Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. i
Table of Contents
1 INTRODUCTION ....................................................................................................................................... 1
1.1 PROFILE OF PROJECT PROPONENT ................................................................................................................. 1
1.2 NAME AND CONTACT ADDRESS OF PROJECT PROPONENT .................................................................................. 1
1.3 IMPLEMENTING ORGANIZATION: ................................................................................................................... 1
1.4 ORGANIZATIONAL CHART............................................................................................................................. 1
1.5 LAND DESCRIPTION .................................................................................................................................... 2
1.5.1 License and its Validity ................................................................................................................. 2
1.5.2 Status of Ownership and Collaboration Agreement ..................................................................... 3
1.5.3 Land Details showing Plot Nos. / Survey Nos. .............................................................................. 3
1.6 LITIGATION(S) OR ORDERS PASSED BY ANY COURT OF LAW / ANY STATUTORY AUTHORITY .......................................... 4
1.7 OBJECTIVES OF THE EIA STUDY ..................................................................................................................... 4
1.8 SCOPE OF THE STUDY .................................................................................................................................. 4
1.9 EIA METHODOLOGY ................................................................................................................................... 4
1.10 PURPOSE OF THE REPORT ............................................................................................................................ 5
1.11 STRUCTURE OF THE EIA REPORT ................................................................................................................... 6
2 PROJECT DESCRIPTION ............................................................................................................................ 7
2.1 GOAL AND OBJECTIVES OF THE PROPOSED PROJECT .......................................................................................... 7
2.2 SIGNIFICANCE OF PROPOSED PROJECT AT REGIONAL LEVEL ................................................................................. 7
2.3 SIGNIFICANCE OF PROJECT AT LOCAL LEVEL ..................................................................................................... 8
2.4 PROJECT BACKGROUND ............................................................................................................................... 9
2.5 SITE SELECTION CRITERIA ............................................................................................................................. 9
2.6 NATURE AND SIZE OF THE PROJECT ................................................................................................................ 9
2.7 PROJECT SITE LOCATION .............................................................................................................................. 9
2.8 ENVIRONMENTAL SENSITIVITY WITHIN 15 KM AND 1 KM RADIUS OF THE PROJECT SITE ................................. 13
2.9 ENVIRONMENT LIABILITY OF THE SITE ........................................................................................................... 13
2.10 SITE CONNECTIVITY .................................................................................................................................. 13
2.11 SITE AND SITE SURROUNDINGS WITHIN 500 M BOUNDARY OF PROJECT SITE ......................................................... 14
2.12 PROJECT SITE AND SURROUNDING PHOTOGRAPHS ........................................................................................... 15
2.13 PROJECT COMPONENTS ............................................................................................................................. 16
2.13.1 Development Concept ................................................................................................................ 16
2.13.2 Land Use Distribution and Area Statement ................................................................................ 16
2.13.3 Project Site Elevation and Sections ............................................................................................. 18
2.13.4 Population Details ...................................................................................................................... 20
2.14 UTILITIES PROPOSED DURING CONSTRUCTION AND OPERATION PHASES ............................................................ 20
2.14.1 Water Requirement and Supply.................................................................................................. 21
2.14.2 Sewage System ........................................................................................................................... 21
2.14.3 Rainwater Harvesting System .................................................................................................... 22
2.14.4 Power Requirement and Supply ................................................................................................. 22
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. ii
2.14.5 Parking........................................................................................................................................ 23
2.14.6 Municipal Solid Waste Management ......................................................................................... 23
2.14.7 E-Waste Management................................................................................................................ 23
2.14.8 Sewage Sludge ............................................................................................................................ 24
2.14.9 Energy Conservation Measures .................................................................................................. 24
2.14.10 Fire Safety Facilities .................................................................................................................... 24
2.14.11 Demolition .................................................................................................................................. 24
2.14.12 Building Materials and Technologies for Construction ............................................................... 24
2.14.13 Quantity of Natural Resources ................................................................................................... 24
2.15 RESOURCE AND MANPOWER ....................................................................................................................... 25
2.16 CONSTRUCTION PERIOD & SCHEDULE .......................................................................................................... 25
2.17 PROJECT COST ......................................................................................................................................... 26
2.18 COMPATIBILITY WITH LOCAL REGULATIONS .................................................................................................... 26
2.19 SOCIAL ACTIVITIES IN THE PROJECT .............................................................................................................. 26
2.20 OTHER RELEVANT INFORMATION ................................................................................................................ 27
3 LEGAL & ADMINISTRATIVE FRAMEWORK .............................................................................................. 28
3.1 ENVIRONMENTAL POLICIES ........................................................................................................................ 28
3.2 LEGAL PROVISIONS FOR ENVIRONMENT RELATED TO BUILDING / CONSTRUCTION / AREA DEVELOPMENT & TOWNSHIP
PROJECTS ............................................................................................................................................................ 29
3.3 SITING OF PROJECTS ................................................................................................................................. 31
3.4 ENVIRONMENTAL CLEARANCE OF DEVELOPMENTAL PROJECTS .......................................................................... 31
3.5 URBAN PLANNING & LAND USE .................................................................................................................. 32
3.6 USAGE OF WATER & WATER POLLUTION...................................................................................................... 33
3.7 AIR QUALITY ........................................................................................................................................... 33
3.8 NOISE LEVEL ........................................................................................................................................... 34
3.9 SOLID AND HAZARDOUS WASTE MANAGEMENT ............................................................................................ 34
3.10 STORAGE AND USE OF PETROLEUM AND HAZARDOUS CHEMICALS ..................................................................... 35
3.11 CENTRAL GROUND WATER AUTHORITY (CGWA) NOTIFICATION ...................................................................... 36
3.12 STATUTORY NATIONAL CAPITAL REGION (NCR) REGIONAL PLAN-2021 ............................................................. 37
3.13 OPERATION OF MOTOR VEHICLES ............................................................................................................... 38
3.14 INSTITUTIONAL FRAMEWORK ...................................................................................................................... 38
3.14.1 Ministry of Environment & Forests ............................................................................................. 38
3.14.2 Central & State Pollution Control Boards ................................................................................... 39
3.14.3 Municipalities & the Municipal Corporations ............................................................................. 39
3.14.4 Haryana Urban Development Authority (HUDA) Administration ............................................... 40
3.14.5 Haryana State Environment Impact Assessment Authority (HSEIAA) / Haryana State Expert
Appraisal Committee (HSEAC) ..................................................................................................................... 41
3.15 ENERGY CONSERVATION BUILDING CODE (ECBC) .......................................................................................... 41
3.16 MANUAL ON NORMS & STANDARDS FOR LARGE CONSTRUCTION PROJECTS ........................................................... 42
4 BASELINE ENVIRONMENT STATUS ......................................................................................................... 43
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. iii
4.1 INTRODUCTION ........................................................................................................................................ 43
4.2 METHODOLOGY OF CONDUCTING BASELINE STUDY ........................................................................................ 43
4.3 CRITERIA FOR BASELINE ENVIRONMENT STUDY ............................................................................................... 44
4.4 COMPONENTS AND PARAMETERS FOR BASELINE ENVIRONMENTAL STUDY .......................................................... 44
4.5 PHYSICAL ENVIRONMENT ........................................................................................................................... 48
4.5.1 Land Use Pattern ........................................................................................................................ 48
4.5.2 Geography & Topography .......................................................................................................... 48
4.5.3 Geology ....................................................................................................................................... 50
4.5.4 Seismo-Tectonic & Nature of Study ............................................................................................ 51
4.5.5 Cyclones and Storm Surges ......................................................................................................... 53
4.5.6 Mineral Resources ...................................................................................................................... 53
4.5.7 Drainage Pattern ........................................................................................................................ 53
4.6 CROPPING PATTERN .................................................................................................................................. 54
4.7 AIR ENVIRONMENT ................................................................................................................................... 54
4.7.1 Meteorological Data from Secondary Sources ........................................................................... 55
4.7.2 Atmospheric Stability .................................................................................................................. 61
4.7.3 Mixing Height ............................................................................................................................. 61
4.7.4 Site Specific Meteorological Data ............................................................................................... 62
4.7.5 Air Quality ................................................................................................................................... 62
4.8 NOISE ENVIRONMENT ............................................................................................................................... 66
4.8.1 Noise Quality .............................................................................................................................. 67
4.9 TRAFFIC .................................................................................................................................................. 68
4.10 TRAFFIC PROJECTION ............................................................................................................................. 69
4.10.1 Population and Trips Generation for Horizon Year 2021 ............................................................ 69
4.10.2 Assumptions for Trip Generation ................................................................................................ 69
4.10.3 Results of Traffic Analysis Study ................................................................................................. 70
4.10.4 Conclusion: ................................................................................................................................. 70
4.10.5 Hierarchy of Road within Proposed Project Site as per IRC: 86-1983 ......................................... 70
4.11 WATER ENVIRONMENT ............................................................................................................................. 71
4.11.1 Ground Water Resources & Availability ..................................................................................... 71
4.11.2 Hydro-geological ........................................................................................................................ 73
4.11.3 Vertical Electric Soundings (VES) ................................................................................................ 74
4.11.4 Surface Water Availability during Construction Phase ............................................................... 76
4.11.5 Surface Water Availability during Operation Phase ................................................................... 76
4.11.6 Alternate Sustainable Water Management Strategies during Operational Phase .................... 77
4.11.7 Water Quality ............................................................................................................................. 77
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. iv
4.11.8 Construction Water Quality ........................................................................................................ 80
4.12 LAND ENVIRONMENT ................................................................................................................................ 80
4.12.1 Soil .............................................................................................................................................. 80
4.12.2 Soil Quality .................................................................................................................................. 81
4.12.3 Soil Fertility ................................................................................................................................. 83
4.12.4 Soil Permeability ......................................................................................................................... 83
4.12.5 Soil Porosity ................................................................................................................................ 83
4.13 BIOLOGICAL ENVIRONMENT ....................................................................................................................... 84
4.13.1 Habitat Assessment .................................................................................................................... 84
4.13.2 Terrestrial Ecology ...................................................................................................................... 84
4.14 SOCIO-ECONOMIC ENVIRONMENT ............................................................................................................... 87
4.14.1 General Socio-Economic Profile .................................................................................................. 88
4.14.2 Demographic Profile ................................................................................................................... 88
4.14.3 Education & Literacy ................................................................................................................... 88
4.14.4 Economic Activity and Livelihood Pattern .................................................................................. 88
4.14.5 Existing Physical & Social Infrastructure Facilities in the Region ............................................... 88
5 POLLUTION SOURCES, IMPACT PREDICTION & IMPACT ASSESSMENT ................................................... 90
5.1 POLLUTION SOURCES ................................................................................................................................ 90
5.2 IMPACT PREDICTION AND IMPACT ASSESSMENT ............................................................................................. 91
5.3 IMPACT ON PHYSICAL ENVIRONMENT ................................................................................................... 93
5.3.1 Impact on Land use & Aesthetic ................................................................................................. 93
5.3.2 Impact on Topography ............................................................................................................... 94
5.3.3 Impact on Geology ..................................................................................................................... 94
5.3.4 Impact on Drains ........................................................................................................................ 94
5.3.5 Impact due to Tectonics / Earthquakes ...................................................................................... 95
5.3.6 Impact on Mineral Resources ..................................................................................................... 95
5.3.7 Climate & Meteorology .............................................................................................................. 95
5.4 IMPACT ON AIR ENVIRONMENT ................................................................................................................... 95
5.4.1 Air Emissions Sources ................................................................................................................. 95
5.4.2 Fugitive Emissions from site preparation ................................................................................... 96
5.4.3 Impact on Air Environment due to Construction Activities ......................................................... 96
5.4.4 Impact on Air Environment during Operation .......................................................................... 103
Model Assumption ..................................................................................................................................... 104
Table 5:11 Max. Resultant GLCs due to Vehicular Movement .................................................................. 104
5.5 IMPACT ON NOISE ENVIRONMENT ............................................................................................................. 111
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. v
5.5.1 Impact on Noise Environment during Construction Phase ....................................................... 111
5.5.2 Impact on Noise Environment during Operation Phase ........................................................... 113
5.6 IMPACT ON WATER ENVIRONMENT ........................................................................................................... 114
Impact on Water Environment during Construction Phase ...................................................... 114
5.6.1 114
5.6.2 Impact on Water Environment during Operation Phase .......................................................... 116
5.7 IMPACT ON LAND ENVIRONMENT .............................................................................................................. 122
5.7.1 Impact on Land Environment during Construction Phase ........................................................ 122
5.7.2 Impact on Land Environment during Operation Phase ............................................................. 124
5.8 IMPACT ON BIOLOGICAL ENVIRONMENT .................................................................................................. 127
5.8.1 Impact during Construction Phase ........................................................................................... 127
5.8.2 Impact during Operation Phase ................................................................................................ 128
5.9 IMPACT ON SOCIO-ECONOMIC ENVIRONMENT ............................................................................................. 128
5.9.1 Positive Impacts ........................................................................................................................ 128
5.9.2 Negative Impacts ...................................................................................................................... 129
5.9.3 Negligible Impacts .................................................................................................................... 130
5.10 IMPACT ON HISTORICAL, ARCHAEOLOGICAL AND ARCHITECTURAL SITES ............................................................ 130
5.11 SUMMARY OF IMPACTS ........................................................................................................................... 130
6 ENVIRONMENTAL MANAGEMENT PLAN ............................................................................................. 134
6.1 INTRODUCTION ...................................................................................................................................... 134
6.2 CAPACITY BUILDING FOR EMP IMPLEMENTATION ........................................................................................ 134
6.3 IMPLEMENT ARRANGEMENTS FOR EMP ..................................................................................................... 134
6.4 ENVIRONMENTAL MANAGEMENT PLAN MATRIX .......................................................................................... 134
6.5 EMP FOR AIR ENVIRONMENT................................................................................................................... 149
6.5.1 Site Preparation ........................................................................................................................ 149
6.5.2 Noise Environment ................................................................................................................... 150
6.5.3 Construction Material Management ........................................................................................ 151
6.5.4 Vehicle Emission Controls and Alternatives .............................................................................. 152
6.6 EMP FOR NOISE ENVIRONMENT ............................................................................................................... 158
6.6.1 Construction Phase ................................................................................................................... 158
6.6.2 Operation Phase ....................................................................................................................... 159
6.7 EMP FOR WATER ENVIRONMENT ............................................................................................................. 159
6.7.1 Construction Phase ................................................................................................................... 159
6.7.2 Water Source Development ...................................................................................................... 160
6.7.3 Provision of Water Body ........................................................................................................... 163
6.7.4 Promoting Reuse of Water after Treatment ............................................................................. 163
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. vi
6.8 EMP FOR LAND ENVIRONMENT ................................................................................................................ 167
6.8.1 Construction Debris .................................................................................................................. 167
6.8.2 Waste from Labour Colonies & Biomass .................................................................................. 167
6.8.3 Topsoil Management ................................................................................................................ 168
6.8.4 Solid Waste Management ........................................................................................................ 168
6.9 EMP FOR E-WASTE MANAGEMENT .......................................................................................................... 170
6.10 EMP FOR ECOLOGICAL ENVIRONMENT ...................................................................................................... 171
6.10.1 Construction Phase ................................................................................................................... 171
6.10.2 Operational Phase .................................................................................................................... 171
6.10.3 Green Belt Plan ......................................................................................................................... 171
6.10.4 Greenbelt Design for Site .......................................................................................................... 172
6.11 EMP FOR SOCIO-ECONOMIC ENVIRONMENT ............................................................................................... 175
6.11.1 Mitigative Measures ................................................................................................................. 175
6.11.2 Social Activities Proposed to be undertaken ............................................................................. 176
6.12 EMP FOR ENERGY CONSERVATION ............................................................................................................ 176
6.12.1 Solar Passive Techniques .......................................................................................................... 177
6.12.2 Adoption of Lighting Control .................................................................................................... 178
6.12.3 Light Power Density (LPD) ........................................................................................................ 179
6.12.4 Use of renewable energy system .............................................................................................. 179
6.12.5 Use of Energy Efficient Building Material ................................................................................. 179
6.12.6 Thermal Properties of Building Components ............................................................................ 182
6.12.7 Thermal Properties of Enhance Building Material .................................................................... 182
6.13 ENERGY BALANCE .................................................................................................................................. 184
6.13.1 Shadow Analysis ....................................................................................................................... 185
6.13.2 Ventilation ................................................................................................................................ 191
6.13.3 Energy Consumption ................................................................................................................. 191
6.13.4 Energy Saving in the Project ..................................................................................................... 191
6.14 STRUCTURAL SAFETY MEASURES .......................................................................................................... 194
6.15 ELECTRICAL HAZARDOUS AND SAFETY MEASURE PLAN .................................................................................. 194
6.16 EMP FOR GREEN HOUSE EFFECTS, RADIATION EFFECTS, OZONE DEPLETION EFFECTS AND ACID RAIN EFFECTS ............. 201
6.17 EMP FOR FIRE FIGHTING ......................................................................................................................... 203
6.18 HEALTH AND WELFARE PLAN.................................................................................................................... 206
6.18.1 Fixation of Hours of Work and Interval of Rest & Spread Over ................................................ 206
6.18.2 Weekly rest, payment of work dones on the day of rest at overtime rate, etc. ....................... 206
6.18.3 Notice of Wage Period .............................................................................................................. 206
6.18.4 Accommodation ....................................................................................................................... 206
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. vii
6.18.5 Latrine and Urinal ..................................................................................................................... 207
6.18.6 Canteens ................................................................................................................................... 207
6.18.7 Medical Facilities ...................................................................................................................... 208
6.18.8 Emergency Care Services or Emergency Treatment ................................................................. 209
6.19 SAFETY MEASURES................................................................................................................................. 209
6.19.1 General Safety Measures .......................................................................................................... 209
6.19.2 Safety for Welding & Cutting .................................................................................................... 210
7 ENVIRONMENTAL MONITORING PLAN ................................................................................................ 212
7.1 GENERAL .............................................................................................................................................. 212
7.2 OBJECTIVES OF ENVIRONMENTAL MONITORING PLAN ................................................................................... 212
7.3 SUGGESTED ENVIRONMENTAL MONITORING PLAN ....................................................................................... 212
7.3.1 Data Analysis ............................................................................................................................ 217
7.3.2 Reporting Schedule ................................................................................................................... 217
7.3.3 Emergency Procedures/Corrective Measures ........................................................................... 217
8 RISK ASSESSMENT & DISASTER MANAGEMENT PLAN ......................................................................... 218
8.1 INTRODUCTION ...................................................................................................................................... 218
8.2 HAZARD ............................................................................................................................................. 218
8.3 RISK .................................................................................................................................................... 218
8.4 HAZARD IDENTIFICATION AND RISK ASSESSMENT DURING THE CONSTRUCTION PHASE ........................................... 219
8.5 METHOD STATEMENTS ............................................................................................................................ 219
8.6 SAFE WORK METHOD STATEMENT STEP BY STEP ......................................................................................... 219
8.7 PERMITS TO WORK................................................................................................................................. 220
8.8 RISK ASSESSMENT DURING THE OPERATION PHASE ......................................................................................... 222
8.8.1 Earthquake Hazard ................................................................................................................... 222
8.8.2 Drought .................................................................................................................................... 223
8.8.3 Flood ......................................................................................................................................... 223
8.8.4 Fire ............................................................................................................................................ 223
8.9 DISASTER MANAGEMENT PLAN FOR CONSTRUCTION PHASE ........................................................................... 224
8.10 DISASTER MANAGEMENT PLAN FOR OPERATION PHASE ................................................................................ 225
8.10.1 On Site Emergency Management Plan ..................................................................................... 225
8.11 KEY PERSONS AND RESPONSIBILITIES .......................................................................................................... 226
8.11.1 Site Main Controller .................................................................................................................. 226
8.11.2 Work Incident Controller .......................................................................................................... 227
8.11.3 Safety Coordinator .................................................................................................................... 227
8.11.4 Medical Officer ......................................................................................................................... 227
8.11.5 Maintenance Support Officer ................................................................................................... 227
8.11.6 Civil Support Officer .................................................................................................................. 227
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. viii
8.11.7 Material Support Officer ........................................................................................................... 227
8.11.8 Area Staff .................................................................................................................................. 227
8.11.9 Running Messengers ................................................................................................................ 228
8.11.10 Employees ................................................................................................................................. 228
8.11.11 Technical Coordinator............................................................................................................... 228
8.11.12 Utilities Coordinator ................................................................................................................. 228
8.11.13 Liaison and Public Relations Coordinator ................................................................................. 228
8.11.14 Transportation Coordinator ...................................................................................................... 228
8.11.15 Communication Coordinator .................................................................................................... 228
8.12 EMERGENCY PREPAREDNESS .................................................................................................................... 228
8.12.1 Fire Detection and Fire Fighting ............................................................................................... 229
8.12.2 Personal Protective Equipment ................................................................................................ 229
8.12.3 Communication System ............................................................................................................ 229
8.12.4 Training .................................................................................................................................... 229
8.12.5 Emergency Control Center ........................................................................................................ 229
8.13 EMERGENCY MANAGEMENT PROCEDURE ................................................................................................... 229
8.14 OFF-SITE EMERGENCY PREPAREDNESS PLAN ............................................................................................... 230
8.14.1 Emergency Code of Practices .................................................................................................... 231
8.14.2 Fire fighting COP ....................................................................................................................... 231
8.15 MANAGEMENT FRAMEWORKS AND CONCLUSION ......................................................................................... 232
8.15.1 Coordination with Concerned Authorities ................................................................................ 232
9 CORPORATE ENVIROMENT RESPONSIBILITY ........................................................................................ 234
9.1 ENVIRONMENT POLICY ............................................................................................................................ 234
9.2 STANDARD OPERATING PROCEDURES ......................................................................................................... 234
9.3 HIERARCHICAL SYSTEM OF THE ORGANIZATION ............................................................................................ 234
9.4 REPORTING MECHANISM OF NON-COMPLIANCE .......................................................................................... 235
10 DISCLOSURE OF EIA PREPARES ............................................................................................................ 237
10.1 THE PROJECT PROPONENT - M/S COMMANDER REALTORS PVT. LTD. ....................................................... 237
10.2 EIA CONSULTANTS – GREENC INDIA CONSULTING PRIVATE LIMITED ...................................................... 238
10.3 AREA OF EXPERTISE (GCPL) .................................................................................................................... 239
10.4 QCI/NABET ACCREDITATION STATUS OF THE EIA CONSULTANT .................................................................... 240
10.5 BRIEF RESUME OF TEAM MEMBERS .......................................................................................................... 242
10.6 ENVIRONMENTAL MONITORING LABORATORY ............................................................................................. 243
11 SUMMARY & CONCLUSIONS ............................................................................................................... 245
11.1 INTRODUCTION ...................................................................................................................................... 245
11.2 PROJECT DESCRIPTION ............................................................................................................................ 245
11.2.1 Salient Features of the Project.................................................................................................. 245
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. ix
11.3 CONCLUSIONS ....................................................................................................................................... 247
11.4 OVERALL JUSTIFICATION FOR IMPLEMENTATION OF THE PROJECT..................................................................... 247
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. x
List of Table
Table 1:1 License Details of Proposed Project Site ................................................................................ 2
Table 1:2 Survey Nos. / Plot Nos. of Proposed Project Site ................................................................... 3
Table 1:3 General Conditions as per EIA Notification 2006 .................................................................. 5
Table 2:1 Project Site Coordinates........................................................................................................ 13
Table 2:2 Landuse Distribution of Project Site ..................................................................................... 17
Table 2:3 Area Statement for Proposed Independent Floors ................................................................ 18
Table 2:4 Population Details for Proposed Independent Floors Project ............................................... 20
Table 2:5 Water Demand in Proposed Independent Floors Project ...................................................... 21
Table 2:6 Wastewater Generation in Proposed Independent Floors Project ......................................... 22
Table 2:7 RWH and Water Body Details in in Proposed Project ......................................................... 22
Table 2:8 Power Demand in Proposed Independent Floors Project...................................................... 23
Table 2:9 Parking Details of Proposed Independent Floors Project ..................................................... 23
Table 2:10 Quantity of Natural Resources ........................................................................................... 25
Table 2:11 Proposed Construction Schedule (Month Wise) ................................................................. 25
Table 3:1 Summary of Environmental Legislation concerning Proposed Project ................................ 29
Table 4:1 Environmental Components & Parameters for Baseline Study ............................................ 45
Table 4:2 Geological Sequence of the Area .......................................................................................... 50
Table 4:3 History of Earth Quake in NCR Region from April 1980 to March 2013 ............................ 52
Table 4:4 Area, production and productivity of Major Crops in Gurgaon .......................................... 54
Table 4:5 Primary Sources & Effects of Air Pollutants due to Proposed Project ................................. 54
Table 4:6 Averaged Minimum Temperature Profile (1997 to 2011) –Met station Palam .................... 55
Table 4:7 Averaged Maximum Temperature Profile (1997 to 2011) –Met station Palam ................... 55
Table 4:8 Rainfall Data for Last Fifteen Years in Delhi (Palam) ......................................................... 56
Table 4:9 Cloud Cover Data for Last Fifteen Years of Delhi (Safdarjung), Morning Hours (8.30 IST)
.............................................................................................................................................................. 56
Table 4:10 Cloud Cover Data for Last Fifteen Years of Delhi (Safdarjung), Evening Hours (17.30
IST) ....................................................................................................................................................... 56
Table 4:11 Monthly Mean Wind Speed in KMPH (Year 1993 – 2005) .............................................. 57
Table 4:12 Monthly Mean Speed in KMPH (Year 2009 – 2014) ......................................................... 57
Table 4:13 Stability Class ..................................................................................................................... 61
Table 4:14 Meteorological Monitoring Data (Winter Season – 01.01. 2015 to 31.01.2015) ............... 62
Table 4:15 Details of Ambient Air Quality Monitoring Locations ....................................................... 63
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xi
Table 4:16 Monitoring Program Results SO2 (g/m3) .......................................................................... 63
Table 4:17 Monitoring Program Results – Nox (g/m3) ...................................................................... 64
Table 4:18 Monitoring Program Results – CO (g/m3) ........................................................................ 64
Table 4:19 Monitoring Program Results – PM10 (g/m3) ..................................................................... 65
Table 4:20 Monitoring Program Results -PM 2.5 (g/m3) ..................................................................... 66
Table 4:21 Primary Effects of Noise Pollution from Construction & Operation Activities of the Site ... 67
Table 4:22 Ambient Noise Standards as per CPCB .............................................................................. 67
Table 4:23 Baseline Background Noise Quality Monitoring Results ................................................... 68
Table 4:24 Traffic Volume Count ......................................................................................................... 68
Table 4.25 Population and Trip generation in horizon year 2021 ......................................................... 69
Table 4.26 Traffic projection and road capacity requirement ............................................................... 70
Table 4.27 Capacity standards (IRC 106) ............................................................................................. 70
Table 4.28 Categorization of Road based on UDFI Norms and as Proposed in the Project Site ......... 71
Table 4:29 True Resistivity in ohm meters for Surveyed point VES-1 ............................................... 75
Table 4:30 Baseline Water Quality Monitoring Location ..................................................................... 78
Table 4:31 Ground Water Quality near the Project Site ....................................................................... 78
Table 4:32 Soil Type based on Particle Size ......................................................................................... 81
Table 4:33 Soil Characteristics at Different Depths ............................................................................. 81
Table 4:34 List of Floral Species found within 10 km radius .............................................................. 85
Table 4:35 List of Avifauna within 10 Km Radius ............................................................................... 86
Table 4:36 Demographic Details .......................................................................................................... 88
Table 5:1 Potential Pollutant Sources & Characteristics ...................................................................... 90
Table 5:2 Identification of potential Impacts during Construction & Operation Phase ........................ 92
Table 5:3 Quantity of Quarry Material ................................................................................................ 94
Table 5:4 Diesel Generator Set Specifications...................................................................................... 97
Table 5:5 Ground Level SO2 (µG/M3) Concentration at Different Locations (24 hourly Averaged) .... 98
Table 5:6 Ground Level NOx (µG/M3) Concentration At Different Locations (24 hours Averaged) .... 99
Table 5:7 Ground Level PM10 Concentration (µG/M3) At Different Locations (24 hours Averaged) . 100
Table 5:8 Ground Level PM2.5 Concentration (µG/M3) At Different Locations (24 hours Averaged) 101
Table 5:9 Ground Level CO (µG/M3) Concentration at Different Locations (1 hours Averaged) ....... 102
Table 5:10 Vehicle Emission Statement ............................................................................................. 104
Table 5:13 Ground Level SO2 (µG/M3) Concentration (24 hourly Averaged) due to DG sets ............ 106
Table 5:14 Ground Level NOx (µG/M3) Concentration (24 hours Averaged) due to DG sets ............. 107
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xii
Table 5:15 Ground Level PM10 Concentration (µG/M3) (24 hours Averaged) due to D.G. Sets ......... 108
Table 5:16 Ground Level PM2.5 Concentration (µG/M3) (24 hours Averaged) due To D.G. Sets ....... 109
Table 5:17 Ground Level CO (µG/M3) Concentration (1 hours Averaged) due to D.G. sets .............. 110
Table 5:18: Noise levels Generated from Construction Equipment ................................................... 111
Table 5:19: Ultimate Water Requirements for Proposed Project ........................................................ 117
Table 5:20: Expected Treated Wastewater Characteristics ................................................................. 121
Table 5:21: Standards for Effluent Disposal ....................................................................................... 121
Table 5:22: Expected Solid Waste Generation ................................................................................... 125
Table 5:23 E-waste Generated – Independent Floors Project ............................................................. 126
Table 5:24 Summary Matrix of Predicted Impacts due to Proposed Project ..................................... 130
Table 6:1 : Environmental Management Plan Matrix ......................................................................... 136
Table 6:2 Parking Details – Independent Floors Project .................................................................... 153
Table 6:3 Trees that can be used as barrier for Air Pollution ............................................................. 153
Table 6:5 Run-Off Coefficient Parameters ......................................................................................... 160
Table 6:6 Wastewater Inlet and Outlet Characteristics ....................................................................... 166
Table 6:7: Proposed List of Plant Species .......................................................................................... 175
Table 6:8 LPD Levels for the Design of Residential Block ............................................................... 179
Table 6:9 Used of Material with Recycled Contents .......................................................................... 182
Table 6:10 Thermal Factors for Building component ....................................................................... 182
Table 6:11 Thermal Properties of Enhance Building Material ........................................................... 183
Table 6:12 List of Codes Adopted for Structural Safety..................................................................... 194
Table 7:2: Applicable Standards for different Environmental Components ....................................... 217
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xiii
List of Figures
Figure 1.1 Organisation Chart ................................................................................................................ 2
Figure 1.2 EIA Methodology .................................................................................................................. 5
Figure 2.1 Location of the Proposed Project Site on GMUC 2031 AD Map ....................................... 10
Figure 2.3 Location of the Proposed Site on District Map ................................................................... 11
Figure 2.4 Location Map of the Proposed Site on Survey of India Toposheet No H43X3 .................. 12
Figure 2.5 Location of Site on Google Image ....................................................................................... 12
Figure 2.6 Geographical Setting of Project Site.................................... Error! Bookmark not defined.
