TEAM ALFARO - FDI Moot · TEAM ALFARO v TABLE OF AUTHORITIES CITED AS FULL CITATION TREATIES AND...
Transcript of TEAM ALFARO - FDI Moot · TEAM ALFARO v TABLE OF AUTHORITIES CITED AS FULL CITATION TREATIES AND...
FOREIGN DIRECT INVESTMENT MOOT COMPETITION
Stockholm, 8-11 November 2018
MEMORIAL FOR RESPONDENT
TEAM ALFARO
FENOSCADIA LIMITED
45 Finley Road
40 TC 1011
- CLAIMANT -
vs.
REPUBLIC OF KRONOS
Suni Street 12
1090 Vasa
- RESPONDENT -
TEAM ALFARO
i
INDEX
TABLE OF ABBREVIATIONS ......................................................................................... III
TABLE OF AUTHORITIES ................................................................................................. V
TABLE OF CASES ............................................................................................................... XI
STATEMENT OF FACTS ..................................................................................................... 1
ARGUMENTS ON JURISDICTION .................................................................................... 3
I. CLAIMANT IS A KRONOS’ NATIONAL. THEREFORE, IT IS NOT AN
INVESTOR UNDER THE BIT ............................................................................................. 3
i. The Ticadian private equity fund has no intention of controlling CLAIMANT’S
business ................................................................................................................................ 6
ii. The concentration of almost all of CLAIMANT’S activities and operations in
Kronos evidences the genuine connection with RESPONDENT ........................................ 8
II. CLAIMANT’S REQUESTS ARE NOT ADMISSIBLE BEFORE THE
ARBITRAL TRIBUNAL ........................................................................................................ 9
i. The motion constituted a choice under the fork in the road provision ................ 10
a. The motion and the request for arbitration are essentially the same ................... 11
b. The present claims should be discussed in RESPONDENT’S courts once it was not
a provisional measure ............................................................................................ 15
III. THE TRIBUNAL HAS JURISDICTION OVER RESPONDENT’S
COUNTERCLAIM ............................................................................................................... 17
i. The wording of the BIT indicates that the parties consented with the
counterclaim ...................................................................................................................... 17
ii. The primary claim and the counterclaim are connected ....................................... 19
iii. The benefits that comes with counterclaims highlight the reasons for this
Tribunal to accept it ......................................................................................................... 21
ARGUMENTS ON THE MERITS ...................................................................................... 23
TEAM ALFARO
ii
IV. RESPONDENT ACTED IN ACCORDANCE WITH ARTICLE 6 OF THE
BIT.......... ................................................................................................................................ 23
i. RESPONDENT did not breach the fair and equitable treatment standard ............. 23
a. The BIT defines fair and equitable treatment as the Minimum Standard of
Treatment ............................................................................................................... 23
b. CLAIMANT’s legitimate expectations were not in accordance with Kronos’
scenario .................................................................................................................. 26
V. THE PRESIDENTIAL DECREE NO 2424 IS NOT EXPROPRIATORY..... 29
i. RESPONDENT’s actions are within its police powers ............................................... 30
ii. The Presidential Decree No 2424 is a non-compensatory regulation ................... 33
iii. General exceptions are provided in article 10 of the BIT ...................................... 35
VI. CLAIMANT IS LIABLE TO PAY COMPENSATION FOR THE
ENVIRONMENTAL DAMAGES CAUSED IN RESPONDENT’S TERRITORY ....... 38
PRAYERS FOR RELIEF ..................................................................................................... 42
TEAM ALFARO
iii
TABLE OF ABBREVIATIONS
ABBREVIATION FULL CITATION
Agreement
Concession Agreement
Arbitration Institute of The
Stockholm Chamber of
Commerce
SSC Arbitration Institute and SCC Rules
BIT Agreement Between The Republic of Ticadia and The
Republic of Kronos for the Promotion and Reciprocal
Protection of Investments
CLAIMANT Fenoscadia Limited
Decree Presidential Decree No 2424
Facts Statement of Uncontested Facts
Fenoscadia Fenoscadia Limited
FET Fair and Equitable Treatment
ICSID International Centre for Settlement of Investment
Disputes
IIA International Investment Agreement
Kronos Republic of Kronos
MIGA Convention Multilateral Investment Guarantee Agency Convention
MST Minimum Standard of Treatment
para. / paras. Paragraph(s)
PO Procedural Order
RESPONDENT Republic of Kronos
TEAM ALFARO
iv
Ticadia Republic of Ticadia
TEAM ALFARO
v
TABLE OF AUTHORITIES
CITED AS FULL CITATION
TREATIES AND CONVENTIONS
Vienna Convention Vienna Convention on the Law of Treaties, 23 May 1969
ARBITRAL AWARDS
Atanasova/Benoit/Ostransky Dafina Atanasova, Carlos Adrián Martínez Benoit Josef
Ostransky, Counterclaims in Investor-state Dispute
Settlement (ISDS) under International Investment
Agreements (IIAS) (Trade and Investment Law Clinic
Papers, 2012).
Berle & Means Berle, Adolf A., Means, Gardiner C., The Modern
Corporation and Private Property (New Brunswick:
Transaction Publisher, 1991).
Bjorklund Andrea K. Bjorklund, The Role of Counterclaims in
Rebalancing Investment Law (17 Lewis & Clark L. Rev.
461, 2013).
Born Born, Gary B., International Commercial Arbitration:
International Arbitration Procedures and Proceedings, 2nd
ed., (Wolters Kluwer Law & Business, 2014).
Brownlie Ian Brownlie, Public International Law, (Oxford
University Press, 6th Edition, 2003 at 509).
Cambridge Dictionary Cambridge International Dictionary of English (Bath:
Cambridge University Press, 1995).
Castka/Balzarova Pavel Castka; Michaela A. Balzarova, A critical look on
quality through CSR lenses: Key challenges stemming
TEAM ALFARO
vi
from the development of ISO 26000 (2007), International
Journal of Quality & Reliability Management, Vol. 24
Issue: 7, pp.738-752.
Dolzer Rudolf Dolzer; Christoph Schreuer, Principles of
International Investment Law, 2nd edition (Oxford
University Press, 2012).
Donald F. Rieger Jr. Donald F. Rieger Jr, Public Policy and Negating
Discriminatory Expropriations in the Municipal Courts
(Cornell International Law Journal, 1974).
Donaldson Donaldson, Thomas, The Ethics of International Business
(Oxford University Press, 1992).
Douglas Cumming Cumming, Douglas, Private Equity: fund types, risks and
returns, and regulation (New Jersey: John Wiley & Sons
Inc. 2009).
Farmer Kelsey Brook Farmer, The Best Defence is a Good
Offense – State Counterclaims in Investment Treaty
Arbitration (LLM Research Paper, Victoria University of
Wellington, 2016).
Hamida Walid Ben Hamida, L' arbitrage transnational unilatéral:
réflexions sur une procédure réservée à l'initiative d'une
personne privée contre une personne publique (Université
Panthéon-Assas, 2003).
Hóber Hobér, K., Parallel Arbitration Proceedings—Duties of the
Arbitrators: Some Reflections and Ideas, in Cremades,
B.M. and Lew, J.D.M. (eds), Parallel State and Arbitral
Procedures in International Arbitration (Paris: ICC
Publishing, 2005).
ISO 26000 International Organization for Standardization, ISO 26000
- Social Responsibility.
TEAM ALFARO
vii
J. Marless J. Marlles, Public Purpose, Private Losses: Regulatory
Expropriation and Environmental Regulation in
International Investment Law (2007) 16 Journal of
Transnational Law & Policy 275.
Kjos Hege Elisabeth Kjos, Applicable Law in Investor-State
Arbitration: The Interplay Between National and
International Law (Oxford University Press, 2013).
Konrad von Moltke Konrad von Moltke, Discrimination and Non-
Discrimination in Foreign Direct Investment Mining
Issues (OECD Global Forum On International Investment,
2002).
Kryvoi Yaraslau Kryvoi, Counterclaims in Investor-State
Arbitration (The British Institute of International and
Comparative Law, 2011).
Lim/Ho/Paparinskis Chin Leng Lim; Jean Ho; Martins Paparinskis,
International Investment Law and Arbitration:
Commentary, Awards and other Materials. (New York:
Cambridge University Press, 2017.)
Lowe Vaughan Lowe, Regulation or Expropriation? Current
Legal Problems, Volume 55, Issue 1 (1 January 2002).
McLachlan/ Shore/
Weiniger
McLachlan, C.; Shore, L; Weiniger, M., International
Investment Arbitration: Substantive Principles (2nd ed.,
2007).
Muchlinski/Ortino/Schreuer Muchlinski,Peter T; Ortino, Federico; Schreuer, Christoph,
The Oxford Handbook of International Investment Law.
ISBN-13: 9780199231386. Oxford: Oxford Handbooks in
Law (June 2008).
Musayev Kamran Musayev, Counterclaims in Treaty-based
Investment Arbitration (Master thesis, University of Oslo,
TEAM ALFARO
viii
2017).
Newcombe/Paradell Andrew Newcombe; Lluís Paradell, Law and Practice of
Investment Treaties (Kluwer Law International, 2009).
Odumosu Ibironke T. Odumosu, The Antinomies of the (Continued)
Relevance of ICSID to the Third World (8 San Diego
International Law Journal 345, 2007).
OECD Gaukrodger, D. Addressing the balance of interests in
investment treaties: The limitation of fair and equitable
treatment provisions to the minimum standard of treatment
under customary international law (OECD Working
Papers on International Investment, 2017).
OECD Indirect
Expropriation
Indirect Expropriation and the Right to Regulate in
International Investment Law (OECD Working Papers on
International Investment, 2004).
Okawa Phoebe Okawa, Issues of Admissibility and the Law on
International Responsibility, in International Law, 4 ed.,
(New York: Oxford University Press, 2014).
Paulsson Paulsson, J., Denial of Justice in International Law. Hersch
Lauterpacht Memorial Lectures (Cambridge University
Press, 2005).
Peterson Luke Eric Peterson, Challenges Under Bilateral
Investment Treaties Give Weight to Calls for Multilateral
Rules (World Trade Agenda, 2001).
Preston Brian Preston, Sustainable Development Law in the
Courts: The Polluter Pays Principle (26 Environmental
and Planning Law Journal 257, 2009).
Schell Schell, James M., Private Equity Funds: business, structure
and operations (New York: Law Journal Press, 2004).
TEAM ALFARO
ix
Schreuer Christoph H. Schreuer, The ICSID Convention: A
Commentary (Cambridge University Press, 2001).
Schwebel Stephen M. Schwebel, In defense of Bilateral Investment
Treaties (Perspectives on topical foreign direct investment
issues No. 135, 2014).
Shaw Malcolm N. Shaw, International Law (5th ed., Cambridge,
2003).
Suarez Anzorena Suarez Anzorena, C.I., Multiplicity of Claims under BITs
and the Argentine Case 2 (2) Transnational Dispute
Management (2005).
Suzy H. Nikièma Suzy H. Nikièma, Compensation for Expropriation
(International Institute for Sustainable Development,
2013).
UNCTAD United Nations Conference on Trade and Development.
Fair and Equitable treatment (UNCTAD Series on Issues
in International Investment Agreements II, 2012).
United Nations United Nations, Glossary of Environment Statistics,
Studies in Methods, Series F, No. 67 (1997).
Van Harten Gus Van Harten, Arbitrator Behaviour in Asymmetrical
Adjudication: An Empirical Study of Investment Treaty
Arbitration (Osgoode Hall Law Journal, 2012).
Wegen/Markert Wegen, G. and Markert, L., Food For Thought on Fork-in-
the-Road—A Clause Awakens from its Hibernation, in
Klausegger, C. Klein, P. Kremslehner, F., Petsche, A.,
Pitkowitz, N., Power, J., Welser, I., and Zeiler, G. (eds),
Austrian Yearbook on International Arbitration (2010)
(Vienna: Manzsche Verlags- und
Universitätsbuchhandlung, 2010) 269–292 (G. Wegen and
L. Markert, in Aust.Y.I.A. (2010).
TEAM ALFARO
x
Wehland Wehland, Hanno, The Coordination of Multiple
Proceedings in Investment Treaty Arbitration, Oxford
International Arbitration Series (2013).
