Question raised Answer provided by LARP Consultant and UWSCG

Resettlement Team

1 This question

was asked by

many APs

When is expected the

commencement of

Construction

activities?

Civil works and construction activities will start after the

Construction Contractor and Supervision Company are

selected through International tender and the relevant

contracts are awarded.

2 This question

was asked by

many APs

How long will the

construction process

last?

Tentatively the construction process will last a year and a

half, more specifically the total of 540 calendar days.

3 This question

was asked by

many APs

Will there be any job

opportunity for local

residents?

According to the proven practice, construction

companies are keen to hire local people with relevant

skills and work experience.

Besides, the LARP will recommend that family members

of severely affected and vulnerable AHs to be given

priority in employment in project-related jobs.

4 Mrs. Izolda

Zabakhidze

Mr. Vazha

Tsukhishvili

How will be

determined

compensation

amount?

The Licensed Appraiser will evaluate the full market value

of your land parcels in accordance to the relevant

legislation of Georgia and International Valuation

Standards and in compliance with the ADB Safeguards

Policy Statement 2009. The market value will be based on

the comparison analyses of current market data; in

particular the most recent sales prices of arable

agricultural land parcels located in vicinity of project site.

No land acquisition process will start until the Draft LARP

is publicly disclosed, compensation entitlements

introduced to you and your feedback, comments

obtained and considered in the FINAL LARP.

5 Mrs. Lia

Lominashvili

I need to buy two flats

for my student

children; will I be able

to buy a flat in Tbilisi

with the

compensation

amount issued for

our land parcels?

The Licensed Appraiser will evaluate the full market value

of your land parcels in accordance to the relevant

legislation of Georgia and International Valuation

Standards and in compliance with the ADB Safeguards

Policy Statement 2009. The market value will be based on

the comparison analyses of current market data; in

particular the most recent sales prices of arable

agricultural land parcels located in vicinity of project site.

In any case, as soon as the Draft LARP and Budget is

prepared official disclosure will take place. The date, time

and place of Public Disclosure meeting will be notified to

each of you, so that you attend, get introduced to the

compensation entitlements, valuation methodology, unit

rates for each type of impact and composition of cash

Compensation package.

Anyone of you will be invited to participate in discussion,

comments and suggestions. Your position will be taken

48

# Name of AP Question raised Answer provided by LARP Consultant and UWSCG

Resettlement Team

into close consideration and if reasonable relevant

amendments will be made to the Final LARP, which will

be made publicly available prior to commencement of

LARP implementation.

6 Mr. Ramaz

Tsukishvili

Our land parcels are

all similar, used for

growing annual

crops; We suppose

that market value of

these parcels should

be similar, meaning

that unit rate per

square meter of land

will be the same for

all, but price will

differ because of the

square meter of a

land parcel.

Thank you for correct statement. Land parcels located

within the project ROW are homogeneous; They are of

similar designation in terms of the land use capacity,

productivity, accessibility and location. Therefore, we

also expect that Licensed Valuator will follow similar

approach and determine one unit rate for land. However,

annual crops, will be evaluated separately, according to

the type of crops each of you grow; in addition any

perennials (although only three of you have trees

standing on your land parcel) will be evaluated at full

replacement cost and cash compensated will be paid in

addition to land and annuals crops compensation.

7 Mr. Pridon

Tsukhishvili

During and after

construction period

how will we get to our

land parcels, we

mean the access road

on foot and by car?

Prior to any civil works or construction activities the

Construction Company will arrange access road for

vehicles to allow you harvest the crops; besides, the

existing pedestrian access will also be maintained, with

slight detour to avoid the boundaries of project

catchment boundaries, so that you are capable to walk to

your parcels for cultivation purposes as well.

8 Mr. Giorgi

Nozadze

The area for the

access road will be

allocated from the

land the UWSCG will

acquire from us, or

we will have to

release extra portion

of land to organize

access road to the

remaining portion of

land parcels after

land acquisition is

accomplished?

The UWSCG will allocate sufficient area/territory to

organize access road, both for vehicles and walking path

for pedestrians out of the land acquired from you for

project purposes.

You will not have to release any extra land from the

remaining portion of land for access road purposes.

Access road will be organized by Construction Company

and Supervised by Construction Supervision and UWSCG.

