Tariff design and Policy framework - Grid connected Biomass Based Power Plants G R Narsimha Rao The...
-
Upload
kenneth-baldwin -
Category
Documents
-
view
217 -
download
0
Transcript of Tariff design and Policy framework - Grid connected Biomass Based Power Plants G R Narsimha Rao The...
Tariff design and Policy framework- Grid connected Biomass Based Power Plants
G R Narsimha RaoThe Energy and Resources Institute
Bangalore
Workshop on ‘Innovative and Sustainable Energy Technologies for Developing Countries : Opportunities and Challenges 28th May 2014, New Delhi
Content
a) Type of biomass power plants
b) Operational efficiency
c) Fuel linkage
d) Tariff design parameters
e) Major deviations in tariffs
f) Recommendations : Sustainable biomass power plants
Type of Biomass Power Plants
a) Conventional power plant – Steam cycle- Power plants 2 - 30 MW range
b) Co – generation power plants- Sugar Industry
- Paper Industry
- Distilleries
c) Gasification
- Small scale IPPs
- Rice Mills
Limitation of biomass power plant : Dedicated energy forestry Source of biomass
Biomass Power Plants : Conversion Technologies
Conventional power plant conversion efficiency increase with large size to be cost – effective
Biomass based power plants cannot use this route as the size of the power station is determined by the size of the fuel resource availability
Pyrolysis and Gasification offers greater efficiency than combustion based steam cycles
- Pyrolysis : Solid biomass to Liquid
- Gasification : Solid biomass to Gaseous
Converted biomass intermediates can be burned in engines or gas turbines to generate power
Biomass Power Plants : Operational efficiency
Type of Plant Operational Efficiency,%
Conventional Power Plant
upto 15 MW 16 - 25
upto 30 MW > 30
Co-generation Power Plant
Thermal energy base operation ~ 80
Electrical energy base operation ~ 65
Gasification Power Plant
Large scale gasification ( > 25MW) ~ 40
Medium scale gasification 30 - 35
Small scale gasification 20 - 25
Fuel Linkage
Fuel Linkage
• Contract with rice mills & agro process units;• Contact with plantations (tea, coffee etc.,);• Contract with forest department;• Social forestry, privately developed plantations .
State Karnataka Andhra Pradesh Tamil Nadu Maharashtra
Rice Husk 40 - 50 25 - 52 36 - 48
Maize / Corn 43 27 44 - 47
Coffee Husk 55
Wood Chips 27 47 - 49
Jaliflora < 18 < 23 29
Chilli powder 25 30
Pam oil < 10
Agro waste < 22 < 30
Average fuel cost in AP is lower compared to other southern states, but still biomass power plants (IPPs) are not really attracted with prevailing tariff.
( Unit : US $ per MT)
Fuel Linkage : Landed cost of fuel
Tariff : Methodology for biomass based power plants
• Power Generation– Capacity
• Installed Power Generation • Auxiliary Consumption• Plant Load Factor• Useful Life
• Fuel Related Assumptions– Heat Rate– Bagasse / Biomass
• During & After Stablisation period• Base Price (FY 14-15)• Goss Calorific Value (GCV)• Fuel Price Escalation
• Operation & Maintenance– Total O&M Expenses – Escalation
a) Project Cost
b) Plant Load Factor (PLF)
c) Operation and Maintenance Expenses (O & M Expenses)
d) Interest on working capital
e) Auxiliary Consumption
f) Fuel Price
g) Fuel Cost escalation
h) Fuel Consumption
Tariff : Cost components for biomass based power plant
Parameter Co-Gen Bio-mass
Project Cost – million USD/MW 0.6 0.8Debt: equity 70:30 70:30Return on Equity (RoE) 16% 16%Interest on Term Loan 11% 11%Depreciation Rate 7% 7%
Minimum Alternate Tax (MAT) on RoE 7.5% 7.5%Plant load factor (PLF) 60% 75%O& M expense including insurance as % of project cost 3% 4%
O & M escalation per annum 5% 5%Interest on working capital on two months bill 12.5% 12.5%Auxiliary Consumption 8% 9%Fuel price- US $./ Metric Ton 20 25Fuel Cost escalation per annum 5% 5%Specific fuel Consumption-kg/unit 1.6 1.16
Most of the Biomass developers have favoured a 2-part tariff
Tariff : Cost components for biomass based power plant
Biomass Power Plant: Conventional
BoilerQ : 27 MT/hH : 65 kg/cm2
T : 480 0CEff : 80 ± 2%
Heat Value : 805 k.Cal/kg
Power Output: 6.5 MW
Exhaust Heat Value : 792 k.Cal/kg
Turbine
Cooling tower
Turbine Efficiency : { (6500 X 860) / (27000 X 805)} X 100 : 25.7 %Boiler Efficiency : 78 – 80 %Plant Efficiency : (0.257 X 0.78) X 100 : 20.0% Plant Heat Rate : ( 860 / 0.2 ) : 4300 k.Cal/kg
Large number of grid connected biomass power plants : 6 - 8 MW
Plant Heat Rate
Biomass Power Plant: Cogeneration
Use of High Pressure boilers results into steam economy
Crushing Capacity TCD
Installed Boiler Design(Pressure, Flow, Temp.)
