Technical Assistance Consultant’s Report · Petroleum and Chemical Industry Federation. They...
Transcript of Technical Assistance Consultant’s Report · Petroleum and Chemical Industry Federation. They...
Technical Assistance Consultant’s Report
Project Number: 46052 March 2015
People’s Republic of China: Roadmap for Carbon Capture and Storage Demonstration and Deployment (Financed by the Carbon Capture and Storage Fund)
Component A–Work Package 3 Report: Selection of early opportunity CCS demonstration projects in the PRC
Prepared by
Huiquan Li, Chinese Academy of Sciences Andrew Minchener, IEA-Clean Coal Center For Department of Climate Change, National Development and Reform Commission (Executing Agency) National Center for Climate Change Strategy and International Cooperation (Implementing Agency)
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
Road Map for Carbon Capture and Storage (CCS) Demonstration and Deployment in the People’s Republic of China
WORK PACK AGE 3 REPORT:
Selection of early opportunity CCS demonstration projects in the PRCHuiquan Li, Chinese Academy of SciencesAndrew Minchener, IEA-Clean Coal Center
March 2015
1
WP3A
FINAL REPORT
TA 8133 Component A
Work Package 3A
Selection of early opportunity CCS
demonstration projects for China
November 2014
2
Key messages
In the PRC, there are some sixteen possible coal based CCS full chain integrated
demonstration projects although the great majority are at the early concept stage. As
such, the level of process information that is available is generally insufficient to allow
any robust assessment of likely technical and economic performance to be
undertaken. Consequently, the best that could be achieved would be a preliminary
ranking of possible projects, after which the Chinese Government could encourage
the project developers to provide a comprehensive pre-feasability dataset and to
show how their proposed projects might meet the following criteria:
Be consistent with Chinese energy & environment strategic objectives, as defined in the 12th Five Year Plan and other government documents;
Have support from local government for the implementation of the proposed project;
Comprise a large scale coal based process that is representative of the technology used in either the Chinese power, chemicals (including coal to liquids and gaseous
fuels), iron and steel, or building sectors, to which a CCS technique will be applied;
Include the whole technical chain of CO2 capture, transportation and utilization/storage;
Be developed sufficiently such that a Front End Engineering Design (FEED) study will be able to start;
Be technically ready for capturing at least 85% CO2 from the gas stream;
Have a storage/utilisation level equal to or larger than 100,000 tonnes of CO2, and preferably close to or in excess of 1 Mt CO2 per year;
Have a geological location identified and characterized to the extent that there is a reasonable expectation that the quantities of CO2 captured over the demonstration
project lifetime can be adequately stored/utilized:
Include downstream heat recovery, if a power project, to improve the overall process efficiency;
Include the design and implementation of a comprehensive monitoring and verification programme for CO2 storage, which will need to be applied also for
EOR applications since a portion of the CO2 remains contained within the
reservoir.
It is strongly recommended that, in order to implement this suggested approach, the
Chinese government should consider setting up an independent panel of industrial
experts to work with the project developers to gather the process related data
necessary to assess the project viability against the key criteria set out above. In this
way, a robust and transparent selection process could be established that would lead
to a shortlist of projects being produced from which the more attractive options could
then be subjected to a FEED study. Once these were completed and, subject to
acceptable results and a financing plan being established, this would allow the
Chinese government to take well informed decisions as to how such bankable
demonstration projects could be taken forward.
3
Within this ADB TA project, an initial assessment procedure has been suggested,
which allows a reasonable preliminary ranking of possible projects to be determined.
This approach considers a range of technical parameters and assigns weighted
scores that are dependent on the overall objective of the demonstration programme.
For example, this can be to either determine the near-term need to identify potentially
low cost opportunities or the longer term requirement to identify possible projects that
offer high replicability potential.
Since the input information to the assessment procedure is limited both in scope and
accuracy, it is evident that there is not a significant differentiation between the results
obtained for the various projects. Based on the criteria used in the low cost
assessment, there is little significance between the rankings for the top four projects,
which comprise coal to chemicals related possibilities. Similarly, for near to medium
term possibilities where replicability is a key issue, there is limited differentiation
between several coal power plant projects. For both options, all these projects are
reasonably well advanced in their planning and design activities and all include some
level of CO2 EOR application, which will provide a revenue stream that will offset
some of the operational costs associated with the implementation of CCS.
Thus, it is evident that the coal-to-chemicals prospects represent the more attractive
low cost opportunities. For the medium term, when wide scale replicability will also
become important, it will be necessary to consider all three first generation CO2
capture possibilities since no clear technology winner can yet be identified. Thus
post-combustion CO2 capture fitted to pulverised coal power plant will be very
important as this technology is readily suited for retrofit to the modern components of
the existing coal power fleet. Similarly, oxyfuel will also need to be considered as it
can be readily applied to existing power plants. In both cases, the technologies will
also be applicable for new applications, with some suggestions that oxyfuel might
offer some potentially significant capital cost and operational cost reductions
compared to the alternatives. Finally, IGCC should not be discounted as, although it is
not yet technically and economically proven, there still appears to be scope to offer
lower CO2 capture opportunities, albeit for new plant only, compared to the other two
prospects in due course.
At the same time, recognising that China might wish to take forward a near term low
cost demonstration opportunity, prior to a robust and transparent selection process
being established, it would be appropriate to specifically examine proposals from
large energy companies that already have CCS/EOR experience at industrial pilot
scale and have already expressed their commitment to work with the NDRC and
international funding organisations such as the Asian Development Bank. When this
commitment issue is considered, a potentially significant and ambitious project is
immediately identified. This is a proposed early stage coal to chemicals plant
demonstration project to be undertaken by Shenhua, with CNCPC using the captured
CO2 for EOR in an oil field in the Erdos region. Most importantly, the Chairmen of both
4
these major SOEs have signed Memoranda of Understanding with the China
Petroleum and Chemical Industry Federation. They intend to first undertake a
pre-feasibility study and pilot test during 2014/2015 and then a FEED study for a 1-2
million tonnes CO2 per year capture and EOR project. This will be supported with an
assessment for a subsequent inter-provincial CCUS network around the Erdos basin
oil fields, including capturing CO2 from coal-fired power plants as well as coal to
chemical plants. Such a network would lead to a CO2 capture and utilisation
opportunity covering part of Inner Mongolia, Gansu, Ningxia, and Shanxi Provinces,
with an annual CO2 utilisation capacity of some 5 million tonnes.
This proposed project offers a very attractive near term demonstration opportunity. It
comprises a low-cost CO2 capture option from a coal to chemicals plant, and has the
joint involvement of China’s major coal producer and its largest oil company, both of
whom have committed to work together. In the near term, the intended project offers a
very significant CO2 capture/utilisation prospect, which will represent one of the largest
planned demonstration projects in the world. There is close proximity to an oil field,
with proven amenability to CO2-EOR, which further emphasises the low cost
possibility. Equally importantly, the oil field region contains a very large number of coal
to chemical plants and coal-fired power plants, and is also distant from large human
agglomerations. As such, the subsequent intended CO2 network is an attractive and
suitably ambitious further stage demonstration that will allow China to establish itself at
the forefront of global CCUS activities.
Consequently, support for this major CCUS project in China by the Asian Development
Bank in collaboration with the NDRC is strongly recommended.
5
Contents 1 INTRODUCTION 1.1 Status of CCS in China 1.2 Scope of work 2 INTERNATIONAL PERSPECTIVES FOR CCS DEMONSTRATION PROJECT DEVELOPMENT 2.1 Global summary of large scale integrated CCS projects 2.2 International approaches for selecting and funding CCS demonstration projects 2.3 The international relevance to China
3 CCS DEVELOPMENT IN CHINA 3.1 Status of China’s CCS initiatives 3.2 Overview of China’s current demonstration project proposals 3.3 Rationale for ranking of possible projects 4 GENERIC APPROACH TO PROVIDE A PRELIMINARY RANKING OF CHINESE DEMONSTRATION PROPOSALS 4.1 Basic principles of intended project evaluation 4.2 Construction of evaluation criteria and indicators system 5. CHINA CCS DEMONSTRATION PROJECT PRELIMINARY EVALUATION AND SELECTION 5.1 Presentation of overall results 5.2 Ranking on a lower cost basis and a replicability basis 5.3 Description of the top ranked projects 6 PROPOSED NEXT STAGES OF THE ASSESSMENT PROCESS 7 RECOMMENDATIONS TO THE NDRC AND THE ASIAN DEVELOPMENT BANK FOR AN EARLY OPPORTUNITY CCS DEMONSTRATION PROJECT 8 REFERENCES
6
List of Tables
Table 1 Regional distribution of large scale integrated CCS projects
(GCCSI 2014a) Table 2 Sector and technology based analysis of LSIP data base (based on GCCSI 2014a) Table 3 Listing of possible large scale coal based CCS demonstration projects in China Table 4 Summary of CCUS demonstration project evaluation index and
classification
Table 5 Methods to assign index weights
Table 6 Index weighting where either cost or replicability is critical Table 7 Basic evaluation results (arrayed by project number)
Table 8 Provisional list of early CCUS projects where low cost is the key
assessment criterion
Table 9 Provisional list of CCUS projects where replicability is the key
assessment criterion
List of Figures Figure 1 Suggested CCUS demonstration project evaluation index system
7
1 INTRODUCTION
1.1 Status of CCS in China The current measures for reducing the greenhouse gas emissions of the People’s
Republic of China (PRC) are focused on improving energy efficiency, energy
conservation and increasing the share of non-fossil fuel energy sources. At the same
time, as reflected in the PRC government’s 2011 Action Plan on Climate Change,
there is a growing recognition that while these options remain important, they will only
go so far and that carbon capture and storage (CCS) will also need to play a key role
in China’s climate change abatement strategies, It is an important climate mitigation
technology that offers medium to long term opportunities to make very deep cuts in
CO2 emissions while continuing to utilize coal for major applications.
In 2013, the National Development and Reform Commission (NDRC) announced that
its Climate [2013] Document No. 849 has been sent to all provincial, autonomous
region, special zone, municipal and city governments, as well as to a wide range of
ministries and commissions, and to all state-owned key enterprises and all related
industry associations. Its purpose is to promote carbon capture, utilisation and
storage pilot and demonstration projects throughout the thermal power, coal chemical,
cement and steel industries (NDRC 2013). This is a powerful document and calls on
the recipients to:
develop pilot and demonstration projects along the CCUS technology chain;
develop CCUS demonstration projects and base;
explore and establish financial incentive mechanisms;
strengthen strategy and planning for CCUS development;
promote CCUS standards and regulation; and
strengthen capacity building and international collaboration.
