Team Productivity and Quality -Understanding the Quintuple Constraint
Jesse Freesewww.fissure.com
for SimProject®
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
www.fissure.com952-882-0800
Agenda
The Five Key Project Management Variables
The Relationship Between the Five Key Variables- What does it look like?
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
- What does it look like?
Using the Relationship on Projects
2
Three Key Project ManagementVariables
-The Triple Constraint
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
Scope
TimeCost
3
Are they Constraints or arethey Variables?
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-164
Scope
TimeCost
• What will it take to make this project happen?or What will win the contract?
• How much money and/or schedule does thecustomer or sponsor have?
• What is the competitor’s estimate? or At what
• What will it take to make this project happen?or What will win the contract?
• How much money and/or schedule does thecustomer or sponsor have?
• What is the competitor’s estimate? or At what
Top Down Constraint Estimation
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
• What is the competitor’s estimate? or At whatestimate will the sponsor look at other options?
• What will management tolerate?• What will the market allow?
• What is the competitor’s estimate? or At whatestimate will the sponsor look at other options?
• What will management tolerate?• What will the market allow?
5
Two More Key ProjectManagement Variables
-The Quintuple Constraint
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
Scope
Quality
Productivityof your team
6
If you want to improveproductivity, what area few things you mightfocus on?
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-167
What is the relationshipbetween the variables? Ifyou change one, what is theimpact on the others?
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-168
As a team identify what the relationship looks like for the following:
Effort Schedule
Team Exercise
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
Size Size
Schedule
Quality
Schedule
Effort
9
Size is constant Size is constant
Let’s look at onemajor driver of theserelationships.
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
relationships.
10
Brook’s Law
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-1611
Ramp Up Time and Limited Divisibility
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-1612
Frederick Brooks -The Mythical Man-Month
• IBM 360 System Development
• Lots of data
• About projects that require communication
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
• About projects that require communication
Addison-Wesley Publishing Company, 1975, 1995
13
Understanding Brook’s LawThe Relationship Between # of People and Productivity
Number of peopleon the project:
Number of 2-way communicationchannels on the project:
1
3
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
3
6
10
What is thetrend here?
14
Five Key Project Variables -Relationship
Quality
Cost Time Cost Time
Quality
BudgetCut
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
Quality& People
Scope
All five variables are balanced.
Scope
Quality& People
Scope and time areadjusted to reflect and stayin balance with the reducedcost.
15
Constraint andEstimate Analysis
Team estimate
Parametric estimate
Difference in cost and time is your “Estimation RISK”
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
Cost
Time
Parametric estimate
Expert estimate
Top down constraint
16
Trade-off Summary
Minimum ScheduleLengthen ScheduleShorten Schedule*
Build Up FastBuild Up Slow
MinimumLongerShorter
ShorterLonger
MaximumDownUp
UpDown
MinimumUpDown
DownUp
Schedule Effort/Cost Quality
Effect
This looksimportant
Pattern
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
Reduce FunctionalityAdd Functionality
Improve Productivity#Productivity Falls
* The schedule cannot be shorter than the minimum schedule. Only if westart the planning process with a schedule longer than the minimum canwe consider shortening it.
# Improving productivity generally takes place on a longer time scale thanproject duration, except large projects that run on for years.
ShorterLonger
ShorterLonger
DownUp
DownUp
UpDown
UpDown
17
Conclusion
• There are five key project variables –hopefully they are not ALL constraints
• The more people you have working together,the lower their individual productivity (andquality)
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16
quality)
• If the five key variables are not in balance,something has to give
18
© Fissure Minneapolis, MN 952-882-0800 www.Fissure.com
5 Variables Presentation 9-16