Tech. Day Presentation.ppt

download Tech. Day Presentation.ppt

of 114

Transcript of Tech. Day Presentation.ppt

  • 8/11/2019 Tech. Day Presentation.ppt

    1/114

    Power Sector Western Region

    Technology Day

    11th May 2009

  • 8/11/2019 Tech. Day Presentation.ppt

    2/114

    Power Sector Western Region

    TECHNOLOGICAL TOOLS

  • 8/11/2019 Tech. Day Presentation.ppt

    3/114

    Power Sector Western Region

    Use of Electrical Torque wrench for Tightening

    Boiler Structure Bolts

    At 1 x 500 MW Khaperkheda

  • 8/11/2019 Tech. Day Presentation.ppt

    4/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 4

    Cycle time reduction in tightening boiler structure bolts

    Background

    At boiler erection site thousands of BOLTED JOINTS are to be tightened

    MANUALLY using DE Spanners for snug tightening & Torque tighteningby trip torque type long handle torque spanner.

    The process of bolting arrangement consumes enormous time forachieving desired results, including uniform tightening & ensuring adesigned torque value.

    This process was identified for taking up Improvement project because ofthe following

    being repetitive in nature

    time consuming

    labour intensive

    having substantial amount of preparatory work to be done before thestarting actual process (set up time)

    high level of risk involved (some locations for actual work place areabove 80 meter above ground level & are to be performed ontemporarily erected scaffoldings

  • 8/11/2019 Tech. Day Presentation.ppt

    5/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 5

    Objective

    Reduction in time taken for complete bolting arrangementnecessary for a 500 MW Boiler erection (at Khaperkheda siteabout 40, 000 no. M24 Bolts of lengths 70160 mm are used)

    Ensuring designed tightness of bolting arrangement without

    further need of cross checking by Quality representative Safer working conditions for Operator

    Cycle time reduction in tightening boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    6/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 6

    Evaluation of alternatives

    1. Pneumatic torque wrench Benefits

    Available with leading hand tool manufacturers like Bosch, Ingersoll Rand &

    others.

    Widely used in manufacturing plants (automotive assembly lines) where high

    turnover per day is the hour of need (but here the Operator has a fixed place &jobs move to his operating area one after another).

    These wrenches are comparatively lighter.

    Drawbacks for us

    Difficulties in ensuring dry air to the wrench in all weather conditions

    Maintaining desired air pressure at a long distance through a compressor

    Requirement of supports since length of air pipes may extend up to 100 meters

    Thus making the whole arrangement very clumsy & big.

    Cycle time reduction in tightening boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    7/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 7

    Evaluation of alternatives

    2. Hydraulic torque wrench

    Benefits

    Available with leading hand tool manufacturers

    Widely used in manufacturing plants

    Drawbacks for us

    Need sophisticated hydraulic equipment (difficult to maintain)

    Require very good quality pressure hoses to feed optimumliquid pressure to the wrench limiting factors

    Practically impossible to provide such facilities at sites

    Cycle time reduction in tightening boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    8/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 8

    Evaluation of alternatives

    3. Electrically operated torque wrench

    Benefits

    Such wrenches are popular in assembly lines especially where

    job sizes are bigger & operator has to move around the job Available with leading hand tool manufacturers

    Electrical cables are much smaller, lighter & easily

    maneuverable

    Operate at 1 phase ac supply abundantly available at all areasof sites

    Cycle time reduction in tightening boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    9/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 9

    Electrically operated torque wrench(contd..)

    Results of Field Trial

    M/s Tristar Industrial Tools Pvt limited was a source located for

    making a demo at Khaperkheda

    Trial was successfully done on 10thApril 2009 at a height of about

    10 meters on Column number 19.

    Time taken to fully tighten bolted joint by ETW was about 15

    seconds as against 3 to 4 minutes by a handle type Trip Torque

    Wrench

    Substantial saving in operation time for the activity

    Saving in manual effort by Operator

    Positive assurance of Quality of bolted joint.

    Cycle time reduction in tightening boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    10/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 10

    Electric wrench for tightening boiler structure bolts

    Technische Daten DEATechnical data DEA

    PLARADGERMANY MakeTechnische Daten DEATechnical data DEA

    Our select ion

    Type DEA 12 TLX Torqu e 200 1220 NM Weigh t 6,8 kg

  • 8/11/2019 Tech. Day Presentation.ppt

    11/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 11

    Electr ic wrench tightening of boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    12/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 12

    Electr ic wrench tightening of boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    13/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 13

    Expected Benefits

    Tangible Saving in Time - On average saving of about 3 minutes per bolt

    Saving in manpower cost

    No need for Quality representative to ensure desired objectiveof proper tightness

    Additional helper to hold spanner and a trip torque wrench, notrequired.

    Intangible

    Safety of Operating Personnel (Operators & others assisting him)

    from any Accidental fall due to Slipping Slipping / Falling of the job from temporary scaffolding

    Better safety of personnel on ground from falling of long torquewrench etc.

    Cycle time reduction in tightening boiler structure bolts

  • 8/11/2019 Tech. Day Presentation.ppt

    14/114

    Power Sector Western Region

    Measurement of Face Run- out of IP & LP Rotors

    by improvised technique at site

  • 8/11/2019 Tech. Day Presentation.ppt

    15/114

  • 8/11/2019 Tech. Day Presentation.ppt

    16/11410/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 16

    Measurement of Face Run- out of I P & LP Rotors

    Normal Practice (Contd..)

    The normal method has few problems associated with it1. It is not possible to restrict axial movement of the rotor in order to avoid

    overshooting the range of the dial gauge.

    2. Area of contact being very small, it requires extreme care and controlwhile operating the EOT, lest it should cause an irreparable accident and

    lead to loss to both men and material.3. It has often been noticed that there is quite an error between the

    measurement made at shop and those made at site leading to avoidableloss of time in correspondence, summoning experts from MUs, etc.

    4. It gives the feeling of using a very primitive and un-reliable method of

    measurement.5. Overall, it is never like measuring the run-outs by anchoring the rotor on

    a lathe to take the measurements and thats exactly the cause of theerror.

  • 8/11/2019 Tech. Day Presentation.ppt

    17/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 17

    Measurement of Face Run- out of I P & LP Rotors

    Suggested New Method

    A simple device is made at site using the following material

    Shaft of 40mm x 1000mm long 1 no.

    Ball Bearings with Plummer block for above shaft 2 nos.

    Supports to anchor the Plummer blocks 2 nos.

    Cross arm 1 no.

    Dial Gauges for mounting to X-arm 2 nos.