Kg/cm2, TPH, 0C
Installed Turbine MW
Internal Cons.MW
Export – Grid
MW
3600 42 / 64 / 410 9.2 3.6 5.5
4000 42 / 75 / 424 16.1 3.8 7.2
4500 66 / 85 / 510 15.5 5.1 10.4
3500 110 / 100 / 540 20.0 4.0 15.0
4800 107 / 120 / 540 24.2 5.2 18.0
4800 107 / 120 /525 24.0 5.5 18.2
10000 67 / (100 +120) / 485 / 510) 15 + 33.75 10.0 25.5
• Export of power depends on initial equipment design• Plant operating efficiency depends on fuel availability
Cogeneration: Sugar Sector
Technical Performance
S No Name Power Plant District Installed Capacity, MW
Boiler / Turbine Fuel Consumption per day, MT
Q, TPH / Pr, Bar Air / Water
1 Indra Power Energies Ltd. Koppal 6 30 / 65 Water 225
2 Koganti Power Pvt. Ltd. Raichur 7.5 35 / 65 Water 250
3 Koppal Green Power Ltd. Koppal 6 30 / 65 Water 200
4 Power Onicks Ltd. Bellary 6 (8 MW upgraded) 32 / 65 Water 250
5 Ravikiran Power Project Pvt Ltd Koppal 7.5 33 / 75 Water 200
6 RK Power Gen Private Ltd. Chitradurga 20 100 / 106(Spread Stoker)
Air 325 (for 12 MW)
Major operating plants 6 MW Range
• Operating Heat Rate of Plants : 4300 k Cal / kWh• Plant Efficiency : ~ 20%• Specific fuel consumption : > 1.4 kg / kWh• Auxiliary power consumption : 12 ± 1 %
Sample Survey : Operating plants in Karnataka state
Technical Performance (Major Deviation)
Based on annual basis Specific fuel consumption is 1.8 – 2.2 kg / kWh for 6 MW biomass power plants(It is mainly due to number of starts / lower operating loads)
Parameter Unit 6 MW 15 MW
Boiler (Q, H) TPH / bar 28 / 65 75 / 105
Boiler Efficiency % 80 ± 2 82 ± 2
Turbine Efficiency % 26 ± 1 29 ± 1
Turbine Heat Rate K Cal / kWh 3300 2965
Plant Efficiency % 20 ± 1 23 ± 1
Plant Heat Rate K Cal / kWh 4300 3740
Fuel Gross Calorific Value K Cal /kg 3040 (Rice husk)
Sp. Fuel Consumption Kg / kWh 1.4 1.2
Auxiliary Power Consumption % 12 ± 1 11 ± 1
Tariff Workings(Major Deviation)
Auxiliary power consumption & Fuel consumption (or plant heat rate)
S No
Component Value Remarks
a Project cost USD 0.9 million per MW
b Plant load factor 75%
c O & M Expenses 4% of Project cost with 5%escalation per annum
d Interest on Working Capital 12.5% on two months bills
e Auxiliary consumption 9% 12 ± 1
f Fuel Price USD 20 per MT
g Fuel cost escalation 5% of fuel cost escalation
h Fuel consumption 1.16 kg / kWh as reasonable SEC 1.4 +
Gasifier based grid connected biomass power plants
Name of
Power PlantVillage/District
Installed
Capacity,
KW
Status
BERI Kabbugiri /Tumkur 150 Not in operation
BERI Kabbugiri, Tumkur 225 Not in operation
BERI Bethamangala, Tumkur 5001 x 200 + 1 x 100
operational
Specific fuel consumption : 1.1 – 1.2 kg/kWh (dry wood)Cost of wood purchased : 2.5 – 2.7 US cent per kgUtility buyback price (PPA) : 3.9 US cent per kWhActual operating cost : > 12US cent per kWh ( at lower cost of wood)Auxiliary power consumption : 15%
Two part Tariff :
I. Fixed cost
