Tamilnadu Generation and DistributionCorporation Ltd
Petition for Determination ofMiscellaneous Charges (Non-Tariff)
February 2018
2
ContentsChapter 1 Preamble ...................................................................................... 5Chapter 2 Proposed Miscellaneous Charges................................................. 81. Service Connection Charges............................................................................ 82. Meters......................................................................................................... 103. Meter Rent .................................................................................................. 114. Meter related Charges .................................................................................. 125. Meter Caution Deposit .................................................................................. 206. Charges for temporary disconnection at the request of the consumer.............. 207. Reconnection Charges .................................................................................. 218. Replacement of Consumer Meter card: .......................................................... 229. Charges for dishonoured cheque:.................................................................. 2310. Charges for Name Transfer of Service ........................................................ 2411. Development Charges ............................................................................... 2512. Registration Charges ................................................................................. 2813. Tariff Change............................................................................................ 2914. Earnest Money Deposit .............................................................................. 3015. Security Deposit........................................................................................ 3016. Furnishing certified copies to consumers..................................................... 31
Chapter 3 Prayer ......................................................................................... 32
3
List of TablesS.NO Table No. Description Page No.
1 Table 1 Service Connection Charges 92 Table 2 Meter Rent 11
3 Table 3Changing/Shifting of Meter Board/LTCT Box/HT Box due to damage or for accommodatingadditional safety features like ELCB etc.
12
4 Table 4Changing of meter at the request of theconsumer without any dispute in accuracy ofthe meter
12
5 Table 5Inspection and Testing of meter when disputearises in the accuracy(Challenge Test)
13
6 Table 6 Installation Testing 147 Table 7 Periodical Inspection 15
8 Table 8 Charges for Rating / Re- Rating of installation(Taking Revised test report) 16
9 Table 9Inspection and Testing of consumer’sinstallation for offering suggestion on request/trouble shooting issues
16
10 Table 10 Replacement of Glass and Meter 1711 Table 11 Replacement of damaged/burnt meter 18
12 Table 12 Resealing charges where seals are foundbroken and attending faults. 19
13 Table 13 Downloading of Meter reading using CMRI -requested by the consumer 19
14 Table 14 Meter Caution Deposit 20
15 Table 15 Temporary disconnection at the request of theconsumer. 20
16 Table 16 Reconnection Charges - LT 2117 Table 17 Reconnection Charges - LT CT & HT 2218 Table 18 Replacement of Consumer Meter card 2319 Table 19 Charges for dishonoured cheque 2420 Table 20 Name Transfer of Service 2521 Table 21 Development Charges – LT (Overhead) 2622 Table 22 Development Charges – HT (Overhead) 2623 Table 23 Development Charges – LT (Cable) 2724 Table 24 Development Charges – HT (Cable) 2725 Table 25 Registration cum Processing Charges 2926 Table 26 Tariff Change 3027 Table 27 Earnest Money Deposit 3028 Table 28 Security Deposit 3129 Table 29 Furnishing Certified Copies to Consumers 31
4
List of Annexures
S.NO AnnexureNos. Description Page Nos.
1 Annexure 1 Service connection charges 372 Annexure 2 Meter Rent 383 Annexure 3 Changing of Meter Board/LTCT Box/HT Box 394 Annexure 4 Changing of Meter/Temporary Disconnection 40
5 Annexure 5Installation testing,rating,re-rating ofinstallation,Inspection and testing of consumer'sinstallation,replacement of glass and meter.
41
6 Annexure 6 Resealing of meter 427 Annexure 7 Downloading of meter reading using CMRI 438 Annexure 8 Meter Caution Deposit 449 Annexure 9 Reconnection 4510 Annexure 10 Dishonoured cheque 4611 Annexure 11 Name Transfer of services 4712 Annexure 12 Development Charges (Overhead lines) 4813 Annexure 13 Development Charges (Under Ground Cable) 4914 Annexure 14 Registration and processing of application 5015 Annexure 15 Change of tariff 5116 Annexure 16 Security Deposits 5217 Annexure 17 G.O.Ms No.31, Energy (B1), Department dt 1.4.2002 53
5
Form 1
Before the Hon’ble Tamil Nadu Electricity Regulatory
Commission
Filing No.
Case No. M.P.No. _____ of 2018
In the Matter of: Miscellaneous Petition for fixing of Miscellaneous Chargesrecoverable from consumers under various sections ofElectricity Act, 2003 and TamilNadu Electricity SupplyCode and Tamil Nadu Electricity Distribution Code ofHonourable Tamil Nadu Electricity Regulatory Commissionand Government Order.
Tamil Nadu Generation and Distribution Corporation Ltd.144, Anna Salai,Chennai – 600 002 - Petitioner
--Nil-- - Respondent
Chapter 1 Preamble
The petitioner named above respectively showeth under
1.1. Tamil Nadu Electricity Board was a State Electricity Board constituted under
section 5 of the Electricity (Supply) Act, 1948 and was in the business of
Generation, Transmission and Distribution of Electricity in the State of Tamil
Nadu.
1.2. TNEB was restructured into TNEB Ltd and two subsidiary companies viz. Tamil
Nadu Generation and Distribution Corporation Ltd and Tamil Nadu Transmission
Corporation Ltd.
1.3. Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO) was
incorporated on 01.12.2009 and the Certificate for commencement of business
was obtained on 16.03.2010.
6
1.4. The Government vide G.O.(Ms.) No.100, Energy (B2) department, dt
19.10.2010 has issued Tamil Nadu Electricity (Reorganisation and Reforms)
Transfer Scheme, 2010 for the purpose of transfer and vesting of property,
rights and liabilities of the Tamil Nadu Electricity Board in the State Government
and re-vesting thereof by the State Government into corporate entities and also
for the transfer of personnel of the Tamil Nadu Electricity Board to corporate
entities and for determining the terms and conditions on which such transfer
and vesting will be made. The opening balances of assets and liabilities are
transferred based on the 2008-09 un-audited balance, which was the latest
available data at that time. TANGEDCO started functioning independently from
1.11.2010 onwards.