  • 8/11/2019 Tech. Day Presentation.ppt

    18/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 18

    Measurement of Face Run- out of I P & LP Rotors

    Brg with

    Plummer

    Block

    Cross Arm

    Shaft Support provided by UnitExternal Support for

    anchoring the

    Plummer Block

    Dial

    Pointers

    Dia

    40

    Shaft

    Fixture developed and used

  • 8/11/2019 Tech. Day Presentation.ppt

    19/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 19

    Measurement of Face Run- out of I P & LP Rotors

    Advantages

    User friendly and costs only Rs.5000/- to make.

    Does not require too much of a precision in machiningthe shaft.

    Does away with repeated rotation of the rotor forevery reading.

    Reduces the risk of the rotor toppling during rotationby EOT crane.

    Compares well with the values attained at works on alathe.

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

  • 8/11/2019 Tech. Day Presentation.ppt

    20/114

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

    TATA Trombay

    This was the 1sttimethe Generator Statorhas been lifted by

    Strand Jack Methodin PS-WR. Also, thisis the 1st for 250MWStators in the whole

    of BHEL. Pictureshows Stator liftedoff the Blocks.

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

  • 8/11/2019 Tech. Day Presentation.ppt

    21/114

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

    TATA Trombay.Contd

    Stator lifting inprogress

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

  • 8/11/2019 Tech. Day Presentation.ppt

    22/114

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

    TATA Trombay.Contd

    Stator lifted andbeing moved insidethe A-Row of TG

    Building

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

  • 8/11/2019 Tech. Day Presentation.ppt

    23/114

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

    TATA Trombay.Contd

    Stator lifted abovethe bottom of TGDeck and ready to

    be moved inside forplacement.

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

  • 8/11/2019 Tech. Day Presentation.ppt

    24/114

    Stator l i f ting by Strand Jack M ethod at 1x250MW Uni t#8

    TATA Trombay.Contd

    Picture shows theStrand JackHydraulic Control

    System

    Stator l i f ting by Strand Jack Method at 1x250MW Uni t#8

  • 8/11/2019 Tech. Day Presentation.ppt

    25/114

    Stator li f ting by Strand Jack Method at 1x250MW Uni t#8

    TATA Trombay.Contd

    Picture shows statorin position

    The entire operation

    was completed in 4hrs from the start.

  • 8/11/2019 Tech. Day Presentation.ppt

    26/114

    Power Sector Western Region

    PORTABLE INDUCTION HEATING MACHINE

  • 8/11/2019 Tech. Day Presentation.ppt

    27/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 27

    I NDUCTION HEATING MACHINE

    Conventionally, we at BHEL Power Sector Sites have been using theInduction Heating Machines of EDN Bangalore make. There are certain

    disadvantages of using this equipment listed below:1. Too bulky and comes in two parts one the Induction HeatingEquipment proper and the other, the operators panel. Weighs a fewtonnes.

    2. Due to its bulk, moving the machine to different areas of work is an

    arduous task. Each shift of the machine is a 1 days activity.3. Often, it has been seen that when the machine is moved from onelocation to the other is has not been in use for a few months, the next re-start is faced with quite a few problems. The reason is not known.

    4. Getting spares on time for the equipment is a big issue. This results in

    machines with minor repairs and requiring spares quarantined.5. Overall the machine is not user-friendly

    6. Costs around Rs. 75 Lakhs per machine

  • 8/11/2019 Tech. Day Presentation.ppt

    28/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 28

    I nduction Heating Machine -.Contd

  • 8/11/2019 Tech. Day Presentation.ppt

    29/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 29

    I nduction Heating Machine -.Contd

    Alternatively, there are machines available in the market and beingused by our competitors that is a vast improvement on the EDN

    Make machine and has the following advantages:1. Very small and easily portable, thus rendering easy movementof the machines to various locations without loss of vital erectioncycle time. Requires only a 2-3 hrs for shifting and re-connecting.The entire machine is as compact as welding transformer and issingle modular. Weighs approx. 105Kgs.

    2. The connections are very simple and does not need expertise.

    3. Though imported, has a presence in the Indian market for thelast 3 years and has been used to weld pipes of 94mm thick atSipat. The machine can be used to thicknesses in excess of100mm pipes as well. The size of MS Pipe for the proposed 660MWUnit with Full Flow is 660 x 102mm.

    4. Costs only Rs.30 Lakhs. For every one machine of EDN Make,one can two of this kind.

  • 8/11/2019 Tech. Day Presentation.ppt

    30/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 30

    I nduction Heating Machine -.Contd

    C d

  • 8/11/2019 Tech. Day Presentation.ppt

    31/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 31

    I nduction Heating Machine -.Contd

    660 MW 800 MW

    System Material Size Material Size

    MS - HalfFlow

    P91 OD 508 x 80 P91 ID 370 x 66

    MSFullFlow

    P91 OD 660 x 102 P91 ID 480 x 90

    HP BypassU/S

    P91 OD 355.6 x 52 P91 OD 355.6 x 54

    HRHHalfFlow

    P91 OD 711 x 40 P91 OD 813 x 49

    HRHFull

    Flow

    P91 OD 864x48 P91 OD 1016 x 58

    LP BypassU/S & D/S

    P91 OD 711 x 40 /OD 1219 x10(SA691 2 Cr)

    P91 OD 864 x 50 /OD 965 x 35

  • 8/11/2019 Tech. Day Presentation.ppt

    32/114

    Power Sector Western Region

    Induction Heating for Opening & Tightening

    Casing fasteners of Steam Turbine

    I nduction Heating for opening & tightening

  • 8/11/2019 Tech. Day Presentation.ppt

    33/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 33

    I nduction Heating for opening & tighteningCasing of Steam Turbine

    Introduction

    Casing of steam turbines are tightened together by usingthreaded fasteners of M48 to M140 size .

    These fasteners referred commonly as studs and cap nuts have

    to be tightened firmly to withstand the high internal pressure

    and temperature.

    During the tightening process, specified value of elongation has

    to be achieved so that during working at high temperature, the

    nuts will not slacken .

    A recommended practice for tightening these fasteners is heat

    tightening.

    I nduction Heating for opening & tightening

  • 8/11/2019 Tech. Day Presentation.ppt

    34/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 34

    I nduction Heating for opening & tighteningCasing of Steam Turbine

    Commonly used devices for heating the fasteners

    Electric heaters - which include heater elements, cables, power source

    /transformer of high capacity etc.

    Gas heaters. This is relatively simpler method which uses the specially

    fabricated bolt heating devices - Gas Torches with special nozzles, and

    oxy-acetylene cylinders , compressed air supply etc.

    Main disadvantages of the above two methods

    Long time taken for the operation

    Due to the slower rate of heating, effectiveness of these methods is

    less and some other problems such as seizure of the threads also

    occur quite frequently.

