Target Man Hours Versus Time S Curve
-
Upload
ren-salazar -
Category
Documents
-
view
40 -
download
0
Transcript of Target Man Hours Versus Time S Curve
![Page 1: Target Man Hours Versus Time S Curve](https://reader035.fdocuments.in/reader035/viewer/2022071708/55cf9b99550346d033a6ac3a/html5/thumbnails/1.jpg)
Target Man Hours versus Time S Curve
To generate the Actual and Target S Curves, a Production Schedule is required.A Production Schedule for this project is shown below.
Figure 13: Production Schedule
To generate a Target Man Hours versus Time S Curve, two sets of calculations are performed.The first set of calculations are performed for each task in the Production Schedule.(1) Calculate the duration in days for each task.ie. Duration = Finish Date - Start Date + 1(2) Calculate Man Hours per day for each task.ie. MHs per Day = Man Hours / Duration
These calculations are shown in the following table.
Figure 14: Target S Curve Calculation 1/2
The second set of calculations are performed for each day in the Production Schedule.(3) Calculate the total Man Hours per Day for all tasks.(4) Calculate the Year To Date Total for Man Hours per Day for all tasks.
These calculations are shown in the following table.
Figure 15: Target S Curve Calculation 2/2
The resulting Target Man Hours versus Time S Curve is shown below.
![Page 2: Target Man Hours Versus Time S Curve](https://reader035.fdocuments.in/reader035/viewer/2022071708/55cf9b99550346d033a6ac3a/html5/thumbnails/2.jpg)
Figure 16: Target Man Hours versus Time S Curve