TB Clinic Project Report

2
Project Fact Sheet Project Name: TB clinic Location: C Block Stage: Construction Sponsor: Carol Gillen Programme Manager: Mike Veale Project Manager: Alessandro Annunziata Director of Estates: Phil Ient Project Update: Project to be completed in April 2014 In Defects until April 2015 Project Brief: In 2011 North Central London Commissioning group stated its intentions that the provision of non-inpatient adult TB services would be reviewed and the feasibility of rationalising and relocating the Royal Free Hospital, UCLH and Whittington TB services to form one centralised service would be explored. The new service will deliver joint working with RFH and UCLH to deliver a collaborative approach to provide the newly commissioned service. Construction works to create adequate clinical areas and storage spaces for effective delivery of services. Structural alteration Heating installation & Mechanical ventilation Hot and cold water services Concrete flat roof insulation New fire smoke detectors Energy efficient windows and new roof lantern New CCTV and security magnet lock New IT infrastructure New Tube System Construction Project Team: Project Manager: Alessandro Annunziata Cost Consultant/QS/CM/Drawings CAD Love Jenkins Associates Lead Designer Alessandro Annunziata Main Contractor Storm building limited M & E Engineer Alessandro Annunziata Electrical SubContractor LSG Structural Engineer n/a Mechanical SubContractor Power Base Project Facts & Figures: Budget: £ 1.1 million Funding Source: Capital Construction Project Programme: Start on Site: January 2014 End Date: April 2014 Occupation Date: end April 2014 For further information contact Capital Project Manager - Eur Ing Alessandro Annunziata email: [email protected] - tel. 020 7288 5394

Transcript of TB Clinic Project Report

Page 1: TB Clinic Project Report

Project Fact Sheet

Project Name: TB clinic

Location: C Block

Stage: Construction

Sponsor: Carol Gillen

Programme Manager: Mike Veale

Project Manager: Alessandro Annunziata

Director of Estates: Phil Ient

Project Update:

• Project to be completed in April 2014

• In Defects until April 2015

Project Brief:

In 2011 North Central London Commissioning group stated its intentions that the provision of

non-inpatient adult TB services would be reviewed and the feasibility of rationalising and

relocating the Royal Free Hospital, UCLH and Whittington TB services to form one centralised

service would be explored.

The new service will deliver joint working with RFH and UCLH to deliver a collaborative

approach to provide the newly commissioned service.

Construction works to create adequate clinical areas and storage spaces for effective delivery

of services.

• Structural alteration

• Heating installation & Mechanical

ventilation

• Hot and cold water services

• Concrete flat roof insulation

• New fire smoke detectors

• Energy efficient windows and new

roof lantern

• New CCTV and security magnet lock

• New IT infrastructure

• New Tube System

Construction Project Team:

Project Manager: Alessandro Annunziata Cost Consultant/QS/CM/Drawings CAD

Love Jenkins Associates

Lead Designer Alessandro Annunziata Main Contractor Storm building limited

M & E Engineer Alessandro Annunziata Electrical SubContractor LSG

Structural Engineer n/a Mechanical SubContractor Power Base

Project Facts & Figures:

Budget: £ 1.1 million Funding Source: Capital

Construction Project Programme:

Start on Site: January 2014 End Date: April 2014 Occupation Date: end April 2014

For further information contact Capital Project Manager - Eur Ing Alessandro Annunziata

email: [email protected] - tel. 020 7288 5394

Page 2: TB Clinic Project Report

TB Clinic – Project information This project consists of the refurbishment of an empty store into a new tuberculosis clinic.

The architectural and engineering design has been focused on the potentiality of the

property to maximize energy efficiency and sustainability, reducing building’s energy

consumption over its lifetime.

Lighting is essential for human health and well-being because it determines our circadian

rhythm, influences our mood and changes the atmosphere around us.

The main characteristics of this project are as follows:

� The natural lighting has been explored to provide the best possible solution for

utilising daylight through the replacement of the existing roof lantern, keeping high

ceiling and fitting a new skylight to create a tunnel of the light from the pitch roof;

� Internal windows into the corridor spreads natural light into the internal rooms that

are disadvantaged being without windows;

� Natural ventilation during the summer without using air-conditioning;

� New Air Handling Unit provides mechanical ventilation and dilute tuberculosis

bacteria inside the clinic and eliminate the risks of contamination of clinical staff;

� The Sputum induction room is a safe area for clinical staff because it has the

highest rate of air extraction and it is isolated from other ductworks;

� Improvement of the fabric of the building with new insulation of the flat roof and of

external walls to save energy during the winter and avoid the installation of air-

conditioning to cool the clinic during the summer;

� Temperature of all the rooms are electronically controlled by thermostatic sensors

providing heating or activating natural ventilation opening the windows of the roof

lantern;

� Rain sensor closes the windows of the roof lantern automatically in the event of the

rain;

� The artificial lighting design enhances the natural light and the ambient illumination.

All the down light luminaires are high efficiency LED lamps, Low-glare and

maintenance-free with an extremely long life of 30,000 hours;

� The decorative luminaires and the ceramic tiles in the reception and in the corridor

creates spectacular effects and guides the patient inside the clinic eliminating the

classic hospital and medical environment;

� The reception and the waiting area give the visitors their first impression of the TB

clinic and contribute to the Whittington Hospital`s brand image. The two arches has

been restored as the original design creating a new point of view walking through

the main corridor. The reception desk has been designed as a curved shape in

white high tech surface (Corian) to give a warm welcome to the public and is

friendly for wheelchairs users;

For more information, to give feedback and users’ perspectives and therefore to progress

the design and delivery of future buildings thus enhancing designers’ knowledge, please

contact

Eur Ing Alessandro Annunziata Salerno Construction Consulting Engineers Ltd

MEng(Hons) Dott.Ing. CEng MICE for Project Management and Design Management Capital Project Manager [email protected] tel. 020 7288 5394