    Apart from this, the arrangements required are also complex and timewasted in maintenance / repairs of the equipment in case of defects is

    quite considerable.

    I nduction Heating for opening & tightening

  • 8/11/2019 Tech. Day Presentation.ppt

    35/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 35

    I nduction Heating for opening & tighteningCasing of Steam Turbine

    Induction heating method for threaded fasteners

    Induction heating method is being used in other site applications such

    as preheating of joints for special welding of alloy steel pipe lines inthermal power stations.

    This method is very quick and effective means for heating.

    By using some modified gadgets, it was found suitable for loosening

    and tightening of the big size threaded fasteners of steam turbines,

    valves etc.

    SAS Nagpur decided to use the induction heating method for loosening

    and tightening of threaded fasteners.

    This method has resulted in saving valuable time for dismantling and

    assembly of steam turbines during overhauls. The method is simple

    and highly effective.

    With the use of induction heating method, the problem of seizure of

    threads necessitating cutting and gouging of the nuts and studs, in

    LMW design, has been minimized.

    I nduction Heating for opening & tightening

  • 8/11/2019 Tech. Day Presentation.ppt

    36/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 36

    I nduction Heating for opening & tighteningCasing of Steam Turbine

    Comparison of time required for bolt opening

    210 MW /500 MW KWU Electric/ Gas Heating Induction Heating

    HP inner casing 6 hrs 3 hrs

    IP Outer casing 10 hrs 7 hrs

    IP inner casing 14 hrs 8 hrs

    Time saved for overhauling is 3 days .

    For a 210 MW set this translates into a gain of 5.04 million units perday

    i.e approx. Rs. 2 crore per day

    For 500 mw set, 12 million units per day i.e.approx. Rs.4.8 crore perday

    LASER ALIGNMENT KIT

  • 8/11/2019 Tech. Day Presentation.ppt

    37/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 37

    LASER ALIGNMENT KIT

    OBJECTIVETo carry out various alignment works in Turbine erection

    With high precision.

    At a reduced cycle time.

    WORKS CARRIED OUT

    Catenary of pedestals

    Centering of bores of Diaphragms, Pedestals, Shaft Seals etc. Alignment of Rotors.

    CATENARY OF PEDESTALS

    Accuracy of 10 Microns achievable.

    Source equipments to be placed at extreme pedestals.

    Mobile equipment placed in intermediate pedestals.

    Laser is passed thro mobile equipment and adjustments carried

    out as per requirement.

    LASER ALIGNMENT KIT

  • 8/11/2019 Tech. Day Presentation.ppt

    38/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 38

    LASER ALIGNMENT KIT

    Centering of Bores of diaphragms,pedestals,shaft seals etc

    Source Laser device fixed in one extreme end pedestalReceiver end device fixed in other extreme pedestal.

    Special fixtures used for centering of intermediate pedestals.

    Online adjustment possible.

    Alignment of Rotors

    Can cater to Coupling Dia from 100 mm to 1200 mm.Alignment Device fixed on couplings to be aligned

    Total misalignment is indicated by just 60 degree rotation of Rotors.

    Misalignment values as well as correction required indicated in

    display.

    Salient Advantages

    Saving in Cycle time.

    Accuracy of Measurement.

    Indication of correction factors.

    LASER ALIGNMENT KIT

  • 8/11/2019 Tech. Day Presentation.ppt

    39/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 39

    LASER ALIGNMENT KIT

    CONCLUSION

    The Laser Alignment kit is a useful equipment that is State of the Art

    in Technology and can be used very effectively in Turbine activities at

    high precision and reduced cycle time, as has been proved in

    Kudankulam site.

    Hence extensive use of this equipment has to be practiced.

    ORBITAL WELDING

  • 8/11/2019 Tech. Day Presentation.ppt

    40/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 40

    ORBITAL WELDING

    PurposeTo provide leak proof joint between Tube to tube sheetin Condenser in addition to Forced expansion

    ProcessGTAW without filler wire addition

    SIGNIFIC NT SPECTS

    Material-Titanium

    Large Qty of welding

    Welding in position & at site

    Materialsupply by Russians

    TIT NIUM TUBES

    Grade : ASTM B 338 Gr2

    Tube Sheet : 35 + 5 mm thick

    Material : ASTM A516Gr 70 + ASTMB 265 Gr 1 CLAD

    ORBITAL WELDING

  • 8/11/2019 Tech. Day Presentation.ppt

    41/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 41

    ORBITAL WELDING

    Why Titanium is used?

    Provides excellent resistance to general and localized attack under

    most oxidizing, neutral and inhibited reducing conditions inaqueous environments.

    Corrosion Resistance due to stable, protective strongly adherentoxide film which forms instantly when a fresh surface is exposedto air moisture.

    This film is transparent and not deducted by visual means.

    Titanium resist corrosion by sea water to temperature as high as260 0C.

    Even exposed to sea water for many years at a depth of over a mileshows no measurable corrosion.

    Provides over 25 years of trouble free sea water service forchemical refinery de-salination and nuclear industries

    ORBITAL WELDING

  • 8/11/2019 Tech. Day Presentation.ppt

    42/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 42

    ORBITAL WELDING

    Has the ability to resist erosion by high velocity sea water

    The presence of abrasive particles such as sand has only a small

    effect on the corrosion resistance of Titanium

    Production began in the late 1950s

    Most widely used titanium is commercial pure (99.5 % Ti)

    Manufacturing Process

    Ingot slab Hot strip cold strip Slitting Forming TIG

    Welding Stress relieving Eddy Current & Ultrasonic testing

  • 8/11/2019 Tech. Day Presentation.ppt

    43/114

    Tensile, flare, flattening & reverse flattening

    Visual InspectionCleanliness, ID, OD, Surface condition, end condition

    and marking.

