Team Garuda Cansat 2012 PFR
-
Upload
rishi-dua -
Category
Technology
-
view
259 -
download
36
description
Transcript of Team Garuda Cansat 2012 PFR
Team Logo
Here
CanSat 2012
Post Flight Review
Team 7634
Garuda
Indian Institute of Technology, Delhi
CanSat 2012 PFR: Team 7634 (Garuda) 1
Team Logo
Here
(If You Want) Presentation Outline
Systems Overview
Mission summary
CanSat overview
Components summary
Physical layout
Concept of Operations and Sequence of Events
Comparison of planned and actual Con-Ops
Comparison of planned and actual SOE
FSW requirements
Flight Data Analysis
Carrier TLM - GPS data
Carrier TLM - Altitude data
Carrier TLM - Air temp data
Carrier TLM - Battery data
Lander TLM - Altitude data
Lander TLM - Battery data
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 2
Team Logo
Here
(If You Want) Presentation Outline
Average descent rate – carrier above 200m
Average descent rate – carrier 91m to 200m
Average descent rate – lander after separation
Bonus Data (impact force calculation)
Failure Analysis
Identification of failures, root causes, and corrective actions
Management
CanSat budget - hardware
CanSat budget - other
Lessons Learned
Discussion of what worked and what didn't
Conclusions
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 3
Team Logo
Here
(If You Want) Team Garuda
Contact Details: <firstname>@teamgaruda.in
Name Major with Year
Arpit Goyal Electrical Engineering, Senior
Rajat Gupta Mechanical Engineering, Senior
Kshiteej Mahajan Computer Science, Senior
Aman Mittal Electrical Engineering, Junior
Prateek Gupta Mechanical Engineering, Junior
Sarthak Kalani Electrical Engineering, Junior
Sudeepto Majumdar Electrical Engineering, Junior
Akash Verma Mechanical Engineering, Sophomore
Rishi Dua Electrical Engineering, Sophomore
Harsh Parikh Computer Science, Freshman
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 4
Team Logo
Here
(If You Want) Team organization
Team Leader
Faculty Mentor
Mechanical
Designs
Akash Verma
Prateek Gupta
Electrical Systems
Arpit Goyal
Sarthak Kalani
Sudeepto Majumdar
Software Control
Harsh Parikh
Kshiteej Mahajan
Rishi Dua
Team Mentor
Alternate Team Leader
Aman Mittal
Rajat Gupta
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 5
Team Logo
Here
(If You Want) Acronyms
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 6
DR – Average Descent Rate
CDH – Communication and Data Handling
CONOPS – Concept of Operations
GCS – Ground Control System
GPS – Global Positioning System
SOE – Sequence of Events
Team Logo
Here
(If You Want)
Mission Summary
Pre launch
• Completing Flight Readiness demo - all work was assigned
before reaching the launch site
• CanSat mass - 648g. We used plastic for the carrier body
and drilled holes in body to keep the weight low
• Payload length - 152mm - Placed lander parallel to carrier
electronics within carrier for efficient space utilization
• No protrusions - electronics placed inside the carrier
• Airframe restraints – The CanSat airframe fitted perfectly
into the height and width of the launcher.
• Antenna length –4m, using a PVC mast
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 7
Team Logo
Here
(If You Want) Launch and Descent
• Launch in Assigned window – time slot 11-12, we launched at 11:20 AM
• Launched - The launch was successful
• CanSat deployed - The CanSat deployed successfully from Launcher
• Lander Separation - battery drained so motor did not work. whereas we got GPS, reason - over testing, replacement not easy
• GPS data - Success, using GPS sensor
• Altitude data - Success, Using Pressure Sensor BMP085
• Air temperature data - Success, Using Temperature Sensor BMP085
• Battery voltage data - Success, Using voltage divider circuit
• CanSat TLM started -Success, By giving ST from ground station
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 8
Team Logo
Here
(If You Want) Recovery
• Carrier Recovered – Recovery crew we were able to locate
CanSat. We had GPS data and plots on Google Maps but
they were not used as the parachutes were bright and we
could see the exact location by observing the descent.
• Carrier Locator Operational - The buzzer did not work
because manual command ‘BU’ was forgotten to be sent.
• Lander Recovered – Since lander did not deploy, carrier and
lander were recovered together
• Lander Locator Operational - The lander buzzer too did not
work due to wiring problem.
