TBWGToronto, Ontario
November 18, 2008
GSA Project Update
Projects in Construction
1. Calais, Maine
2. Jackman, Maine
3. Champlain, New York
4. Massena, New York
5. Warroad, Minnesota
6. Portal, North Dakota
7. Blaine (Peace Arch), Washington
Jackman, Maine
• Progress is at 53%• Project is ahead of the
scheduled July 2010 completion
• Close coordination with MTQ concerning highway alignment
• Close coordination with Hydro Quebec concerning three phase power
Calais, Maine
• Progress is at 60%• Estimated completion is
November 2009• Additional funding in 2009
required to maintain scheduled completion date
• Discovery of significant ledge at time of construction start
Champlain, New York
• Cargo Facility Completed in 2007
• Administration building completed in 2008
• Overall Project completion December 2008
• Project delivered on time and within budget
Massena, NY
• Progress is at 57%• Estimated completion is
October 2009• Project is within budget• Project included
reconstruction of a traffic circle
• Close coordination with NYSDOT
Warroad, Minnesota
• Progress is at 10%• Estimated completion is
January 2010• Significant wetlands in
the vicinity• Port facilities will be
located about a mile south of boundary
Portal, North Dakota
• Progress is at 19%• Estimated completion is
September 2011
• Remaining funding will be available in 2009
• Construction of ancillary facilities will occur in 2009
Peace Arch, WA
• Progress is at 10%• Estimated completion is
August 2010• Additional funding
required in 2009 to maintain schedule
• Crossing will be operational for 2010 Olympics
Out-Year Construction
1. Derby Line, Vermont (2009)
2. Alexandria Bay, New York (2010)
3 Madawaska, Maine (2011)
Derby Line, VT
• Design award is pending
• Site adaptation will be utilized to expedite project
• Construction start planned for 2009
• Completion 2011
Alexandria Bay, New York
• Design is underway• Conceptual stage is
complete• Significant site/civil work• Construction start is
planned for 2010• Completion 2012
Madawaska, Maine
• Design is underway• Concepts under
development• Inspection facilities will be
remote from the bridge landing
• Construction start is planned for 2011
• Completion 2013
Other LPOE Projects
1. Lewiston, NY (NFBC)
2. Peace Bridge – Buffalo, NY (PBA)
3. New International Crossing – Detroit (MDOT)
4. Blue Water Bridge – Port Huron, MI (MDOT)
Questions?
Thank You