9 Gela Katsitadze What if our crops we

will grow next year on

the remaining portion

of land parcel is

damaged during

construction

process?

If such damage is incurred during the construction period,

a landowner is encouraged to take advantage of

grievance redress mechanism and visit UWSCG local

service center to register the grievance.

The claim will be revised, on spot examination

undertaken and relevant compensation issued to

reimburse the loss incurred by damage caused during

construction process.

Amount of compensation will be determined according to

the principles of compensation entitlements provided

under the approved LARP for the proposed project.

49

# Name of AP Question raised Answer provided by LARP Consultant and UWSCG

Resettlement Team

10 Mr. Zaza

Tsukhishvili

Mrs. Zina

Chighladze

Will we be able to

harvest the crops

prior to

commencement of

construction

activities?

Most likely you will have sufficient time to collect your

yield prior to commencement of construction activities.

In any case, the LARP will consider one year cash

compensation for annual crops according to the entire

area of project affected land parcels.

50

Annex 2. Minutes of LARP Disclosure Meeting

Minutes of the Public Disclosure Meeting

Land Acquisition and Resettlement Plan prepared for Chiatura Water Supply System Construction financed under the

Urban Service Improvement Program (USIIP Tranche 6)

Date: January 16, 2018

Location: Meeting Hall of Sachkhere Municipality

Participants:

Zaza Sikharulidze – Deputy Director for Technical Issues, UWSCG

Maka Goderdzishvili - Head of the Environment Protection, Resettlement and Permits, Lela Shatirishvili - Resettlement

Consultant for ADB funded Chiatura Water Supply System Construction Project

Beniamin Palavandishvili – Mayor of Sachkhere Municipality

Paata Nadiradze - Mayor of Chiatura Municipality

Levan Ivanashvili - Head of Sakrebulo at Sachkhere Municipality

On January 16, 2018 an official Public Disclosure Meeting was held in Sachkhere Municipality (Meeting Hall) on the Final Draft

LARP of Chiatura Water Supply System Construction financed under the Urban Service Improvement Program (USIIP Tranche 6).

The Public Disclosure Meeting was attended by representatives of UWSCG, Municipality and Sakrebulo of Chiatura and

Sachkhere, ADB Georgia Mission, construction supervision company Hill International Temelsu J.V, independent licensed

valuator and project affected persons.

Mr. Zaza Sikharulidze, Deputy Technical Director at UWSCG, and the Mayors of Chiatura and Sachkhere municipalities opened

the meeting. The opening speech was followed by Mr. Zaza Sikharulidze, who briefed the audience on the objectives of Chiatura

Water Supply Construction project and its importance for the population of Chiatura city.

Maka Goderdzishvili, Head of Environment Protection, Resettlement and Permits of UWSCG introduced Lela Shatirishvili, ADB

Resettlement Consultant for Chiatura Water Supply Construction Project.

Lela Shatirishvili made a presentation in power point and briefly described major aspects and objectives of Chiatura Water

Supply System Construction Project LARP prepared in compliance with ADB SPS 2009, LARF and active legislation of Georgia.

She described the activities undertaken during LARP preparation and highlighted their importance to develop fair compensation

package for each and every project affected household. She also touched upon the method of calculation of compensation unit

rates for annual crops, perennials and replacement saplings; spoke about additional one-time allowance allocated for vulnerable

households and owners of severely affected land parcels.

The presenter briefly reviewed valuation methodology, calculation of replacement value at market prices and the composition

of the compensation package. Additionally, she once again explained the importance of the cut-off date, June 22, 2017 as

defined for the given project; touched on the legislative instruments of country active legislation as used in general practice

during implementation of land acquisition and resettlement projects.

At the end of the presentation, reference was made to the Grievance Redress Mechanism and Grievance Redress Commission

operating within the company and being available for any interested person.

At the completion of presentation, Information Booklets were distributed to every AP.

51

After the completion of presentation, the panel opened a question-answer session. (Annex 1).

During the question-answer session, two project affected persons, Lia Lominashvili and Liza Mosiashvili, at first expressed

discontent with the land price. Maka Goderdzisvili, the Head of Environment Protection, Resettlement and Permits invited Lia

Lominashvili to have a closer view at the drawi g of ROW displa ed i the Meeti g Hall. After the AP’s prior o se t, Ms. Goderdzishvili once again publicly explained the breakdown of full composition package of the given land parcel. Ms.

