TAXIWAY ALPHA REHABILITATION
Transcript of TAXIWAY ALPHA REHABILITATION
TAXIWAY ALPHA REHABILITATION
Ashton B. Watson, P.E., C.M., ACE
Airport Engineer
Pavement Management Plan
Pavement Management Plan
Capital Investment Program
Consultant Selection and Negotiation
• RFQ for General Engineering Services
• Pool of firms to chose from
• Scope and Fee
• Geotech, Surveying, Utility locates, Design,
Bidding, Electrical, SRM, Construction
Admin, Materials Testing
• Independent Fee Estimate
• Negotiation
• Procurement and City Council Approval
• Above is about 9 month process
Design Schedule
Intersection Geometry of TWY A,G,R
*Hot Spot 1
Other Design Considerations
• Shoulders
• Asphalt vs. Concrete
• Future Concourse and Ramp Expansion
• Underdrains
• Lighting systems
• Regulator at East Lighting Vault
• 2.5% Longitudinal Taxiway Grade
• Modification of Standards
• Oil-Water Separators
Other Design Considerations
Construction Safety and Phasing Plan
Safety Risk Management (SRM) Workshop
• Foreign Object Debris/Damage
• Contractor Vehicle Deviation/Loss of Situational
Awareness
• Pedestrian Loss of Situational
Awareness/Pedestrian Deviation
• Pilot Loss of Direction/Pilot Confusion
• Debris damage tow workers and equipment
caused by jet blast
• Head-to-Head taxiing aircraft at AAL Maintenance
Ramp
Safety Risk Management (SRM) Workshop
Safety Risk Assessment (SRA) Workshop
Public Contact
• Closing 5/23 as a runway
• Press Release and Council Manager Memo
• Coordination with FAA, AAL, FedEx, UPS
• 7460 Permits
• NCDENR
Value Engineering
• Original Estimate = $12,534,360
• Bid Opening = $13,454,449
• Negotiated Price = $12,823,949 (2.3% over)
• Value Engineering Items:
• Contractor Retain Millings
• Cement-Treated Base instead of P-403
• Liquid AC type: PG64-22 instead of PG76-22
• Removal of Glasgrid Interlayer
UPS Change Order