This initiative will play a major role in driving forward CCS demonstration and
deployment in China.
1.2 Scope of work This study considers the international perspectives of CCS development, including
the various approaches to establish major demonstration projects, and draws lessons
on how such experience might benefit China’s own CCS ambitions. The international
perspectives of CCS development are assessed, including the various approaches to
establish major demonstration projects. China’s current CCS activities are reviewed,
including its current large scale demonstration project proposals. Recommendations
on how to move forward are then made such that China can subsequently establish a
robust, transparent approach to identifying and supporting the initiation of significant
CCS demonstration projects.
8
2 INTERNATIONAL PERSPECTIVES FOR CCS DEMONSTRATION PROJECT DEVELOPMENT
2.1 Global summary of large scale integrated CCS projects The Global CCS Institute (GCCSI) publishes an annual listing of all publically declared
large scale integrated CCS projects (LSIPs) worldwide. The GCCSI defines LSIPs as
those which involve the integrated capture, transport and storage of CO2 at a scale of:
at least 800,000 tonnes of CO2 annually for a coal-based power plant, or
at least 400,000 tonnes of CO2 annually for other emission-intensive industrial facilities (including natural gas-based power generation).
Table 1 Regional distribution of large scale integrated CCS projects
(GCCSI 2014a)
Region Status Total
Identify Evaluation Definition Construction Operation
USA 0 4 6 2 7 19
Europe 1 3 5 0 2 11
Australia & New Zealand
0 3 0 1 0 4
Canada 0 0 1 5 1 7
China 6 2 4 0 0 12
Middle East 0 2 0 1 0 3
Other countries in Asia
1 1 0 0 0 2
Africa 0 0 0 0 1 1
South America
0 0 0 0 1 1
Total 8 15 16 9 12 60
As of February 2014, some 60 such projects were listed (GCCSI 2014a). Twelve are defined as operational. These are natural gas based process projects either to remove CO2 to meet pipeline quality standards or for chemicals manufacture, mostly using pre-combustion technology. The very great majority of the remaining projects are at the early stages of identification, evaluation and definition. Table 1 provides a
9
regional breakdown for the projects, based on the GCCSI database as of 24 February 2014. Further analysis of the information shows that the great majority of projects are intended for implementation in the USA and then China, Europe and Canada. Table 2 indicates that the majority of the projects are being developed for the non-power sectors, particularly in the case of gas. In overall terms there is a small majority of coal based projects worldwide compared to gas and oil options.
Table 2 Sector and technology based analysis of LSIP data base
(based on GCCSI 2014a)
Sector CO2 capture technology Total
Post-combustion Pre-combustion Oxy-combustion
Coal power 7 12 4 23
Coal
Chemicals
- 9 - 9
Gas power 3 - - 3
Gas
chemicals/
processing
- 17 - 17
Oil processing - 2- - 2
Unknown - - - 6
Total 60
It is also worth noting that many of the potential LSIPs identified by the GCCSI in North America and to some extent Europe are based on natural gas processing, with CO2 EOR as the preferred usage route. This is in contrast to China where the focus is on coal, both for power and conversion activities. In China coal to chemicals projects appear to offer significant possibilities for CCS demonstration including CO2 EOR.
2.2 International approaches for selecting and funding CCS demonstration projects The basis, rationale and issues arising from various approaches adopted within OECD countries to select and fund commercial prototype CCS demonstration projects are presented. The importance of this review is to highlight the experiences arising from these various approaches, which were undertaken in order to ensure transparency and value for money as these projects are to be funded in part with public money. In Europe and the USA, there have been significant R&D projects undertaken, with the objective to reduce the cost and efficiency penalties associated with post-combustion, pre-combustion and oxyfuel based CO2 capture techniques for coal fired power plants, and to develop alternative technologies for the longer term that may have advantages such as chemical looping (GCCSI 2013). While this is of
10
significant international value, there has been limited progress towards establishing commercial prototype CCS demonstration projects. In part, this has been due to uncertain investment conditions but also due to the lack of supportive policies and appropriate regulatory conditions. That said, there are efforts in both the USA and the UK to break down such barriers with programmes to establish large scale demonstration projects. In particular, there are two major programmes that have been supported by the governments of the USA and the UK, and in both cases valuable lessons can be learned from such experiences as their respective first attempts to establish a viable demonstration programme did not proceed successfully.
2.2.1 The USA FutureGen CCS demonstration project FutureGen is a USA government project that was in created in 2003, for implementation as a public-private partnership. It has proved very difficult to achieve a viable commercial prototype demonstration project although a robust way forward now appears to be in place. While this has created certain difficulties for the government, it has provided a valuable learning curve that may be of benefit to other countries with ambitions to establish a new technology option at such a large scale (Floger 2013).
First attempt at a public –private partnership The initial plan was to build a near-zero-emissions gasification based coal fuelled 275 MWe power plant to produce hydrogen and electricity while using CCS, with 1 Mt/year of CO2 being captured, transported and stored in a saline aquifer. This project was intended to be designed, developed and operated by the FutureGen Industrial Alliance, a non-profit consortium of coal mining and electric utility companies, with the USDOE providing a portion of the required funds. The Alliance comprised a consortium of 10 companies from the USA, China and Australia. The initial estimated gross project cost, including construction and operations, and excluding offsetting revenue, was set by DOE at $1.65 billion, with the expectation that they would provide US$1 billion and the Alliance would provide the balance. In order to select a viable project, the USDOE called for tenders, which led to four potential options being selected as a short list. The project developers for these four options were then required to submit pre-feasability level technical and economic plans for all parts of the CCS chain, from which in 2007 a winning consortium was chosen, with plans to build an IGCC project with pre-combustion capture in Illinois. As an example of the process, selection of the CO2 storage site was based on a review of proposals against a set of environmental, technical, regulatory, and financial criteria, with input from external technical advisors on power plant design and CO2 storage. An initial twelve proposals were reduced to four by this process, and those four were reviewed further, including a determination of their suitability via an environmental impact analysis as required by the National Environmental Protection Administration. However, it became evident that the level of detail in much of this assessment process was not adequate as the estimated costs for the chosen project rose steadily, reflecting very much the lack of maturity of the IGCC+CCS concept at that time. The DOE sought to draw in additional funding from industry but, in the absence of a firm costing, this approach was not successful. Indeed the project was still in the development stage when its funding was cancelled in January 2008.
11
Second attempt with FutureGen2.0 Despite this significant failure to establish a technically and financially viable project, the USA Government remained keen to establish a way forward. The USDOE expressed support for continuing the project using stimulus funds and making it a part of a larger portfolio of research projects developed in collaboration with other countries. There was a shift in technology choice to oxyfuel combustion in that this was thought to offer significant potential in terms of lower cost and efficiency penalties compared to post-combustion capture while being a type of technology that would not be vulnerable to large cost uncertainties compared to IGCC with pre-combustion capture. The general approach adopted to select a project for this second attempt remained very similar to that used previously, with possible candidates being solicited, a short list being drawn up and a pre-feasability study being undertaken for each project on the shortlist to identify the efficiency penalties, likely costs and a viable CO2 storage location. This has led to the selection of the Future Gen 2.0 demonstration project, which has replaced the ill-fated original IGCC concept. The USA DOE continues to cooperate with the FutureGen Industrial Alliance, which comprises all its original overseas members and almost all its national members. This time the aim is to retrofit a 200MWe coal-fired power plant in Meredosia, Illinois with oxy-combustion technology. The goal is to capture more than 1 Mt of CO2 each year, which accounts for more than 90% of the plant’s CO2 emissions, and to reduce other emissions to minimal levels. This will require testing of the oxygen separation technology, new boiler and exhaust processing technology after combustion at power plant scale. In particular, the plant’s CO2 purification and compression unit is expected to deliver 90% CO2 capture and reduce other emissions, such as SOx, NOx and particulates, to near-zero levels. The CO2 is to be transported and stored underground in nearby deep saline aquifers (Bellona 2013). This is a three phase programme. Phase 1 included technical and financial activities, such as identification of a storage site, preliminary characterization and test drilling, and a commitment from the Illinois Commerce Commission to cover the FutureGen 2.0 project’s output under its power purchasing plans. This was completed successfully in February 2013, after which the USDOE announced the beginning of Phase 2 of the project development with a new cooperative agreement between the FutureGen Industrial Alliance and the DOE. At this point, the USDOE made a financial commitment of support that allowed the developers to move forward with the first US$100 million worth of work on demonstration of the oxy-combustion technology. Recently, the project received the final approval that it needed in order to begin the construction activities when the DOE formally approved its commitment and allocated US$1 billion for the FutureGen Alliance (GCCSI 2014b).
2.2.2 The UK Government CCS demonstration competition As with the USDOE, the UK Government via its Department of Energy and Climate Change has encountered significant problems in ensuring that viable CCS demonstration projects can be selected for public funding support.