Goderdzishvili clearly showed that aside to land compensation, all other types of project impact to this specific land parcel, such

as loss of annual crops and severe impact to the land parcel were calculated separately and counted into the full compensation

package.

After additional discussion on the composition of cash compensation package, project affected persons expressed that full

compensation package including land compensation unit rate-12 GEL per square meter was satisfactory.

In the closing phase, the UWSCG once again voiced that the company will put all efforts to ensure LARP implementation

procedures were held smoothly through meaningful negotiations with APs.

The official Public Meeting was then closed.

52

Annex 1

N

Question asked by

Question

Answer

1 Demur Tsukhishvili What is price identified for land acquisition, i.e. what will

be the price on one square meter of land?

Zaza Sikharulizde: Land compensation has been determined

according to the location, designation and productivity and

based on the current market price comparison approach.

Considering that project affected land parcels located is the

mail source of income for local population, during evaluation

the upper limit of price range was defined, that is 12 GEL per

one square meter of land.

2 Demur Tsukhishvili

Will any other compensation issued to the owners of land

parcels not cultivated by the moment of inventory?

Zaza Sikharulidze: As described in the LARP prepared by

UWSCG owners of project affected land parcels that were not

cultivated by the moment of inventory will receive cash

compensation for hey calculated according to the entire area of

the land parcel.

3 Imeda Chitadze This land parcels are major source of income for local

population, what should we do now?

Maka Goderdzishvili:

UWSCG took into consideration that land parcel subject to

acquistion are main source of income for local population.

Therefore, project impact to land parcels has been minimized.

Larger portion of land will still remain under private ownership

and will maintain pre-project designation and value.

4 Lia Lominashvili Population did not expect such a low price? According to

what were the land parcels evaluated?

Mindia Tabaghua: In general, land market value is determined

according to the market price comparison approach; i.e.

through research and analyses of the most recent sales prices of

land parcels of similar designation, location and ect.

In addition, we studied the listings, obtained the information

of recent transactions and conducted analyses of sales prices.

For the given project we studied land sales prices at the local

market. Besides we took into consideration that in real terms,

often pushed by some circumstances, potential sellers agree to

lower sales price. In addition, we obtained various listing

announcements and information on auctions. As a result of

data analyses and price comparison approach

53

N

Question asked by

Question

Answer

It was determined that 12 GEL per sq.m. is the most optimal

value for land and will be fair replacement value for project

affected land parcels.

5 Liza Mosiashvili Will there be any access road to get to the land parcels?

Maka Goderdzishvili: UWSCG will ensure to organize access

road to the land parcels

54

40

40 For public meeting, see the following link: http://water.gov.ge/news/full/1337

55

56

57

58

59

60

61

Annex 3. Grievance Form

Grievance Form

Section of Complainant:

Full Name:

_________________________________

_________________________________

Mailing/Permanent Residence Address:

Village: ---------------------------------------------

Municipality: -------------------------------------

Preferred option of communication: Mark

with X

Response mailed to:

______________________________

Face-to-face meeting in GR Focal Point

______________________________

Contacts

Mobile: ------------------------------------------------

Landline: ------------------------------------------------

E-mail: ------------------------------------------------

Language for Communication (mark with X) Georgian

Other_____________________ (please specify)

Complain submission date: Date of hearing:

Please, describe the reason of your discontent or claim in details. Use extra pages if needed.

Present copies of the relevant documents, if available

62

Complainant

Full Name:___________________________

Signature: ___________________________

Date: _______________________________

Received by:

Full Name:________________________

Signature:__________________________

Date: ____________________________

Annex 4. Sample of the Grievance Log

Grievance Log

No Date /

Location

Name of

Complainant

Contact Details

Details of Complaint

Investigation / Mitigation

Action

Resolution

Status*

63

*Open or Closed (If closed include date)

Filed by PIU Environment Specialist::________________________________________________ Date:___________________________

64

Annex 5. Information Booklet

Information Booklet For Land Acquisition and Resettlement Plan

Of

Chiatura Water Supply System Construction Project GEO: CHI-01

Dear Reader,

This Information Booklet is developed for you to share the information about the Project for Construction and Operation of Chiatura Water Supply System. This public

document briefs the important activities defined in the Land Acquisition and Resettlement Plan (LARP) prepared in compliance with the legislation of Georgia and the

guidelines of the Social Performance Statement of the Asian Development Bank (ADB SPS 2009).