Yu-Hsin Lin Controlling Controlling-Minority Shareholders: corporate
governance and leveraged corporate control (June 20,
2017). 2017 (2) Columbia Business Law Review 453-510
(2017).
TEAM ALFARO
xi
TABLE OF CASES
CITED AS FULL CITATION
ARBITRAL AWARD
ADC v Hungary ADC Affiliate Limited and ADC & ADMC Management
Limited v The Republic of Hungary, ICSID Case No.
ARB/03/16 (2 October 2016).
Al Warraq v Republic of
Indonesia
Hesham T. M. Al Warraq v Republic of Indonesia,
UNCITRAL (15 December 2014).
Azurix Azurix Corp. v Argentine Republic ICSID Case No.
ARB/01/12, Award, (14 July 2006).
Burlington Burlington Resources Inc. v Republic of Ecuador, ICSID
Case No. ARB/08/5 (7 February 2017).
CME CME Czech Republic B.V. (The Netherlands) v The Czech
Republic, UNCITRAL, Award (14 March 2003).
CMS CMS Gas Transmission v Argentina, Decision on Objection
to Jurisdiction (17 July 2003).
Commerce Commerce Group Corp and San Sebastian Gold Mines, Inc.
v The Republic of El Salvador, ICSID Case No
ARB/09/17, Award (14 March 2011).
Desert Line Desert Line Projects LLC v The Republic of Yemen, ICSID
Case No. ARB/05/17, Award (6 February 2008).
EDF EDF (Services) Limited v Romania, ICSID Case No.
ARB/05/13, Award (8 October 2009).
Eudoro Armando Olguín v
Republic of Paraguay
Mr. Eudoro Armando Olguín v Republic of Paraguay,
ICSID Case No. ARB/98/5, Award (26 July 2001).
TEAM ALFARO
xii
GAMI Investments GAMI Investments, Inc. v The Government of the United
Mexican States, UNCITRAL, Award (15 November 2004).
Glamis Gold v USA Glamis Gold, Ltd. v United States of America,
UNCITRAL, Award (8 June 2009).
Goetz Antoine Goetz & Others and S.A. Affinage des Metaux v
Republic of Burundi, ICSID Case No. ARB/01/2, Award
(21 June 2012).
H&H H&H Enterprises Investments, Inc. v Arab Republic of
Egypt, ICSID Case No. ARB 09/15, Decision on
RESPONDENT’s Objections to Jurisdiction (5 June 2012).
Klöckner Klöckner Industrie-Anlagen GmbH and others v United
Republic of Cameroon and Société Camerounaise des
Engrais, ICSID Case No. ARB/81/2 (1983).
Lauder Ronald S Lauder v The Czech Republic, ICSID, Final
Award (3 September 2001).
LG&E v Argentina LG&E Energy Corp., LG&E Capital Corp., LG&E
International Inc. v Argentine Republic, ICSID Case Nº
ARB/02/1, Decision on Liability (3 October 2006).
Maffezini Emilio Agustin Maffezini v Kingdom of Spain, Award,
ICSID Case No ARB/97/7, Award (13 November 2000).
Metalclad Metalclad Corp v United Mexican States, ICSID Case No.
ART(AF)97/1, Award (30 August 2000).
Methanex v United States Methanex Corporation v United States of America,
UNCITRAL, Award (3 August 2005).
Middle Middle East Cement v Egypt (ICSID), Award (12 April
2002).
Morris Philip Morris Brands SÀRL, Philip Morris Products S.A.
TEAM ALFARO
xiii
and Abal Hermanos S.A. v Oriental Republic of Uruguay,
ICSID Case No. ARB/10/7, Award (8 July 2016)
Neer L. F. H. Neer and Pauline Neer (U.S.A.) v United Mexican
States, RIAA (15 October 1926).
Nykomb Synergetics v
Latvia
Nykomb Synergetics Technology Holding AB, Stockholm
v The Republic of Latvia, Riga, SCC, Award (16 December
2003).
Occidental Occidental v Ecuador, LCIA, UNCITRAL, Award (1 July
2004).
Pan American Pan American Energy v Argentina (ICSID), Decision on
Preliminary Objections (27 July 2006).
Parkerings-Compagniet Parkerings-Compagniet AS v Republic Lithuania, ICSID
Case No. ARB/05/8, Award (11 September 2007).
Paushok Sergei Paushok, CJSC Golden East Company, CJSC
Vostokneftegaz Company v The Government of Mongolia,
Award on Jurisdiction and Liability (28 April 2011).
Plama Plama Consortium Limited v Republic of Bulgaria, ICSID
Case No. ARB/03/24, Order on Provisional Measures (06
September 2005).
Perenco Ecuador PEcuador Ltd v Republic of Ecuador, ICSID Case No
ARB/08/6, Interim Decision on the Environmental
Counterclaim (11 August 2015).
PNG PNG Sustainable Development Program Ltd v Papua New
Guinea, ICSID Case No ARB/13/33, Decision on the
CLAIMANT’s Request for Provisional Measures (21 January
2015).
Pugachev Pugachev v Russian Federation, Interim Award, IIC 1268
(7 July 2017), United Nations General Assembly [UNGA];
TEAM ALFARO
xiv
United Nations Commission on International Trade Law
[UNCITRAL].
Quiborax Quiborax v Bolivia, ICSID Case No. ARB/06/2, Decision
on Provisional Measures (26 February 2010).
Ronald S. Lauder v The
Czech Republic
Ronald S. Lauder v The Czech Republic, UNCITRAL,
Award (3 September 2001).
Roussalis Spyridon Roussalis v Romania, ICSID Case No. ARB/06/1,
Award (7 December 2011).
S.D. Myers S.D. Myers, Inc. v Government of Canada, UNCITRAL,
Final Award (30 December 2000).
Saluka Saluka v Czech Republic, Partial Award, UNCITRAL (17
March 2006).
Sempra Sempra Energy International v Argentine Republic, ICSID
Case No. ARB/0/16, Award (28 September 2007).
SGS v Pakistan SGS Société Générale de Surveillance S.A v Islamic
Republic of Pakistan, ICSID Case No. ARB/01/13,
Procedural Order (16 October 2002).
SGS v Philippines SGS Société Générale de Surveillance S.A. v Republic of
the Philippines, Decision on Jurisdiction (29 January 2004).
Siemens v Argentina Siemens A.G. v The Argentine Republic, ICSID Case No.
ARB/02/8, Award (17 January 2007).
SPP SPP v Egypt (ICSID), Decision on Jurisdiction (27
November 1985).
Suez Suez, Sociedad General de Aguas de Barcelona S.A., and
Vivendi Universal S.A v The Argentine Republic, ICSID
Case No. ARB/03/19, Award (9 April 2015).
Suez InterAgua v Argentina Suez, Sociedad General de Aguas de Barcelona S.A., and
TEAM ALFARO
xv
InterAgua Servicios Integrales del Agua S.A. v The
Argentine Republic, ICSID Case No. ARB/03/17, Decision
on Liability (30 July 2010).
Tallim United States (Tallim) B.V. and Aktsiselts Tallinna Vesi v
Republic of Estonia, ICSID Case No. ARB/14/24, Decision
on RESPONDENT’s Application for Provisional Measures
(12 May 2016).
Tecmed Tecmed v Mexico, ICSID Case No. ARB (AF)/00/2,
Award (29 May 2003).
Telenor Mobile
Communications A.S. v The
Republic of Hungary
Telenor Mobile Communications A.S. v The Republic of
Hungary, ICSlD Case No. ARB/04/15, Award (13
September 2006).
Texaco Chevron Corporation and Texaco Petroleum Company v
Ecuador, UNCITRAL, PCA Case No 2009-23, Third
Interim Award on Jurisdiction and Admissibility (27th
February 2012).
Thunderbird International Thunderbird Gaming Corporation v The
United Mexican States, UNCITRAL, Award (26 January
2006).
Tokios Tokios Toheles v Ukraine, ICSID Case No. ARB/02/18,
Award (26 July 2007).
Urbaser Urbaser et al. v The Argentine Republic, ICSID Case No.
ARB/07/26, Award (8 December 2016).
Vivendi Compañía de Aguas del Aconquija SA & Compagnie
Générale des Eaux (Vivendi) v Argentine Republic, Award,
21 November 2000, 5 ICSID Reports 296.
Waste Management Waste Management, Inc. v United Mexican States, ICSID
Case No. ARB(AF)/00/3, Award (30 April 2004).
TEAM ALFARO
xvi
DOMESTIC AND INTERNATIONAL COURT DECISIONS
Banco Nacional de Cuba v
Sabbatino
Banco Nacional de Cuba v Sabbatino, 376 U.S. 398
(1964).
Chorzów Factory Chorzów Factory, Interpretation (Germany v. Poland),
No. 11 (1927), Dissenting Opinion of Judge Anzilotti,
PCIJ (Ser. A).
Mugler v Kansas Mugler v Kansas, 123 U.S. 623 (1887).
Oscar Chinn Case Britain v. Belgium, Permanent Court of International
Justice (1934), P.C.I.J. (Ser. A/B) No. 63.
Pennsylvania Coal Co v Mahon Pennsylvania Coal Company v. Mahon, 260 U.S. 393
(1922).
Sooraram Pratap Reddy & Ors.
v Distt. Collector, Ranga Reddy
Sooraram Pratap Reddy & Ors. v District Collector,
Ranga Reddy Distt. & Ors., Supreme Court of India (5
September 2008).
TEAM ALFARO
1
STATEMENT OF FACTS
1. This case concerns to Republic of Kronos (“Kronos” or “RESPONDENT”) actions to
protect its environment and the health of its population due to the damages caused by
Fenosadia Limited’s (“Fenoscadia” or “CLAIMANT”) mining operations.
2. RESPONDENT is an underdeveloped country that discovered the occurrence of lindoro, a
rare earth metal, in its Northern region (hereinafter “the Site”). Since there were no
national companies in RESPONDENT’s territory with appropriate expertise to extract it,
in November 1998, the Kronian government decided to conduct a public auction for the
concession of rights to extract the metal, which was won by CLAIMANT. The
exploitation effectively started in August 2008.
3. CLAIMANT and RESPONDENT, then, signed an Agreement in order to protect and
regulate the rights to exploit lindoro. Among the obligations settled, CLAIMANT
committed to operate sustainably, taking the due precautions with the disposal of any
waste result of the exploitation. However, CLAIMANT has not complied with such
obligations.
4. The Agreement also provided for inspections in CLAIMANT’s activities. Over the years,
the inspection reports of the Ministry for Environmental Matters have shown that the
exploitation conducted by CLAIMANT had a significant potential to cause environmental
damages, and since 2010, year that CLAIMANT concentrated its mining activities and
resources in Kronos, the volume of toxic wastes found in RESPONDENT’s river
increased.
5. In 2012, 35% of CLAIMANT’s shares were bought by Kronian nationals - who started to
exert control over the company’s matters and from that year until today, the majority of
CLAIMANT’s board of directors is comprised by Kronian national as well.
6. Moreover, given the conclusions of the Federal University Study, it came to
RESPONDENT’s attention that CLAIMANT’s activities caused the pollution of the Rhea
River and that an urgent measure should be taken by the Kronian government to avoid
further harm. The current high level of contamination of the Rhea River placed it
among the top three most polluted rivers in the world. A complete decontamination
might take five years and cost no less than USD 75 million. The Study also
TEAM ALFARO
2
demonstrated that since CLAIMANT’s activities started in RESPONDENT’s territory, it has
been verified a significant increase in cardiovascular disease and microcephaly.
7. Considering that CLAIMANT blatantly failed to fulfill its environment-related
obligations by causing severe damages to RESPONDENT’s environment and to the health
of its population, RESPONDENT had no choice but to strengthen its environmental
framework by immediately issuing the Presidential Decree No 2424 - a measure totally
within its sovereign powers and pretty much expected from a government.