The first UK competition The UK established the basis for UK infrastructure investment within the energy sector of the economy. The Government’s vision is that it can reduce carbon emissions from the energy sector and tackle climate change through supporting:
the commercial deployment of CCS;
12
the introduction of new nuclear power stations;
increased deployment of renewable energy sources; and
improved energy efficiency. The UK government has stated its belief that the energy market will drive the most efficient investment strategy for power generation, which will incentivise investment in low carbon energy generation to meet the challenges arising in delivering a secure, low carbon and affordable energy system. However, for the short to medium term, the Government recognises that it needs market mechanisms to continue to support emerging low carbon technologies, including CCS. On this basis, in 2007, the Government launched a competition for industry to run a project to design, construct and operate the UK’s first commercial-scale CCS demonstration project at a coal-fired power station by 2014. The Government further made a commitment to make up to £1 billion available in capital investment for the first such demonstration project. It made a call for proposals, which received a positive response from industry. However, after establishing a short list of four possible projects, the competitive process began to fail. Firstly, two of the four shortlisted bidders subsequently withdrew, due in part to longer term uncertainty as to the prospects following the demonstration phase. The government then provided a total of £40 million (~US£60 million) to fund FEED studies for both the remaining possible projects, with all of the findings from such studies subsequently being made available in the public domain. Such studies typically follow on from initial high-level (pre-feasability) plans, and allow project developers to refine designs and, for example, obtain quotes from suppliers. This gives greater certainty on costs before the project developer and, in this case, the government commits significant funding on construction. As the FEED studies were completed, one of these two bidders then withdrew because their intention to build a new supercritical coal power plant with CCS did not fit the government’s declared timescale. This left one bidder, comprising a consortium of Scottish Power, National Grid and Shell. In October 2010, the Government estimated that the Scottish Power consortium’s bid required capital of £1.9 billion, based on data provided by the Scottish Power consortium before its engineering and design work had been completed. This was well in excess of the Government’s £1 billion capital budget for the project. In October 2011, the government ceased contractual negotiations as it couldn’t agree a deal that would represent value for money since the project couldn’t be funded within its agreed £1 billion capital limit. A second sticking point was that it couldn’t agree with Scottish Power how to offset the additional cost of the new carbon price floor (a minimum charge for emitting CO2) to secure the availability of Longannet power station for the duration of the demonstration project. Furthermore, it concluded that there was also no prospect of agreeing contract terms, including IPR issues, which would be mutually acceptable to all members of the consortium. Consequently, the competition was cancelled. In hindsight, following an Audit Office enquiry, it was decided that, while the competition was launched based on the strategic importance of CCS, it lacked both a detailed business case and a viable means for options appraisal. There was insufficient clarity over how a single demonstration project would contribute to policy objectives. The original project specifications were deemed to be too narrow, which limited the number of bidders applying to the competition, the technical project options they could submit, and the flexibility of the negotiations. The Department also gave limited weight to commercial viability when it assessed bidders’ outline proposals.
13
Regulatory uncertainty further contributed to the Department’s inability to reach a commercial contract (National Audit Office 2012). As with the FutureGen approach, although the competition did not result in a contract, it increased the UK Government’s experience of the associated technical, regulatory and commercial challenges, and its knowledge of the costs of CCS. With regard to the latter point, it has paid for the two FEED studies, which may help to reduce the costs of future engineering and design work (CCSA 2014). Given the potential importance of CCS to establishing a low carbon economy, the UK Government has persisted in its attempts to establish a sound financial basis for support of a commercial scale CCS demonstration, as described below.
The UK CCS commercialisation competition This second attempt by the UK government to select CCS demonstration projects is intended to support industrial practical experience in the design, construction and operation of commercial-scale CCS. The £1 billion capital funding is meant to: generate learning that will help drive down the costs of CCS;
test and build familiarity with the CCS specific regulatory framework;
encourage industry to develop suitable CCS business models; and
contribute to the development of early infrastructure for CO2 transport and storage. As part of the improved learning process available to the government for its new programme, DECC has declared that its competition will need to fully investigate the costs and the technical, price and regulatory risks in individual projects and compare their value. It will monitor the return that industry is likely to make and how government risks can be minimised. It has also set governance arrangements to assess routinely whether the programme is on course to deliver value for money. This is expected to include, at the project level, formal breakpoints with triggers for further reviews as necessary to test the value for money of proceeding further. This second competition was launched in April 2012. Its objective is to identify and support projects that can contribute to reducing the costs of CCS technology so that it can compete with other low carbon technologies in the 2020s. This resulted in a wide range of outline proposals being submitted, from which a shortlist of four was drawn up. In October 2012, DECC announced that all four were being taken forward into a new intensive phase of pre-feasability project definition combined with detailed commercial negotiations. On 14 January 2013, DECC confirmed it had received revised proposals from all four projects. In March 2013, DECC announced that two bidders had been shortlisted for the next phase of the competition (Gov.UK 2013a). These are:
The Peterhead Project, for which Shell UK and Scottish Southern Electric (SSE) intend to retrofit post-combustion capture to an existing Combined Cycle Gas
Turbine (CCGT) at Peterhead Power Station, Aberdeenshire. The flue gas stream
will be routed to an absorber where about 90% of the CO2 will be removed by
application of amine capture technology. The CO2 will be transported by pipeline
approximately 100km offshore to the Goldeneye platform, where it will be injected
into a depleted gas reservoir for long-term storage, at a depth of more than 2km
under the floor of the North Sea. The project will capture in the region of 1Mt of CO2
each year during a 10-year demonstration phase.
14
The White Rose Project, for which Capture Power Limited (a consortium of Alstom Power, Drax Power Station and the British Oxygen Company) and National Grid
will build a new state-of-the-art 426MWe (gross) clean coal power plant with full
CCS, capturing approximately 2 Mt of CO2 per year. This will link into the planned
development of a CO2 transportation and storage infrastructure to an offshore
saline aquifer in the North Sea, which would have capacity for storing CO2 arising
in the future from possible additional CCS projects in the area. The Government then entered in to negotiations with these two preferred bidders to agree terms for FEED studies. As of April 2014, contracts had been signed for both the White Rose project and the Peterhead project. A final investment decision will be taken by the Government in early 2015 on the construction of the two projects, which, on that timescale, would be expected to become operational by 2020. In accord with the broader objectives outlined above, the UK Government is working with industry to create a new cost-competitive CCS industry for implementation in the period 2020 to 2030 (Gov.UK 2014). Support for the development of CCS includes: the £1 billion commercialisation competition to support practical experience in the
design, construction and operation of commercial-scale CCS;
a £125 million, 4-year co-ordinated research, development and innovation
programme; and
reform of the UK electricity market so CCS will be able to compete with other
low-carbon energy sources The latter point is being addressed with the development of a new pricing mechanism through the introduction of a Contract for Difference (CfD). This aims to secure the significant investment required to replace the generation capacity scheduled to close by 2020 and deliver a secure, low-carbon electricity system in a least-cost way. The CfD is a long term, private law contract that pays the generator the difference between an estimate of the market price for electricity (the ‘reference price’) and an estimate of the long term price needed to bring forward investment in a given technology (the ‘strike price’). This removes generators’ long term exposure to electricity price volatility, substantially reducing the commercial risks faced by these projects, encouraging investment in low-carbon generation at least cost to consumers (Gov.UK 2013b). The expectation is that companies with low-carbon generation with a CfD will sell their electricity into the market in the normal way, and remain active participants in the wholesale electricity market. This approach recognises that the levels of support required to ensure the transition to a decarbonised electricity market (and to achieve carbon and renewable energy targets) must take account of two core objectives, namely minimising costs to consumers and reducing uncertainty for investors. There are costs to replacing the UK’s ageing energy infrastructure with low-carbon alternatives, and the Government will aim to minimise the impact of its policies on the costs that consumers and businesses pay. The intention is that by giving advance visibility of the support available, and when and how prices may change, will provide developers with the clarity they need in order to plan their projects and take investment decisions.
2.3 The international relevance to China The USA and UK CCS demonstration programmes have both encountered significant
problems in establishing robust and transparent means of evaluating possible projects
15
for a commercial prototype CCS demonstration. Such means are necessary as, in
both cases, public money is being used to provide part funding. Of the two, the pitfalls
arising and the solutions applied are better described in the public domain in the case
of the UK. The lessons learned are of great value and would appear to be applicable
to any nation considering supporting a large scale demonstration project, including
China, whether this will be by open competition or by an alternative arrangement.
For any country that is determined to pursue CCS, the rationale and choices for
demonstration projects are strategic considerations, with a need for the national
context, technology status and other factors, such as feasibility, stakeholder interest,
timing and cost, to be taken into account. In particular, whatever the means used to
select possible projects for such demonstrations, there needs to be an audit trail of
steps taken and decisions made, since no government, internal or external investor
should sanction such a major investment unless they can be sure that the project is
technically robust and that a sound business case can be made. This requires the
project developer to provide suitable reassurances such that the funding body can
make an informed decision.
In the near term, the expectation is that CCUS, with CO2 utilisation included rather
than just storage, will be critical to making the technology a commercially viable option
within China as it offers a potential revenue stream that can to some extent offset the
additional operational costs arising. The main focus of such utilisation is for Enhanced
Oil recovery (EOR) although there are smaller scale options including for the
production of food and beverages, fertilizer and algae. It is also important to recognise
that CO2 utilisation can only fulfil a relatively minor role due to limited market
opportunities once large scale CCS deployment has to be implemented. CO2 based
EOR has been tested at reasonable scale in China, up to 100,000 tonnes CO2/year,
and there are strong plans to scale up such activities. To date, much of the CO2 has
been provided through natural gas stripping although some has been sourced from
CO2 capture on a coal fired power plant (Minchener 2011). EOR offers the least
carbon intensive route to obtain extra oil from domestic reservoirs, so improving
energy security for China. From a CCS perspective, much of the CO2 can remain
trapped in the oil deposit and provided that this is monitored this proportion of the
trapped CO2 can be designated as being stored. The exact proportion will depend on
the geological characteristics of the deposit. Studies in China have suggested that
about 60–70% of the CO2 is permanently sealed in the ground while the remainder is
removed with the extracted oil.