Project Overview and Scope of Impact

Chiatura Water Supply System Construction Project41 is implemented within the framework of Urban Service Improvement Investment Program (USIIP Tranche 6),

financed by the government of Georgia and Asian Development Bank. Project Executing Agency is United Water Service Company of Georgia LLC.

The results of hydrological investigation conducted during preparation of Chiatura Water Supply System rehabilitation design, confirmed that the most suitable area

for drilling the exploration boreholes for Chiatura water supply is the studied area located parallel to the river Kvirila on the terrace, at the distance of 150 meters from

the river. To supply the city with 75 l/sec of water extraction, it is sufficient to drill seven (7) boreholes at 50 m distance from each other.

According to the final design, the total area of land allocated for boreholes, i.e. project ROW will comprise 3.94 hectares of agricultural land. In particular, 77 agricultural

land parcels owned by the residents of village of Chikha in Sachkhere rayon. Among these 77 land parcels 16 land parcels will be fully acquired, while 61 land parcels

will subject to partial acquisition only.

41 PR: 43405-ICB-CHI-01

65

Table 1. The summary of project affected land parcels and area of land acquisition

The table below describes the scope of project impact determined as a result of census, socio-economic surveys, demarcation, land surveys and title search of project

affected land parcels followed with inventory of project affected assets.

Table 2. Summary of project impact

Description of Impact Number

Land parcel 77

Household 70

Total number of project affected persons 158

Vulnerable HH 13

Severe Impact 74

Land parcels to be fully acquired 16

Land parcels subject to partial acquisition 61

Structure (deteriorated) 1

Land parcel with annual crops and/or hey 76

Fruit bearing trees 9

Decorative /timber perennials 2

According to the magnitude and the level of severity of project impact on affected persons and communities, considering the ADB SPS 200942, the project was classified

as Category B.

42 http://www.adb.org

Scope of Impact

No of parcels

Total area

(sq.m.)

Area to be acquired

(sq.m.)

Area remaining with

AHs (sq.m.)

Full acquisition 16 19,147 19,147 0

Partial acquisition 61 122,045 20,207 101,838

Total 77 141,192 39,354 101,838

66

LARP Preparation Activities

During the LARP preparation, the following activities were undertaken:

a. Onsite identification and enumeration of all project affected land parcels;

b. Census and collection of socio-economic data on each located project affected household;

c. Demarcation and survey of all project affected land parcels in the presence of owner, or owner's legitimate representative, owners of the adjacent land parcels,

representatives of local government and municipality;

d. Inventory of project affected assets being determined during demarcation and land survey in the presence of the owner, or owner's legitimate representative and

representatives of local government and municipality;

e. Additional inventory of project affected assets conducted by the licensed valuator who also conducted market research on secondary land sales43 prior to

preparation of valuation report and determination of compensation unit rates for affected land and assets;

f. Preparation of cash compensation package separately per each project affected land parcel and broken down per type and volume of impacts subject to cash

compensation.

ADB Resettlement Policy Principles

The UWSCG has prepared LARP in compliance with the applicable laws of Georgia, LARF and ADB Safeguards Policy Statement (SPS 2009) on Involuntary Resettlement.

The document will exercised as the guiding instrument, to ensure that project implementation to meet ADB major objectives of ADB on IR. In particular, to

a. avoid involuntary resettlement, wherever possible;

b. minimize involuntary resettlement by exploring Sub-Project and design alternatives;

c. enhance, or at least restore, the livelihoods of all displaced persons in real terms, relative to pre-Sub-Project levels; and

d. improve the standards of living of the displaced poor and other vulnerable groups.

The land will be acquired in accordance with the laws of Georgia and the ADB Safeguards Policy Update (2009). All affected persons (APs) will be compensated for the

lost and/or damaged assets at replacement costs and receive adequate allowances depending on the severity of impacts and vulnerability status.

Notice to contractors cannot be given until the UWSCG has confirmed that payment has been fully disbursed to the displaced persons and rehabilitation measures are

in place, and already-compensated/assisted displaced persons have cleared the area in a timely manner; and area is vacated and free from any encumbrances.