1.5. Final transfer scheme transferring the assets and liabilities to successor entities
of erstwhile Tamil Nadu Electricity Board has been notified by Government of
Tamil Nadu vide GO.MS. No 49 (Energy Department) dated 13.08.15 and
incorporated in 2015-16 audited accounts.
1.6. As per Section-46 of Electricity Act, 2003, the State Commission may, by
Regulations, authorise a Distribution Licensee to charge from a person requiring
a supply of electricity in pursuance of Section-43 any expenses reasonably
incurred in providing any electric line or electrical plant used for the purpose of
giving that supply.
1.7. In addition to Revenue from sale of power, TANGEDCO is collecting
Miscellaneous charges from consumers on account of service connection
charges, Meter Rent, Meter caution Deposit, Re-connection charges,
Registration charges etc.
1.8. Accordingly,as submitted by TNEB the Hon’ble Tamil Nadu Electricity Regulatory
Commission has issued Order on Non- Tariff related Miscellaneous Charges dt
31.08.2004 (w.e.f.01.10.2004) without any increase for the rate prevailed from
1999.TANGEDCO has filed petition for Non- Tariff related Miscellaneous Charges
and the same was admitted by the Hon’ble Commission on 31.07.2012 and
numbered as M.P. No.16 of 2012 .The Hon’ble Commission has ordered that the
petition filed by TANGEDCO is dismissed as withdrawn, based on the
TANGEDCO’s submission in view of poor power situation prevailing at that time.
7
1.9. This application for the revision of Miscellaneous charges, is being filed before
the Honourable Tamil Nadu Electricity Regulatory Commission and it is prayed
to approve the proposed miscellaneous charges and TANGEDCO requests the
same may be effective from 01.04.2018 or earlier.
1.10. Need
It is submitted that the need for which revision now requested for the Meter
Caution Deposit, Security Deposit, Development charges, service connection
charges and also for the various services provided by the TANGEDCO. The Cost
of service rendered by the utility increased over 13 years. The marginal
increase of these charges would compensate a portion of the capital cost/cash
flow requirement of TANGEDCO for the year 2018-19.
Sd-----19.02.2018Chief Financial Controller/Regulatory Cell,
Petitioner
8
Chapter 2 Proposed Miscellaneous Charges
1. Service Connection Charges
2.1. In accordance with section 45 of the Electricity Act 2003, the Hon’ble
Commission authorise the Distribution licensee TANGEDCO to collect
service connection charges in Regulation 45 of Tamil Nadu Electricity
Distribution Code.
Service connection charges is
(i) For connecting up an installation, the Licensee shall be entitled to
charge the consumer the actual cost of materials upto meter board,
labour, transport plus overhead charges. (ii) Extension, improvement
or alteration to service lines to meet any additional demand will be
charged on the same basis. In each case, the consumer will be
furnished with an estimate of the cost of the work and this amount is
payable in advance. On completion of the work, a bill for the actual
amount payable will be forwarded to the consumer and any difference
shall be paid by the consumer or will be refunded by the Licensee as
the case may be. (iii) The estimate for service connection charges
may also include the service connection charges for metering referred
to in regulation 45(2). The licensee shall give due credit for the
materials if any supplied by the consumers
2.2. In the existing order on the Non- Tariff related Miscellaneous Charges w.e.f.
01.10.2004, the service connection charges for three phase LT services with a
connected load (CL) up to 112 kW are charged equally. Based on the prevailing
estimate sanction procedures, it is submitted that it is proposed to charge
seperate SC charges for
a) Low Tension Three Phase service connections with less than 18.6 kW.
b) Low Tension Three Phase service connections with Connected Load between
above 18.6 kW and up to 50 kW.
c) Low Tension CT service connections with Connected Load between above 50
kW and up to 112 kW.
9
2.3. It is prayed to approve the proposed Service Connection Charges as submitted
below
Charges in Rupees
Singlephase
Threephase
Singlephase
3phasewith CL
<18.6 kW
3phasewith CL
(18.6 kW-50 kW)
LTCT(50 kW -
112kW)
I LT services
1 Domestic IA 250 500 600 900 2000 2900
2 Hut IB
3 Bulk Supply IC Nil Nil 600 900 2000 2900
4 Street Light & Water Supply IIA 250 500 600 900 2000 2900
5 Government Educationalinstitutions etc
IIB(1) 250 500 600 900 2000 2900
6 Private Educationalinstitutions
IIB(2) 250 500 600 900 2000 2900
7 Actual Places of worship IIC 250 500 600 900 2000 2900
8 Cottage & Tiny Industries IIIA(1) 250 500 600 900
9 Power Loom IIIA(2) 250 500 600 900
10 Industries IIIB 250 500 600 900 2000 2900
11 Agriculture IV
12 Commercial V 250 500 600 900 2000 2900
II HT services
1 11 kV
2 22 kV
3 33 kV
4 110 kV
5 230 kV
Basis for proposed charges are submitted in
NilNil
Nil
NA
NA
Nil
Annexure 1
Nil
ProposedExisting
Nil
Table 1Service Connection Charges
Sl.No
Category Tariff
Existing Proposed
Note: All the Service connection materials are to be provided by the applicants.
10
2. Meters2.4. It is submitted that Regulation 5 (11) of Tamil Nadu Electricity Supply
Code, authorise the Distribution licensee TANGEDCO to collect meter
related charges as specified below:
“Meter rental charges shall be payable by the consumer, unless the
consumer elects to purchase a meter, in accordance with the rates as
the Commission may fix from time to time for different categories of
consumers. The Licensee shall, besides meter rent where payable,
collect charges towards changing of meters and boards, testing of
meters, testing of installations, inspection charges etc., at the rates
specified by the Commission from time to time.”
