2006 WORK PLAN

FY2006 ANNUAL WORK PLANTable of Contents - Program Work Plans

Coastal WatershedsComprehensive Everglades Restoration Plan ProgramDistrict Everglades ProgramKissimmee Restoration ProgramLake Okeechobee ProgramLand Stewardship Program Modeling & Scientific Support ProgramOperations and Maintenance ProgramRegulation ProgramWater Supply ProgramMission Support Program

1

2006 WORK PLAN

Coastal WatershedsProgram

GOALTo restore coastal watersheds and estuaries through local initiatives and partnerships; increase predictive capacity to enhance and improve water management and restoration of coastal ecosystems; and decrease flood damages District-wide through proactive flood management planning

PROGRAM COORDINATOR:Seάn Sculley

2

Coastal Watersheds Program

Continued legislative and grant funding support with the goal that the majority of funding for this program to come from dedicated sourcesPartnerships with local governments and other stakeholders through the Service Centers to implement projects

Water SupplyUtilizes technical criteria for establishing MFLsIdentifies the scientific basis for initial environmental water reservations

CERPUtilizes scientific/technical data to support local restoration projectsMonitors improvements to estuaries resulting from restoration projects

Lake Okeechobee/Operations and MaintenanceUtilizes technical data for operational decisions which account for environmental conditionsUtilizes technical data for Lake Okeechobee Water Supply and Environment Regulation Schedule refinements

District EvergladesWater quality improvements in the Everglades will benefit estuarine waters, particularly Florida Bay

The Coastal Watersheds Program involves developing and implementing projects and flood management planning activities that improve the quality, quantity, timing, and distribution of flows to coastal water bodies from their tributary watersheds. The program originated to support the technical criteria for Minimum Flows and Levels (MFLs), in partnership with the Water Supply Program, to provide scientific and technical support to SFWMD priority projects, and to develop water quality targets that may lead to Pollutant Load Reduction Goals (PLRGs) or Total Maximum Daily Loads (TMDLs). Local initiatives such as stormwater improvement projects are implemented through this program in the Service Centers. The program includes efforts to understand the effects of changing flows of fresh water to estuaries from both a water quantity and a water quality perspective, and to identify the existing legal sources of water that are beneficial to fish and wildlife. This scientific information is focused largely on salinity, seagrass, and other biological indicators, and has contributed directly to operational decisions related to the release of water from Lake Okeechobee.

KEY ASSUMPTIONS

INTERRELATIONSHIP TO OTHER PROGRAMS

3

OVERVIEW

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

Indian River Lagoon License Tag Program

Martin County:• Habitat Enhancement on Bird Island

1 Executed Agreement with The Audubon Society

• Invasive, Non-Native Plant Removal

1 Executed Agreement with The Nature Conservancy

• Girl Scout Camp Sewer Connection

1 Executed Agreement with the Loxahatchee River District

Palm Beach County:TBD 2 Executed Agreements with

selected grant recipients from Palm Beach County

St. Lucie County• Exotic Plant Removal, Replanting, Pier Access

1 Executed Agreement with St. Lucie County Mosquito Control District

• Shoreline Re-Vegetation/ Establish Mangrove

1 Executed Agreement with Environmental Learning Center

St. Lucie River Issues Team Projects

• Oyster Reef Restoration Project

2 Executed Cost-Share Agreement with Martin County

• Pollutant Load Reduction Goals for St. Lucie Estuary: Biological Responses to Limiting Nutrients

2 Executed Agreement or Work Order with Selected Vendor

Southern Indian River LagoonNo FY2006 Projects in Strategic Plan $7,656,646

Coastal Watersheds 4

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006• Correlation Among Rainfall Events, Nutrients & Phytoplankton Composition in 10 Mile Creek Area

2 Executed Cost-Share Agreement with Univ. of Florida - IFAS

• Identification and Quantification of Pesticides Entering the sty. Lucie Estuary

2 Executed Cost-Share Agreement with Univ. of Florida - IFAS

• Soil Amendment to Reduce Pollutants in Surface Runoff from Citrus Groves in the Indian River Area

2 Executed Cost-Share Agreement with Univ. of Florida - IFAS

• Phytoremediation to Remove Nitrogen & Phosphorus from Stormwaters in Detention Water Systems

2 Executed Cost-Share Agreement with Univ. of Florida - IFAS

• Septic Tank (OSDS) Impacts on the St. Lucie River and Indian River Lagoon

2 Executed Cost-Share Agreement with Florida Inst. of Technology

• Sand Scrub Conservation Easement

2 Executed Agreement with Treasure Coast Reg. Cons. Development Council

• Old Palm City - Phase III 4 Executed Agreement with Martin County

• Tropical Farms Roebuck Creek WQ Retrofit

4 Executed Agreement with Martin County

Coastal Watersheds 5

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006• Ten Mile Creek Natural Area Restoration and WQ

4 Executed Agreement with St. Lucie County

• E-8 Waterway Phase 2 WQ Retrofits

4 Executed Agreement with City of Pt. St. Lucie

• Watershed Pollutant Loading Model

4 Executed Agreement or Work Order with Selected Vendor

• St. Lucie Fish Health as Biological Performance Measures

4 Executed Agreement with NOAA Fisheries

Indian River Lagoon Initiative Projects

• Jensen Beach Impoundment Water Restoration

2 Executed Agreement with Martin County

• Salerno Creek Stormwater Quality Retrofit

2 Executed Agreement with Martin County

• Vitolo Salt March Restoration 2 Executed Agreement with St. Lucie County Mosquito Control District

• Water Quality Enhancements BMPs

2 Executed Agreement with Ft. Pierce Farms Water Control District

• Harmony Heights Stormwater Improvements Ph II

4 Executed Agreement with St. Lucie County

• FL Aquifer Well Decommissioning

4 Executed Agreement with Treasure Coast Res/Dev Cncl

Moore's Creek Retrofit Project Phases 3 & 4

4 Executed Agreement with City of Ft. Pierce

Coastal Watersheds 6

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006• Taylor Creek Streambank Erosion & Sedimentation Proj

4 Executed Agreement with Treasure Coast Reg. Cons. Development Council

• South Sewall's Point Road at Homewood

4 Executed Agreement with Town of Sewall's Point

Complete St. Lucie River Issues Team Projects:

• Hibiscus Park Stormwater Mgmt Improvement

2 Project completed

• Paradise Park Stormwater Mgmt Improvement

3 Projects completed

• Harmony Heights Stormwater Mgmt Improvement - Phase I

• Stormwater Education Project• Troop-Indiantown Water Quality BMPs• City of Stuart Stormwater Baffle Box Retrofit

Complete upgrades to the Westport Wastewater Treatment Plant

2 Project completed

Coastal Watersheds 7

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

LOXAHATCHEE RIVER AND ESTUARY

Complete technical criteria for the initial reservation for NW Fork.

Complete technical criteria for the initial reservation for NW Fork

1 Complete technical criteria

$4,021,200

Loxahatchee River Preservation Initiative Projects:

• Atlantic Ridge Hydrologic Restoration - Ph I

1 Executed Agreement with Fl Dept of Environmental Protection

• Lox River Monitoring 1 Executed Agreements with Loxahatchee River District

• Kitching Creek - Ph. IV 1• Cypress Creek Restoration - Ph I• Little Club Stormwater Quality Retrofit• Cypress Creek Restoration - Ph I

1

• Limestone Creek Rest - North• C-18 Sediment Removal 1 Executed Agreement with Jupiter

Inlet District• Community Stormwater Retrofits

1 Executed Agreements with Town of Jupiter

• Urban Stormwater Mgmt Rehab - Ph II• Limestone Creek Rest - South

Loxahatchee River/Estuary

Executed Agreements with Martin County

Executed Agreements with Palm Beach County

Coastal Watersheds 8

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006• Hydrologic Restoration of Harborview Park

1 Executed Agreement with Town of Jupiter Utilities

• Exotic Vegetation Removal 1 Executed Agreement with South Indian River Water Control Dist

Complete Loxahatchee River Preservation Initiative Projects:

Project completed

• Riverbend Park Hydrologic Improvements

2

• Jones Creek Restoration - Phase 1

2

• Jonathan Dickinson State Park Water & Sewer Lines

2

• Lox River Exotic Removal 3Complete Loxahatchee River Three Dimensional Integrated Surface and Groundwater Model

4 Model Calibrated and Verified

Coastal Watersheds 9

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

BISCAYNE BAY Biscayne Bay SWIM Projects:

• South-Central Biscayne Bay Hypersalinity Analysis

1 Executed Agreement with US Geological Survey

• Biscayne Bay Water Quality Model

1 Issue work order

• Virginia Key Restoration 1 Executed Agreement with Miami-Dade County

• Miami River Basin 21 Stormwater Retrofit

1 Executed Agreement with Miami-Dade County

• BB Blue-Way and Habitat Improvement

1 Executed Agreement with City of Miami

1 Complete Estuarine Research Federation poster "Long-Term Nutrient Trends form the Everglades Agricultural Area to Two South Florida Estuaries: A Comparison of Florida Bay and Biscayne Bay"

4 Complete Draft Report of the relationship of South Florida Water Mgmt Model output and salinity

Biscayne Bay

$4,099,250

Obtain and analyze additional Biscayne Bay science and technical data, and develop quantitative scientific tools, to effectively guide water management and restoration decisions that affect Biscayne Bay, in support of the Strategic Science Plan for Biscayne

Complete technical criteria for MFLs for South-Central Biscayne Bay -----------------Complete technical criteria for initialreservations forNorthern & Central Biscayne Bay

Coastal Watersheds 10

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

FLORIDA BAY AND FLORIDA KEYS

Complete seagrass model development and data analysis for Florida Bay and Florida Keys Feasibility Study water quality model.

Complete seagrass model development and data analysis for Feasibility Study water quality model

4 Complete seagrass model with documentation

$2,524,976

2007 -Determine water quality effects of changing operations and restoration of freshwater flow

Analyze water quality and flow data and dissolved organic matter fate results for FL Bay and Keys Feasibility Study water quality model and operations analysis

4 Interim report on water quality data analysis

Florida Keys SWIM Projects: 2• Alternative Water Supply: Desalinization Plant• White St. Outfall Elimination• Exotic Species Eradication• Benthic Habitat Eradication

Florida Keys & Florida Bay

Executed Agreements with Local Governments

Coastal Watersheds 11

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

ESTERO BAY Complete Watershed Nutrient Loading Study

Complete Watershed Nutrient Loading Study

4 Study completed$1,226,100

Develop 2D Hydrodynamic Model

Develop 2D Hydrodynamic Model

4 Model calibrated and verified

Estero Bay SWIM Projects:• Bonita Springs Stormwater Mgmt Improvement Projects

3 Executed agreements with City of Bonita Springs

Complete Ten Mile Canal Filter Marsh - Phase I

1 Project completed

Estero Bay

Coastal Watersheds 12

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

NAPLES BAY Commence data collection for hydrodynamic/water quality modeling

Commence data collection for hydrodynamic/water quality modeling

3 Executed Agreement or Work Order with Selected Vendor

Complete SWIM Plan Complete Naples Bay SWIM Plan

4 SWIM plan completed

Naples Bay SWIM Projects:

• Naples Basin Stormwater Improvements - Basin III

3 Executed Agreement with City of Naples

• Naples Basin Stormwater Improvements - Basin V

3 Executed Agreement with City of Naples

Begin Gordon River Water Quality Park design

• Begin Gordon River Water Quality Park Design

3 Executed Amendment with Collier County

Commence Lely area stormwater project

• Lely Area Stormwater Improvement Project

3 Executed Agreement with Collier County

Naples Bay

$3,230,400

Coastal Watersheds 13

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

CHARLOTTE HARBOR

Complete SWIM Plan Complete Charlotte Harbor SWIM Plan

4 SWIM Plan completed

Charlotte Harbor Initiative Projects:• Bowmans Beach Park Restoration

3 Executed Agreement with City of Sanibel

• Sanibel Wetlands Restoration Project

3 Executed Cost-Share Agreement with Sanibel-Captiva Conservation Fund

CALOOSAHATCHEE RIVER/ESTUARY

Complete Technical Criteria for Initial Reservation.