Figure 2.7 Environmental Sensitivity with 15 km & 1 km radius of the Project SiteError! Bookmark
not defined.
Figure 2.8 Site Connectivity at Project Site ......................................................................................... 14
Figure 2.9 Site Features within 500 m Boundary of Project Site .......................................................... 15
Figure 2.10 Photographs - Site and Surrounding Features ................................................................... 16
Figure 2.12 Land-use Distribution of Proposed Project Site ................................................................ 17
Figure 2.13 Section of Proposed Independent Floors ........................................................................... 19
Figure 2.14 Elevation of Proposed Independent Floors ........................ Error! Bookmark not defined.
Figure 2.15 Perspective View of Proposed Independent Floors ........................................................... 20
Figure 4.1 Contour Plan of the Project Site .......................................................................................... 49
Figure 4.2 Locations of Field Investigations points at Project Site ..................................................... 51
Figure 4.4 Drainge Pattern within 500 m Radius of Project Site ......................................................... 54
Figure 4.5 Wind Rose Diagrams for 8.30 Hrs. (Morning ) for the Year 1985-2002 ........................... 58
Figure 4.6 Wind Rose Diagrams for 17.30 Hrs. (Evening) for the Year 1985-2002 ............................ 59
Figure 4.7 Wind Rose Diagram for Year 2009 – 2014 ......................................................................... 59
Figure 4.8 Wind Rose at Project Site .................................................................................................... 62
Figure 4.9 Air, Noise, Water and Soil Monitoring Locations .............................................................. 63
Figure 4.10 Concentration of SO2 (g/m3) ............................................................................................ 64
Figure 4.11 Concentration of NOx (g/m3) .......................................................................................... 64
Figure 4.12 Concentration of CO (g/m3) ............................................................................................ 65
Figure 4.13 Concentration of PM10 (g/m3) .......................................................................................... 65
Figure 4.14 Concentration of PM 2.5 (g/m3) ........................................................................................ 66
Figure 4.15 Location of Traffic Volume Count .................................................................................... 68
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xiv
Figure 4.17 Road network considered for traffic forecasting ............................................................... 70
Figure 4.18 Hierachy of Roads within Project Site .............................. Error! Bookmark not defined.
Figure 4.19 Groundwater User Map of Gurgaon District ..................................................................... 73
Figure 4.20 Site Plan showing location of surveyed points .................................................................. 75
Figure 4.21 Resistivity Curve for surveyed point VES-1 Obtanied for Proposed Project Site ............. 76
Figure 5.1: Spatial Distribution of 24 Hours Average SO2 GLC (µG/M3) ............................................. 99
Figure 5.2: Spatial Variation of 24 hours averaged NOx GLC (µG/M3) .............................................. 100
Figure 5.3: Spatial Distribution of 24 hours averaged PM10 GLC (µG/M3) ......................................... 101
Figure 5.4: Spatial Distribution of 24 hours averaged PM2.5 GLC (µG/M3) ........................................ 102
Figure 5.5: Spatial Distribution of 1 hours averaged CO GLC (µG/M3) ............................................. 103
Figure 5.6: Spatial Distribution of 24 Hours Average SO2 GLC (µG/M3) ........................................... 107
Figure 5.7: Spatial Variation of 24 hours averaged NOx GLC (µG/M3) .............................................. 108
Figure 5.8: Spatial Distribution of 24 hours averaged PM10 GLC (µG/M3) ......................................... 109
Figure 5.9: Spatial Distribution of 24 hours averaged PM2.5 GLC (µG/M3) ........................................ 110
Figure 5.10: Spatial Distribution of 1 hourly averaged CO GLC (µG/M3) .......................................... 111
Figure 5.11: Spatial Variation of Incremental Noise Level during Construction Phase without Control
............................................................................................................................................................ 113
Figure 5.12: Spatial Variation of DG-set Noise Levels around the Project Site during Operation Phase
without Control ................................................................................................................................... 114
Figure 5.13: Water Balance for Proposed Project ............................................................................... 120
Figure 6.1: EMP Implementation Chart .............................................................................................. 135
Figure 6.2 Schematic layout of Cement Godown ............................................................................... 152
Figure 6.3 Traffic Circulation and Parking Plan ................................................................................. 155
Figure 6.4 Traffic Circulation & Parking Plan: Stilt Level (A4 type Typical) ................................... 156
Figure 6.5 Traffic Circulation & Parking Plan: Stilt Level (A3 type Typical) ................................... 157
Figure 6.6 Section of RWH Pit Proposed ........................................................................................... 161
Figure 6.8 Dual Plumbing Line Diagram .............................................. Error! Bookmark not defined.
Figure 6.9 Waste Management Flow Diagram ................................................................................... 170
Figure 6.10 Landscape Plan – Proposed Independent Floors Project ... Error! Bookmark not defined.
Figure 6.11 Electrical Line Diagram.................................................... Error! Bookmark not defined.
Figure 6.12 Earth Pit Layout Plan (ESS) .............................................. Error! Bookmark not defined.
Figure 6.13 Location of Lightning Arrestors in Proposed Project (TYPICAL UNIT) ...................... 200
Figure 6.14 Fire Tender Plan for Proposed Independent Floors Project ............................................. 204
Figure 6.15 Proposed Fire Escape Route Plan (TYPICAL) ................. Error! Bookmark not defined.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xv
Figure 9.1 Hierarchical System of the Organisation ........................................................................... 235
Figure 9.2 Reporting Mechanism of Non-Compliance ..................................................................... 236
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xvi
List of Annexures
Annexure 1.1 : License copy issued by DTCP (11.7188 Acres)
Annexure 1.2 : License copy issued by DTCP (1.3438 Acres)
Annexure 1.3 : Copy of Order no. 593 (Land Exchange Order) (5.075 Acres)
Annexure 1.4 : Copy of Approved ToR issued by HSEAC
Annexure 2.1 : Environment Sensitivity Map
Annexure 2.2 : Application to HUDA for Water Supply Assurance
Annexure 2.3 : Electrical Load Calculation
Annexure 2.4 : List of Building Material
Annexure 3.1 : Discharge Standards
Annexure 3.2 : Drinking Water Quality Standards
Annexure 3.3 : Ambient Air Quality Standards
Annexure 3.4 : Ambient Noise Quality Standards.
Annexure 4.1 : Site specific Metrological Data
Annexure 4.2 : CPCB Notification
Annexure 4.3 : Ambeint Air Quality Results for Winter season (Nov.’2014 to Mar.’ 2015)
Annexure 4.4 : Noise Quality Results for Winter season (Nov.’2014 to Mar.’ 2015)
Annexure 4.5 : Traffic Results for Winter season (Nov.’2014 to Mar.’ 2015)
Annexure 4.6 : Groundwater Quality Results for Winter season (Nov.’2014 to Mar.’ 2015)
Annexure 4.7 : Soil Quality Results for Winter season (Nov.’2014 to Mar.’ 2015)
Annexure 4.8 : Forest NOC
Annexure 4.9 : NOC from Depty Comissioner (DC) regarding Aravali Notification
Annexure 6.1 : Noise & Vibration Control Plan
Annexure 6.2 : Parking Calculation
Annexure 6.3 : Rainwater Harvesting Design Calculation
Annexure 6.4 : STP Design Details Report
Annexure 6.5 : Ventilation Plan
Annexure 6.6 : Energy Saving Calculations for Solar Water Heating
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. xvii
Annexure 6.7 : Energy Saving using energy efficient equipments / devices
Annexure 6.8 : List of Electrical Code
Annexure 9.1 : Standard Operating Procedures
Annexure 10.1 : Copy of MoEF accreditation of ITL Labs Private Limited
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 1.
1 INTRODUCTION
1.1 PROFILE OF PROJECT PROPONENT
M/s Commander Realtors Pvt. Ltd. Limited is one of the associate companies of Ireo Pvt. Ltd. Ireo is
amongst the largest focused Foreign Direct Investment ( FDI ) in the Indian Real Estate managing
approximately USD 2 billion of capital having the backing of Blue Chip Investors and respected
Financial Institutions. They have emerged as a major pan-India developer equipped with financial
strength to fully leverage available opportunities in this sector. All the policies and standard operating
procedures followed by Ireo Pvt. Ltd. are applicable to and are abide by all its subsidiary companies
M/s Commander Realtors Pvt. Ltd. , proposing to develop a Independent Floors at Sector 61, Village
Ullawas, Tehsil Sohna, District-Gurgaon, in the State of Haryana as a part of its vision to develop
state-of-the-art infrastructure for the Nation. The establishment of the project will bring more
developmental activities in the area and there will be an enhancement in the living standards of local
people.
1.2 NAME AND CONTACT ADDRESS OF PROJECT PROPONENT
The contact Name and address of M/s Commander Realtors Pvt. Ltd. is as given below:
Dr. Asha Sharma, Authorized Signatory
M/s Commander Realtors Pvt. Ltd.
C/o Ireo Pvt. Ltd.
Ireo Campus, Sector-59, Village-Behrampur
Gurgaon -122011
Ph.No – 0124 – 4795000,
Fax. No. 0124 -4795100
1.3 IMPLEMENTING ORGANIZATION:
M/s Commander Realtors Pvt. Ltd. will be developing organization and will develop Independent
Floors at Sector 61, Village Ullawas, Tehsil Sohna, District-Gurgaon, in the State of Haryana as a part
of its vision to develop state-of-the-art infrastructure for the Nation. The project will know as
“Independent Floors Development, Sector 61, Gurgaon”
1.4 ORGANIZATIONAL CHART
M/s Commander Realtors Pvt. Ltd. is one of the associate companies of Ireo Pvt. Ltd. Hence, all the
policies and standard operating procedures followed by Ireo Pvt. Ltd. are applicable to and are abide
by all its subsidiary companies.
The organization chart of M/s Commander Realtors Pvt. Ltd. is shown in Figure 1.1
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 2.
Figure 1.1 Organisation Chart
1.5 LAND DESCRIPTION
The proposed Independent Floors project has total area of 73,401.77 sq m (18.138 Acres) at Sector
61, falling under the revenue boundary of village Ullawas, Tehsil Sohna, District Gurgaon, State
Haryana. The land details showing plot no. / survey nos, status of ownership of land, license and its
validity and its collaboration agreement are given below.
1.5.1 License and its Validity
The proposed project is Independent Floors project and the license & order details granted by DTCP
are given below in Table 1.1
Table 1:1 License Details of Proposed Project Site
S.No License No // Order Date Validity Annexure
1. License No. 63 of 2009 03.11.2009 02.11.2015 1.1
2. License No. 60 of 2012 11.06.2012 10.06.2016 1.2
3. Order No. 593
(Land Exchange Order) 19.08.2014 __ 1.3
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 3.
1.5.2 Status of Ownership and Collaboration Agreement
The details of land ownership along with collaboration agreement have been submitted along with
Form 1 and appraised during the 116th Meeting of HSEAC held on 07.02.2015 for ToR approval. The
summary of the land schedule is given in subsequent section.
1.5.3 Land Details showing Plot Nos. / Survey Nos.
Refer Table 1.2 given below for the details of Khasra nos.
Table 1:2 Survey Nos. / Plot Nos. of Proposed Project Site
LICENSE DETAILS ISSUED BY DTCP
Land owned by
Land schedule
Village Rect. Kila
A License No. 63 of 2009
1 Commander Realtors Pvt. Ltd. Ullawas 15 6 min
2 Ornamental Realtors Pvt. Ltd Ullawas
14 12
15 15
14 11
20
3 BTVS Buildwell Pvt. Ltd. Ullawas
14
19
21/1
22
15 25/1
23 5/1
24 2/1/1/1
1/1/1
4 Buzz Hotels Pvt. Ltd. Ullawas 15
16
17
24
25/2
5 Regal Green Lands Pvt. Ltd. Ullawas 14 8/2 min
6 Massifcon Buildwell Pvt. Ltd. Ullawas 15 7 min
7 KSS Properties Pvt. Ltd. Ullawas 14 23/1
8 Golden View Builders Pvt. Ltd. Ullawas
15 23/2 min
23 3/1/2 min
4/1
Sub Total (A) 11.7188 Acres
B License No. 60 of 2012
1 Commander Realtors Pvt. Ltd. Ullawas 14 18/2
15 18 min
2
Commander Realtors Pvt. Ltd. (118/135), Smt.
Ramrati w/o. Lakhpat, Giriraj S/o. Lakhpat &
Baleshwari, Suman D/o. Lakhpat (2/135)
share, Smt. Sansaar Devi w/o. Hemchand
(15/135) share
Ullawas 14 21/2
3 Rampal, Kishan Ss/o. Shyamlal Ullawas 14 13/1
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 4.
Sub Total (B) 1.3438 Acres
C Order no. 593 (Land Exchange Order) 5.075 Acres
Total (A+B+C)
18.138 Acres
(73,401.77 sqm)
1.6 LITIGATION(S) OR ORDERS PASSED BY ANY COURT OF LAW / ANY
STATUTORY AUTHORITY
There are no litigation pending or filled against the proposed project and / or directions orders passed
by any court of law or any statutory authority against the project.
1.7 OBJECTIVES OF THE EIA STUDY
The basic objective of this EIA study is to collect the baseline data within the impact zone so as to
identify the associated impacts and propose suitable mitigation measures due to the construction and
operation of the proposed project. The area for the general study has been identified as 10 km radius
around the proposed project. The core study area is within 500 m radius from the boundary of the
project site as per EIA Guidance Manual for Building, Construction, Township and Area
Development Projects issued by MoEF (section 3.3). The objectives of the EIA study are as follows:
i. to describe the proposed project and associated works together with the requirements for
carrying out the proposed development;
ii. to identify and describe the elements of the community and environment likely to be
affected by the proposed developments;
iii. to identify, predict and evaluate environmental and social impacts expected to arise during
the construction and operation phase of the project in relation to the sensitive receptors;
iv. to identify the negative impacts and develop mitigation measures so as to minimize
pollution, environmental disturbance and nuisance during construction and operations of the
development; and
v. to design and specify the monitoring and audit requirements necessary to ensure the
implementation and the effectiveness of the mitigation measures adopted.
1.8 SCOPE OF THE STUDY
The study involves, detailed reconnaissance visit to the site to assess the existing environmental
baseline condition of the area, subsequent assessment of potential impact from the construction
activity and operation phase of the proposed development in order to suggest the necessary mitigation
measures, required to be taken for the protection of the environment.
1.9 EIA METHODOLOGY
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 5.
Project Scoping
Identify potential sources of
Impact
Predict consequences and
likelihood of Impact
Project Site
Evaluate the significance
Investigate options for
mitigation
Prepare final EIA report
(Along with EMP and
DMP)
EC from regulatory
authorities
Inte
ract
ion
wit
h P
roje
ct P
rop
on
ents
Co
nsu
ltatio
n w
ith sta
keh
old
ers
Ba
seli
ne
Stu
die
s( E
xis
tin
g d
ata
Co
llec
tio
n a
nd
new
su
rvey
s
The EIA study for the proposed project has been carried out as per the EIA guidelines of the Ministry
of Environment and Forest (MoEF) and to meet the general requirement of the Haryana State
Environmental Impact Assessment Authority (Haryana SEIAA). The EIA methodology for the
proposed project has been described in Figure 1.2
Figure 1.2 EIA Methodology
1.10 PURPOSE OF THE REPORT
The proposed Independent Floors is a designated project under Category B of the Schedule and falls
under Item 8b (Townships and Area Development projects) of the Environmental Impact Assessment
(EIA) Notification dated September 14, 2006 and requires Environmental Clearance from the State
Environment Impact Assessment Authority (SEIAA).
As per the EIA notification 2006, the proposed project being a construction project, none of the
following General conditions (GC) are applicable for this development.
Table 1:3 General Conditions as per EIA Notification 2006
S.No. Criteria (within 10 km from boundary)
1 Protected Areas notified under the Wildlife (Protection Act), 1972
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 6.
2 Critically Polluted Areas as notified by CPCB from time to time
3 Notified Eco-sensitive areas
4 Interstate boundaries and International boundaries
The purpose of this report is to document the outcome of the Environmental Impact Assessment (EIA)
study for the proposed development of the Independent Floors at Sector 61, Village Ullawas, Tehsil
Sohna, District Gurgaon. M/s Commander Realtors Pvt. Ltd. has retained M/s GreenC India
Consulting Private Limited to conduct the Environmental Impact Assessment study for the proposed
project as per the structure, given in the EIA Notification 2006 (and subsequent amendment made
thereof) and in accordance with the Terms of Reference (ToR) approved and issued by HSEAC
during its 116th Meeting held on 07.02.2015. The copy of approved ToR issued by HSEAC is
enclosed as Annexure 1.4.
The purpose of the EIA report is to address the information on the nature and extent of potential
environmental impacts, both negative and positive, during the construction and operative phase of the
proposed project and related activities taking place concurrently.
1.11 STRUCTURE OF THE EIA REPORT
The Rapid Environment Impact Assessment (REIA) Report presents the existing baseline scenario,
assessment and evaluation of the environmental impacts that may arise during the construction and
operation period. Following impact prediction, required mitigation measures and Environmental
Monitoring Plan have been formulated. The content of the remainder part of the report is as follows:
Chapter 2: Project Description
Chapter 3: Legal & Administrative Framework
Chapter 4: Baseline Environment Status
Chapter 5: Pollution Sources, Impact Prediction and Impact Assessment
Chapter 6: Environment Management Plan
Chapter 7: Environmental Monitoring Plan
Chapter 8: Risk Assessment & Disaster Management Plan
Chapter 9: Corporate Environment Responsibility
Chapter 10: EIA Prepares
Chapter 11: Summary & Conclusion
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 7.
2 PROJECT DESCRIPTION
2.1 GOAL AND OBJECTIVES OF THE PROPOSED PROJECT
The objectives of the EIA study are as follows:
1) To describe the proposed project and associated works together with the requirements for
carrying out the proposed development.
2) To identify and describe the elements of the community and environment likely to be affected
by the proposed developments.
3) To establish the baseline environmental and social scenario of the project site and its
surroundings.
4) To identify, predict and evaluate environmental and social impacts expected to rise during the
construction and usage of the project in relation to the sensitive receptors.
5) To develop an Environmental Management Plan that identifies the negative impacts and
develops mitigation measures so as to minimize pollution, environmental disturbance and
nuisance during construction and operation of the development.
6) To design and specify the monitoring requirements necessary to ensure the implementation
and the effectiveness of the mitigation measures adopted.
2.2 SIGNIFICANCE OF PROPOSED PROJECT AT REGIONAL LEVEL
The real estate sector in India assumed greater prominence with the liberalisation of the economy, as
the consequent increase in business opportunities and labour migration led to rising demand for
commercial and housing space. At present, the real estate and construction sectors are playing a
crucial role in the overall development of India’s core infrastructure.
Residential real estate industry has witnessed stupendous growth in the past few years owing to the
following reasons:
• Continuous growth in population
• Migration towards urban areas
• Ample job opportunities in service sectors
• Growing income levels
• Rise in nuclear families
• Easy availability of finance
Demand for houses increased considerably whilst supply of houses could not keep pace with demand
thereby leading to a steep rise in residential capital values especially in urban areas. Despite
slowdown of the economy, the demand for housing continues to be strong in the country, particularly
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 8.
in the National Capital Region (NCR). Real estate consultants say that the strong demand in the
housing sector in the NCR is mainly due to strong growth in the service sector in the economy, at
around 9%.
At the same time, the government's decision to open up foreign direct investment (FDI) in multi-brand
retail will also give boost to demand in several cities, including those in the NCR. At the same time,
FDI in real estate has also started picking up as the sector has emerged as one of the best sector for
investment. According to a report by Cushman and Wakefield, the total FDI in construction
development has seen a significant fall since 2008. But the recent years have seen a strong rebound.
According to the report, the first half of 2012 recorded nearly Rs 27,600 crore inflow, which is close
to breaching the total level in 2011.
As investment increase in the sector, the construction activities are also likely to further pick up in the
coming years. This will certainly add to fresh supply in the housing sector. But at the same time, the
demand for residential real estate has also picked up in the country, particularly in the NCR.
According to C&W (Cushman and Wakefield), the demand for residential units will be around 3.80
lakh during 2012-16 in the NCR.
2.3 SIGNIFICANCE OF PROJECT AT LOCAL LEVEL
Achieving land potential in a rational and judicious manner is one of the prime objectives of this
Independent Floors development. This will be done by minimizing the impact on environmental
resources, enhancing the infrastructure quality to allow uninhibited freedom for human resource
development and provide gainful economic opportunities for employment. Urban environment on
sustainable lines will be developed, by harnessing the existing environmental resources, adopting state
of the art technologies to minimize waste generation (through recycling) and dependency on
motorized modes of transportation.
This part of the district of Gurgaon is slowly experiencing new and an upgraded emerging trend in
terms of improvement in infrastructure, new roads development etc with a real urgency of new area
development. As the area will achieve good connectivity through the sector level road development
by HUDA and through the existing southern peripheral road and Golf link road and railways, hence
these factors are likely to attract the building construction sector to come up to provide the better
infrastructure facility for the increased population.
The proposed project will lead to following benefits.
Improvement in social infrastructure by providing additional employment oppurtunities to the
skilled as well as unskilled people;
Trigger growth in the district and in the region as the area will be developed and will result in
associated development;
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 9.
The planned development with modern infrastructure facilities and source of income would
improve quality of life of local community.
Provision of residential development to cater to the increased
2.4 PROJECT BACKGROUND
The proposed project is a designated Residential Project as per Gurgaon Manesar Urban Complex
Plan(GMUC) 2031 AD, and the license/order has been accorded by Directorate of Town & Country
Planning (DTCP) for the above said development. The copy of the license/order granted by DTCP is
enclosed as mentioned in Chapter 1. The entire Independent Floors complex would be developed in
an area of 18.138 acres, which comprises of 184 Nos. of Plots with Stilt +3 level.
2.5 SITE SELECTION CRITERIA
The overall development in Gurgaon is governed as per approved Gurgaon Manesar Urban Complex
Plan (GMUC) 2031 AD.
The proposed site is selected as per the Gurgaon Manesar Urban Complex Plan (GMUC) 2031 AD.
The project site and site surrounding areas do not have any ecological sensitive areas and will be
designed to minimize the environmental impact associated with the development. The design brief
places a strong emphasis on achieving a high level of environmental performance, durability, and
healthy indoor air quality through integrated design, best practices and emerging technologies.
Sustainability is integrated into all phases of the design process using an integrated approach which
balances social, economic, and environmental factors.