The initial stage in establishing a CCS demonstration project should be the provision
of a pre-feasability study for the power plant or other industrial process. This is a high
level assessment of the project that will establish an overall process concept, covering
the host plant and all stages of the associated CCUS techniques, in sufficient detail to
determine likely process performance and a techno-economic assessment such that
a better than order of magnitude costing can be determined. Within such a
16
pre-feasability framework, it is then possible to broadly identify capital and operating
costs that will be incurred should CCUS be introduced. This will allow a preliminary
assessment of whether such a project should be viable. As well as the technical
assessment, there would be a need to determine the conformity of each project with
the following criteria. Thus the intended project should:
Be consistent with Chinese energy & environment strategic objectives, as defined in the 12th Five Year Plan and other government documents;
Have support from local government for the implementation of the proposed project;
Comprise a large scale coal based process that is representative of the technology used in either the Chinese power, chemicals (including coal to liquids and gaseous
fuels), iron and steel, or building sectors, to which a CCUS technique will be
applied;
Include the whole technical chain of CO2 capture, transport and utilization/storage;
Be developed sufficiently such that a Front End Engineering Design (FEED) study will be able to start;
Be technically ready for capturing at least 85% CO2 from the gas stream;
Have a utilization/storage level equal to or larger than 100,000 tonnes of CO2, and preferably close to or in excess of 1 Mt CO2 per year;
Have a geological location identified and characterized to the extent that there is a reasonable expectation that the quantities of CO2 captured over the demonstration
project lifetime can be adequately stored/utilized:
Include downstream heat recovery, if a power project, to improve the overall process efficiency;
Include the design and implementation of a comprehensive monitoring and verification programme for CO2 storage, which will need to be applied also for
EOR applications since a portion of the CO2 remains within the reservoir. The expectation is that the owners of an acceptable project will be able to provide a positive response to each criterion listed above. The one exception at this first stage selection process might be the CO2 storage monitoring and verification where the fallback response would be the adequate recognition of the need for such a programme and suggestions as to how the owner might go about addressing this requirement if their project reaches the short list. If this pre-feasability study appears positive, the next stage would be to develop a robust design and costing for such a large scale technology demonstration. For this, it would be necessary to undertake a detailed front end engineering design (FEED) study, which corresponds to the point where very significant financial commitment needs to be made. To put the scale of this pre-project investment in context, the two FEED studies that were funded by the UK Government in their first CCS competition cost some RMB 400 million in total. The FEED study provides a verifiable means to justify the rationality of the technical CCUS option for the demonstration project, including system definition, identification of key problems and justification of proposed solutions. Items to be considered include:
17
Maturity of the demonstration project, including operational scope, scale of input, readiness of the infrastructure and associated industrial facilities for project
implementation, and availability of the necessary expertise, site and equipment;
Project innovativeness, including technological sophistication, and compatibility/suitability for implementation in China; and
Availability of a comprehensive management plan, including strategy and procedures to ensure full implementation of the project.
There will be a need to provide preliminary but justifiable estimates of the impact of applying CCUS to the industrial process on: process/cycle efficiency and the energy penalty per unit output; and
investment and operational costs including equipment for each part of the CCUS chain, extra land requirements, any characterisation work for the CO2 storage site,
additional coal use, water use, manpower, waste products disposal, environmental
permits, monitoring and verification costs. This will provide support for the overall financial model and plan, including total incremental cost of the demonstration and likely sources of financing. There will be a further need for the project owner to have a long-term operations plan for the plant with the CCUS integration when and after the project is completed. The project owner should also make a commitment to provide non-IPR data and materials to facilitate project evaluation by external experts, including dissemination of such information and materials generated during the implementation of the project as part of a programme for public awareness and acceptance, with some emphasis on the monitoring and verification results for any CO2 storage site (including EOR) within the project. It is also important to stress that China has already adopted this approach in the China-EU Near Zero Emissions from Coal (NZEC) Phase 2 collaborative project. Thus the Chinese team, under the guidance of the Ministry of Science and Technology and comprising key national CCS experts from well-regarded institutes and universities, made a call for proposals and then selected three coal based power sector proposed demonstration projects that had been put forward by major Chinese industrial organisations. The developers of each of these three projects are now being funded by the European Commission to carry out a small prefeasibility study. Once these studies are completed, the most appropriate proposal will be selected by the Chinese team to receive further significant funding from the European Commission to undertake a FEED study.
3 CCS DEVELOPMENT IN CHINA
3.1 Status of China’s CCS initiatives CCS can in principle be applied to any large scale stationery fossil fuel process. For
coal based technologies, this could include their use for the power, iron and steel,
cement and chemicals sectors. Globally, coal power dominates coal use and as such
must be seen as the more important sector to address. The next largest sectors are
iron and steel, and cement. However, in these cases, to date, progress with CCS
development is limited due to technical issues that have yet to be resolved. Globally,
18
the coal to chemicals sector is much smaller than the others, with almost all modern
units having been established in China.
From the Chinese perspective, current coal use in the power, iron and steel, cement
and chemicals sectors is about 2,200 Mt, 450Mt, 450Mt and 170 Mt respectively.
Interestingly, the coal chemicals sector, although currently smaller than the others,
offers significant near term relatively low cost CCS demonstration opportunities. This
is because the CO2 capture stage, which normally represents close to 80% of CCS
costs, is an integral part of the chemicals production process and so doesn’t represent
an add-on process cost. Consequently the overall CCS costs will be very much lower
than those in the other coal sectors.
CCS is a R&D priority for China, covering all capture options, transport and storage,
together with a strong level of international co-operation. The drivers are to reduce the
energy penalties and high costs for the first generation technologies while developing
improved second generation systems. Over the last decade, the national CCS
research programme has ranged from fundamental research on CO2 use for EOR
applications and long-term storage, to the development of advanced CO2 capture
technologies based on adsorption and absorption processes, and to explore and
characterise CO2 storage options together with technology for the monitoring of CO2
storage integrity. Many of these R&D activities include a strong level of international
co-operation, through capacity-building programmes with, amongst others, Australia,
Canada, the European Commission, Italy, Japan, the UK and the USA.
With regard to progression beyond research, China may have made a later start than
many other countries but it has achieved rapid success with various industrial
development activities. There are some very significant large industrial scale trials
that are being funded and implemented by major Chinese power generation, coal and
oil companies.
Indeed, China has established a significant CO2 capture technology base.Thus, for
post-combustion CO2 capture, China is as well advanced as other countries, with
Huaneng Power having successfully implemented a 120,000 tonnes CO2 /year
capture unit on a side-stream from the ultra-supercritical 2x660MWe Shidongkou No
2 pulverised coal power plant in Shanghai, the largest coal based project of its kind
prior to the successful start-up of the Boundary Dam project in Canada. Huaneng
Power is now examining a demonstration scale option for this technology via the
NZEC Phase 2A China-EU cooperation programme. For pre-combustion capture,
various companies have learnt a lot from their coal to chemicals programmes.
Shenhua Group has undertaken a full chain CCS trial on a coal to synthetic oil unit,
which comprises part capture of the CO2 vented from the coal gasifiers together with
compression and subsequent tanker transport and storage in a saline aquifer, at an
annual rate of 100,000 tonnes. There are plans to develop a larger facility capable of
handling ~1Mt CO2 annually. Further, Huaneng Power is planning to examine the
19
detailed application at an annual scale of 60,000 tonnes CO2 capture/year on a
sidestream from China’s first 250 MWe IGCC demonstration plant. With regard to
oxyfuel, Huzhong University of Science and Technology has undertaken extensive
trials at small industrial scale and is now working closely with Dongfang Boilers to
establish a 35MW industrial pilot scale unit. They are also undertaking a capacity
building project, with ADB and Dongfang Boilers support, to define the basis for a 200
MWe demonstration unit that would be hosted by Shenhua Guohua Power. This is
being supported by the ADB via the TA8133 Component B capacity building project.
Such oxyfuel demonstration plans are at a comparable scale to the intended activities
in the USA, if rather smaller than what may go ahead in the UK.
When CO2 storage is considered, Chinese understanding may not be as advanced as
that in the EU and the USA. However, increasingly, China is building up its expertise
and is starting to establish the basis for a national CO2 storage atlas, which
represents a key step in the rationalization of CCS. These points are considered
below.
There are various CO2 EOR activities underway, including monitoring of CO2 stored,
reflecting China’s interest in CO2 utilisation. A series of large-scale trials by major oil
companies is underway, which are a direct scale-up and development of the research
undertaken previously. This includes PetroChina, which has carried out a major CO2
EOR-related activity by stripping CO2 from a natural gas source and injecting it into at
the Jilin Oilfield, Liaoning Province. PetroChina reports that, in some cases, oil
recovery through CO2 injection may be enhanced by 10–20%. For 2015, the aim is to
achieve an annual additional oil extraction of 500,000 tonnes, with a CO2 storage
capacity of some 0.8–1.0 Mt (MOST 2010). Sinopec has undertaken some EOR
activities in the Shengli oilfield of Shandong Province (Zhang and others, 2011) using
CO2 captured in a post-combustion capture system with MEA solvent at the Shengli
coal power plant. There are provisional plans to scale up operations for a 1 Mt/y CO2
EOR demonstration project in the oilfield for operation by 2015 (MOST 2011).
CO2 EOR may be less developed in China than the USA although China’s oil
companies are now major representatives within the industrial scene. As such, they
are gaining the necessary expertise by cooperating with other companies and, as
appropriate, buying that expertise through international business purchases (Ding
2009; MOST 2013). Apart from EOR, China has also shown significant interest in
other CO2 uses, including CO2 synthesis for energy chemicals, copolymer plastics
and carbonic acid esters. This work is mostly at the small scale pilot development
stage.
With regard to storage, as distinct from EOR in which only some of the CO2 is
permanently retained in the deposit, there is reasonable recognition that the use of
onshore and, in places, offshore storage in saline aquifers represents the ultimate
way forward. The leader in assessing aquifer based CO2 storage has been Europe,
20
with about 1Mt of CO2 being successfully stored and monitored each year for over
twenty four years in an offshore aquifer. That said, China’s onshore saline aquifer
study on the Shenhua coal to oil project in the Erdos region, which was established
with USA technical assistance, represents a valuable assessment in its own right.
It is also important to highlight some of the financial issues, which are covered in
greater detail in other work packages. For China, the funds to carry out the underlying
research have been provided through the National High-Tech (863) Programme, the
National Basic Research (973) Programme, the State Science and Technology
Support Programme, major science and technology special funds, and various
international cooperation project funds. For the subsequent industrial pilot scale
activities, funding has been gathered from a number of sources. These include public
funds, via various government sources, international financing by organisations such
as the ADB and the European Commission, as well as from the industrial enterprises
themselves. For the possible large scale demonstrations, in general terms, the
approach is similar but the scale of requirements is much greater. Indeed, every study
on financing for CCS demonstrations in developing countries, including the work of
the ADB, has highlighted the importance of international grant support, and support to
operations to be combined with other fiscal measures (The Climate Group, 2010).
Consequently, financing of an early-stage demonstration project will be a complex
process. Finally, with regard to policies and regulations, China has made limited progress. It
has issued a series of policies, which relate to climate change and possible mitigation
approaches, in which it has publically recognized the potential importance of CCS in
order to establish near-zero emissions fossil fuel power generation systems. However,
to date, while a significant R&D programme is underway, there has not been too much
consideration of subsequent technology deployment and there has been no declared
intention to progress beyond the demonstration stage (Minchener 2011).