Complete technical criteria for initial reservation

4 Complete technical criteria

Caloosahatchee River/ Estuary SWIM Projects:• Caloosahatchee Nutrient Study 2 Executed Cost Share Agreement

with FL Gulf Coast University

• Hendry County Tributaries Restoration/BMPs Project

3 Executed Agreement with Hendry Co. Soil & Water Conservation District

• Glades County Tributaries Restoration/BMPs Project

3 Executed Agreement with Glades Co. Soil & Water Conservation District

• Stormwater Improvement Projects

3 Executed Agreement with East County Water Control District

$3,509,213

Charlotte Harbor

$1,051,000

Caloosahatchee River/Estuary

Coastal Watersheds 14

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006• Ft. Myers Carrell Canal Improvements

3 Executed Agreement with City of Ft. Myers

• Cape Coral Stormwater Improvements

3 Executed Agreement with City of Cape Coral

• LaBelle Stormwater Plan Implementation

4 Executed Amendment - complete planning, design and evaluation of two basins

FEMA Business Plan Projects:

• Collier County Cooperating Technical Partnership

2 Executed Agreement with Collier County

• Broward County Mapping Activity Statement

4 Work orders executed

• Palm Beach County Mapping Activity Statement

4 Work orders executed

Lake Worth Lagoon SWIM Projects

2 Executed Agreements with Palm Beach County

Miami-Dade Initiative Projects 3 Projects scopes completed and executed agreements with local governments

Complete Stormwater Mgmt Improvements Projects:

4 Projects completed

• Lake Istokpoga Canal Dredging and Sediment Removal

$12,889,051

Flood Mgmt PlanningFLOOD MANAGEMENT PLANNING

No FY2006 Projects in Strategic Plan

Coastal Watersheds 15

Coastal Watersheds - FY2006 Annual Work Plan

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006• City of Homestead Utilities

• Village of Biscayne Park• City of Coral Gables• City of Florida City• Town of Golden Beach• City of Miami Gardens• Town of Miami Lakes• City of Miami Springs• City of N Miami Beach• City of South Miami• City of Sunny Isles Beach

All On-going $2,191,510All On-going $3,710,219

$46,109,565

Other Programmatic EffortsPersonnel Program Total

Coastal Watersheds 16

2006 WORK PLAN

Comprehensive Everglades

Restoration Plan Program

GOALTo restore, preserve and protect South Florida’s ecosystem while providing for other water-related needs of the region, including water supply and flood protection

PROGRAM COORDINATOR:Lawrence Gerry

17

Comprehensive Everglades Restoration Plan Program

The SFWMD is partnering with the U.S. Army Corps of Engineers to implement the Comprehensive Everglades Restoration Plan (CERP). CERP is the largest ecosystem restoration project in the world. It includes a series of projects to take place over more than 30 years. The restoration plan is largely focused on increasing water storage, and improving the timing, quality, and distribution of water deliveries to the ecosystem. Major components include planning, design, real estate acquisitions and construction. Operation, maintenance and monitoring will follow. In 2000, Congress approved CERP under the Water Resources Development Act, and authorized the first 10 projects and 6 pilot projects. The SFWMD is the major local sponsor of CERP, as well as the related feasibility studies for Southwest Florida and Florida Bay/Florida Keys.Seven Critical Restoration Projects also are included in this program. The success of this monumental initiative will be continuously evaluated through Restoration Coordination and Verification (RECOVER).

KEY ASSUMPTIONS

INTERRELATIONSHIP TO OTHER PROGRAMS

Governing Board strategic priority: Expedite construction and operation of Everglades restoration projects through Acceler8Lands for priority projects will be acquired in

advance of the official scheduleFunding for the program will continue at least

$200M per year -- ad Valorem contribution for CERP exceeds $100M with an additional $100M in state funds. The program will be accomplished as a partnership with the U.S. Army Corps of EngineersFederal appropriations for CERP will continueMaster implementation sequencing plan will be the

baseline used to measure CERP progress

Coastal WatershedsProvides scientific/technical data to support local restoration

projectsMonitor improvements to estuaries resulting from restoration

projectsDistrict Everglades

Focuses on water quality and complements CERP focus on water storage and timing of deliveriesComponent of overall strategy for Everglades Restoration

18

OVERVIEW

Comprehensive Everglades Restoration Plan Program

INTERRELATIONSHIP TO OTHER PROGRAMS…CONTINUED

Lake OkeechobeeASR and reservoir projects will provide

additional options to enhance Lake management strategies

Operations and MaintenanceProvides O&M of Critical Restoration Projects

& other CERP worksLand Stewardship

Interim management of acquired CERP lands is dependent upon construction scheduling

Water SupplyProjects will have water resource

development benefits for implementing MFLs, water reservations, and providing additional water supplyShares development and application of

resources/tools, especially computer models and water resource planning data

RegulationCoordination of proposed permit applications

adjacent to CERP projects

19

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

Acceler8, CERP Planning and Critical Restoration ProjectsSTRATEGIES: CERP Planning Project 1 Complete Acquisition of $358,000

Implement Acceler8 Biscayne Bay Coastal Phase I Tractsin a dual-track mode; Wetlands - Phase I 1501 Pre-Application The Corps and District Meetingwill continue planning, Army Corps of Engineers:while the District, using Brief District EngineerCertificates of and Governing BoardParticipation, proceeds on Tentatively with detailed design Selected Planand construction of 3 Complete Groundwater WellPhase I (Acceler8); InstrumentationComplete Project Draft ProjectImplementation Reports; Implementation Report /Coordinate Acceler8 Environmental Impactand non-CERP projects Statement Published

in Federal RegisterMILESTONES: Army Corps of Engineers:

Complete Project Hold Alternative Implementation Report Formulation Briefing

[FY07] 4 Public and Agency ReviewStart Acceler8 of Draft Project Construction Acceler8 Project Implementation Report /

[FY07] Biscayne Bay Coastal Environmental ImpactComplete Acceler8 Wetlands - Phase I StatementConstruction Deering Estate and

[FY09] Cutler Flow-way 1 Stakeholder and Technical $746,636 Review of Basis of Design Report Complete

404 Permit Application

Acceler8, CERP Planning and Critical Restoration Projects

CERP 20

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

2 Complete Basis of DesignReport

Preliminary EngineeringNotice to Proceed

4 1502 Pre-ApplicationMeeting

1502 Permit Application404 Permit Public NoticeStakeholder and Technical

Review of PreliminaryEngineering Complete

Complete Preliminary Engineering

Intermediate DesignNotice to Proceed

STRATEGY: CERP Planning Project 2 1501 Pre-Application $1,000 Implement Acceler8 C-111 Spreader Meetingin a dual-track mode; Canal Army Corps of Engineers:The Corps and District Brief District Engineerwill continue planning, and Governing Boardwhile the District, using on Tentatively SelectedCertificates of PlanParticipation, proceeds 3 Identification of Projectwith detailed design Land Acquisition Needsand construction of to Land ManagementPhase I (Acceler8); Army Corps of Engineers:Complete Project Hold Alternative Implementation Reports; Formulation BriefingCoordinate Acceler8 4 Department of Interior:and non-CERP projects Draft Coordination Act

Report

Acceler8, CERP Planning and Critical Restoration Projects

CERP 21

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

MILESTONES:Complete Project Acceler8 Project 2 404 Permit Application $1,192,211 Implementation Report C-111 Spreader Stakeholder and Technical

[FY06] Canal Review of Basis of DesignStart Acceler8 Report CompleteConstruction Complete Basis of Design

[FY06] ReportComplete A8 3 Preliminary EngineeringConstruction Notice to Proceed

[FY09] 4 Submit for ReviewPreliminary Engineering

Intermediate EngineeringNotice to Proceed

STRATEGIES: CERP Planning Project 4 Acquisition of Flowage $902,418 Implement Acceler8 Picayune Strand Easements in Belle Meadein a dual-track mode; Hydrologic RestorationThe Corps and District Acceler8 Project 1 Levees, Canals and Site $17,651,797 will continue planning, Picayune Strand Work:while the District, using (Southern Golden Basis of Design ReportCertificates of Gates Estates) Notice to ProceedParticipation, proceeds Hydrologic Restoration Pump Station:with detailed design Stakeholder and Technicaland construction of Review of PreliminaryPhase I (Acceler8); Engineering CompleteContinue to acquire Complete Preliminary necessary lands; Engineering Coordinate Acceler8 Final Plans and Specsand non-CERP projects Notice to Proceed

Permitting and Approvals:

Acceler8, CERP Planning and Critical Restoration Projects

CERP 22

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

MILESTONES: 1502 Pre-ApplicationStart Acceler8 1502 Permit ApplicationConstruction 2 Permitting and Approvals:

[FY06] 404 Permit Public NoticeComplete Acceler8 Levees, Canals and SiteConstruction Work:

[FY09] Stakeholder and Technical Review of

Basis of Design Report Complete

Complete Basis of Design Report

Preliminary EngineeringNotice to Proceed

Submit for ReviewIntermediate Engineering

Pump Station:Submit for Review

IntermediateEngineering

3 Levees, Canals and SiteWork:

Stakeholder andTechnical Review ofPreliminaryEngineering Complete

Complete Preliminary Engineering

Final Plans and SpecsNotice to Proceed

Acceler8, CERP Planning and Critical Restoration Projects

CERP 23

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

Pump Station:Submit for Review

Pre-Final Plans and Specifications

Complete Final Plans andSpecs (Bid Package)

4 Permitting and Approvals:1502 Permit Issuance404 Permit IssuanceDepartment of Interior

Land Use ChangeApproval

Levees, Canals and SiteWork:

Submit for ReviewPre-Final Plans andSpecifications

Complete Final Plans andSpecs (Bid Package)

Pump Station:Construction Start -

Notice to Proceed

Acceler8, CERP Planning and Critical Restoration Projects

CERP 24

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

STRATEGIES: CERP Planning Project 1 Army Corps of Engineers: $4,791 Implement Acceler8 C-43 West Basin Storage Hold Alternative in a dual-track mode; Reservoir - Part 1 Formulation BriefingThe Corps and District 2 Decision Re: Acquisitionwill continue planning, of Additional Propertywhile the District, using 3 Department of Interior:Certificates of Draft Coordination ActParticipation, proceeds Reportwith detailed design 4 Draft Project and construction of Implementation Report /Phase I (Acceler8); Environmental ImpactComplete Project Statement PublishedImplementation Reports; in Federal RegisterCoordinate Acceler8and non-CERP projects Acceler8 Project 1 Department of Interior $17,679,386

C-43 West Reservoir Land Use ChangeMILESTONES: Request

Complete Project Notice to Proceed -Implementation Report Construction of Test Cells

[FY07] 2 Complete Initial Start Acceler8 Construction of Test CellsConstruction 4 Submit for Review

[FY07] Preliminary DesignComplete Acceler8 Intermediate DesignConstruction Notice to Proceed

[FY10] 404 Permit Public NoticeSTRATEGIES: CERP Planning Project 1 Public and Agency Review $0

Implement Acceler8 Acme Basin B Discharge of Draft Project in a dual-track mode; Implementation Report / The Corps and District Environmental Impactwill continue planning, Statementwhile the District, using Final Coordination ActCertificates of Report Received

Acceler8, CERP Planning and Critical Restoration Projects

CERP 25

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

Participation, proceeds 2 Governing Board Approvalwith detailed design of Letter of Supportand construction of for Project ImplementationPhase I (Acceler8); ReportComplete Project 1501 SubmittalImplementation Reports; Army Corps of Engineers:Coordinate Acceler8 Division Engineer'sand non-CERP projects Notice for Final Project

Implementation Report / MILESTONES: Environmental Impact

Complete Project StatementImplementation Report 3 1501 Approval

[FY06]Start Acceler8 CERP - Acceler8 Project 1 Submit for Review $12,730,300 Construction Acme Basin B Intermediate Engineering

[FY06] Submit for ReviewComplete Acceler8 Pre-Final Plans and Construction Specifications

[FY07] Complete Final Plans andSpecs (Bid Package)

2 1502 Permit Issuance404 Permit IssuanceConstruction Start - Notice

to Proceed STRATEGIES: CERP Planning Project 1 Army Corps of Engineers: $0

Implement Acceler8 Site 1 Impoundment Headquarters Forwardsin a dual-track mode; Completed ProjectThe Corps and District Implementation Reportwill continue planning, with Public and Agencywhile the District, using Comments forCertificates of Record of DecisionParticipation, proceeds 2 1501 Submittalwith detailed design 1501 Approval

Acceler8, CERP Planning and Critical Restoration Projects

CERP 26

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

and construction ofPhase I (Acceler8); CERP - Acceler8 Project 1 Stakeholder and Technical $3,769,742 Complete Project Site 1 Impoundment Review of Basis of DesignImplementation Reports; Report CompleteCoordinate Acceler8 Complete Basis of Designand non-CERP projects Report

Preliminary EngineeringMILESTONES: Notice to Proceed

Start Acceler8 Submit for ReviewConstruction Preliminary Engineering

[FY07] 2 Stakeholder and TechnicalComplete Acceler8 Review of PreliminaryConstruction Engineering Complete

[FY09] Complete PreliminaryEngineering

Intermediate EngineeringNotice to Proceed

1502 Pre-ApplicationMeeting

1502 Permit Application3 Submit for Review

Intermediate EngineeringFinal Plans and Specs

Notice to Proceed4 Submit for Review

Final Plans and SpecsComplete Final Plans

and Specs (Bid Package)1502 Permit Issuance404 Permit Issuance

Acceler8, CERP Planning and Critical Restoration Projects

CERP 27

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

STRATEGIES: CERP - Acceler8 Project 1 Test Cells: Complete $181,811,063 Implement Acceler8 C-44 Reservoir / Final Designin a dual-track mode; Stormwater Reservoir: Issue DraftThe Corps and District Treatment Areas Basis of Design Reportwill continue planning, (Component of Indian 1502 Pre-Application while the District, using River Lagoon - South) MeetingCertificates of 2 Complete Acquisition ofParticipation, proceeds Lands for Acceler8 with detailed design C-44 Reservoir Projectand construction of Test Cells: Issue Phase I (Acceler8); Construction Notice toContinue to acquire Proceednecessary land; Reservoir: Submit for Coordinate Acceler8 Review Final Basis of and non-CERP projects Design Report

Reservoir: PreliminaryMILESTONES: Engineering Notice to

C-44 Reservoir and ProceedStormwater Treatment 1502 Permit ApplicationAreas: 404 Permit ApplicationStart Acceler8 404 Permit Public NoticeConstruction 3 Test Cells: Initial

[FY07] Construction CompleteComplete Acceler8 Submit for ReviewConstruction [FY10] Preliminary Engineering