43 Secondary land sales is the term often used in Georgia to describe sales transaction when a private person is willing to sell land/real property acquired from the State through the

privatization process.

67

June 22, 2017 is defined as the cut-off date for the given project.

Compensation eligibility is limited to AHs by the cut-off date, June 22, 2017. The cut-off date is the completion date of the census, demarcation and land surveys, title

search, socioeconomic survey and inventory of project affected assets. These surveys have been undertaken from May 2 to June 22 of the year 2017.

Thus, the owners of all seventy-seven (77) project affected land parcels eligible to cash compensation under the LARP are identified.

Worth to be noticed: any person(s) who attempt to occupy any territory with the project ROW after June 22, 2017 will be classified as illegal encroachers and will not

receive cash compensation for expenses undertaken within the ROW after June 22, 2017. Such person, if any, will be given three months advance notice to vacate

premises.

Legal-Regulatory Framework

In Georgia specific laws and normative acts regulate ownership rights. Legislation of Georgia also determines the rules for expropriation of ownership for public need

and considers issuance of compensation to cover resettlement costs at market value. The types of loss subject to compensation are determined and defined that

compensation should be issued for damaged assets as well as lost income. Pursuant to the legislation consultations and notifications are important to ensure

participatory involvement of project affected persons in the process of project preparation and implementation.

Under the active legislation, during the implementation of resettlement action plan the following mechanism are to be undertaken:

a. Acquisition of project affected land and assets located within the ROW through the negotiation and issuance of defined compensation prior to the

commencement of civil works;

b. Exercising the right of expropriation based on the Court decision and after issuance of defined compensation in case the negotiations fail.

Valuation Methodology and Compensation Unit Rates

The independent licensed valuator has been deployed to prepare Valuation Report and determine compensation unit rates per each type of affected asset and income

loss. The Valuation Report describes the methods used for determination of compensation unit rates as full replacement cost at current market values.

The Valuation Report developed in Georgian language is being presented to the UWSCG and is readily available upon request of interested APs.

68

The unit rates for project affected assets (land, structure, perennials) and income loss (annual crops) are defined under the Valuation Report prepared by the

independent licensed valuator. Whereas, the amount of one-time allowances, in addition allocated to severely affected and vulnerable APs, are defined based on the

principles of RPF, ADB SPS 2009, and the good practice examples.

During LARP implementation One-page Description document prepared separately for each project affected land parcel reflecting the breakdown of cash compensation

package individually will be handed to the AP.

Table 3: Cash Compensation Unit Rates

# Compensation Item Unit Measure Unit Rate (GEL)

1 Agricultural /non-agricultural land sq.m. 12

2 Replacement cost for deteriorated structure

(100 sq.m.) sq.m. 290

3 Replacement value for fruit bearing perennials

sour plu , i.e. Tke ali number 143

4 Replacement value for hazel nut bushes number 130

5 Timber value of project affected perennial

(Hornbeam) number 130

6 Purchase of best quality saplings number 15

7 Annual Crops (corn) sq.m. 0.40

8 Annual Crops (wheat) sq.m. 0.40

9 Annual Crops (corn and beans) sq.m. 0.55

10 Annual Crops (pumpkin) number 2.00

11 Perennial crops (Lucerne) sq.m. 0.14

12 Annual crops (hay) sq.m. 0.12

13 Vulnerability No of AHs 1036

14 Severe Impact No of Parcels 1036

69

Compensation Entitlements and Mitigation Measures

Compensation Entitlements are defined specifically for this project and applicable to APs facing loss of land, assets and income, incorporate cash compensation at full

replacement cost at the current market values in compliance with the ADB SPS 2009 and active legislation of Georgia.

The entitlements are detailed below:

Non-agricultural / Agricultural arable land will be cash compensated at full replacement cost in the amount sufficient to purchase replacement land of equal in value

and productivity in vicinity to the project affected land parcel. Method for calculation of full replacement cost will include cost of preparation of land to levels similar

to those of the affected land. The taxes and fee related to processing transaction registration will be covered by the Executing Agency.

"Orphan land": remaining piece of land which as a result of land take has lost previous designation and became economically unviable. In such case, landowner is

eligible to claim full cash compensation for the entire area of such land parcel.