    Tube to tube sheet joiningContact Rolling (0 to 5 % wall thinning for a length of 10

    mm)

    Orbital WeldingFor highly reliable leak tightness

    Forced Rolling (8 to 10 % wall thinning for a length of

    25mm)

    Physical Testing

    ORBITAL WELDING

    PROCESS FLOW CHART

  • 8/11/2019 Tech. Day Presentation.ppt

    44/114

    PROCESS FLOW CHART

    Front / Rear end tube sheet cleaningwire

    brush mounted in portable drilling machine

    followed by acetone

    Visual inspection

    Titanium tube insertion

    Initial cleaning before contact rolling

    Initial contact rolling up to 10mm

    Sh 1 of 3

    PROCESS FLOW CHART CONTD

  • 8/11/2019 Tech. Day Presentation.ppt

    45/114

    End facing of tube & tube sheet up to 0.05 mm

    Welding

    Visual inspection

    Rectification of repair work

    Final expansion 8 to 10 % by lubricating

    SAE 40 oil

    Excess length trimming in the rear side

    PROCESS FLOW CHART CONTDSh 2 of 3

    PROCESS FLOW CHART CONTD Sh 3 f 3

  • 8/11/2019 Tech. Day Presentation.ppt

    46/114

    Tube tightness test by MAUS Gun G-150

    Dye Penetrant testing

    Final cleaning by acetone

    PROCESS FLOW CHART CONTD Sh 3 of 3

    TUBE SPECIFICATION

  • 8/11/2019 Tech. Day Presentation.ppt

    47/114

    TUBESPECIFICATION

    TUBE INSERTION AT KODAMKULAM

  • 8/11/2019 Tech. Day Presentation.ppt

    48/114

    TUBE INSERTION AT KODAMKULAM

  • 8/11/2019 Tech. Day Presentation.ppt

    49/114

    FRONIUS MODEL - FPA 2000 (AUSTRIAN MAKE)

    PROGR M BLE ORBIT L WELDING M CHINES

    AFTER TUBE INSERTION

  • 8/11/2019 Tech. Day Presentation.ppt

    50/114

    AFTERTUBE I NSERTION

    TUBE SHEET PROTECTION

  • 8/11/2019 Tech. Day Presentation.ppt

    51/114

    TUBESHEET PROTECTION

    Welding parameters for FRONIUS MODEL - FPA 2000

  • 8/11/2019 Tech. Day Presentation.ppt

    52/114

    Welding parameters for FRONIUS MODEL - FPA 2000

    Process : GTAW (Automatic )

    No of weld passes 1Argon Gas flow rate 4 to 6 ltr /min

    Pre Gas time T10 30 SecPost Gas time T11 30 SecPre Fusion current I21 90A

    Pre fusion current time T21 0.1Sec

    Pulse current I22 90ATime of pulse current T22 100msec

    USE OF HYDRAUL IC OPERATED TORQUE CONTROLLED BOLT

  • 8/11/2019 Tech. Day Presentation.ppt

    53/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 53

    TIGHTNING KIT

    OBJECTIVE

    To adopt a safe State of the Art methodology in bolt

    stretching of coupling bolts of TG Couplings.

    GENERAL COUPLINNGS IN TG

    HP Tubine to IP Turbine

    IP Turbine to LP Turbine

    LP Turbine to Generator Shaft

    REQUIREMENT

    The coupling bolts which are like pins, having a clearance of 0.03mm

    diametrically, have to be stretched up to 0.55 mm ,depending on the bolt

    dimensions to ensure uniform tightening .

    USE OF HYDRAUL IC OPERATED TORQUE CONTROLLED BOLT

    G G

  • 8/11/2019 Tech. Day Presentation.ppt

    54/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 54

    TIGHTNING KIT

    Prevalent practice

    Nut of the Coupling bolt is tightened by a box spannerLeverage applied on end of the spanner by EOT crane through slings.

    Differential expansion monitored by Dial Gauge positioned at bolt ends.

    Sources of Error

    Dial gauge at the nut end has to be fitted with a long extensionrod,which may lead to error in reading.

    Disturbances in the nut also can lead to erratic readings.

    Safety element

    The whole stretching operation dependent on skill of the Fitter and

    EOT Crane operator

    Fine movements in EOT Crane not possible

    Danger of slipping/shearing always present.

    USE OF HYDRAUL IC OPERATED TORQUE CONTROLLED BOLT

    TIGHTNING KIT

  • 8/11/2019 Tech. Day Presentation.ppt

    55/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 55

    TIGHTNING KIT

    RECOMMENDATION

    Hydraulically operated Torque controlled Bolt tightening kit can be used.

    Manufacturing Unit to specify Torque tightening values of individualcouplings.

    ADVANTAGES

    No error in reading.

    Uniformity in bolt stretchingSafe for the working personnel

    Safe for the equipment

  • 8/11/2019 Tech. Day Presentation.ppt

    56/114

    Power Sector Western Region

    IMPROVED PROCESSES

    ALL -VOLATI LE & OXYGENATED TREATMENT

  • 8/11/2019 Tech. Day Presentation.ppt

    57/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 57

    ALL VOLATI LE & OXYGENATED TREATMENT

    `

    AVT :The basic idea of AVT is to minimize corrosion &erosion corrosion in the low temperature region by

    using deaerated high purity water with elevated PH.The actual PH range depend on cycle metallurgy

    In absence of Oxygen, the primary reaction of iron

    dissolution is inhibited by increasing PH.

    The solubility of ferrous hydrazine rises with increasein temperature and then decreases with steep drop to

    the solubility of magnetite between 200250 0C. This

    results in undesirable magnetite deposit in this

    temperature range.

    ALL -VOLATI LE & OXYGENATED TREATMENT

  • 8/11/2019 Tech. Day Presentation.ppt

    58/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 58

    `

    To maintain the solubility of ferrous hydroxide in feedwater below or equal to that of magnetite at 250 0C and

    to exclude the possibility of over saturation, a minimumPH of 9.6 should be maintained. A PH of 10 would beeven better.

    Hydrazine acts both as a O2scavenger & corrosioninhibitor by formation of ferrous oxide hydrate.

    OXYGENATED TREATMENT :This process uses oxygenated high purity water tominimize corrosion & erosion corrosion in the feedwater train.

    Oxygen, Hydrazine peroxide, air are used as

    oxidants

    ALL -VOLATI LE & OXYGENATED TREATMENT

  • 8/11/2019 Tech. Day Presentation.ppt

    59/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 59

    `

    Oxygen level should be 30-50 ppb for drum units and 30-

    150 ppb for Once Through Units.

    Ph level shall be 9-9.6 at Drum units and 8-8.5 for OnceThrough Units

    In oxygenated system, p rotective layer consists of

    Magnetite(FE3O4) and Hematite(FE2O3) layers

    For temperature ranges upto 250 0C the addition ofoxygen allows the formation of oxide protective layer which

    have a very low corrosion product release rate in the

    following water

    ALL -VOLATI LE & OXYGENATED TREATMENT

  • 8/11/2019 Tech. Day Presentation.ppt

    60/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 60

    ALL VOLATILE TREATMENT (AVT)

    Ferrous or mixed feedwater train

    Cation conductivity 0.2-0.4 S/cm pH 8.89.6 (Dependent on feedwater metallurgy)

    Fe 10ppb N2H4 ( >3x02)

    O2 30 ppb )NH3 ( 20 -70 ppb )

    OXYGENATED TREATMENT (OT)All ferrous feedwater trainCation conductivity < 0. 15 S /cmpH 8.08.5

    HP

    HeatersBoiler BFP DA LP Heaters CP CEP CondenserHP

    HeatersBFP

    LP BYPASS SYSTEM

  • 8/11/2019 Tech. Day Presentation.ppt

    61/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 61

    LP BYPASS SYSTEM

    LP BYPASS SYSTEM

    MODIFICATION CARRIED OUT IN OLD LPBPSYSTEM

    In case of Turbine trip, direct command will beissued to LP Bypass valves for opening upto 45%for 3 secs.