• Egg intact – The idea to use sponge ball worked well as
expected by the rigorous testing results.
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 9
Team Logo
Here
Systems Overview
Presenter: Rishi Dua
CanSat 2012 PFR: Team 7634 (Garuda) 10
Team Logo
Here
(If You Want) Mission Overview
The Main Objective:
The main purpose of CanSat is to provide egg safety from launch to landing.
Auxiliary Objectives:
• Launching CanSat.
• Descend CanSat from 600m to 200m at a constant descent rate of 10 m/s +/-
1 m/s
• Changing constant descent rate to 5 m/s +/- 1m/s at 200m
• Releasing the lander with egg at 91 m altitude.
• Landing lander with descend rate less than 5m/s without damaging egg.
• Collecting data at ground station from sensors in CanSat through x-bee radio
modules.
Selectable (Bonus) Mission:
Calculating thrust force after lander has landed; Data to be collected at rate more
than 100Hz and stored on board for post-processing.
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 11
Team Logo
Here
(If You Want) CanSat overview
• Used unidirectional antenna
• Parachutes for decent control
• Plastic body made to keep CanSat low weight
• Placed lander parallel to carrier electronics within carrier for
efficient space utilization
• Egg compartment located at the bottom of the lander
packed using sponge
• DC Motor actuated flap separation mechanism
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 12
Team Logo
Here
(If You Want) Component Summary
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 13
Team Logo
Here
(If You Want)
Electrical Components Summary-
Carrier
CanSat 2012 PFR: Team 7634 (Garuda) 14
XBee GPS BMP085 Antenna
(RPSMA)
Buzzer Resistors Arduino Uno SD card
L293D
Battery
Presenter: Rishi Dua
Team Logo
Here
(If You Want)
CanSat 2012 PFR: Team 7634 (Garuda) 15
Electrical Components Summary –
Carrier
GPS Data
SD Card
BMP 085
(T&P sensor)
Xbee Pro
Battery Voltage
Buzzer
Arduino Uno
Serial Data Serial for Tx
Through
ADCI2
C
data
L293D
(buffer for
actuator) Output
PWM
Presenter: Rishi Dua
Team Logo
Here
(If You Want)
Electrical Components Summary-
Carrier
Component Use
XBee Data Communication from Carrier to Ground
station.
GPS Getting the GPS data to the GCS.
BMP Pressure and Temperature Data
Antenna Transceiver For sending and receiving the XBee data.
Buzzer For Locating the carrier and lander.
Battery For powering up the carrier and lander system.
Arduino Uno Microcontroller for the data processing.
Resistors For voltage dividing circuit.
SD Card For storing on-flight data
L293D Motor Driver IC
CanSat 2012 PFR: Team 7634 (Garuda) 16Presenter: Rishi Dua
Team Logo
Here
(If You Want)
Electrical Components Summary -
Lander
CanSat 2012 PFR: Team 7634 (Garuda) 17
MMA 7361 BMP085 Resistors
Buzzer SD Card Battery
Presenter: Rishi Dua
Team Logo
Here
(If You Want)
CanSat 2012 PFR: Team 7634 (Garuda) 18
Electrical Components Summary–
Lander
SD Card
BMP 085
(T&P sensor)
Battery Voltage
Buzzer
Arduino UnoThrough
ADC
I2C
data
MMA 7361 (Accelerometer) Through
ADC
Presenter: Rishi Dua
Team Logo
Here
(If You Want)
Electrical Components Summary -
Lander
Components Use
MMA 7361 Get Accelerometer Data
Buzzer Locating the lander
Battery Powering up the CanSat system.
SD card For storing on-flight data
Arduino Uno For processing the data.
Resistors Voltage dividing circuit.
CanSat 2012 PFR: Team 7634 (Garuda) 19Presenter: Rishi Dua
Team Logo
Here
(If You Want)
Mechanical Components Summary -
Carrier
• Frame –
• Bonding -
CanSat 2012 PFR: Team 7634 (Garuda) 20
Components Use
Motors For opening and closing of
leafs and flaps
Flap Deployment of lander
Leaf Second parachute
deployment.
Components Use
Elfy To glue together acrylic
Electrical Tapes To hold the components.
Presenter: Rishi Dua
Team Logo
Here
(If You Want)
Mechanical Components Summary-
Lander
• Frame -
Bonding –
CanSat 2012 PFR: Team 7634 (Garuda) 21
Components Use
Acrylic Rods Support mechanism with less weight.
