TASK AND CLIENT INFORMATION App 6... · Web viewDuring the diving phase of the operation the Diving...
Click here to load reader
Transcript of TASK AND CLIENT INFORMATION App 6... · Web viewDuring the diving phase of the operation the Diving...
Inshore Diving Operations ForCanals and River Trust
Diving Operation Risk and Method Statement
Example
CRT No: Client:Project: ExampleRevision:Date: xx/xx /2016
QUALITY ASSURANCEAmendments
Date Revision Amendment Prepared by
Checked by Approved by
Prepared for Review PB
Copyright & Confidentiality
The information contained within this document is provided for the sole use of employees of Bridgeway Consulting Ltd, authorised clients and subcontractors. All rights are reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, magnetic tape, mechanical, photocopying, recording or otherwise without permission of Bridgeway Consulting Ltd. Printed copies of this document are considered as uncontrolled.
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
Table of Contents
1 TASK AND CLIENT INFORMATION......................................................................................................32 DIVING INFORMATION........................................................................................................................... 43 DIVE PLAN............................................................................................................................................... 54 METHOD STATEMENT........................................................................................................................... 85 RISK ASSESSMENT............................................................................................................................. 106 EMERGENCY ARRANGEMENTS.........................................................................................................137 INDUCTION AND BRIEFING: CHECKLIST..........................................................................................168 CHANGE 0F RECORD........................................................................................................................... 179 Appendix A Dive Hazard Plan (Found in Site Pack)...........................................................................18
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
1 TASK AND CLIENT INFORMATION
Client Date
Canals and River Trust xx/xx/2016
Task DescriptionBrief Description of the Task:
Information Supplied by Canals and River TrustService information packHazard planAP-002
Site Hazards Identified By Canals and River Trust
DIVER ENTRAPMENT - Underwater obstructions may be present at the dive site including sluice door and chamber
UNDERWATER OBSTRUCTION(S) - If underwater obstruction(s) are found they will be identified and if possible removed to a safe place, if they cannot be removed easily the size and dimensions will be recorded and the dive plan altered so the diver will not become snagged up in any way.
ACCESS TO THE WATER – Is via slipway or folding ladder from towpath.
MOORED BOATS – All staff to be on there best behaviour language to be controlled noise kept to a minimum.
LOW VISIBILITY - Underwater visibility is likely to be poor
BIOLOGICAL CONTAMINATION - Leptospirosis and other waterborne pathogens may be present. Contaminated sharps may also be present at the site. Full dry suits and gloves are to be worn by divers. Barrier cream and hot water washing facilities will be available in the welfare van.
BOATING ACTIVITY – Navigation will be open, Leisure vessels use this site. All staff to keep a good lookout for vessel movements.
DEBRIS - Debris may be present on or below the water surface.
ACCESS TO SITE – Direct Public access to into the car park
Client Contact Details
Permits Issued By BCL Permits Issued by Client
Yes
Information about the Work SiteDive Vehicle Access – North of the village of Pewsey on the A345 Park in car park of the Waterfront public
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
House. Nearest Post Code is: SN9 5NT.
Diver Access – will be by towpath wall and ladder freeboard less than 0.5m
Remember a fully kitted diver must not climb ladders over 2.0m and generally freeboard up to 0.5m is accepted suitable for manual recovery of an unconscious diver. Freeboard over 0.5m will require a means of mechanical assistance for the recovery of an unconscious diver.
2 DIVING INFORMATION
Supervisor Team SizeFive
Dive Location Vessel N/A
Diving SystemHSE Compliant SSDE Mobile Dive Spread
Helmet TypesKM 27 Hard Hat and KMB 28 Band Mask
Support Plant RequiredHand Tools only
Tools and EquipmentMeasuring ToolsCement Mixer
Emergency Plan PreparedYes
Diver/Access/ Egress/Recovery Specialist PPE Required
Aluminium Ladder/Slipway Life jacket, PPE As per BCL Rules
BCL Comments /Notes
All personnel must adhere to the BCE PPE policy whilst on site. A Flags and warning Boards to be placed prior to any works commencing...
On Site ChecklistItem Description of Task Completed? Action By
1. Barrier the area around the dive control All Personnel2. TBT on site about known hazards All Personnel3. Set up SSDE All Personnel4. Carry out PMS All Personnel
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
5. Pre dive function test, Dress diver to perform operation All Personnel6. Carry out diving as per instruction below All Personnel7. Debrief The diver and check all information given All Personnel8. De Mobilise, Clean Equipment, load equipment in a safe
and orderly fashion, clear area All Personnel
9. Sign divers logbooks and complete dive log Dive Supervisor
3 DIVE PLAN
Main Task SummaryThe following operations will be conducted.
