TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750...

14
TB Flats and Ekola Flats Wind Projects Wyoming Energy Summit 23 May, 2018

Transcript of TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750...

Page 1: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

TB Flats and Ekola Flats Wind Projects

Wyoming Energy Summit

23 May, 2018

Page 2: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Invenergy Company Introduction

TB Flats Wind Project

2

Page 3: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Quick Facts

112large-scale

projects

17,353megawatts

$25B+ capital raised

900+ employees

3

Page 4: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Broad Expertise

We develop, own and

operate large-scale

renewable and other clean

energy generation and

storage facilities in North

America, Latin America,

Japan and Europe.

* As of January 5, 2018; includes projects that are

operating, in construction or contracted.

Renewables include wind, solar and storage.

Natural Gas

10 projects

5,519 MW

Wind

83 projects

11,349 MW

Solar

13 projects

391 MW

Advanced Energy Storage

6 projects

94 MW

4

Page 5: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Extensive Reach

Wind

Solar

Natural Gas

Advanced Energy Storage

Regional Office

Corporate Headquarters

* As of January 5, 2018; includes projects that are operating, in construction

or contracted. Renewables include wind, solar and storage.

5

Page 6: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

370 390 460 800

1,570

3,380

4,2604,450 4,680

5,6406,050

6,780

8,830

9,98010,464

17,353

Gross Total MW

Natural Gas Renewables

Sustained Growth

Invenergy has

developed projects

totaling more than

17,300 megawatts.*

* As of January 5, 2018; includes projects that are

operating, in construction or contracted. Renewables

include wind, solar and storage.

6

Page 7: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

TB Flats and Ekola Flats Wind ProjectsSummary

➢ 750 Megawatts

➢ Up to approximately 300 Wind

Turbines, depending on turbine

technology

➢ Planned turbine types are Vestas

V-136 4.2MW and Vestas V-110

2.0MW. Estimated 134 turbines.

➢ Access roads, underground

collection lines, O&M Building,

Project Substations, overhead

230kV generation-tie lines and

permanent met towers

➢ Located adjacent to Dunlap Wind

Project and Seven Mile Hill Wind

Project, near Medicine Bow

➢ Currently targeting a Q2 2019

Construction Start Date

➢ Currently targeting a Q4 2020

Commercial Operations Date

➢ Developing in partnership with

PacifiCorp / Rocky Mountain

Power

➢ Planned to transfer ownership to

PacifiCorp / Rocky Mountain

Power prior to construction

7

Page 8: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Regional Wind Summary

Rawlins Medicine Bow

Laramie

Casper

TB Flats

Ekola Flats

Page 9: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Site Photos

Page 10: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

PacifiCorp’s Energy Vision

2020

Page 11: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Development Timeline

2009 First meteorological towers erected

2015 Interconnection requests submitted

2016 Land signed, development underway

2017 Sign Development Transfer Agreement with PacifiCorp

Open Houses in Hanna and Medicine Bow

Response to PacifiCorp’s System-Wide Request for Proposals Submitted

2018 Open houses in Medicine Bow, Rawlins, and Laramie

Conditional Use Permit Applications submitted

Projects selected as Development Transfers as part of PacifiCorp's Energy Vision 2020

Wyoming Industrial Siting Division Permit Applications Submitted

2019 PacifiCorp and contractors begin Construction

2020 Turbine Deliveries and Installation

Commercial Operations and project completion

Page 12: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Economic Benefits to Carbon County

➢ $30-45 million dollars in local sales and use taxes during two years of construction

➢ $6-7 million dollars in annually property taxes, beginning in 2021 (reducing annually over

time)

➢ $2.4-$2.7 million dollars in annual Wyoming Wind Excise Taxes

➢ A total of approximately $245 million dollars in total taxes to Carbon County and Wyoming,

much of which will stay in the County, over a 30-year project life

➢ An average of approximately 480 construction jobs, and 30-40 full-time permanent positions

during operations

➢ $3-5 million in annual landowner payments, increasing over time

➢ An estimated $50-70 million will be injected into the Carbon County economy over the

construction period in addition to direct construction expenditures

Page 13: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Letters of Support

The TB Flats Project has received letters of support from the following

entities:

➢ Town of Medicine Bow

➢ Town of Hanna

➢ The Historic Virginian Hotel, Medicine Bow

➢ WLC Engineering, Rawlins

➢ Hampton Inn, Rawlins

➢ Carbon County Economic Development Corporation

➢ Wyoming Infrastructure Authority

➢ Hanna Hometown Market, Hanna

➢ Vet Chefs, Hanna

➢ The Manly Store, Hanna

➢ Q Creek Land & Livestock Company

➢ Rawlins National Bank

➢ Oftedal Construction

➢ EconoLodge, Rawlins

➢ Timberline Hospitality, Rawlins

➢ Best Western Cotton Tree, Rawlins

Page 14: TB Flats and Ekola Flats Wind Projects...TB Flats and Ekola Flats Wind Projects Summary 750 Megawatts Up to approximately 300 Wind Turbines, depending on turbine technology Planned

Contact Information

14

Krista Mann

Director, Renewable Development

Phone: (303) 800-9335

Email: [email protected]

Company Information:

www.invenergyllc.com