Structures: Structure-buildings (including condemned one) will be compensated in cash at full replacement cost, i.e. construction cost without any deductions for

depreciation, salvaged materials, or transaction costs. The compensation for houses/buildings will include the cost of lost utility (water, electricity, sewerage, gas)

connections. Construction cost calculation considers market cost of the materials to build a replacement structure with an area and quality similar to or better than

those of the affected structure, or to repair a partially affected structure, plus the cost of transporting building materials to the construction site, plus the cost of any

la or a d o tra tor’s fees. A appli a le ta es a d fees for tra sa tio registratio ill e o ered the Executing Agency.

Deteriorated structure: cash compensation for deteriorated structure was determined based on the market price of the salvaged materials. The ruined remnant of the

structure, fragments of remaining walls composed by old construction blocks and bricks can hardly be used for further construction purposes. Therefore, in given case

evaluation was conducted according to the current market value of the salvaged materials.

Fruit bearing perennials: Cash compensation shall reflect income replacement. Cash compensation will be calculated at current market value and according to type,

age, and productive value of project affected fruit tree. Annual yield capacity of a mature fruit bearing tree multiplied to market price of a fruit (kg/GEL) and multiplied

to the number of years required to grow a new tree to same productivity age.

Decorative /non fruit bearing perennials: Compensation will be calculated for timber value of decorative trees and perennials not bearing fruits at current market

value and according to type and age of affected tree.

Replacement Samplings: eligible APs will receive additional cash for purchase of seedlings per each project affected tree including fruit bearing, decorative and timber

trees.

70

Annual Crops: Default payment of cash compensation at current market rates for annual crops per entire area of project affected land parcel. Compensation will be

issued even in case the APs have managed to collect the yield. Crop compensation will be paid to landowners. In case of tenancy agreement, cash compensation will

be paid to owner/tenant based on the specific sharecropping agreements (written/verbal) being made between these two parties.

Community Structures and Public Utilities: If affected, assets will be fully relocated or rehabilitated to meet their pre-project functions and utilities.

Additional Rehabilitation Measures

The LARP considers additional rehabilitation measures to be provided to AHs that qualify as vulnerable and severely affected.

One-time allowance for vulnerability: In addition to the compensation of lost land and crops, vulnerable AHs will be provided with additional rehabilitation measures;

in particular, one-time allowance set to cash compensation calculated based on the minimum subsistence monthly income level for the household of five (5) persons

multiplied to 3 months per AH. The amount (1036 GEL per affected household) of compensation are calculated based on the data retrieved from official website of the

National Statistics Office of Georgia – GEOSTAT44. Additionally, the members of vulnerable families will be given priority in employment in project-related jobs.

One-time allowance for severe impact: APs losing more than 10 % of income generating land, in addition to the compensation of lost land and crops, will be provided

with additional rehabilitation measures; in particular, one-time allowance set to cash compensation calculated based on the minimum subsistence monthly income

level for the household of five (5) persons multiplied to 3 months per AH. The amount (1036 GEL per severely affected land parcel) of compensation is calculated based

on the data retrieved from official website of the National Statistics Office of Georgia – GEOSTAT45. Additionally, the members of vulnerable families will be given

priority in employment in project-related jobs.

Contractor's Temporary Requirements: The civil works contract will require the contractor to be responsible for the temporary acquisition and reinstatement of all

land required outside the road reserve for construction camps, offices, borrow pits, materials storage sites, materials processing sites, and haul roads. The contractor

will select the land parcels they require and they will be responsible for negotiating agreements directly with land owners to occupy the land. In the event that a

contractor fails to obtain the agreement of a landowner, the contractor would be required to select an alternative site and negotiate a new agreement. No involuntary

occupation of land for temporary construction purposes would occur. Provision will be made in the civil works contract for the contractor to be responsible for providing

44 http://www.geostat.ge/index.php?action=page&p_id=179&lang=eng. Minimum monthly income subsistence level for the household of 5 members is 345/30 GEL. In particular:

345.30 X 3= 1035.90 GEL; rounded to 1036 GEL per affected household. 45 Same as above.

71

adequate measures to cater for existing traffic while the construction works are in progress. The contractors shall be required to obtain the approval of the executing

agency for all proposals for traffic management during the construction of the civil works contracts and also they shall be required to maintain all temporary diversion

roads and existing roads used to carry diverted traffic from the main road.