8. Therefore, complying with the Kronian Environmental Act (KEA) and assuring the
welfare of the population, as required by the BIT, RESPONDENT revoked CLAIMANT’s
operating licenses and lawfully terminated the Agreement through the Decree No 2424.
9. Due to this fact, CLAIMANT filed a motion before RESPONDENT’s courts directly
questioning the Decree’s reasons and the impacts it supposedly caused on CLAIMANT’s
activities. Not satisfied with the national pronouncement, CLAIMANT now seeks relief
in arbitration through a request that has essentially the same grounds discussed in the
national court and represents a double choice under the dispute settlement clause of the
BIT, which is not admissible.
TEAM ALFARO
3
ARGUMENTS ON JURISDICTION
10. RESPONDENT contends that the Arbitral Tribunal lacks jurisdiction over the present
dispute since (I) CLAIMANT is not an investor under the 1995 Ticadia-Kronos Bilateral
Investment Treaty (therefore “BIT”); and, that (II) CLAIMANT’s requests are not
admissible in view of the lawsuit CLAIMANT filed before the domestic courts of
RESPONDENT. However, in the remote possibility of the Arbitral Tribunal understands
that it has jurisdiction over this dispute, (III) RESPONDENT’s counterclaim shall be
admitted.
I. CLAIMANT IS A KRONOS’ NATIONAL. THEREFORE, IT IS NOT AN INVESTOR UNDER
THE BIT
11. RESPONDENT will hereinafter demonstrate that Fenoscadia Limited is a Kronian
company, since it is controlled by Kronian nationals, has a substantial business in
Kronos; and, does not have an effective link with Ticadia to be considered a national of
this country. In view of these facts, CLAIMANT cannot be considered an investor under
the BIT and is not eligible to take advantages from it, since article 11(1) of the BIT
expressly states that in case of an eventual investment dispute, the parties are a
“contracting party” and an “investor of the other contracting party”1.
12. It is important to highlight that RESPONDENT does not question the fact that CLAIMANT
had, until a certain part of its history, Ticadian nationality. However, that situation
started to change over the years. The intention of commuting CLAIMANT’s nationality
from Ticadian to Kronian became latent in 2010, when the company decided to move
almost all of its operations to Kronos and effectively shut down its activities in
Ticadia.2 Then, in 2012, the nationality changing process was finally concluded, when
Kronian nationals acquired a considerable amount of CLAIMANT’s voting shares and
received from the remaining shareholders their managing power of the company,
assuming CLAIMANT’s control.3
1 BIT, p. 44
2 Facts, p. 33.
3 Ibidem.
TEAM ALFARO
4
13. The first evidence of CLAIMANT’s Kronian nationality can be demonstrated by the
analysis of the company’s controlling situation. It is a fact that CLAIMANT’S effective
control is exerted, since 2012, by a group of Kronian shareholders that acquired 35% of
CLAIMANT’s voting shares.4 By the time of the acquisition, the Ticadian private equity
fund, that owns the remaining voting shares, decided to delegate its powers of decisions
to those Kronian shareholders.5
14. In light of this, since 2012 CLAIMANT is not just partially owned but also controlled by
Kronian nationals,6 as they sum up the power of decision that arose from their own
shares and from shares of the Ticadian private equity fund. Furthermore, with the
purpose of facilitating the controlling of CLAIMANT by the Kronian nationals, they also
compose the majority of CLAIMANT’s board of directors.7
15. The second situation that demonstrates CLAIMANT’s Kronian nationality is the fact that
CLAIMANT has a genuine connection with Kronos and not with Ticadia. The intention
of dissolving CLAIMANT’s connection with Ticadia and enhancing its connection with
Kronos started a long time ago, even before the Kronian nationals had acquired
CLAIMANT’s shares and had comprised the majority of its board of directors. In 2010,
such intention became indisputable since CLAIMANT decided to shut down its activities
in Ticadia and concentrate most of its operations and resources in Kronos.8 From that
year on, the link between CLAIMANT and Ticadia started to become more and more
brittle, meanwhile its connection with Kronos grew strongly.
16. Another fact that evidences the genuine connection between Kronos and CLAIMANT is
that, even before the acquisition of CLAIMANT’s shares by the Kronian nationals, most
decisions of the board of directors were already based on CLAIMANT’s activities in
Kronos, in favor of Kronos interests and implemented in Kronos territory.9 That trend
has only increased after the acquisition of the voting shares by the Kronian nationals in
2012, those who constitute CLAIMANT’s board of directors and, consequently, exert
4 Facts, p. 32.
5 Ibidem, p. 33.
6 Ibidem.
7 Ibidem.
8 Ibidem.
9 Ibidem, p. 34.
TEAM ALFARO
5
considerable control over the company. By that time, CLAIMANT transferred all of its
activities to Kronos.10
17. Therefore, the meager links left between CLAIMANT and Ticadia are merely formal ties,
such as its documents that still refer to Republic of Ticadia as its place of incorporation
and meetings of the board of directors that occasionally take place in Ticadia, which
may configure Ticadia as the place where the siège social is located.
18. However, one situation must be observed. The adoption of the place of incorporation or
the siège social criteria, ignoring the controlling situation of a company and its genuine
connection with the country it alleges to be a national from, to define the investor’s
nationality, has proved its own failure: treaty shopping rates increase when BITs don’t
comprise any denial of benefits clause or control rule stipulating that there has to exist
at least a real economic connection between the investor and the home state in order for
it to be qualified as a national of one of the parties and an eligible investor.11
19. Treaty shopping occurs when a company that has no genuine connection with a country
declares itself as its national, intending to take advantages, benefits and protections
under a treaty that this country has signed. CLAIMANT perfectly fulfills this hypothesis:
it has no activities, operations or employees in Ticadia; it is not controlled by
Ticadians, since the Ticadian shareholders delegated their voting power to the Kronian
shareholders; the decisions are taken only envisioning Kronos’ interests; the decisions
are implemented in Kronos and none of Ticadia’s interests are taken into account.
20. The increasing in treaty shopping rates is merely an example of the many problems that
can emerge from considering just the place of incorporation or the place of the siége
social of a company. For that reason, there is a growing trend in analyzing the control
structure of companies and its effective managers to define its nationality.12 That
analysis shall be done to identify CLAIMANT’s nationality, which would lead to the
conclusion that CLAIMANT is a Kronian company, therefore not an eligible investor
according to the BIT.
10 Facts, p. 34.
11 ZHANG, p. 50.
12 UNCTAD, pp.170-181.
TEAM ALFARO
6
i. The Ticadian private equity fund has no intention of controlling CLAIMANT’s
business
21. CLAIMANT is a company incorporated in Ticadia in 1993 that had 65% of its voting
shares sold to a Ticadian private equity fund (hereinafter “PE fund”) in 1998 and the
other 35% of its shares were bought by Kronian nationals in 2012.13
22. Private equity fund is a form of investment14, an equity that originates from
partnerships of many companies and institutional investors that intent to invest in solid
private companies with growth perspective by buying their stocks to achieve a fine
profit from that business’ growth.15 If the investment is not being as profitable as
expected, the fund sells its shares and pursuit another company to invest in.16
Therefore, a private equity fund can be composed of uncountable investors (partners)
that do not aim to be the effective owners and exert control over the invested company,
since their interest is only to obtain profit from an investment. That is precisely
CLAIMANT’s situation.
23. The Ticadian PE fund that owns 65% of CLAIMANT’s voting shares has a widely held
stock owned by nationals of multiple countries17, who have the sole objective to obtain
profit from CLAIMANT’s business. The lack of interest of those investors in managing
and controlling the company was already clear when they decided to invest through a
private equity fund and became even more evident when that fund delegated18 its power
of decision over CLAIMANT’s business to the Kronian nationals, owners of the other
35% of CLAIMANT’s shares.
24. The three Kronian owners of 35% of CLAIMANT’s voting shares and members of the
company’s board of directors for the past five years19 are the ones who truly care about
CLAIMANT’s development - not just for investment purpose, different from the Ticadian
PE fund - and that exert effective control over the company. It is a known fact that
13 Facts, p. 32.
14 Douglas Cumming [eb].
15 Schell [eb].
16 Douglas Cumming [eb].
17 PO2, p. 56.
18 Facts, p. 32.
19 Ibidem, pp. 32-33.
TEAM ALFARO
7
those three Kronians have the necessary expertise to conduct and control a mining
company, given their experience in mining industry in other countries20. They have,
indeed, been managing the company successfully for already five full years.21
25. In that sense, it is unreasonable to ignore CLAIMANT’s managing situation in order to
accept that CLAIMANT is still a Ticadian company simply because it was incorporated
under Ticadia’s law 25 years ago or because 65% of CLAIMANT’s shares are owned by
that Ticadian PE fund. As stated before, PE funds are merely intermediaries between
uncountable investors from different nationalities and the companies they intend to
invest, for the sole purpose of profiting, with no intention of controlling those
companies. Thus, the nationality of a PE fund shall not interfere in the nationality of its
invested companies, especially in a situation such as CLAIMANT’s, when there exists a
small, but articulated and easily identifiable group that do dominate the affairs of the
company.
26. It is indisputable that the Kronian shareholders manage and exert substantial control
over CLAIMANT.22 Furthermore, it is important to highlight that it is perfectly possible
to a company be controlled by a group or individual that owns a minor amount of
shares.23 One of the hypothesis that enables that kind of controlling happens when a
group or individual accumulate the power that arose from their own shares and the
power that arose from the shares of others shareholders, until totalize enough stock
interest to control the company.24 Precisely CLAIMANT’s condition, since the Ticadian
PE fund delegated the power of their shares to the Kronian owners.
27. In conclusion, it is glaring that CLAIMANT has acquired Kronian nationality through the
past years, once, as demonstrated, it is fully controlled and managed by Kronian
nationals that take into account exclusively Kronos’ economic interests and has all of
its activities and operations in the country. CLAIMANT clearly has no connection with
Ticadia, since the latter’s interests are not even taken into account in the matter.
20 Facts, p. 33.
21 Ibidem.
22 Ibidem.
23 Yu-Hsin Lin, p. 456.
24 Berle & Means, p. 75.
TEAM ALFARO
8
ii. The concentration of almost all of CLAIMANT’s activities and operations in
Kronos evidences the genuine connection with RESPONDENT
28. CLAIMANT’s Kronian nationality can be verified by the fact that its effective controllers
are Kronian, as demonstrated above, as well as CLAIMANT’s economic interests, mining
activities and operations are concentrated in RESPONDENT’s territory since 2010.25 Not
just that, CLAIMANT indeed shut down its activities in Ticadia in that same year.26
29. CLAIMANT may allege, in spite of its activities and operations had been transferred to
Kronos, that the fact of CLAIMANT being incorporated in Ticadia and its head office
also remaining in Ticadia form a stronger link between CLAIMANT and Ticadia than
between CLAIMANT and RESPONDENT. However, that argument is nothing but a
desperate tentative to create a connection that does not exist between CLAIMANT and
Ticadia.
30. The incorporation neither establishes nor proves a genuine connection between the
company and the country it was incorporated, since it can be constituted under the laws
of a particular country but turn out to have foreign effective beneficial owners and lack
any real interests, especially economic, in the place the company is incorporated.27 That
is precisely CLAIMANT’s scenario, being Fenoscadia Ltd. a company incorporated in
Ticadia, which has Kronian nationals as the beneficial owners and effective managers
and controllers of the company.
31. Moreover, the fact that the head office – as the incorporation – is in Ticadia, does not
constitute a genuine link with the country, since it represents a mere formal tie. To a
genuine link be created, the company must have an economic interest in the country.
By analyzing the circumstances of the present case, it is demonstrated that CLAIMANT’s
economic interest is entirely in Kronos, and not in Ticadia.