Hip Protector Impact Distribution for Egg Protection
Circular Disk (Plastic) To hold the electrical Components
Foam Ball Shock Absorption for Egg Protection
Components Use
Electrical Tape To hold the electrical components
Elfy To glue the electrical components
Epoxy To glue the joints together
Presenter: Rishi Dua
Team Logo
Here
(If You Want) Physical Layout- CanSat
Presenter: Rishi Dua
126mm
Space for Electronics
Parachute on top
Lander detachment from bottom
Lander
Motor
CanSat 2012 PFR: Team 7634 (Garuda) 22
Team Logo
Here
(If You Want) Physical Layout- Lander
145m
m
Space for
parachutes
Electronic Components
Egg
Egg protection system
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 23
Team Logo
Here
(If You Want) Physical Layout
Presenter: Rishi Dua CanSat 2012 PFR: Team 7634 (Garuda) 24
Team Logo
Here
Concept of Operations and Sequence
of Events
Presenter: Harsh Parikh
CanSat 2012 PFR: Team 7634 (Garuda) 25
Team Logo
Here
(If You Want)
Comparison of planned and actual
Con-Ops
• Safety Inspection
• Briefing
• Last Mechanical control
• Last Electrical control
• Coming at Competition Arena
• Checking weight of Cansat
Pre Flight
• Power-on the Cansat
• Placing the Cansat in Rocket.
• Place the Rocket on launch pad
• Launch
• Recover the Cansat after flight
Launch and Flight
• Locating CanSat
• Saving Data
• Analyzing Data
• Preparing PFR
• PFR Presentation
Post Flight
*The Operation(s) in red is the one which failed
CanSat 2012 PFR: Team 7634 (Garuda) 26Presenter: Harsh Parikh
Team Logo
Here
(If You Want)
Comparison of planned and actual
SOE
*The Operation(s) in red is the one which had problems.
On CanSat
Keep CanSat in
rocket
Launch Rocket
Leaving CanSat
from rocket at
600m
Descent rate should be 10m/s when CanSat is at height more
than 200m
Descent rate should be 5m/s when CanSat is at height more than
91m
Detaching lander at
91m
Collecting data from sensors
Sending Data to ground station
Data Analysis
Calculating collision
force
Detecting CanSat Off
CanSat
CanSat 2012 PFR: Team 7634 (Garuda) 27Presenter: Harsh Parikh
Team Logo
Here
(If You Want) Overview of Con-Op and SOE
Planned Actual Reasons
Safety Check Successful Provided checklist was checked more than twice
GCS connection Successful Rigorous testing was done before
Placing Egg Payload on the
CanSat
Successful Easy Design of Lander Egg Placement
Loading CanSat in Launch
vehicle
Successful Size was well within limit and there were no
protrusions
Following the designed flow
of CanSat
Lander didn’t
deploy
As the battery drained out, the flap motor couldn’t
get enough power to rotate. Failure of Separation
mechanism.
Telemetry processing,
archiving and analysis
Successful Testing already done many times and high gain
antenna used
Switching on the Carrier
locating device
Failed Manually command ‘BU’ was forgotten to be sent
from GCS
Switching on the Lander
locating device
Failed Wiring problems.
Recovery Successful Bright Colored Parachutes with help from
organisers
CanSat 2012 PFR: Team 7634 (Garuda) 28Presenter: Harsh Parikh
Team Logo
Here
(If You Want) Con-Op and SOE
• The Cansat was almost ready and tested before coming to
arena but there were minor changes at last moment on the
module
• The spherical casing along with bubble wrap was prepared
on field.
• There was need of battery change in Lander and Carrier but
only Lander’s battery was changed due to lack of time and
complicated battery fixture
• Everything else went according to plan, also the Cansat was
completely recovered.
CanSat 2012 PFR: Team 7634 (Garuda) 29Presenter: Harsh Parikh
Team Logo
Here
(If You Want) FSW Requirements
• FSW required sea-level pressure and elevation of the
launch place (Jim Burkett Ranch, Texas) to calculate exact
altitude of CanSat.
• This was done using a meteorological website and then
making elevation at ground to zero.