2.6 NATURE AND SIZE OF THE PROJECT
As mentioned above the proposed Independent Floors Project will be developed as an area
development project spread over a total plot area of 18.138 acres (73,401.77 sqm) in the Sector 61,
village Ullawas, Gurgaon, Haryana.
The proposed project is a designated residential project as per Gurgaon Manesar Urban Complex Plan
(GMUC) 2031 AD. The proposed project will comprise of 184 Nos. of Plots with Stilt +3 level.
The project will also involve internal development of basic infrastructure such as internal roads,
power supply, water supply, sewer and storm water pipe network, waste management system along
with landscape development within the project premises.
2.7 PROJECT SITE LOCATION
The proposed project site is strategically located within the National Capital Region of New Delhi, in
the State of Haryana.The site falls in the Gurgaon district of State Haryana, which is one of the fastest
growing districts in India with a huge demand of commercial & residential development to cater the
need of public & private sector companies and for increased population respectively. The site is well
connected with Existing Golf course extension road (Southern peripheral Road). Apart from this, the
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 10.
60 m wide HUDA sector road has been developed recently which also increases the connectivity of
the proposed development. The project location/site marked on GMUC 2031 AD is given in Figure
2.1. The Approved Sectoral Plan with project site superimposed on the same and approach roads for
the site are shown in Figure 2.2.
The proposed project site is located in the revenue village of Ullawas, Tehsil Sohna, Gurgaon,
Haryana. The location of the proposed site on District Map, SOI Topo sheet and Satellite Image is
given in Figure 2.3, Figure 2.4 and Figure 2.5 respectively.
Figure 2.1 Location of the Proposed Project Site on GMUC 2031 AD Map
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 11.
Figure 2.2 Location of the Proposed Site on District Map
Project Site
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 12.
Figure 2.3 Location Map of the Proposed Site on Survey of India Toposheet No H43X3
Figure 2.4 Location of Site on Google Image
Project Site
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 13.
The geographical setting of the project is shown in Figure 2.6 and Coordinates of the project site are
given in Table 2.1
Table 2:1 Project Site Coordinates
Marks on image Latitude Longitude
1 280
24’21.50” N 770
06’02.91” E
2 280
24’18.75” N 770
06’03.29” E
3 280
24’17.68” N 770
05’58.82” E
4 280
24’18.75” N 770
06’03.29” E
5 280
24’19.14” N 770
06’07.99” E
6 280
24’21.26” N 770
06’07.65” E
7 280
24’21.24” N 770
06’06.45” E
8 280
24’22.05” N 770
06’06.41” E
9 280
24’22.07” N 770
06’07.35” E
10 280
24’25.11” N 770
06’07.33” E
11 280
24’25.33” N 770
06’03.77” E
12 280
24’25.33” N 770
05’58.26” E
2.8 ENVIRONMENTAL SENSITIVITY WITHIN 15 KM AND 1 KM RADIUS OF THE
PROJECT SITE
The map showing environment sensitivity within a radius of 15 km and 1 km of the project site are
shown in Figure 2.7. Also detailed Environmental Sensitivity Map is attached in Annexure-2.1
2.9 ENVIRONMENT LIABILITY OF THE SITE
The project site does not have any environmental liability.
2.10 SITE CONNECTIVITY
The connectivity of the site through air, roads and railway links is as follows:
Road – The site is well connected with the existing Golf course extension road (Southern Peripheral
Road). Apart from this 60m wide HUDA Sector road has been developed recently, which also increase
the connectivity of the proposed development.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 14.
Connectivity through Metro - The nearest existing metro station is HUDA city center, which is
located at a distance of about 7.0 km in North NorthWest direction.
Rail –– The nearest railway station is Gurgaon, which is located at a distance of 13.0 km towards
North west of project site.
Air – The nearest airport from the proposed site is the Indira Gandhi International Airport which is
located at distance of 17.0 km, towards North.
Overall the site is very well connected with NCR and nearby towns both by rail and road transport as
shown in Figure 2.8.
Figure 2.5 Site Connectivity at Project Site
2.11 SITE AND SITE SURROUNDINGS WITHIN 500 M BOUNDARY OF PROJECT SITE
The proposed site is slightly undulating with level variation of ~6 m between the highest and lowest
point. The site surroundings comprise of urban / rural setup and the land use in the surrounding area
comprises of villages with residential set up and barren land. The details of the surrounding features
have been given below and shown in Figure 2.9.
North: The nearby area towards the north side of the project site is vacant land earmarked for
residential development purpose.
South: Various Group Housing Projects are located towards the southern side of the project site.
East: The eastern side of the proposed project site is the presence of the settlements of village
Behrampur at a distance of approximately 0.87 km, towards the east direction.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 15.
West: Village Ullawas is located towards the west side of the project site at a distance of 0.48 km.
Figure 2.6 Site Features within 500 m Boundary of Project Site
2.12 PROJECT SITE AND SURROUNDING PHOTOGRAPHS
The photographs for site and site surrounding features are shown in Figure 2.10
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres),Sector 61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 16.
Figure 2.7 Photographs - Site and Surrounding Features
1 2
3
4
5
67
8 9
101112
Independent Floors development Project (18.138 Acres)
Project Site
1 2
3 4
3
1 2
4
2.13 PROJECT COMPONENTS
2.13.1 Development Concept
The planning of the proposed development has been largely governed by the manmade and the natural
attributes of the site. The proposed project will comprise 184 Nos. of Plots with Stilt +3 level. One
level basement is also planned to be provided in the proposed Independent Floors project. The internal
roads of proposed project will be developed as a part of the construction work.
The site is well connected with the existing Existing Golf course extension road (Southern peripheral
Road). Apart from this, the 60 m wide HUDA sector road has been developed recently which also
increase the connectivity of the proposed development. Pedestrian pathways and footpaths of
adequate widths will be provided for pedestrian safety and to reduce the vehicular movement within
the site. Total area under roads for the proposed land will be 18,065.74 sqm
2.13.2 Land Use Distribution and Area Statement
The site layout diagram with all the activities is shown in Figure 2.11. This illustrates the major
project components and their locations on the project site.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 17.
2.13.2.1 Land Use Distribution
The proposed Independent Floors project has total licensed area of 73,401.77 sq m (18.138 acres), out
of which 13.0626 Acres of area falls under two licences and the remaining area (5.075 Acres) falls
under Land exchange of Nallah. The proposed Independent Floors project will be developed at
Sector-61, Sohna falling under the revenue boundary of village Ullawas, Tehsil Sohna, District
Gurgaon and State Haryana. The landuse distribution and area Statement of 18.138 acres for 184 Nos.
of Plots with Stilt+3 level are detailed out in Table 2.2 and Figure 2.12
Table 2:2 Landuse Distribution of Project Site
S.No Landuse Area (sq m) Percentage (%)
1 Area under Plots 43200.714 58.86
2 Road and Paved Area 18,065.74 24.61
3 Green Area including water body 9709.99 13.23
4 Undecided Land use 2425.326 3.3
Total 73401.77 100
Figure 2.8 Land-use Distribution of Proposed Project Site
2.13.2.2 Area Statement
The proposed Independent Floors project will comprise of 184 Nos. of Plots with Stilt+3 levels with
car parking facility to provided at Stilt.
The Area Statement and FSI for the proposed Independent Floors are given below in Table 2.3.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 18.
Table 2:3 Area Statement for Proposed Independent Floors
S No. Description Area (m2)
1 Total Land Area 73,401.77 (18.138 Acres)
2 Ground Coverage
2.1 Permissible 23,265.33
2.2 Proposed 21,898.26
3 Permissible FSI or FAR 1.75
3.1 Permissible FAR 66,078.80
3.2 Proposed FAR 65,962.78
4 Basement area 26,419.66
5 Non FAR area 14,859.57
6 Stilt Area 18,128.78
7 Total proposed built up area including Basement
(3.2 + 4 + 5+6)
1,25,370.79
2.13.3 Project Site Elevation and Sections
The height of the buildings is 13 m. The section and elevation for the proposed project is given below
in Figure 2.13 and Figure 2.14 respectively. The perspective view of the project site is shown in
Figure 2.15.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 19.
Figure 2.9 Section of Proposed Independent Floors
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 20.
Figure 2.10 Perspective View of Proposed Independent Floors
2.13.4 Population Details
The population detail for the proposed development comprising of plots has been given in Table 2.4.
Table 2:4 Population Details for Proposed Independent Floors Project
S.No Particular Details Total dwelling
Units
Occupancy per
Unit
Total
Occupancy
1. Type of Dwelling Units
a) Independent Floors 552 4.5 2484
Total 552 -- 2484
2.14 UTILITIES PROPOSED DURING CONSTRUCTION AND OPERATION PHASES
The infrastructure facilities planned for the proposed project are highlighted in the following sub-
section and explained in detailed under Chapter 6 - Environmental Management Plan.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 21.
2.14.1 Water Requirement and Supply
2.14.1.1 Water Requirement
During construction phase, total water requirement is about 150 KLD, out of which 80 KLD is the
average peak demand of construction activities water requirement and domestic water requirement
for labourers is 70 KLD, (Considering 1200 construction labors during the peak construction period
@ 45 lpcd water demand as per Central Public Health and Environmental Engineering Organisation
(CPHEEO) and 200 will be residing in labour camp @ 86 lpcd as per Manual on Construction &
Large Building Projects).
During the operation phase, the estimated total water demand for project is about 480 KLD. The
detailed water calculation is given in subsequent section 5.6.2.1. The break-up of water demand in
proposed Independent Floors project is given below in Table 2.5:
Table 2:5 Water Demand in Proposed Independent Floors Project
S. No Details Independent Floors Project
1 Fresh 231 KLD
2 Recycle 249 KLD
3 Total 480 KLD
2.14.1.2 Water Source
During the construction phase, treated raw water to be collected and transported from STP of HUDA
and then further treatment will be given to same at project construction site as per the desired
construction water quality. The potable water requirement will be met by Tanker Supply.
During operation phase, the total water demand will be met primarily through public water supply
(HUDA Municipal Water Supply) system and reuse of treated wastewater from STP. The details on
water resource development are given in Section 5.6.2
In case of any abstraction of groundwater, due permission will be obtained from CGWA. The receipt for
Water Assurance from HUDA is attached for reference as Annexure-2.2
2.14.2 Sewage System
During the construction phase, it is expected that 57 KLD of waste water will be generated from
labour camps, which will be disposed off in septic tanks. The waste water from septic tanks will be
disposed through mobile STP tankers.
During Operation Phase, the total wastewater generated from the project site will be 277 KLD. This
generated wastewater will be treated in an on-site sewage treatment plant based on Membrane
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 22.
Bioreactor along with provision of UV treatment having total design capacity of 320 KLD. The
details of wastewater generation and the proposed STP in above said project is given in Table 2.6:
Table 2:6 Wastewater Generation in Proposed Independent Floors Project
S. No Details Quantity STP Capacity Treatment Technique to be used
in Proposed STP
1 Wastewater
Generation 277 KLD 320 KLD
Membrane Bioreactor alongwith
provision of UV treatment.
The details of design of STP are given in Section 6.7.4
2.14.3 Rainwater Harvesting System
To conserve the water resources, scientifically designed rain water harvesting structures will be
installed at 16 locations. Apart from these, water body has been created to recharge the aquifers.
Details of RHW structure in proposed project are given in Table 2.7.
Table 2:7 RWH and Water Body Details in in Proposed Project
S. No Details Nos. / Area
1 Rainwater Harvesting Structure 16 Nos.
2 Water Body 1005 sq m
The details design of rainwater harvesting structure including run-off calculations are given in Section
6.7.2 and water body details are presented in Section 6.7.3.
2.14.4 Power Requirement and Supply
Power requirement has been estimated for both construction and operation phases.
During construction phase, power will be met through DG sets and during the operation phase will
be sourced from Dakshin Haryana Bijlee Vitran Nigam Limited (DHBVNL), with back-up power
supply during operation phase of the proposed development.
Total Power requirement for the construction phase is approx. 1000 kVA which would be met through
DG sets
The power requirement for the operation phase is estimated in terms of the total maximum demand
load, which is approximately 6,402 kW (6.4 MW). Backup power will be provided by installing 5 DG
sets of 4 x 1500 & 1 x 500 KVA capacity each.The electrical load calculation is enclosed as
Annexure 2.3. The fuel consumption for 5 Nos. of DG sets has been calculated to be approx. 1.3
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 23.
KL/hour of HSD. The DG sets will be installed with acoustic enclosures and adequate stack height as
per the CPCB norms. The power demand for the proposed Independent Floors project is given in
Table 2.8.
Table 2:8 Power Demand in Proposed Independent Floors Project
S. No Details Total
1 Total Demand Load 6402 kW
2 Total Power Back-up 6500 kVA
3 DG Set Configuration 4 x 1500 kVA & 1 x 500 kVA
2.14.5 Parking
The project premises will have specialized parking facilities for smooth traffic movement within the
project site. Parking facility is provided inside the project premises and is provided on the stilt. It is
proposed to provide a provision for 1397 Nos. at Stilt. A total provision for 1397 Nos. will be
provided.
The parking provisions made in proposed project are given in Table 2.9.
Table 2:9 Parking Details of Proposed Independent Floors Project
S. No Details Total Parking
1 Stilt 1397 Nos.
Total Parking Proposed 1397 nos.
The details of parking calculations and parking plan for proposed Independent Floors have been given
in Section 6.5.4.
2.14.6 Municipal Solid Waste Management
About 1.25 TPD of MSW will be generated during the operation phase form the proposed
Independent Floors and will be handled as per the Municipal Solid Waste Management & Handling
Rules, 2000.
2.14.7 E-Waste Management
Approximate 3.59 TPA of e-waste will be generated in a worst case scenario from the proposed
development which will be stored at an identified location to be setup within site and will be sent to
authorized recyclers or e-waste processing plants for treatment as per E- Waste [Management &
Handling] Rules, 2010.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 24.
2.14.8 Sewage Sludge
An approximately 0.02 TPD of dried sludge will be generated from the proposed STP of 320 KLD
capacity based on Membrane Bioreactor along with provision of UV treatment. The sludge from
STP will be used as manure in landscaping.
The details of Solid Waste Management are given in Section 6.8.4.
2.14.9 Energy Conservation Measures
In the Operational Phase, appropriate energy conservation measures & management plan will be
adopted in order to minimize the consumptions of non-renewable fuel. The details of measures
adopted along with details of percentage saving are described in the Environment Management Plan,
Section 6.12 & Section 6.13
2.14.10 Fire Safety Facilities
The proposed project involves development of Independendent floors which will cater to various
activities and may cause fire hazard. A proper fire fighting system will be designed as per the
provisions of National Building Code (NBC) of India, 2005 Part-IV and Fire Protection Manual
issued by Tariff Advisory Committee and the latest Indian and International standards/codes. The fire
protection system will cover the entire internal and external premises of the buildings.
Following systems are planned to be provided for the building:
Portable Fire extinguishers
The fire protection details for Proposed Independent Floors are as provided in Section 6.17
2.14.11 Demolition
There is no existing structure or any material on the site which requires demolition. Hence no debris
treatment is required.
2.14.12 Building Materials and Technologies for Construction
The list of building material is enclosed as Annexure 2.4. The building materials will be purchased
from reputed manufacturers with valid test certificates only and preference with be given to local
markets. All material will be delivered to site and shall be processed for final installation at site only.
2.14.13 Quantity of Natural Resources
Table 2.10 present the quantity of natural resources proposed to be used.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 25.
Table 2:10 Quantity of Natural Resources
Description Course Sand in Cum CoarseAggregates in Cum Diesel in KL per hour
Quantity 9000 45000 0.1
Source of
Material Local market Local market Local market
2.15 RESOURCE AND MANPOWER
To the maximum extent possible, the local labor shall be employed during construction phase.
However, semi-skilled manpower and technical personnel shall be hired from outside. During the
peak period of construction, approximately 1200 labours will be hired, out of which 1,000 labourers
will be hired from nearby areas and about 200 labourers will be residing in labour camp that will be
developed on temporary basis & will destroy the same after completion of construction phase.
Approximately, 20 persons will be employed during the operation phase of the proposed project.
2.16 CONSTRUCTION PERIOD & SCHEDULE
The total construction period for the development of proposed Independent Floors is approximately 5
Years. The construction activity will start after getting the Environment Clearance (EC) and No
Objection Certificate (NOC) from respective authorities.
The proposed construction schedule for proposed project is given below in Table 2:11.
Table 2:11 Proposed Construction Schedule (Month Wise)
S.no. Description/ Items Duration in
Month(s) Start Date Finish Date
PROJECT 60 06-08-2014 10-08-2019
a
Design & Development
work (Included GFC,
Tender award of work)
18 06-08-2014 06-02-2016
Master Plan Development 15 06-08-2014 06-11-2015
Floor Development 15 06-08-2014 06-11-2015
Services (B/ wall, gate,
guard room, Road PH,
Electrical, STP, UG/ OHT)
15 10-11-2014 06-02-2016
b Environmental approvals 6 18-10-2014 19-04-2015
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 26.
c Construction Phase of
Project 36 06-02-216 08-02-2019
d Handing over of Projects 6 08-02-2019 10-08-2019
2.17 PROJECT COST
The total project cost including the land cost and construction cost is given in Table 2.12.
Table 2:12 Project Cost
Independent Floors Land Cost
(In crores)
Construction Cost
(In crores)
Total
(In crores)
(Residentail Floors ) 24.16 213.01 237.17
2.18 COMPATIBILITY WITH LOCAL REGULATIONS
The project has been design considering all EHS legislation, statutory and regulatory requirements as
detailed in Chapter 3 – Legal & Administrative Framework.
2.19 SOCIAL ACTIVITIES IN THE PROJECT
The following social activities are proposed to be undertaken:
1. Empowerment of Communities, inclusive of Socio-Economic growth
a. Skill development/vocational training (For Men & Women)
2. Community Healthcare
a. General Health camps
b. Specialised Health camps
c. Specialised Medical treatment (Indoor treatment)
d. Health Awareness camps (HIV/AIDS, General Health etc.)
3. Other activities
a. Promotion of Art & Culture
b. Promotion of local Sports & Games
c. Awareness Programs (In-house & External).
The expenditure on the above mentioned CSR activities will be carried out in accordance to the
Companies Act, 2013.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 27.
2.20 OTHER RELEVANT INFORMATION
M/s Commander Realtors Pvt. Ltd. proposes to incorporate features of green buildings to the
maximum extent possible.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 28.
3 LEGAL & ADMINISTRATIVE FRAMEWORK
The 1972 United Nations (UN) Conference on Human Development at Stockholm influenced the need
for a well-developed legal mechanism to conserve resources, protect the environment and ensure the
health and well being of the people in India. Over the years, the Government of India has framed several
policies and promulgated number of Acts, Rules and Notifications aimed at management and protection
of the environment. As a result, our country now has a fairly comprehensive set of environmental
legislation aimed at ensuring that the development process meets the overall objective of promoting
sustainability in the long run.
Moreover, the Indian Constitution has also incorporated specific articles to address environmental
concerns through the 42nd Constitutional Amendment of 1976. As stated in the Constitution of India, it
is the duty of the state (Article 48 A) to ‘protect and improve the environment and to safeguard the
forests and wildlife of the country’. It imposes a duty on every citizen (Article 51 A) ‘to protect and
improve the natural environment including forests, lakes, rivers and wildlife’. Reference to the
environment has also been made in the Directive Principles of State Policy as well as the Fundamental
Rights.
3.1 ENVIRONMENTAL POLICIES
Several environment policy statements have been formulated in the last few decades as a part of the
Government’s approach to integrate environmental and developmental aspects of planning. The policies
reflect a gradual shift in emphasis from pollution abatement and control to proactive and voluntary
approaches for pollution prevention in keeping with global paradigm shifts and trends in environment
management.
Following are some of the key policies that have been laid down by the Central Government:
National Forest Policy, 1988;
National Conservation Strategy and Policy Statement on Environment and Development, 1992;
Policy Statement on Abatement of Pollution, 1992.
National Environmental policy, 2006
Despite these policy documents, a need for a comprehensive policy statement had been evident for some
time in order to infuse a common approach to the various sectoral and cross-sectoral, approaches to
environmental management. As a result, a National Environment Policy (NEP, 2006) has been drawn up
as a response to our national commitment to a clean environment, mandated in the Constitution in
Articles 48 A and 51 A (g), strengthened by judicial interpretation of Article 21. The policy is still in
draft form and addresses environmental concerns in all-developmental activities.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 29.
3.2 LEGAL PROVISIONS FOR ENVIRONMENT RELATED TO BUILDING /
CONSTRUCTION / AREA DEVELOPMENT & TOWNSHIP PROJECTS
The proposed project is governed by various Acts, Rules and Regulations set by Ministry of
Environment and Forests (MoEF) at the Central level and other regulatory agencies at the State and local
level. Various environmental standards, specifications and guidelines of Central Pollution Control Board
(CPCB) and State level agencies will also be applicable.
It is important to note that the Central government framed an ‘umbrella legislation’, called the
Environment (Protection) Act, 1986 to broadly encompass and regulate an array of environmental
issues. The overall purpose of EPA is to establish an overall coherent policy and provide a basis for the
coordinated work of various government agencies with operational responsibility for the environment
and natural resources. This legislation also invests authorities with regulatory powers to address specific
issues affecting the environment. The Act does not allow any person to establish an industry, operation
or process that discharges or emits any environmental pollutants in excess of standards prescribed under
specific rules and notifications.
The Acts, Rules and Notifications applicable to environmental aspects of the construction and
operational phase of proposed project is summarized in Table 3.1 and briefly described in the following
sections.
Table 3:1 Summary of Environmental Legislation concerning Proposed Project
Legislation Areas / Activities Covered
Environment (Protection) Act,
1986 with Rules.
Overall Environment Protection
Compliance to environmental (Air, Water, Noise) Standards issued
under EPR
EIA Notification, 2006 in
supersession of 1994
notification
Building Construction Projects
Filling up of Form I and Form 1A for projects with ≥20000 sq.m
and <1,50,000 sq.m. of built-up area for construction projects.
Township and Area Development Projects
Submission of REIA Reports for township and area development
projects with area ≥ 50 ha and or built up area ≥1,50,000 sq .m
Air (Prevention and Control of
Pollution) Act, 1981 with Rules.
Protection of Air Quality
Consent to Establish (NOC) for establishing and Consent to
Operate (CTO) for activities causing air pollution from DG sets
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 30.
Legislation Areas / Activities Covered
from SPCB
Compliance to National Ambient Air Quality Standard
Water (Prevention and Control
of Pollution) Act, 1974 with
Rules.
Protection of Water Quality
Discharge of sewage from the site
Obtaining Consent to Establish (NOC) for establishing and Consent
to Operate (CTO) for activities causing water pollution from SPCB
Water Cess Act, 1977 Paying Water Cess to Local Body for sourcing of domestic water
Noise Pollution (Regulation and
Control) Rules, 2000
Compliance with Ambient Noise Standards in accordance to land
use of the area
Hazardous Waste
(Management, Handling and
Transboundary Movement)
Rules, 2008
Obtaining Authorization from SPCB for handling and storing of
hazardous waste like waste oil and lubricants. Following guidance
for handling and storing of such hazardous waste
Manufacture, Storage and
Import of Hazardous Chemicals
Rules, 2000 (as amended)
Notifying regulatory authority (in this case, the State Factories
Inspectorate) of storage of hazardous substances like LPG
Follow guidance on such storage, maintain updated MSDS, submit
annual Safety Report to authority
Prepare Onsite Emergency Plan
Motor Vehicles Act with Rules Lay down restrictions for vehicles not having Pollution Under
Control Certificate (PUCC) or proper labeling to enter premises
Petroleum Act with Rules 2000 Comply with guidance and safety measures for storage, and
transportation of petroleum substances within project area premises
Municipal Solid Waste Rules,
2000
Management (Collection, Handling, Intermediate Storage) of
domestic waste from residences
Bio-Medical Waste
(Management and Handling)
Amendment Rules, 2000
Management (Collection, Handling, Intermediate Storage) of
medical waste from Health Services
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 31.
Legislation Areas / Activities Covered
State Town Planning Acts
Obtain permits and sanction for land
Develop Independent Floors in accordance with Land use and
Master plans
State Groundwater Regulation
Conform to restriction for drawing of groundwater
Arrange for recharge through Rainwater Harvesting Schemes (as
applicable)
CGWA Notification
Public Notice No. 1 of 2011
dated 13th August,
Declared “Gurgaon District” as notified area in term of Ground
water Usage
Required prior permission from CGWA for extraction of ground
water
Siting Guidance Follow Siting Guidance as far as practicable
Avoid sites which are environmentally sensitive
3.3 SITING OF PROJECTS
The siting of developmental projects in India is managed by Siting Guidelines for activities and projects
delineated by the MoEF and the CPCB. The overall purpose of the guideline is to aid proponents in
judiciously selecting project sites, keeping in mind various environmental sensitivities. However, the
guidelines for siting are not legally enforceable except for areas which are ecologically fragile (as
notified by certain specific notifications). Additionally, State Governments sometimes formulate State
wide siting guidelines for development planning.
3.4 ENVIRONMENTAL CLEARANCE OF DEVELOPMENTAL PROJECTS
The requirement involved in the setting up of select development projects (projects with potential to
cause significant environmental impacts) in India is through the Environmental Clearance (EC) Process
affected on the basis of an Environmental Impact Assessment study/filling up of necessary forms. The
EC process is mandated by the EIA notification dated September 14, 2006 and is administered by the
State level regulatory and government bodies (as the State Pollution Control Board and the Environment
Departments) and the Ministry of Environment and Forests (until formation of committee as mandated
by EIA notification of September 14, 2006) at the Central Government level.
The following projects or activities shall require prior environmental clearance from the concerned
regulatory authority, which shall hereinafter referred to be as the Central Government in the Ministry of
Environment and Forests for matters falling under Category ‘A’ in the Schedule and at State level the
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 32.
State Environment Impact Assessment Authority (SEIAA) for matters falling under Category ‘B’ in the
said Schedule, before any construction work, or preparation of land by the project management except
for securing the land, is started on the project or activity:
1. All new projects or activities listed in the Schedule to this notification
2. Expansion and modernization of existing projects or activities listed in the Schedule to this
notification with addition of capacity beyond the limits specified for the concerned sector, that
is, projects or activities which cross the threshold limits given in the Schedule, after expansion
or modernization
3. Any change in product - mix in an existing manufacturing unit included in Schedule beyond the
specified range.
Building /Construction projects/Area Development projects and Townships projects have been
categorized under Item 8 of the Schedule.
8 (a) Any building and construction projects with area 20000 sq.mtrs and <1,50,000 sq.mtrs. of
built-up area would require filling up of Form I and Form IA.