32. As stated before, CLAIMANT’s substantial business is fully concentrated in Kronos and
nowhere else. CLAIMANT’s activities are in Kronos, CLAIMANT’s operations are in
Kronos, CLAIMANT’s 200 employees are Kronians, CLAIMANT’s manager shareholders
25 Facts, p. 33.
26 Ibidem.
27 Fillers, p. 52.
TEAM ALFARO
9
are Kronians, CLAIMANT even passes part of its revenue to Kronos. Everything related
to CLAIMANT, beyond the place of its incorporation or administrative office, is in
Kronos. To complement that, CLAIMANT has absolutely no link with Ticadia, it has no
operation or any other activity in Ticadia - since it decided to shut down its operations
in that country and transfer all to Kronos - no Ticadian employees, nothing.
33. In conclusion, considering that CLAIMANT’s substantial business is in Kronos, it is duly
evidenced that CLAIMANT’s economic interest is related to Kronos and not even
remotely related to Ticadia. That situation set out a genuine link between CLAIMANT
and RESPONDENT, then, defines CLAIMANT’s nationality, since a genuine link is
required to test the nationality of a company.28 The fact that all the decisions taken by
CLAIMANT’s managers are implemented in Kronos’ territory and envisioning only
Kronos’ interests - and none of Ticadia’s - supports and reinforces the argument and
the Kronian nationality of the enterprise.29
II. CLAIMANT’S REQUESTS ARE NOT ADMISSIBLE BEFORE THE ARBITRAL TRIBUNAL
34. The present arbitral request and the motion filed by CLAIMANT are two sets of
proceedings addressing largely similar issues. Bearing that in mind, it should be taken
into consideration the fork in the road provision, which constitutes a barrier against
uncoordinated multiple proceedings and represents the intention of the signatories to
preclude investors from initiating treaty proceedings where previously only contractual
claims have been submitted.
35. In the next lines, RESPONDENT will demonstrate that the complaint CLAIMANT filed
before RESPONDENT’s courts cannot be pursued in this arbitration once it is essentially
the same as the lawsuit submitted in the Request for Arbitration. Furthermore,
CLAIMANT’s decision to seek relief before state courts is unquestionable and prevents
an Arbitral Tribunal from settling the dispute.
28 Okawa, p. 493.
29 Facts, p. 34.
TEAM ALFARO
10
i. The motion constituted a choice under the fork in the road provision
36. A fork in the road clause or electa una via is a common clause in Bilateral Investment
Treaties that serves to prevent multiple claims, once the parties’ choice to submit to
domestic courts or international arbitration is unique and irreversible30 and precludes by
treaty from bringing another set of proceedings in another forum.31 Exactly on these
grounds is the dispute settlement clause of the BIT between CLAIMANT and
RESPONDENT.
37. Article 11, Section 2 of the BIT provides that one of the parties concerned can choose
to submit the dispute for resolution to or domestic courts and administrative tribunals,
or arbitral tribunals.32 Moreover, the final choice represents the impossibility to pursue
the resolution in other court or tribunal.33
38. What occurs in the present case is that CLAIMANT clearly triggered the fork in the road
clause by filling a motion before RESPONDENT’s courts directly questioning the
Decree’s reasons and the impacts it supposedly caused on CLAIMANT’s activities.
However, not satisfied with the national pronouncement, CLAIMANT now seeks relief in
arbitration through a lawsuit that has essentially the same grounds discussed in the
national court and represents a double choice under the dispute settlement clause of the
BIT, which is not admissible.34
39. In light of this, RESPONDENT will demonstrate that the issues in respect of which
CLAIMANT seeks relief are essentially the same as the ones filed in RESPONDENT’s
courts and clearly represent an attempt to seek a second bite at the cherry.35
Consequently, CLAIMANT is precluded, by the fork in the road provision, from pursuing
his claims under the present arbitral tribunal.36
30 Emilio Agustin Maffezini v Kingdom of Spain, para 63.
31 Lim/ Ho/Paparinskis, p. 102.
32 BIT, p. 44.
33 Ibidem.
34 Ibidem, p. 37.
35 Pugachev v Russian Federation, para 28–29.
36 Ibidem, para 29.
TEAM ALFARO
11
a. The motion and the request for arbitration are essentially the same
40. In the fork in the road application, the essentiality of the actions is strictly linked to the
the identity of the disputes submitted to both domestic courts and international
arbitration37, once its main reason is to avoid multiple proceedings, preventing the
investor having numerous bites at the cherry.38
41. Under provisions of this kind, the lack of access to international arbitration applies only
if the same dispute was submitted to the domestic courts. However, it is important to
highlight that the disputes should not be necessarily identical, but in some way related
to the investment.39
42. Therefore, in order to determine whether the choice has been made, it is necessary to
verify an identity of parties, object, and cause of action40 between previous and
subsequent proceedings.41These criteria are known as triple-identity test and are
broadly used by the jurisprudence42 to verify the true application of the fork in the road
clause.43
43. Starting to analyze the mentioned criteria, RESPONDENT sustains that the two judicial
proceedings are essentially the same once the claims asserted in both of them directly
question the Decree’s reasoning and its impacts in CLAIMANT’s activities. In other
words, it is impossible to separate potential contract breaches from the BITs violations
as they are closely linked.
44. In the present case, both the BIT, more specifically in article 9, and the Agreement
signed by RESPONDENT and CLAIMANT settled environmental measures and regulations
in order to protect environment and promote health and safety of Kronos’ population.
37 Schreuer, pp.247–248.
38 Lim/ Ho/ Paparinskis, p. 102.
39 Muchlinski/Ortino/Schreuer, p. 849.
40 Wehland, pp. 86 - 93.
41 Chorzów Factory, Dissenting Opinion of Judge Anzilotti, para 23.
42 Ronald S Lauder v. The Czech Republic, paras 162–163; Occidental v Ecuador, paras 38–63; Compañía de
Aguas del Aconquija SA & Compagnie Générale des Eaux (Vivendi) v Argentine Republic, paras 40, 42, 53–
55, 81.
43 Durgan/ Rubins/ Sabahi/ Jr., p. 367.
TEAM ALFARO
12
Between the measures settled it is CLAIMANT’s obligation to operate sustainably, taking
the due precautions with the disposal of any waste of the exploitation.44
45. However, over the years, inspection reports have shown that the exploitation conducted
by CLAIMANT had a significant potential to cause environmental damages45 and since
2010, year that CLAIMANT concentrated its mining activities and resources in Kronos,46
the volumes of toxic wastes found in RESPONDENT’s river increased.47 Not just that, a
study conducted by the Kronian Federal University concluded that CLAIMANT has
failed to avoid contamination of the Rhea River48 and, consequently, blatantly failed to
fulfill its environment-related obligations, putting RESPONDENT’s environment and
population in danger.49
46. Therefore, facing the breaches of the Agreement and the BIT and the damages caused
by CLAIMANT’s misconducts, RESPONDENT unilaterally revoked CLAIMANT’s operating
licenses and terminated the Agreement through the Decree No 2424.50 In this context,
the Decree No 2424 was the basis of the discussion in the motion and it is in the present
lawsuit, once CLAIMANT sought to suspend it in order to avoid the revocations and now
discuss the damages caused by these acts.
47. Exactly in these terms, RESPONDENT sustains that this arbitral tribunal should follow
the understanding of the large majority of arbitral tribunals that define the identity of
the causes of action and object only where the claims asserted in both of them have the
same legal basis.51 That is the case of the CMS Gas Transmission v. Argentina,52
Vivendi v. Argentina,53 Middle East Cement v. Egypt,54 Occidental Exploration v.
44 Agreement, p. 47.
45 Case, p. 15.
46 Facts, p. 33.
47 Case, pp. 15 – 16.
48 Ibidem, p. 16.
49 Case, p. 52.
50 Ibidem.
51 Wehland, p. 93.
52 CMS Gas Transmission v Argentina, para 80.
53 Compañía de Aguas del Aconquija SA & Compagnie Générale des Eaux (Vivendi) v Argentine Republic,
para. 55.
54 Middle East Cement v Egypt, para. 71.
TEAM ALFARO
13
Ecuador55 and Pan American Energy v. Argentina56 where the Tribunals analyzed
claims’ fundament instruments in order to consider the difference of causes of action
and object.
48. Moreover, in the H&H v. Egypt57 case, the ICSID Tribunal, after analyzing the case
facts, concluded that the fork in the road provision was triggered once the treaty claims
had the same fundamental basis as the claims submitted before the local fora.
49. In that sense, the present discussion has essentially the same base, once the claims filed
by CLAIMANT in the national court essentially sought to avoid the end of his business
and the claims here in arbitration now seek compensation for termination of the
Agreement and the licenses and the alleged exploitation. The present lawsuit is barely
an extension of the Decree itself and cannot represent a different cause of action or
object.
50. Based on those grounds, the treaty claims are clearly based on a contractual violation,
which may trigger a fork in the road provision.58 Consequently, CLAIMANT is prevented
from bringing decree claims under the BIT’s dispute resolution clause once it had
previously relied on the Decree as a basis for its claims in RESPONDENT’s domestic
courts.
51. Following in this line, substantially the same claims are responsible from triggering a
fork in the road clause59 and prevent parties from bringing the same proceeding in order
to avoid potential conflict60 and the potential persuasive effect of a decision rendered in
the other forum.61
55 Occidental v Ecuador, paras 48–49.
56 Pan American Energy v Argentina, para. 157.
57 H&H Enterprises Investments, Inc. v Arab Republic of Egypt, para 56.
58 Chevron Corporation and Texaco Petroleum Company v Ecuador, para. 144.
59 McLachlan/ Shore/Weiniger, p. 89.
60 SPP v Egypt, paras 82, 88.
61 Hobér, p. 256.
TEAM ALFARO
14
52. Facing the identity of the instruments and the facts in the two sets of proceedings,62 it is
not possible to consider the distinction of the cause of action and object between the
proceedings brought by CLAIMANT.
53. Moreover, as CLAIMANT may sustain, the trigger of the fork in the road clause depends
on the identity of both plaintiffs and defendants in domestic and international
proceedings. Starting from this idea, RESPONDENT argues that in the present case the
parties are the same and no special denomination can change the identity of it.
Fenoscadia Limited and the Republic of Kronos are strictly the same parties in both
national and arbitration procedures and even have the same positions as CLAIMANT and
RESPONDENT.
54. However, even if this Tribunal understands that the formal party identity is not a
request under the fork in the road clause, once it would undermine the main reason of
the clause,63 CLAIMANT sustains that the attempt to distinguish parties by self-giving a
different title (investor) constitutes a desperate tentative and is not a proper tool to
prevent the triggering of the provision, characterizing a bad faith action.64
55. In that sense, RESPONDENT sustains that this arbitral tribunal should consider the
position taken in the Vivendi v. Argentina annulment decision case65 when facing
similar problems. The decisions of the ICSID Tribunal focused in the object and the
cause of action of the proceedings to determine the application of the fork in the road
provision, instead of focusing in the strict identity of the parties.66
56. For all that has been said, it is possible to understand that the two instruments are
essentially the same, once the parties requests, objects and causes of action are similar
and, consequently, do result in triggering the ‘fork in the road’ provision. However, if
the arguments about the triple-identity test do not seem sufficient to move away the
admissibility of the present arbitration, facing CLAIMANT’s choice to discuss the case in
62 Wegen/Markert, p. 554.
63 Suarez Anzorena, p. 24; Compañía de Aguas del Aconquija SA & Compagnie Générale des Eaux (Vivendi) v
Argentine Republic, para 55.
64 Commerce Group Corporation and San Sebastian Gold Mines Incorporated v El Salvador, para 137.
65 Compañía de Aguas del Aconquija SA & Compagnie Générale des Eaux (Vivendi) v Argentine Republic,
paras 55, 105 and 113.
66 Wehland, p. 91.
TEAM ALFARO
15
the national courts, the present claims should have been discussed in the State Court
once it does not constitute a provisional measure.
b. The present claims should be discussed in RESPONDENT’s courts once it
was not a provisional measure
57. RESPONDENT sustains that CLAIMANT’s possible argument that the motion filed in
RESPONDENT’s courts was an interim measure is an attempt to internationalize a
domestic dispute and, thus, the Tribunal is not the appropriate forum to decide this
request. Moreover, the motion do not fulfill the requirements for granting interim
measures.