    It is expected that within this 3 secs., the sprayvalves will open and the spray water pressure will beachieved.

    However, if the spray water pressure has not

    reached a value of 5 kg/cm2 within 3.5 secs., or thecondenser wall temperature has become more than90 0C, the LP Bypass trip command will be issued

    LP BYPASS SYSTEM

  • 8/11/2019 Tech. Day Presentation.ppt

    62/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 62

    SS S S

    The sensing of pressure is done by installation ofadditional pressure transmitters at the downstream

    of spray water valves The modification was implemented first in

    Vindhyachal U#10 and two occasions since themodification, the turbine has tripped and LP Bypassvalves opened within 5 secs thereby saving theboiler trip

    LBPB SYSTEM FOR NEW 250 MW SETS

    To address this issue, now BHEL, Hwr has gone for

    a new High Pressure LP Bypass system which hasmuch better response time. Such system have beensupplied at 1 x 250 MW Parli, 1 x 250 MW Paras, 4 x250 MW JPL and 2 x 250 MW Bhilai sites.

    LP BYPASS SYSTEM

  • 8/11/2019 Tech. Day Presentation.ppt

    63/114

    10/10/2014Exploring Heights ..................... Setting Standards .................... Marching Towards ExcellencePower Sector Western Region 63

    The logic provided for the operation of the LBBypass valves are similar to that of the older low

    pressure LPBP valves. However, the following arethe new features of High Pressure LPBP valves

    The LPBP valves on sensing increase HRHPressure, automatically opens without looking for

    adequate water pressure

    For the water injection spray control valves, twocurves have been implemented, one for control andthe other for protection based on down stream

    pressure of LPBP valves.

    LP BYPASS SYSTEM

  • 8/11/2019 Tech. Day Presentation.ppt

    64/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 64

    SS S S

    If the actual water injection flow is less than flowcorresponding the protection flow, then the LPBP

    valves closes on water injection flow protection.

    The following problems have been noticed in the newsystem

    As per the water injection curve, a continuous waterflow is required to the system which is unnecessaryand wasteful.

    The spray water flow element and flow transmitter is

    showing 0 reading upto 50% of spray control valveopening.

    The problem has been taken up with BHEL, Haridwar

    LP BYPASS SYSTEM

  • 8/11/2019 Tech. Day Presentation.ppt

    65/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 65

    Conclusions :

    The new High Pressure system is working satisfactorilyand therefore, the boiler tripping due to reheaterprotection in the new system has been avoided in therecently commissioned units.

    By implementing the modification in the old units asdone at NTPC Vindhyachal U#9, 10, the problem of theold units can also be resolved.

  • 8/11/2019 Tech. Day Presentation.ppt

    66/114

    Power Sector Western Region

    BEST PRACTICES

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    67/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 67

    CARD BOARD BLASTING OF LUB OIL AND CONTROL

    OIL LINES OF STEAM TURBINESGENERAL PRACTICE

    Only mechanical cleaning is done before start of oil flushing forlub oil and control oil system of steam turbines.

    BEST PRACTICE

    Exhaustive card board blasting along with mechanical cleaningis carried out for all the control and lub oil system before start ofoil flushing.

    This practice is being followed in almost all the sites now.

    ADVANTAGES

    Effective cleaning and time reduction.

    ,

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    68/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 68

    USE OF PORTABLE CENTRIFUGE DURING LUB OIL

    FLUSHING OF ROTARY MACHINESGENERAL PRACTICE

    Generally oil flushing were carried out at ambient temperaturewithout any centrifuging arrangement for rotary machines such

    as BFP, ID Fans, FD Fans and Mills.BEST PRACTICE

    Oil flushing is carried out with portable oil centrifuge having in-built heating arrangement .

    ADVANTAGES

    Effective cleaning and time cycle reduction.

    ,

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    69/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 69

    CHEMICAL CLEANING OF PRE BOILER SYSTEM WITH

    CEPGENERAL PRACTICE

    Carried out by using temporary pumps, tanks and piping alongwith boiler acid cleaning setup

    BEST PRACTICE

    Existing CEP and Hotwell are used for the purpose of circulationin the entire system

    ADVANTAGE

    Effective cleaning of the entire system with minimum number oftemporary loops

    Cost and time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    70/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 70

    USE OF DEAERATOR AS MIXING TANK FOR PRE-

    BOILER FLUSHING

    GENERAL PRACTICE

    Mixing tanks and associated pipings are arranged for carrying

    out the pre boiler flushing activities.

    BEST PRACTICE

    For industrial sets, Deaerator itself is used as mixing tank for

    carrying out chemical cleaning of pre-Boiler system.

    This results in cost and time cycle reduction.

    ,

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    71/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 71

    CHEMICAL CLEANING OF BOILER (WW, SH) AND MSLINES IN INDUSTRIAL PROJECTS

    GENERAL PRACTICE

    Stages are : Alkali boilout, Acid cleaning and passivation

    BEST PRACTICE

    Alkali flushing, Citric acid cleaning, passivation of the entiresystem

    ADVANTAGE

    Chemical cleaning activities can be completed even before Boilerlight up

    Since both SH and MS lines are acid cleaned & steam blowingcycle is considerably reduced

    Cost and time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    72/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 72

    CHEMICAL CLEANING OF HSD AND NAPHTHA LINES INCCPP

    GENERAL PRACTICE

    Cleaned by card board blasting

    BEST PRACTICE

    Citric acid cleaning with passivation

    ADVANTAGE

    Where the length of HSD and Naphtha lines is more than 500meters cardboard blasting shall not be very effective. Hence,

    citric acid cleaning is a most effective way of ensuringcleanliness of the entire piping

    Time cycle reduction and trouble free operation

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    73/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 73

    USE OF THERMIC FLUID HEATER FOR COMMISSIONINGACTIVITIES IN GREEN FIELD PROJECTS

    GENERAL PRACTICE

    Auxiliary boiler is used for generation of steam for pre-

    commissioning activities like flushing of Boiler Feed Line,Condensate Lines, Drip Lines etc.

    BEST PRACTICE

    Thermic fluid heater is used in green field projects in place ofauxiliary boiler for carrying out chemical cleaning activities.