2.5. Under the heading of Meters, at present the following charges are being
collected :
(a) Meter Rent(b) Meter Related Charges(i) Changing of Meter Board(ii) Changing of meter at the request of the consumer not due to increase in
consumption(iii) For Testing, if it is proved to be correct within the prescribed limit (challenge
Test)(iv) Installation Testing2.6. Now under the heading of Meters, the following charges including above
charges /modification of above charges and new charges are submitted for
collection from the consumers:
(a) Meter Rent(b) Meter Related Charges(i) Changing/Shifting of Meter Board/ Meter box for LT, LTCT & HT and(ii) Changing of Meter at the request of the consumer without any dispute in
accuracy of the meter(iii) Inspection and Testing of Meter when dispute arises in the accuracy (Challenge
test)(iv) Installation Testing arising out of failure or replacement.(v) Charges for rating / re-rating of installation at the instance of the
Consumer(vi) Resealing charges where seals are found broken/temporary disconnection
charges.
11
(vii) Replacement of Glass and Meter(viii) Charges for replacement of damaged / burnt meter(ix) Special meter reading charges as per the request of the consumer
3. Meter Rent2.7. It is submitted that, as per the provision under section 47 (1(b)) and section 55
(1) of the Electricity Act, 2003, the TANGEDCO is entitled to collect a meter
rent. As per section 47(4) of the Electricity Act, 2003, the consumer is entitled
to receive interest at the bank rate to be specified by the Commission for the
meter security deposit paid by the consumer.
2.8. In Para:3.3 (Meter Rent) of Tariff order on non-tariff related miscellaneous
charges w.e.f.1.10.2004, it has been stated that the meter rent for LT services
and the interest on MCD will be a meagre amount and it is proposed to match
both charges. Further, this will eliminate considerable accounting works in
computing the interest for small amounts and issuing credits through
consumption bills or cash payment and accordingly, no meter rent has been
collected and in turn no interest has been paid for the Meter Caution Deposit.
It is proposed to continue with the existing status.
2.9. It is prayed to approve the proposed meter rent as submitted below:
Charges in RupeesS.No Description Existing Proposed
LT Services
1Single Phase Mechanical/Electronicmeter
Nil Nil
2 Three Phase Electronic meter Nil Nil
3 Multi function Meter for LTCT SCs Nil NilHT ServicesMulti function Tri vector electronic meter
411 kV,22 kV,33 kV-Rs./Service/month or part thereof
2000 /SC 3200 /SC
5EHT -Rs. /service/month or part there of
2000 /SC 3200 /SC
Basis for proposed charges are submitted in
Table 2Meter Rent
Annexure 2
12
4. Meter related Charges
2.10. Changing/Shifting of Meter Board/LTCT Box /HT Box due to
damage or for accommodating additional safety features like Earth
Leakage Circuit Breaker(ELCB) etc.,
It is prayed to approve the proposed charges for the changing of Meter Board/
LTCT Box /HT Box due to damage or for accommodating additional safety
features like ELCB etc., as submitted below:
Charges in RupeesS.No Description Existing Proposed
1 Low Tension 150 580
2Low Tension Three Phase(Upto 18.6 kW)
150 1150
3Low Tension Three Phase(18.6 kW to 50 kW)
150 1920
4 LT CT Box 150 4040
5 HT BoxNot
specified6310
Basis for proposed charges are submitted in
Table 3
Changing/Shifting of Meter Board/LTCT Box /HT Box due todamage or for accommodating additional safety features like
ELCB etc.
Annexure 3
2.11. Changing of meter at the request of the consumer without any
dispute in accuracy of the meter
It is prayed to approve the proposed charges as submitted below
Charges in RupeesS.No Description Existing Proposed
1 Low Tension 50 580 + actual cost of meter
2Low Tension Three Phase(Upto 18.6 kW)
50 860 + actual cost of meter
3Low Tension Three Phase(18.6 kW to 50 kW)
50 1440 + actual cost of meter
4 LT CT 50 3380 + actual cost of meter5 High Tension 200 3810 + actual cost of meter
Changing of meter at the request of the consumer
Table 4
Annexure 4Basis for proposed charges aresubmitted in
13
2.12. Inspection and Testing of meter when dispute arises in the
accuracy: (Challenge Test)
It is prayed to approve the proposed charges as submitted below
Charges in Rupees
S.No Description Existing Proposed
1 Low Tension single phase 100 /SC
2 Low Tension Three phase
3 LTCT
4 High Tension
Charges for the Challenge Testmade at Government ElectricalStandards Laboratory (GESL)or at National AccreditationBoard for Testing andCalibration Laboratory (NABL)shall be as per the rates inforce at GESL or NABL, as thecase may be, which shall becollected by the licensee fromthe consumer for whom thesaid Challenge Test was made.