58. According to Tallim v. Estonia case67, the arbitration tribunals must rely on five
requirements, recognized internationally68, for granting interim measures: (i) prima
facie jurisdiction; (ii) prima facie existence of a right susceptible of protection; (iii)
necessity of the measure; (iv) urgency; and (v) proportionality.69 These five elements
must be met to grant any interim measure70 and that is not the case.
59. Regarding the element of prima facie jurisdiction and existence, CLAIMANT’s choice to
pursue its claims in RESPONDENT’s national courts establish the prima facie jurisdiction
of the National Tribunal and the attempt to discuss it again in arbitration would
constitute a bad faith action and an attempt to give a second bite at the cherry.71 As for
prima facie existence of a right susceptible of protection, no reasonable possibility of
success on the merits of CLAIMANT’s claims are present once the expropriation was
based on CLAIMANT several misconducts and breaches of the BIT72 and the
Agreement.73
67 United States (Tallim) B.V. and Aktsiselts Tallinna Vesi v Republic of Estonia.
68 Sergei Paushok, CJSC Golden East Company, CJSC Vostokneftegaz Company v The Government of
Mongolia, para 40; Paushok and Others v Mongolia, para 40.
69 United States (Tallim) B.V. and Aktsiselts Tallinna Vesi v Republic of Estonia, para 78.
70 Pugachev v Russian Federation, para 60.
71 Ibidem, para. 68.
72 BIT, p. 43.
73 Case, p. 47.
TEAM ALFARO
16
60. Regarding the necessity of the measures, according to the Tokios Tokelés case74, the
interim measures seek to avoid an irreparable prejudice to the right involved. For
irreparable prejudice the jurisprudence75 understands as a harm or prejudice that cannot
be remedied or compensated by monetary damages.
61. In that sense, the UNCITRAL Tribunal, in Sergei Viktorovich Pugachev v The Russian
Federation76, held similar comprehension when decided that the necessity standard was
not satisfied once the harm claimed was not irreparable given it can be compensated by
monetary damages and there is no sufficient evidence to conclude that the civil
proceedings would worsen the present dispute.
62. The lack of necessity in the motion is based exactly on these grounds, once the harm
claimed is reparable since it can be compensated by monetary damages.
63. Analyzing the urgency requirement, RESPONDENT sustains that CLAIMANT’s act to
withdraw the motion77 do not express the urgency of the situation once he decided to
discuss its extension in an arbitration tribunal almost one year after the alleged
expropriation acts78. The content and prevailing circumstances suggest that there is
simply no urgency for the Provisional Measures sought.79
64. For all that has been said, it is clear that CLAIMANT has failed to establish that all the
five requirements for granting interim measures are met in the present case.80
Consequently, facing no changing circumstances from the two procedures, CLAIMANT
must be precluded from seeking a further bite of the apple.
74 Tokios Toheles v Ukraine, para 132.
75 Pugachev v Russian Federation, para 99; Plama Consortium Limited v Republic of Bulgaria, para 46;
Quiborax v Bolivia, para 156.
76 Pugachev v Russian Federation.
77 Case, p. 7.
78 Facts, pp. 36 - 37.
79 PNG Sustainable Development Program Ltd v Papua New Guinea, para 32.
80 Ibidem, para 25. Born, pp. 3787–3790.
TEAM ALFARO
17
III. THE TRIBUNAL HAS JURISDICTION OVER RESPONDENT’S COUNTERCLAIM
65. To establish jurisdiction under a counterclaim, the Tribunal has to determine (i) the
consent between the parties to assert counterclaim and (ii) the connectedness with the
primary claim and the counterclaim. Additionally, it becomes necessary for the
Tribunal to analyze (iii) the benefits that comes with a counterclaim, as it brings several
benefits to the procedure and render efficiency to the investor-state arbitration.
66. In light of this, RESPONDENT will demonstrate that the present counterclaim is in
conformity with these fundamental requirements, thus the Tribunal should admit the
counterclaim.
i. The wording of the BIT indicates that the parties consented with the
counterclaim
67. Arbitration is based on the will of the parties81 and consent represents their intentions
for the possibility, or not, to assert counterclaim.82 In the present case, the Tribunal
should assert jurisdiction since the parties’ intention was to allow counterclaims.
68. Article 11 (5) of the BIT83 established that it would not be acceptable to assert
counterclaim in certain situations. However, RESPONDENT’s counterclaim does not fall
under the exceptions of such clause. Therefore, if the parties excluded the possibility to
enter with counterclaims in specific situations, it means that the parties` intention was
to allow counterclaim in all the remained scenarios.
69. Hence, if the instrument excludes a specific category of counterclaims, it is presumed
that other counterclaims are allowed.84 Whether the parties’ intention was to prohibit
counterclaims all together, they would have inserted in the BIT.
70. Although international investment is asymmetrical, states can - and have - brought
counterclaims against the investors when its requirements are presented85. Hence, the
81 Cordero-Moss, p. 211, para. 2.
82 Musayev, p. 7.
83 BIT, p. 44.
84 Hamida, p. 224.
TEAM ALFARO
18
parties’ intention was clearly to permit counterclaims and RESPONDENT has the right to
file counterclaims.
71. The Dispute Settlement clause86 established that a dispute between the state and the
investor will include an investment agreement, an investment authorization or an
alleged breach of any right conferred or created by the Agreement. Therefore, the
Arbitration Agreement is a broader clause that includes the present counterclaim as the
environmental damage is a breach of a right conferred by the Agreement. In Sempra87
the tribunal decided to extend its jurisdiction to judge counterclaim in issues resulted in
breaches of the treaty. Moreover, a broader arbitration agreement can extend a
tribunal’s jurisdiction to judge a counterclaim.88
72. This broad dispute, with a similar language, is also present in US-Estonia BIT and
Belgium–Luxembourg–Burundi BIT, which consider to include disputes concerning
not only divergent conduct by the State, but also by the investor89. Thus, if the dispute
resolution is broad, the tribunals are more likely to allow counterclaims90, as it was held
by several tribunals91.
73. Furthermore, a broadly arbitration agreement is related to the inclusion of investor’s
obligations that allow to assert a counterclaim92. In this view, in Al Warraq v
Indonesia93, the tribunal allowed a counterclaim once the BIT imposes obligations
under the investor and this was considered as permission to the State assert
counterclaim.
85 Schwebel, p. 3.
86 BIT, p. 44.
87 Sempra Energy International v Argentine Republic, para. 289.
88 Saluka, para. 50.
89 Kjos, p. 135.
90 Kryvoi, p. 216.
91 Iran-U.S. Claims Tribunal (IUSCT), International Center for Settlement of Investment Disputes (ICSID)
tribunals, and United Nations Commission on International Trade Law (UNCITRAL) tribunals.
92 Kjos, p. 135.
93 Al Warraq v Republic of Indonesia, para. 663.
TEAM ALFARO
19
74. In the present case, the BIT contains obligations to both parties94, consequently it is
possible to RESPONDENT assert a counterclaim. Unless expressly excluded by the
Arbitration Agreement, the tribunal jurisdiction extends to counterclaims.
75. In the recent Perenco95 case, the tribunal permitted the State to assert a counterclaim
against the investor. The counterclaim was related to alleged environmental
contamination, an alleged breach of its obligations under domestic environmental law,
and was accepted by the tribunal. The exact same situation occurred in the present
dispute, since RESPONDENT asserted the counterclaim based on the compensation for
the damages caused by CLAIMANT in the environment, mainly through the
contamination of the Rhea River.96
76. Moreover, the omission in the BIT to exclude all counterclaims and the possibility to
allow counterclaims in SCC means that this Tribunal has jurisdiction. In that sense, the
Tribunal should understand that by applying rules of an arbitral institution and not
making any reservations, the parties also agree to submit counterclaims.97
77. Article 9 of the SCC Rules allows counterclaims. Since it explicitly and unambiguously
permits the filing of counterclaims, it is an indication that the parties already consented
to allow counterclaim when they chose this chamber.98
78. Therefore, the intention of the parties to allow counterclaims are present and this
Tribunal has jurisdiction.
ii. The primary claim and the counterclaim are connected
79. The connection between the counterclaim and the principal claim is an imperative
requirement to evaluate the counterclaim99, being a requirement that also defines the
94 Article 9 and 10 of the BIT, p. 43.
95 Perenco Ecuador Ltd v. Republic of Ecuador.
96 Case, p. 16.
97 Dissident opinion in Roussalis v Romania.
98 Al-Warraq v Indonesia, para. 664.
99 Farmer, p. 14
TEAM ALFARO
20
jurisdiction over such dispute100. In the present case, RESPONDENT’s counterclaim has
connection with the primary claim.
80. CLAIMANT's primary claim is that the Decree issued by RESPONDENT breached Article 7
of the BIT by expropriating its investment.101 Considering that the State’s environment
counterclaim is based on compensation for damages by a result of CLAIMANT’s
exploitation of lindoro that arose from article 9 (2) of the BIT102, the relationship
between the claim and the counterclaim is fulfilled.
81. In Saluka103, the tribunal decided that “legitimate counterclaim must have a close
connection with the primary claim to which it is a response”. Furthermore, in
Klöckner104 the decision emphasised the necessary connection with matter of the
counterclaim and the matter of the principal claim, defined as “indivisible” and
“interdependent”.
82. Moreover, in Urbaser105 the tribunal decided it had jurisdiction to judge the
counterclaim. The tribunal justified the decision by stating that a factual link between
original and ancillary claims is sufficient to give jurisdiction to the tribunal. In this
case, a merely factual link is clearly present.
83. In Desert Line106 case the tribunal identified the connection between the counterclaim,
which was based in damages for the party’s violation of its obligations, and the primary
claim, that was based in contractual breaches of road construction contract.
84. Hence, as the primary claim and the second claim are in connection with the
exploration of lindoro, this Tribunal should allow counterclaim in accordance with the
jurisprudence that recognize the connection in similar cases.107
100 Atanasova/Benoit/Ostransky, p. 26.
101 Case, p. 8.
102 Case, p. 16.
103 Saluka v Czech Republic, para. 61.
104 Klöckner v Cameroon, para. 65.
105 Urbaser et al. v The Argentine Republic, para. 1151.
106 Desert Line v Yemen.
107 SGS v Pakistan, para. 108; SGS v Philippines, para. 40.
TEAM ALFARO
21
iii. The benefits that comes with counterclaims highlight the reasons for this
Tribunal to accept it
85. The acceptance of counterclaims also brings various benefits108 to the procedure,
making the investor-State arbitration more efficient, in according with the principles of
arbitration.
86. The counterclaim brings procedural efficiency, once the complex facts developed in the
course of the arbitration in the treaty claim would be also relevant to the domestic law
claims.109 In that way, the judgement of related claims in the same agreements would
enhance the dispute time for the parties.110 A rejection to analyse the counterclaim
could result in a duplication of proceedings, inefficiency, and increased transaction
costs.111
87. Thus, CLAIMANT’s conducts to discharge the counterclaim is controversial and totally
contrary to the efficiency of this proceeding. CLAIMANT decided to withdraw the main
claim from the state courts jurisdiction to enter in the arbitral jurisdiction112, however,
now refuses to discuss the entire matter in the arbitration, arguing that the parties
should return to the state court to discuss the counterclaim. This act in controversial and
disconnected as the reasons to CLAIMANT opt to a arbitration procedure are similar to
the argues that this arbitral Tribunal has to allow the counterclaim.