Taxation and Deposit/Escrow Accounts

In no case will the AHs be liable for any taxes and eventual transaction fees; these will be paid by the UWSCG.

Amount of cash compensation will be deposited on the special account with the UWSCG if during LARP implementation process any AP is missing, absent, or deceased

and issuance of compensation is postponed due to legal procedures.

Procedures to Address Grievances

The Grievance Redress Commission will be operating within the framework of the project. The role and responsibility of the GRC is to accept claims and complaints,

assess its validity, determine the scope of eventual impacts, and timely resolve the issue, including the claims regarding the compensation.

Project related claims and grievances will be addressed according to the below described procedures

Phase Action

Level

Process Timeline

1st

Phase

UWSCG

Local

Service

Center

The designated person at the UWSCG Local Service

Center will first give hearing to the aggrieved person,

then register the grievance and assign registration

number. Then he/she will inform about the grievance

upper level person to the local service center

responsible for grievances, and circulating the

document exchange intranet the grievance is provided

to UWSCG Department of International Procurement

and Donors Relationship, Department of Environment

2 weeks

72

Phase Action

Level

Process Timeline

Protection, resettlement and Permits; besides he/she

contacts the representatives of the Construction

Contractor and Construction Supervision Company.

2nd

Phase

UWSCG

GRC

In case the complaint is not resolved on the 1st Phase,

AP (complainant), seeking timely and efficient review

and resolution of the complaint, is eligible to address

the Grievance Redress Commission.

After receiving written complaints of AP, the GRC will

review and prepare a Case File for GRG hearing and

resolution. A formal hearing with GRC will be scheduled

in agreement with aggrieved AP. Liaison persons

assigned by the PIU will keep communication with AP to

schedule meetings, advise AP submission of additional

supporting documents or proves to support his/her

claim, collect such documents presented by AP and

present to the GRC during formal hearing. Besides, the

support includes assistance in preparation written

complaint to GRC, if required.

The decisions from majority of the members will be

considered final from the GRC and will be issued to AP

after signed by GRC members. The case record will be

updated and the decision will be communicated to the

complainant within 14 days of submission.

3 weeks

3rd

Phase

ADB

Georgian

Mission

In case the GRC fails to resolve problem raised in the

complaint and grievance still remains unresolved after

two-week time period since its official submission, the

interested person is eligible to apply to Asian

Development Bank Georgia Mission.

73

Any physical and legal person, any appellant can communicate his/her concern to the Court at any stage of grievance redress. The GRC will not influence or restrict the

AP from applying to court for legal remedies.

If the complaint is found invalid, the GRC formulates a response and sends a written letter to the complainant, explaining the reasons of rejection. The complainant

can appeal the decision and bring the case to the local Court.

Contact Information

For any additional information and advice, please approach the following persons:

United Water Supply Company of Georgia

Address: 76-b Vazha-Pshavela Ave., Tbilisi, Georgia

Telephone: +(995 32) 291 90 60

Maka Goderdzishvili, Head of Resettlement and Environmental Unit

Mobile Phone: +995 599 22 99 25

The Copy of the Grievance Form is attached in the Annex 1.

74

Appendices

Annex 1. Grievance Form

Grievance Form

Section of Complainant:

Full Name:

_________________________________

_________________________________

Mailing/Permanent Residence Address:

Village: ---------------------------------------------

Municipality: -------------------------------------

Preferred option of communication:

Mark with X

Response mailed to:

______________________________

Face-to-face meeting in GR Focal Point

______________________________

Contacts

Mobile: ---------------------------------------------

Landline: -------------------------------------------

E-mail: ----------------------------------------------

Language for Communication (mark with

X)

Georgian

Other_____________________ (please

specify)

Complain submission date: Date of hearing:

75

Please, describe the reason of your discontent or claim in details. Use extra pages if needed.