4 Complete Preliminary Engineering

Intermediate EngineeringNotice to Proceed

Submit for ReviewIntermediate Engineering

Acceler8, CERP Planning and Critical Restoration Projects

CERP 28

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

STRATEGIES: CERP Planning Project 1 Public and Agency Review $0 Implement Acceler8 Everglades for Draft Projectin a dual-track mode; Agricultural Area - Implementation Report /The Corps and District Storage Reservoirs - Environmental Impactwill continue planning, Phase I Statementwhile the District, using Governing Board ApprovalCertificates of of Letter of Support forParticipation, proceeds Project Implementationwith detailed design Reportand construction of 2 1501 SubmittalPhase I (Acceler8); Army Corps of Engineers:Complete Project Division Engineer's Implementation Reports; Notice for Final ProjectCoordinate Acceler8 Implementation Report /and non-CERP projects Environmental Impact

Statement

Acceler8, CERP Planning and Critical Restoration Projects

CERP 29

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

MILESTONES: 3 1501 ApprovalComplete ProjectImplementation Report Acceler8 Project 1 Submit for Review $81,389,998

[FY06] Everglades Preliminary EngineeringStart Acceler8 Agricultural Area - Intermediate EngineeringConstruction Phase 1A Notice to Proceed

[FY06] Reservoir 404 Permit Public NoticeComplete Acceler8 2 Complete Preliminary Construction Engineering

[FY09] Final Plans and SpecsNotice to Proceed

Submit for ReviewIntermediate Engineering

3 Submit for ReviewPre-Final Plans and Specifications

Complete Final Plans andSpecs (Bid Package)

1502 Permit Issuance404 Permit IssuanceDepartment of Interior Land

Use Change Approval4 Construction Start -

Notice to Proceed

Acceler8 Project 1 Preliminary Engineering $2,173,287 Everglades Notice to ProceedAgricultural Area - Submit for ReviewBolles and Preliminary EngineeringCross Canal 2 Intermediate Engineering

Notice to Proceed3 Submit for Review

Intermediate Engineering

Acceler8, CERP Planning and Critical Restoration Projects

CERP 30

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

Final Plans and SpecsNotice to Proceed

4 Submit for ReviewPre-Final Plans and Specifications

Complete Final Plans andSpecs (Bid Package)

STRATEGIES: CERP Planning Project 1 Draft Project $20,000 Implement Acceler8 Broward County Implementation Report /in a dual-track mode; Water Preserve Environmental ImpactThe Corps and District Areas Statement Publishedwill continue planning, in Federal Registerwhile the District, using Public and Agency ReviewCertificates of of Draft ProjectParticipation, proceeds Implementation Report /with detailed design Environmental Impact and construction of StatementPhase I (Acceler8); 2 Department of Interior:Complete Project Final Coordination ActImplementation Reports; Report ReceivedCoordinate Acceler8 Governing Board Approvaland non-CERP projects of Letter of Support for

Project ImplementationMILESTONES: Report

C-9 Impoundment 3 Completion of All LandC-11 Impoundment and Acquisitions for C-9 andWCA 3A/B Levee Seepage C-11 ImpoundmentsManagement Components: and Water ConservationComplete Project Area 3A/3B SeepageImplementation Report Management Acceler8

[FY06] Projects and Resolution Start Acceler8 of Associated LandConstruction Issues

Acceler8, CERP Planning and Critical Restoration Projects

CERP 31

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

[FY06] WCA 3A/3B - Complete Acceler8 1501 SubmittalConstruction C-11 Impoundment - WCA 3A/B Levee Seepage 1501 Submittal

[FY08] C-9 Impoundment -C-9 and C-11 1501 Submittal

[FY09] WCA 3A/3B - 1501 Approval

C-11 Impoundment - 1501 Approval

C-9 Impoundment -1501 Approval

Army Corps of Engineers:Division Engineer'sNotice for Final ProjectImplementation Report /Environmental Impact Statement

Acceler8 Project 1 Submit for Review $1,341,348 Water Conservation Preliminary EngineeringArea 3A / 3B Intermediate EngineeringLevee Seepage Notice to ProceedManagement 404 Permit Public Notice

2 Intermediate EngineeringNotice to Proceed

3 Complete Preliminary Engineering

Final Plans and SpecsNotice to Proceed

Submit for ReviewIntermediate Engineering

Acceler8, CERP Planning and Critical Restoration Projects

CERP 32

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

1502 Pre-Application Meeting

1502 Permit Application4 Submit for Review

Pre-Final Plans & SpecsComplete Final Plans and

Specs (Bid Package)404 Permit Issuance1502 Permit IssuanceConstruction Start - Notice

to Proceed

Acceler8 Project 1 Submit for Review $922,236 C-11 Impoundment Preliminary Engineering

404 Permit Public Notice2 Stakeholder and Technical

Review of PreliminaryEngineering Complete

Intermediate EngineeringNotice to Proceed

3 Complete Preliminary Engineering

Submit for ReviewIntermediate Engineering

Final Plans and SpecsNotice to Proceed

1502 Pre-Application Meeting

1502 Permit Application

Acceler8, CERP Planning and Critical Restoration Projects

CERP 33

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

4 Submit for ReviewPre-Final Plans & Specs

Complete Final Plans andSpecs (Bid Package)

1502 Permit Issuance404 Permit IssuanceConstruction Start - Notice

to Proceed

Acceler8 Project 1 Submit for Review $1,970,284 C-9 Impoundment Preliminary Engineering

404 Permit ApplicationDepartment of Interior

Land Use ChangeRequest

2 Stakeholder and TechnicalReview of PreliminaryEngineering Complete

Intermediate EngineeringNotice to Proceed

404 Permit Public Notice3 Complete Preliminary

Engineering Submit for Review

Intermediate EngineeringFinal Plans and Specs

Notice to Proceed1502 Pre-Application

Meeting1502 Permit Application

Acceler8, CERP Planning and Critical Restoration Projects

CERP 34

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

4 Submit for ReviewPre-Final Plans and Specifications

Complete Final Plans andSpecs (Bid Package)

1502 Permit Issuance404 Permit IssuanceConstruction Start - Notice

to ProceedMILESTONE: Critical Project 1 Complete Construction $30,000

Complete Construction Ten Mile Creek 2 Complete Installation of[FY06] Telemetry Equipment

Begin Interim Operations and Testing Phase

MILESTONE: Critical Project 1 Complete Earthwork $468,754 Complete Construction Lake Trafford for Disposal Facility

[FY07] Restoration 3 Dredging of Organic Sediment - 50 percentComplete

MILESTONE: Critical Project 3 Complete Construction $927,168 Complete Construction Lake Okeechobee of Nubbin Slough

[FY06] Water Retention / Stormwater TreatmentPhosphorus Removal Area

4 Begin Interim Operations and Testing Phase forNubbin SloughStormwater TreatmentArea

Acceler8, CERP Planning and Critical Restoration Projects

CERP 35

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

MILESTONE: Critical Project 1 Complete Installation of Three $20,280 Complete Construction Western Tamiami Trail Three - 36 inch

[FY06] Culverts Culverts (Numbers: 70a, 72a and 72b)

2 Complete Installation of Final Four Single

36 inch Culverts (72c, 73a, 73b and 75a)

Complete ProjectConstruction

MILESTONE: Critical Project 1 Complete Demolitions $7,727,193 Complete Construction Southern Corkscrew on Previously Acquired

[FY06] Regional Ecosystem Lands Watershed / Imperial 4 Complete Full LandRiver Flow-way Acquisitions /

CondemnationsSTRATEGY: CERP Planning Project 1 Complete Rescreening $1,260,000

Complete Project Lake Okeechobee of AlternativesImplementation Report Watershed 2 Brief Division Engineer

[FY07] and Governing Boardon Tentatively

Milestone not shown in Selected PlanStrategic Plan 3 Army Corps of Engineers:

Hold Alternative Formulation Briefing

4 Complete 1501 Submittal to Florida Department of

Environmental ProtectionComplete Draft Project

Implementation Report

CERP Planning Projects, Studies and

Pilot Projects, and Critical Restoration

Projects

3

Tier Two CERP Planning Projects, Studies and Pilot Projects, and Critical Restoration Projects

CERP 36

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

MILESTONES: CERP Planning Project 1 Complete Allapattah $8,531,490 C-23/24, C-25, Northfork Indian River Parcel A West Ditch Filland Southfork Lagoon - South 2 Request Modification ofComponents: and Allapattah Permit from FloridaComplete Construction Restoration Department of

[FY10-15] Environmental Protectionto add Parcel B

3 Complete Allapattah Parcel A West Initial Berm Construction

4 Initiate Allapattah Parcel B Construction

MILESTONES: CERP Planning Project 2 Identify Final Array of $46,831,399 Complete Project North Palm Beach AlternativesImplementation Report County - Part 1 3 Identification of ProjectNorth Palm Beach County - Land Acquisition NeedsPalm Beach Aggregates to Land Management

[FY09] Complete Design ofComplete Construction L-8 Pump StationPalm Beach Aggregates 4 Brief Division Engineer

[FY09] and Governing BoardPal-Mar/Corbett, C-51 and on Draft TentativelyOther Components: Selected PlanComplete Construction Complete Construction

[FY10-15] of G-161 StructureMake Payments to

Palm Beach Aggregatesand Nine Gems

Start Construction of L-8 Pump StationArmy Corps of Engineers:

Hold Alternative Formulation Briefing

CERP Planning Projects, Studies and

Pilot Projects, and Critical Restoration

Projects

CERP 37

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

MILESTONES: CERP Planning Project 1 Local Sponsor Approval $0 Complete Construction Everglades Project Management L-31 North and S-356 National Park Plan

[FY10-15] Seepage Management 2 Initiate ProjectImplementation Report

MILESTONES: CERP Planning Project 3 Complete Construction Budgeted inStart Construction Caloosahatchee (C-43) of Two Additional Deep Water Supply

[FY06] Aquifer Storage and Test Borings on Site DepartmentComplete Construction Recovery Pilot Project for FY06

[FY07]MILESTONES: CERP Planning Project 3 Surface Facility Construction Budgeted in

Complete Construction Hillsboro Aquifer Substantial Completion Water Supply[FY06] Storage and Recovery 4 Begin Two-Year Cycle Department

Pilot Project Testing for FY06MILESTONES: CERP Planning Project 4 Army Corps of Engineers: $2,645,040

Complete Construction Aquifer Storage Prepare Draft Screening[FY10-15] and Recovery Model of Floridan Aquifer

Regional Study Install Test Well Pair atPalm Beach AggregatesSite

MILESTONES: CERP Planning Project 1 Complete In-Progress $0 Complete Project Melaleuca Review for DraftImplementation Report Eradication Project Implementation

[FY07] and Other ReportStart Construction Exotic Plants 2 Army Corps of Engineers:

[FY09] Receive ProjectGuidance Memorandumfrom South AtlanticDivision and Headquarters

3 Army Corps of Engineers:Hold AlternativeFormulation Briefing

CERP Planning Projects, Studies and

Pilot Projects, and Critical Restoration

Projects

CERP 38

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

DISCUSSION: CERP Planning Project 1 Complete Initial Screening $279,466 The District is the Local Southwest Florida of AlternativesSponsor for Feasibility Feasibility Study 2 Army Corps of Engineers:Studies Hold Feasibility Scoping

MeetingDISCUSSION: CERP Planning Project 2 Complete Integration of $683,000

The District is the Local Florida Bay / Water Quality ModelSponsor for Feasibility Florida Keys 3 Complete Modeling of Studies Feasibility Study Management Scenarios

4 Complete Modeling ReportComplete Transfer of

Technology (Training Session)

STRATEGY: Related Project 1 Final Alternative $1,307,682 Coordinate non-CERP C-111 / Modified Water Formulationprojects; this project is the Deliveries / Combined Recommend Tentativelyprecursor to many CERP Structural and Selected Planprojects and components Operations Plan

STRATEGY: CERP - Program Element 1 Complete Performance $112,020 Implement program-level Restoration Measure Document management activities Coordination Report

Verification - 3 Complete Conceptual MILESTONE: RECOVER Aquifer Storage and

Complete Conceptual Recovery Contingency Aquifer Storage and PlanRecovery Contingency 4 Complete Sea Level RisePlan Sensitivity Analysis

[FY06]

CERP Program-Level Budget Elements

Program-Level and RECOVER Milestones

CERP Planning Projects, Studies and

Pilot Projects, and Critical Restoration

Projects

CERP 39

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

STRATEGY: CERP - Program Element 1 Implement Community $596,000 Implement program-level Public Involvement Partnership for CERP ad valoremmanagement activities; and Outreach and Acceler8Outreach and partner with 4 Complete First Year Jobs stakeholders and Training / Workforce community Development Program

STRATEGY: CERP - Program Element 3 Complete Urban Corridor $20,000 Implement program-level Environmental and Analysismanagement activities; Economic Justice Complete Economic Outreach and partner with Justice Mapsstakeholders and 4 Complete Equity Programcommunity Plan Revision

STRATEGY: CERP - Program Element 3 Complete Information and $1,651,078 Implement program-level Information and Data Data Program management activities Management Management Plan

Revision4 Move Project Management

System from CERPZoneinto South Florida WaterManagement DistrictEnvironment

Program-Level and RECOVER Milestones

CERP 40

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

STRATEGY: CERP - Program Element 1 Army Corps of Engineers: $0 Implement program-level Master Recreation Complete Geographicmanagement activities Plan Information System

Maps3 Army Corps of Engineers:

Complete Master Recreation Plan ProgramAnalysis Report forCERP and Acceler8

STRATEGY: CERP - Program Element 1 Complete Regional Model $2,227,857 Implement program-level Interagency Modeling (South Florida Watermanagement activities Center (System-wide Management Model)

Modeling) Documentation PeerReview

2 Complete Regional ModelRuns for Aquifer Storageand Recovery ContingencyPlan

Complete Final Draft of Interagency Modeling

Center Business Processes Document

3 Complete Regional ModelRuns for Sea Level RiseSensitivity Analysis

4 Develop and ImplementRegional Simulation ModelTransition Training Planfor Interagency ModelingCenter Staff

Program-Level and RECOVER Milestones

CERP 41

Comprehensive Everglades Restoration Plan and Acceler8

Strategic Plan Category

Strategic Plan - Deliverables and Milestones Annual Work Plan Projects

Quarter

Annual Work Plan - Success Indicator Annual Budget

2006 2006 2006 2006 2006

STRATEGY: CERP - Program Element 1 Complete Monitoring and $5,380,287 Implement program-level Adaptive Assessment Assessment Plan (MAP 2)management activities and Monitoring Implementation Reportincluding adaptive 2 Complete Adaptiveassessment and Management Strategymonitoring 3 Complete Annual

Assessment Reports for:MILESTONE: ▪Greater Everglades

Complete Annual ▪Southern EstuariesAssessment Report ▪Northern Estuaries

[FY06] ▪ Lake OkeechobeeComplete Adaptive

Management Recommendation forDecompartmentalization

Complete Annual System- Wide Assessment

All On-going $27,312,773All On-going $11,711,426

$444,387,410

Other Programmatic EffortsPersonnel Program Total

4

Program-Level and RECOVER Milestones

CERP 42

2006 WORK PLAN

District Everglades Program

GOALRestore Everglades water quality, hydrology and ecology

PROGRAM COORDINATOR:Dean Powell

43

District Everglades Program

The District Everglades Program is focused on the SFWMD’s responsibilities outlined in the Everglades Forever Act and the Settlement Agreement of the Federal Lawsuit. The Everglades Construction Project (ECP) is the first major step in Everglades Restoration and part of the Everglades Forever Act, passed by the Florida Legislature in 1994. This Act directs the District to acquire land and design, permit, construct and operate a series of Stormwater Treatment Areas (STAs) in order to reduce phosphorus levels from stormwater run-off and other sources before it enters the Everglades Protection Area. The Everglades Forever Act also requires that the District investigate technologies that may be superior to the STAs, and to implement basin-specific solutions to achieve compliance with long-term water quality standards. During the 2003 legislative session, the 1994 Everglades Forever Act was amended to include the Conceptual Plan for Achieving Long-Term Water Quality Goals (Long-Term Plan) as the appropriate strategy for achieving the long-term water quality goals for the Everglades Protection Area.

Governing Board strategic priority: Achieve Everglades water quality standards

Dedicated revenues fund all research, monitoring, engineering and construction activities for DistrictEverglades projects based on expansion of the Everglades Forever Act

CERPComplements District Everglades focus on water quality by

focusing on water storage and timingof deliveries to the Everglades

Water quality and hydrologic improvements in the Everglades will benefit estuarine waters, particularlyFlorida Bay

Maintaining and operating Stormwater Treatment Areas structures, pump stations and leveesCoastal Watersheds

Component of overall strategy for Everglades RestorationOperations & Maintenance

KEY ASSUMPTIONS

INTERRELATIONSHIP TO OTHER PROGRAMS

44

OVERVIEW

District Everglades

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006Accelerated Everglades

Forever Act (EFA) Projects

1 Notice to Proceed on 30% design; Submit 30% design in Qtr 1

2 Complete 30% design;Notice to Proceed 60% Design

3 Complete 60% design; Start 90% design

1

Submit final 100% Plans & Specs for *STA 6 Section 2; Start Procurement Process for Construction for STA 6 Section 2; Complete Plans and Specs for STA 5 Flow-way 3; Start procurement process for Construction STA 5 Flow-way 3; Complete Draft Basis of Design Report for Build-out*Stormwater Treatment Area (STA)

2

Notice to Proceed for construction on STA 6 Section 2; Complete Final Basis of Design Report (BODR) for Buildout; Notice to Proceed for construction on STA 5 Flowway 3

3 Start Pump Procurement Process for Build-out; Initiate Design of Build-out

4 Complete Final Plans and Specs for Build-out

Everglades Agricultural Area (EAA) Feasibility Study

1 Complete EAA Feasibility Study $83,000

$23,638,706

Compartment B Cell 4 $20,648,004

Compartment C STA 6 Section 2

STA 5 Flow Way #3

Final Everglades Construction project (STA 6

Section 2)

Everglades Construction

Project(ECP)

EvergladesForever ActAccelerated

Projects

Everglades 45

District Everglades

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006Ancillary work to complete STA 1 East

4 Complete ancillary work $732,520

VegetationManagement 4

Complete conversion to Submerged Aquatic Vegetation (SAV) in cells 2, 4N, 4S and 6

Cell 1 Levee Construction

4 Complete construction

Vegetation Management

4 Complete conversion to SAV in cells 1B and 3

Cell 3 Levee Construction

2 Complete construction

Vegetation Management 4 Complete conversion to SAV in cells 1B and 3B

Cell 2B Levee Construction

4 Complete construction

Vegetation Management 4 Complete conversion to SAV in Cell 2B

VegetationManagement

4 Complete conversion to SAV in cells 2, 4N, 4S and 6

Stormwater Treatment Area Projects

STA Enhancement ProjectsEvaluation of full-scale STA Enhancements

$12,662,033

STA 1E

STA 1W

STA 3/4

STA 5 Long

Ter

m P

lan

Impl

emen

tatio

n

STA Enhancements

Everglades 46

District Everglades

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Operation & Maintenance (O&M) of STAs

VegetationMaintenance 4

3,500 acres of aquatic vegetation treated by end of Qtr. 4. 5,000 acres of emergent vegetation treated by the end of Qtr. 4

Monitoring and reporting requirements for all Everglades Construction Project operating permits

All Reports submitted monthly and annually per permit requirements

1

Field sampling procedures developedData collection commences

2Final report submitted with presentation to Technical Oversight Committee

Annual vegetation surveys within STAs

4 Surveys are conducted from May through September

Annual water quality collection within each cell of the STAs

4 Water samples are taken during vegetation survey and analyzed for Phosphorus and Nitrogen species.

$4,604,922

Calculation of Phosphorus budgets for each major flow-path for each STA.

4 Update table of Phosphorus budgets for annual South Florida Environmental Report.

Monitoring Phosphorus removal effectiveness of STA-3/4 Periphyton-Assisted Stormwater Treatment Area (PSTA) project

All Reports submitted monthly and annually per permit requirements

Stormwater Treatment Area Operation and Maintenance

$11,191,618

STA Optimization and Performance

Installation/Implementation of Total Flow Proportional Samplers at S-319 and S-

362 (STA1E)

Everglades 47

District Everglades

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006Phosphorus Source Control ProgramUpdated water quality data for water year 2005, for all Everglades CP (including EAA and C-139 basins) and non-ECP basins in South Florida Ecosystem Report

2 Include report in South Florida Ecosystem Report

Annual update on water quality improvement projects

2 Include update in South Florida Ecosystem Report

Allocate all grant funds 4 Contracts awarded

Recovery of Impacted areas within the Everglades Protection AreaImplement and conduct research programs regarding accelerated recovery.

All Water samples will be taken eight times with about 40 samples per event, soil and vegetation samples will be sampled 4 times with about 36 and 24 samples each event, respectively.

3 Development of plots for wildlife usage

4 Completion of spraying and burning of plots

$2,859,045

Complete annual Everglades Status Reports

Implementation of Cattail Habitat Improvement Project- experiment to

assess accelerated habitat recovery as a result of

ecosystem manipulation

$1,332,637

Everglades 48

District Everglades

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Publication for the development and monitoring of a Complexity and Health Tree Island Index (CAHTI) that will be used to monitor how islands change as a function of hydrology

Annual Report

2 Complete semi-annual report

4 Complete semi-annual report

Wildlife Studies3 Draft annual report

4 Compile reportIssue Final annual report

Ecosystem StudiesComplete annual Everglades Status Reports

Softwater/hardwater response research project

4 Project review and data analysis. Completion of spatial sampling of Loxahatchee National Wildlife Refuge and begin preliminary data analysis

Loxahatchee Impoundment Landscape Assessment (LILA)

4 Complete detailed Work Plan and Deliverable Schedule for tree island experiments that are associated with a new 3-year Florida International University contract.

On-going $5,233,651On-going $11,686,303

$102,031,755

Other Programmatic EffortsPersonnel Program Total

Research & Evaluation

$7,359,316

Vegetation Studies

4

Res

earc

h an

d Ev

alua

tion

Establish Everglades tree tolerances for

hydrologic stress anddefine water depth

and hydrologic needs for marsh

species

Tree Island Research

Lygodium Research Contracts

Everglades 49

2006 WORK PLAN

Kissimmee Restoration Program

GOALTo restore the ecological integrity of the Kissimmee River and floodplain ecosystem; improve water quality, water supply, natural resources and flood control level of service in the Kissimmee Upper Basin; and regulate the headwater and river system to balance impacts to the upper and lower basins.

PROGRAM COORDINATOR:Ruth Clements

50

Kissimmee Restoration Program

The historic Kissimmee River originated at Lake Kissimmee and meandered for 103 miles, through a 1-3 mile wide floodplain, to Lake Okeechobee. Severe flooding throughout central Florida in the late 1940s prompted the state to petition the federal government to prepare a flood control plan for central and southern Florida.

In 1948, Congress authorized the U.S. Army Corps of Engineers (USACE) to initiate construction of the Central and Southern Florida Project. Implementation of the 1962-1971 flood control project replaced the Kissimmee River with a 56 mile long, 300 ft. wide, 30 ft. deep drainage canal (C-38). Water control structures and related features also were built in the upper lakes region. Although the project was extremely successful at achieving flood control, channelization drained 36,000 acres of floodplain wetlands and led to drastic declines in wildlife and ecosystem function.

In 1992, Congress authorized the Kissimmee River Restoration and the Headwaters Revitalization Projects - a $578 million partnership between USACE and SFWMD (local sponsor). Activities include 105,000 acres of land acquisition; canal filling, reconnection of existing remnant river reaches, including carving of new river reaches; structure modification, removal and replacement; and a comprehensive monitoring program to evaluate restoration project success.

KEY ASSUMPTIONS

Governing Board strategic priority: acquire land for Kissimmee River Restoration

U.S. Army Corps of Engineers will identify all necessary lands for Kissimmee River Restoration

Adequate funding to purchase lands will be available

Sufficient funding for Restoration Evaluation

Project requirements

51

OVERVIEW

Kissimmee Restoration ProgramINTERRELATIONSHIP TO OTHER PROGRAMS

CERP/Lake OkeechobeeKissimmee River Restoration will have downstream benefits for CERP & Lake Okeechobee

Operations & MaintenanceKCOL Long Term Management Plan will provide data to support regulation schedule alternatives

Land StewardshipProvides interim and long-term management of acquired lands

Water Supply Development of technical criteria for minimum flows and levels, and for initial reservations

52

OVERVIEW (continued)

Over 7 miles of backfilling of Phase I were completed in 2001, and work is under way to design and model the extent of backfilling necessary for Phases II, III and IV. Per accordance with the Project Cooperative Agreement between the USACE and the District, monitoring of restoration evaluation continues to quantify the success of the efforts undertaken to date. Another aspect is that much of the water flowing to the Kissimmee Chain of Lakes (KCOL) and the Kissimmee River originates in rapidly urbanizing basins north of the KCOL - in the Kissimmee Upper Basin. The Kissimmee Upper Basin Restoration Initiative is a partnership between the SFWMD and local governments to annually fund water resource projects to improve downstream water quality, water supply, natural resources and flood control levels of service.

Another on-going initiative in the Kissimmee Upper Basin is the KCOL Long Term Management Plan (LTMP). The purpose of this initiative is to create a coordinated, multi-disciplinary framework for resolving water management issues in the Kissimmee Chain of Lakes.

These issues will be formalized in a Conceptual Ecosystem Model that will then be used to generate Agency Action Plans that will describe how participating agencies will address agreed upon issues through their mandates.