88. Moreover, to consider a primary claim and a counterclaim in the same setting
guarantees a more coherent decision and better results, which would not be insured in
case of separate review of those claims.113 It would render a more clear and predictable
doctrine about the scope and application of investment rights.114 Therefore,
108 Bjorklund, p. 475.
109 Goetz v Burundi, para. 279.
110 Kryvoi, p. 220.
111 Roussalis v Romania, para. 206.
112 Facts, p. 37.
113 Musayev, p. 6.
114 Susan D. Franck, p. 5.
TEAM ALFARO
22
counterclaims avoid further appeal to litigation, seeking justice in the same fora the
investor chose in the first place.115
89. In Goetz116 the tribunal admitted its jurisdiction over counterclaims. Their reasons
relied in efficiency, centralization of inquiry, avoiding duplication, impasses from
attempted jurisdictions against parallel proceedings and the irony of forcing the State
back to local courts.
90. Add to that, a counterclaim would affect the whole cost-benefit calculus of the
procedural, as it would also influence issues in relation with the third part funding. For
this reason, allowing counterclaims recalls the beneficial effects of procedural economy
and the better administration of justice.117
91. Furthermore, a joint decision from the primary claim and the counterclaim will
guarantee a consistent result for both claims, which could not be possible with a
separate review of those claims.118 In the Burlington119 case, a environmental
counterclaim was allowed by the tribunal, once the parties agreed that a counterclaim
would bring a judicial economy and consistency.
92. Hence, if it is this Tribunal understanding that CLAIMANT should be considered as an
investor under the BIT, and that the fork in the road clause was not triggered by the
lawsuit filed before RESPONDENT’s state court, it should be also held that this Tribunal
has jurisdiction to judge this counterclaim, as it fulfills the fundamental requirements of
a counterclaim, as well as brings several benefits to this procedure, since it renders
efficiency to the investor-State arbitration.
115 Guido Carducci, pp. 66/67.
116 Antoine Goetz and others v Republic of Burundi.
117 Kjos, p. 137.
118 Musayev, p.6.
119 Burlington Resources Inc. v Republic of Ecuador, para. 60.
TEAM ALFARO
23
ARGUMENTS ON THE MERITS
IV. RESPONDENT ACTED IN ACCORDANCE WITH ARTICLE 6 OF THE BIT
93. CLAIMANT may argue that RESPONDENT did not act in accordance with the fair and
equitable treatment provisions (hereinafter “FET”) contained in the BIT. However, it
will be demonstrated that RESPONDENT did act following the FET provisions to the
extent possible, taking into consideration the scope of the clause and the possible
grounds for a fair and equitable treatment breach claim.
i. RESPONDENT did not breach the fair and equitable treatment standard
a. The BIT defines fair and equitable treatment as the Minimum Standard of
Treatment
94. In order to define the scope of protection granted by the BIT, it is essential to consider
that the choice of words plays a significant role in demonstrating the intention of the
parties as well as the objectives and purposes of the treaty.120 Thus, it is indispensable
for this Tribunal to consider such choices when interpreting the BIT clauses.121
95. At the moment the Contracting Parties decided to include a FET provision in the BIT
defining the standard of treatment of aliens “in accordance with the customary
international law”122, they demonstrated their intention of restricting the scope of the
fair and equitable treatment clause.
96. Once the variations of the FET clause are crucial in the task of detecting the scope of
application and the due interpretation to be given, it is necessary now to define the
consequences of the FET clause in the BIT being bound to the customary international
law.
120 Vienna Convention on the Law of Treaties, Article 31.
121 Methanex v United States, para. 29.
122 BIT, p. 41.
TEAM ALFARO
24
97. The customary international law refers to rules and principles originated from a general
and consistent States’ practice that they follow from a sense of legal obligation.123 This
process of construction and development is slow, which means that the content of a
FET clause grounded in customary international law is unlikely to evolve rapidly.124 It
is not the same that occurs with an autonomous FET clause, which is more vague and
subjective.
98. The latter does give room for a broader debate, inviting to elaborate a series of rules
and include other principles linked to fairness, such as protection to arbitrary conduct,
legitimate expectations, and stability of the legal framework.125 However, an expansive
FET clause interpretation may result in an open-ended and unbalanced approach, which
favors investor interests and overrides legitimate regulation in the public interest126,
especially in a situation where the scope of fair and equitable treatment is well-defined,
such as in the present case.
99. As to the threshold of liability applied by arbitral tribunals, it has been generally higher:
following the Neer127 case, the State’s conduct needs to be egregious or outrageous.128
Although RESPONDENT recognizes that the understanding of what is egregious has
evolved since the 1920s, a reference to the minimum standard of treatment of aliens in
a FET clause conveys a clear message that only the very serious acts of
maladministration can be seen as violating the treaty.129
100. After recognizing the distinction between autonomous FET clauses and those linked to
customary international law, NAFTA tribunals have understood that the latter
"necessarily lead their tribunals to analyze custom"130. CLAIMANT may allege that the
MST has evolved, but it is necessary to demonstrate custom - established and repeated
123 Shaw, p. 810.
124 OECD, p. 13.
125 Ibidem, p. 14.
126 UNCTAD, p. 11.
127 L.F.H. Neer and Pauline Neer v United Mexican States.
128 UNCTAD, p. 13.
129 Ibidem,.
130 Glamis Gold v USA, para. 606.
TEAM ALFARO
25
state conducts131 - highlighting that arbitral awards do not constitute State’s practice
and cannot create customary international law.132
101. While the requirements to transform specific rules and principles into custom are not
reached and proved by CLAIMANT, the fundamentals of the Neer standard still apply
today133: to violate the customary international law minimum standard of treatment, it
is necessary to demonstrate a gross denial of justice, manifest arbitrariness, lack of due
process, evident discrimination, or a manifest lack of reasons — so as to become
inconsistent with accepted international standards.134
102. Consequently, by restricting the FET-MST clause to international customary law, this
Tribunal must make a narrow interpretation of the fair and equitable concept, such as
other tribunals did in similar cases. As defined by the S.D. Myers135 tribunal, a breach
of FET under the international customary law would only happen when the host state’s
conduct rises to a level that is unacceptable from the international perspective.
103. The Waste Management136 tribunal stated that a breach of FET under such
circumstances only happen if the host state acts in an “arbitrary, grossly unfair, unjust
or idiosyncratic” way. In the Thunderbird137 case, the understanding was that the
explicit use of MST makes the threshold of a FET violation-based claim remains high,
thereby restricting the scope of the FET standard.
104. By that, many consequences that arise from the interpretation of FET as an autonomous
standard do not exist in the present case. There are concepts, especially the legitimate
expectations, which are not referred to in actual FET provisions - they are considered
“arbitral inventions”.138 Consequently, such concepts cannot be applied in the present
dispute.
131 UNCTAD, p. 27.
132 Glamis Gold v USA, para. 605.
133 Ibidem, para. 616.
134 Ibidem.
135 S.D. Myers v Canada, para. 263.
136 Waste Management v United Mexican States, para. 98.
137 Thunderbird v United Mexican States, para. 194.
138 UNCTAD, p. 9.
TEAM ALFARO
26
b. CLAIMANT’s legitimate expectations were not in accordance with Kronos’
scenario
105. Although already demonstrated that a mere non-corresponding to expectations cannot
be sufficient to find a breach of the minimum standard of treatment139, it will also be
demonstrated that CLAIMANT’s expectations have no basis and are not reasonable or
justifiable. Even though RESPONDENT contends that a legitimate expectation claim
could not exist in the present case once this Tribunal is dealing with an MST-FET
clause, it is necessary to demonstrate why such claim could not prevail.
106. It is convenient for CLAIMANT to allege that a State's legitimate regulation in the public
interest violates its expectations. The issuance of the Decree, based on the KEA, was a
measure entirely into the sovereign powers of States. In Morris140, after the CLAIMANT
started an arbitral proceeding due to new tobacco-control legislation enacted by
Uruguay’s new president, the tribunal stated that "protecting public health has since
long been recognized as an essential manifestation of the State’s police power".
107. Being a quintessential manifestation of states’ sovereignty, any expectation raised from
this kind of regulatory measures is unfounded.
108. CLAIMANT may argue that RESPONDENT did not respect its legitimate expectations
towards the investment. To make such allegations, CLAIMANT would have to sustain
that it had a legitimate expectation that its rights would not be regulated or restricted in
any way.141
109. A level of expectations on the part of the investor is correlated with the investment
environment in the host country. The content of such expectations should always be
adapted to the level of development of the host country.142 Moreover, favorable
business conditions and goodwill are transient circumstances, subject to inevitable
change.143
139 Glamis Gold v USA, para. 620.
140 Philip Morris v Uruguay, para. 291.
141 UNCTAD, p. 149.
142 Ibidem, p. 14.
143 Oscar Chinn Case, para. 88.
TEAM ALFARO
27
110. Kronos is an underdeveloped country that, at the time the investment was made, didn’t
have any environmental legislation that could affect CLAIMANT’s business.144 However,
it must be seen that the increasing environmental awareness of many governments
around the world indicates that measures created for these purposes will only grow.145
One of the factors to be taken into consideration when arguing legitimate expectations
is the investor’s obligation to have a general awareness of the environment it was
operating.146 Not only that, but the BIT contained provisions regarding environment
protection and awareness.147
111. In Methanex v United States148 the tribunal decided that, since governmental
environmental and health protection institutions, at federal and state level, had been
continuously monitoring the impact of the chemicals used in the CLAIMANT’s business,
then it could not argue that an eventual ban would be a breach of its legitimate
expectations. RESPONDENT continuously monitored CLAIMANT’s activity; moreover, the
Nationalist Party always demonstrated its high commitment to its environmental
agenda.149
112. Although no legislation existed by the time Fenoscadia made its investment, even
though the idea of FET and legitimate expectations itself imply in a stable legal and
business framework150, it should not evolve into an overly-broad and unqualified
formulation.151 As stated by the EDF152 tribunal, FET does not mean the virtual
freezing of legal regulation of economic activities. An investor cannot rely upon a BIT
as an insurance policy against the risk of any changes in the host state’s legal
framework - such expectations would not be legitimate or reasonable.153
144 Facts, p. 33
145 J. Marlles, p. 275.
146 UNCTAD, p. 27.
147 BIT, p. 43.
148 Methanex v United States of America, para. 10.
149 Facts, p. 34.
150 UNCTAD, p. 76.
151 Saluka Investments v Czech Republic, para. 110.
152 EDF v Romania, para. 217.
153 Ibidem, para. 221-237.
TEAM ALFARO
28
113. In Parkerings-Compagniet154 it was held that, since Lithuania was an underdeveloped
country in political transition, the investor should have regarded changes in the
legislative regime as possible, and, that in such situation, no expectation that the laws
would remain unchanged would be legitimate - this is exactly the situation that
CLAIMANT was on. RESPONDENT was going through a radical government change after
another party took office after the Liberal Party ruled for almost 60 years.
114. The presidential statements that CLAIMANT relies on did not, in fact, mention that no
regulation would ever exist.155 The then president of Kronos only asserted that the
country would support the company and that Fenoscadia’s good results would benefit
the Kronian economy.156 Thus, such statements are not sufficient to create legitimate
expectations.
115. In the Saluka157 case, it was decided that the host state’s right to regulate domestic
matters should be taken into consideration as well and that a breach of FET would have
to be determined by weighing of the investor’s legitimate expectations and the state’s
legitimate regulatory interests. The tribunal then came to the conclusion that, as far as
state-implemented policies can affect the investor’s interests, if it is justified by public
policies and does not manifestly violates international customs a breach of the
legitimate expectations did not happen.
116. In the present case, what this Tribunal must consider is Kronos’ scenario. The country
saw itself in a health crisis, with the activities of a foreign company seriously affecting
its population and generating damage that is already estimated to an amount of 150
million dollars.158 Any expectation that regulatory action would not be taken in such
situation cannot be regarded as legitimate or reasonable.
117. Undoubtedly, an investor can - and will - have legitimate expectations regarding its
investment. However, arbitral tribunals cannot find a violation of FET based on
legitimate expectations without taking into consideration the actual regulatory,
154 Parkerings-Compagniet v Lithuania, para. 335-336.
155 Case, p. 53.
156 Ibidem, p. 49.
157 Saluka Investments v Czech Republic, para. 112.
158 Case, p. 17.
TEAM ALFARO
29
economic, social and political context the host stated finds itself in.159 It would be
unreasonable for this Tribunal to place CLAIMANT’s legitimate expectations above
RESPONDENT’s right to regulate in an emergency situation such as the one it saw itself
on - hence, any possible legitimate expectations claim should be dismissed by this
Tribunal.