1. The diver will swim the length of the area to be inspected looking for possible snags or trip hazards.
2. The diver will inspect the determined area of wall 160m.
3. A report will be compiled on the diver’s findings.
Note:During the diving phase of the operation the Diving Supervisor will keep notes of all findings.
During the diving operations the CRT representative will be given verbal updates on findings as the project progresses.
Site DetailsDive Site Access –
Special Site Controls Required (From Client information) (ACoP Ref 27, a-h)Full PPE including Life jackets
Team Size and Responsibilities (ACoP Ref 32a) (ACoP Ref 76-78)Five
Dive Supervisor, The Diving Supervisor is responsible for all diving operations at the site and shall ensure that the procedures referred to in this method statement are implemented and that accurate records of all operations are maintained throughout
Diver,The Diver reports to the Diving Supervisor. He is not only responsible for performance of his duties in a safe and professional manner but also for the wellbeing of his colleagues. No action on his part should jeopardise either his own safety or that of those personnel associated with his work.The Diver represents the Company while in employment with BCL and must conduct himself properly at all times. He must comply with safety requirements and confine any grievances, complaint or criticism to his immediate Supervisor, or BCL Project Manager.Stand by Diver,
A Stand-by Diver is a qualified diver whose role is to provide assistance to the diver or divers in the water in an emergency.Consequently:
He should know the emergency procedures. He should follow, from the beginning, the communications between the Diving Supervisor and the
Divers.
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
He must be ready to intervene immediately.
Tender x 2The Tender is answerable to the Dive Supervisor. He is responsible for all general duties involved with the operation other than those performed by specialist personnel.It should be understood that the term Tender does not imply that a person designated as such is not a qualified diver nor does it mean that he can dive.
Site Hazard Summary (ACoP Ref 32b)As per risk assessment, Tool Box Talk prior to operations to be performed, The Supervisor to access the area to ensure safe to operate. Canals and River Trust informed hazard locations are shown in Canals and River Trust Hazard plan located in Task Order Brief and Appendix A..
Intended Diving Methods (ACoP Ref 39)Full surface supplied with communications. Stand by diver in immediate state of readiness dressed in.
Suitability of Air Supply (ACoP Ref 46, 61 and 62)The breathing medium for this diving operation will be compressed air.
The diver’s air supply will be supplied from the LP compressor and all the ancillary back up supplies as previously stated. The maximum anticipated depth will be no more than 10m.
The final delivery pressure will be monitored, by the Dive Supervisor, at the dive panel located at the Dive Control.
The standby diver will be supplied with an independent air supply to the working diver.
The diver’s gases will be constantly monitored for delivery pressure from the dive panel located in dive control.
Bail Outs
All divers will wear a ‘bailout’ cylinder charged with compressed air. All bailouts will be fully charged, function tested and the contents reported to the Dive Supervisor.
The in water diver will be periodically requested to check their bailout pressures and report the reading to the Dive Supervisor to ensure that there is no leakage through the side block into the helmet.
Emergency Decompression Arrangements (ACoP Ref 48 and 110-115)Mr. Dave Alcock – Operations Manager. (Murryfield) (0151) 648 8000
Nearest Chamber is:-Whipps Cross Hyperbaric Unit, University Hospital London. Tel:07740 – 251635.
Weather and Currents (ACoP Ref 49-52) (Site and Day Specific)The Diving Supervisor will review the weather conditions and assess the suitability for the commencement of operations, in particular, deployment of the diver. This shall be recorded in the dive/daily logAny discharges/intakes are to be isolated where possible
Specialist Equipment (ACoP Ref 54-60)
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
Hand tools only.
Access, Egress, Recovery Plan (ACoP Ref 39)Access is to be gained to the dive site via the ladder which will be secured to a bollard or suitable area.Recovery – in an emergency the diver is recovered via towpath less than 0.5m.If this is not possible use of a work flat, or davit arm and Jason’s Cradle will be used to recover the diver. For areas where the walls are high a two man riding basket and crane will be used.