Regulations will be needed to support the demonstration and deployment of CCS in
China, particularly for the geological storage of CO2, but also to address the safety of
pipelines carrying CO2 and the environmental impact of CO2 capture plants. There has
been considerable work undertaken internationally, based on the EU member states’,
USA, Canadian and Australian initiatives, together with the outputs arising from the
International Energy Agency (IEA) Working Group on CCS regulation (IEA 2010).
Various ADB capacity building studies have also considered this issue. These have
concluded that for demonstration purposes, existing regulations should be able to be
modified to accommodate CCS demonstration (ADB 2010 and 2013) and that the
outputs arising should provide the basis for deployment-specific regulations to be
established.
3.2 Overview of China’s current demonstration project proposals
The industrial scale pilot activities have built on the laboratory work, provided
information for design of plant, allowed an understanding of how capture systems
21
work with real flue gas streams, and provided hands-on experience for some aspects
of CO2 utilisation and storage. This has led to a number of commercial prototype
demonstration prospects, of which those that meet the GCCSI criteria are included in
the LSIP database (GCCSI 2014a).
On the basis of information provided either by MOST or the GCCSI, a list of possible
coal based CCS demonstration projects has been compiled, Table 3. This comprises
several possible projects that meet the GCCSI criteria plus others that are smaller but
within the broad range that might be worthwhile taking forward, as agreed by the
NDRC and ADB. Those projects marked with a * include some data that have been
provided either from MOST or from discussions with prospective project developers.
However, in all cases, it can be seen that the level of information that has been
obtained is very limited, which is a combination of many potential projects being at an
early concept stage together with a reluctance by developers to provide data. In
particular, with regard to utilization/storage opportunities within oil fields and saline
aquifers, there is minimal site specific data available. Therefore the estimates are
limited in most instances to indicative capacities within potential candidate areas of
the main sedimentary basins and the overall oilfields. As such, there is considerable
uncertainty in any assessments of the likely distance between CO2 source and
possible storage areas. Combined with the limited information on the intended CO2
capture route, this means that the estimates of the overall CCS costs are very
uncertain. Consequently, the scope to be able to provide a meaningful ranking of
these potential projects is constrained. This has a direct impact on what can be
achieved, as is considered in the section below.
22
Table 3 Listing of possible large scale coal based CCS demonstration projects in China
Name Location
Scale
(tonnes
CO2
/year)
CO2
concentration
prior to
capture
Capture
process
CO2
utilisation/
storage
option
CO2
Transportation
distance (km)
CO2 emission
reduction
cost
(RMB/tonne)
Project status
Phase 3 of
China
Huaneng
Group's
GreenGen
Project *
Tianjin 500,000
-1500,000 35%-45%
Coal based IGCC
power plant,
pre-combustion
capture
Geological
storage
or EOR
<100 400-500
Preliminary feasibility
study. Provisional plan
to operate in 2016.
Have not yet entered
the substantive action
Sinopec
Shengli Oil
Field CCS
Project
Shandong 1,000,000 13-16%
Coal-fired power
plant, post-
combustion capture
EOR <100 350-400
1st phase completed.
Plan to complete 2nd
phase construction
during 2015
Shenhua
Group Yulin
Coal to
Liquid
Project*
Shaanxi 2,000,000 35-45%
Coal chemical,
pre-combustion
capture
EOR 10-50 200-300
Preliminary feasibility
study. Plan to progress
construction in 2015.
Shenhua
Ningxia Coal
to Liquid
Plant Project
Ningxia 2,000,000 35-45%
Coal to chemicals,
pre-combustion
capture
EOR 10-50 200-300
Preliminary feasibility
study. Plan to progress
construction in 2015.
23
Name Location
Scale
(tonnes
CO2
/year)
CO2
concentration
prior to
capture
Capture
process
CO2
utilisation/
storage
option
CO2
Transportation
distance (km)
CO2 emission
reduction
cost
(RMB/tonne)
Project status
Yanchang
Oil Field
EOR Project
Shaanxi 360,000 35-45%
Coal to chemicals,
pre-combustion
capture
EOR <50 300-350
Design. Plan to
complete construction in
2014. Carbon capture
part of the project has
commenced, the oil
recovery part of the
project is under site
selection and testing
Shanxi Intl
Energy
Group
CCUS
Project
Shanxi 2,000,000 40-50%
Coal-fired power
plant, 2x350MW,
oxyfuel combustion
capture
geological
storage or EOR 100-200 210-270
Preliminary feasibility
study and so capyture
costs are very
approximate. Have not
yet entered the
substantive action
Alstom &
Datang
Daqing
Project
Heilong
jiang
1,000,000
(50%
capture rate)
40-50%
Coal-fired power
plant, 350MW, oxyfuel
combustion capture
Storage +EOR 50-100 200-300
Feasibility study, plan to
start construction during
2015
Datang &
Alstom
Dongying
Project
Shandong 1,000,000 40-50%
Coal-fired power
plant, 1000MW,
oxyfuel capture
Storage +EOR 50-100 200-300
Feasibility study, plan to
start construction during
2015
24
Name Location
Scale
(tonnes
CO2
/year)
CO2
concentration
prior to
capture
Capture
process
CO2
utilisation/
storage
option
CO2
Transportation
distance (km)
CO2 emission
reduction
cost
(RMB/tonne)
Project status
Lianyung
ang IGCC
with CCS
Project
Jiangsu 3,000,000 40-50%
Coal-fired power
plant,pre-combustion
capture
Storage or
chemical
industry
30-50 200-300
Planning. Have not yet
entered the substantive
action
China
Guodian
Corp CCUS
Project
Tianjin 2,000,000 13-17%
Coal-fired power
plant,
post-combustion
capture
geological
storage or EOR - 300-400 Planning
Huaneng
Group
Yuhuan
Power Plant
Phase III
Zhejiang 500,000
-800,000 13-17%
Coal-fired power
plant,
post-combustion
capture
EOR or
chemical
industry
>100 300-400 Planning
CO2
Geological
Storage
Project
Inner
Mongolia 1,000,000 35-45%
Coal chemical,
pre-combustion
capture
Underground
salt water
cavern
<50 250-350
Planning. The first
phase of project is
funded by the ministry of
land and resources.
Yulin Energy
/Chemical
Group
Shaanxi 350,000 >90%
Coal chemical,
pre-comb capture
Industrial grade
CO2 <50 <200 Preliminary feasibility
study.
25
Name Location
Scale
(tonnes
CO2
/year)
CO2
concentration
prior to
capture
Capture
process
CO2
utilisation/
storage
option
CO2
Transportation
distance (km)
CO2 emission
reduction
cost
(RMB/tonne)
Project status
Shenhua
Guohua
oxyfuel
project
Shenmu,
Shanxi 1,000,000 13-17%
200 MWe coal-fired
power plant,
oxygen-enriched
combustion capture
Storage +EOR 130-150 200-300
Feasibility study, plan to
start construction during
2015
Huizhou
Refining,
coal to
hydrogen
project
Guang
dong 300,000 13-17%
Coal-fired power
plant, pre-combustion
capture
Offshore storage
+EOR 100-200 200-300 Preliminary feasibility
study.
Whole
industry
chain project
The
Northwest 5,000,000 40-50%
Coal chemical,
pre-combustion
capture
EOR 100-200 200-300
Preliminary feasibility
study, plan to launch in
2015
26
3.3 Rationale for ranking of possible projects
Within the Chinese context, the requirement is to demonstrate the complete CCUS
chain, in order to build on the previously undertaken research activities and the
various industrial pilot scale CCUS technology projects. As described above, such
demonstrations need to encompass technical, environmental and economic
performance issues such that enterprises can be encouraged to accept commercial
CCUS projects and that ultimately positive public perception can be achieved. These
demonstrations also allow the Chinese Government to establish appropriate
mechanisms for the organization and management of subsequent large-scale CO2
emission reduction projects, in order to lay the foundation for future deployment of
commercial scale CCUS projects. The sixteen possible coal based CCS demonstration projects for China that have
been identified, Table 3, represent a reasonable listing although the great majority are
at the early concept stage. As noted above, the level of process information that is
available is generally insufficient to allow any robust assessment of likely technical
and economic performance to be undertaken. Consequently, the best that could be
achieved would be a preliminary ranking of possible projects. Once such a ranking
has been produced, the Chinese Government could encourage the project developers
of the more promising options to produce a comprehensive pre-feasability dataset
and to show how their proposed projects meet the following criteria:
Be consistent with Chinese energy & environment strategic objectives, as defined in the 12th Five Year Plan and other government documents;
Have support from local government for the implementation of the proposed project;
Comprise a large scale coal based process that is representative of the technology used in either the Chinese power, chemicals (including coal to liquids and gaseous
fuels), iron and steel, or construction sectors, to which a CCS technique will be
applied;
Include the whole technical chain of CO2 capture, transportation and utilization/storage;
Be developed sufficiently such that a Front End Engineering Design (FEED) study will be able to start;
Be technically ready for capturing at least 85% CO2 from the gas stream;
Have a utilization/storage level equal to or larger than 100,000 tonnes of CO2, and preferably close to or in excess of 1 Mt CO2 per year;
Include downstream heat recovery, if a power project, to improve the overall process efficiency;
Include the design and implementation of a comprehensive monitoring and verification programme for CO2 storage, which will need to be applied also for
EOR applications since a portion of the CO2 remains contained within the
reservoir.
It is strongly recommended that, in order to implement this suggested approach, the
Chinese government should consider setting up an independent panel of industrial
27
experts to work with the project developers to gather the process related data
necessary to assess the project viability against the key criteria set out above. In this
way, a robust and transparent selection process could be established that would lead
to a shortlist of projects being produced from which the most attractive, realistic
options could then be subjected to a FEED study. Once these were completed and,
subject to acceptable results and a financing plan being established, this would allow
the Chinese government to take well informed decisions as to how such bankable
demonstration projects could be taken forward.
4 GENERIC APPROACH TO PROVIDE A PRELIMINARY RANKING OF CHINESE DEMONSTRATION PROPOSALS
Within this ADB TA project, recognising the data limitations, a possible procedure has
been suggested, which would allow a reasonable preliminary ranking of possible
projects to be determined. This approach considers a range of technical parameters
and assigns weighted scores that are dependent on the overall objective of the
demonstration programme. For example, this can be to determine the near-term need
to identify potentially low cost opportunities in the coal to chemicals sector and the
medium term requirement to identify possible projects that offer high replicability
potential, which would focus on the coal power sector.