300 /SC
Inspection and Testing of meter when dispute arises in the accuracy(Challenge Test)
Table 5
14
2.13. Installation Testing
It is prayed to approve the proposed charges as submitted below:
Charges in Rupees
SinglePhase
ThreePhase
SinglePhase
ThreePhase
I LT Services1 First test and inspection
2
Further test on inspection due tofaults in installation(If needed as per statutory) below18.6kW
580 860
3
Further test on inspection due tofaults in installation(If needed as per statutory)(18.6kW to 50 kW)
II LTCT1 First test and inspection
2Further test on inspection due tofaults in installation(If needed as per statutory)
III HT Services
1For the first and subsequent testbefore commissioning for each visit
2
Further test on inspectionSubsequent Inspection / testingwarranted due to absence ofcontractor or his representative ordue to defects in wiring ofConsumer’s premises/due to anyfaults in installation /Resetting ofmeters for every open accesstransaction / opening of AB Switch/
IVCharges for taking Meter Readingin Wind Farm(per wind farm service per month)
Basis for proposed charges are submitted in
Table 6Installation Testing
DescriptionSl.No
Free 2880
Annexure 5
Existing Proposed
Free Free
75
Nil 1920
75 2880
3810
300 1000
75 3810
Nil
15
2.14. Fees for Periodical Inspection:
It is submitted that, as per Central Electricity Authority (Measures relating toSafety and Electric Supply) regulations, 2010, Chapter III (General Safetyrequirements) regulation 30, every installation shall be periodically inspectedand tested at intervals not exceeding five years either by the ElectricalInspector or by the supplier as may be directed by the State Government. Theinspection and testing fees was last notified by the Government videG.O.No.31,Energy (B1) Department, dt.01.04.2002 . Therefore, the feesprescribed for inspection of installation i.e., low, medium, high voltage or anyother charges to be fixed from time to time shall be collected from theconsumer concerned , whenever the service was inspected by Board’s Officialsduring mass inspections or any other inspection conducted as per the formsprescribed by CEA under regulation 30, sub regulation (3) and the same maykindly be approved.
C ha rge s in R upe e sS.No D e script ion E x ist ing P ropose d
I LT se rvice s
1D om estic and o ther serv icesw ithout m o to r lo ad
25Rs.25 /- o r any o thercharges to be fixedfrom tim e to tim e
II Othe rs
1 U pto and inclusive o f 5 kV A 50Rs.50 /- o r any o thercharges to be fixedfrom tim e to tim e
2A bove 5 kV A and up to andinclusive o f 25 kV A
75Rs.75 /- o r any o thercharges to be fixedfrom tim e to tim e
3A bove 25 kV A and up to andinclusive o f 50 kV A
100Rs.100 /- o r any o thercharges to be fixedfrom tim e to tim e
4A bove 50 kV A and upto andinclusive o f 250 kV A
150Rs.150 /- o r any o thercharges to be fixedfrom tim e to tim e.
5A bove 250 kV A and up to andinclusive o f 500 kV A
250Rs.250 /- o r any o thercharges to be fixedfrom tim e to tim e
6 A bove 500 kV A 500Rs.500 /- o r any o thercharges to be fixedfrom tim e to tim e
Basis fo r p roposed charges are subm itted in
T a ble 7P e riod ica l Inspe ct ion
G .O .M s No .31, E ne rgy(B 1),D e pa rtm e nt dt 1 .4.2002
16
2.15. Charges for Rating / Re- Rating of installation (Taking Revised test
report)
It is prayed to approve the proposed charges as submitted below:
S.No Description Existing Proposed
1 LT single phase 580
2 LT Three phase (Upto 18.6 kW) 860
3 LT 3 phase (Beyond 18.6 kW) 1920
4 LT CT 2880
5 High Tension 3810
Basis for proposed charges are submitted in
Charges for Rating / Re- Rating of installation(Taking Revised test report)
Table 8
Annexure 5
Charges for service necessitated due to conversion of an installation oradditions and/or alternations to an installation / Charges for temporarydisconnection at Consumer’s request
Nil
Charges in Rupees
2.16. Inspection and Testing of consumer’s installation for offering
Suggestions on request/ trouble shooting issues
It is prayed to approve the proposed charges as submitted below
Charges in RupeesS.No Description Existing P roposed
1 LT single phase 580
2 LT Three phase (Upto 18.6 kW) 860
3 LT 3 phase (Beyond 18.6 kW) 1920
4 LT CT 2880
5 H igh Tension 3810
Basis for proposed charges are subm itted in
Inspection and T esting of consumer’s insta lla tion for offeringsuggestion on request/ trouble shooting issues
T able 9
A nnexure 5
N il
17
2.17 Replacement of Glass and Meter:
It is prayed to approve the proposed charges as submitted below
Charges in Rupees
S.No Description Existing Proposed
1 LT single phase 580 + actual cost of meter
2 LT Three phase (Upto 18.6 kW) 860 + actual cost of meter
3LT Three phase with CL between 18.6kW to 50 kW
1920 + actual cost of meter
4 LT CT 2880 + actual cost of meter
5 High Tension 3810 + actual cost of meter
Basis for proposed charges are submitted in Annexure 5
Replacement of Glass and MeterTable 10
Nil
2.18. Note Submission no. :- 1. This amount will be charged without prejudice
to the right of the TANGEDCO to take any other action or impose penalty on
the consumer as per the prevailing rules. Since, in such case, the meter has to
be sent for testing , the meter changing charges shall be levied additionally.
2.19. Note Submission no.: -2. This amount will be charged without prejudice
to the right of the TANGEDCO to recover the estimated cost of theft of energy.
Principles of natural justice shall invariably be followed and opportunity of being
heard shall be given to the consumer before levying such charge.
18
2.20. Charges for replacement of damaged/burnt meter
The cost of burnt out meter shall be collected and shall be replaced by a
good meter immediately without any lapse of time. The released burnt meter
shall be examined by MRT wing of the Licensee. If the meter is burnt out
due to mistake of Consumer or fault in the Consumer premises, there shall
be no refund of the cost of meter collected by the Licensee and if it is due to
the technical reasons like voltage fluctuation etc, attributable to the system
constraints, the cost of meter collected by the Licensee shall be adjusted
against the future consumption charges of the Consumer under intimation to
the Consumer.