8 (b) Any Townships and Area Development projects Covering an area ≥ 50 ha and or built up
area ≥1, 50,000 sq .mtrs would require Environmental Impact Assessment (EIA) study apart
from Form I and Form IA.
The Consent to Establish (also termed as the No Objection Certificate or NOC) under the Air and Water
Acts would be an independent work.
3.5 URBAN PLANNING & LAND USE
Planned urban development is encouraged by successive Five Year Plans and State Governments that
have promulgated Urban Town Planning Acts to provide for proper land use zoning for residential,
commercial and industrial areas, control on slums and urban sprawl, design and development of civic
amenities (such as sewerage and waste disposal) and development of Master Plans for important urban
areas in their respective States. The provisions of the Acts generally regulate the following principal
issues related to urban development:
Declaration of Planning Areas and constitution of Planning and Development Authorities;
Formulation and statutory approval of Land Use and Development Control Plan;
Manage the development of land according to Land Use and Development Control Plans;
Power to acquire land for urban development under the Land Acquisition Act, 1894;
Levy penalty for unauthorized development in nonconformity with plans.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 33.
The proposed project is located in Gurgaon and must conform to provisions of the State level Acts and
local bylaws.
Additionally, the Constitution has recently empowered Urban Local Bodies (Municipalities and
Corporations) through the 73rd
Amendment of the Constitution to play a crucial role in development and
maintenance of environment related infrastructure.
3.6 USAGE OF WATER & WATER POLLUTION
The use of water resources and the discharge of polluted water (sewerage) are primarily regulated by the
Water Cess Act, 1977 and the Water (Prevention and Control of Pollution) Act, 1974.
The Water (Prevention and Control of Pollution), Cess Act, 1977 including Rules 1978 and 1991
provides for levy and collection of Cess on water consumed by the local authorities and by persons
carrying on certain industries with a view to generate resources for prevention and control of water
pollution. It also covers specifications on affixing of meters, furnishing of returns, assessment of Cess,
interest payable for delay in payment of Cess and penalties for non-payment of Cess within the specified
time. The project will fall under the Act only if they source water from water supply schemes of urban
municipalities and corporations and these bodies levy such cess as some form of water tax to the
proposed project.
The Water (Prevention and Control of Pollution), Act, 1974 including Rules, 1975 (as amended up to
1988) provides for the prevention and control of water pollution and maintaining or restoring good water
quality for any establishment. The Act assigns functions and powers to the CPCB and SPCBs for
prevention and control of water pollution and all related matters.
The Environment (Protection) Rules under the EPA also lays down specific standards for quality of
water effluents to be discharged into different type of water bodies (sewers, surface water bodies like
lakes and rivers, marine discharge). The standards are presented in Annexure 3.1. Additionally, the
potable water supplied to occupants of Independent Floors should also conform to the National Drinking
Water Standard IS: 10500 (Refer Annexure 3.2).
Of late, with rapid depletion of groundwater resources in several areas of the country, efforts have been
initiated to regulate the use of groundwater resources. The focus of such acts and rules (many are which
are still in draft form) is to provide for mechanisms that would lead to replenishment of groundwater
reserves through techniques like ground water recharging.
3.7 AIR QUALITY
The Air (Prevention and Control of Pollution) Act, 1981 including Rules 1982 and 1983 was enacted to
prevent, control and reduce air and noise pollution. According to Section 21 of the Act, no person shall
establish or operate any activity, which can cause air pollution without obtaining Consent to Establish
(CTE) as per the Air Act.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 34.
The Act also lays down national ambient air quality standards for common pollutants like PM2.5, PM10,
Sulphur dioxide (SO2), Oxides of Nitrogen (NOx), Carbon monoxide (CO) and Lead (Pb) with the intent
of managing air quality for different category of areas (residential, industrial and sensitive). The EPR
also specifies source emission standards determined on the basis of the impact of pollutants on human
health, vegetation and property for activities, which can pollute the air. The project would not contribute
much to air pollution; the relevant standards are presented in Annexure 3.3. The SPCBs, on a case to
basis, can also make the emission standards more stringent on the considerations of the carrying capacity
of a specific air shed and the existing pollution levels of ambient air quality.
It may be noted that normally the CTE for the Air and Water Act is provided in the form of a No
Objection Certificate (NOC) to the project proponent when the project falls under the 32 categories of
activities covered by the EIA notification. The NOC is generally provided after the submission of the
EIA report.
3.8 NOISE LEVEL
With the objective of regulating ambient noise level in the environment, the Central Government has
notified the Noise Pollution (Regulation and Control) Rules, dated 26th December 1989 and amended in
February 14, 2000 under the EPA. The noise standards for different category of areas is based on the
“A” weighted equivalent noise level (Leq) are as presented in Annexure 3.4. Noise standards in the work
environment (would be relevant for construction phase of the project) are specified by Occupational
Safety and Health Administration (OSHA, USA), which in turn are being enforced by Government of
India through model rules framed under the Factories Act and Rules. The standards are presented in
Appendix - IV. The EPR also lays down equipment specific noise emission standards for Air
conditioners and Construction Equipment, which would be in use for the proposed project. Specific
standards for control of noise from traffic and other sources and measures to be taken for reduction of
noise by using acoustic treatment, exhaust muffler have also been specified through the Environment
(Protection) Second Amendment Rules, 2002 notified through notification GSR 371 (E) on 17th May,
2002.
3.9 SOLID AND HAZARDOUS WASTE MANAGEMENT
A monitoring committee (see section 7), would be responsible for collection and handling of domestic
solid waste to an approved waste disposal site as per the provisions of the Municipal Solid Waste Rules,
2000. The following provisions would apply to the project:
Organize collection of municipal solid wastes through any of the methods, like community bin
collection (central bin), building to building collection, collection on regular pre-informed
timings and scheduling.
Ensure that bio-medical and other hazardous wastes are not mixed with municipal solid wastes
and that such wastes follow the rules (the Bio-Medical Waste (Management and Handling)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 35.
Amendment Rules, 2000 and the Hazardous Waste (Management and Handling) Rules, 2003)
separately specified for the purpose;
Separately collect and dispose horticultural, construction and demolition waste in accordance
with local legislation, bylaws or directives issued by the authorities concerned.
Organize awareness programmes in cooperation with the municipality for segregation of wastes,
promote recycling/ reuse of segregated materials and encourage community participation in
waste segregation.
Establish storage facilities by taking into account quantities of waste generation in the
complexes and locate them in such a way that it is accessible to the residents.
Ensure that such storage facilities are aesthetically acceptable and user-friendly and designed in
a way that wastes stored are not exposed. The storage facilities or ‘bins’ should also be of ‘easy
to operate’ design for handling, transfer and transportation of waste. Bins for storage of
biodegradable wastes shall be painted green, those for storage of recyclable wastes shall be
printed white and those for storage of other wastes shall be printed black.
Manual handling of waste shall be prohibited. If unavoidable due to constraints, manual
handling shall be carried out under proper precaution with due care for safety of workers
The Hazardous Waste (Management and Handling) Rules, 2000 require facilities to classify wastes into
categories, manage them as per the prescribed guidelines and obtain prior authorization from the SPCB
for handling, treatment, storage and disposal of Hazardous Wastes. The project has the potential to
generate hazardous waste during its construction and operational phases and such waste generation
should be properly monitored and managed. The following kinds of hazardous waste may be generated
from the construction phase of the project:
Spent oil and lubricants from construction equipments;
Paint residues during the painting of the buildings;
Asbestos Contaminated Material (ACM) generated from dismantling of temporary housing for
construction workers.
3.10 STORAGE AND USE OF PETROLEUM AND HAZARDOUS CHEMICALS
The project will be storing certain hazardous substances within their premises and would have to
conform to the provisions of Manufacture, Storage and Import of Hazardous Chemicals Rules, 2000 and
the Petroleum Act with Rules 2000.
The storage of Liquid Petroleum Gas (LPG) in bulk for supply of cooking gas to the residents/occupants
would require the project to conform to the following requirements:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 36.
Take necessary precautions to prevent major accidents and limit their consequences to humans
and the environment;
Provide information, training and necessary safety equipments to persons working at the storage
site;
Bring major accidents involving fire or explosion linked LPG as the potential cause of
substantial loss of life and property or adverse impact on the environment to the notice of
concerned authorities (as identified in Schedule 5);
Furnish a annual Safety Audit report to the concerned authority in the pro-forma given in
Schedule 6 of the Rules;
Prepare and maintain Material Safety Data Sheets in accordance to the pro-forma given in
Schedule 9 of the Rules; and
Prepare an On-Site Emergency Plan as indicated in Schedule 11 of the Rules.
The Petroleum Rules also lay down safeguards and measures for storing of different classes of
petroleum, which will be applicable to the Service Station operating from within the premises of the site.
3.11 CENTRAL GROUND WATER AUTHORITY (CGWA) NOTIFICATION
The Central Government constituted the Central Ground Water Authority vide notification of the
Government of India in the Ministry of Environment and Forests vide Number S.O. 38 (E) dated the
14th January, 1997, as amended from time to time, for the purposes of regulation and control of ground
water development and management in the whole of India. The Authority in exercise of its powers and
performance of its functions under section 5 of the Environment (Protection) Act, 1986 (No. 29 of 1986)
is empowered to issue directions in writing to any person, officer or any Authority and such person,
officer or authority shall be bound to comply with such directions.
Accordingly, the authority based on the ground water resource assessment undertaken by Central
Ground Water Board in consultation with the State Government vide Public Notice No. 1 of 2011
published on 13th August, declared "Gurgaon district" as "notified area” for regulation of ground water
abstraction/ development , where ground water withdrawal is more than the average annual
replenishment of ground water resources and the ground water levels are also declining on long term
basis.
Now, therefore, in exercise of the powers conferred under section 5 and clauses (xii) and (xiv) of sub-
section (2) of section 3 of the Environment (Protection), 1986 read with paragraph 2 of the notification
of the Government of India in the Ministry of Environment and Forest number S.O. 38 (E) dated 14th
January, 1997, the Authority with a view to protect and preserve the ground water resources hereby
declare the entire Gurgaon district of Haryana state as “Notified area” and issues the following
directions, which are listed as below:-
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 37.
Restrictions in the area are imposed on construction and installation of any new structure for
extraction of ground water resources without prior specific approval of the Authorized Officer
(Deputy Commissioner) in the Gurgaon district and subject to the guidelines /safeguards
envisaged from time to time in this connection by Authority for ground water extraction and
rain water harvesting / recharge etc.
The authorized officer (Deputy Commissioner, Gurgaon) shall ensure that no new ground water
abstraction structure is constructed / installed in Gurgaon district, Haryana after the publication
of this Public Notice.
3.12 STATUTORY NATIONAL CAPITAL REGION (NCR) REGIONAL PLAN-2021
NCR Planning Board prepared a Regional Plan with the perspective year 2021 for the National
Capital Region which was notified on 17.09.2005. The Regional Plan-2021 for NCR provides a
model for sustainable development of urban and rural settlements to improve quality of life as well as
a rational regional land use pattern to protect and preserve good agricultural land, environmentally
sensitive areas and utilize unproductive land for urban areas through an inter-related policy
framework relating to settlement systems, economic activities, transportation, telecommunication,
regional land use, infrastructural facilities such as power and water, social infrastructure, environment,
disaster management, heritage and tourism.
Regional Plan-2021 for NCR has shown a great concern on various depleting natural resources like
land, water, forest, biodiversity both in sense of flora & fauna of the rapidly urbanizing NCR. Seeing
the present fast pace of growth and urbanization as well as change in approach in economic
development, like proposed Independent Floors, at present land is facing a threat of not only by way
of haphazard unplanned development, unauthorized construction, encroachments by shabby slums &
shanty areas but also unbalanced development with focus of development at the core of the Region.
In order to protect the land from conversion of good agricultural land into non-agricultural uses at
random and balanced development of the region there is a dire need of early preparation of various
plans at different level for both urban settlements as well as rural settlements following policies laid
down in the Regional Plan-2021 for NCR and with a focus to have a rural-urban continuum.
Further, to have balanced development of the NCR, it is also required that various
proposals/strategies/projects to provide the essential services/core infrastructure like shelter, water,
sewerage, sewage treatment, solid waste management, drainage, power, transport, etc. be also
implemented in a time bound manner by the constituent State Governments, Central Ministries and
their concerned Departments/Agencies. Further new approaches and innovative techniques are
required to be adopted by the concerned Agencies to improve & enhance the availability of water &
power. The ground water recharging and water harvesting are required to be integrated in the
building byelaws and amendments are also required to be carried out in various Town Planning Acts
by the Constituent State Governments for conserving the water recharging areas.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 38.
3.13 OPERATION OF MOTOR VEHICLES
The Central Motor Vehicle Act (MVA) and Rules, 1989 (MVR) prescribe that vehicles falling in the
category of transport vehicles (buses, trucks, taxis and auto rickshaws) undergo an annual fitness
certification. The motor vehicle inspectors attached to the State Transport Department generally carry
out this function. Additionally, vehicle owners also have to obtain Pollution under Check Certificate
(PUCC) from a recognized testing center and display it on their vehicles. Additionally, to address the
problem of risk associated with transportation of hazardous substances by road and the consequences of
transportation emergencies, should they arise, provisions have been laid down in the MVR.
Accordingly, any road carriage involved with the transportation of hazardous goods which can be
harmful to human life or which can possibly cause damage to the environment in case of accidents and
spillage shall have to comply with the labeling requirements and safety guidance specified in the MVR.
3.14 INSTITUTIONAL FRAMEWORK
Whereas the legislative branch of the government (Parliament) is responsible for the enactment of
environmental law and the judiciary for its enforcement in the case of transgression, it is the function of
the executive branch (ministries, regional and local authorities) to determine policies and administer
environmental law in actual practice. Also, since an environmental dimension has now become a part of
all economic activities, an effective mechanism of coordination and control is the responsibility of the
central environmental agency so that environmental policies can be translated into action.
The Government of India took a major step in 1972 when it constituted the National Committee on
Environmental Planning and Coordination (NCEPC). Later in 1980, the Government of India
established a new Department of Environment on the recommendation of a committee constituted by the
Indian Parliament. The Central and State Pollution Control Boards were set up and entrusted with the
task of air and water pollution control in 1974.
3.14.1 Ministry of Environment & Forests
In view of the growing importance of environmental affairs, the Government of India set up a
Department of Environment in November 1980 under the portfolio of the Prime Minister. The
Department, later renamed as the Ministry of Environment and Forests (MoEF) plays a pivotal role in
environmental management for sustained development and for all environmental matters in the country.
The major responsibilities of MoEF include:
Environmental resource conservation and protection, including environmental impact
assessment of developmental projects;
Co-ordination with the other ministries and agencies, voluntary organizations and professional
bodies on environmental action plans;
Policy-planning;
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 39.
Promotion of research and development, manpower planning and training and creation of
environmental awareness;
Liaison and coordination with international agencies involved in environmental matters.
Developmental project proponents are also required to submit Environmental Impact
Statements/Assessments to establish that installing adequate pollution control and monitoring equipment
plan preventive measures, and that effluent discharged into the environment will not exceed permissible
levels. The MoEF appraises these statements/assessments and approves the project from the
environmental angle. The respective State Pollution Control Board is to give a No Objection Certificate
(NOC) before the EIA exercise is undertaken.
3.14.2 Central & State Pollution Control Boards
The Central Pollution Control Board is directly responsible for pollution control throughout the national
territory. In addition to the control of air, noise and water pollution it is also responsible for to ensure
effective control on disposal of hazardous wastes and storage and handling of hazardous chemicals and
substances.
Additionally, with the enactment of air and water pollution laws, states have set-up their own Pollution
Control Boards (SPCBs) to monitor industrial emissions and effluents and to approve the operation of
new industries after careful scrutiny. The functions of the SPCBs include:
The planning of comprehensive state programs for the prevention and control of air and water
pollution and to ensure the implementation thereof.
Inspection of control equipment, industrial plants, etc.
Establishing norms in consultation with the Central Board and having regard to national air
quality standards, gaseous emission standards from industrial plants, automobiles, etc. Different
emission standards may be laid down for different industrial plants, having regard to the
quantity and composition of emissions into the atmosphere from such plants and the general
pollution levels in the area;
Advising the State Government on siting of new polluting industry.
3.14.3 Municipalities & the Municipal Corporations
The Constitution (74th) Amendment Act of 1994 accorded constitutional status to the urban local bodies
(ULBs) and recognized the municipal governments as the third tier of governance. While prescribing a
uniform local governance structure that can be applicable across the country, it provides a framework for
elected local governments for their effective functioning to ensure provisions of urban services and
infrastructure. With the objective of bringing about a basic shift from the existing a “top down”
management system to a “bottom up” decentralized and participatory planning approach, the
amendment also provided for constitution of Ward Committees in municipalities with a population of
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 40.
more than 300,000 people, Metropolitan Planning Committees and District Planning Committees for
consolidation and preparation of plans for spatial, social and economic development. The Amendment
Act also provided for devolution of financial powers from the state government for strengthening of
municipal finances.
The 12th Schedule of the 74th Amendment Act lists eighteen functions and responsibilities to be carried
out by the ULBs including public health, sanitation, conservancy and solid waste management related
activities.
3.14.4 Haryana Urban Development Authority (HUDA) Administration
The Haryana Urban Development Authority (HUDA) is a statutory body under Haryana Urban
Development Authority Act, 1977. Haryana Urban Development Authority is a prime agency of the
State Government engaged in the planned development of urban areas in the state. It undertakes
development of land after the same is acquired by the Govt. of Haryana through its Urban Estates
department for specific land uses, like residential, Commercial and Industrial etc. in accordance with
the provisions of the Development Plans of a particular area.
The Development Plans are got prepared and published by the Director Town & Country Planning
Haryana, in exercise of the powers conferred by Sub-Section 7 of section 5 of the Punjab Scheduled
Roads and Controlled Areas (Restriction of Unregulated Development) Act, 1963. After acquisition
of land, a layout plan is prepared on the basis of a plane table survey of the acquired land, and in
accordance with the norms & standards evolved by HUDA for providing a congenial living
environment.
For the purpose of ensuring health and safety of the allottees and for proper aesthetics and a desirable
street picture, Haryana Urban Development Authority( Erection of Buildings) Regulations, 1979
have been framed, which besides other design / Structural requirements, specify the proportion of the
site which may be covered with building, F.A.R., Max. height etc. in the case of different types of
buildings.
The functions of Haryana Urban Development Authority are:-
To promote and secure development of urban areas in a systematic and planned way with the
power to acquire sell and dispose off property, both movable and immovable.
Use this so acquired land for residential, industrial, recreational and commercial purpose.
To make available developed land to Haryana Housing Board and other bodies for providing
houses to economically weaker sections of the society, and
To undertake building works.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 41.
3.14.5 Haryana State Environment Impact Assessment Authority (HSEIAA) / Haryana State
Expert Appraisal Committee (HSEAC)
In exercise of the powers conferred by sub-section (1) and clause (v) of sub-section (2) of section 3 of
the Environment (Protection) Act, 1986, read with clause (d) of sub-rule (3) of rule 5 of the
Environment (Protection) Rules, 1986 and in supersession of the notification number S.O. 60 (E)
dated the 27th January, 1994, except in respect of things done or omitted to be done before such
supersession, the Central Government has directed that on and from the date of its publication the
required construction of new projects or activities or the expansion or modernization of existing
projects or activities listed in the Schedule to this notification entailing capacity addition with change
in process and or technology shall be undertaken in any part of India only after the prior
environmental clearance from the Central Government or as the case may be, by the State Level
Environment Impact Assessment Authority, duly constituted by the Central Government under sub-
section (3) of section 3 of the said Act, in accordance with the procedure specified hereinafter in this
notification.
As per EIA notification the projects or activities falling under category B of the schedule shall require
prior environmental clearance from the State Environment Impact Assessment Authority (SEIAA),
before any construction work, or preparation of land by the project management except for securing
the land, is started on the project or activity.
Accordingly Ministry of environment Govt. of India vide notification NO.S. O. 899 (E). Dated 21-04-
08 constituted State Environment Impact Assessment Authority (SEIAA) for the state of Haryana.
The Authority consists of Chairman, member and Member Secretary. In order to assist the Authority,
State Expert Appraisal Committee has been constituted by Govt. of India for examination of the
project and recommendations to SEIAA. The SEAC is also consisting of Chairman and six members.
3.15 ENERGY CONSERVATION BUILDING CODE (ECBC)
Commercial building sector in India is expanding rapidly at over 9% per year spurred largely by the
strong growth in the services sector. Electricity consumption in the commercial sector in India at
present accounts for about 8% of the total electricity supplied by the Electricity Utilities, and has been
growing annually at about 11-12%. This is mainly attributed to the increasing energy intensiveness of
newly constructed commercial buildings;
Several studies in the country have shown that energy efficiency is not getting adequate attention
when the new buildings are designed. Incorporation of energy efficiency provisions at the design
stage of the new buildings is critical and so will be made mandatory by Ministry of Power by 2012 for
all new buildings.– Better to be proactive than keeping in view the Energy Conservation Act 2001
(EC Act), Bureau of Energy Efficiency (BEE) with technical support from USAID under its Energy
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 42.
Conservation and Commercialization (ECO) Project, has developed Energy Conservation Building
Codes (ECBC) Energy Conservation Building Code (ECBC)
ECBC, considering five climatic zones in India, sets the minimum energy performance standards for
large commercial buildings that have a connected load of 500 kW or greater or a contract demand of
600 kVA or more, having conditioned area of 1000 sq. m. or more.Annual energy consumption in the
conditioned commercial buildings in the country is estimated to be about 200 kWh or more per sq. m
of floor area. Electricity consumption in ECBC compliant buildings can be brought down to 120-160
kWh per sq. m., showing energy saving potential of 20- 40 % depending on the hours of building use
during the day, climatic conditions, etc.
Ministry of Power, Government of India launched ECBC 2007 on 27 May 2007 for its
implementation in commercial buildings on voluntary basis all over India, with a view to make this
mandatory in the next couple of years depending upon the experience gained during the voluntary
period. ECBC encourages energy efficiency for all building components and systems such as building
envelope, lighting, heating ventilation and air conditioning (HVAC), service water heating, and
electric power and motors within the building facilities, while enhancing the thermal and visual
comforts and productivity of the occupants
ECBC mandates/prescribes U-factor and R values of insulation assembly for five climatic zones in
India, Solar Heat Gain Coefficients and Visible Light Transmission levels for fenestration, energy
efficiency levels of air conditioning systems, and number of other parameters for ECBC compliance
in commercial buildings. In this context, good understanding of ECBC features and application of
several developed products and technologies could play an important role in improving energy
efficiency in the buildings, leading to energy cost savings for the building owners/users.
3.16 MANUAL ON NORMS & STANDARDS FOR LARGE CONSTRUCTION PROJECTS
The manual has been development by Ministry of Environment and Forests, GoI to assist the
developers and project proponents measures and and quantify environmental impacts of proposed
construction, and derive mitigation options to minimise impacts. The manual also shall enable
evaluation of construction projects by the expert appraisal committee. The proponent have use
mitigation options, other than the ones described in the manual, to mitigate environmental impacts of
the project. The manual provides a range of environmental issues that had been considered in
assessing the environmental impacts of projects and how to identify and assess the issues pertaining to
the project. The measures are suggestive and intended to assist project specific environmental
management practices. The manual details out the submittals required to fulfil requirements of EC
Application (Form 1 and 1A). This manual also comprises of a list of mandatory and expected criteria
that needs to be adopted in a project for getting necessary clearance from regulatory authority.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 43.
4 BASELINE ENVIRONMENT STATUS
4.1 INTRODUCTION
This chapter describes the existing environmental settings in the study area. In order to identify any
potential impact on and to the natural and socioeconomic environment, it is essential to have a
thorough understanding of the nature of the existing environment prior to commencement of the
proposed activities. This acts as a need to characterize the existing baseline environmental and socio-
economic conditions through primary monitoring, undertaking focused surveys and the collection of
secondary information from various published sources. The major purposes of describing the
environmental settings of the study area are:
To assess the existing environmental quality, as well as the environmental impacts of the future
developments being studied;
To identify environmentally significant factors or geographical areas that could preclude any
future development.
Additional purposes of the baseline studies are to provide sufficient information so that decision
makers alien with the general location can develop an understanding of
The project need
Environmental characteristics of the study area
The following section describes the environmental setting of the site, period, components and
methodology for the baseline studies in detail.
4.2 METHODOLOGY OF CONDUCTING BASELINE STUDY
The guiding factors of the present baseline study are the requirements laid down by the Central
Pollution Control Board (CPCB) and guidelines as per the Environmental Impact Assessment
Notification.
The baseline environmental monitoring has been carried out in winter season of 2014-2015 for a
period of one season (3 month) (3rd
November’2014 – 10th March’2015) and the data have been used
for EIA study. The above mentioned time period has been duly approved by HSEAC during the 116th
ToR appraisal meeting held on 07.02.2015.
For the purpose of the EIA study, the general impact zone for the proposed implementation shall
confine within a radius of 10 km from the center of the project site and specific impact within the
project area.
The studies were conducted by considering the following:
The various environmental attributes were divided into primary and secondary studies. Primary
attributes such as micro-meteorology, air environment, water, soil, noise, traffic, flora and fauna
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 44.
and socio-economic aspects were assessed and on-site monitoring and review of the past studies
conducted; and
Secondary attributes such as land use studies, geology, physiological characteristics have been
assessed by literature review of studies conducted in the past and by various government
publications.
The baseline studies started with reconnaissance survey and site visits in the study area for fixing the
monitoring locations for collecting the primary data. Various Government, Semi-Government
departments were approached for getting information for the secondary data generation.
4.3 CRITERIA FOR BASELINE ENVIRONMENT STUDY
For the purposed of EIA study, the study area has been classified into general study area and core study
area. The general study area extends upto 10 km radius from the site and has been studied for any likely
general impacts. The core area for the proposed implementation shall confined within a radius of 500 m
from the boundary of the project site, since the nature of the project is such that most of the potential
impacts are likely to occur within this area.
Baseline monitoring study has been conducted for one season. The location of the baseline monitoring
has been selected with respect to proposed land-use and environmental susceptibility of the critical
areas. The sampling locations have been selected on the basis of the following factors:
Predominant wind directions recorded secondary scoured –
http://www.windfinder.com/windstats/windstatistic_delhi_indira_gandhi_airport.htm#
Existing topography;
Drainage pattern and location of existing surface water bodies like ponds, tals, nalas;
Location of villages/towns/sensitive areas;
4.4 COMPONENTS AND PARAMETERS FOR BASELINE ENVIRONMENTAL STUDY
The various components studied as a part of the baseline study are discussed in the following sections
components:
Physical Environment
Air Environment
Noise Environment
Water Environment
Land Environment
Ecological Environment
Socio-Economic Environment
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 45.
The different parameters of the above components (as mentioned in the Terms of Reference) are
furnished in Table 4.1.