Site Specific Issues
Plant and Equipment (ACoP Ref 93-109)Plant and Equipment Lists as below
Item Qty Description BCL/Vessel/Client/Hire
1Kirby Morgan 27B Superlite helmet c/w communications, first stage regulator, bail out whip, contents gauge and whip for diver one.
BCL
1 DSI 28B Bandmask c/w communications, first stage regulator, bail out whip, contents gauge and whip for standby diver. BCL
2 One hundred metre umbilical consisting of air, communications and pneumo for diver one and standby diver. BCL
1 Two diver LP Air Control Panel complete with separate supplies for diver, standby diver and reserve. BCL
2 AR vest recovery harnesses c/w lead weights and ten litres, 232 Bar Working Pressure Bail Out Bottles. BCL
2 Air storage cylinders. Thirty litres – 200 bar working pressure cylinders. BCL
2 Gas – Arc Hi flow regulators to reduce air from HP to LP at source. BCL
1 35cfm LP Air Compressor. Petrol compressor with two stage filtration for breathing air BCL
As Rqd Suits, knives, fins, gloves etc. BCL
As Rqd
PPE consisting of hard hats, coveralls, high visibility waistcoats, ear protection and eye protection. BCL
As Rqd
Consumable items including vehicle and compressor fuel, tape for umbilical’s, rope etc. BCL
1 Tool box and spares kit. BCL1 Oxygen Resuscitator, First Aid Kit. & Rescue stretcher BCL1 Mobile dive control BCL
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
Diving Supervisors Responsibilities (ACoP Ref 122-132)The Bridgeway Consulting Limited Diving Supervisor is responsible for all diving operations at the site and shall ensure that the procedures referred to in this method statement are implemented and that accurate records of all operations are maintained throughout including but not limited to Tool Box Talk, Risk assessment Planed Maintenance System etc.
The diving Supervisor will In accordance with the Diving at Work Regulations 1997 (SI 2776), regulation 6 (2) (b) (I) and regulation 9, be appointed as a Diving Supervisor for Air Diving Operations covered by the Approved Code of Practice for Commercial Diving Projects (L104 Rev 2.) The appointment of the diving supervisor will be recorded by Bridgeway Consulting Ltd.
Manual Handling Risks All tools to be lowered into position by rope securely tied to items. All items shall be lowered /recovered in a controlled manner. Work gloves to be worn at all times when handling abrasive or sharp-edged materials. 2 man lift for diving compressor
COSHH AssessmentsFuel, Noise
Reference Information Site Hazard Plan.Wharf and approach walls.Photo’s of area to be inspected.
4 METHOD STATEMENT
Access and Site EnvironmentThe access and egress is via the dive Ladder, extreme care should be taken while accessing the project area
The Complete Air Diving system will set up next to the work site adjacent to the access and egress point, once installed, the equipment will be inspected and tested in accordance with HSE regulations” for the preceding operation.
The area allocated for this purpose is to be sectioned off and all personnel are to be advised of diving operations.
The diver will familiarise himself on surface with the location of the work site in particular in relation to diver entry point into the water.
The diver will be deployed to the work site. The divers swim route to the work site should be defined so that his access route shall be as straight as necessary to avoid obstructions, where practicable. Where the area is bleak, warm weather gear to be worn with gloves.
Work MethodsCarry out Toolbox talk, as discussed and referred to this RAMS and associated Risk Assessment
Once the Diving Supervisor has confirmed all systems are functioning satisfactorily he will instruct the diver to enter the water via the ladder.
After the diver enters the water and on reaching the bottom, the supervisor will take a Pneumo reading to establish the diver’s depth and record it in the dive log (this will be continually checked by the Supervisor during the dive)
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
The diver under the direction of the diving supervisor will inspect and carry out the following.
1. The diver will swim the length of the area to be inspected looking for possible snags or trip hazards.
2. The diver will inspect the determined area of wall 160m.
3. A report will be compiled on the diver’s findings.
Clearing Away Site At the end of each working day the helmets are to be disconnected from the umbilical’s
and washed with fresh water On completion of the works all equipment is removed from site and the area is tidied and squared
away. No rubbish is to be left and the site is to be left cleaner than when we arrived
Specialist Equipment NeedsHand tools OnlyCement Mixer
Site Controls/ResponsibilitiesDiving supervisor is in overall control once diving operation underway
C&RT will:- Issue a permit to work. Undertake an environmental appraisal for the works and inform the dive contractor of any specific
environmental & heritage requirements Isolate, sluices and valves which the diver would be working on. Isolate inlets & outlets. The keys will be handed over to the dive supervisor before the diver enters
the water. Control the public interface.