2.21. It is prayed to approve the proposed charges as submitted below
Charges in RupeesS.No Description Existing Proposed
1 LT Single Phase 580 + actual cost of meter2 LT Three phase (CL upto 18.6 kW) 860 + actual cost of meter
3LT Three phase (CL between 18.6kW to 50 kW)
1920 + actual cost of meter
4 LT CT 2880 + actual cost of meter5 High Tension 3810 + actual cost of meter
Basis for proposed charges are submitted in
Table 11Replacement of damaged/burnt meter
Nil
Annexure 5
2.22. Resealing charges where seals are found broken
2.23. The Consumer shall ensure that the metering equipment and seals provided
are not damaged / tampered with and consumer may request disconnection of
services temporary
2.24. In case, the licensee’s seal are damaged by the consumers and request
disconnection of services temporary, it is prayed to approve the proposed
charges as submitted below:
19
Charges in RupeesS.No Description Existing Proposed
1 LT single phase 580
2 LT Three phase 860
3 LT CT 21104 High Tension 2640
5 Attending faults at HT services 2000 4270
Basis for proposed charges are submitted in
Table 12Resealing charges where seals are found broken and
attending faults
Nil
Annexure 6
2.25. Note Submission no. :- 1. This amount will be charged without prejudice
to the right of the TANGEDCO to take any other action or impose penalty on
the consumer as per the prevailing rules. Since, in such case, the meter has to
be sent for testing, the meter changing charges shall be levied additionally.
2.26. Note Submission no.: -2. This amount will be charged without prejudice
to the right of the TANGEDCO to recover the estimated cost of theft of energy.
Principles of natural justice shall invariably be followed and opportunity of being
heard shall be given to the consumer before levying such charge.
2.27. Downloading of Meter reading using CMRI - requested by the
consumer
It is prayed to approve the proposed charges as submitted below:
Charges in Rupees
S.No Description Existing Proposed
1 High Tension 10/Page 2540 /Reading
Basis for proposed charges are submitted in
Table 13
Downloading of Meter reading using CMRI - requested by theconsumer
Annexure 7
20
5. Meter Caution Deposit
2.28. The provision under section 55 of the Electricity Act, 2003 stipulates that
the licensee may require the consumer to give him security for the price of a
meter.
It is prayed to approve the proposed Meter Caution Deposit as below:
C harges in RupeesS.N o D e script io n E x ist ing P ro po se d
I LT Se rvice s
1 S ing le phase Meter 700 /Meter 600 /Meter
2 T hree Phase Meter
a E lectron ic S tatic m eter 2760 /Meter
b E lectron ic S tatic T ype LT C T operated 4390 /Meter
II H T Se rvice s
1 11 kV Meter p lus m eter ing set
2 22 kV Meter p lus m eter ing set
3 33 kV Meter p lus m eter ing set
III E H T Se rvice s
1 110 kV
2 230 kVBasis fo r p ropo sed charges are subm itted in
100000 /SC 453000 /SC
A nne x ure 8
T a ble 14M e te r C a ut io n D e po sit
40000 /SC 149420 /SC
2500 /Meter
Note: The interest on MCD payable to the HT consumers will be adjusted along with
ACCD.
6. Charges for temporary disconnection at the request of theconsumer.
2.29. It is prayed to approve proposed charges for disconnection
C h a r g e s in R u p e e sS .N o D e s c r ip t io n E x is t in g P r o p o s e d
1 L T S in g le P h a s e 5 8 0
2L T T h r e e p h a s e(C L u p to 1 8 .6 k W )
8 6 0
3L T T h r e e p h a s e(C L b e tw e e n 1 8 .6 k W to 5 0 k W )
1 4 4 0
4 L T C T 3 3 8 0
5 H ig h T e n s io n 3 8 1 0
B a s is fo r p r o p o s e d c h a r g e s a r e s u b m i tte d in A n n e x u r e 4
T a b le 1 5T e m p o r a r y d is c o n n e c t io n a t t h e r e q u e s t o f t h e c o n s u m e r .
N i l
21
7. Reconnection Charges:
2.30. It is submitted that as per Regulation 5 (8) of Tamil Nadu Electricity Supply
Code ,the Licensee shall collect reconnection charges from LT/HT consumers at
the rates specified by the Commission from time to time. It is prayed to
approve the proposed reconnection charges as submitted below:
2.31. LT Consumers:
Charges in Rupees
Cut out/Overhead
UnderGround
Single/ThreePhase
Single/Threephase
Singlephase
Threephase
Singlephase
Threephase
Singlephase
Threephase
1 Domestic I A2 Bulk Supply IC
3Street Light &Water Supply
II A
4Govt and Govtaided Edu. Ins.
IIB(1)
5 Private Edu. Ins. IIB(2)6 Places of worship IIC
7Cottage & TinyIndustries
IIIA(1)
8 Power Loom IIIA(2)9 Industries IIIB10 Agriculture IV 60 30011 Hut IB
Basis for proposed charges are submitted in
Overhead Under Ground
Table 16Reconnection Charges - LT
Cut out
Existing
TariffS.NO Category
Proposed
Nil Nil
60 300
Annexure 9
30060
200 350 500 500 650 750
2.32. LTCT Services: Reconnection charges for the LTCT services is being
proposed as Rs. 1200/ per service. Further, in respect of LTCT services remain
disconnected for more than 6 months, testing of meter by MRT personnel
would be required. Hence, it is proposed to charge an amount of Rs.4100/- per
service to the LTCT services remains disconnected for more than 6 months.
22
2.33. HT Consumers: Reconnection charges for the HT services is being
proposed to be revised from Rs.3000/ per service to Rs 5000/- per service.