Table 4:1 Environmental Components & Parameters for Baseline Study
S. No Components Parameters
1 Physical Environment
Land Use Pattern
Landuse within 10 km radius from the project Site
Landuse within project Site
Geography & Topography
General terrain
Relief / Contour, Slope & Terrain of Project Site
Geology
General Geology of the Area
Sub-surface Geology
Geotechnical Investigations at Site
Tectonics Seismo-tectonic & nature of the study area
Cyclones and Storm
Surges
Cyclones and / or storm surges within 10 km Radius from the
project Site
Mineral Resources Mineral resources of the area and the site
Drainage Drainage pattern within 500 m radius of project site
Cropping Pattern Cropping Pattern in the Gurgaon
2 Air Environment
Meteorological Data
Secondary data for climatic aspects collected from nearest IMD
station - temperature, precipitation, wind speed, wind rose,
atmospheric stability and mixing height.
Primary data for climatic aspects collected by onsite meteorological
monitoring conducted for one season for relative pressure,
temperature, precipitation, humidity, wind speed and wind direction
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 46.
S. No Components Parameters
Ambient Air Quality
Ambient air quality monitoring at identified locations
Parameters: PM10, PM2.5, SO2, NOx, Pb and CO
Frequency: 8 hourly sample for PM10, PM2.5 , SO2, NOx, and 1
hourly sample for CO - 2 times a week for 1 month
Location: Five Locations
3 Noise Environment
Ambient Noise Quality
Ambient noise quality monitoring at identified locations (Leq day,
Leq night)
Frequency: Continuous monitoring (24 hourly)
Parameters: Equivalent Noise level in dBA (Leq day & Leq Night)
Location: Five Locations
4 Traffic
Traffic Volume Count Existing Traffic Volume Count at one junction during weekday
Traffic Projection
Population and Trips Generation for Horizon Year 2021
Traffic project using Cube Voyager Software
Traffic scenario within project during operation phase
Hierarchy of road within project site
5 Water Environment
Ground Water Resources
and Availability
Ground water resources in the study area, depth of water table
Hydro-geology within project site
Vertical Electric Soundings (VES) test to know the groundwater
regime in the project site
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 47.
S. No Components Parameters
Surface Water Resources
and Availability
During construction
During operational
Alternate Sustainable Water Management Strategies
Water Quality
Groundwater quality near the project site monitored and compare
with IS 10500 standards
Construction water quality test and compare with IS 456:2000
standards
6 Land Environment
Soil
Study the soil profile of the study area by collecting one grab soil
samples from project site
Soil type & Characteristics
Soil porosity and Permeability
Sub soil permeability
Inherent Fertility
7 Biological Environment
Habitat Assessment Assessment of habitation within the project site
Terrestrial Ecology
Study of flora within 10 km radius and project area
Study of fauna within 10 km radius and project area
8 Socio-economic
Environment
Genral Socio-economic profile
Demographic profile
Economic activity and livelihood pattern
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 48.
S. No Components Parameters
Existing Physical & Social Infrastructure Facilities in the Region
4.5 PHYSICAL ENVIRONMENT
4.5.1 Land Use Pattern
The objectives of land use studies are
To determine the existing land use pattern in the study area and to assess its compatibility with
the proposed development;
To analyze the impacts on land use in the study area.
The study of land use in the area enables one to know about the present land use practices as well as
to know the type of land that can be used for various development activities envisaged in post project
scenario. It also enables to envisage the scenario emerging due to the increase in demand for land with
increase in population and the impacts arising due to the interface with the various project activities.
4.5.1.1 Landuse pattern within Project Site
A study of the land use pattern of the project site reveals that the proposed project site is very sparsely
vegetated land with very small bushes. There are no habitations, forests and crops within the project
site.
4.5.2 Geography & Topography
4.5.2.1 General Terrain
The present Gurgaon district comprise of blocks Tauru, Nuh, Pataudi, Nagina, Punhana, F.P.Jhirka,
Sohna, Gurgaon & Farrukhnagar. It is the southern-most district of Haryana. On its north, it is bounded
by the district of Rohtak and the Union Territory of Delhi.Faridabad district lies to its east. On its south,
the district shares boundaries with the states of Uttar Pradesh and Rajasthan. To its west, lie the district
of Rewari and the State of Rajasthan. The overall topography of the project site is marked by alluvial
plains and at some places by undulating dunes. The average plain elevation of the district is about 215-
220 meters above mean sea level.
4.5.2.2 Relief / Contour, Slope & Terrain of Project Site
From the contour map (Refer Figure 4.1), it has been observed that the site has moderate topography
with slight variation of highest and lowest point. The existing ground levels (EGL) at the time of the
topographical survey varies from RL 237.5 (lowest) to 244 m (highest). The site slopes slightly from
east towards west.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 49.
Figure 4.1 Contour Plan of the Project Site
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 50.
4.5.3 Geology
4.5.3.1 Geology of the Area
The Delhi Supergroup is exposed in the Aravalli Mountains of Rajasthan. These mountains extend from Delhi to south west direction through Haryana and
Rajasthan up to Gujarat. The succession of Delhi Supergroup is composed mainly of quartzites, conglomerates, grits, slates and Phyllites.
The succession of Delhi Supergroup has been divided into two parts. The Lower part, which is predominantly arenaceous, is called the “Alwar Group” and the
Upper part which is mainly argillaceous is called the “Ajabgarh Group”. In Alwar area, there is a succession of calcareous group rok bed in between Alwar and
Ajabgarh groups.
The succession of the Delhi Supergroup is given below given in Table 4.2.
Table 4:2 Geological Sequence of the Area
Group Lithology
Ajabgarh Group Phyllites and slates with calc-gneisses and calc-schists
Alwar Group Quartzites, grits and conglomerates
----------------------------Unconformity-----------------------
Raialo Group of banded gneissic complex
The proposed project site falls in Alwar Group. The rocks of the Alwar Group are distributed though unevenly, throughout the Northern parts of the Aravalli
range.
The Alwar succession, estimated to be more than 3 km in thickness, is almost entirely made up of compact quartzites, conglomerates, grits and slates. The
succession contains several sill like bodies of epidiorites showing both the intrusive and extrusive character.
4.5.3.2 Geotechnical Investigations at Site
Geo technical study has been carried out to investigate the stratigraphy at the site and to develop engineering recommendations for foundation design and
construction.
To accomplish these purposes, the study was conducted in the following phases:
Drilling a total of four (4) boreholes to 15 m depth or refusal, whichever is earlier; in order to evaluate the stratigraphy at the site, and to collect
samples for laboratory testing;
Testing selecting soil and groundwater samples in the laboratory to determine their pertinent index and engineering propertiesof the soils; and
Analyzing all field and laboratory data in order to develop recommendations for design and construction of foundations.
A layout plan showing the locations of our field investigation points is illustrated in Figure 4.2
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 51.
Figure 4.2 Locations of Field Investigations points at Project Site
Results of Geo-Technical Investigation
As per the results of geo-technical investigation carried out at site, following findings were obtained
1. Site Stratigraphy: The surficial soils at the site primarily consist of alternating layers of sandy silt and silty fine sand to the maximum explored depth. The
site generally consist of Medium dense brown silty fine sand with traces of gravel to about 6.0m depth, below this Dense to very dense brown sandy silt, low
plastic to about 11.0m depth, below this Very dense brown silty fine sand with traces of gravel is encountered to about 15.45m. There is a variation in the
depth and thickness of the various strata across the site.
2. Ground Water: Ground water was encountered at about 14.7m depth at the time of field investigation. Fluctuations may occur in measured water levels due
to seasonal variations in rainfall and surface evaporation rates.
3. Liquefaction Susceptibility Assessment: Liquefaction is not likely to take place at the site in the event of an earthquake.
The detailed site stratigraphy and engineering recommnadations for foundation at proposed project have been presented in geotechnical investigation report
which has already been submitted along Form 1.
4.5.4 Seismo-Tectonic & Nature of Study
The proposed site falls in Zone IV, as per seismic zoning map of India and hence is susceptible to earthquakes. The seismological map of the project site is
shown in Figure 4.3. The history of earthquake in the NCR region for last 30 years is shown in Table 4.3.
Seismicity of the proposed site will be taken into consideration during designing of the structural components of the development in the construction phase. The
depth of the foundation, footing of the structural components, the bending moment calculations shall adhere to the criteria of seismic load. Necessary seismic
factors, suggested by Indian Meteorology Department (IMD IS1893-Part I, 2002) shall be incorporated suitably, while designing the structures to safeguard
against earthquake risks.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 52.
Figure 4.3 Seismological map locating project site
Table 4:3 History of Earth Quake in NCR Region from April 1980 to March 2013
Dates
Location
Magnitude
Latitude (°N) Longitude (°E)
21 May 2014 - - 5.6
12 Nov 2013 - - 3.1
16 April 2013 28.87 95.12 5.3
30 April 2013 J & K – HP Border 4.1
1 May 2013 J & K – HP Border 5.8
5-Mar-12 28.808 76.772 4.9
7-Sep-12 28.38 77.12 4.2
16-Nov-94 28.5 76.95 2.9
15-Oct-94 28.59 79.92 2.8
28-Jul-94 28.51 77.25 2.8
3-Dec-93 28.6 77.4 3.5
6-Aug-93 28.64 77.14 2.5
27-Mar-93 28.63 77.2 3.6
16-Feb-93 28.63 76.35 2.6
6-Jun-92 28.65 76.69 2.8
27-Aug-90 76.35 28.58 4.0
15-May-90 76.43 29.12 4.1
27-April-80 77.38 28.37 4.7
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 53.
4.5.5 Cyclones and Storm Surges
As per the records collected from IMD, no cyclones and / or storm surges have been recorded during the last 25 years in the region.
4.5.6 Mineral Resources
The mineral resources, available in the district comprise of silica sand, building stone, kallar/reh and and brick clays. The quarries of silica sand are located on
Harchandpur-Badkhal ridge, Bandhwari & Sohna ridge near Kharak. The building stones are quarried at Ghamrauj, Ranyalla Basidpur, Rithath, Sohna & Rojka
whereas the slate is mined around Tigaon and Ghat Shamsabad.
4.5.7 Drainage Pattern
The proposed project site area does not have any drains or streams within 500 m radius of project site; hence the proposed development would not involve any
alteration of the natural drainage system. However, the natural drainage of the area will not be affected as drains/channels will be provided within the proposed
site area. The project will involve construction of paved areas and hence the quantity of runoff will increase due to reduced infiltration. This runoff will be
collected through a well-designed storm water network and will be recharge ground water through rain water harvesting pits. Refer Figure 4.4 showing that no
natural drainage pattern is present in the proposed project site.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 54.
4.6 CROPPING PATTERN
The predominate farming system in Gurgaon district is Agriculture integrated with Animal Husbandry. The major cropping systems under the existing farming
system are bajrawheat, bajra-mustard guar-wheat and guar-mustard. Wheat and Mustard are the main crops in rabi, which occupy 49,833 ha and 21,967 ha,
respectively with an average productivity of 36.80 and 12.40 q/ha. In kharif, bajra is the major crop occupying 32,833 ha with the productivity of 14.25 q/ha.
Table 4:4 Area, production and productivity of Major Crops in Gurgaon
Crop Area (ha) Prod (tons) Productivity (Kg/ha)
Wheat 49833 183592.5 36.8
Musturd 21967 27246.2 12.4
Bajra 32833 46801.6 14.25
Paddy 2100 6484.5 30.88
Source: Deputy Director Agriculture, Gurgaon
4.7 AIR ENVIRONMENT
Assessment of prevailing ambient air quality status in the vicinity of proposed project site is an important part of environmental impact assessment study. The
tropical climatic conditions, especially monsoon winds prevailing in India mainly control the transport and dispersion of air pollutants during different seasons.
According to the Indian climatology, for all practical purposes in air pollution studies, there are three seasons in a year, viz. winter, summer and post-monsoon.
Significant changes are observed in predominant winds and weather conditions during these seasons (seasonal variation) apart from the local topographical
influences, which ultimately control the air pollution impacts.
The baseline studies for air environment covers reconnaissance, identification of specific air pollutants expected to have impacts from the proposed project and
assessing their prevailing levels in ambient air at representative locations within the core study area (500 m) around the project site.
During the construction phase of the project, the following pollutant is anticipated to emitted:
PM10, PM2.5 from all construction activities.
During the operational phase of the project, the following pollutants are anticipated to be emitted:
NOx, PM10, PM2.5 and CO from vehicle exhaust within the project site and on the sector road adjacent to the site
NOx, PM10, PM2.5,, CO and SO2 from diesel generator sets.
Table 4.5 provides potential primary sources and effects of air pollutants during the construction and operational phases of the proposed project.
Table 4:5 Primary Sources & Effects of Air Pollutants due to Proposed Project
Pollutant Source Adverse Effects
Sulphur Dioxide (SO2) Combustion of Sulphur-containing fossil fuels
for
Construction equipment
Vehicles
Diesel generators
Reduced visibility
Irritation of eyes
Aggravation of respiratory diseases (asthma, emphysema)
Nitrogen Oxides (NOx) Combustion of fossil fuels for
Construction equipment
Vehicles
Diesel generators
Aggravation of respiratory illness
Reduced visibility
Formation of acid rain
PM10, PM2.5, Construction activities
Combustion of fossil fuels for construction
equipment, vehicles and diesel generators
Soiling
Reduced visibility
Aggravation of the effects of gaseous pollutants
Increased cough and chest discomfort
Reduced lung function
Aggravation of respiratory and cardio-respiratory diseases
Carbon Monoxide (CO) Combustion of fossil fuels for
Construction equipment
Reduced visibility
Deterioration of metals, textiles, leather, finishes, coatings, etc.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 55.
Pollutant Source Adverse Effects
Vehicles
Diesel generators
Irritation of eyes
Aggravation of respiratory diseases (asthma, emphysema)
Source: South Coast Air Quality Management District (SCAQMD) 1993. CEQA Air Quality Handbook
4.7.1 Meteorological Data from Secondary Sources
Meteorological conditions prevailing at a geographical area play an important role in determining its existing air quality and environmental conditions. Climate,
seasons and other meteorological parameters influence and alter site-specific activities and operations. The meteorological data collected from secondary sources
for the area are presented in the subsequent sections.
4.7.1.1 Temperature
Climatological data is used for devising baseline ambient air quality monitoring plans. Table 4.6 & Table 4.7 presents the minimum and maximum temperature
profile of the region (data collected at MET Station Palam, New Delhi) for the period 1997 to 2011 from Indian Meteorological Department (IMD), Lodhi Road,
New Delhi. As per the data given in Table 4.6 and Table 4.7, the study area experienced averaged extreme lowest temperature 5.9o
C in the month of December,
2005 and extreme highest 42.6o Cin the month of June, 2009 respectively.
Table 4:6 Averaged Minimum Temperature Profile (1997 to 2011) –Met station Palam
DATE JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1997 6.6 9.2 15.2 20.4 24.4 25.9 27.4 25.8 25.2 19 14.2 9.2
1998 7.2 11.2 14.4 22.9 27.9 28.1 27.1 26.4 26.1 21.6 14.9 8.9
1999 8.5 9.6 14.3 20.9 26.8 27.9 27.8 26.9 25.7 19.6 13.1 7.4
2000 7.6 9 14.2 22.5 27.4 27.6 26.2 26.5 24.5 20.2 14 7.1
2001 6.1 9.4 14.8 21.3 26.3 26.4 27.3 26.5 24.8 20.4 12.8 8.5
2002 7 9.6 15.4 23 27.2 28.6 30.7 27.2 23.5 20 13.2 8.9
2003 6.6 11 15.1 22.2 25.7 29.6 26.3 26.5 25 18 11.8 10.1
2004 7.9 9,9 16.3 23.3 26.1 27.1 28.6 26.2 24.9 19.5 13.2 9.3
2005 7.1 10.9 17.3 20.6 25.9 28.4 27.2 26.9 25.1 18.6 12.3 5.9
2006 6.6 13.3 15.5 22.7 26.8 27 28.2 26.8 24.5 20.4 14.2 18.7
2007 6.4 12.3 15.1 22.9 26.3 28.3 27.4 26.9 25.5 17.7 13.6 8.2
2008 6.3 8.3 17.3 21.6 25 26.2 26.9 26.3 24.4 21.2 13.8 10.6
2009 8.8 11 16.5 22.5 27 29 28.2 27.5 25.2 19.7 14.4 9.7
2010 8.5 11.7 18.8 25.7 28.7 28.8 27.5 26.4 24.3 21.3 15.8 8.6
2011 7 11.3 16.3 21.1 27.2 27.3 27.2 26.6 25 20 15.6 8.8
Source: India Meteorological Department (IMD), Regional Meteorological Centre, Lodhi Road, New Delhi - 110003
Table 4:7 Averaged Maximum Temperature Profile (1997 to 2011) –Met station Palam
DATE JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1997 20.3 23.7 28.7 33.7 38.7 37.5 36.1 33.7 35.2 29.1 25.4 17.1
1998 19.6 23.3 27.2 37.1 42.6 39.8 34.7 33.5 33.9 31.4 27.6 22.1
1999 18.6 23.7 31.4 39.6 41.1 39.5 36.3 35.8 34.0 33.3 29.5 23.3
2000 20.2 21.6 29.9 39.2 40.8 37.6 33.6 34.5 34.8 35.2 29.4 24.1
2001 19.1 25.2 30.8 36.3 39.6 35.6 34.9 35.5 37.3 34.7 29.7 23.4
2002 20.4 24.0 31.3 39.6 41.8 39.7 40.5 35.2 32.3 34.0 28.9 24.6
2003 17.0 23.2 30.0 38.3 40.8 41.1 34.1 33.6 32.7 33.1 28.1 20.5
2004 18.4 25.2 33.7 38.8 39.5 38.3 38.5 33.5 35.7 30.9 28.6 22.7
2005 19.5 22.8 30.8 37.1 40.6 40.9 34.2 35.8 33.7 32.8 28.9 22.0
2006 21.8 29.6 29.7 38.1 40.3 38.5 35.2 35.4 34.7 34.0 28.9 22.9
2007 21.5 24.5 28.1 38.8 39.7 38.6 36.2 35.0 34.8 33.8 29.0 22.1
2008 20.0 22.5 33.3 36.9 37.7 34.7 34.8 33.4 33.6 34.1 28.7 23.8
2009 21.1 25.6 31.7 37.4 41.0 42.6 38.0 36.0 34.3 33.7 27.8 23.8
2010 19.2 25.7 34.6 41.5 42.4 41.7 35.7 33.6 31.0 33.1 27.5 22.1
2011 19.2 24.5 30.6 36.3 41.3 38.9 35.4 34.4 33.8 33.5 29.6 23.5
Source: India Meteorological Department (IMD), Regional Meteorological Centre, Lodhi Road, New Delhi - 110003
4.7.1.2 Precipitation
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 56.
Table 4.8 shows averaged monthly rainfall during last fifteen years in Delhi.The maximum mean monthly rainfall for year 2003 is 495.6 mm and occurs during July
while the mean minimum monthly rainfall of 0.0 mm takes place in the month of October, November and December of 2008.
Table 4:8 Rainfall Data for Last Fifteen Years in Delhi (Palam)
DATE JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1997 6.3 1.4 13.4 28.6 43.1 80.3 70.2 295.3 23.9 52.8 15.7 51.4
1998 1 23 16.7 4.4 6.1 107.1 166.6 186.6 131.8 49.4 9.5 0
1999 65.7 2.5 6.3 0 9.3 36.4 143.5 24.5 73.1 8 0 0
2000 17.4 44.7 5.3 2.6 32.7 96.8 232.1 127.7 27.5 0 1.4 1.5
2001 23 11.2 6.5 27.9 88.3 150.2 99 77.1 15.4 29.9 0.5 0.5
2002 16.9 11.1 0 0 150.7 13.1 1.7 121.3 124.2 0 0.9 16.1
2003 39.2 24 2.1 0 9.9 75.2 495.6 171.2 52.3 0 0.3 18.7
2004 28.4 0 0 28.3 73 16.8 65.8 218.6 2.9 76.7 0 0
2005 5 39.7 19.7 7.9 5.6 100.2 295.4 107.5 293.5 0 0 0
2006 1.8 0 25.1 3.4 44.6 53.9 107 103.2 186.9 3.4 0.2 8.2
2007 0.7 63.5 53 1 50.3 148.8 126.3 177.2 9.1 0 0 0.3
2008 0.7 0.3 0 27.3 148.6 153.1 149.5 169.6 76.5 0 0 0
2009 4.1 5.8 7.5 3.1 15.5 18.6 113.6 142.1 184.6 2.8 13.2 3.1
2010 0.7 11.2 0 7.5 12.8 9.2 203 362.3 344 1.3 27.2 3.7
2011 0.2 38.8 2.8 10 22.6 120.4 67.1 144.5 320.6 0 0 0
Source: India Meteorological Department (IMD), Regional Meteorological Centre, Lodhi Road, New Delhi – 110003
Year Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
2009 0.0 1.0 0.0 8.0 1.5 18.0 68.1 96.3 244.1 0.0 24.5 0.0
2010 1.0 11.3 0.0 0.0 0.2 0.8 310.8 302.6 198.5 0.0 15.0 1.0
2011 0.0 4.9 0.3 0.1 10.6 57.6 115.9 159.1 102.6 0.0 0.0 0.0
2012 1.3 0.0 0.0 3.3 1.7 1.5 147.6 249.2 81.4 0.0 0.0 0.0
2013 11.0 53.0 2.5 4.0 0.0 25.7 96.1 173.0 35.7 0.0 0.0 0.0
Source: http://www.imd.gov.in/section/hydro/distrainfall/webrain/haryana/gurgaon.txt
4.7.1.3 Cloud Cover
The historical data of cloud cover have been obtained from the Indian Meteorological Department (IMD). Table 4.9 and Table 4.10 provide the details of cloud
cover data of morning hours and evening hours of Safdarjung, New Delhi.
Table 4:9 Cloud Cover Data for Last Fifteen Years of Delhi (Safdarjung), Morning Hours (8.30 IST)
DATE JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1997 2 1 4 2 2 3 5 5 3 3 3 6
1998 3 3 3 2 1 4 5 6 3 2 1 4
1999 6 3 1 0 2 2 5 4 4 1 0 2
2000 4 2 1 1 1 3 6 4 3 0 1 1
2001 4 1 2 2 3 4 6 4 1 1 0 2
2002 3 2 2 1 3 6 4 4 0 1 1 1
2003 5 2 2 2 1 3 6 4 4 0 1 1
2004 6 2 0 2 1 3 4 5 1 2 1 3
2005 4 3 2 1 2 3 5 3 4 0 0 1
2006 2 2 3 2 2 4 5 4 2 1 0 3
2007 2 3 2 1 2 4 5 5 3 0 0 2
2008 3 2 2 2 3 6 6 5 3 0 0 2
2009 3 2 2 1 2 2 4 4 2 1 - -
2010 5 2 1 1 1 3 5 6 5 0 2 1
2011 5 2 2 1 1 4 6 5 4 0 1 1
Source: India Meteorological Department (IMD), Regional Meteorological Centre, Lodhi Road, New Delhi - 110003
Table 4:10 Cloud Cover Data for Last Fifteen Years of Delhi (Safdarjung), Evening Hours (17.30 IST)
DATE JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
1997 2 2 4 3 3 4 6 5 4 4 4 4
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 57.
1998 3 3 4 3 2 4 5 6 3 2 1 0
1999 4 3 2 0 2 3 5 5 4 1 1 1
2000 2 2 1 1 2 4 6 6 3 0 1 1
2001 1 2 2 - 3 5 6 5 2 1 0 1
2002 2 3 2 3 3 3 4 6 3 0 1 2
2003 3 2 - 1 2 4 6 6 5 0 1 2
2004 2 1 0 2 2 4 6 6 2 2 1 2
2005 3 4 3 2 4 3 6 3 4 0 0 1
2006 3 2 2 2 2 3 6 3 4 0 0 1
2007 3 3 3 1 3 3 6 5 3 0 1 2
2008 4 1 2 2 3 5 6 6 4 1 0 2
2009 6 2 2 2 3 3 5 5 2 1 - -
2010 3 3 1 1 2 3 6 6 5 1 2 2
2011 0 3 1 1 2 3 6 6 5 1 2 2
Source: India Meteorological Department (IMD), Regional Meteorological Centre, Lodhi Road, New Delhi - 110003
4.7.1.4 Wind Speed
Wind direction is reported as the direction from which the wind blows and is based on surface observations. Over the course of a year, wind usually blows in all
directions with varying frequencies. Certain directions, which occur more frequently than others, are known as the prevailing wind directions. Pollutant
concentrations typically decrease with increasing wind speed as a result of dispersion. However, when wind speeds are high, while there is good dispersion of
gases and particles, there is more potential for re-suspending surface dusts. Wind speed near zero, indicating low turbulence and may lead to very high pollutant
concentrations near the ground. Wind speed increases with height as surface friction reduces. Ground level pollutant concentration is inversely proportional to
the wind speed. Hence, during the higher wind speed month, the ground level pollutant concentration would be less and vice.
The wind data has been obtained from nearest IMD station for the period 1993-2002. The Analysis of wind records during 1993 – 2002 shows that the winds are
generally light to moderate in this area. It can be seen that the annual mean wind speed varies from 3.9 to 9.4 Km/h. The strongest winds are observed during the
months of May – June i.e. Summer Season and the weakest during October – November. The monthly mean values of the various meteorological parameters for
the period 1993-2002 and yearwise monthly mean value from year 2000 to 2005 are presented in Table 4.11.
Table 4:11 Monthly Mean Wind Speed in KMPH (Year 1993 – 2005)
Year Jan. Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1993-
2002 6.7 7.2 8.02 7.9 9.4 8.9 7.6 8.0 6.6 3.9 4.2 5.19
2000 7.2 6.7 6.3 7.9 12.3 8.0 7.1 8.0 7.4 3.4 4.3 5.2
2001 7.6 7.7 7.5 8.0 9.5 7.0 8.0 9.8 5.0 0.8 1.9 3.6
2002 3.4 7.0 7.2 7.3 8.5 8.0 14.2 6.8 5.8 3.9 4.3 4.3
2003 5.7 7.3 7.9 8.4 8.5 8.6 6.2 6.2 5.1 4.1 5.4 5.7
2004 6.6 8.9 9.6 8.3 11.8 8.3 10.0 7.1 7.2 3.2 3.6 6.0
2005 6.9 8.0 6.7 8.7 7.2 9.1 7.1 10.8 5.3 4.1 5.6 5.3
Statistics mean monthly wind data for the Year 2009 – 2012 is shown below in Table 4.12.