It is very important to consider intermediate cost (additional) to maintain plant performance & PLF
Value : Rs per kWh
Two part Tariff :
II. Variable cost
Parameters Biomass Power Plant Rating
Water Cooled Condenser Air Cooled Condenser
6 MW 15 MW 6 MW 15 MW
Plant Heat rate, K.Cal/kg 4300 3740 4601 4002
Plant Efficiency, % 20 23 18.7 21.5
Rice Husk –Gross Calorific Value, K.Cal/kg : 3040
Specific Fuel Consumption(kg/ Wh) 1.41 1.23 1.51 1.32
Prevailing average price of Rice Husk : USD 43 per MT
Variable Charge, cent per kWh 6.0 5.3 6.5 5.7
Based on the capacity of the plant and technology adopted (like water or air cooled condenser), variable cost has been worked out
Biomass based power plant : Tariff(working)
Two part Tariff : Fixed + Variable cost
Parameters Biomass Power Plant Rating/Type
Water Cooled Condenser Air Cooled Condenser
6 MW 15 MW 6 MW 15 MW
Fixed Cost, cent per kWh 3 for New Plants
3.5 for old plants (10 years)
3.3 Average of 20 years period
3.1 for New Plants
3.75 for old plants (10 years)
3.6 Average of 20 years period
Variable Cost, cent per kWh 6.0 5.3 6.5 5.7
Total operational cost,
cent per kWh
9.3 8.6 10.1 9.3
Regulator Issue : Cost of Fuel(Rice Husk Market Price)
Rice Husk price linkage with paddy minimum support price (MSP) fixed by the Government
Financial Year MSP of paddy MSP of paddy Rice husk price (avg) Rs.per Qnt. Rs.per MT Rs.per MT2008-09 900* & 930** 9000 & 9300 18002009-10 1000 & 1030 10000 & 10300 20502010-11 1000 & 1030 10000 & 10300 20502011-12 1080 & 1100 10800 & 11000 22002012-13 1250 & 1270 12500 & 12700 2500
* Common grade ** A grade
Source: Rice husk price collected from millers & IPPs MSP of paddy from APMC
Sample calculation for the year 2012-13 Cost of 1 MT of paddy (MSP) Rs.12500/-Quantity of Husk generated 20%
Cost of 1 MT of rice husk Rs.12500 x 0.2 : Rs.2500/-
Based on local demand fuel price vary significantly
Sustainability of Biomass power plants
Recommendations :
Biomass projects : where fuel cost component is variable therefore its important that biomass tariff should have both separate fixed and variable tariff components;
Fixed cost can be fixed for 20 years basis; Escalation in variable cost is linked with the indexation mechanism (or) actual cost incurred
towards fuel in review year; Variable cost review period should be 2 years;
To ensure availability of biomass and reduce the biomass price volatility among biomass power projects follow the Govt. guidelines;
(a minimum radial distance of 50 kM between plants)
Not to allow plants to go for OPEN ACCESS, it will result in higher volatility in local biomass price;
Govt. policy should support the development of technologies
potential to compete with fossil fuels within reasonable length not only to grow the fuel at low cost to convert it to electricity in a highly efficient manner (like Fluidized bed gasifiers, gas turbines & combined cycles)
THANK YOU