    This results in cost and time saving.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    74/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 74

    ACID CLEANING WITH EDTA

    GENERAL PRACTICE

    Generally HCL is used for acid cleaning of main boiler.

    BEST PRACTICE

    HCL is replaced by EDTA for all green field projects especially,where auxiliary steam is not available.

    This is safe, environment friendly and reduces time cycle.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    75/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 75

    PROVISION OF ADDITIONAL INTERSTAGE VALVES FOR

    STEAM BLOWINGGENERAL PRACTICE

    Interstage valves are not used during steam blowing operationsresulting in three to four days shut down for start of subsequent

    steam blowing operations.

    BEST PRACTICE

    Additional temporary valves are used at Main Steam HP Bypass

    lines, CRH Lines during steam blowing operations.

    This has resulted in cycle time reduction.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    76/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 76

    CONTINUOUS STEAM BLOWING IN CCPP

    GENERAL PRACTICE

    Puffing method is used due to limitation of fuel firing system

    BEST PRACTICE

    Continuous blowing method (30 minutes) is used in stages

    ADVANTAGE

    Effective cleaning and time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    77/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 77

    HIGHER STEAM BLOWING PARAMETERS

    GENERAL PRACTICE

    Steam blowing is carried out at 40 Kg / sq cm and 300350 deg C

    BEST PRACTICE

    Steam blowing carried out at 50 Kg / sqcm and 370400 deg C

    ADVANTAGE

    Effective cleaning due to higher disturbance factor at elevated

    parameters Time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    78/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 78

    USE OF FRESH LUB OIL BOTH FOR FLUSHING AND REUSE

    IN ALL INDUSTRIAL SETS

    GENERAL PRACTICE

    Flushing oil is used for oil flushing operation, fresh oil is used for

    normal operationBEST PRACTICE

    After cleaning of entire lub oil system by cardboard blasting freshoil is used both for flushing and normal use

    ADVANTAGE

    Cost and time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    79/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 79

    AIR LEAK TEST OF LUB OIL, CONTROL OIL, AND

    CONTROL FLUID SYSTEM

    GENERAL PRACTICE

    No separate test conducted before start of flushing resulting inleakage of oil / fluids

    BEST PRACTICE

    Entire system is pressure tested with compressed air at 5 to 6Kg/sqcm before start of flushing operation

    ADVANTAGELeakage of oil and control fluid is minimised

    Cost and time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    80/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 80

    GENERATOR SEAL OIL FLUSHING

    GENERAL PRACTICE

    Seal oil flushing is done for the site erected pipes upto the inletnozzle in the end shield

    BEST PRACTICE

    Pre-fabricated pipes from the end shield upto seal ring inlet arealso included in the final stage of flushing.

    ADVANTAGEAvoids damage to Generator seal from the entrapped foreignmaterial.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    81/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 81

    HYDRAULIC TEST OF LUB OIL, CONTROL OIL AND

    SEAL OIL LINES

    GENERAL PRACTICE

    Jacking oil pumps were used for carrying out hydraulic test of luboil, control oil and seal oil line after flushing.

    BEST PRACTICE

    AC seal oil pimp is used for the purpose of hydraulic test of theabove system.

    ADVANTAGEAvoids damage to Jacking oil pumps.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    82/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 82

    CONDENSER MASS FLUSHING

    GENERAL PRACTICE

    Cleaning of condenser is normally carried out during steamdumping operation

    BEST PRACTICE

    Condenser tubes are thoroughly flushed through high pressurejets (fire fighting water) before commissioning of CEP

    ADVANTAGE

    Duration of steam dumping operation reduced

    Cost and time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    83/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 83

    CLEANING OF VACUUM PUMP SUCTION LINES

    GENERAL PRACTICE

    No structured cleaning is envisaged except draining the systemthrough drain valves (NB50) during initial commissioning ofvacuum pumps

    BEST PRACTICE

    Vacuum pumps suction lines are throughly cleaned throughcardboard blasting before commissioning of vacuum pumps

    ADVANTAGE

    Smooth trouble free operation

    Damage of vacuum pumps due to entry of foreign material isavoided

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    84/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 84

    OLTC COMMISSIONING

    GENERAL PRACTICE

    OLTC is commissioned normally after attaining continuousoperation of unit, i.e., CW system has been put into service forprolonged period

    BEST PRACTICE

    OLTC is commissioned either

    Immediately after running of CW pump or

    Before conductance of PG test after thorough cleaning ofcondenser tubes

    ADVANTAGE

    Collection efficiency of balls increase

    Trouble free condenser operation

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    85/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 85

    SELF CONTAINED BEARING COOLING ARRANGEMENTAT EPC PROJECT

    GENERAL PRACTICE

    Lub oil coolers for ID, FD and PA Fans are kept charged throughthe bearing cooling water system

    BEST PRACTICE

    In EPC project where due to certain circumstances there is adelay in commissioning of Cooling Water system a separate selfcontained cooling arrangement (Sintex tank, pumps and suitablehoses) to facilitate initial commissioning

    ADVANTAGE

    Trial operation of all major boiler auxiliaries can be completed bythis method leading to time cycle reduction

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    86/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 86

    PRE ERECTION CHECKING OF BUS-DUCTS

    General Practice

    Bus-ducts are cleaned and erected

    Commissioning jobs taken up later

    Best Practice

    While at ground, check tightness of all electrical connections ofheaters, thermostats etc

    Check heaters healthiness and adjust thermostat tripping pointseasily now

    Check drain pad holes before lifting so that any corrections, if

    required can now be done easily

    Trial assembly of Bus-duct structure on ground before erection

    Avoids difficulty in commissioning / troubleshooting

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    87/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 87

    TURBINE X-CRITERIA

    General Practice

    In X1 criteria for turbine rolling, main steam inlet temperature toturbine has been used for criteria calculation. During any boiler trip

    and restart, X1 criteria gets fulfilled even though boiler outlettemperature is less. This leads to cold steam entering the turbine.

    .

    .Best Practice

    Additional criteria X11 introduced using Temperature before HPbypass.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    88/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 88

    ADDITIONAL TRIPPING DURING ATT

    General Practice

    Tripping criteria during conductance of ATT does not include manyvital trip inputs

    .

    .Best Practice

    Conditions like MFT, Turbine Bearing temperature VH, axial shift VH,vacuum low, cold gas temp trip, seal oil temp trip etc are added

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    89/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 89

    COMMISSIONING OF ATRS, ATT & AUTOSYNCHRONIZER

    General Practice

    Normally, ATRS, ATT and Auto-synchroniser are getting commissioned aspending points and not as a part of normal plant commissioning.