4.1 Basic principles of intended project evaluation This suggested approach is generic, based on a mathematical method that is applied
to build a comprehensive evaluation model, from which an integrated assessment
index is calculated. This has been used as the theoretical basis of technology
selection and project scheduling. Each project is assessed against several criteria, in
each case with a score being assigned. These scores are aggregated with the overall
index being calculated by a weighted integrated computing approach to provide the
final selection result, i.e. the CCUS Project Priority. The weighting of the scores
reflects the fact that if project selection should be driven by the need to ensure low
costs projects then there will be some differential compared to selecting projects
where replicability is the priority. As the level of information on most projects is very
limited, this system can provide some guidance as to project suitability within the
national context. However, it is not a means by which significant financial decisions
can be taken, as noted previously.
A large scale CCUS demonstration project needs to address technological, economic
and environmental issues within a complex implementation framework that will most
likely involve several organisations from various industrial sectors. This raises major
organization and managerial challenges, which must be met in order to lay the
foundation for a subsequent commercial scale project that will comprise the start of
the PRC deployment phase. As such, there is a need to consider the following project
principles:
28
Sustainable development principle, which should comply with the required
environmental sustainability of China's energy strategy.
Within the near term CCS demonstration opportunities, the need is to ensure that CO2
utilisation can be included wherever possible as a revenue source that can contribute
to lowering the overall costs of such demonstrations.
Economic principle, which recognizes the need to drive down energy use and
costs for the overall CCS process.
The cost per tonne of CO2 avoided for CCS is lower than most other low and near
zero CO2 technologies (Stern 2010). However, because it needs to be applied at large
scale, this currently represents a very significant additional cost burden on the coal
based process to which CCS might be applied. This places several obligations on
demonstration project developers, in particular to learn by doing such that the means
to reduce efficiency losses and ways to limit capital and operating costs can be
established.
Reliability principle, which means that there must be a strong case that any
technology to be demonstrated can meet the expected performance
requirements on a consistent basis.
It is important for early CCUS demonstration projects to succeed and to establish
long-term, stable operation, which can increase the confidence of the government and
the public that these technologies can meet the future requirements for decarbonizing
the coal based industrial economy. Thus the technology chosen to be demonstrated
has to have been shown to be reliable at least at the industrial pilot scale. While this is
generally the case with most CO2 capture options, the PRC has less experience of
large scale CO2 pipeline transport and relatively limited CO2 storage projects although
its knowledge of CO2 driven EOR is growing rapidly.
The scope to expand principle, which means there must be the prospect that
any demonstration of a technology can be subsequently scaled up for
commercial applications.
For example, if a demonstration project has an annual CO2 capture of up to 1,000,000
tonnes, the technology should be capable of being scaled-up to 10,000,000
tonnes/year before 2030, such that the demonstration can address the future
application of industrialization scale.
Funding availability principle, which requires that robust funding routes can be
identified in order to reflect the significant potential of the designated CCS
demonstration project.
Financing of an early-stage demonstration project will be a complex combination of
various forms of support. These include public funds, via various government sources,
international financing by organisations such as the ADB and the European
Commission, together with the project developers’ own investment.
29
Legal and regulatory support principle, which ensures that the demonstration
projects can proceed.
Regulations will be needed to support the demonstration and deployment of CCS in
China, particularly for the geological storage of CO2, but also to address the safety of
pipelines carrying CO2 and the environmental impact of CO2 capture plants. Various
ADB capacity building studies have considered this issue. These have concluded that
for demonstration purposes, existing regulations should be able to be modified to
accommodate CCS demonstration (ADB 2010 and 2013) and that the outputs arising
should provide the basis for deployment-specific regulations to be established.
The suggested CCUS demonstration project evaluation index system is outlined in
Figure 1.
Figure 1 Suggested CCUS demonstration project evaluation index system
4.2 Construction of evaluation criteria and indicators system The comprehensive evaluation index system is multifaceted. The following key issues
are considered particularly relevant (Shen 2010):
Integration of the various parts of the CCS process
30
Quantifiable outcomes
Specific application characteristics
Fully relevant to Government policy objectives
4.2.1 Evaluation design and scoring criteria
The evaluation index system has been established by selecting relatively independent
indexes which are also rich in connotation. The theoretical analysis method is used to
fully reflect and distinguish each index based on project benefit characteristics.
Subsequently, the method of frequency analysis is used to gather statistics and
analyzes various indexes from a variety of sources. Finally, the actual CCUS technical
benefit evaluation index system is established by screening and adjusting of the index,
based on expert opinion.
4.2.2 Construction of model
An analysis hierarchy process (AHP) is used to establish the index system. First, the
target is divided into a specific criteria layer and a target layer, and then each layer is
subdivided into smaller systems where the index can be established. Once the indices
for these small systems are established, the whole index system can be divided into
three layers, namely the target layer, criteria layer and index layer (Diakoulaki 1995).
Based on a study of the characteristics of CCUS demonstration projects, and adjusted
by expert consultation, the evaluation index system is established with a hierarchy
structure of target layer and index layer, Table 4. In the hierarchy structure, the target
layer is to reflect the overall level of the CCUS demonstration project, which is
expressed by the CCUS Project Priority (CPP).
For the CCUS technology comprehensive evaluation model, the weighting of each
index is very important. For this multi-objective, multi-attribute decision-making
problem, the effect of each assessment on the result and attributes is not equal, and
the index weight can be used to describe the relative importance of the attributes of
the decision-making plans. When the value of every index is determined, the
evaluation result significantly depends on index weights. There are currently several
methods to determine such weights, which are reviewed in Table 5 (Zhou 2007). For
this study, the use of experts to determine the index weights has been adopted. Thus, the assignment of the index weightings is given as follows: indexes in the same
criterion layer are assigned with an equal weight; the weights of different criterion
layers are assigned by the class due to their importance, and the weight of higher
class is two times of the nearby one; all the eight criterion are classified into three
classes, namely normal criterion (weight 1), important criterion (weight 2) and leading
criterion (weight 3). For the selection of leading criteria, according to different
evaluation directions, two different weight standards are determined based on
economic benefit and potential replication of the projects and technologies, Table 6.
31
Table 4 Summary of CCUS demonstration project evaluation index and classification
Criterion layer Evaluation index
5 4 3 2 1
Sources of CO2 CO2 sources
Key industries (power plant, steel, cement, coal to chemicals company)
Non-ferrous metal industry
Other chemical, construction material industries
Other industries Non-chemical industries
CO2 concentration >80% 60%-80% 40%-60% 20%-40% <20%
CO2 emission reduction cost
unit emission reduction costs (RMB)
<200 200-299 300-399 400-599 >600
Byproduct economic benefits of CO2 utilization
>500 RMB / t-CO2 200-500 RMB / t-CO2 100-200 RMB / t-CO2 <100 RMB / t-CO2 0 RMB / t-CO2
Global performance of CO2 emission reduction technologies
Technical maturity Mature and being promoted
Under promotion with 3~5 demonstration projects
One demonstration project
Under intermediate trial stage
Under laboratory trial stage
Scale of project emission reduction
>1,000,000tpa CO2 300,000-1,000,000tpa CO2
100,000-300,000tpa CO2
10,000-100,000tpa CO2
<10,000tpa CO2
Domestic IPR 100% At least 90% At least 80% At least 70% Less than 70%
Emission reduction program integrity
Storage source compared to CO2 storage requirement
On-site utilization or
storage(0-10km)
Utilization after
short-distance pipeline
transportation (10-50km)
Utilization after
medium distance pipe
transportation
(50-100km)
Utilization after
long-distance
transportation
(>100km)
No utilization
Applied potential of emission reduction technologies
Near-term potential >100,000,000 tpa CO2 10,000,000-100,000,000 tpa CO2
5,000,000-10,000,000 tpa CO2
1,000,000-5,000,000 tpa CO2
<1,000,000 tpa CO2
Middle and long term potential
>1,000,000,000 tpa CO2
100,000,000- 1,000,000,000 tpa CO2
50,000,000- 100,000,000 tpa CO2
10,000,000- 50,0000,000 tpa CO2
<10,000,000 tpa CO2
Project organization and financing options
Organization One single enterprise Two enterprise cooperation
Three enterprise cooperation
Four to five enterprise cooperation
Five and above enterprise cooperation
32
Table 5 Methods to Assign Index Weights
Item Method Brief Introduction of the Method Characteristics of the method
Subjective
weighting
methods
Experts
Mark Expert consulting, back to back evaluation and summarizing.
This method is easy to operate and by using the
knowledge of the experts, the conclusion is easy
to reach. However, the subjectivity is strong and
it can be difficult to achieve convergence of
experts’ views.
AHP
For multi-layer structure system, firstly with the comparison of relative amount,
determine several judgment matrix, and then set the eigenvectors as the weights,
finally comprehensively calculate the weights.
High reliability, with small errors. However, this
can still be affected adversely by subjective
assessments at the early stage of the overall
process.
Objective
weighting
methods
Entropy
method
According to the basic principle of information theory, information is a measurement
of orderly degree in a system and entropy is measurement of disorder degree in a
system. And if the entropy of an index is smaller, the information that this index
offers is larger, the effect of the index in the comprehensive evaluation is larger and
the weight of this index is higher.
All these objective weighting methods rely on the
quality of data and ignore the relative importance
of the index itself. So when data are insufficient
or the distribution of index value is unbalanced, it
is not suitable to adopt objective weighting
methods.
Standard
deviation
method
Similar to entropy method, if the standard deviation of an index is lager, it indicates
that the variation of this index is larger, the information it offered is more, the effect
of the index in the comprehensive evaluation is larger and the weight of this index is
higher. Otherwise, if the standard deviation of an index is smaller, it indicates that
33
the variation is larger, the information it offered is less, the effect of this index in the
comprehensive evaluation is smaller and the weight is lower.
CRITIC
When determining the objective weight of the index, the conflict of intensity and
contrast intensity should be considered. Contrast intensity indicates the gap of the
values assigned by different evaluation scheme of the same index, which is shown
in the form of standard deviation.