Kissimmee Restoration

Strategic Plan Category Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

2Confirm Chandler Slough KRR project land requirement from USACE

3 Initiate and complete up to 15% of Chandler Slough land acquisition if required by USACE

4complete up to 50% of Chandler Slough land acquisition, if required by the USACE

4 FPC Flood Protection Project complete and initiate Basinger Grove construction

4 Conceptual plan for Catfish Creek complete

4Packingham Slough pump and culvert construction 30% complete

2Produce Hydrologic performance measures for the Kissimmee River

2South Florida Environmental Report published

Proposed Phase IV A Backfilling KRR Restoration Evaluation 3Initiate and lead monitoring and multi agency field coordination efforts for construction

KISS

IMM

EE R

IVER

RES

TOR

ATIO

N A

ND

HEA

DW

ATER

S R

EVIT

ALIZ

ATIO

N

Tier Two Projects

Phase 1 Restoration Evaluation

Develop technical criteria for initial water reservation for the

Kissimmee RiverKRR Restoration Evaluation 4

Start technical basis for Initial Water Reservations (IWR) Kissimmee River Rulemaking

$39,472,440

Complete Chandler Slough land acquisition meaning land acquisition for Kissimmee

Restoration complete

Complete KRR Land acquisition. Initiate and complete up to 50%

of Chandler Slough land acquisition

KRR Construction/Mitigation in lieu of Land Acquisition

Kissimmee 53

Kissimmee Restoration

Strategic Plan Category Strategic Plan - Deliverables and

Milestones

Annual Work Plan Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

3Produce hydrologic Performance Measures for lakes

3 Initiate Public workshops on performance measures and plan formulation

4Model calibration and verification 75% complete

4Initiate alternative evaluations of system operations

2 Develop performance measures for Chain of Lakes

2 South Florida Environmental Report published

3 Initiate Agency Action Plans & Data Collection and Monitoring Plans

4 Draft KCOL LTMP document released for public review

2 Execute cooperative agreements with St. Cloud and Orange County

2 Work initiated on all projects

3 Receive 1st deliverables and/or achieve 1st milestones on all projects

4 Receive final deliverables and close work orders on all projects

All On-going $19,483All On-going $3,393,282

$47,160,508

Other Programmatic EffortsPersonnel Program Total

KUB RestorationAnnually develop and complete local water resource partnership

projects

$118,753

Chain of Lakes Complete KCOL LTMP

$4,156,550

St. Cloud Stormwater Grid - Phase 2; Holden Heights Stormwater Improvements - Phase 3; West Orange Basin Model

Chain of Lakes Complete KCOL LTMPKissimmee Chain of Lakes Long Term Management Plan (KCOL LTMP)

KRR Kissimmee Watershed Hydrologic Assessment Modeling

and Operations Plan

Kissimmee 54

2006 WORK PLAN

Lake Okeechobee Program

GOALTo improve the health of the Lake Okeechobee ecosystem by improving water quality, reducing or eliminating exotic species and better managing water levels.

PROGRAM COORDINATOR:Susan Gray

55

Lake Okeechobee Program

The Lake Okeechobee Program is focused on the development and implementation of management activities that will allow the lake to support a greater diversity of native plants and animals while providing flood protection, water supply, navigation and recreation. Lake Okeechobee is the "liquid heart" of South Florida's interconnected aquatic ecosystem. The lake provides a number of values and benefits to the state's population and environment, including water supply for agriculture, urban areas and the environment; flood protection; a multi-million dollar sport and commercial fishery; and habitat for wading birds, migratory waterfowl, and the federally endangered Everglades Snail Kite. The Lake Okeechobee program is geared toward solving three major problems facing the lake and its watershed: (1) excessive nutrient loading; (2) extreme high and low water levels in the lake; and (3) exotic species. As required by state legislation, the South Florida Water Management District - in cooperation with the Florida Department of Environmental Protection, Florida Department of Agriculture and Consumer Services, and public/stakeholders input - completed the Lake Okeechobee Protection Plan (LOPP) in January 2004. The completed plan contains an implementation schedule for subsequent phases of phosphorus load reduction in order to meet the target goal of 140 metric tons by the year 2015. The plan also contains required elements of exotic species control and research and monitoring.

KEY ASSUMPTIONS

Governing Board strategic priority: reduce phosphorus inputs to Lake Okeechobee

Annual funding support ($5.0M) from the state legislature to implement the LOPP

56

OVERVIEW

Lake Okeechobee Program

INTERRELATIONSHIP TO OTHER PROGRAMSKissimmee Restoration

Kissimmee River Restoration will have downstream benefits for Lake Okeechobee

Coastal WatershedsProvides technical data for operational decisions which account for environmental conditions

Lake Okeechobee Water Supply and Environment regulation schedulerefinements

Operations and MaintenanceEnvironment Regulation schedule impacts inflow/outflow structure operations

Melaleuca and torpedo grass plant control within the Lake

CERPLake Okeechobee ASR projects will provide additional options to

enhance Lake management strategies

Lake Okeechobee Watershed project will provide essential water and storage benefits

Water SupplyDevelopment of technical criteria for minimum flows and levels and initial reservations

57

Lake Okeechobee

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

LAKE RESEARCH AND ASSESSMENT

1 Prepare and submit documentation for temporary planned deviation for spring recession subject to Governing Board go ahead

$639,650

2 Begin spring drawdown for Lake Okeechobee if conditions are suitable

3 Evaluate lake responses to spring drawdown.

4 Continue to support USACE long term regulation schedule evaluations and NEPA process

SPRING RECESSION PROJECT - Boat Marina and Harbor Dredging

1 Initiate procurement of contractors to determine amount of sedimentation that has occurred since last recession

Tier Two ProjectsEvaluation and refinements of the Lake Regulation Schedule (continue from FY05) - Environmental Assessment and / or Environmental Impact Statement

Continue refinements to the Lake Water

Supply and Environment

Regulation Schedule with the collaboration

of the USACE (through 2008)

Lake Okeechobee 58

Lake Okeechobee

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20062 Mobilize contractors to conduct

sediment removal if necessary

3 Continue Sediment Removal

4 Complete Sediment Removal

1 Plant harvested seeds for generation; complete seed germination Study

2 Re-initiate POs for revegetation

3 Plant pond apples and cypress trees

4 PO closeout and evaluation1 Complete plans and

specifications for south pumps; conduct feasibility of L-59, L-60 canal dredging

2 Bid for temporary forward pumps

3 Install temporary forward pumps

1 Develop scope

2 Initiate contract to determine pump size, location, canal improvements

SPRING RECESSION PROJECT - Temporary Forward Pumps

SPRING RECESSION PROJECT - Native Plant Revegetation Efforts

Fast Track - Permanent Forward Pumps

Lake Okeechobee 59

Lake Okeechobee

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20064 Complete Hydrology and

Hydraulics analyses; initiate design

1 Conduct quarterly survey

2 Conduct quarterly survey

3 Conduct quarterly survey

4 Conduct annual survey

1 Public workshop to present rule amendments and solicit

2 Rule presented to board for adoption.

Complete Annual Lake Okeechobee

Assessment

Conduct quarterly and annual submerged aquatic

plant surveys to assess Lake condition

WATERSHED MANAGEMENT

Tier One ProjectsComplete Works of the District Rule Amendments

Other Projects

Lake Okeechobee 60

Lake Okeechobee

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1 Hold public workshop, complete work plan, obtain permits

2 Okeechobee County executes agreement with dredging contractor and begins work

3 Complete Phase I of dredging project

2 Initiate agreement

3 Initiate design and permitting

4 Complete design

1 Design approval with Tribe

2 Initiate design and permitting criteria.

3 Initiate construction

4 Construction at 50%

Former Dairy Remediation (Continue from FY05)

1 Finalize 100% design plans at Pilgrim Dairy. Initiate 30% design plans for former Larson 7

Complete Taylor Creek tributaries dredging (Continue from FY05)

$4,357,102Other Projects

Construct pilot storage/treatment facility on public or private properties

Design and construct a shallow 800 acre reservoir on the Brighton Seminole

Reservation.

Lake Okeechobee 61

Lake Okeechobee

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20062 Construction mobilization on

Pilgrim Dairy; finalize 100% design for Larson 7 and complete permit application.

3 Construction mobilization for Larson Dairy; complete 1-yr performance monitoring on former Mattson, Candler and McArthur 5 dairies. Initiate monitoring at Pilgrim and Larson 7.

4 Continue performance monitoring at Pilgrim and Larson.

500 acres of melaleuca annually

Treat 2,000 acres of torpedo grass and 500 acres of melaleuca

4 Complete by 4th quarter $1,212,750

4,000 acres of torpedo grass annually

Control the expansion of cattails into Key fisheries habitat

4 Complete by 4th quarter

EXOTIC CONTROL ACRES TREATED

Lake Okeechobee 62

Lake Okeechobee

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1 Initiate Feasibility Study; Initiate Field Data Acquisition

$30,000,000

2 Complete Feasibility Study; Initiate Component Design

3 Permit Pre-application Meetings; Complete 30% Design

4 Complete 60% Design1 Complete land acquisition for

Phase I (77 acres)

2 Initiate land acquisition for Phase II

3 Complete design and initiate permitting for Phase I

4 Complete permitting for Phase I

1 Complete design and permitting

2 Initiate construction

3 Construction 30% complete

4 Construction 60% complete

All On-going $34,176All On-going $3,025,736

$50,764,681

Other Programmatic Efforts

Nubbin Slough STA expansion (Continue from

FY05)

Tier Two ProjectsRESTORATION

PROJECTSLake Okeechobee Fast TrackTaylor Creek and Nubbin Slough

Complete land acquisition for urban stormwater project

(through 2007)

Lemkin Creek Urban STA (Continue from FY05)

$11,495,267

Program TotalPersonnel

Lake Okeechobee 63

2006 WORK PLAN

Land Stewardship Program

GOALTo restore conservation and preservation lands to a natural condition, provide compatible public access, and efficiently manage project lands

PROGRAM COORDINATOR:John Dunnuck

64

Land Stewardship Program

The Land Stewardship Program manages property and associated water areas owned or controlled by the South Florida Water Management District. Lands are protected, enhanced, restored, and preserved for project purposes and for the use and enjoyment of existing and future generations. The program began in 1981 with passage of the state's Water Management Lands Trust Fund, which enabled the state's water management districts to buy lands needed for water management, water supply, and the conservation and protection of water resources - and to make them available for appropriate public use. Since that time, the SFWMD and its acquisition partners have purchased 310,000 acres of environmentally sensitive lands (not counting 800,000 acres in the three Water Conservation Areas that were acquired prior to 1981). Water resource projects, or those lands associated with the Comprehensive Everglades Restoration Plan consisting largely of impacted agricultural lands, have added another 145,000 acres. The program has direct management responsibility for 177,000 acres in 13 projects, including two mitigation banks and several regional mitigation areas. For the 133,000 acres of non-District managed lands, agreements or leases have been entered into with other agencies or local governments. The Land Stewardship Program includes activities to restore lands to their natural state and condition, manage them in an environmentally acceptable manner, and to provide public recreational opportunities that are compatible with protecting natural resources. Program activities include: developing and implementing land management plans, controlling invasive exotic plants, restoring natural fire regimes, restoring native communities, employing multiple use practices, and opening lands for appropriate public use.

KEY ASSUMPTIONSContinued state funding through the Water Management Lands Trust Fund for land management efforts

Utilize available resources from mitigation programs for land management purposes

Interim management of acquired CERP lands is dependent upon construction scheduling

65

OVERVIEW

Land Stewardship Program

INTERRELATIONSHIP TO OTHER PROGRAMS

CERPProvide interim and long-term management of acquired lands dependent on construction scheduling

Kissimmee RestorationProvide interim and long-term management of acquired lands

Operations and MaintenanceProvide exotic plant control for District-owned lands and mitigation projects

66

Land Stewardship

Strategic Plan Category Strategic Plan - Deliverables

and Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Complete and Accept Phase I

3 Complete data scrub

NEW STEWARDSHIP MANAGEMENT PLANS

Upper Reedy CreekKissimmee River Pool A

New Stewardship Management Plans 4 Complete 100% of New

Management Plans by Quarter 4Steward ship Management

Plans UpdateCREWNicodemus Slough Stewardship Management

Plans update 4 Complete 100% of updated Management Plans by Quarter 4

1 Treat 4,650 acres of Exotics

2 Treat 10,850 acres of Exotics

3Complete Rough Island

RestorationTreat 10,850 acres of Exotics

4 Treat 4,650 Exotics

1 Perform 2,400 Acres of Prescribed Burns

2 Perform 5,600 Acres of Prescribed Burns

3 Perform 5,600 Acres of Prescribed Burns

4 Perform 2,400 Acres of Prescribed Burns

$7,499,306

Internal Resources

ACRES TREATED FOR EXOTICS ON PUBLIC

LANDS31,000 Land Stewardship

ACRES OF PRESCRIBED FIRES 16,000 Land Stewardship

Not highlighted in Strategic Plan

INTEGRATED REAL ESTATE INFORMATION SYSTEM

(IRIS)$1,233,000

Projects

Land Stewardship 67

Land Stewardship

Strategic Plan Category Strategic Plan - Deliverables

and Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Final Approval to submit documents to State

2 Submit Public Use Rule to State for Approval

DEVELOP RECREATION MASTER PLAN DRAFT

4

Develop Land Stewardship Recreation Master Plan

incorporating local agency plans with phased approach for review

by LRC.

Internal Resources

LOXAHATCHEE MITIGATION BANK Recover Investment 4 Receive revenues to cover initial

investment ($300k) All On-going $14,266,550All On-going $4,077,868

$28,971,024Personnel Program Total

$1,894,300

Other Programmatic Efforts

UPDATE AND REVISE PUBLIC USE RULES

Land Stewardship

Land Stewardship 68

2006 WORK PLAN

Modeling & Scientific Support

ProgramGOALTo provide technically sound modeling and scientific services in support of District water resources programs

PROGRAM COORDINATOR:

Linda Lindstrom

69

Modeling & Scientific Support Program

District programs depend on scientific support and computer modeling for all aspects of water management. This program centralizes these major functions.

As recommended in the Strategic Modeling Plan, this program includes the development, implementation and migration of the next-generation Regional Simulation Model (RSM) to replace current regional models; the implementation of the Capability Maturity Model (CMM) for all model development and implementation; and modeling oversight, peer review, scope review, model library and data set creation.