Table 4:12 Monthly Mean Speed in KMPH (Year 2009 – 2014)
Month of year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec SUM
Dominant Wind dir WNW WNW WNW WNW WNW WNW ESE ESE WNW WNW WNW W WNW
Wind probability
5 9 11 12 11 17 8 6 8 3 2 3 7
> = 4 Beaufort (%)
Average
Wind speed
(Knots)
6 7 8 8 8 9 7 7 7 6 6 6 7
Source – http://www.windfinder.com/windstats/windstatistic_delhi_indira_gandhi_airport.htm#
4.7.1.5 Wind-rose
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 58.
The wind rose diagrams for the Year 1985-2002 at 08.30 Hrs. (Morning) and 17.30 Hrs. (Evening) is given in Figure 4.5 and Figure 4.6 respectively. Figure 4.5
shows that at 8.30 hrs., the predominant wind direction is west and Figure 4.6 shows North west to be the predominant wind direction at 7.30 hrs.
Figure 4.4 Wind Rose Diagrams for 8.30 Hrs. (Morning ) for the Year 1985-2002
Source: Indian Meteorological Data, GoI
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 59.
Figure 4.5 Wind Rose Diagrams for 17.30 Hrs. (Evening) for the Year 1985-2002
Source: Indian Meteorological Data, GoI
4.7.1.6 Wind Rose Diagrams for the Year 2009-2014
The wind rose for the Year 2009 – 2014 for day time is given in Figure 4.7, which shows wind direction during the whole year, the predominant wind direction
during the day time is West North West.
Source: http://www.windfinder.com/windstats/windstatistic_delhi_indira_gandhi_airport.htm#
Figure 4.6 Wind Rose Diagram for Year 2009 – 2014
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 60.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 61.
Source: http://www.windfinder.com/windstats/windstatistic_delhi_indira_gandhi_airport.htm#
4.7.2 Atmospheric Stability
The amount of turbulence in the ambient air has a major effect upon the rise and dispersion of air pollutant plumes. The amount of turbulence can be
categorized into defined increments or "stability classes". The most commonly used categories are the Pasquill stability classes A, B, C, D, E, and F. Class A
denotes the most unstable or most turbulent conditions and Class F denotes the most stable or least turbulent conditions. The frequency of stability classes during
the monitoring period is provided in Table 4.13.
Table 4:13 Stability Class
Stability Class Frequency (%)
A – Extremely Unstable 18.6
B – Unstable 16.3
C – Slightly Unstable 5.8
D – Neutral 6.5
E – Slightly Stable 12.1
F – Stable to Extremely Stable 40.7
The data indicate that during the monitoring period, the site exhibited trends of primarily stable to extremely stable conditions. Stable conditions exhibit poor
vertical mixing, and low levels of contaminant dispersion. Use of this stability data for modeling purposes will produce higher concentrations of pollutants at a
given receptor (i.e. more conservative results).
4.7.3 Mixing Height
Mixing Height (MH) is the vertical extent through which the contaminant plume can be mixed. Forecasting of mixing height is done with the aid of the vertical
temperature profile. The MH is a function of stability. In unstable air, the MH is higher and in stable air the MH is lower. With a lower MH, there is a smaller
volume of air in which the pollutant can be dispersed, resulting in higher concentrations in the ambient environment. There is a seasonal variation of MH.
During summer daylight hours, MH can be few thousand feet whereas for winter it can be a few hundred feet. It varies also in the course of a day. It is lowest at
night and increases during the day. Secondary information has been used to determine the mixing height over Gurgaon district and it varies from 50-2500 meters
(CPCB, 2002)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 62.
4.7.4 Site Specific Meteorological Data
Meteorological information is important for devising baseline ambient air quality monitoring plans and for the prediction of impacts from air quality modeling.
At project site, a meteorological station was installed. Hourly meteorological data was collected for one season. Monitoring was done as per IS: 8829: Micro-
meteorological Techniques in Air Pollution. As per the requirement of Form 1A under the Section 2 (Water Environment) & Section 5 (Air Environment), the
project site specific data was collected with respect to wind speed, direction, temperature, humidity and rainfall for one season.
Table 4.14 provides maximum, minimum and average temperature, rainfall, wind speed, relative pressure and humidity over the seasonal monitoring conducted
at the site for one month during the environmental baseline monitoring period (winter season). The meteorological data monitoring for one month of 2015 (1st
January’2015 – 31st January’2015) is enclosed as Annexure 4.1.
Table 4:14 Meteorological Monitoring Data (Winter Season – 01.01. 2015 to 31.01.2015)
Season Temperature Wind speed Rainfall Relative Pressure Humidity
Maximum 22.2ºC 22.6 kmph 0.0 mm 29.25 in Hg 99 %
Minimum 5.2 ºC 0 kmph 0.0 mm 19.14 in Hg 31 %
Average 12.77 ºC 3.83 kmph 0.0 mm 29.01 in Hg 63.76 %
4.7.4.1 Wind Rose at Site
The wind rose denotes a class of diagrams designed to display the distribution of wind direction experienced at a given location over a period of time - long for a
Climatological record of prevailing winds or short to show wind character for a particular event or purpose. Wind rose summarizes a considerable amount of
wind frequency information into a single graphic during the monitoring period at the proposed site and is shown in Figure 4.8 below:
Figure 4.7 Wind Rose at Project Site
The wind rose diagram reveals that wind was blowing predominantly towards the Northwest (NW) and West (W) direction having speed in the range of 0.5- 3.6
m s-1 during the monitoring period. The onsite average wind speed was observed as 3.83 m s-1 with frequency of calm winds 12.50 % during the monitoring
period. The wind rose diagram shows that during the monitoring period observed predominant wind direction (northwest and west) was almost concurrent with
climatologically prevailing wind direction (northwest and west).
4.7.5 Air Quality
The existing quality of the air environment serves as an index for assessing the pollution load and the assimilative capacity of any region and forms an important
tool for planning project activity in the area. The primary data for air quality was monitored as per the following period and utilized for EIA study:
(i) Baseline monitoring for ambient air quality has been carried out between 3rd
November’2014 – 10th March’2015 for three month continuously (Winter
Season, 2014-2015) as per (1) EIA guidance manual – Building, Construction and Township and Area Development Project (Source MoEF Website –
http://environmentclearance.nic.in/writereaddata/Form-1A/HomeLinks/building-construction_may-10.pdf) and CPCB notification No. B-
29016/20/90/PCI-1. dt. 18.11.2009 on National Ambient Air Quality Standards and the same is enclosed as Annexure 4.2.
4.7.5.1 Methodology for Baseline Meteorology monitoring
The background-monitoring program was carried out as per standard methodologies and accepted protocols as detailed by the MoEF. Air quality was monitored
with 5 numbers high volume samplers, for 24 hours continuously, twice in a week for one season. Each sampler maintained a volumetric flow rate between 1.0-
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 63.
1.2 m3/min. In this manner 24 hourly averaged values for all pollutants were collected at each of the locations. Analysis of pollutants was done as per standard IS
codes.
LOCATIONS OF AAQ MONITORING STATIONS
An assessment of baseline air quality was undertaken to establish the status of exposure of the receptors. This assessment was accomplished by examining
sources of air emissions within the study area and by conducting a site–specific background–sampling program.
The basic considerations for designing air quality surveillance programme within 500 m as per EIA guidance manual (Page no 14) include:
Nature of Project (Building Construction)
Meteorological Conditions
Topography
Selected Pollution Pockets in the Area and Likely impact area
Keeping the historical meteorological conditions, topography, physical features, sensitive locations and current and anticipated pollution loads, in mind and
based on the reconnaissance survey of the project area, a monitoring framework for air quality in the study area (5 km radius) has been drawn up. In this manner,
a total of 5 numbers of monitoring locations have been selected to assess the existing air quality in the area. All the monitoring locations for air, noise, water and
soil are shown in Figure 4.9. Table 4.15 gives the details of air quality monitoring locations. These locations are truly representative of the area.
Background data was collected for PM 2.5, PM10, SO2, NOx and CO as per CPCB guidelines for one season.
Table 4:15 Details of Ambient Air Quality Monitoring Locations
Monitor Description Approximate Distance to centre of site
(km)
Direction
AQ1 Project site - -
AQ2 Near Village Ullawas 0.48 km W
AQ3 Near CGHS Society Sector-58 0.33 km NE
AQ4 Near Village Behrampur 0.87 km E
AQ5 Near Village Ghata 1.95 km NNE
Figure 4.8 Air, Noise, Water and Soil Monitoring Locations
Village Behrampur
AQ4
Sector-58
AQ3
Village Ullawas
AQ2
Village Ghata
AQ5
Project Site (18.138 Acres)
AQ1
RESULTS OF AAQ MONITORING
The revised National Ambient Air Quality Standards (GSR 826(E), 16.11.2009) for PM10, PM2.5, SO2, NOx and CO are presented in Annexure 3.3.
Monitoring results (observed levels and ranges) of these parameters for winter season are presented in Table 4.16 to Table 4.20, and Figure 4.10 to Figure
4.14, where exceedances of NAAQS are highlighted. The table also defines the locations of sampling, their distance from the site and land-use categories. The
air quality monitoring results for winter season (3rd
November’2014 – 10th March’2015) are presented in Annexure 4.3.
a) Monitoring Results SO2: The monitoring results of SO2 are given in Table No. 4.16 and Figure 4.10.
Table 4:16 Monitoring Program Results SO2 (g/m3)
Station Location Name Maximum Minimum Mean NAAQS
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 64.
AQ1 Project site 10.6 6.5 8.55
80
AQ2 Near Village Ullawas 11.6 6.1 8.85
AQ3 Near CGHS Society Sector-58 12.9 6.1 9.5
AQ4 Near Village Behrampur 10.4 6.3 8.35
AQ5 Near Village Ghata 11.1 7.1 9.1
Figure 4.9 Concentration of SO2 (g/m3)
The monitor was placed at all the locations for assessing the concentration of SO2, which is well within the NAAQ standard specified for SO2 with a maximum
value of only 12.9 g / m3 at Near CGHS Society Sector 58. The overall air quality of the area is good.
b) Monitoring Results NOx: The monitoring results of NOx are given in Table No. 4.17 and Figure 4.11.
Table 4:17 Monitoring Program Results – Nox (g/m3)
Station Area Maximum Minimum Mean NAAQS
AQ1 Project site 23.8 13.2 18.5
80
AQ2 Near Village Ullawas 22.1 12.2 17.15
AQ3 Near CGHS Society Sector-58 22.7 13.8 18.25
AQ4 Near Village Behrampur 22.2 13.2 17.7
AQ5 Near Village Ghata 21.9 11.5 16.7
Figure 4.10 Concentration of NOx (g/m3)
The monitor was placed at all the locations for assessing the concentration of NOX, which is well within the NAAQ standard specified for NOX with a maximum
value of only 23.8 g / m3 at Project Site. This is also from the heavy vehicular emissions from traffic plying on the nearby road to the site. However, the overall
air quality of the area is good.
c) Monitoring Results CO: The monitoring results of CO are given in Table No. 4.18 and Figure 4.12.
Table 4:18 Monitoring Program Results – CO (g/m3)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 65.
Station Area Maximu
m
Minimu
m Mean NAAQS
AQ1 Project site 943 727 835
4000
AQ2 Near Village Ullawas 1029 706 867.5
AQ3 Near CGHS Society Sector-58 1087 742 914.5
AQ4 Near Village Behrampur 961 719 840
AQ5 Near Village Ghata 981 767 874
Figure 4.11 Concentration of CO (g/m3)
The ambient air quality monitoring results show that, the CO concentrations at all the locations ranges from 1087 to 943 µgm/m3
approximately, which reveals
that the air quality in terms of CO concentration also show good conditions of ambient air in all nearby locations.
d) Monitoring Results PM10: The monitoring results of PM10 are given in Table No. 4.19 and Figure 4.13.
Table 4:19 Monitoring Program Results – PM10 (g/m3)
Station Area Maximum Minimu
m Mean NAAQS
AQ1 Project site 99.76 75.89 87.825
100
AQ2 Near Village Ullawas 105.61 75.23 90.42
AQ3 Near CGHS Society Sector-58 106.39 78.30 92.345
AQ4 Near Village Behrampur 97.28 65.30 81.29
AQ5 Near Village Ghata 99.17 70.12 84.645
Figure 4.12 Concentration of PM10 (g/m3)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 66.
The monitor was placed at all the locations for assessing the concentration of PM10. Monitored PM10 level is slightly high at locations near Ullawas & Near
CGHS Society Sector 58 with maximum value of 106.39 g / m3. This may be due to construction activity and continuous vehicular movement in surrounding
areas. However, this is only for short duration and will not impact on environment in long term.
e) Monitoring Results PM2.5 : The monitoring results of NOx are given in Table No. 4.20 and Figure 4.14.
Table 4:20 Monitoring Program Results -PM 2.5 (g/m3)
Station Area Maximum Minimum Mean NAAQS
AQ1 Project site 59.62 45.49 52.555
60
AQ2 Near Village Ullawas 62.39 41.45 51.92
AQ3 Near CGHS Society Sector-58 65.47 40.15 52.81
AQ4 Near Village Behrampur 57.33 43.13 50.23
AQ5 Near Village Ghata 59.15 35.95 47.55
Figure 4.13 Concentration of PM 2.5 (g/m3)
The monitor was placed at all the locations for assessing the concentration of PM2.5. Monitored PM2.5 level is slightly high at locations near Ullawas & Near
CGHS Society Sector 58 with maximum value of 65.47 g / m3.
Interpretations
With respect to pollutants, the results of the monitoring program indicated the following:
Observed PM10 and PM2.5 level is slightly higher to the NAAQ standard at the monitored locations Near Ullawas & near CGHS Society Near Sector 58
(probably due to ongoing construction activities and continuous vehicular movement in surrounding environment).
Observed NOx, SO2 and CO levels are well within the specified standards by NAAQ, i.e. 80 g / m3 for NOx and SO2 and 4000 g / m
3 for CO .
The overall observation of the project site and its surrounding area shows that the ambient air quality of the area is fairly good except the concentration level of
PM10 and PM2.5.
4.8 NOISE ENVIRONMENT
Unpleasant sounds are classified as noise pollution. Sound possesses three definite properties: intensity, frequency and duration. Intensity is the loudness of a sound,
or the pressure it exerts through the ear. It is measured in decibels (dB). In assessing noise, an empirical measure called "dB (A)" indicates damage to hearing. The
higher the dB (A) value, the greater is the risk of damage to hearing. Loud noise may adversely affect people in many ways. For example noise may interface with
sleep, speech, communication and can cause annoyance and other physiological problems. Occupational noise exposure, is also the most common cause of Noise-
Induced Hearing Loss (NIHL), threatens the hearing of individuals exposed to noise pollution for longer periods of time, at a less intense level. For example,
repeated exposure to noise pollution at a construction site can cause NIHL to construction workers, an effect that cannot be reversed.
During the construction of the site, the following source of noise pollution is anticipated:
Construction equipment.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 67.
During the operational phase of the site, the following sources of noise pollution are anticipated:
Diesel generator operation.
Increase in transport noise from the adjacent surrounding roads of the site and from within the site.
Table 4.21 provides primary sources and effects of Noise Pollution at site during the construction and operation phases.
Table 4:21 Primary Effects of Noise Pollution from Construction & Operation Activities of the Site
Pollutant Source Primary Effects
Noise Construction activities
Transport
Human activities
Annoyance
Interference with communication
NIHL
Interference with sleep
Aural pain, nausea & reduced muscular control
Performance effects
Effects on social behavior
Source: http://www.epa.nsw.gov.au/soe/97/ch1/15_3.htm
4.8.1 Noise Quality
Unwanted noise and unpleasant sounds are generally classified as noise pollution. Normally a person begins to identify sounds when a level of 10 to 15 dB is
reached. The other end of the scale is known as the threshold of pain (140 dB), or the point at which the average person experiences pain. Noise is generally
measured in frequency-weighted scales and noise quality measurements are generally represent in the ‘A’ level and reported as dB (A).
Methodology of Background Noise Quality Monitoring
A site–specific background noise quality monitoring program was conducted for the existing project site.
The basic considerations for designing noise quality surveillance programme include:
Vehicle Movement Within the Impact Zone
Activities in surrounding villages / settlements/nearby areas
Ecologically Sensitive Locations
Based on the above mentioned criteria, noise monitoring was conducted at 5 locations within the impact zone. Sound Pressure Level (SPL) measurements were
automatically recorded to give the noise level for every hour, continuously for 24 hours in a day. Accordingly one full day (i.e. 24 hourly values) of data was
collected at each of the locations.
The standards of equivalent noise levels viz. Leq-day and Leq-night have been prescribed by the CPCB as given in Table 4.22.
Table 4:22 Ambient Noise Standards as per CPCB
Area Code Category of Area/ Zone
Limits in dB(A) Leq*
Day Time Night Time
(A) Industrial area 75 70
(B) Commercial area 65 55
(C) Residential area 55 45
(D) Silence Zone 50 40
1. Day time shall mean from 6.00 a.m. to 10.00 p.m.
2. Night-time shall mean from 10.00 p.m. to 6.00 a.m.
3. Silence zone is defined as an area comprising not less than 100 m around hospitals, educational institutions and courts. The silence zones are zones, which
are declared as such by the competent authority.
Noise levels were calculated using the following equation:
Where Li = levels observed at n equally spaced times during interval T.
Sources of Noise Emissions Surrounding the Site
The major source of noise in the site surrounding area is the vehicular movement along the 60m wide road and construction activities in the vicinity of the site.
The impacts from these sources are expected to be captured in the levels of noise measured in the site-specific background noise monitoring study.
n
i
L
Teq
i
nL1
10, 10/1log10
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 68.
Baseline Background Noise Quality Monitoring in the Study Area
Results of baseline background noise quality monitoring for winter season are presented in Table 4.23 and the locations of monitoring stations are already
shown in Figure 4.9. The results of noise monitoring carried out during winter season of 2014-2015 (3rd
November’2014 to 10th March’ 2015) are presented in
Annexure 4.4.
Interpretation of Background Noise Quality Monitoring Results
The ambient noise quality results indicate that day time as well as night time noise levels are well within the prescribed limits.
Table 4:23 Baseline Background Noise Quality Monitoring Results
Location
Code Location Name
Distance from Site
Boundary/ Direction
(Km)
Day Time Night Time
Land-use
Category Leq
(dB (A)
Limit (dB
(A)
Leq
(dB (A) Limit (dB (A)
NQ1 Project site - 54.8 55 44.4 45
Rural +
Residential
NQ2 Near Village Ullawas 0.48 km 52.1 55 38.1 45
NQ2 Near CGHS Society Sector-58 0.33 km 48.7 55 39.9 45
NQ4 Near Village Behrampur 0.87 km 52.7 55 38.2 45
NQ5 Near Village Ghata 1.95 km 49.8 55 37.4 45
4.9 TRAFFIC
The site is well connected with Existing Golf course extension road (Southern peripheral Road). Apart from this, the 60 m wide HUDA sector road has been
developed recently which also increase the connectivity of the proposed development.
The traffic volume count was conducted at two junctions (i) Golf Course Extension Road (SPR) and (ii) Sector Road adjacent to project site (60m wide road) to
analyze the traffic flow for weekdays and weekends. Figure 4.15 shows the traffic volume count locations and Table 4.24 shows the volume count at the
junction as mentioned above. The traffic volume count conducted during the winter season of 2014-2015 (03.11.2014 & 10.03.2015) are presented in Annexure
4.5.
Figure 4.14 Location of Traffic Volume Count
TM1
Table 4:24 Traffic Volume Count
S. No Vehicle Type Traffic Volume Count
Golf Course Extension Road (SPR) (TM1)
Traffic Volume Count
HUDA Sector Road (60m) adjacent to Project Site (TM2)
Weekday Weekend Weekday Weekend
1 Truck 1622 1837 622 737
2 Bus 241 159 54 44
3 Trailers 86 85 71 58
4 Tractor 66 64 40 47
5 Cars 1671 1102 733 598
6 Jeep/Auto 1168 915 138 115
7 T. Wheel 1994 1093 619 506
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 69.
8 Cycles 285 164 205 167
Total Vehicular Count 7133 5419 2482 2272
4.10 TRAFFIC PROJECTION
4.10.1 Population and Trips Generation for Horizon Year 2021
As a part of the initiative of developing efficient transport connectivity (traffic arising due to development of commercial complex and in the vicinity), a study
has been carried out for Traffic Forecast and Transport Planning based on the population projections as per GMUC 2025. Traffic forecasting has been done to
assess the horizon year (2021) traffic intensity on the project influence area (PIA) network /intersections and determining capacity requirements for transport
infrastructure. The road network in the vicinity of project site is as shown in Figure 4.16.
Figure 4.15 road network in the vicinity of project site
To Dwarka
From Pataudi
MULTI UTILITY CORRIDOR
LEGEND
UNDER CONSTRUCTION
COMPLETED
FUTURE EXPANSION
Project Site
The estimated daily population and trips for horizon year 2021 is summarized in Table 4.26
Table 4.25 Population and Trip generation in horizon year 2021
Sectoral Residing Population Floating Population Total Person Trips Peak Hour Vehicular Trips (PCU)
Development
Sector-58 35,929 20,023 73,629 3,829
Sector-59 20,490 2,433 29,899 1,456
SEZ 14,378 97,516 1,89,736 11,741
Sector-60 8,100 4,854 14,124 804
Sector-61 20,567 12,784 39,432 1,830
Total Sectoral Development 99,464 1,37,610 3,46,820 19,660
Total Population & Trips 2,37,074
4.10.2 Assumptions for Trip Generation
The following assumptions have been adopted to estimate the approximate number of trip generation:
Per Capita Trip Rate (PCTR) – PCTR as 0.7 for residing population and 1.75 for floating population
Modal Split – Model split as 16% private car, 25% two wheeler, 19% taxi/cab, 20% bus and 20% metro
Average Occupancy – Average occupancy as 2.5 for private car, 1.25 for two wheeler, 5 for taxi/cab and 35 for bus
Peak Hour factor – Peak hour factor is considered as 10% of total daily traffic
The estimation of peak hour vehicular traffic (PCU) has been carried out on study area road network based on generalized cost function using Cube Voyager
Software. The software determines the – (i) traffic intensity on surrounding area road network (ii) turning movements on surrounding intersections (iii) level
of service and capacity requirements for surrounding roads and intersections
The project site road area network for which the above forecasting has been carried out is as shown in Figure 4.17
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd., P a g e | 70.
Figure 4.16 Road network considered for traffic forecasting
4.10.3 Results of Traffic Analysis Study
The results obtained from the technical analysis is as shown in Table 4.27
Table 4.26 Traffic projection and road capacity requirement
Road
Section
SPR (155-
158)
SPR (150-
155)
SPR (146-
150)
SPR (143-
146)
SPR (137-
143)
SPR (134-
137)
Sec58-
Ghatta
(152-155)
Sec58-
Ghatta
(149-152)
Sec59-
SEZ
(177-176)
Sec59-
SEZ
(178-177)
Sec58-
Sec59
(145-136)
Sec58-
Sec59
(142-143)
Sec 59-
Sec 61
(135-133)
Sec59-
Sec61
(135-136)
Other Local
Roads
Peak Hr
Forecast in
PCU (2025)
15600 15100 15200 18500 16300 16600 8800 8700 8900 4600 2400 3900 3600 3600 Below
2000
Lane
Required 6 x 6 6 x 6 6 x 6 6x 6 6 x 6 6 x 6 4 x 4 4 x 4 4 x 4 2 x 2 2 x 2 2 x 2 2 x 2 2 x 2
2 x 2
Undivided
HUDA
Cross Section
6 x 6 Lane
(Variable ROW from 132 m to 162 m)
4 x 4 Lane
(60 m ROW)
2 x 2
Undivided (24 m ROW)
Remark* Sufficient Sufficient Sufficient
Note: * Compare with the capacity standards given in IRC: 106 (refer Table 4.28)
Table 4.27 Capacity standards (IRC 106)
Type of Carriageway Total Capacity (PUC/Hour) Capacity per lane (PCU/Hour)
8 Lane Divided 10290 1300
6 Lane Divided 7710 1300
4 Lane Divided 5140 1300
2 Lane Divided 2140 1100
4.10.4 Conclusion:
The above study has been carried out for Horizon Year 2021 considering road linkages of sector 58, sector 59, sector 60, sector 61, and proposed group housing.
It is concluded that
1) The total residing population and floating population in the above sectoral development is 99,464 and 1,37,610 respectively.
2) The total person trips generated in total sectoral development is estimated to be 3,46,820, that in turn will generate peak hour vehicular trips of 19,660
PCU.
3) The cube voyager software runs for estimation of level of service and capacity requirements for surrounding roads and intersections depicts that the
cross sections of HUDA sector roads in the vicinity of the project have sufficient capacity when compared to Capacity Standards given in IRC 106
(Refer table 4.27).
4.10.5 Hierarchy of Road within Proposed Project Site as per IRC: 86-1983
Table 4.29 gives the recommended land width for roads in urban areas as per the IRC:86-1983 (Geometric Design Standards for Urban Roads in Plains) and the
hierarchy of roads proposed within project. The Figure 4.18 shows the hierarchy of roads matching with the hierarchy as per IRC.
Project Site
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 71.
Table 4.28 Categorization of Road based on UDFI Norms and as Proposed in the Project Site
S.No Category Road Width as per
IRC:86-1983 (m)
Proposed Width of the Road within the
Project Site
1 Arterial 50-60 60 m (HUDA sector road)
2 Sub - Arterial 30-40 -
3 Collector Street 20-30 24 m wide Road
4 Local 10-20 10 m (Internal Circulation Road in
proposed project)
4.11 WATER ENVIRONMENT
The assess the impacts on surface and groundwater due to the proposed activity, it is essential to study
existing water resources in project area available with respect to their existing quality as well as their
supportive capacity to represent the baseline status of water environment.
The existing water resources, both surface and groundwater are identified with their respective significance
within the study area around project site. The representative sampling locations for surface water and
ground water are selected to assess the existing (pre-project) status of water quality in the impact zone. The
standard methods prescribed sampling as well as the analytical procedures for individual parameters are
followed in this study.
This section documents the baseline scenario of the water environment in the study area and discusses both
water resources and quality. The data has been collected from various secondary sources and primary
survey carried out in the impact zone.
4.11.1 Ground Water Resources & Availability
Central Ground Water Authority (CGWA) has identified Gurgaon and adjoining industries as “Notified
Area”. Gurgaon block is over exploited from hydro geological point of view. The depth of water table in
the district varies from 1 m to 30 m.
Both alluvium and Quartzite from the acquifer in the district whereas the yield of wells and tube wells
located in the alluvial acquifer ranges from 5.0 - 45.0 m3/hr. The yield of wells in the quartzite rock
formation can produce a yield of 10 – 15 m3/hr.
The net annual groundwater availability in the district is 718 MCM/year. The gross annual draft is 421
MCM/year and the stage of groundwater development in the district is 64 %. Blocks showing over
exploitation of ground water are Gurgaon, Farukhnagar and Pataudi Taoru.