Present copies of the relevant documents, if available

Complainant

Full Name:___________________________

Signature: ___________________________

Date: _______________________________

Received by:

Full Name:________________________

Signature:__________________________

Date: ____________________________

76

Annex 2. Project Implementation Schedule

Activities/ Months May June July Aug Sept Oct Nov Dec Jan Feb Mar

2017 2017 2017 2017 2017 2017 2017 2017 2018 2018 2018

Preparation of Initial LARP

Public Orientation Meetings

Enumeration, demarcation and survey of

project affected parcels

Census, SES, Inventory

Title Search

Deploying Valuator /Inventory &

appraisal

Data analyses

Developments of initial LARP & tentative

budget

UWSCG & ADB review, provision

comments to initial draft LARP & Budget

Incorporating comments &

announcement of LARP Public Disclosure

UWSCG & ADB No Objection for LARP

implementation commencement

LARP Implementation - Land Acquisition

& Issuance of Compensations

Technical Assistance to APs (registration

updates, legal consultancy)

Negotiations & Cash Compensation of

AHs

Processing Sales Agreements & Issuance

of Compensations

Resolving outstanding issues &

grievances

Construction Contract award

77

Annex 6. Sample of Questionnaire

Census & Socio Economy Survey Questionnaire Municipality: Sachkhere / Village: Chikha Date: ___________, 2017

AP Code (map number of affected land parcel): Full name of HH Head:

Number of persons in HH: ID Number of Landowner:

Male: ID Valid until:

Female: Contact Phones:

Vulnerability:

Demography of HH

Member (Head) Spouse Son Daughter Fathe

r

Mother Daughter-in-

law

Son-in-

law

Grand-

daughter

Grand-

son

Broth

er

Sist

er

Other

Male

Other

Female

Relationship to

HH Head – enter

names

Age or Date of

Birth

Social /Marital

Status

Gender (M/F)

Primary

occupation

Educational level

See codes below

Disability or

chronic illness

Ethnicity

Religion

78

Primary Occupation: 1. Farmer 2. Pensioner 3. Unemployed 4. Civil Servant 5. Business (non-farming) 6.Intermitent job (outside of rayon) 7. Housewife

8. University student; 9. Secondary school student; 10. In the kindergarten 11. Army; 12Other

Educational Level: 1. Primary 2. Secondary 3. Technical 4. Higher (University) 5. None (primary not completed)

Disability: 1. Invalid 1st Category 2. Invalid 2nd Category 3. Invalid 3rd Category 4. Other invalidity or chronic illness

Possessions of HH

Does your household own one or several of the following items:

Brief description of residential house:

Color TV Satellite Dish Telephone Mobile

phone

Internet Private well Hot water Gas heater

Wood

stove

Electric

heater

Laptop PC

Washing

machine

Refrigerator Bicycle Motorcycle Car Tractor Mini tractor Microbus Lorry Cattle Goat Chicken

House Built in (year) Number of floors Number of bedrooms Fully furnished Livable (unfinished

renovation)

Poor condition

Building material – Bricks

& Blocks

Kitchen inside WC Inside Bathroom Inside Wooden house WCs outside

79

Costs and Expenditures of HH

What is the approximate annual expenditures of your household? ______________GEL/Year

Food Clothing Spirits/

Cigarettes

Consumer

goods

House

maintenance

Schooling University Utilities Health Mortgage loan Quick

loans

Farming/

agricultur

e

Livestock Business Transport Vehicle

maintenance

Renting

Land/assets

Sports/ Leisure Travelling Vocational

training

Other

Other: ______________________ (please, specify)

How much in average do you spend monthly: _________________________GEL?

Land Tenure:

How many land parcels does your HH own: ________________________

Type /designation of a land parcel Used for Annual yield (kg/Year) Income if any (GEL/Year)

Residential-homestead

Orchard/Garden

Agricultural arable

Agricultural grazing

Rented from private owner

Rented from the State/Municipality

80

Sources of Income of HH

What is the approximate annual income in GEL from sources listed below?

Farming

Annual

crops

Livestock

/Meat

Milk

product

s

Poultry

(chicken

/eggs)

Business Regular

Salary

Intermittent

seasonal job

Remitta

nces

Selling agricultural

produce at the local

market

Sellin

g

cattle

Worki

ng

abroad

Tradin

g

If other, please specify: _________________________________________________________________________________________

Do you self-consume some of your produce? (YES /NO) __________ Approximately how much (%) of your produce is self-consumed per year?

______________________________________

Vulnerability

I e u erator’s assess e t (not a question), is there potential for vulnerability in this household: Yes / No

If yes, please specify:________

1: Single Elderly

2: Person with disability

3: Very poor, cannot cope with their basic needs

4: Female-Headed Household

5: Targeted Social Assistance

6: Other