This program also includes water quality monitoring and assessment operations. Water quality monitoring systems track ecosystem status and the performance of District projects including information needed to meet legal and regulatory requirements. Activities included are regional-scale water quality monitoring, laboratory operations, quality assurance/quality control, data stewardship, and associated support services. An Environmental Monitoring Coordination team has been established to manage and oversee all District monitoring activities. This program is also responsible for theannual production of the South Florida Environmental Report (SFER) – which provides scientific and engineering status and findings

70

KEY ASSUMPTIONS

Recognition that the regional modeling and monitoring efforts are key District functions which are essential for the planning, construction, assessment and management of water resources as outlined in priority District programs, and thus require continued funding to maintain continuity.

Continued functioning of Modeling Oversight and Environmental Monitoring Coordination Teams for assistance in prioritizing all modeling and managing all monitoring, respectively.

Continued availability of hydrologic, water quality and ecological data for modeling and resource assessments.

Outsourcing can be used to handle increases in modeling, monitoring and assessment workload.

OVERVIEW

Modeling & Scientific Support Program

Coastal WatershedsProvides data required to assess water quality conditions in all major coastal estuaries which supports local restoration efforts Supports development of water quality targets for PLRGs and TMDLsPerforms emergency monitoring during pulse releases from Lake Okeechobee to the Saint Lucie and Caloosahatchee estuariesProvides RSM support, identifies modeling needs and ensures adherence to modeling standards developed by this programCERPProvides the water quality monitoring network and data for the CERP Monitoring and Assessment Plan which will monitor system-wide performance of CERPProvides ambient or baseline data for the Acceler8 and CERP projects from which to measure project performance as well as the infrastructure to support project-level water quality monitoringProvides RSM support, identifies modeling needs and ensures adherence to modeling standards developed by this programDistrict EvergladesProvides the infrastructure to support water quality monitoring required for the Everglades Forever Act operational permits, STA optimization studies, and Everglades Stormwater Program stipulated by the Long Term Plan to achieve Everglades water quality standardsConducts the water quality monitoring and assessment for the Everglades Settlement AgreementProvides RSM support, identifies modeling needs and ensures adherence to modeling standards developed by this program

INTERRELATIONSHIP TO OTHER PROGRAMS

71

Modeling & Scientific Support Program

Kissimmee RestorationProvides monitoring network and data required to assess water quality conditions of the Kissimmee River, the Upper-Chain-of-Lakes and performance of restoration effortsProvides RSM support, identifies modeling needs and ensures adherence to modeling standards developed by this programLake OkeechobeeProvides monitoring network and data required to assess water quality of the lake interior and its in-flows and out-flows in support of the Lake Okeechobee Protection Plan and the Operating PermitProvides the infrastructure to support water quality monitoring in the Okeechobee Watershed and for local restoration projects.Performs emergency monitoring of Lake Okeechobee pulse releasesProvides RSM support, identifies modeling needs and ensures adherence to modeling standards developed by the programWater SupplyProvides the infrastructure to support ground water quality monitoringProvides RSM support, identifies modeling needs and ensures adherence to modeling standards developed by the programOperations and MaintenanceProvides water quality data needed to support operational decision-makingDepends on timely collection and processing of hydrometeorologic data for modeling and resources assessmentsProvides RSM support

INTERRELATIONSHIP TO OTHER PROGRAMS

72

Modeling and Scientific Support

Strategic Plan Category Strategic Plan - Deliverables

and Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Complete RSM implementation for South Florida 1 Part I Peer Review: RSM Theory

4 Documentation of the RSM 2005 calibration

Implement standardized methodology for RSM development (level 2 CMM)

2 Complete CMM gap analysis

Develop and implement Standardized Modeling Protocols (level 2 CMM + peer review)

4 Complete Standardization methodology (CMM level 2+ peer review

Modeling Oversight Create a formal Library of Models

Modeling Oversight3

Initiate creation of a formal Library of Models

$157,500

Water Quality Monitoring Optimization Complete Water Quality Network

Optimization

Water Quality Monitoring Network

Optimization

3 Completion and approval of Final Comprehensive WQ Network Optimization Report and Guidance Document for Developing a District WQ Monitoring Evaluation Tool

$440,728

Capability Maturity Model (CMM)

Capability Maturity Model

Other Major Projects

Regional Simulation Model (RSM)

Regional Simulation Model (RSM)

$1,301,608

$863,550

Part II Peer review: Natural System RSM validationComplete peer review of model

code

3

Modeling 73

Modeling and Scientific Support

Strategic Plan Category Strategic Plan - Deliverables

and Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20061 Environmental Monitoring

Coordination Team Discussion2 Completion of Draft Plan and

Internal Peer Review

3 Presentation to MAT, DLT and Governing Board, if necessary

4 Finalize Plan1 Continued sample collection and

analyses, data validation , qrtly statistical analysis, and monthly inter-agency progress meetings

4 Completion of final report and presentations to TOC and 40E-63 Rule Making

1 Completion and review of Draft SOP; users trained

3 implementation of database changes and finalization of SOP

$112,950

Strategies :Development of Water Quality Strategy

Water Quality Monitoring Strategic

Plan

Complete optimization of autosamplers

Autosampler Optimization

Monitoring Process Improvements and

Technical Enhancements

Implement new site naming convention and registration process

Site Naming and Registration SOP

Modeling 74

Modeling and Scientific Support

Strategic Plan Category Strategic Plan - Deliverables

and Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20061 Completion of Business

Procedures SOP

2 Completion of Water Quality Site Registration

3 Completion of first series of (5) Maps

1 Finalization of Phase 1 testing; training conducted

2 Phase 2 - Identification of software enhancements

3 Phase 2 - Development and Testing of software enhancements

4 Complete and implement Phase 2 of Mobile GIS/GPS based Location Verification Tool

2 Completion of draft Lab Operations Business Plan and presentation to MAT and DLT

3 Presentation of Plan to Governing Board for approval to implement

2 LIMS - Completion of installation and implementation of system along with custom programs and interfaces

3 Q2 - Completion of acceptance testing and finalization of project

$558,860Replacement of Laboratory Information

Management System (LIMS)

5-year Laboratory Operations Business

Plan

Complete and implement monitoring location verification tool

Mobile GIS/GPS-Based Monitoring

Location Verification Tool

Laboratory Operations

Complete Lab Operations Business Plan

New Water Quality Monitoring Site Map

Series

Develop new series of water quality monitoring site maps

Modeling 75

Modeling and Scientific Support

Strategic Plan Category Strategic Plan - Deliverables

and Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20061 Selection and purchase of

instrumentation2 Installation/training/initial

shakedown of instrument3 Method development/parallel

testing4 Finalize method/complete

validation/submit update of analyte list to HRS

1 Completion of Draft 2006 SFER, 2 Completion of Final 2006 SFER,

Volumes I and II (Main Report), and Executive Summary

4 Completion of Draft 2007 SFER, Volume I and Peer Review

Water Quality Monitoring in Compliance with Legal Mandates and Permits

Regional Water Quality Monitoring

Network Operations and Qtrly Compliance

Reporting

All On-going

$3,848,363

All On-going $355,869All On-going $8,627,049

$16,618,977

$352,500

Fish Tissue Mercury Analyzer Pilot Study

Program Total

Recurring Activities

Production of South Florida Environmental Report

South Florida Environmental Report

(includes annual compliance reporting)

Other Programmatic Efforts

Personnel

Modeling 76

2006 WORK PLAN

Operations & Maintenance Program

GOALTo minimize damage from flooding, provide adequate regional water supply, and protect and restore the environment by optimally operating and maintaining the primary flood control and water supply system.

PROGRAM COORDINATOR:Alex Damian

77

Operations & Maintenance Program

The Operations and Maintenance Program consists of activities to effectively and efficiently manage the primary canals and associated structures in South Florida.

Operations and Maintenance Program activities include the Central and Southern Florida (C&SF) Project, as well as the Big Cypress Basin, as authorized by Ch. 373 F.S. and the U.S. Army Corps of Engineers.

Activities include the operation and maintenance of 500 water control structures, 50 pump stations, and managing 1,969 miles of canals and levees - 1,800 miles in the C&SF Project, and 169 miles in the Big Cypress Basin.

KEY ASSUMPTIONS

Governing Board strategic priority: refurbish the regional water management system

Mission Support is able to meet the additional contractual workload requirement for structure refurbishments

Ongoing state funding is received for Kissimmee Chain of Lakes aquatic plant management and District-wide exotic plant management

INTERRELATIONSHIP TO OTHER PROGRAMSDistrict Everglades

Maintaining and operating STA structures, pump stations, levees and canals

Lake OkeechobeeMelaleuca/torpedo grass control within the LakeLake Okeechobee Water Supply and Environment

regulation schedule impacts inflow/outflow structure operations

CERPProvides operations and maintenance of Critical Restoration Projects and other CERP works

78

OVERVIEW

Operations & Maintenance Program

INTERRELATIONSHIP TO OTHER PROGRAMS…CONTINUED

CERPProvides operations and maintenance of Critical Restoration Projects and other CERP works

Kissimmee RestorationKissimmee Chain of Lakes Long Term Management Plan will provide data to support regulation schedule alternatives

Land StewardshipProvides land management and exotic plant control for District-owned lands and mitigation projects

Coastal WatershedsProvides technical data for operational decisions and Water Supply and Environment schedule refinements

Water SupplyWater supply considerations related to the operation of Lake Okeechobee

79

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Capital Projects Completed/Cost 40 Capital Projects/$30.2m 1

Continue construction on 23 projects, complete 7;

2Continue construction on 16 projects, complete 10;

3Continue construction on 6 projects, complete 3;

4Continue construction on 3 projects, complete 1

1

Kissimmee Field Station Relocation 1st Qtr - Obtain easements & complete design package;

2

Begin solicitation for construction services, apply for building permits, obtain land development permits

3Award construction contract & start construction

4 Continue construction

FY06 Capital Program - Kissimmee Field Station

FY05 Capital Program -Hurricane Recovery Projects

$44,750,082

O + M 80

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Capital Projects Completed/Cost 40 Capital Projects/$30.2m 1

Pump Station S-140 Upgrades 1st Qtr - Continue detailed design

2Complete design package;

3Begin solicitation for construction contractors

4Award construction contract

1 Structure Automations continue detailed design;

2 Complete Design packages;

3 Begin solicitation for construction contractors,

4 Award construction contract

FY06 Capital Program -North Shore PS Hurricane Hardening, Automations & Telemetry

1

North Shore PS Hurricane Hardening, Automations & Telemetry 1st Qtr - Continue detailed design;

FY06 Capital Program -Pump Station S-140

FY06 Capital Program -Structure Automations

O + M 81

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Capital Projects Completed/Cost 40 Capital Projects/$30.2m 2 Complete design

packages;

3 Begin solicitation for construction contractors;

4 Award construction contracts

FY06 Capital Program -Canal Dredging & Bank Stabilization (C-51, C-16, C-7)

1

Canal Dredging & Bank Stabilization (C-51, C-16, C-7) Conduct preliminary Assessments and surveys; determine land & Right of way issues;

2Complete surveys; develop work plans, start work on land issues;

3Continue work on land issues; start detailed design;

O + M 82

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Capital Projects Completed/Cost 40 Capital Projects/$30.2m 4

Continue work on land issues; continue detailed design

1North Microwave Tower Spur 1st Qtr - Continue detailed design;

2 Complete design package; obtain FCC permit;

3 Begin solicitation for construction contractor;

4 4th Qtr - Award construction contract

FY06 Capital Program -Structure Inspection & Canal Conveyance Capacity Programs

1

Structure Inspection & Canal Conveyance Capacity Programs 1st Qtr - Start inspections;

FY06 Capital Program -Structure Inspection & Canal Conveyance Capacity Programs

2 Continue inspections & evaluate results;

FY06 Capital Program -North Microwave Tower Spur

O + M 83

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Capital Projects Completed/Cost 40 Capital Projects/$30.2m 3

Continue inspections, evaluate results, program future projects;

4Complete program for FY06; develop SOW's for WO's for FY07

1

Select Contract systems analyst and IT programmer, Conduct field surveys, Phase II Plan Outreach, Initiate communications outreach

2

Conduct field surveys,Initiate DB conversion design efforts, and VDCA conversion modelInitiate public web site design

3

Design DCVP, DBHYDRO architecture changes,Conduct field surveys

4Update impacted database list,Conduct field surveys

NAVD 88 Datum Conversion $1,468,892

Completion of Telvent Water Management System Punch List 4

Complete 100% of project by 4th quarter

O + M 84

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1

Decision on whether to move forward with relocation

3

Commence construction if agreed to move forward on relocation

Complete scheduled maintenance on time

Complete 30 pump station and gate structure overhauls. Maintain 50 pump stations and 500 structures.

30 Pump Station and Gate Overhauls

Tier Two Projects

BCB Facility Relocation

BCB Golden Gate #3and weir #2 4Begin construction in FY06

Activities

Operations 19 million acre-feet of water moved annually Structure Operations 4

Acre feet of water moved (Approx. 19M) $4,544,211

1

$5,147,451

Acres of Levees and Canal Banks Maintained/

Cycles Completed30,169 Acres/4 cycles Canal/Levee Maintenance 4

30,169 Acres of levee and canal banks maintained; 4 cycles completed $7,645,414

Structure / Pump Station Maintenanceand Refurbishment 4

Completed Overhauls of Pump Stations and Gate

Structures

O + M 85

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

46,800 acres of vegetation treated annually Exotic/Aquatic Plant Control 1 10,000 Acres of

vegetation treated

210,000 Acres of vegetation treated,

311,800 Acres of vegetation treated,

415,000 Acres of vegetation treated,

Electronic Communications Site Installation / Maintenance

CJ - Electronics / Communications & Control

1Loggernet Components - Upgrade 25 field monitoring sites to Telvent compatible.

