Team Mate Conceptual Design Review

8
{ { Team Mate Team Mate Conceptual Design Review Conceptual Design Review Amelia Weller, Erick Chewakin, Will Hakes, Amelia Weller, Erick Chewakin, Will Hakes, Emma Mossinger, Brendon Barela, Jason Emma Mossinger, Brendon Barela, Jason Schelz, Ethan Long Schelz, Ethan Long 9/16/10 9/16/10 Fall 2010 Rev A 08-23-10

description

Fall 2010 Rev A 08-23-10. Team Mate Conceptual Design Review. Amelia Weller, Erick Chewakin , Will Hakes, Emma Mossinger , Brendon Barela , Jason Schelz , Ethan Long 9/16/10. Our objective is to study the amounts of UV radiation in the upper stratosphere. - PowerPoint PPT Presentation

Transcript of Team Mate Conceptual Design Review

Page 1: Team Mate Conceptual Design Review

{{

Team MateTeam MateConceptual Design ReviewConceptual Design ReviewAmelia Weller, Erick Chewakin, Will Hakes, Emma Amelia Weller, Erick Chewakin, Will Hakes, Emma

Mossinger, Brendon Barela, Jason Schelz, Ethan Mossinger, Brendon Barela, Jason Schelz, Ethan LongLong

9/16/109/16/10

Fall 2010 R

ev A

08-23-10

Page 2: Team Mate Conceptual Design Review

Our objective is to study the amounts of Our objective is to study the amounts of UV radiation in the upper stratosphere. UV radiation in the upper stratosphere.

We believe that we will find an increased We believe that we will find an increased amount of UV radiation as compared to amount of UV radiation as compared to previous years’ data.previous years’ data.

We are doing this because we think that it We are doing this because we think that it would be fascinating to see the difference would be fascinating to see the difference in UV radiation with the solar flare that in UV radiation with the solar flare that has occuredhas occured

Mission OverviewMission Overview

Page 3: Team Mate Conceptual Design Review

We will complete our mission by using a We will complete our mission by using a light to frequency converter in conjunction light to frequency converter in conjunction with an Arduino microcontroller that will with an Arduino microcontroller that will allow the payload to take data points on allow the payload to take data points on the amount of UVA radiation present in the amount of UVA radiation present in the atmosphere.the atmosphere.

• PartsParts• Arduino microcontrollerArduino microcontroller• Light to frequency converterLight to frequency converter• CameraCamera• HOBOHOBO

DesignDesign

Page 4: Team Mate Conceptual Design Review

Design cont.Design cont.

Page 5: Team Mate Conceptual Design Review

Team MembersTeam MembersManagementManagement

Team Member Address Phone # Specialty Assistant Position

Amelia Weller Cockerell 109

(775)220-4294 Team Leader and Budget/Schedule

Testing

Brendon Barela Crosman104

(303)518-7810 C&DH and Science

Emma Mossinger Crosman203

(925)348-0954 Testing Lead Structures/Thermal

Ethan Long Aden (303)587-0220 Structures/Thermal Lead Electrical

Erick Chewakin Brackett206

(719)433-1480 Electrical Lead

Jason Schelz Crosman120

(203)912-3059 C&DH Structure/Thermal

Will Hakes Crosman004

(970)749-9158 Science Lead

Page 6: Team Mate Conceptual Design Review

ScheduleSchedule

Management Con’tManagement Con’tDate Time What9/7 6:45 PM First Meeting9/9 7:30 PM Begin Proposal9/10 2:20 PM Assign Specializations9/14 7:30 PM Team Meeting (design complete)9/15 6:30 PM Team Meeting (proposals complete)9/16 7:00 AM Proposals AND Presentations Due9/21 At apt Order Hardware9/28 7:00 PM Team Meeting (begin construction)9/28 9:30 AM Heater Due10/5 7:00 AM DD Rev A/B and CDR Presentation Due10/5 7:00 PM Team Meeting10/12 7:00 PM Team Meeting (prototyping design complete)10/19 7:00 PM Team Meeting (cold test complete)10/26 9:30 AM Pre-Launch Inspection10/26 7:00 PM Team Meeting10/28 9:30 AM Mission Test11/2 7:00 AM LLR Presentations and DD Rev C Due11/2 7:00 PM Team Meeting (design review)11/5 At apt Balloon Weigh-in and Turn In11/5 2:00 PM DLC 270A & LRR Cards Due11/6 4:45 AM LAUNCH DAY!11/16 7:00 PM Team Meeting (work on presentation)11/23 7:00 PM Team Meeting (work on presentation)11/30 7:00 AM All Presentations and Data Due12/4 9:00 AM DD Rev D and Team Videos Due

Page 7: Team Mate Conceptual Design Review

BudgetBudgetComponent Price (including shipping) Weight Place of Purchase

HOBO Data Logger Provided 25.0g --

Foam core Provided --

Canon A570IS Digital Camera w/ Memory Card

Provided 220.0g --

9V Batteries $25 101.4g Hardware Store

Heater Provided 100g --

Arduino USB Board (Duemilanove)

$36.85 + tax 32.0g SparkFun

Aluminum Tape Provided --

SFE Light to Frequency Converter- TSL235R

$14.75 1g Robotshop

PVC Tubing Provided

Washer and Paperclip Free We have these

Foam Insulation Provided

Hot Glue Provided

Velcro $5 Hardware Store

Switches Provided 20.0g

TOTALS: PRICE: Weight: $81.60 499.4

Page 8: Team Mate Conceptual Design Review

Inability to finishInability to finish Difficulty ProgrammingDifficulty Programming Systems failing during the flightSystems failing during the flight Not getting good picturesNot getting good pictures

Biggest WorriesBiggest Worries