V. THE PRESIDENTIAL DECREE NO 2424 IS NOT EXPROPRIATORY
118. Contrary to CLAIMANT’s arguments, RESPONDENT’s actions did not result in the
indirect or direct expropriation of Fenoscadia’s investment. Not every single state
conduct that leads to economic harm to the investor or deprives it of its own investment
can be considered expropriatory.160
119. In order to determine whether expropriation happened, there are a series of factors that
must be analyzed: the impact of the measure and its duration, the extent to which the
measure breaks the investor’s legitimate expectations, and the nature, purpose and
character of the measure.161 In the present case, it will be demonstrated that
RESPONDENT’s conducts could not, at any moment, be regarded as expropriatory.
120. As previously stated, not every measure that leads to the economic loss or deprivation
can be considered as expropriatory. In the CME162 case, the tribunal held that indirect
expropriation only occurs when a State takes deliberate acts that “effectively neutralize
the benefit of property of the foreign owner”. The GAMI Investments163 tribunal held
that the affected property must be impaired to such an extent that it must be seen as
taken.
121. In the present case, this Tribunal is not dealing with a measure directed at a specific
party that intends to undoubtedly take possession of the investment, but a legislation
preventing any kind of lindoro exploitation. This means that the Decree did not aim to
undermine CLAIMANT’s business or hold control of Fenoscadia, but to regulate and
159 UNCTAD, p. 77.
160 Ibidem, p. 68.
161 Ibidem, p. 57.
162 CME v Czech Republic, para. 150.
163 GAMI Investments v United Mexican States, para. 126
TEAM ALFARO
30
temporarily stop all possible lindoro mining. RESPONDENT made it clear that the
measures were not permanent, with Kronos being open to the possibility of CLAIMANT
re-initiating its activities in the country.164 Moreover, the Kronian government does not
hold control over CLAIMANT’s facilities.
122. As stated by the Tecmed165 tribunal, measures adopted by a state cannot be considered
as an “indirect de facto expropriation” if they are reversible and temporary. A similar
conclusion was reached by the S.D. Myers166 tribunal, which decided that the orders
issued by the Canadian government did intend to curb SD’s initiative, but only for a
certain time, and thus no expropriation had happened. In the Suez167 case, it was
decided that unless measures constitute substantial and permanent deprivation, they
cannot be considered expropriatory.
123. Regarding the legitimate expectations, as already demonstrated, these were not harmed
by RESPONDENT’s acts. Therefore, another expropriation criterion has been dismissed.
124. The nature, purpose, and character of the measure will be analyzed further on,
demonstrating that it was a good faith regulatory act, based on RESPONDENT’s police
powers, done lawfully and pursuing public purpose.
i. RESPONDENT’s actions are within its police powers
125. First, it is crucial to clear out that states can make good faith use of its police powers in
order to make restrictions upon activities held on its territory168 in order to guarantee
the prevalence of public interest and the welfare of its population. Investment treaties
should not restrict a state's right to regulate.169
126. Police powers, in a narrower perspective, refer to measures that a government can take
to justify a state action that would otherwise amount to a compensable deprivation or
164 PO2, pp. 56-57.
165 Técnicas Medioambientales Tecmed v United Mexican States, para. 116.
166 S.D. Myers v Canada, paras. 287-288.
167 Suez et al. v Argentina, para. 129
168 Newcombe/Paradell, p. 15.
169 UNCTAD, p. 80.
TEAM ALFARO
31
appropriation of property.170 It allows the state to act in protection of essential public
interests from certain types of harm.
127. The regulatory conduct of states must carry a presumption of validity.171 There is
nothing within the language of BITs that purports to undermine the permanent
sovereignty of States over their own territories and economies.172 Prima facie, a lawful
exercise of powers of governments may affect foreign interests without amounting to
expropriation.173 Moreover, the BIT determines that host States must “strive to
minimize harmful environmental impacts occurring within its territory”.174
128. Although a state’s regulatory measure in order to protect the environment, health and
safety of the population will frequently impose regulatory and compliance costs at an
investment, these will normally not reach the threshold of substantial deprivation175, as
of even the non-compliance of the state with contractual obligations is not understood
as equivalent to expropriation.176
129. This is exactly what happened in the present case: CLAIMANT would have to bear the
costs of its own harm in order to keep and continue operations in Kronos, a burden that
Fenoscadia refused to accept.
130. In order to comprehend the fundamentals of the measure, it will be necessary to
examine the involved public purpose.177 As the present dispute treats about the
impugnment of a democratically elected government’s action, it becomes necessary to
analyze the context in which the measure was enacted.
131. Considered as an underdeveloped country and with little to none environmental
regulations178, Kronos turned out to be an ideal host for any mining company seeking
profit. After a few years passed, being the past administration a major supporter of
170 Newcombe/Paradell, p. 26.
171 UNCTAD, p. 80
172 Lowe, p.4.
173 Brownlie, p. 352.
174 BIT, p. 43.
175 Newcombe/Paradell, p. 357.
176 Waste Management, Inc. v United Mexican States, para. 175.
177 LG&E v Argentina, para 251.
178 Facts, p. 32-33.
TEAM ALFARO
32
lindoro exploitation, it is not straightforward to assume that the people of Kronos
noticed the sudden increase of diseases in the region179 and sought for the change of
government.
132. The claim that a recently elected administration with parliament majority would not act
in conformity with the public interest should be dismissed, as the importance of
maintaining the health of the population is far more important than the profit made with
the exploitation of lindoro, and the state must comply with this humanitarian policy in
respect with international customary law itself.180
133. Even if considered the highly unlikely possibility in which only the affected population
was against the exploitation of lindoro, the public interest can still be claimed by even a
fraction of the community.181
134. To deny the motivating public purpose would be to benefit the investor with the sole
effects doctrine unilaterally,182 that determines that the motive behind the regulation be
worthless,183 observing just the effects caused on the investor’s property.
135. This bias would allow the impunity of the investor, as it generates no side effect for the
pollution performed leading to an easy profit at the expense of the responding state.184
The prevalence of the sole effects doctrine would prevent regulation in public health
and environmental protection185 disregarding the necessity of proactive regulation and
protection of natural essential interests that surpass criteria of optionality.186
136. In the S.D. Myers187 case, it was held that, when determining whether expropriation
happened or not, it was crucial to look at the real interests involved and the purpose and
effect of the governmental measure. Along the same lines, the LG&E188 tribunal
179 Case, p. 51.
180 Methanex v USA, para. 7.
181 Sooraram Pratap Reddy & Ors. v Distt. Collector, Ranga Reddy, para. 67.
182 Dolzer, p. 122.
183 Nykomb Synergetics v Latvia.
184 Odumosu, p. 345.
185 Van Harten, pp. 91-92.
186 Suez InterAgua v Argentina, para 238.
187 S.D. Myers v Canada, para. 281-285.
188 LG&E v Argentina, para. 170.
TEAM ALFARO
33
decided that there must be a balance in the analysis of both of the causes and effects of
a measure in order to qualify it as expropriatory or not.
137. There are State measures which do not constitute expropriation under international law,
such as essential regulations aiming to secure the welfare of the community and
therefore are non-compensable - even if they reach the level of total deprivation.189
138. The Presidential Decree No 2424 was created exclusively aiming at protecting the
health of Kronian nationals and the country’s environment and natural resources.
Consequently, the enactment of the Decree is within RESPONDENT’s police powers, and
cannot be treated as expropriatory.
ii. The Presidential Decree No 2424 is a non-compensatory regulation
139. Contrary to CLAIMANT’s requests, RESPONDENT’s measures are not to be considered
expropriatory, but rather a non-compensatory regulation. The state’s right to regulate is
well recognized under the customary international law190, as it would be practically
impossible to maintain a functioning state if every legislative change lead to the
compensation of the affected.191 It has long been accepted that a state act under its
police powers is not subject to compensation.192
140. Governments do not owe compensation for a non-discriminatory bona fide
regulation.193 To be declared as discrimination it is necessary to prove different
treatments to different parties194. However, in the present case, the Presidential Decree
No 2424 prohibited lindoro exploitation from all present and future companies,
therefore not targeting CLAIMANT, as the purpose was to cease the environmental
damages caused by the exploitation.
189 UNCTAD, p.72.
190 LG&E v Argentina, para. 195; Saluka v Czech Republic, para. 306.
191 Pennsylvania Coal Co v Mahon, p. 260 U.S. 413.
192 UNCTAD, p. 78.
193 Suez InterAgua v. Argentina, para. 128.
194 ADC v Hungary, para. 442.
TEAM ALFARO
34
141. Moreover, the bona fide regulation is affirmed as for there to be an indirect
expropriation the state should have taken a teleologically driven action or have profited
from it195, not applying to this dispute, as Kronian citizens lost jobs and the state lost a
large source of profit in order to protect the environment from the consequences of
lindoro exploitation.
142. Furthermore, the measure taken by RESPONDENT did not meet the criterion of
appropriation to recognize an expropriation196 as it respected the legislation and aimed
for the public benefit.197
143. One of the factors evaluated to declare an expropriation is the duration of the
measure198, which was temporary, as RESPONDENT had agreed to negotiate the
exploitation if CLAIMANT admitted its responsibility on the damages.199 CLAIMANT
rejected the offer and fourteen months after the emission of the Decree entered with
requests to arbitrate in the SCC.200 Similarly, the tribunal in S.D. Myers201 understood
that not even eighteen months were enough to demonstrate an indirect expropriation, as
the state had not benefited.
144. Tribunals such as Methanex202 and Saluka203 have reached the conclusion that,
according to international law, non-discriminatory regulation that follows a public
purpose and is enacted in accordance with due process and ends up affecting, inter
alios, a foreign investment is not deemed to be compensatory and expropriatory unless
very specific commitments have been made by the host state and the investor can
undoubtedly rely on such commitments. Both tribunals have also agreed that general
regulations made within the state’s police powers are not compensable.
195 Eudoro Armando Olguín v Republic of Paraguay para. 84; Ronald S. Lauder v The Czech Republic para.
203.
196 OECD Indirect Expropriation, p. 3.
197 Mugler v Kansas, 123 U.S. 623 (1887).
198 Telenor Mobile Communications A.S. v The Republic of Hungary para. 70.
199 PO2, pp. 56-57.
200 Facts, p. 37.
201 S.D. Myers, Inc. v. Government of Canada, para. 287.
202 Methanex v United States of America, IV D, para. 7.
203 Saluka v Czech Republic, para. 262.
TEAM ALFARO
35
145. Even tribunals with a more rigid approach, such as Azurix204, decided that, even though
public purpose alone cannot fully justify non-compensation, such criterion aligned with
proportionality and non-discrimination would ultimately remove the state’s
responsibility to compensate the investor.
146. This Tribunal could consider that the mere fact that a measure regards the protection of
the environment does not provide a justification for non compensation, which was the
rationale followed by the tribunals in Tecmed205 and Metalclad206 - but this is not the
case at stake. None of such cases dealt with urgent matters that put human health at
risk, such as the present one. When an investment can result in the threat of the
population’s life, a ban can result in the complete destruction of the investment and still
no compensation is due.207
147. It has been generally concluded that the right to compensate does not exist when it
would arise from reasonably necessary regulations passed for the protection of public
health, safety or welfare.208 As decided by the Saluka209 tribunal, states are not liable to
pay compensation for good faith regulations aimed at general welfare.