$5,969,298

1

Telemetry Installations and Maintenance - Complete 11 major field Telvent communication sites

1 Rebuild 26 Hydrologic Collection sites

2

Process and update 563,799 station days of electronically /manually transmitted raw hydrologic data within 72 hours.

1

346 (New Sites)/1021 (Maintained Sites)

$15,201,746

Vegetation Management to provide access of district Right-of-Way and maintenance of canal channel areas for water movement.

O + M 86

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

2 Process 375 station days historical backlog.

Electronic Communications Site Installation / Maintenance

CJ - Electronics / Communications & Control 4 Installation of 346

Electronic Communication Sites (87 per quarter)

4

Decrease response time of data acquisition systems maintenance to 72 hour turnaround

1 Successfully manage 35 SESS contracts

1 Complete 35 vertical surveys

2 Complete 35 vertical surveys

3 Complete 35 vertical surveys

4 Complete 35 vertical surveys

1

Completed 6 Legally Mandated Data Requests/Reports and 5 ad hoc requests

O + M 87

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006Electronic Communications Site Installation / Maintenance

CJ - Electronics / Communications & Control

2

Completed 4 Legally Mandated Data Requests/Reports and 5 ad hoc requests

3

Completed 11 Legally Mandated Data Requests/Reports and 5 ad hoc requests

4

Completed 4 Legally Mandated Data Requests/Reports and 5 ad hoc requests

1

Rapid Response Streamgauging Team activities to complete operations criteria

1 Perform QA/QC on Selected 208 Data Sites

2 Perform QA/QC on Selected 208 Data Sites

3 Perform QA/QC on Selected 208 Data Sites

O + M 88

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

4 Perform QA/QC on Selected 208 Data Sites

1 92 Permits2 92 Permits3 92 Permits4 92 Permits

1 Completion of 514 Facility Maint. Tasks

2 Completion of 514 Facility Maint. Tasks

3 Completion of 513 Facility Maint. Tasks

4 Completion of 513 Facility Maint. Tasks

3Complete annual placards/fees for 46 storage tank systems

1Annual leak detection certifications for 7 storage tank systems

2Annual leak detection certifications for 4 storage tank systems

3Annual leak detection certifications for 29 storage tank systems

1-4

24 fuel analysis (sulfur monitoring) for pump stations (aver. 6-9 samples per quarter)

1-4Complete permit/license renewals for field/pump

$187,833

CO - General Maintenance

Right of Way Management Permit

Issued

368 ROW Permits

CL - Right-of-Way Management

$1,364,298

$122,201

Contamination Assessment &

Remediation Fuel Tank Placards obtained

49 Pump Station PermitsCD - Contamination Assessment &

Remediation - Water Control Structures

General Maintenance Completed Tasks

2054 Facility Maintenance Tasks

O + M 89

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

CI-Equipment Maintenance 2 Complete 25% of Capital Lease purchase $1,296,072

3 Complete 50% of Capital Lease purchase

4 Complete 25% of Capital Lease purchase

2 Purchase 10% of Fleet by 2nd Quarter

3 Purchase 50% of Fleet by 3rd Quarter

4 Purchase 100% of Fleet by 4th quarter

Heavy Equipment/Preventative

Maintenance

147 Preventive Maintenance Activities on Heavy

Equipment/169 PMs on Light Equipment

O + M 90

Operations & Maintenance

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

Heavy Equipment/Preventative Maintenance

147 Preventive Maintenance Activities on Heavy Equipment/169 PMs on Light Equipment

CI-Equipment Maintenance 1

Completion of 36 PMs on Heavy Equipment; completion of 42 PMs on Light Equipment on vehicles outside of O&M.

2

Completion of 37 PMs/ Heavy Equipment; completion of 42 PMs Light Equipment on vehicles outside of O&M.

3

Completion of 37 PMs on Heavy Equipment; completion of 42 PM on Light Equipment on vehicles outside of O&M.

4

Completion of 37 PMs on Heavy Equipment; completion of 43 PMs\ on Light Equipment on vehicles outside of O&M.

All On-going $1,879,821All On-going $40,962,461

$130,539,780

Other Programmatic EffortsPersonnel Program Total

O + M 91

2006 WORK PLAN

Regulation Program

GOALTo provide fair, consistent and timely review of permit applications in accordance with the adopted rules and criteria of the District, ensure compliance with issued permits, and take enforcement action where necessary

PROGRAM COORDINATOR:Bob Brown

92

Regulation Program

The Regulation Program involves implementing the District's permitting authority under Ch. 373, F.S. to regulate the management and storage of surface waters through Environmental Resource Permits (ERPs), the consumptive use of water through Water Use Permits, and the construction, repair and abandonment of wells through Water Well Construction Permits. Linked with the ERP program is implementation of the sovereign submerged lands authority delegated to the SFWMD by the Governor and Cabinet, sitting as the Board of Trustees of the Internal Improvement Trust Fund.

Environmental Resource Permits ensure that proposed surface water management systems, including wetland dredging or filling, do not cause adverse water quality, water quantity or environmental impacts. Water Use Permits ensure that proposed uses are reasonable-beneficial, will not interfere with any presently existing legal users, and are consistent with the public interest. Water Well Construction Permits ensure that groundwater resources are protected from contamination as aresult of well construction activities.

KEY ASSUMPTIONS

Contract staffing can be used to help handle the 50% increase in the water use permitting workload

Expanded Regulatory Staffing in the Martin / St. Lucie Service Center

INTERRELATIONSHIP TO OTHER PROGRAMSCERP

Coordination of all permit applications located in or adjacent to CERP projects

Water SupplyImplementation of regulatory components of the District's Water Supply Plans

93

OVERVIEW

Regulation

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1

1)Deliver e-noticing production release;2)Baseline e-submittal and e-compliance deployment schedule based on completed Software Requirement Specifications

2 Complete 50% of ePermitting designs

3 Deliver 1st e-submittal and e-compliance production release

4 Complete 100% of ePermitting designs

$1,685,669

1

Initiate the review of approximately 64 Lower West Coast basin D irrigation renewal applications

2

Initiate the review of approximately 102 Lower West Coast basin E irrigation renewal applications

IMPLEMENT WATER USE BASIN RENEWALS

Lower West Coast Basins D/E, Broward

County Basin

Implement Water Use Renewals for Lower West Coast Basins D/E, and the

Broward County Basin

E-PERMITTING AND ELECTRONIC DOCUMENT MANAGEMENT SYSTEM

Water Use Permitting

Budgeted at Mission Support

Program

Complete Environmental

Resource Permit system and Complete

E-noticing

Complete Water Use Permit system and Complete E-noticing

Regulation 94

Regulation

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

3

Initiate the review of approximately 157 Broward Basin irrigation renewal applications

4Continue the review of basin irrigation basin renewal applications

1

Complete the review of an average of 475 permit applications

2

Complete the review of an average of 475 permit applications

3

Complete the review of an average of 475 permit applications

4

Complete the review of an average of 475 permit applications

1234

CONTINUE REVIEW OF PERMIT APPLICATIONS

Conduct an average of 310 compliance investigations per quarter

Review new permit applications

Perform compliance inspections and take enforcement actions when necessary

CONTINUE REVIEW OF PERMIT APPLICATIONS

Regulation 95

Regulation

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006$749,011

CONTINUE REVIEW OF PERMIT APPLICATIONS

1

Complete the review of an average of 575 permit applications per quarter

Review new permit applications

2

Complete the review of an average of 575 permit applications per quarter

3

Complete the review of an average of 575 permit applications per quarter

4

Complete the review of an average of 575 permit applications per quarter

CONTINUE REVIEW OF PERMIT APPLICATIONS 1

Complete an average of 2,125 compliance investigations per quarter

2Complete an average of 2,125 compliance investigations per quarter

3Complete an average of 2,125 compliance investigations per quarter

4Complete an average of 2,125 compliance investigations per quarter

CONTINUE REVIEW OF PERMIT

APPLICATIONS

Environmental Resource Permitting

Perform compliance inspections and take

enforcement actions when necessary

CONTINUE REVIEW OF PERMIT

APPLICATIONS

Regulation 96

Regulation

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1234

1

Initiate rulemaking process for ERP delegation

2

Administer training of county employees and monitor delegation progress

3

Administer training of county employees and monitor delegation progress

4

Transition ERP process to Counties subject to timing of Rulemaking

All On-going $91,604All On-going $14,365,464

$16,891,748

Other Programmatic Efforts

Implement partial ERP delegation to Miami-Dade and Collier counties

Keep current with new certifications and reduce backlog by 10%

Personnel Program Total

Environmental Resource Permit (ERP) DELEGATION

CONSTRUCTION CERTIFICATION AND CONVERSION

Implement partial ERP delegation to Miami-Dade and Collier Counties

Complete current construction certification and reduce backlog

Complete 90% of current certifications and reduce backlog by 10% by year end

Regulation 97

2006 WORK PLAN

Water Supply Program

GOALEnsure an adequate supply of water to protect natural systems and to meet all existing and projected reasonable-beneficial uses, while sustaining water resources for future generations

PROGRAM COORDINATOR:Carlyn Kowalsky

98

Water Supply Program

The Water Supply Program is responsible for the District's evaluation of long-term water supply needs, and the planning and development of needed water resource development projects. Four regional water supply plans are developed and implemented to meet the water supply needs of present and future populations, agriculture and natural systems, pursuant to the requirements of the Florida Water Resources Act. Computer modeling is used to evaluate the effectiveness of proposed solutions in meeting projected human demands and environmental requirements. Environmental targets, which are developed for major ecosystems by the Coastal Watersheds and other programs, and incorporated into planning and permitting efforts. Water conservation is encouraged through a combination of strategies, including regulatory and financial incentives.

Minimum Flows and Levels (MFLs) and Water Reservations for natural systems, both required by statute, help ensure the sustainability of water resources. If minimum targets cannot be met, recovery plans are developed. Water Reservations prevent the allocation of water needed to protect and restore ecosystems. Water Use Permitting (see Regulation Program) is a powerful tool used to implement Water Supply Plans, MFLs and Water Reservations. The Water Supply Program also coordinates with local government comprehensive planning efforts, creating a linkage between land use and water supply planning.

KEY ASSUMPTIONS

Governing Board strategic priority: Implement key water supply plan recommendations to meet current and future demands

Modeling support will be available to coincide with plan update requirements

Identification of future Lower East Coast and Lower West Coast water resource and water supply development projects will occur in FY05 as part of plan updates

99

OVERVIEW

Water Supply Program

INTERRELATIONSHIP TO OTHER PROGRAMS

Coastal WatershedsProvide technical criteria for establishing MFLs

Identify the scientific basis for initial environmental water reservations

Kissimmee RestorationDevelopment of technical criteria for minimum flows and levels, and for initial

reservations.

Lake OkeechobeeDevelopment of technical criteria for MFLs and initial reservations

Operations and MaintenanceWater supply considerations related to the operation of Lake Okeechobee

RegulationImplementation of regulatory components of the District's Water Supply Plans

CERPProjects will have water resource development benefits for implementing MFLs &

water reservations

Shares the development and application of resources and tools, especially computer models and water resource data

100

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Conduct regional workshops & WRAC meetings

2 Prepare draft list of projects

3 Submit draft plan to Governing Board and DEP

4 Plan adopted by Governing Board

1 Conduct regional workshops2 Prepare draft list of projects3 Submit draft plan to Governing Board

and DEP4 Plan adopted by Governing Board

1 Conduct regional workshops2 Prepare draft list of projects3 Submit draft plan to Governing Board

and DEP4 Plan adopted by Governing Board

1 Conduct regional workshops2 Prepare draft list of projects3 Submit draft plan to Governing Board

and DEP4 Plan adopted by Governing Board

Lower East Coast Water Supply Plan

Tier Two Projects$3,543,113

CO

MPL

ETE

WAT

ER S

UPP

LY P

LAN

UPD

ATES

Kissimmee Basin Water Supply Plan

Lower West Coast Water Supply Plan

Upper East Coast Water Supply Plan (added after strategic plan adopted due to legislative mandate)

Kissimmee Basin Plan Update,

Lower West Coast Plan Update,

Lower East Coast Plan Update,

Upper East Coast Plan Update

Water Supply 101

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Begin work on technical document.2 Finalize technical document, develop

draft rule language & permit criteria, hold workshops

3 Governing board adoption of rule

1 Begin work on 2x2 model runs.Begin to quantify existing water.

2 Identify targets & existing legal user demands, complete 2 x 2 model runs, Complete quantification of existing water

3 Complete model documentation & peer review, begin development of draft technical document

4 Complete draft technical document, conduct internal review, complete peer review of draft document

1 Negotiate scope of work with Tribe2 Well siting evaluation completed3 Permit application submitted by Tribe

4 Tribe responses to Permit RFIs1 Notice to Proceed2 Ongoing Construction3 Ongoing Construction4 Complete Construction

Petition FDEP to begin testing

Hillsboro ASR Pilot Project

Initial Water Reservations - Everglades and Associated Areas

Indian Prairie Basin ASR

INIT

IAL

WA

TER

RES

ERVA

TIO

NS

Establish initial reservationfor one water body

Initial Water Reservations - Loxahatchee -

Water Supply 102

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Continue to support FDEP study

2 Complete FDEP study,Begin addressing findings of studyInitiate scope/progress development for demonstration pilot project.