Further, in respect of HT services remain disconnected for more than 6 months,
testing of meter by MRT personnel would be required. Hence, it is proposed to
charge an amount of Rs. 8100/- per service to the HT services remains
disconnected for more than 6 months. it is prayed to approve the proposed
reconnection charges for LTCT and HT consumers as submitted below:
Charges in Rupees
S.No Description Existing Proposed
I Within 6 Months from the date of disconnection
1 LT CT 300 1200
2 High Tension 3000 5000
II Beyond 6 Months from the date of disconnection
1 LT CT 300 4100
2 High Tension 3000 8100
Basis for proposed charges are submitted in
Table 17
Reconnection Charges - LT CT & HT
Annexure 9
8. Replacement of Consumer Meter card:
2.34. It is submitted that as per Regulation 5 (9) of Tamil Nadu Electricity Supply
Code, the licensee shall collect charges at the rate specified by the Commission
for replacement of consumer meter card if lost or damaged.
2.35. Further, it is submitted that there is no changes proposed for existing
charges, it is prayed to approve the same and equivalent charges effecting
service connections , for replacement, lost or damaged card and used up as
follows:
23
Charges in RupeesS.No Description Existing Proposed
New service connection1 HT/LT CT services2 LT services
Replacement / lost / damaged1 HT/LT CT services 5 52 LT services 5 5
Used up1 HT/LT CT /LT services Free Free
Table 18Replacement of Consumer Meter card
Nil Nil
9. Charges for dishonoured cheque:
2.36. It is submitted that as per Regulation 5 (10) of Tamil Nadu Electricity Supply
Code, the licensee shall collect service charges as specified by the commission
time to time from the consumer, when a cheque given by the consumer is
returned by the bank for any reason whatsoever.
2.37. When Cheques given by the Consumers either for current consumption
charges or towards any other charges of current consumption
deposit/additional current consumption deposit are returned by the Bank for
any reason, a service charges of Rs.250/- is being collected for both LT and HT
consumers.
2.38. Even though the no. of HT consumers are less compare to LT consumers,
the energy consumed by the HT consumers are more and hence the current
consumption charges payable by the HT consumers are also high. Moreover,
they are paying the charges for the energy already consumed by them. As
such, when the cheque issued by a LTCT consumer / HT consumer for the
energy already consumed by them, is returned by the Bank as dishonoured, the
day to day financial planning of the TANGEDCO gets affected very much and
the resulting financial hardship would be considerable.
2.39. In this connection, it is submitted that in Regulation 15 (4) of Tamil Nadu
Electricity Supply Code, differentiation has been made between LT and HT
consumers as regards to the minimum levy of additional service charges in the
event of dishonour of cheque.
24
2.40. Hence, it is prayed to approve the proposed charges for dishonoured cheque
depending upon the cheque amount for the financial hardship caused for LT
CT/HT services plus service charges in respect of HT/LT consumers as
submitted below:
Charges in RupeesS.No Description Existing Proposed
1 Cheque amount Upto Rs. 10,000/-
5% of amountsubject to minimumof 250+ servicecharges of 250
2Cheque amount of Rs.10, 001 andupto Rs.1,00,000/-
3.5% of amountsubject to minimumof 1250 + servicecharges of 250
3 Cheque amount Above Rs.1,00,000/-
2.5% of amountsubject to minimumof 4750 + servicecharges of 250
Basis for proposed charges are submitted in
Table 19Charges for dishonoured cheque
Rs 300 for LTand Rs 1000
for HT
Annexure 10
10. Charges for Name Transfer of Service
2.41. It is submitted that as per regulation 4 (2) of Tamil Nadu Electricity Supply
Code of Hon’ble commission, Name Transfer Charges shall be recoverable from
the consumers, by the Licensee. In Regulation 5 (7) of the above Supply Code,
the details of documents to be furnished for considering the name transfer have
been indicated.
2.42. In order to effect name transfer, it would be essential to verify all the
necessary documents mentioned in Regulation 5(7) of the Supply Code and to
ensure whether the service is live or under disconnection. Based on the
activities involved and the man power requirement, it is prayed to approve the
proposed Name Transfer Charges as submitted below:
25
Charges in RupeesS.No Description Existing Proposed
I Low Tension Services (Legal Succession,Sale of Property)
1 LT category Domestic 200 400
2All LT category except Domesticand Hut
200 1500
3 Hut 50 50
II High tension Services 2000 7500
III Wind Mill and Solar 100000 200000
Basis for proposed charges are submitted in
Table 20Name Transfer of Service
Annexure 11
11. Development Charges
2.43. LT Category
It is submitted that as per section 46 of the Electricity Act 2003, the State
Commission shall authorise a distribution licensee to charge from a person
requiring supply of electricity in pursuance of Section 43 any expenses
reasonably incurred in providing any electric line or electrical plant used for the
purpose of giving that supply. Accordingly , for connecting up an installation,
the TANGEDCO shall be entitled to collect the entire cost of the service lines
including material, transport and labour from the consumers.