The standard deviation indicates the gap between the values assigned by different
evaluation scheme of the same index. And the standard deviation is bigger, the gap
between different methods is bigger. Since contrast intensity is based on the
correlation between indexes, if two indexes are positive correlation, it indicates that
the contrast intensity of these two indexes is smaller.
Artificial
neural
network
A large-scale parallel non-linear dynamics system.
34
Table 6 Index weighting where either cost or replicability is critical
Guiding
index
CO2
source
CO2
concn
CO2
unit
redn
cost
CO2
utilizn
benefit
Tech maturity
%
CO2
redn
IPR
CO2
source and sink match
Near
term potl
Long term potl
Organizn
Cost 1 1 3 3 2 2 2 2 2 2 1
Replicability 1 1 2 2 2 2 2 2 3 3 1
35
5. CHINA CCUS DEMONSTRATION PROJECT PRELIMINARY EVALUATION AND SELECTION
The sixteen potential CCUS demonstration projects have been assessed using the generic model approach described above and a ranking
assigned.
5.1 Presentation of overall results The results are given in Table 7.
Table 7 Basic evaluation results (arrayed by project number)
Name
Allotted scores for each criterion
Overall
project
ranking
CO2
indl
Source
CO2
concn
Unit
CO2
redn
cost
CO2
utilsn
benft
Tech
mature
IPR %
CO2
redn
Source
and
Sink
Match
Short
term
potl
Long
term
potl
Organ Cost
basis
Repl
basis
Phase 3, China
Huaneng Group's
Tianjin GreenGen
Project
5 3 2 1 4 4 3 3 4 5 5 2.72 2.96
36
Sinopec Shengli Oil
Field CCS Project
5 1 3 3 4 5 3 4 4 5 4 3.12 3.24
Shenhua Group
Yulin Coal to Liquid
Project
5 3 3 3 4 5 3 3 5 3 3 3.00 3.08
Shenhua Ningxia
Coal to Liquid Plant
Project
5 3 4 3 4 5 3 2 5 3 3 3.04 3.08
Yanchang Oil Field
EOR Project
5 3 3 3 4 4 2 2 5 3 3 2.76 2.84
Shanxi International
Energy Group
CCUS Project
5 3 4 1 2 5 2 2 4 5 3 2.64 2.80
37
Alstom & Datang
Daqing Project
5 3 4 2 2 5 2 3 4 5 3 2.84 2.96
Datang & Alstom
Dongying Project
5 3 4 2 2 5 2 3 4 5 3 2.84 2.96
Lianyungang IGCC
with CCS Project
5 3 4 2 4 5 2 2 5 3 3 2.84 2.92
China Guodian
Corporation CCUS
Project
5 1 3 1 4 5 2 1 4 5 5 2.60 2.80
Huaneng Group
Yuhuan Power Plant
Phase III
5 1 3 3 4 4 3 2 4 5 3 2.84 2.96
38
CO2 Geological
Storage Project
5 3 4 1 3 5 3 4 5 3 2 2.84 2.96
CCUS project of
Yulin Energy and
Chemical Group
5 5 4 2 4 4 3 2 4 4 3 2.92 3.00
Shenhua Guohua
oxyfuel project
5 3 4 2 3 5 3 2 4 5 5 3.00 3.12
Huizhou refining
coal to hydrogen
project
5 1 4 1 3 3 3 2 4 5 4 2.60 2.76
Whole industry
chain project 5 3 4 3 4 5 3 2 5 3 3 3.08 3.12
39
5.2 Ranking on a lower cost basis and a replicability basis The top ranked early CCUS demonstration projects in the PRC, which would be for
plants in the coal-to-chemicals sector, where low cost capture and CO2-EOR is
economically feasible, are listed in Table 8. For the power sector, some early CCUS
demonstration projects have also been identified, as listed in Table 9. These have a
similar selection criteria to the coal to chemicals projects, but with an emphasis on the
potential for low-cost capture, future replicability and the credibility of the project’s
supporting proponents.
Table 8 Provisional list of early CCUS projects where
Low cost is the key assessment criterion
Rank Project Name Location
CO2 capture
scale
(tonnes/year)
Project Status
1 Whole industry chain
project
The
Northwest 5,000,000
Preliminary
feasibility study.
2 Shenhua Ningxia Coal to
Liquid Plant Project Ningxia 2,000,000
Preliminary
feasibility study.
3 Shenhua Group Yulin Coal
to Liquid Project Shaanxi 2,000,000
Preliminary
feasibility study.
4
CCUS project of Yulin
Energy and Chemical
Group
Shaanxi 350,000 Preliminary
feasibility study.
Since the input information to the modelling process is limited both in scope and
accuracy, it is evident that there is not a significant differentiation between the results
obtained for the various projects. As such, while the listing in Table 8 broadly
represents the more promising opportunities, there is little significance between the
rankings, based on the criteria used in the assessment. Thus these four coal to
chemicals related possibilities are reasonably well advanced in their planning and
design activities and all include some level of CO2 EOR application, which will provide
a revenue stream that will offset some of the operational costs associated with the
implementation of CCS.
Where replicability is paramount, there are two potential coal power projects that
generally show significant promise while also showing that the assessment process
cannot readily identify specific winners, in part due to the lack of adequate quantifiable
process and financial data. For the medium term, when wide scale replicability will
become important, it will be important to consider all three first generation CO2
capture possibilities since no clear technology winner can yet be identified. Thus
post-combustion CO2 capture fitted to pulverised coal power plant will be very
important as this technology is readily suited for retrofit to the modern components of
40
the existing coal power fleet. Similarly, oxyfuel will also need to be considered as it
can be readily applied to existing power plants. In both cases, the technologies will be
applicable for new applications, with some suggestions that oxyfuel might offer some
potentially significant capital cost and operational cost reductions compared to the
alternatives. Finally, IGCC should not yet be discounted as, although it is not yet
technically and economically proven, there still appears to be scope to offer lower CO2
capture opportunities, albeit for new plant only, compared to the other two prospects
in due course.
Table 9 Provisional list of CCUS projects
where replicability is the key assessment criterion
Rank Project Name Location
CO2 capture
scale
(tonnes/year)
Project Status
1 Sinopec Shengli Oil Field
CCS Project Shandong 1,000,000 Design.
2
Shenhua Guohua oxyfuel
combustion 200 MWe
project
Shanxi
Shenmu 300,000
Preliminary
feasibility study.
5.3 Description of the top ranked projects A short description is given below for those possible projects in Tables 8 and 9 where
either fully verifiable data (GCCSI 2014c) or an alternative description in english from
reputable national sources are available.
5.3.1 Regional whole industry chain project
Project owner: Shenhua Group
Location: Initial work in Inner Mongolia, with the aim to establish a regional network
also covering Gansu, Ningxia, and Shanxi Provinces
Technical aspects
Pre-feasibility study and pilot test planned for 2014/2015 and then a FEED study for a 1-2 million tonnes CO2 per year capture and EOR project plus an assessment
for a subsequent inter-provincial CCUS network around the Erdos basin oil fields,
including capturing CO2 from coal-fired power plants as well as coal to chemical
plants Overall aim is a CO2 capture and utilisation opportunity covering part of Inner
Mongolia, Gansu, Ningxia, and Shanxi Provinces, with an annual CO2 utilisation
capacity of some 5 Mt.
Key deliverables
Shenhua and CNCPC have signed a MOU with the China Petroleum and Chemical Industry Federation, to work together and for CNCPC to use the
captured CO2 for EOR in an oil field in the Erdos region.
41
5.3.2 Shenhua Ningxia Coal to Liquid Plant CCS Project
Project owner: Shenhua Group
Location: Ningdong Energy Chemical Industry Base, Ningxia Province
Technical aspects
Pre-combustion CO2 capture
CO2 transport via onshore to onshore pipeline 200-250km
Various storage options are being considered, as well as CO2 EOR
New build coal-to-liquids (CTL) plant capturing around 2 Mt CO2 each year, with an
expected life time capture of 60 – 70 Mt.
Key deliverables
Pre-feasibility (concept) studies were completed in 2009.
Commercial operation not expected before 2018.
5.3.3 Yulin Energy and Chemical Group CCS demonstration in Shaanxi
Province
This project is too small to appear on the GCCSI LSIP database. Information has
been provided via various national experts working on this ADB study.
Project owner: Yulin Energy and Chemical Group
Location: Shaanxi Province, China
Technical aspects
Pre-combustion capture of waste CO2 arising from the coal to methanol process
CO2 transport by onshore to onshore pipeline for 200-250km
Use of CO2 in enhanced oil recovery
CO2 capture of around 350,000tonnes per annum.
Total CO2 capture for the life time of the project is expected to be in the range of 6-8 Mt.
CO2 transport distance of 200-250 km by pipeline for use in EOR at an operating oil field in Shaanxi Province.
Key deliverables
Final investment decision for CCS project is expected in 2014.
CO2 available for storage (capture operation start date) is expected in 2015-2016.
A commercial agreement for the off-take of CO2 for use in EOR has been reached.
Pilot scale capture unit with an annual capacity of 50,000 tonnes CO2 was built in November 2012. Project approval for the second phase has been sought. It is
claimed that the necessary capital investment has been guaranteed although no
details are forthcoming
42
5.3.4 Sinopec Shengli Oil Field EOR Project (Phase 2)
Project owner: Sinopec
Location: Dongying, Shangdong Province, China
Technical aspects
Retrofit of post-combustion carbon dioxide (CO2) capture at an existing fluidised bed boiler power plant.
Capture of around 1 Mt per annum of CO2, with an equivalent power output range of 101 – 250 MWe range.
Total CO2 capture for the life time of the project is expected to be in the range of 21 – 30 Mt.
Transport distance of between 50km – 100km by pipeline for use in EOR at an operating oil field in Shangdong Province.
Key deliverables
Final Investment Decision for CCS project is expected in 2014.
CO2 available for storage (capture operation start date) is expected in 2015-2016.
A commercial agreement for the off-take of CO2 for use in EOR has been reached.
Scope to identify means to reduce the relatively high energy consumption of the capture process, which might include new absorber design with better solvents as
well as heat integration and coupling optimization. In the longer term, the
introduction of membrane separation as an alternative CO2 capture technology,
which has the potential to reduce energy consumption, may prove possible. Thus
would require a separate demonstration project.