    So after the pending point is cleared, customer is normally not using the

    system.

    Best Practice

    We are putting efforts for commissioning these system in the first rolling

    synchronisation itself.

    Recently at Bhilai and Tata Trombay, ATRS and Auto-synchroniser have

    been commissioned during first few start-ups.

    At Tata Trombay, ATT is also commissioned.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    90/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 90

    DC EOP AND SOP LATCH RELAY

    General Practice

    Lub Oil pressure low switch starts DC EOP through max systemSLC latch relay contract..

    .

    Best Practice

    SLC latch relay contract in DC EOP and SOP cabinet looped so thatlub oil pressure low switch contact starts DC EOP and SOP directly,

    bypassing MAX system SLC ON. This safeguards machine in the event of AC as well as failure of max

    system

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    91/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 91

    AUTOSYNCHRONIZATION

    General Practice

    As per circuit configuration, auto synchronizer after fulfilling its setcondition directly closes the Generator circuit breaker..

    .Best Practice

    Additional contact of check synchronization relay wired up in autosynchronization circuit. Here autosynchroniser setting arecoordinated with setting of check synchronizing relay so thatautosynchroniser and check synchronization relay operates at thesame time.

    This helps in safeguarding the machine during malfunctioning ofautosynchronizer.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    92/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 92

    AUTOSYNCHRONIZER TESTING

    General Practice

    As per normal practice, autosynchronizer is tested and its outputcommand is verified within the panel terminals..

    Best Practice

    Autosynchronizer is tested in cold condition with supply of PTvoltages through injection kit and actual Generator breaker closing(ensuring that isolators are open)

    This helps in optimization of autosynchronizer setting morecorrectly and also total circuit gets checked.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    93/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 93

    USE OF MULTIPLE FILTRATION MACHINES FORTRANSFORMER DRYOUT

    General Practice

    One Oil filtering machine (about 6 KL capacity) engaged for dryout

    Best Practice More than one such machine put in parallel operation to optimally

    utilise transformer drain header flow capacity

    Advantage

    Cycle time reduced around 50%

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    94/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 94

    TURBINE BEARING METAL TEMPERATURE CHECKING

    General Practice

    As per normal practice, cabling from bearing metal temperature JBto control room/Cold Junction Compensation(CJC) JB are checked

    after installation of thermocouple in bearings...Best Practice

    Before installation of thermocouples in bearing, signal upto DCSchecked by heating the thermocouple tag wise.

    This ensures correctness of connection, readings and alsoambiguity of polarity change is avoided.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    95/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 95

    DAVR DUMMY LOAD TESTING

    General Practice

    As per normal practice, the AVR/DAVR dummy load testing iscarried out at site with the help of 500W lamp or any available

    resistive load...Best Practice

    Dummy load testing is carried out with same type of resistive load

    which is identical in ratio to that of factory testing. With this type oftesting, exact and identical readings with factory can be ensured.

    Customer as well as commissioning engineer gets betterconfidence on DAVR working.

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    96/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 96

    PAINTING OF TRANSFORMERS AND BUS-DUCTS

    General Practice

    Painting works for busducts and transformers are attempted atvery late stages

    Becomes difficult because of shutdown requirement and thusopportunity may not be there

    Best Practice

    At least Station transformer and its busducts may be paintedimmediately after erection completion (before first charging).This transformer hardly goes into shutdown later

    Better to paint the other transformers and busducts as well assoon as possible before charging

    However, customer opinion / permission may be required sincethey may insist on painting only after all works are completed

    Best Practices, TSX PSWR

  • 8/11/2019 Tech. Day Presentation.ppt

    97/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 97

    SEQUENCE STARTUP OF HT DRIVES

    General Practice

    All HT drives are generally started individually during firstcommissioning of the drives

    This lead to a pending point as we do not get suitable opportunity tocommission the HT drives in sequence mode

    Best Practice

    All the HT drives to be started in sequence during first startup of the

    any HT drive

  • 8/11/2019 Tech. Day Presentation.ppt

    98/114

    Introduction

  • 8/11/2019 Tech. Day Presentation.ppt

    99/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 99

    Implementation of Best Practices during Overhauling

    of T.G. has resulted into the following -

    Overhauling cost reduction.

    Reduce overhauling periods.

    Improvement in quality.

    Introduce latest technologies.

    Improve customer satisfaction

    Implementation of Best practices

  • 8/11/2019 Tech. Day Presentation.ppt

    100/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 100

    Use of latest technology like induction heating for dismantling andassembly of turbine.

    Unit de-synchronization at 480 C of HP shaft temp by decreasingthe load before shut down..

    Turbine oil pump stop at 125C (HPS temp).

    Barring gear stop at 125C (HPS temp).

    To initiate overhauling activities as soon as machine comes tobarring gear.

    Decoupling of Generator rotor from turbine rotor and put backturbine rotor in barring.

    Start dismantling of generator and O/H activities thereafter.

    Review by Site and follow-up from HQ

  • 8/11/2019 Tech. Day Presentation.ppt

    101/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 101

    Site reviews all activities minutely

    Time taking processes, idle times between activities, delay in

    arranging spares and mobilization of experts from units etc

    are identified well in advance.

    HQ also involves in reviewing processes and all important

    issues and HQ inputs are duly incorporated on activity

    planning at site.

    Reduction in overhauling duration to the target schedule is

    attributed to meticulously planning and follow-up of critical

    activities, which is accomplished in a shortest duration.

    Strategic Planning

  • 8/11/2019 Tech. Day Presentation.ppt

    102/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 102

    List out the History of past problems

    Pre-overhaul survey record.

    Analyze Present running behavior.

    Input from MOUs and utilities.

    Timely arrange experts service from MOUs

    Milestone based review.

    Mobilization of resources 3 days before start of Overhaul.

    Scheduling of sequential & parallel activities

    Identification of idle time & to avoid them by detailed planning inadvance

    All the anticipated spares required for completion of theoverhauling work arranged at T.G. Floor before start of the work.

    Generator work starts within 36 hrs of De-synchronization

  • 8/11/2019 Tech. Day Presentation.ppt

    103/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 103

    0000 hrs : De-synchronization (HP shaft temp at 480 Deg.C)

    17.5 hrs : Barring gear stop (HP shaft temp at 400 Deg C)

    17.5 hrs. to 20.5 hrs:

    AOP stop

    Lub o i l to b rg. 5,6,7 blanked & brg . 4 min im ized

    LP-Gen coupl ing decoup l ing

    Hand barr ing w i l l con t inue dur ing th is per iod

    20.5 hrs : B/G re-started

    With this practice Generator rotor thread out work startswithin 36 hrs of de-synchronization.