CanSat 2012 PFR: Team 7634 (Garuda) 30Presenter: Harsh Parikh
Team Logo
Here
Flight Data Analysis
Presenter: Arpit Goyal
CanSat 2012 PFR: Team 7634 (Garuda) 31
Team Logo
Here
(If You Want) Carrier TLM: GPS data
Presenter: Arpit Goyal CanSat 2012 PFR: Team 7634 (Garuda) 32
TLM from Carrier was started by sending a ‘ST’ command
from GCS.
Telemetry of GPS data is displayed below:
$GPGGA,162631.000,3157.8494,N,09916.9001,W,2,9,0.9
4,501.6,M,-22,M,,*75
Following slides will show trajectory of CanSat using
Google Earth API.
Team Logo
Here
(If You Want) Carrier Trajectory Google Earth
CanSat 2012 PFR: Team 7634 (Garuda) 33Presenter: Arpit Goyal
Team Logo
Here
(If You Want)
Carrier Trajectory Google Earth: Side
View
CanSat 2012 PFR: Team 7634 (Garuda) 34Presenter: Arpit Goyal
Launch
Pad, Jim
Burkett
Ranch
Team Logo
Here
(If You Want)
Carrier Trajectory Google Earth: Top
View
CanSat 2012 PFR: Team 7634 (Garuda) 35Presenter: Arpit Goyal
Team Logo
Here
(If You Want)
Carrier TLM: GPS data,
No of Satellites
CanSat 2012 PFR: Team 7634 (Garuda) 36Presenter: Arpit Goyal
Team Logo
Here
(If You Want) Carrier TLM - Altitude data
CanSat 2012 PFR: Team 7634 (Garuda) 37Presenter: Arpit Goyal
200m
height
from
Ground
Avg. Descent Rate =
(735-626)/(120-101)
= 5.73 m/s
Avg. Descent Rate =
(1182-735)/(84-36) =
9.3125 m/s
*535.9 is the altitude of Jim
Burkett ranch launch site from
sea level.
Team Logo
Here
(If You Want) Carrier TLM - Air temp data
CanSat 2012 PFR: Team 7634 (Garuda) 38Presenter: Arpit Goyal
Team Logo
Here
(If You Want) Carrier TLM - Battery data
CanSat 2012 PFR: Team 7634 (Garuda) 39Presenter: Arpit Goyal
Team Logo
Here
(If You Want) Lander TLM – Altitude data
CanSat 2012 PFR: Team 7634 (Garuda) 40Presenter: Arpit Goyal
Since, lander was not
separated from
Carrier, the altitude
plot will be almost
same as that of carrier
Team Logo
Here
(If You Want) Lander TLM – Battery Voltage data
CanSat 2012 PFR: Team 7634 (Garuda) 41Presenter: Arpit Goyal
Team Logo
Here
(If You Want) Impact Force Calculation
CanSat 2012 PFR: Team 7634 (Garuda) 42Presenter: Arpit Goyal
Impact Force
1.63g – 0.72g
= 0.91g
So, Impact
Force =
Mass*0.91g/0.
3 = 0.648*3 =
1.944g
Sampling
Frequency: 100Hz
Team Logo
Here
(If You Want)
Carrier TLM – Descent Rate
Calculations
CanSat 2012 PFR: Team 7634 (Garuda) 43Presenter: Arpit Goyal
200m
height
from
Ground
Avg. Descent Rate =
(735-626)/(120-101)
= 5.73 m/s
Avg. Descent Rate =
(1182-735)/(84-36) =
9.3125 m/s
*535.9 is the altitude of Jim
Burkett ranch launch site from
sea level.
Team Logo
Here
Failure Analysis
Presenter: Harsh Parikh
CanSat 2012 PFR: Team 7634 (Garuda) 44
Team Logo
Here
(If You Want) Failure Analysis
• The Lander didn’t deploy from Carrier
– The lander was to be supposed to deployed at 91m by opening of the flap at the bottom of Carrier. The flap would rotate with the help of geared motor. As the battery drained of in mid of flight the power was not enough for the motor to make it rotate.
– Tools not compatible with USA power standard
– Corrective Measures: • Will make battery holder more easily replaceable next time
• Will arrange tools on time according to US and will try to come to US a day earlier.
• The buzzer was not on while the CanSat had landed
– The drained off battery turned the tables.