2.44. It is submitted that the development charges are being collected to recover
at least a part of the cost of creation of necessary infrastructure facility for
extension of supply. it is prayed to approve the proposed development Charges
as submitted below:
26
2.45. LT Category: The following are submitted in respect of LT consumers in
overhead lines areas
Charges in Rupees
Singlephase
Threephase
Singlephase
Threephase/LTCT
1 Domestic IA 400 /SC 1400 /SC 2000 /SC 2000 /kW
2 Bulk Supply IC Nil 200 /kW Nil 2000 /kW3 Public Water Supply IIA 400 /SC 200 /kW4 Street Light IIA
5Government institutionsetc
IIB(1)
6Private Educationalinstitutions
IIB(2)
7 Places of worship IIC
8 Cottage & Tiny Industries IIIA(1)
9 Power Loom IIIA(2)10 Commercial V
11 Industries IIIB NA 200 /kW NA 2000 /kW
12 Hut IB
13 Agriculture IVBasis for proposed charges are submitted in
2000 /kW
Nil
NilAnnexure 12
Nil
300 /Location
Nil
400 /SC 200 /SC
TariffS.No Category
Existing
Table 21Development Charges - LT (Overhead)
Proposed
2.46. HT Category: The following are submitted in respect of HT consumers:
Charges in Rupees
S.No Description Existing Proposed
1 High tension Services350/kVAwithoutceiling limit
3300 /kVA
Basis for proposed charges are submitted in
Table 22
Development Charges - HT (Over head)
Annexure 12
27
2.47. LT Category: The following are submitted in respect of LT consumers in
cable areas
Charges in Rupees
Singlephase
Threephase
Singlephase
Threephase/LTCT
1 Domestic IA 400 /SC 1400 /SC 7200 /kW 7200 /kW
2 Bulk Supply IC Nil 200 /kW Nil 7200 /kW
3 Public Water Supply IIA 400 /SC 200 /kW
4 Street Light IIA
5 Government institutionsetc
IIB(1)
6 Private Educationalinstitutions
IIB(2)
7 Places of worship IIC
8 Cottage & Tiny Industries IIIA(1)
9 Power Loom IIIA(2)
10 Commercial V
11 Industries IIIB NA 200 /kW NA 7200 /kW
12 Hut IB
13 Agriculture IV
Basis for proposed charges are submitted in
Nil Nil
Annexure 13
7200 /kW
300 /Location
400 /SC 200 /SC
Nil Nil
Table 23Development Charges - LT (Cable)
S.No Category Tariff
Existing Proposed
2.48. HT Category: The following are submitted in respect of HT consumers:
Charges in Rupees
S.No Description Existing Proposed
1 High tension Services350/kVAwithout
ceiling limit12000
Basis for proposed charges are submitted in
Table 24Development Charges - HT (cable)
Annexure 13
28
2.49. Further it is submitted that the above development charges at the
appropriate rate may also be permitted to collect as and when the consumer
approaches the TANGEDCO for the following services in addition to the new
service connections also.
(i) Whenever the consumer applies for additional loads in the existing service
connection.
(ii) When application for conversion of single phase service into three phase
service is received, the difference between the charges fixed for three phase
service and single phase service may be collected.
(iii) As regards, temporary supply one fourth of the Development charges for the
respective category may be collected.
12. Registration Charges:
2.50. It is submitted that as per Regulation 5(12) of Tamil Nadu Electricity Supply
Code Licensee shall collect the Registration Charges at the rates specified by
the Commission. In this connection, the following is submitted before the
Hon’ble Commission for consideration:
2.51. The Registration of application involves not only the registration of
application but also involves the investigation for processing the application. On
investigation only, it can be ascertained whether the application involves any
extension or improvements to the distribution network which is necessary to
prepare the necessary estimate and obtaining the sanction accordingly.
2.52. Similarly, in the case of HT services also, preliminary investigation is
considered necessary to ascertain the technical feasibility for considering the
request of the consumer as per the application.
2.53. Hence, it is submitted to change the nomenclature as “Registration – cum –
Processing Charges”.
2.54. Considering the activities involved and the man power requirement, the
following is submitted
29
Registration – cum – Processing Charges
For new service connection / additional load or reduction in load
2.55. It is prayed to approve the proposed registration cum processing charges as
submitted below:
Charges in RupeesS.No Description Existing P roposed
I Low T ension Services
1 A ll LT category except Hut 50 /SC 400 /SC
2 Hut 5 /SC 5 /SC
II LT CT Services 50 /SC 2500 /SC
III High tension Services 500 /SC 5500 /SC
Basis fo r proposed charges are subm itted in
T able 25R egistration cum P rocessing Charges
A nnexure 14
2.56. It is submitted that the above Registration charges may also be collectedfrom the HT and LT consumer approaching the TANGEDCO for the following:-
a. Whenever the consumer applies for conversion of LT services into HT servicesand vice versa
b. Whenever the consumers applies for additional load/demandc. Whenever the consumer applies for reduction of load/demandd. Whenever the consumer applies for shifting of services.e. When application for shifting lines/Structures/Equipments under Deposit
Contribution works.f. Whenever the application for Temporary Supply is applied
g. Whenever the application for change of tariff and replacement of defectivemeters
h. Whenever the consumer approaches for any other services.
13. Tariff Change:
2.57 It is submitted that at present there is no charge collected for tariff change
and now it has been proposed to collect the charge from the consumer,
considering verification, processing, sending intimation, taking revised test
report are needed. It is prayed to approve the charges for tariff change as
submitted below
30
Charges in RupeesS.No Description Existing Proposed
1Low Tension services from lower tohigher tariff
600
2Low Tension services from higher tolower tariff
1000
3 High Tension 3000
Basis for proposed charges are submitted in
Table 26Tariff Change
Nil
Annexure 15
14. Earnest Money Deposit
2.58 It is submitted that Regulation 34(1) of Tamil Nadu Electricity Distribution Codeof Hon’ble commission provides for collection of Earnest Money Deposit, fromthe Applicants. At present Earnest Money Deposit is collected in respective ofLT Industrial consumers and HT consumers. It is prayed to approve the EarnestMoney Deposit charges submitted below:
Charges in RupeesS.No Description Existing Proposed
1 Low Tension Industries 600 /kW 2000 /kW
2 High Tension 800 /kVA 3100 /kVA
Basis for proposed charges are submitted in
Table 27Earnest Money Deposit
Annexure 16
15. Security Deposit:
2.59The Earnest Money Deposit collected is converted to Security Deposit Charges
after the service is effected.