    Procedure for decoupl ing of LP-Generator in hot conditions

  • 8/11/2019 Tech. Day Presentation.ppt

    104/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 104

    Turbine is on Turning Gear. JOP in service, AOP in service.

    Loosening of pedestal cover bolts, removal of Vibration probes.

    Close turning gear valve to reduce the speed. Simultaneously

    loosen and remove pedestal cover bolts.

    When Turbine speed becomes zero. Stop AOP while JOP is

    continuously kept in service. Continue Hand Barring.

    Remove pedestal 4 cover. Close Lubricating oil throttle valve to

    the minimum possible.

    Simultaneously blank lub oil supply to bearing 5,6 and 7 by putting

    gasket in lub oil supply line. (parallel, by 3 gangs). Keep watch on

    bearing 1,2 and 3 metal temperature and simultaneously do hand

    barring.

    Procedure for decoupl ing of LP-Generator in hot conditions

  • 8/11/2019 Tech. Day Presentation.ppt

    105/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 105

    Put tin sheet/polythene to cover on bearing 4. Start EOP andcontinue hand Barring.

    Loosen LP-Generator coupling bolts and decouple LP-generatorby continuing hand barring.

    Shift generator rotor away from turbine Stop EOP and Adjust brg. 4lubricating oil throttle valve to normal. Put pedestal cover backand start EOP & barring gear.

    Dismantling & prepare for rotor thread out.

    At the time of rotor thread out, stop turning gear again and stopEOP. Remove pedestal 4 cover.

    After thread out put pedestal 4 cover back. Turbine on Barring

    gear with AOP in service till HP shaft temp comes to 125 deg C .

    Note: Jacking oil pump is throughout kept in service.

    PSWRs Best records on TG overhauls

  • 8/11/2019 Tech. Day Presentation.ppt

    106/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 106

    Overhauling of IP-LP Turbine & Generator including LP Turbine

    blades MPI have been carried out in record lowest time of 8

    days barring to barring. (13 days Bar to Bar) on year 2007 at250MW U#2 Dahanu TPS.

    Overhauling of LP Turbine & Generator have been carried out in

    record lowest time of 9 days barring to barring. (15 days Bar to

    Bar) on year 2005 at 250MW U#2 Dahanu TPS . This was achieved

    as an exceptional case to avoid power problem in Mumbai.

    Overhauling of HP- LP Turbine & Generator including HP rotor

    replacement & HP/IP coupling hole reaming, LP free standing

    blades MPI & NFT along with bearings 1,2 & 4 replacement have

    been carried out in record lowest time of 13 days baring tobarring. (18 days Bar to Bar) on year 2006 at 250MW U#1 Dahanu

    TPS.

    PSWRs Best records on TG overhauls

  • 8/11/2019 Tech. Day Presentation.ppt

    107/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 107

    Overhauling of IP-LP Turbine & Generator including LP

    Turbine blades MPI & NFT have been carried out in record

    lowest time of 12 days barring to barring. (17 days Bar to Bar)in year 2008 at 250MW U#2 Dahanu TPS.

    Unit-3 HP Module overhauled in 14 days barring to barring

    (19days bar to bar) in year 2006 at 200MW U-3 KSTPS NTPC

    Korba.

    Capital Overhauling of HP-IP-LP Turbine & Generator

    including HP rotor replacement & HP/IP coupling hole reaming,

    LP free standing blades MPI & NFT have been carried out in

    record lowest time of 35 days barring to barring in year 2008 at500MW U#8 NTPC VSTPS Vindhyachal .

    Schedule comparison

  • 8/11/2019 Tech. Day Presentation.ppt

    108/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 108

    Sl.

    No Capacity (MW)

    Capital Overhauling TG SET (Barring to Barring)

    Previous Best Record Present Record

    1 500

    (All three module +Gen)

    36 Days Unit-6, NTPC,KSTPSKorba on year 1996

    35 days Unit-, NTPC, VSTPSVindhyachal on year 2008

    2 250(HP-LP&GEN)

    30 Days Unit-U-2 REL, DahanuTPS on year 2002

    13 days Unit-U-2 REL, DahanuTPS on year 2006

    3 250

    (IP-LP&GEN)

    - 8 days Unit-U-2 REL, DahanuTPS on year 2007

    4 200/210

    (HP Module)

    28 Days Unit-2 NTPC KSTPSon year 2001

    15 Days Unit-3 NTPC KSTPSon year 2006

    Conclusion

  • 8/11/2019 Tech. Day Presentation.ppt

    109/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 109

    A benchmark on record minimum duration in KWU design TG setoverhaul could be achieved.

    It was the determination, commitment, monitoring and follow-up ofassociated activities that ascertained to achieve a challengingtarget.

    Working out activities well in advance with subcontractor

    agencies/ partners and round the clock execution of job with newstrategies helped to meet schedule deadlines.

    Work can be started as soon as machine comes to Barring gear.

    Cooling Down period can be saved relatively by 4 days during the

    Generator overhauling.

  • 8/11/2019 Tech. Day Presentation.ppt

    110/114

    Power Sector Western Region

    IMPROVED SITE FACILITIES

    Porta Cabins - to overcome delay in site mobil isation

  • 8/11/2019 Tech. Day Presentation.ppt

    111/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 11110/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 111

    Award of Enabling works and its construction takes considerable

    time, after receipt of confirm order. This delays posting of site

    staff and material management including posting of ConstructionManager.

    PSWR has decided to procure Porta Cabins with all amenities as

    replacement of Conventional Site office sheds.

    This will be provided in all new sites like Satpura, Mauda,Chandrapur, Raigarh, Vindhyachal, Bela Ideal Energy including

    all forthcoming sites.

    NIT has been floated and tender is likely to be finalized by end

    April 2009.

  • 8/11/2019 Tech. Day Presentation.ppt

    112/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 112

    Porta Cabins - to overcome delay in site mobil isation

  • 8/11/2019 Tech. Day Presentation.ppt

    113/114

    10/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 11310/10/2014

    Exploring Heights ..................... Setting Standards .................... Marching Towards Excellence

    Power Sector Western Region 113

    Advantages of Porta Cabins

    1. Quick mobilization

    2. Quick realization of mobilization advance from customer

    3. Quick demobilization

    4. Flexibility in use & can be installed as per the site condition

    5. Environmental friendly due to cleanness & easy maintenance

    6. Provide better facility to site staff

    7. Light weight (Easy in handling and transportation)

    8. Aesthetic look.

    9. Durable and Termite proof

    10. Seismic-resistant11. Economical in long term because of repetition

    12. Thermal Insulation

  • 8/11/2019 Tech. Day Presentation.ppt

    114/114