– Corrective Measures: Will make battery holder more easily replaceable next time
Presenter: Harsh Parikh CanSat 2012 PFR: Team 7634 (Garuda) 45
Team Logo
Here
(If You Want) Failure Analysis
• The battery of Cansat drained off in between the flight
– It was noticed that battery had low life left before the flight, but we were unable to replace it because, replacement of battery was complicated due to clustered design.
– The battery already installed drained off due to excessive testing
– Corrective Measures: Will make battery holder more easily replaceable next time. Ensure to place new battery at the time of launch.
• Entanglement of circuit wires and uncertainty of connection
– It was presumed that it would be convenient to make circuit by hand and that no PCB was needed, this made the circuitry lot more wired and clustered
– Due to so many wires, they use to entangle and also it was not convenient to change any component.
– Corrective Measures: Will use printed boards next time. They are easy to make and more reliable.
Presenter: Harsh Parikh CanSat 2012 PFR: Team 7634 (Garuda) 46
Team Logo
Here
Management
Presenter: Rishi Dua
CanSat 2012 PFR: Team 7634 (Garuda) 47
Team Logo
Here
(If You Want) CanSat Budget – Hardware
CanSat 2012 PFR: Team 7634 (Garuda)Presenter: Rishi Dua
S.No. Component Quantity Rate (USD) Cost (USD)
1 Arduino Board Uno 2 27.6 55.2
2 Pressure Sensor Bosch 2 20.0 40.0
3 GPS sensor 1 50.0 50.0
4 Accelerometer 1 12.0 12.0
5 Xbee Radios 1 pair 50.6 50.6
6 Battery Duracell 10
(2 to be used, 8 spare)
2.4 24.0
7 Audio Buzzer 2 1.5 3.0
8 Antenna A24HSM450 2 6.0 12.0
9 Parachutes 3 25.0 75.0
10 Material for structure and
fabrication
N.A 50.0 50.0
11 DC Motors 2 5.0 10.0
TOTAL 381.8
48
Team Logo
Here
(If You Want)
Components Cost (USD)
Laptop for GCS None
Travel 9000
Rental 700
Test facilities 100
Total 9800
CanSat Budget – Other Costs
CanSat 2012 PFR: Team 7634 (Garuda)Presenter: Rishi Dua 49
Team Logo
Here
(If You Want) CanSat Budget – Sponsors
CanSat 2012 PFR: Team 7634 (Garuda)Presenter: Rishi Dua 50
Team Logo
Here
Lessons Learned/Conclusions
Presenter: Kshiteej S. Mahajan
CanSat 2012 PFR: Team 7634 (Garuda) 51
Team Logo
Here
(If You Want) Worked/ Didn’t Work
Worked• The bi-hemispherical sponge
egg casing along with bubble wrap and hip impact distributor.
• Parachutes with proper spill holes were able to control descend rate and drift
• Telemetry data was successfully received
• GPS sensor gave accurate data
• Pressure sensor, used to get altitude worked accurately
• Temperature sensor gave accurate data
Didn’t Work
• The lander deployment
system failed due to
battery drain
• The buzzer used to locate
carrier and lander didn’t
went ON due to wiring
problems.
• Battery could not provide
sufficient power for
motor.
Presenter: Kshiteej S. Mahajan CanSat 2012 PFR: Team 7634 (Garuda) 52
Team Logo
Here
(If You Want) Lessons Learned (1)
• The prime most lesson learned was that if PCB was
used instead loose circuit, the circuitry would have
been less complex, less clustered and more organized.
• This may help us to easily change components or
battery, also there will be no entanglement in wirings.
• Secondly, it was concluded that over testing of leaf and
flap motors resulted in drain off of battery.
• We should use the new batteries just before the flight
so that it may sustain for long time.
CanSat 2012 PFR: Team 7634 (Garuda)Presenter: Kshiteej S. Mahajan 53
Team Logo
Here
(If You Want) Lessons Learned (2)
• We were unable to test the complete integration of
Cansat due to lack of local facilities. Thus we were not
able to check the deployment of lander.
• If Cansat was completely integrated much before, we
would have been able to test if from different site
instead of using local facility.
• We must try different designs physically so as to assure
its working in different scenario which will be the result
of continuous testing.
CanSat 2012 PFR: Team 7634 (Garuda)Presenter: Kshiteej S. Mahajan 54
Team Logo
Here
(If You Want)
Thank You
CanSat 2012 PFR: Team 7634 (Garuda)Presenter: Kshiteej S. Mahajan 55