Name of State Haryana
Name of District Gurgaon
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 72.
Geographical Area (sq.km.) 2,766
Major Geological formation Alluvium/Hard rock
Major drainage system Yamuna
Population ( As on 2001 ) 16,57,669
No of Blocks 9
Existing Major / Medium irrigation projects Gurgaon Canal
Utilizable ground water resources (MCM) 718
Net ground water draft (MCM) 421
Stage of ground water development (%) 64
Average annual Rainfall (mm) 626
Range of Temperature (oC) 5.1 – 40.0
Block showing over exploitation of ground water Gurgaon, Farukhnagar, Pataudi Taoru
The groundwater user map of Gurgaon district is as shown in Figure 4.19.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 73.
Figure 4.17 Groundwater User Map of Gurgaon District
Source Central Groundwater Board (2003)
The study of water resources is important from the point of view to assess the sufficiency of water
resources for the needs of the project in its various stages and the impact of the project on water
environment. In the proposed project, to assess the groundwater potential, hydro-geological study has been
carried out.
4.11.2 Hydro-geological
The area is mainly underlain by alluvium of quaternary age which forms the principal ground water
reservoir. At deeper levels, ground water also occurs in fractures, joints of hard rock formations. The
alluvium comprises of unconsolidated sediments, which are heterogeneous in composition. These are
constituted by beds of sands and clays with calcareous concretions (Kankar). The overall thickness of
alluvial sediments occurs down to about 85m.
The subsurface geological formations can be devided onto older alluvium and newer alluvium. The
newer alluvium sediments are deposited at shallow depths, whereas older alluvium is the result of past
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 74.
cycles of sedimentation and occurs at deeper depth. The area under the project is covered by newer and
older alluvium, which is characterized by presence of fine grained formations. These deposits consist of
inetrbedded, lenticular, interfringing sediments of sand various grades, silty clay intermixed with kankar
in various proportions. The ground water occupies the interstices of the unasserted alluvial sediments
comprising fine to medium grained sands, kankar, gravel and clays. The granular zones generally form
good repository of ground water. The potential aquifer zones in the area lies under unconfined to semi-
confined conditions. Rainfall is chief source of ground water recharge.
The Hydrogeological setting of the site is relatively favourable. The depth of water levels in the area is
reported between 20 to 25m below ground level.
There is no major drainage feature in the site area.
4.11.3 Vertical Electric Soundings (VES)
The geophysical investigation by way of vertical electrical sounding (VES) was conducted at one point
to determine the probable underground strata and potential ground water bearing zones. Schlumberger
configuration of potential and current electrodes was deployed for obtaining true resistivity values of the
sub surface geological starata so as to study the availability of water bearing zones occurring in horizons
at various depth ranges. The apparent resistivity values at different current and potential electrode
separation were recorded in the field. For obtaining sub surface lithological information, the maximum
current electrode separation in the range of 300 to 700 m was carried. Deep penetration, micro processor
based, signal stacking, A.C. resistivity meter was used for taking vertical electrical sounding at the point.
The apparent restivity values recorded in the field were plotted and interpreted with the help of
softwares.
The computerized resistivity curve obtained for the surveyed point is given in Fig-4.21 and point of
geophysically investigated is marked in fig.-4.20(site plan)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 75.
Figure 4.18 Site Plan showing location of surveyed points
Results of VES
Curve Matching Method
The interpreted result shows existence of three geo-electric layers representing different hydrogeological
set up and these are tabulated below:
Table 4:29 True Resistivity in ohm meters for Surveyed point VES-1
Layer Depth Range (m) BGL Ture Resistivity
(Ohm-m)
Inferred Strata
1st 0.00 – 2.20 142 Dry surface soil with sandy silt
2nd
2.20 – 20.90 57 Partially saturated coarse grained sand
3rd
20.90 – 95.40 19 Saturated fine grained silty sand
4th 95.40 – 153.4 10 Saturated fine grained sandy silt
The interpreted results of resistivity survey indicates that the water level at the site occur at about 37m
below ground level as at this depth there is drop in true resistivity value from 68 ohm-m to 15.99 ohm-m.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 76.
Below water level, the true resistivity value is of the order of 19 ohm-m indicating presence of Saturated
fine grained sandy silt..
Figure 4.19 Resistivity Curve for surveyed point VES-1 Obtanied for Proposed Project Site
4.11.4 Surface Water Availability during Construction Phase
During the construction phase, treated raw water to be collected and transported from STP of HUDA and
then further treatment will be given as per the desired construction water quality at project site.
4.11.5 Surface Water Availability during Operation Phase
Sourcing water from HUDA water supply for the licences covered under Gurgaon Manesar Urban
Complex Plan.
Presently Gurgaon city gets water through 70 km long Gurgaon Water Supply Channel, which
originates from village Kakroi, in district Sonepat and culminates at village Basai in Gurgaon where
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 77.
water is filtered and treated in two water treatment plants of 20 MGD each. The construction work on the
third water treatment plant of 20 MGD at Basai is under progress. This treated water is regulated to
various areas (upto sectors 57).
To meet the increasing potable water demand in Gurgaon, Government of Haryana (GoH) has
formulated an additional plan to construct a 65.6 km long National Capital Region (NCR) Water
Channel which would off take from Delhi Branch and pass through the districts of Sonipat, Rohtak and
Jhajjar by gravity flow and have eight head regulators. This NCR channel would have a total capacity of
800 cusecs. Initially this would supply 500 cusecs and gradually as the population increases will add 300
cusecs more. This NCR Channel, on which the work has already started, is expected to be ready by the
time the proposed group housing project comes up. This Project falls within the Gwal Pahari Master Plan
area. To cater to the planned areas under Gwal Pahari Master Plan, the GoH has decided to set up a new
Water Treatment Plant (WTP) to be constructed by the Haryana Urban Development Authority
(HUDA). The plant will have a storage capacity of 66 MGD and it will be constructed at Chandu-
Budhera, in two phases. In the first phase, 22 MGD treatment plant will be built and the remaining
capacity will be completed in the second phase.This Project falls within Sector 61 of Sohna under
Gurgaon Manesar Urban Complex Plan– 2031 AD. As per the requirement we have already applied to
HUDA for asurance of water. The receipt of the same has been attached as Annexure 2.4.
4.11.6 Alternate Sustainable Water Management Strategies during Operational Phase
The Project Proponent is committed to carry out extensive water management practices (recycle and reuse)
as a part of its environmental sustainability strategy. Our master plan is proposed to be based upon “water
balance” or the balance between the volume of water removed from our groundwater supplies and volume
water returned to our groundwater supplies from rainfall, ponds, and innovative stormwater management
techniques.
The Proposed Water Conservation and Development Measures include: i) Development of water sources
like rainwater harvesting systems and collection of Run-off, ii) Minimizing water consumption by a
combination of water saving devices and other domestic and commercial water conservation measures, and
iii) Treated waste water use. The details are given in Section 6.7.2
4.11.7 Water Quality
Methodology of Baseline Water Quality Monitoring
The basic considerations for designing water quality surveillance programme include:
Topography
Surface run off
Natural and manmade drainage/irrigation canal systems
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 78.
As per the requirement of Form 1A under the Section 2 (Water Environment), Water sampling and
analysis has been conducted to establish baseline water quality in the area. Sampling has been done
following the standard guidelines for physical, chemical and bacteriological parameters. Analysis has
been carried out by following the methods prescribed in “Standard methods for the examination of water
and wastewater (American Public Health Association)”.
Results of Baseline Water Quality Monitoring
GROUNDWATER QUALITY
Ground water was collected from one location during winter season of 2014-2015 (3rd
November’2014 –
10th March’2015) in the study area of Village Ullawas for analysis. Table 4.30 gives the location details.
Table 4:30 Baseline Water Quality Monitoring Location
SN Station Code Station Name Distance from Site
Boundary (Km) Category
1 GW1* Ullawas Village 0.48 W Rural + Residential
*GW – Ground Water Monitoring Locations
Table 4.31 depicts the physico-chemical characteristics of the ground water samples, as compared with
the standard (IS 10500: Indian Standards/Specifications for Drinking Water) reference values. The
results of ground water quality monitoring carried out during the winter season of 2014-2015 (3rd
November’2014 – 10th March’2015) are presented in Annexure 4.6.
Table 4:31 Ground Water Quality near the Project Site
S.No Parameters Results
Complete test as per IS:10500·
2012
Desirable Limit Permissible
Limit
i Colour (Hazen Unit) 1 5 Max 25 Max
ii Odour Unobjectionable Unobjectionable Unobjectionable
iii Taste Agreeable Agreeable Agreeable
iv Turbidity, NTU 1 5 Max 10 Max
v pH Value 7.31 6.5 to 8.5 No relaxation
vi Total Hardness (as
CaC03), mg/l 141 300 Max 600 Max
vii Iron (as Fe), mg/l 0.119 0.3 Max 1 Max
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 79.
S.No Parameters Results
Complete test as per IS:10500·
2012
Desirable Limit Permissible
Limit
viii Chloride (as Cl), mg/l 67 250 Max 1000 Max
ix Fluoride (as F), mg/l 0.28 1 Max 1.5 Max
x Dissolved solids,
mg/l 434 500 Max 2000 Max
xi Calcium (as Ca),
mg/l 44 75 Max 200 Max
xii Magnesium (as Mg),
mg/l 19 30 Max 100 Max
xiii Copper (as Cu), mg/l BDL 0.05 Max 1.5 Max
xiv Manganese (as Mn),
mg/l BDL 0.1 Max 0.3 Max
xv Sulphate (as S04),
mg/l 30.8 200 Max 400 Max
xvi Nitrate (as N03),
mg/l 0.65 45 Max No relaxation
xvii Phenolic compounds
(as C6H5OH), mg/l BDL 0.001 Max 0.002 Max
xviii Mercury (as Hg),
mg/l BDL 0.001 Max Not relaxation
xix Cadmium (as Cd),
mg/l BDL 0.01 Max Not relaxation
xx Selenium (as Se),
mg/l BDL 0.01 Max Not relaxation
xxi Arsenic (as As}"
mg/l BDL 0.01 Max Not relaxation
xxii Cyanide (as CN),
mg/l BDL 0.05 Max Not relaxation
xxiii Lead (as Pb), mg/l BDL 0.05 Max Not relaxation
xxiv Zinc (as Zn), mg/l BDL 5 Max 15 Max
xxv Anionic detergents
(as MBAS), mg/l BDL 0.2 Max 1.0 Max
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 80.
S.No Parameters Results
Complete test as per IS:10500·
2012
Desirable Limit Permissible
Limit
xxvi Chromium (as Cr
6+ ),
mg/l BDL 0.5 Max No relaxation
xxvii
Polynuclear aromatic
hydrocarbons' (as
PHA),g/l
BDL - -
xxviii Mineral oil, mg/l BDL 0.01 Max 0.03 Max
xxix Pesticides, mg/l BDL Absent 0.00.1
xxx Alkalinity. mg/l 159 200 Max 600 Max
xxxi Aluminium (as Al).
mg/l BDL 0.03 Max 0.2 Max
xxxii Boron,mg/l BDL 1 Max 5 Max
xxxiii Sodium as Na 18.2 150 No relaxation
xxxiv coliform/100ml,
MPN Absent Absent
xxxv Escherichia
coli/100ml Absent Absent
BDL- Below Detectable Limit
INTERPRETATION OF BASELINE GROUND WATER QUALITY MONITORING
The physico chemical analysis of water suggests that water quality is within the desirable as well as the
permissible limits of drinking water standards IS: 10500-202.
4.11.8 Construction Water Quality
The raw water collected from STP of HUDA and further treated for construction purposes shall be
analyzed before use for construction and compared with water quality standards prescribed for
construction purpose as per IS 456:2000
4.12 LAND ENVIRONMENT
4.12.1 Soil
Impacts on land environment from construction activities can be mainly attributed to disposal of
solid/hazardous waste and discharge of wastewater either onto land (direct impacts) or into water bodies,
which are also used as irrigation water resources (indirect impacts). Moreover impacts on
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 81.
land/vegetation are also expected due to fallout of air pollutants. Accordingly for environmental impact
assessment it is pertinent to study the characteristics of soil, the resulting changes in soil due to disposal
of harmful substances on land and the resultant behavior of the surrounding soil environment.
4.12.2 Soil Quality
The soil of the region is older alluvium and was deposited in the earlier times with no recurring deposits
in present time.
The pre project status with respect to soil characteristics (physical, chemical and bacteriological), land
use pattern in the impact zone around the project site forms the baseline status of the land environment.
The basic consideration for designing soil quality surveillance program include
Physical and chemical properties of the area;
Erosion potential;
Storm water run-off quality;
Agricultural productivity of land;
Soil quality analysis has been done in one location at project site.
4.12.2.1 Particle Size Distribution
A quantitative assessment of the type and characteristics based on particle size distribution in the soil
was made by wet sieve analysis and sedimentation analysis using hydrometer, as per procedures laid
down in IS: 2720 Part IV. The type of soil based on particle sizes is given in Table 4. 32.
Table 4:32 Soil Type based on Particle Size
S. No Type of Soil Units Range
1 Gravel % 2.9 - 3.9
2 Sand % 39.6 – 41.3
3 Silt % 49.2 – 50.3
4 Clay % 5.6 – 7.2
The above table indicates that the majority of the soil is of silt type (50.3%) followed by Sand (41.3 %).
4.12.2.2 Soil Characteristics
Table 4.33 presents the physical and chemical characteristics results of soil sample collected during
winter season of 2014-2015 at project site. The results of soil quality monitoring carried out during the
winter season of 2014-2015 i.e. (3rd
November’2014 – 10th March’2015) are presented in Annexure 4.7.
Table 4:33 Soil Characteristics at Different Depths
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 82.
Sr.
No.
Parameter Units Results
Soil Sample 1
(0-15 cm)
Soil Sample 2
(15-30 cm)
Soil Sample 3
(30-60 cm)
Soil Sample
4
(60-100 cm)
1 Texture - Siltloam Siltloam Siltloam Siltloam
Gravel % 3.9 3.6 3.1 2.9
Sand % 41.3 41.1 40.8 39.6
Silt % 49.2 49.5 50.1 50.3
Clay % 5.6 5.8 6.0 7.2
2 pH - 8.11 7.98 8.0 7.92
3 Nitrogen Mg/100gm 1.46 1.15 1.14 1.12
4 Phosphorus Mg/100gm 9.5 8.2 7.5 7.6
5 Potassium Mg/kg 0.61 0.48 0.39 0.35
6 Moisture % 9.2 10.2 10.5 10.2
7 Bulk Density gm/cm3 1.41 1.45 1.47 1.48
8 Sulphates Mg/100gm 44.8 32.6 30.5 29.6
9 Organic
Matter
% 0.69 0.41 0.41 0.38
10 Chlorides Mg/100gm 154 142 129 121
11 Water
Holding
Capacity
% w/w 22.2 20.9 20.5 20.1
12 Conductivity
(20% slurry)
µ
mhos/Cm
1368 1295 1315 1341
13 Porosity % v/v 24.1 24.2 24.3 24.6
14 Iron as Fe Mg/kg 100.5 79.3 58.2 53.6
15 Zinc as Zn Mg/kg 1.85 1.68 1.43 1.45
16 Copper as Cu Mg/kg 0.52 0.21 0.45 0.28
17 Lead as Pb Mg/kg BDL (0.02) BDL (0.02) BDL (0.02) BDL (0.02)
18 Sodium as Na Mg/kg 105 99.3 98.8 91.5
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 83.
19 Boron as B Mg/kg BDL (0.02) BDL (0.02) BDL (0.02) BDL (0.02)
20 Sodium
absorption
Ratio (SAR)
% 8.0 7.9 7.8 7.6
21 Permeability
Rate
cm/hr 19.8 20.2 20.7 21.0
Interpretation of Soil Characteristics of the Project Site
The soil is siltloam at all the four depths i.e. 0-15cm, 15-30cm, 30-60cm, 60-100cm.
The organic content is also low at all the four depths.
The soil is fit for construction work.
4.12.3 Soil Fertility
The soil fertility was analyzed as per the criteria adopted by Department of Farmer Welfare &
Agriculture Development, Govt. of Madhya Pradesh for soil fertility. (Source:
http://www.mpkrishi.org/EngDocs/AgriLeft/Soilt/soiltHome.aspx).
The results given in Table 4.32, shows that the soil is not very fertile, due to the low percentage of
Organic contents (0.38 – 0.69 %) and major nutrients such Nitrogen (N) - (1.12- 1.46 mg/100gm),
Phosphorous (P) – (7.5 - 9.5 mg/100gm) and Potassium (K) – (0.35 - 0.61 mg/kg).
4.12.4 Soil Permeability
In order to determine the intake capacity of recharge wells to be constructed in the area, the permeability
(infiltration) test has been carried out in the adjoining area by MoEF/ NABL accredited laboratory.
In the test borewell down to the depth of 100m was carried out. The results show that the permeability
rate varies in the range of 19.8 to 21.1 cm/hr.
4.12.5 Soil Porosity
Soil porosity refers to that part of a soil volume that is not occupied by soil particles or organic matter.
Pore spaces are filled with air, other gases, or water. Large pores (macropores) allow the ready
movement of air and the drainage of water. They are also large enough to accommodate plant roots and
the wide range of tiny animals that inhabit the soil. Large pore spaces permit fast infiltration and
percolation of water through a soil or soil horizon. Small pores (micropores) exhibit attractive forces
strong enough to hold water in the pore. They are the water retention system of the soil which provides
water storage for plant roots. During precipitation, macropores conduct water into the soil where it fills
the micropores. At field capacity all pores small enough to retain water against the pull of gravity are
filled. Clay soils have numerous micropores and hold large quantities of water, but since they have few
macropores they produce very slow infiltration rates. The pores in the clays may be so small and hold
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 84.
water so tenaciously that the water is not available to plants. Sandy soils with numerous macropores but
few micropores have higher infiltration and percolation rates but a lower water-holding capacity than
other soil textures. A lower water-holding capacity can mean less available water for plant roots. For
revegetation purposes, plants perform best in intermediate soil textures (loams) where soils contain
mixtures of micro- and macropores.
The soil porosity at site varies from 24.1%- 24.6% by v/v which indicating it to be less porous as per
protocol FAO / IS : 2720.
4.13 BIOLOGICAL ENVIRONMENT
The data on biological environment has been collected from the literature/secondary survey and visual
inspection of the project site to i) establish the baseline ecological conditions of the general study area
(area within 10 Km radius of the project site), ii) to have a preliminary assessment at the project site iii)
to assess the potential ecological impacts of the proposed project upon ecology, iv) to develop adequate
and feasible mitigation measures (via inputs to project design and layout, working practices, or
compensate where appropriate) and v) to keep residual ecological impacts with acceptable limits, This
section of report presents the ecological baseline of the area.
4.13.1 Habitat Assessment
The site area is almost a barren land with sparse vegetation. No protected areas (including either reserve
or protected forests) are located within the study area. Besides, the proposed project area is neither
located within an existing or any proposed ecological sensitive zone known for providing habitat and
movement corridor for any kind of animals or under PLPA, 1900 or under any other applicable forest
laws on land. The project proponent has obtained NOC from the forest department regarding the
regarding applicability of forest of forest laws on land. The copy of NOC obtained is enclosed as
Annexure 4.8. The Depty Commissioner (DC) has also given the NOC under Aravali notification
stating that none of the khasra nos. falls under the Aravali. The copy of NOC obtained from DC is
enclosed as Annexure 4.9.
Hence, the impact on the wildlife values due to development of project is not expected.
4.13.2 Terrestrial Ecology
4.13.2.1 Floral Profile
This part of Haryana falls under Semi-Arid Punjab plains in terms of Bio-geographic provinces. The
land use pattern of the area is unproductive. There is no ecological sensitive zone.
An ecological study of the ecosystem is essential to understand the impact due to project development
activities on the existing flora and fauna of the area. The objective is to study and understand the present
status of the ecosystem in the study area. The present study was undertaken to predict changes as a result
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 85.
of project activities and to suggest feasible measures for maintaining/enhancing the conditions. This
section describes the ecology of the area based on information compiled from secondary data available
for the area and visual inspection and tree survey of the project site.
FLORA WITHIN 10 KM RADIUS
The proposed site in Haryana falls under Semi-Arid Punjab plains in terms of Bio-geographic provinces.
The land use pattern of the proposed site and the surrounding areas is non-productive and semi urban.
There is no ecological sensitive zone providing habitat and movement for any kind of animals in the
immediate vicinity of the proposed site. No permanent aquatic ecosystem with significant ecological
resources is also found within the study area. Based on the information compiled from secondary sources
and visual inspection, the list of common trees and shrubs observed within 10 km radius of the project
site is presented in Table 4.34.
Table 4:34 List of Floral Species found within 10 km radius
Tree Shrubs Herbs
Acacia nilotica (Babul) Adhatoda vascica Acalypha indica
Acacia tortilis (israeli kikar) Ageratum conyzoides Achyranthes aspera
Albizzia procera (Siris) Calotropis procera (Ak) Aerva lanata
Azadirachta indica (Neem) Cassia occidentalis Amaranthus caudatus
Bauhinia variegata (kachnar) Datura metel (krishna datura) Amaranthus spinosus
Butea monopserma (Palash) Thevetia nerifolia Ambrosia artimisfolia
Cassia siamea (Kassod) Langerostomia speciosa
(Queen’s Flower)
Argemon exicana
Dalbergia sissoo (Shisham) Climber Argemone glauca
Eucalyptus spp. (Safeda) Cuscuta reflexa (Akash Bel) Bidens pilosa
Ficus religiosa (Pipal) Tribulus terrestris
(Gokhru)
Cannabis sativa
Leucaena leucocephala (So-Babul) Vallaris heyni(Dudhi) Chenopodium alba
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 86.
Tree Shrubs Herbs
Melia azadirachta (Bakain) Chenopodium murale
Prosopis juliflora (Vilayati kikar) Cleome gynandra
Terminalia arjuna (Arjun) Croton achnocarpus
Grasses
Ristida purpurea
Cynodon dactylon
Cyperus bulbosus
FLORA WITHIN PROJECT SITE
The project site is an undulating barren land and supports only few shrubby grasses and seasonal herbs.
4.13.2.2 Faunal Profile
FAUNAL PROFILE WITHIN 10 KM RADIUS
The absence of a good forest cover and litter formation has lead to lack of ideal habitats for fauna. In
most parts of the general study area, which has the characteristics of an urban ecosystem, wild fauna is
obviously very impoverished. There are, however, species associated with human habitats. Main wild
life mammals within various part of the study area are Jackal, Fox, Hyaena, etc., and reptiles & snakes.
The domestic animals consist of cows, buffaloes, camel, goats and dogs. Apart from common birds like
fowl, peacock, house sparrow, house crow, pigeons, parrots, dove, cuckoo, vulture, kite etc., other birds
like bulbul, patridge, sand-grouse, baya, tailor bird, kingsfisher etc. are also met within various parts of
the study area. List of the avifauna found in the general study area is given in Table 4.35
Table 4:35 List of Avifauna within 10 Km Radius
S.No. Zoological Name Common Name
01. Pycnonotus cafer Red vented bulbul
02. Columbus livibus Rock Pigeon
03. Acridotheres tristicus Common myna
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 87.
S.No. Zoological Name Common Name
04. Ploceus Philippines Weaver bird
05. Passer domisticus House Sparrow
06. Megalaima merulinus Indian cuckoo
07. Alcedo atthis Common Kingfisher
08. Bubulcus ibis Cattle Egret
09. Corvus splendens House crow
10. Pycnonotus cafer Red vented bulbul
No wildlife sanctuary / park is located within 10km radius of the project area. No rare or endangered
species have been recorded in the project area.
FAUNA WITHIN THE PROJECT SITE
During the physical survey, no mammalian species were observed in the proposed site. This is due to the
existing land use pattern.
4.14 SOCIO-ECONOMIC ENVIRONMENT
The baseline situation is based on demographic structure, economic activity, education, literacy profile
and infrastructural scenario of the study area. On the basis of the data compiled in this section, the EIA
study attempts to predict and evaluate future impacts of the project on the people of the affected village,
their social, economic, physical and psychological health and well-being, economic facilities, heritage
culture, lifestyle and other value systems.
The information provided in the following sections has been primarily derived from two sources, viz. the
primary source (Census of India, extensive surveys conducted in the villages covering various socio-
economic attributes) and secondary sources (published and unpublished data, newspapers etc).
The primary survey was conducted in a few surrounding villages in order to assess the prevailing social
and economic conditions and in identifying the various problems and major issues in the concerned
villages due to the proposed development. Discussions and consultations were carried out in the villages,
regarding some basic information related to amenities, caste structure, livelihood, transportation etc. The
understanding of the locals about the project, its negative and positive benefits were also elicited.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 88.
4.14.1 General Socio-Economic Profile
The study area covers the following villages– Ullawas Village, Behrampur Village, Kadarpur Village
and Ghata of district Gurgaon in the state of Haryana. The total population of the villages is 8717 people,
with 1206 households in total.
The project is not likely to have significant demographic changes on the villages located.
4.14.2 Demographic Profile
The baseline data for the population of the surrounding area is significant to the study as it enables to
predict the population that may be impacted by the proposed project. It also enables in determining the
situation due to an increase in population during the tenure of the project, until its completion, and, the
various impacts arising as a result of the different project activities. Table 4.36 provides the break-up of
population, household size and sex ratio of the identified villages.
Table 4:36 Demographic Details
Village Total Population Total Households Total Male Total Female
Ullawas 1,506 213 815 691
Behrampur 1,472 208 785 687
Kadarpur 4,235 597 2,224 2,011
Ghata 1,504 188 810 738
Total 8,717 1206 4,634 4,127
Source: Census of India, 2001
As seen in Table 4.36, Kadarpur village has the highest population (4,235) followed by Ullawas (1,506)
and Ghata (1,504).
4.14.3 Education & Literacy
Primary and intermediate level school facilities are available within 5 km radius. Private technical
education institutes are present in the vicinity of the site.
4.14.4 Economic Activity and Livelihood Pattern
An understanding of the economic activities and livelihood pattern is important to predict the impact of
the project activities on the economy of the region. Livelihood pattern coupled with educational profile
would assist in identifying areas where the local workforce can be integrated into the project activities.
4.14.5 Existing Physical & Social Infrastructure Facilities in the Region
Schools:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 89.
The city is home to a number of world class educational Institutes; there are several primary
and secondary schools located in the area. The educational facilities are provided in stages i.e.
junior basic school, senior basic school, higher secondary school, degree colleges, Pre-
primary and primary educations are mainly the responsibility of the local bodies. Middle,
secondary and senior secondary education is primarily looked after by Directorate of
Education, Government of Haryana. At the University level, Govt. of Haryana is also
running Degree Colleges being funded by UGC and Haryana Govt. Apart from this a number
of private organizations are also engaged in imparting education at all levels of schooling.