BCL: will:- All underwater equipment Provide all necessary tools
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
5 RISK ASSESSMENT
Risk Matrix (Guide)1 2 3 4 5
Severity
1 Low Low Low Low Low2 Low Low Medium Medium Medium3 Low Medium Medium Medium Medium4 Low Medium Medium High High5 Low Medium Medium High High
HAZARD Initial Risk CONTROLS Residual Risk
Job Steps Hazard Description and Effect
Persons at Risk
Hazard Severity
Likelihood of occurrence
Risk Rating
List the controls that are in place or are required
Hazard Severity
Likelihood of occurrence
Risk Rating
Set Up General Public, contact with plant, life support equipment Public 2 4 Medium
TBT, Risk Assessment, barrier working area and create pedestrian walkway, correct signage to warn of diving activities
2 2 Low
OperationsWorking over Water, Falling In,Drowning
All 5 4 High TBT, life Jackets to be worn at all times by personnel, Safety lines if appropriate 2 2 Low
Diving Operations
Diver Entrapmentinjury to Diver Divers 4 4 High
Pre-Dive Safety Brief, TBT, Close Tendering on the surface, Stand by diver at immediate readiness Ensure any permits to work and isolations are in place.Good umbilical Management tender to actively tend the divers umbilical
2 2 Low
Diving operations Unconscious diver Divers 4 3 Medium
Follow Emergency Procedures, Jump Stand By diver, Regular maintenance check on Equipment, attentiveness of supervisor. Emergency contact numbers in place
4 2 Low
General Operations Slips , Trips and falls All 4 5 High
TBT, Ensure personnel are aware of the environment, Good Housekeeping, Safety briefing, Identify Known Hazards,
4 2 Low
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
HAZARD Initial Risk CONTROLS Residual Risk
Job Steps Hazard Description and Effect
Persons at Risk
Hazard Severity
Likelihood of occurrence
Risk Rating
List the controls that are in place or are required
Hazard Severity
Likelihood of occurrence
Risk Rating
Diving Operations Vessel movements Divers 5 4 High
Permit to work system in place, BW to issue notice to mariners, all personnel to remain vigilant of Shipping Traffic, VHF communication with local authority, Safety brief, ‘A’ Flag to be Displayed during Daylight Hours, Operational Lights During Hours of Darkness, Boat Movement to be Authorised via Dive Supervisor
3 2 Low
General operations River tidal flow All 4 3 Medium
All personnel are to wear life jackets while working near water, no diving in excessive river flow, Review environmental conditions prior to diver deployment.Tidal monitoring.Adherence to umbilical management protocol.Refer to AODC Guidance 'The effects of underwater currents on diver’s performance and safety', AODC 047.Continuous communications between Dive Supervisor and divers.
4 2 Low
General operations
Biological contamination (Leptospirosis) All 4 3 Medium
Leptospirosis Pocket Card and briefingCover cuts and abrasions full PPE including gloves for all personnel, TBTHygiene control - Wash before eatingToolbox Talks – general hygiene for water conditions
4 2 Low
Diving Operations
Gates & Sluices Inlet & Outlet Valves Divers 4 4 High
The gates & valves which the diver is working on and the adjacent gate and the sluices will be isolated and pad locked off and the nose valves closed. The keys are to be given to the dive supervisor before the diver enters the water,
2 2 Low
Diving Operations Positive Pressure Divers 5 4 High
TBT, no diving till equal pressure between upstream and downstream rivers
3 2 Low
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
HAZARD Initial Risk CONTROLS Residual Risk
Job Steps Hazard Description and Effect
Persons at Risk
Hazard Severity
Likelihood of occurrence
Risk Rating
List the controls that are in place or are required
Hazard Severity
Likelihood of occurrence
Risk Rating
Diving Operations Low Visibility Divers 4 4 High
Diver to take extreme care when negotiating the river. Litter and debris could entangle the diver. Visibility is > 0.5m so most hazards cannot be seen to be avoided. Any large items are to be removed to the side and disposed of.
2 2 Low
General Operations High Walls All 4 5 High
TBT, Ensure personnel are aware of the environment, Good Housekeeping, Safety briefing, Identify Known Hazards. All staff are to wear life jackets at all times.