148. By the arguments presented RESPONDENT demands that this Tribunal recognizes the
bona fide regulation performed by the government - otherwise CLAIMANT would be
rewarded with a large compensation for jeopardizing the well being of the inhabitants.
iii. General exceptions are provided in article 10 of the BIT
149. Hereby it will be presented RESPONDENT’s full compliance with the BIT and customary
international law. Firstly, as the signed BIT materialized the undisputable principle of
the right of regulation210 in its article 10 stating the acceptable general exceptions that
204 Azurix Corp. v The Republic of Argentina, para. 310.
205 Técnicas Medioambientales Tecmed v United Mexican States.
206 Metalclad v United Mexican States.
207 Newcombe/Paradell, p. 35.
208 Ibidem, p. 23.
209 Saluka v Czech Republic, para. 147.
210 Técnicas Medioambientales Tecmed v United Mexican States, para. 119.
TEAM ALFARO
36
should be taken in consideration to protect the well being of the region or to avoid
being inconsistent with the principles of customary international law.211
150. A breach of contract can be characterized as extraordinary action adopted by a
contracting party to surpass a provision.212 As of this case, RESPONDENT utilized of its
police powers in compliance with the article 10, not going beyond the contracting
parties rights neither abusing its sovereignty.
151. The general exceptions can only be employed when the action does not rely on
arbitrary means, discrimination or the breach of an international restriction. The
concept of arbitrary measure is drawn as an optional activity that does not contain a
purpose to sustain it213, which, as previously mentioned, does not apply to the present
case.
152. Likewise, the discriminatory claim is not to be considered as the limitation fit in the
general national plan of regulation of industries, and had no punitive character directed
to particulars.214 As there are no national companies that exploit the mineral215, there
would be no benefit of the discrimination for the state.
153. Moreover, in order to determine a discriminatory measure it is necessary to observe the
causality of the action, where its non-existence would benefit both parties216 - not
applying to the present case, as the Decree No 2424 was essential to protect the citizens
of Kronos from the pollution caused by the exploitation.
154. With both parties being signatories of the Vienna Convention217, RESPONDENT had no
choice but to terminate the agreement as the circumstances presented violated the basis
of the consent of the parties.218
211 BIT, pp. 43-44.
212 Siemens v Argentina p. 248.
213 Azurix Corp. v Argentina, para. 392.
214 Donald F. Rieger Jr. p. 174.
215 Facts, p. 32.
216 Konrad von Moltke, p. 4.
217 Facts, p. 32.
218 Vienna Convention on the Law of Treaties.
TEAM ALFARO
37
155. Therefore, the usage of the article 10 was fair and necessary as otherwise RESPONDENT
would be obliged to breach either the BIT or a human rights convention, as both would
be conflicted.219
156. CLAIMANT may argue that the Decree was unconstitutional. However, as seen in the
case file, it is a responsibility of the Speaker of the House to determine whether a
public hearing is necessary or not;220 in the present case, it was decided that there was
no need to hold such hearings. This attitude can be easily understood when analyzing
the urgent situation Kronos was passing through.
157. The measure was indispensable not only to comply with customary international law
and the BIT, as prevented accusations of environmental discrimination221, in which the
state by supporting the investment would continue to assist a harmful entity against the
people in the region. Thus, a scenario where RESPONDENT could maintain the
exploitation without regulating does not exist given these extraordinary repercussions.
158. Microcephaly is a rare disease that affects one newborn each several thousands and has
no specific treatment.222 In recent years there has been a surprising growth of this
condition in the areas surrounding the Site, as a study shown that 88% of the examined
newborns have presented indications of microcephaly, even though this particularity
was practically nonexistent until 2012.223
159. As an acknowledged environmentalist-focused administration, the Nationalist Party
won the presidential elections in 2014 and had to proceed to repair the environmental
legislation that was neglected by past governments. It needed to act fast, given the
urgency of the matter, therefore not being obliged to send a formal notice to the other
party.224
219 Suez InterAgua v Argentina, para. 240.
220 Facts, p. 35.
221 Steve Lerner.
222 World Health Organization.
223 Case, p. 51.
224 UNCTAD p. 40.
TEAM ALFARO
38
160. To deny the significance of the general exceptions is to invite the leading advantage of
the investor in an arbitral dispute, as it facilitates the justification for a failed business
based on the right to regulate, freely undermining the state’s sovereignty.225
VI. CLAIMANT IS LIABLE TO PAY COMPENSATION FOR THE ENVIRONMENTAL
DAMAGES CAUSED IN RESPONDENT’S TERRITORY
161. Since already demonstrated that the counterclaim is admissible before this Tribunal, the
merits of the claim must be discussed. Not only RESPONDENT complied with all of its
prerogatives, as it becomes crucial to notice the counterpoints that lead to the present
case. Henceforth it will be demonstrated the aftermath of CLAIMANT’s violations of the
BIT leading to the justified termination of the Agreement.
162. Tribunals tend to agree that environmental stewardship is of great importance in
today’s world and, if a legal relationship between a state and an investor results in
environmental damage, the state is then entitled to receive full compensation for such
damages.226
163. It must be taken into consideration that Kronos is an underdeveloped country and the
estimated costs for cleaning the Rhea River already reach USD 75 million.227
164. It becomes disproportionate to acknowledge RESPONDENT’s intentions as oppressive,
based on the fact that when the lindoro exploitation begun there were virtually zero
regulations besides the Agreement.228 For that reason, the consequence of the
exploitation could not have been foreseen leading to a strong yet necessary regulation.
165. It is, from a while, common ground to both parties that metal exploitation and mining
are hazardous activities that inherently put the environment at risk. Accordingly,
companies that exercise such activities must guarantee a very high standard of care in
their operations, especially when operating in environmentally fragile areas.229
225 Peterson, p. 3.
226 Perenco Ecuador v Republic of Ecuador, para. 34.
227 Case, p. 51.
228 Facts, p. 33.
229 Perenco Ecuador v Republic of Ecuador, para. 37.
TEAM ALFARO
39
RESPONDENT had been monitoring CLAIMANT’s activities since 2011 and is aware that
lindoro exploitation could potentially cause environmental harm from then.230
However, RESPONDENT could not impose restrictions to CLAIMANT’s activities until the
enactment of the KEA.231 Not only that, but as it can be seen from the presidential
statements made by the former government and the background story of Fenoscadia’s
development in Kronos, it can be assumed that environmental protection was not a
worry for the previous administration.
166. It was within CLAIMANT’s responsibilities to be aware that graspel, the toxic metal
disposed in lindoro exploitation, is harmful to human health. As it is stated in the case
files, there is a recent development in a series of global studies demonstrating that such
metal can be linked to the rise of cardiovascular diseases.232 Moreover, the study
conducted by the Kronian Federal University demonstrated a connection between
lindoro exploitation and Kronos’ recent health crisis233 - therefore demonstrating the
causal nexus between CLAIMANT’s wrongful act and RESPONDENT’s damages.
167. RESPONDENT contends for the polluter pays principle234, which determines that the
responsible for the harm is also the one to bear with the reparation costs, whether it had
the intention to cause such harm or not.235 With CLAIMANT not recognizing its
responsibility, the community would have to bear the costs of the pollution, being
inconsistent with the principles of sustainable development.236
168. The polluter-pays principle is predicted in the BIT237 and, furthermore, in
RESPONDENT’s own regulation, explicitly in the KEA238. It is also predicted in the
Water Convention, which both parties are signatories239 - even though it is not applied
230 Case, p. 15.
231 Ibidem.
232 Ibidem, p. 50.
233 Ibidem, p. 51.
234 United Nations.
235 Preston.
236 Ibidem.
237 BIT, p. 43.
238 PO2, p. 57.
239 Facts, p. 32.
TEAM ALFARO
40
in the present case, since the Rhea River is not transboundary, it clearly demonstrates
that both Ticadia and Kronos adopt environmental-friendly policies.
169. Therefore, RESPONDENT’s conduct to demand payment for the environmental damage
caused by Fenoscadia is in full compliance with the BIT and Kronian regulations. It
would be unreasonable for this Tribunal to accept that CLAIMANT starts an arbitral
proceeding based on the same BIT it now demands RESPONDENT to breach.
170. Moreover, considering that CLAIMANT initiated arbitral proceedings based on supposed
BIT breaches by RESPONDENT, it can be expected that Fenoscadia was aware of the
provisions regarding the polluter-pays principle.
171. CLAIMANT was negligent with its conducts and the effects they could produce in the
environment and, consequently, in the Kronian population. As demonstrated in the case
file, Fenoscadia did not embrace any corporate social responsibility standard in its
practices and internal policies240, going against a clear international trend. The
adherence to CSR represents the company’s intention to act in an ethical and
transparent way, contributing to the health and welfare of the society.241
172. Moreover, the concept of international corporate social responsibility (hereinafter
“ICSR”) goes beyond the idea of adopting environmental-friendly policies and ethical
codes of conduct. It may be considered to rest on the obligations that companies owe to
the societies in which they operate.242 This can be furthermore based on the concept of
a “social contract” and the need of all the agents, including non-state agents, to observe
the preservation of human dignity through adherence to fundamental human rights.243
173. Investments cannot enter a country as if there was no society or community there.
Consequently, their activities will have impact whether for good or ill.244 Companies do
240 PO2, p. 57.
241 Castka/Balzarova, p. 10.
242 Muchlinski/Ortino/Schreuer, p. 640.
243 Donaldson, p. 378.
244 Muchlinski/Ortino/Schreuer, p. 638.
TEAM ALFARO
41
not operate in the vacuum - their relationship with the society and the environment they
operate on is a critical factor to measure their capacity to operate efficiently.245
174. Corporations may build in a corporate social responsibility project into their plans.
However, not doing so may cost them a change in the order of social and political
activities in which they develop their investment in.246
175. It must be pointed out that, even though RESPONDENT does not apply the strict liability
concept in its domestic legislation247, it would be nearly impossible to fully
demonstrate that CLAIMANT acted in negligence or bad faith. Moreover, by asserting an
environmental counterclaim, RESPONDENT has the burden of proving that Fenoscadia’s
activities resulted in an environmental effect that exceeded the applicable regulatory
limits.248 However, this Tribunal must consider that, until the enactment of the KEA,
RESPONDENT’s environmental regulation was virtually non-existent.
176. The Perenco Ecuador249 tribunal dealt with a similar situation: the country made a
counterclaim regarding environmental legislation breaches and the strict liability was
considered inapplicable in the case. The tribunal decided, however, that it was
unacceptable for it to allow that the company simply argued that “a spill” happened
during normal course of business and it could not be liable unless it were proved that
negligence occurred. It also came to the conclusion that regulatory exceedance can be
considered evidence of operational failure and, consequently, evidence of fault.
177. Consequently, this Tribunal should follow the same rationale - even if it considers
RESPONDENT’s regulation too strict or in exceedance, it is merely the demonstration of
CLAIMANT’s operational failures that consequently led to the necessity of drafting the
KEA.
178. Although CLAIMANT argues that it is not responsible for the pollution and the health
costs that RESPONDENT had to bear, mere allegations that it was acting in good faith and
did not have knowledge of any possible harm it was causing are not sufficient to
245 ISO 260000.
246 Muchlinski/Ortino/Schreuer, p. 641.
247 PO2, p. 57.
248 Perenco Ecuador v Republic of Ecuador, para. 45.
249Ibidem, para. 374.
TEAM ALFARO
42
exclude its liability. Once the polluter-pays principle is a clear part of Kronos and
Ticadia governmental policies and legal frameworks, this Tribunal should grant
RESPONDENT’s counterclaim requests.
PRAYERS FOR RELIEF
179. In light of the above submissions, RESPONDENT respectfully requests this Tribunal to
find that:
(i) CLAIMANT is not an eligible investor under the 1993 Ticadia-Kronos BIT;
(ii) CLAIMANT’s request is not admissible as the fork in the road clause was triggered by its
previous motion in RESPONDENT’s state court;
(iii) RESPONDENT’s counterclaim is admissible;
(iv) RESPONDENT acted in accordance with Article 6 of the BIT;
(v) The Presidential Decree n. 2424 did not expropriate CLAIMANT’s investment;
(vi) The counterclaim must be granted in the merits, considering CLAIMANT’S liability to pay
for the environmental damages it caused in Kronos.
COUNSELS FOR THE RESPONDENT
TEAM ALFARO
24 SEPTEMBER 2018.