3 Continue addressing findings of study; initiate design of demonstration project

4 Continue addressing findings of studyContinue design of demonstration project.

1 Submit FY06 draft work program to DEP. Submit final work program to Governing Board as part of South Florida Environmental Report

2 Submit South Florida Environmental Report to the Florida Legislature

4 Initiate preparation of FY07 draft work program

Floridan model 1 Floridan Model Implementation / Lower East Coast

2 Floridan Model Implementation - Database Update

3 Field level hydrogeologic data collection- for model implementation

Implement Water Supply Plan recommendations

Five-Year Water Resource Development

Work Program

Specific water supply plan recommendation (now

mandated by ch.373, FS)

Canal Reuse Project(Palm Beach, Broward,

Miami-Dade)

Planning

Tier Two Projects

Water Supply 103

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

4 Floridan Model Implementation / Upper East Coast

1 Project Charter & Plan Approval2 Develop weekly demand estimates

Conduct Hydraulics & hydrology analysis

3 Develop Draft Management Zones4 Finalize Supply Side Management

Plan1 Review and comment on local comp.

plan amendments, evaluation and appraisal reports, and Ch. 298 District plan updates.

2 Review and comment on local comp. plan amendments, evaluation and appraisal reports, and Ch. 298 District plan updates.

3 Review and comment on local comp. plan amendments, evaluation and appraisal reports, and Ch. 298 District plan updates.

4 Review and comment on local comp. plan amendments, evaluation and appraisal reports, and Ch. 298 District plan updates.

Ensure linkage between land use and water supply

plans

Comprehensive Plans

Ensure adequate water supply

Supply Side Management

Water Supply 104

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Address water supply operational issues related to management of the C&SF Project

2 Address water supply operational issues related to management of the C&SF Project

3 Address water supply operational issues related to management of the C&SF Project

4 Address water supply operational issues related to management of the C&SF Project

1 Create draft of technical document

2 Finalize technical document

3 Conduct external peer review4 Publish notice of rule development,

revise technical document, hold workshops

1 Publish notice of rulemaking with rule text

2 Governing board adoption of rule1 Create draft of technical document2 Finalize technical document3 Conduct external peer review

MINIMUM FLOWS AND

LEVELS

Establish MFLs for two water bodies

Biscayne Bay MFL

Florida Bay MFL

Lake Istokpoga

Participation with Operations Team and

coordination of operational issues

Planning (continued)

$485,128

Ensure adequate supply of water

Minimum Flows and Levels

Water Supply 105

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

4 Publish notice of rule development, revise technical document, hold workshops

1 Conduct background studies

2 continue background studies

3 Conduct background studies.4 Compile information needed to

prepare technical document

1 Initial SOW development2 Select consultant, finalize SOW and

issue notice to proceed with feasibility study.

3 Perform Phase I analysis4 Receive Analysis Report1 Sixty percent G-161 construction;

initiate G-161 operations model; start G-92 construction.

2 Complete G-161 and receive deliverables from operations model. Continue G-92 construction.

3 Complete construction4 Complete telemetry instrumentation

and testing.

Loxahatchee River Tributaries MFL (2007)

Budget Element (DB) - Implementation$5,632,967Seawater desalination

feasibility study.

North Palm Beach Regional Water Delivery Structures (G-161 Construction and development of operations model, new G-92)

Implement key recommendations from

Water Supply Plans

Water Supply 106

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Initiate Contract ManagementDevelop FY07 Application

2 Continue management of FY06 contracts. Distribute application, hold workshops & identify selection committee for FY07

3 Continue management of FY06 contracts. Review & evaluate FY07 project proposals. Propose projects for Board approval.

4 Continue management of FY06 contracts. Solicit Board approval for FY07 projects.

1 Execute annual contract for FY06Receive/review 8 MIL quarterly reports. Develop/distribute quarterly MIL newsletter

2 Receive/review 9 MIL quarterly reports. Develop/distribute quarterly MIL newsletter.

3 Receive/review 9 MIL quarterly reports. Develop/distribute quarterly MIL newsletter.

4 Receive/review MIL 9 quarterly reports. Develop/distribute quarterly MIL newsletter. Board approval of FY07 contracts

Water Savings Incentive Program (Water SIP)

Contract Management - FY06

CO

NSE

RVA

TIO

N

Conservation$1,725,117Ensure adequate water

supply

Encourage water conservation through a

combination of strategies

Mobile Irrigation Laboratories

Comprehensive Contract/FDACS &Regional Purchase

Orders

Water Supply 107

Water Supply

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects

Quarter

Annual Work Plan -Success Indicator

Annual Budget

2006 2006 2006 2006 2006

1 Solicit Board approval for FY06 projects. Execute Contracts.

3 Continue contract managementProcess April Invoices

4 Continue contract managementProcess August Invoices to complete projects.Report to Governor & Legislature.

1 Continue contract management6 projects completed

2 Continue contract management6 projects completed

3 Continue contract management6 projects completed

4 Continue contract management6 projects completed

All On-going 249,730$ All On-going 6,394,221$

61,186,955$

$43,156,679Alternative Water Supply

2 Initiate contract management & reporting

AWS Grant ProgramPre- FY06

(52 projects with 26 to be finished in FY06)

Other Programmatic EffortsPersonnel Program Total

ALTE

RN

ATIV

E W

ATER

SU

PPLY

PR

OG

RAM

Ensure adequate water supply (New Program not Highlighted in Strategic

Plan)

Alternative Water Supply funding pursuant

to SB444(for FY06)

Water Supply 108

2006 WORK PLAN

Mission Support Program

GOALTo ensure business and data integrity in compliance with Florida Statutes and Governing Board policy by providing timely and accurate business, human resource, information technology, policy, outreach, and safety expertise within consistent, reliable, streamlined processes.

PROGRAM COORDINATOR:Aaron Basinger

109

Mission Support Program

The Mission Support Program delivers high quality, cost-effective, business, legal and technical services that enable the District and employees to succeed. Mission Support includes functions such as executive management, human resources, legal, ombudsman, financial management, risk assessment, environmental technical assistance, procurement, facilities management, legislative affairs, emergency management, information technology, flight operations, security management, strategic planning, public information and outreach.

In addition to the milestones shown over the Strategic Plan's 10-year time frame, this program has a high number of significant milestones that reoccur annually, including:

HR Solutions Annual ReportStaffing assessments / job profilesAnnual performance reviewsEnhanced employee communications and recognitionOutsourcing efforts assessmentAnnual training plan and schedule updateStrategic Plan cycleAnnual Financial ReportingTechnology storage/backup systems reviewsPublic outreach strategy updatesProject management training and certificationEmergency response training and exercisesSouth Florida Environmental Report – Volume IIAnnual Audit PlanInspector General’s Annual Report

110

OVERVIEW

Mission Support Program

KEY ASSUMPTIONS

Governing Board priority: continue to recognize the value of employees

Mission Support staffing will not increase, while demands of Mission Support will continue to increase

Implementation of new enterprise-wide systems will provide business efficiencies and improvements

Management will continue to evaluate outsourcing of non-core activities and shift resources to the highest priorities

INTERRELATIONSHIP TO OTHER PROGRAMS

The Mission Support Program supports all District programs and priorities. Key examples are technical support for the E-Permitting initiative for Water Use permits, data collection and assessment, IT support, financial management, and procurement.

111

Mission Support

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects / Activities

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1Finalize schedule of activities for FY06 and hold District celebration event

2 Implement at least 2 employee related activities

3 Implement at least 2 employee related activities

4 Implement at least 2 employee related activities and evaluate/plan for FY07

1

Complete delivery and evaluate 2005 leadership program for first half of leadership team (5 workshops - approx 150 participants)

2

Begin delivery of 2006 leadership program for second half of leadership team (5 workshops - approx 150 participants)

3Complete delivery of 2006 leadership program for 2nd half of leadership team

4 Evaluate 2006 leadership program and plan follow-up activities

1 Implement completed profiles2 Complete staff alignment

3 Complete skills assessment to identify gaps as required

4Plan training and development to meet gaps

HUMAN RESOURCES

Other Projects

$2,031,284

Implement Leadership Development Program

Implement District Leadership Development Program - HR Solutions Dept

$135,000

Implement Employee Committee Annual Project Plan

Improved Employee Committee Activities - HR Solutions Dept

Tier One Project

Recurring activities section of strategic plan

Complete skills based job profiles ( Fin., PM, HR) - HR Solutions Dept

Internal staff resources

Mission Support 112

Mission Support

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects / Activities

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1 Software Development plan / Work Breakdown Structure

2 Detailed requirements / Use Cases

3Software architecture substantially complete

4 Software Development

1Delivery of pilot Arc Hydro database. Delivery of three pilot tools.

2Completion of Pilot Project

1

Continue delivering activities for Phase II (conversion of IWEB)

2Implement release 2 & 3 of Phase II (conversion of IWEB)

Consolidated Data Management - Information Technology DeptNOTE: Specifically for the Bio DB project and does not include additional sub-projects for CDMP

$23,794,542

Tier Two Projects

Strategic Plan FY2007

INFORMATIONTECHNOLOGY

Enterprise Implementation of Enhanced Arc Hydro Database - Information Technology Dept

Tier One ProjectStrategic Plan FY2010

$180,000

$575,000

SFWMD Portal Development - Information Technology Dept

Mission Support 113

Mission Support

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects / Activities

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1 Implement and run in parallel with existing package

2 Remove old package and run replacement live

1 eQuest (financials & procurement) Configuration phase completed

2 eQuest (financials & procurement) Integration Test completed

3 eQuest (financials & procurement) User Acceptance Testing completed

4 eQuest (financials & procurement) initial deployment completed

1Rule Development

2 Implement Rule

3District Staff Program Training

4Analyze Impact of SBE Program vs. MBE Program

BUSINESS SUPPORT

Other Projects

Tier One ProjectImplement payroll, financials, and maintenance management SAP software

e-Quest (SAP) - Finance & Admin Dept

$23,538,134

Develop Small-Business Program

Develop Small Business Program - Procurement Dept

Internal staff resources

Other ProjectsReplace virus detection package

Migrate to Virus Detection Software Used By Our IT Security Outsourcer - Information Technology Dept

$223,500

Mission Support 114

Mission Support

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects / Activities

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 20061 Update 10-yr revenue forecast

3Update 10-yr strategic plan and complete FY07 draft annual work plan and preliminary budget

4Adopt millage rates, Ag Privilege tax roll, and FY07 budget in compliance with Statute

2 Obtain Short-term financing if necessary

4 Issuance of first series of COPS.

1

Conduct second set of sessions with Palm Beach, Broward, Dade; Conduct first set of sessions with Martin/St. Lucie and Okeechobee

2Conduct second set of sessions with Orlando, Osceola and Lower West Coast

3

Conduct third set of sessions with Palm Beach, Broward, Miami - Dade; Conduct second set of sessions with Martin/St. Lucie and Okeechobee

4 No activity planned due to legislative sessions

PUBLIC

INFORMATION

Debt issuance for Acceler8

Debt issuance for Acceler8 -Finance & Admin Dept

Recurring activities section of strategic plan

Implement Annual Business Cycle - Finance & Admin Dept

Internal staff resources

Internal staff resources

Internal staff resources

ProjectsRecurring activities section of strategic plan

Support development & implementation of Regional Water Supply Plans by educating local & elected officials on issues & plans through use of Water Academies - Service Centers

Mission Support 115

Mission Support

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects / Activities

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006

1 Develop statement of work and select vendor for public awareness survey.

2

Review baseline from previous public awareness survey. Review strategic plan. Hold meetings with staff, and key personnel to gather input for survey. Develop scope for approx. 30 survey questions.

3Coordinate with vendor to conduct public awareness survey. Analyze statistical results of survey.

4

Coordinate with vendor to ensure final report in accordance with District's statement of work. Update strategic outreach plans based on results of survey and staff input. Implement plan.

1Complete upgrade for Water Supply areas Lower East Coast and Lower West Coast

2Complete upgrade for Water Supply Planning areas Kissimmee and Upper East Coast

3Complete upgrade of Watershed Management website for Everglades and Estuaries.

4Complete upgrade of Watershed Management website for Kissimmee and Okeechobee.

Conduct public awareness survey

Conduct public awareness survey - Dept of Public

Information

Complete external web-site upgrade

Complete external web-site upgrade - Dept of Public Information

$50,000

$50,000

Mission Support 116

Mission Support

Strategic Plan Category

Strategic Plan - Deliverables and

Milestones

Annual Work Plan -Projects / Activities

Quarter

Annual Work Plan -Success Indicator Annual Budget

2006 2006 2006 2006 2006Complete alignment of outreach budget to programs (Service Centers) and Media buying campaign (Dept of Public Info)

4

Complete implementation of outreach plans (Service Centers) and complete Media buying campaign (DPI)

Internal staff resources

1 Identify Tier 3 projects and Project Managers

2 Load 25% of projects

3 Load next 25% of projects

4Load remaining 50% of projects

All On-going $25,947,845All On-going $37,566,227

$114,541,532Personnel Program Total

PROJECT MANAGEMENT

ProjectsInitiate Tier 3 project schedules

Initiate third Tier of project schedules into District-wide P3e system - Enterprise Project Management Office $450,000

Other Programmatic Activities