4 2 Low
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
6 EMERGENCY ARRANGEMENTS
Site Emergency PlanSite Emergency
The following procedures are to be followed by the dive crew in the event of a site emergency when a diver is deployed.
General Muster Duty Personnel Report to designated Muster Station (TBA)
All non-essential personnelShut down all non-essentials plant and go to muster station as advised by the Diving Supervisor.
Supervisors To remain at his station. Instruct divers to return. Inform the client of the status of diving operations and await further instructions.
Tenders Are to remain at their station, await instructions from the supervisor.
Surface Standbys To remain at their station and await further instructions.
In Water Diver Return to the access and egress leave bottom and exit the water.The divers are to undress to await further instructions from the supervisor.
When ordered by the Supervisor.( All Divers/Tenders are present,) are to go to muster point immediately.
In the event that the all clear is given all personnel may resume normal duties and diving operations can continue
Decompression Treatment under Normal Operating Conditions
Note: It is not envisaged that any decompression treatment will be required because all diving operations will be performed in ‘Free Time’.
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
Emergency ContactsCompanyBridgeway Consulting LtdBridgeway House2 Riverside WayNottinghamNG2 1DP0115-9191111
Emergency Services
Local Coastguard Station VHF Channel 16
Police, Fire, Ambulance 999
Closest Hyperbaric Centre
Nearest Chamber is:-Whipps Cross Hyperbaric Unit, University Hospital London. Tel:07740 – 251635.
The Great Western Hospital,Marlborough Road,Swindon,Wiltshire,SN3 6BB. Tel: 01793 604020.Medical Support
Appointed Dive DoctorTim Fitzsimmons 0151 228 9101
DDCMr. Dave Alcock – Operations Manager. (0151) 648 8000
Murrayfield Hospital Holmwood Drive ThingwallWirral
Example Method RA Underwater Inspection – Feb 2016
EMERGENCY EVENT
NON-WATER IN WATER
NOT DIVING RELATED DIVING RELATED
DCI RELATED
DCI NON DCI
RENDER FIRST AID NON-DCI
CONTACT DIVING SPECIALIST (ADVISOR)
SUPERVISOR TO ASSESS SITUATIONRECOVER DIVER FROM WATER
NO FURTHER ACTION REQUIREDFURTHER MEDICAL ACTION REQUIRED
ACT ON ADVICE PROVIDED
IMPLEMENT RECOVERY PLANADMINISTER FIRST AID
CONTACT LOCAL HOSPITAL
MAINTAIN CONTACT WITH MEDICAL ADVISOR
CONTACT COASTGUARD FOR ADDITIONAL SUPPORT IF REQUIRED
NO FURTHER ACTION
DELIVER INJURED PERSON TO HOSPITAL
TREAT CASUALTY AT DESIGNATED FACILITYDELIVER CASUALTY TO DESIGNATED FACILITYTREAT IN HOSPITAL
PREPARE ACCIDENT REPORT / RIDDOR IF REQUIRED
REVIEW LESSONS LEARNT
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
7 INDUCTION AND BRIEFING: CHECKLIST
Project BriefingDetails of Project:Working from a public area.Dress Code (PPE)Training Requirements. General Emergency Arrangements.First Aid
Site InformationDiving Safety Access and EgressLifting Operations.Hazards Summary and Control Measures.Emergency Procedures.Others are working on / close to site.
Any Questions?
Task SpecificProposed Work MethodsSpecialist ToolsSpecial Precautions Any Questions?
BCL SpecificTBTRisk assessmentPMSMethod review?Pre dive checks
Any Questions?
Attendance RecordName Role Signed Date
Supervisor
Briefing Feedback Remarks
Induction / Tool Box Talk byDate Tool Box Talk No.
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
8 CHANGE 0F RECORD
(Details amendments, revisions or updates made on site)Risk Assessment Review
1.
Date Who made change? Why? Signed
2.
Date Who made change? Why? Signed
Method Statement Revisions
1.
Date Who made change? Why? Signed
2.
Date Who made change? Why? Signed
Emergency Plan Updates
1.
Date Who made change? Why? Signed
2.
Date Who made change? Why? Signed
Example Method RA Underwater Inspection – Feb 2016
Client: Canals and River Trust
Project Name: Underwater Inspection
Document No: j------ -DPP
Revision: 01
9 Appendix A Dive Hazard Plan (Found in Site Pack)
Example Method RA Underwater Inspection – Feb 2016