5.3.5 Shenhua Guohua oxyfuel CCS project
Information was obtained via national experts working on a complementary ADB
project
Project owner: Shenhua Group
Location: Shenhua Guohau Power Plant, Shenmu, Shanxi Province
Technical aspects
200MW oxyfuel combustion CO2 capture retrofit project
CO2 capture of 1 Mt per year
CO2 transport via onshore to onshore pipeline 50-80km
Some CO2 EOR is intended with the rest of the CO2 being stored in a saline aquifer
Key deliverables
Pre-feasability study is in progress and is expected to be finished within 2014
43
6 PROPOSED NEXT STAGES OF THE ASSESSMENT PROCESS As has been described in Section 2.3, ultimately there is a need to establish a robust
verifiable approach for project selection, which would build on the preliminary
assessment reported here in Tables 8 and 9. This would comprise a pre-feasability
study for the more promising power plant or other industrial process projects listed. As
well as the technical, economic and environmental assessments, there would be a
need to determine the conformity of each project with the following criteria to ensure
that the intended project should:
Be consistent with Chinese energy & environment strategic objectives, as defined in the 12th Five Year Plan and other government documents;
Have support from local government for the implementation of the proposed project;
Comprise a large scale coal based process that is representative of the technology used in either the Chinese power, chemicals (including coal to liquids and gaseous
fuels), iron and steel, or building sectors, to which a CCS technique will be applied;
Include the whole technical chain of CO2 capture, transportation and storage /utilisation;
Be developed sufficiently such that a Front End Engineering Design (FEED) study will be able to start;
Be technically ready for capturing at least 85% CO2 from the gas stream;
Have a storage/utilisation level equal to or larger than 100,000 tonnes of CO2, and preferably close to or in excess of 1 Mt CO2 per year;
Have a geological location identified and characterized to the extent that there is a reasonable expectation that the quantities of CO2 captured over the demonstration
project lifetime can be adequately stored/utilized:
Include downstream heat recovery, if a power project, to improve the overall process efficiency;
Include the design and implementation of a comprehensive monitoring and verification programme for CO2 storage, which will need to be applied also for EOR applications since a portion of the CO2 remains contained within the reservoir.
For the proposed projects where the pre-feasability studies appear most positive, the next stage would be to undertake a detailed front end engineering design (FEED) study. This provides a verifiable means to justify the rationality of the technical CCS option for the demonstration project, including system definition, identification of key problems and justification of proposed solutions. This will provide support for the overall financial model and plan, including total incremental cost of the demonstration and likely sources of financing. In addition, where the likelihood that a financing plan is justified and can be established, the project owner should also make a commitment to provide non-IPR data and materials to facilitate project evaluation by external experts, including dissemination of such information and materials generated during the implementation of the project as part of a programme for public awareness and acceptance, with some emphasis on the monitoring and verification results for any CO2 storage site (including EOR) within the project.
44
Finally, as has been strongly recommended already, the Chinese government should consider setting up an independent panel of industrial experts to work with the project developers to gather the process related data necessary to assess the project viability against the key criteria set out above. Once these were completed and, subject to acceptable results and a financing plan being established, this would allow the Chinese government to take well informed decisions as to how such bankable demonstration projects could be taken forward.
7 RECOMMENDATIONS TO THE NDRC AND THE ASIAN DEVELOPMENT BANK
FOR AN EARLY OPPORTUNITY CCS DEMONSTRATION PROJECT
Notwithstanding the need to establish a robust selection process, and recognising
that China might wish to take forward a near term low cost demonstration opportunity
prior to such an organisational approach being established, it is worthwhile to
consider how best to proceed in the near term. Thus it is appropriate to specifically
examine proposals from large energy companies that already have CCS/EOR
experience at industrial pilot scale and have already expressed their commitment to
work with the NDRC and international funding organisations such as the Asian
Development Bank.
A potentially significant and ambitious project is immediately identified from the
shortlist given in Table 8. This is the proposed early stage coal to chemicals plant
demonstration project to be undertaken by Shenhua, with CNCPC using the captured
CO2 for EOR in an oil field in the Erdos region. The Chairmen of both these major
SOEs have signed Memoranda of Understanding with the China Petroleum and
Chemical Industry Federation. They intend to first undertake a pre-feasibility study and
pilot test during 2014/2015 and then a FEED study for a 1-2 million tonnes CO2 per
year capture and EOR project plus an assessment for a subsequent inter-provincial
CCUS network around the Erdos basin oil fields, including capturing CO2 from
coal-fired power plants as well as coal to chemical plants. This would lead to a CO2
capture and utilisation opportunity covering part of Inner Mongolia, Gansu, Ningxia,
and Shanxi Provinces, with an annual CO2 utilisation capacity of some 5 million
tonnes.
This proposed project offers a very attractive near term demonstration opportunity. It
comprises a low-cost CO2 capture option from a coal to chemicals plant, and has the
joint involvement of China’s major coal producer and its largest oil company, both of
whom have committed to work together. In the near term, the intended project offers a
very significant CO2 capture/utilisation prospect, which will represent one of the largest
planned demonstration projects in the world. There is close proximity to an oil field,
with proven amenability to CO2-EOR, which further emphasises the low cost
possibility. Equally importantly, the oil field region contains a very large number of coal
to chemical plants and coal-fired power plants, and is also distant from large human
agglomerations. As such, the subsequent intended CO2 network is a very attractive
and suitably ambitious further stage demonstration that will allow China to establish
itself at the forefront of global CCUS activities.
45
Consequently, support for this major CCUS project in the PRC by the Asian
Development Bank in collaboration with the NDRC is strongly recommended.
8 REFERENCES
ADB (2010) TA7286 PRC People’s Republic of China: carbon dioxide capture and
storage demonstration-strategic analysis and capacity building. Asian Development
Bank Final Report (October 2010)
ADB (2013) TA 8001 (PRC) People’s Republic of China: study on carbon capture and
storage in natural gas-based power plants. Asian Development Bank Final Report
(December 2013)
Bellona (2013) DOE approves Phase 2 of CCS FutureGen 2.0 project. Available from:
http://bellona.org/ccs/ccs-news-events/news/article/doe-approves-phase-ii-of-ccs-futu
regen-20-project.html (11 February 2013)
CCSA (2014) Reports and publications. Available from:
http://www.ccsassociation.org/news-and-events/reports-and-publications/
(Accessed January 2014)
Diakoulaki and others (1995) Determining objective weights in multiple criteria
problems: the critic method. Computers & Operations Research, 1995, 22(7): 763-770.
Ding M & Wu Y (2009) Current and future situation of CCS (2009)
Floger P (2013) FutureGen: A Brief History and Issues for Congress. Available from:
www.fas.org/sgp/crs/misc/R43028.pdf (3 April 2013)
GCCSI (2013) The Global Status of CCS: 2013. Available from:
http://www.globalccsinstitute.com/publications/global-status-ccs-2013 Global CCS
Institute, Australia (10 October 2013)
GCCSI (2014a) Listing of Large-scale Integrated CCS Projects. Global CCS Institute.
Available from: http://www.globalccsinstitute.com/projects/browse (24 February
2014)
GCCSI (2014b) DOE approves $1B for FutureGen 2.0. Available from:
www.globalccsinstitute.com/institute/news/doe-approves-1b-futuregen-20 (17
January 2014)
GCCSI (2014c) Projects browse. Available from:
http://www.globalccsinstitute.com/projects/browse (5 June 2014)
Gov.UK (2013a) Preferred bidders announced in UK’s £1bn CCS Competition.
Available from:
www.gov.uk/government/news/preferred-bidders-announced-in-uk-s-1bn-ccs-compet
ition Department of Energy & Climate Change (20 March 2013)
Gov.UK (2013b) Electricity Market Reform: Contracts for Difference. Available from:
https://www.gov.uk/government/publications/electricity-market-reform-contracts-for-di
fference Department of Energy & Climate Change (19 December 2013)
Gov.UK (2014) Increasing the use of low-carbon technologies. Available from:
https://www.gov.uk/government/policies/increasing-the-use-of-low-carbon-technologi
es/supporting-pages/carbon-capture-and-storage-ccs Department of Energy &
Climate Change and Department for Transport (24 January 2014)
46
Guo M & Can W (2013) Global status and related policies of technologies of carbon
capture, utilization and storage. Energy of China 2013, 35(3)
Minchener A (2011) CCS challenges and opportunities for China. CCC/190 IEA
Clean Coal Centre, London UK (December 2011)
MOST (2010) Carbon capture, utilisation and storage development in China.
Available from:
http://no.china-embassy.org/eng/kj/achivements/P020101014674327840098.pdf
Edited by the Department of Social Development and the Administrative Centre for
China’s Agenda 21, of the Ministry of Science and Technology of China (2010)
MOST (2011) Carbon capture, utilization and storage technology development in
China, Ministry of Science and Technology (2011).
MOST (2013) 12th Special planning of national science and technology development
of CCUS. Ministry of Science and Technology of P.R.C (2013)
National Audit Office (2012) Carbon capture and storage: lessons from the
competition for the first UK demonstration. Available from:
https://www.nao.org.uk/report/carbon-capture-and-storage-lessons-from-the-competit
ion-for-the-first-uk-demonstration/ (March 2012)
NDRC (2007)15th development planning of the coal industry (2007)
NDRC (2013) Notice of National Development and Reform Commission on promoting
carbon capture, utilisation and storage pilot and demonstration. NDRC Climate [2013]
Document No. 849 (May 2013)
Shen Y and others (2010) A hybrid selection model for emerging technology.
Technological Forecasting & Social Change, 2010, (77):151–166.
Stern N (2010) Stern review: The economics of climate change. Available from:
http://mudancasclimaticas.cptec.inpe.br/~rmclima/pdfs/destaques/sternreview_report
_complete.pdf (2010)
The Climate Group (2010) CCS in China: toward market transformation (2010)
USDOE (2013) NETL’S carbon capture and storage database-version 3. Available
from: http://netl.doe.gov/research/coal/carbon-storage/cs-global/database
Zhou S (2007) An integrated impact assessment and weighting methodology:
evaluation of the environmental consequences of computer display technology
substitution. Journal of Environmental Management, 2007, (83):1–24.