2.60 In order to safeguard the interest of the Licensee, the initial CCD equivalent to
3 months estimated current consumption charges for LT services and 2 months
estimated current consumption charges for HT services are being collected at
the time of extending supply for sanctioned load for LT services /demand
applied for HT services. It is prayed to approve the initial CCD as submitted
below:
31
Charges in Rupees
Singlephase
Threephase
Singlephase
Threephase
I LT Services1 Domestic IA 1000 /kW 1800 /kW2 Bulk Supply IC3 Public Water Supply IIA4 Street Light IIA
5Govt and Govt aidedEdu. Ins. Hostels
IIB(1)
6 Private Edu.Ins IIB(2)7 Places of worship IIC
8Cottage & TinyIndustries
IIIA(1)
9 Power Loom IIIA(2)10 Commercial V11 Industries IIIB NA 600 /kW NA 2000 /kW12 Hut IB13 Agriculture
Normal Nil NilSFS 125/HP Nil
14 LTCT Services 600 /kW 2000 /kWII High tension Services 800 /kVA 3100 /kVA
Basis for proposed charges are submitted in Annexure 16
2000 /kW
Table 28Security Deposit
600 /kW
IV
2000 /kW
Existing Proposed
Nil Nil
S.No Category Tariff
200 /SC
16. Furnishing certified copies to consumers
2.61Considering paper, Xerox cost, manpower involved), it is submitted that the
following charges may be approved on the basis of the Regulation 17 (9c) of
Tamil Nadu Electricity Supply Code.
Charges in RupeesS.No Description Existing Proposed
1 Contractor’s completion cum test report 100/sheet
2 Ledger Extract of energy charges100/Calendar yearor part thereof
3 Agreement 100/sheet4 Details of Security Deposits held 100/sheet5 Estimate 100/sheet
6Any other correspondence relating toLT/HT installation
100/sheet
Furnishing Certified Copies to Consumers
Nil
Table 29
32
Chapter 3 Prayer3 The TANGEDCO prays the Honourable Commission that
3.1 To approve the proposed charges for service connection charges as
submitted in Para 2.3 above.
3.2 To approve the proposed charges for meter rent as submitted in Para 2.9
above.
3.3 To approve the proposed charges for changing/shifting of Meter Board/LTCT
Box/HT Box as submitted in Para 2.10 above.
3.4 To approve the proposed charges for changing of meter at the request of the
consumer without any dispute in accuracy of the meter as submitted in Para
2.11 above.
3.5 To approve the proposed charges for inspection and Testing of meter when
dispute arises in the accuracy as submitted in Para 2.12 above.
3.6 To approve the proposed charges for installation testing charges as
submitted in Para 2.13 above.
3.7 To approve the proposed charges for Periodical Inspection as submitted in
Para 2.14 above.
3.8 To approve the proposed charges for rating/Re-rating of installation as
submitted in Para 2.15 above.
3.9 To approve the proposed charges for inspection and testing of consumer’s
installation for offering suggestion on request/ trouble shooting issues as
submitted in Para 2.16 above.
3.10 To approve the proposed charges for replacement of meter glass as
submitted in Para 2.17 above.
3.11 To approve the proposed charges for replacement of damaged and burnt
meter as submitted in Para 2.21 above.
3.12 To approve the proposed charges for resealing as submitted in Para 2.24
above.
3.13 To approve the proposed charges for down loading of meter reading using
CMRI as submitted in Para 2.27 above.
3.14 To approve the proposed Meter Caution Deposit as submitted in Para 2.28
above.
33
3.15 To approve the proposed charges for temporary disconnection at the request
of the consumer as submitted in Para 2.29 above.
3.16 To approve the proposed reconnection charges as submitted in Para 2.31
and Para 2.33 above.
3.17 To approve the proposed charges for replacement of consumer meter cards
as submitted in Para 2.35 above.
3.18 To approve the proposed charges for dishonoured cheque submitted in Para
2.40 above.
3.19 To approve the proposed charges for Name transfer of service submitted in
Para 2.42 above.
3.20 To approve the proposed Development charges submitted in Para 2.45 and
2.46.
3.21 To approve the proposed charges for registration submitted in Para 2.55
above.
3.22 To approve the proposed charges for Tariff change submitted in Para 2.57
above.
3.23 To approve the proposed Earnest Money deposit submitted in Para 2.58
above.
3.24 To approve the proposed security deposit submitted in Para 2.60 above.
3.25 To approve the proposed charges for furnishing certified copies to consumers
submitted in Para 2.61 above.
Sd-----19.02.2018Chief Financial Controller/Regulatory Cell,
Petitioner
34
FORM 2
&
ANNEXURES
35
FORM – 2
BEFORE THE HON’BLE TAMIL NADU ELECTRICITY REGULATORY
COMMISSION, CHENNAI
Filing No :
Case No : M.P.No of 2018
IN THE MATTER OF : Miscellaneous Petition for fixing of Miscellaneous
Charges recoverable from consumers under
various sections of Electricity Act, 2003 and
TamilNadu Electricity Supply Code and Tamil
Nadu Electricity Distribution Code of Honourable
Tamil Nadu Electricity Regulatory Commission
and Government Order.
Tamil Nadu Generation and Distribution Corporation Ltd.,(TANGEDCO),N.P.K.R.R Malaigai,144, Anna Salai,Chennai -2. ……. Petitioner
Versus
NIL ---- Respondent
Affidavit verifying the petition
I, V.UMAMAGESWARI, D/o N.VAMANAN, aged about 55 years, serving as
the Chief Financial Controller, Regulatory Cell, Tamil Nadu Generation
and Distribution Corporation Limited (TANGEDCO) having office at
No. 144, Anna Salai, Chennai–600002, do hereby solemnly affirm and
sincerely state as follows:
36
1. I am the Chief Financial Controller, Regulatory Cell of the
petitioner herein, as such I am well acquainted with the facts of
the case and authorized to file the present petition.
2. I solemnly affirm on this the 19th day of February, 2018 that the
contents of the above petition are true to my knowledge and I
believe that no part of it is false and no material has been
concealed there from.
Sd-19.02.2018
Deponent
3. Solemnly affirmed atChennai, on this the19th day of February,2018 and signed hername in my presence
}}}}}