Tele-Communication
Telecommunication facility in the study area is adequate; electronic telephone exchange is
working in the study area, and mobile facility is also available.
Roads and Transportation System
The site is well connected with Existing Golf course extension road (Southern peripheral
Road). Apart from this 60m wide HUDA Sector road has been developed recently, which also
increase the connectivity of the proposed development.
Post-Office
Postal cum telegraph facility is also available. Post office facility is available at area.
Banks
The Study Area is having branches and ATMs of all major nationalized as well as privatized
banks.
Hospital
Civil Hospital caters to health needs of this region and also has to share the burden of
migratory as well as floating population from neighboring states.
Community Health Centre plays a significant role and is committed to provide health care
facilities to the people of this region and it does so through a network of existing primary,
secondary and tertiary hospitals, dispensaries/ health centers, school health clinics, child care
centers; by implementation of various state and national programme under medical and public
health sector for prevention and eradication of various diseases. ESI Dispensary & Good
Private Clinic facility is available in Gurgaon and South-West Delhi region. There are number
of hospitals within 15 km radius of the project site. Paras Hospital , Kabliji Hospital, Artmis
hospital Civil Hospital , Private hospital, Max hospital, Medicity etc. Apart from these a chain
of government runs and private dispensaries as well as small nursing homes in the locality
serve as first aid to the local people.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 90.
5 POLLUTION SOURCES, IMPACT PREDICTION & IMPACT
ASSESSMENT
5.1 POLLUTION SOURCES
Pollutants generated during the construction and operation phase of the proposed development either be
liquid, solid and gaseous in nature. The generation of pollution may be periodic, continuous or accidental.
Potential sources of pollutants and their characteristics during the construction and operation phase are
given below in Table 5.1.
Table 5:1 Potential Pollutant Sources & Characteristics
S.
No Activity / Area Pollutant Pollutant Characteristics Frequency
CONSTRUCTION PHASE
1. Ground excavation
and leveling
Air emissions: PM10,
PM2.5 CO, NOx, SO2
Dust from construction
activities and excavation.
Particulates, NOx and CO
from vehicle exhaust
Temporary during
construction phase
only- bulk of the
emissions are expected
from ground working
and leveling activities.
Earth / solid waste Solid waste from
construction activity and
excavation.
Periodic.
Noise Noise generated from
construction equipment and
machinery
Temporary during
initial construction
phase.
2. Labour Camps Sewage Sewage generated from
temporary labour camps on
site
Temporary – during
the initial construction
phase
Solid Waste Solid Waste generated from
temporary labour camps on
site
Temporary – during
the initial construction
phase
OPERATION PHASE
1. Vehicular
movement
Air emissions and
noise
Vehicle exhaust emissions Continuous / Periodic
2. Diesel power
generators
Air emissions
SO2, NOx, PM, CO from fuel
burning
Continuous
Noise
Noise due to running of
equipment
Continuous
Hazardous waste Used Oil Generation Periodic, during oil
changes
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 91.
S.
No Activity / Area Pollutant Pollutant Characteristics Frequency
3. Commercial/Indust
rial/Residential
Wastewater Wastewater containing
waste food matter
Continuous
Domestic Solid waste Garbage / Food waste Continuous
4. Project area
including common
toilets
Sewage
Domestic wastewater – BOD,
S.S, Pathogens
Continuous
Domestic Solid
Wastes
Bio-degradable and non-
biodegradable wastes
Continuous – small
quantities
5. Raw water
treatment
Wastewater Backwash water discharge Continuous
Solid waste Sludge from coagulation
process
Continuous
6. Sewage treatment
Plant
Solid waste Settled and stabilized sludge Continuous
Treated water Treated sewage used for
horticulture
Continuous
7. Diesel Storage Solid waste
Settled sludge during tank
cleaning
Occasional
Oil
Oil spillage – Accidental
large spills due to pipe
rupture
Oil Spillage - Small
quantities due to small pipe
leaks
Accidental / Only due
to poor housekeeping
8. Maintenance/
housekeeping
Wastewater Floor washing Continuous
Solid waste Used equipment parts and
garden wastes
Continuous
9. Vehicle Parking
Area
Oil Spills Minor oil leaks in parking lot Continuous – small
quantities
10. Storm water drains Wastewater Contamination discharge
from site – Mainly suspended
solids
During rainy season
5.2 IMPACT PREDICTION AND IMPACT ASSESSMENT
The primary function of an environmental impact assessment study is to predict and quantify potential
impacts, assess and evaluate the magnitude and their importance in order to develop an environmental
management plan to mitigate the impacts. Environmental impacts could be positive or negative, direct or
indirect, local or regional and also reversible or irreversible.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 92.
Baseline environmental conditions at the proposed site for various parameters were provided in Chapter 4
whereas Table 5.1 given above provides the various pollution loads and stressors that could impact the
environment. This chapter discusses the incremental environmental impacts on the environmental parameters
during the construction and operation phases of the project. The potential impacts have been identified in
Table 5.2. The mitigative measures for the adverse impacts, if any are discussed in Chapter 6 Environmental
Management Plan.
Table 5:2 Identification of potential Impacts during Construction & Operation Phase
S. No Components Aspect Potential Impact
CONSTRUCTION PHASE
1. Ambient Air
Quality
Dust emissions from site preparation,
excavation, material handling and other
construction activities at Site.
Minor negative impact inside the premises.
No negative impact outside project site.
Short term
2. Noise
Noise generated from construction
activities, operation of construction
equipment and traffic.
Minor negative impact near noise generation
sources inside premises.
No significant impact on ambient noise levels
at sensitive receptors.
Short term
3. Water quality Surface runoff from project site
Oil/fuel and waste spills.
Improper debris disposal
Discharge of sewage from labour
camp.
No significant negative impact.
Short term
4. Landuse and
Aesthetics
Land development Minor positive impact
5. Topography &
Geology
Site development No Significant Impacts
6. Soil Construction activity leading to topsoil
removal and erosion.
Minor negative impact
7. Ecology
Flora & Fauna
Habitat disturbance during construction
activity
Minor negative impact
Short term
8. Socio-economy Increased job opportunity for locals.
Economy related to residential real
estate development, material supply
etc. expected to boom.
Overall positive impact
9. Traffic Pattern Haul Truck movement and possibility
of traffic congestion outside site on
Sohna-Gurgaon Road
Minor negative impact
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 93.
S. No Components Aspect Potential Impact
OPERATION PHASE
1 Ambient Air
Quality
Particulate and gaseous emissions from
DG sets and vehicle movement Minor Negative impact
2 Noise
Noise from vehicle movement and
operation of diesel generator sets
during power failure.
Minor negative impact inside premises.
No significant impact at sensitive receptors.
3 Water Quality Oil/fuel and waste spills.
Discharge of sewage.
Discharge of contaminated storm water
No significant adverse impact
4 Water usage Use of over ~231 KL per day fresh
water at peak demand
Minor negative impact
5 Soil Storage and disposal of solid and
hazardous wastes
Discharge of sewage
Fuel and material spills
Pesticides use
No negative impact
6 Ecology
Flora & Fauna
Landuse change
Discharge of wastewater to surface
water bodies
No negative impact
7 Socio-economy Increased job opportunity in the
proposed project for the locals.
Overall positive impact
8 Traffic Pattern The proposed project is likely to add
significantly to the predicted traffic
during peak hours.
Moderate Negative Impact
5.3 IMPACT ON PHYSICAL ENVIRONMENT
5.3.1 Impact on Land use & Aesthetic
The land acquired for the proposed development is mainly a non productive land with undulating
topography. The existing land use of the acquired site does not have any agricultural practices; although,
some of the small bushes and seasonal vegetation exist within the site. However, the said land has already
granted license for Independent Floors development by Directorate of Town & Country Planning (DTCP).
Therefore, it can be adhered that the proposed development will not cause any loss to agricultural
productivity, as the land is not having any such activity at present.
The proposed facade of the project was designed with climate responsive elements, sensitive use of stone,
water and greenery to create an efficient and aesthetic work environment. Planned environment friendly
development would create a positive impact on the aesthetics and visual appeal of the region.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 94.
The proposed development on the project site include development of large inter connected landscaped
areas and open spaces at various levels which would enhance the overall aesthetics of the area.
The change in aesthetics and visual appeal of the region will also be positive, wherein unplanned development
will give way to a planned, environment friendly and sustainable urban habitat.
5.3.2 Impact on Topography
The project site has moderate topography with slight variation of highest and lowest point. The existing
ground level (EGL) at the time of the topographical survey varies from RL 237.5 (lowest) to 244.0
(highest). The proposed activity during the construction phase would involve excavation work and leveling of
proposed site. Since the proposed site involves the construction of one level basement, it is estimated that
about 1,50,000 cum earth will be excavated. The cut fill will be balance by volume of earth which would be
excavated and for filling low lying area and construction of embankment for roads.
The construction activities will proceed in a manner so as to maintain the natural slope of the area by
creating basement.
No additional stresses will be imposed by the project on these parameters and hence no significant impacts
are expected.
5.3.3 Impact on Geology
Quarry material requirements for the proposed development have been estimated, as such the key natural
materials such as earth, sand, stone will be sourced from licensed and government approved quarries.
Table 5:3 Quantity of Quarry Material
Description Course Sand in
Cum Fine Sand in Cum
Aggregates in
Cum
Quantity 45000 9000 60000
Source of Material Local market Local market Local market
It will be ensured that these quarries have required environmental approvals and abundant capacities to
meet the requirement of the project. A significant quantity of natural material requirement will be
substituted by using flyash. Hence, no negative impact is envisaged on the local geology of the area.
5.3.4 Impact on Drains
As discussed earlier in Section 4.5.7 the site does not have any streams or drains. The site has a moderate
terrain, with little variation of highest and lowest part of the land.
The construction activities will not have an impact on the existing drainage pattern of the proposed site as
the natural slope will be maintained and the excess runoff will be channelised through garland drains
provided around the construction areas.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 95.
5.3.5 Impact due to Tectonics / Earthquakes
The project area falls under seismic zone IV as per the Seismic Zoning Map of India (IS 1893, Part-I, 2002)
and therefore area is moderately susceptible to earthquakes. The proposed development will not involve any
change in the tectonics of the area as the topography of the area will be maintained by creating adequate
basement and through the leveling of land, as and when required. However, the design of the proposed
building will take into consideration all these risks, associated with the incidents like earthquake.
5.3.6 Impact on Mineral Resources
No impact on minerals is anticipated because of the construction of proposed Independent Floors
development, as currently there are no signs of presence of minerals in direct influence area of the proposed
development.
5.3.7 Climate & Meteorology
The climate and meteorological pattern of the region impact due to the proposed development as there will
be low spatially restricted short term impact due to cutting of vegetation. The development of peripheral
green belt development and landscape plantation is a part of the proposed development which will help in
improving the micro-climate of the region.
5.4 IMPACT ON AIR ENVIRONMENT
5.4.1 Air Emissions Sources
Air emissions have no boundaries and can migrate from one place to another place depending upon the
wind direction and speed. The sources of air emission can be grouped into three categories of point, area
and line sources:
1. A pollutant source that can be treated in a dispersion model as though pollutants were emitted from
a single point that is fixed in space. Example: the mouth of a smoke stack.
2. An array of pollutant sources so widely dispersed and uniform in strength that they can be treated in
a dispersion model as an aggregate pollutant release from a defined area at a uniform rate. Such
sources may include vehicles and other small engines, small businesses and household activities, or
biogenic sources, such as a forest, that release hydrocarbons.
3. An array of pollutant sources along a defined path that can be treated in dispersion models as an
aggregate uniform release of pollutants along a line. Example: the sum of emissions from individual
cars traveling down a highway can be treated as a line source.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 96.
5.4.2 Fugitive Emissions from site preparation
During the construction phase of the project, the principle source of air pollution will be dust from exposed
site areas, stockpiling, and movement of vehicles along unpaved roads, excavation and handling of
construction materials.
5.4.3 Impact on Air Environment due to Construction Activities
Air Quality
During the construction phase, the major sources of air emissions include:
Particulate Matter (PM) associated with the construction activity
Emissions due to the operation of DG sets, to be used for supplying power
The impact due to the operation of DG sets during the construction phase
In order to quantify the impact of SPM associated with the construction activity, it is planned that the
construction activity will be carried out in phases. The emission sources will be distributed throughout the
project site and will fall under the category of area source.
Basic Consideration
In the absence of information regarding the quantity and type of construction equipment to be deployed at
any particular time, overall emission factor for SPM from construction activities has been used. Overall
SPM emission has been estimated using the emission factor of 1.2 tons SPM/month of activity/acre as per
AP-42 Section 13.2.3.3 (USEPA, 1995). This emission factor is used for developing emission estimates
from construction activities throughout a geographical area and is most applicable for construction
operations with medium activity level, moderate silt contents and semiarid climate (USEPA, 1995). The
derivation of the factor assumes that construction activity occurs 30 days per month, making the above
estimate somewhat conservatively high for total suspended particulate (U.S. EPA, 1995).
For the air environmental impact assessment study, MoEF recommended air quality model, Industrial
Source Complex Short Term (ISCST3-version 3) has been applied to predict ground level incremental
concentrations (GLCs).
Air Dispersion Model - (ISCST3)
Air dispersion modeling can be used to predict atmospheric concentrations of pollutants at specific locations
(receptors) over specific averaging times (i.e. annual, daily and hourly). An atmospheric dispersion model
accounts for emissions from a source; estimates how high into the atmosphere they will go, how widely they
will spread and how far they will travel based on temporal meteorological data; and outputs the pattern of
concentrations that will occur for various exposure periods, thereby providing the exposure risks for different
receptors.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 97.
Industrial Source Complex Short Term (ISCST3) air dispersion model was used to predict ground level
concentrations of the contaminants emitted from area and point sources at the site during both the
construction and operational phases.
In order to predict the air pollutants, the model requires the following input parameters:
Hourly meteorological data;
The source description including emission rates of the various contaminants, type of source (i.e. area
and point) and source emissions characteristics, as described above;
The receptor locations and grid layout will be based on the site coordinates, receptor locations and
nature of sources.
The incremental concentrations have been predicted for Suspended Particulate Matter (SPM) over an
averaging time of 24 hours. This case provides a prediction of the maximum concentrations at each receptor
for a 24–hourly period during which meteorological conditions were least conducive for dispersion of
pollutants and does not include the effect of precipitation.
Impact due to DG sets during Construction Phase
The total maximum demand load during construction phase is about to be 1000 kVA, which will be sourced
from DG sets to be used at project site. The capacity of DG sets is about 1000 kVA (500 kVA + 320 kVA
+ 180 kVA). During construction phase, diesel generator sets operated for back-up power supply are
identified as the source of gaseous and particulate emission. SO2, NOx, PM10, PM2.5 and CO emissions are
expected due to fuel combustion in generator sets.
Impact Prediction of DG set emission at Proposed Independent Floors Project
The specifications used for modeling of D.G. sets installed for power back-up in proposed project are given
in Table 5.4
Table 5:4 Diesel Generator Set Specifications
S. No. Particulars DG set Capacity
180 KVA
DG set Capacity
320 KVA
DG set Capacity
500 KVA
1 No of DG sets 1 1 1
3 No of stacks 1 1 1
4 Height of stack (m) 6 m above GL 6 m above GL 6 m above GL
5 Diameter of stack (m) 0.2 0.3 0.35
6 Exit velocity of gas (m/s) 20 25 25
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 98.
7 Exit gas Temperature (0C) 569 502 538
8 Sulphur Content in Fuel (%) 0.5 by weight % 0.5 by weight % 0.5 by weight %
9 Fuel Consumption (L/hr) 29.9 51.1 77
10 Density of Fuel (kg/m3) 856 856 856
11 Emission rate (g/s) for
each DG set
SO2 0.25 0.25 0.5
NOx 0.10 0.3 0.73
PM10 0.003 0.05 0.1
PM2.5 0.003 0.05 0.1
CO 0.03 0.035 0.07
The maximum predicted increment in concentrations of SO2, NOx, PM10, PM2.5 and CO due to D.G. sets are
estimated about 0.161 µg/m3, 6.684 µg/m
3, 5.609 µg/m
3, 2.527 µg/m
3 and 1.659 µg/m
3 respectively. The
details of predicted value with back ground air quality levels along with NAAQS are provided in Table 5.5
through Table 5.9 The spatial distribution of predicted pollutants concentration are also shown in Figure
5.1 through Figure 5.5. As the D.G. sets will be operated for back-up power supply only, hence the impact
of generation of gaseous pollutants in the ambient environment will be negligible.
Table 5:5 Ground Level SO2 (µG/M3) Concentration at Different Locations (24 hourly Averaged)
Concentration (g/m3) Maximum 24 Hour GLC NAAQS
SO2 Contribution from Site 18.49
80 µg/m3
SO2 Baseline (Maximum) 12.9
Total SO2 31.39
SO2 Contribution from Site to Maximum SO2 58.90%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 99.
Figure 5.1: Spatial Distribution of 24 Hours Average SO2 GLC (µG/M3)
Table 5:6 Ground Level NOx (µG/M3) Concentration At Different Locations (24 hours Averaged)
Concentration (g/m3) Maximum 24 Hour GLC NAAQS
NOx Contribution from Site 7.39
80 µg/m3
NOx Baseline (Maximum) 23.8
Total NOx 31.19
NOx Contribution from Site to Maximum NOx 23.69 %
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 100.
Figure 5.2: Spatial Variation of 24 hours averaged NOx GLC (µG/M3)
Table 5:7 Ground Level PM10 Concentration (µG/M3) At Different Locations (24 hours Averaged)
Concentration (g/m3) Maximum 24 Hour GLC NAAQS
Predicted Incremental PM10 Contribution 0.22
100 µg/m3
PM10 Baseline (Maximum) 106.39
Resultant PM10 106.61
PM10 Contribution from the Proposed
Project towards maximum background
PM10
0.21%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 101.
Figure 5.3: Spatial Distribution of 24 hours averaged PM10 GLC (µG/M3)
Table 5:8 Ground Level PM2.5 Concentration (µG/M3) At Different Locations (24 hours Averaged)
Concentration (g/m3) Maximum 24 Hour GLC NAAQS
Predicted Incremental PM2.5 Contribution 0.22
60 µg/m3
PM2.5 Baseline (Maximum) 65.47
Resultant PM2.5 65.69
PM2.5 Contribution from the Proposed
Project towards maximum background
PM2.5
0.33%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 102.
Figure 5.4: Spatial Distribution of 24 hours averaged PM2.5 GLC (µG/M3)
Table 5:9 Ground Level CO (µG/M3) Concentration at Different Locations (1 hours Averaged)
Concentration (g/m3) Maximum 1 Hour GLC NAAQS
CO Contribution from Site 2.21
4000 µg/m3
CO Baseline (Maximum) 1087
Total CO 1089.21
CO Contribution from Site to
Maximum CO 0.203 %
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 103.
Figure 5.5: Spatial Distribution of 1 hours averaged CO GLC (µG/M3)
5.4.4 Impact on Air Environment during Operation
The major air emissions expected during the operation phase will be due to the tailpipe emissions from
onsite traffic. To assess the quantitative impact, air quality modeling has been carried out using MoEF
approved model ISCST (Industrial Source Complex Short Term) version 3 for DG sets emission. The
vehicular emission model (CALINE) has been used to predict concentrations of specific vehicular
pollutants (CO and NOx).
Tailpipe emissions from On-site Traffic – Area Source
CO is considered as the primary pollutant anticipated as tailpipe emissions from light and heavy vehicles
traveling on the road. Apart from this, NOx also add pollutant load into the environment. Air quality impact
assessment due to additional traffic load on the main road connecting to the proposed site has been carried
out under worst-case scenario and assuming the maximum number of vehicles traveling per hour on these
roads. The CO and NOx concentrations prediction due to the proposed project is assessed with the help of
CALINE4 Model- A versatile dispersion model for predicting air pollutants levels near the road and is
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 104.
given by California Department of Transportation. The emission rate along with estimated vehicular rate is
given in Table 5.10.
Table 5:10 Vehicle Emission Statement
Sl.
No.
Category of
Vehicles
Expected No.
of Vehicles
Emission Rate (g/km)
PM* SO2
# NOX
* CO
2 Car 1397 0.004 0.0028 0.20 1.30
*- Emission Factor development for Indian Vehicles, ARAI Pune, #- The SO2 emission has been calculated based on Diesel
Consumption
Model Assumption
The emission load has been evaluated by mathematical modeling using ISCST 3, US-EPA software for DG
set and Caline 4 for Vehicular Movement. The average meteorological data of December month was
considered as met input for model study. The flue gas from DG set with 30 meter stack height shall travel
up to 1.5 km approximately. Also the dispersion of vehicular emission is limited to 100 m, after that particle
will get stabilized on the earth surface due to their specific settling velocity. Hence, the extent of the
modeling is limited for 2 km from the location of DG set. The incremental GLCs due to vehicular
movement have been calculated at a distance of 50m from the road to present the worst case scenario. The
output results are tabulated in Table 5.11 below.
Impact due to vehicular Movement
The proposed development will have the 1397 nos. car parking facility for the residing population. The
impact of vehicular movement on ambeint air quality has been predicted by using Caline 4. The maximum
resultant value of ground level concentrations (GLCs) of pollutants due to vehicular movement are provided
below in Table 5.11.
Table 5:11 Max. Resultant GLCs due to Vehicular Movement
Sr. No. Pollutant Unit Max. Baseline
GLCs
Max. Incremental
GLCs due to
Vehicular
Movement*
Max. Resultant
GLCs
1. PM10 µg/m3 106.39 0.54 106.93
2. PM2.5 µg/m3 65.47 0.23 65.7
3. SO2 µg/m3 12.9 0.07 12.97
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 105.
Sr. No. Pollutant Unit Max. Baseline
GLCs
Max. Incremental
GLCs due to
Vehicular
Movement*
Max. Resultant
GLCs
4. NOX µg/m3 23.8 3.137 26.937
5. CO mg/m3 1087 0.056 1087.056
*- Incremental GLCs at exposure distance of 50m from the road
Impact due to DG sets
The total demand load is 6.4 MW, which will be sourced from Dakshin Haryana Bijlee Vitran Nigam
Limited (HVPNL). During operation phase, diesel generator sets operated for back-up power supply are
identified as the only major sources of gaseous and particulate emission. SO2, NOx, PM10, PM2.5 and CO
emissions are expected due to fuel combustion in generator sets. To serve as a back-up power supply for
proposed project, power is to be supplied through 5 D.G. sets.
Impact Prediction of DG set emission at Proposed Independent Floors Project
The specifications used for modeling of D.G. sets installed for power back-up in proposed project are given
below in Table 5.12.
Table 5:12 Diesel Generator Set Specifications
S. No. Particulars
Values Values
1500 kVA 500 kVA
1 No of DG sets 4 1
2 No of stacks 4 1
3 Height of stack (m) 30 30
4 Diameter of stack (m) 0.35 0.35
5 Exit velocity of gas (m/s) 65 70
6 Exit gas Temperature (0C) 392.4 523.6
7 Sulphur Content in Fuel (%) 0.25 by weight % 0.25 by weight %
8 Fuel Consumption (L/hr) 309 77
9 Density of Fuel (kg/m3) 856 856
10 Emission rate (g/s) SO2 0.0243 0.0082
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 106.
NOx 1.023 0.34
PM10 0.5112 0.05
PM2.5 0.066 0.023
CO 0.39 0.13
The maximum predicted increment in concentrations of SO2, NOx, PM10, PM2.5 and CO due to D.G. sets are
estimated about 0.161 µg/m3, 6.684 µg/m
3, 5.609 µg/m
3, 2.527 µg/m
3 and 1.659 µg/m
3 respectively. The
details of predicted value with back ground air quality levels along with NAAQS are provided in Table
5.13 through Table 5.17 .The spatial distribution of predicted pollutants concentration are also shown in
Figure 5.6 through Figure 5.10. As the D.G. sets will be operated for back-up power supply only, hence
the impact of generation of gaseous pollutants in the ambient environment will be negligible.
Table 5:13 Ground Level SO2 (µG/M3) Concentration (24 hourly Averaged) due to DG sets
Description Maximum 24 Hour GLC
Concentration (g/m3)
NAAQS
SO2 Contribution from Site 0.161
80 µg/m3
SO2 Baseline (Maximum) 12.9
Total SO2 13.061
SO2 Contribution from Site to Maximum SO2 11.84%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 107.
Figure 5.6: Spatial Distribution of 24 Hours Average SO2 GLC (µG/M3)
-2000 -1500 -1000 -500 0 500 1000 1500 2000
-2000
-1500
-1000
-500
0
500
1000
1500
2000
0.007
0.014
0.021
0.028
0.035
Table 5:14 Ground Level NOx (µG/M3) Concentration (24 hours Averaged) due to DG sets
Description Maximum 24 Hour GLC
Concentration (g/m3)
NAAQS
NOx Contribution from Site 6.684
80 µg/m3
NOx Baseline (Maximum) 23.8
Total NOx 34.484
NOx Contribution from Site to Maximum NOx 19.38%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 108.
Figure 5.7: Spatial Variation of 24 hours averaged NOx GLC (µG/M3)
-2000 -1500 -1000 -500 0 500 1000 1500 2000
-2000
-1500
-1000
-500
0
500
1000
1500
2000
1.2
2.4
3.6
4.8
6
Table 5:15 Ground Level PM10 Concentration (µG/M3) (24 hours Averaged) due to D.G. Sets
Description Maximum 24 Hour GLC
Concentration (g/m3)
NAAQS
Predicted Incremental PM10 Contribution 5.609
100 µg/m3
PM10 Baseline (Maximum) 106.39
Resultant PM10 111.999
PM10 Contribution from the Proposed Project towards
maximum background PM10 5.00%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 109.
Figure 5.8: Spatial Distribution of 24 hours averaged PM10 GLC (µG/M3)
-2000 -1500 -1000 -500 0 500 1000 1500 2000
-2000
-1500
-1000
-500
0
500
1000
1500
2000
0.9
1.8
2.7
3.6
4.5
5.4
Table 5:16 Ground Level PM2.5 Concentration (µG/M3) (24 hours Averaged) due To D.G. Sets
Description Maximum 24 Hour GLC
Concentration (g/m3)
NAAQS
Predicted Incremental PM2.5 Contribution 2.527
60 µg/m3
PM2.5 Baseline (Maximum) 65.47
Resultant PM2.5 67.997
PM2.5 Contribution from the Proposed Project towards
maximum background PM2.5 3.72%
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 110.
Figure 5.9: Spatial Distribution of 24 hours averaged PM2.5 GLC (µG/M3)
-2000 -1500 -1000 -500 0 500 1000 1500 2000
-2000
-1500
-1000
-500
0
500
1000
1500
2000
0.4
0.8
1.2
1.6
2
2.4
Table 5:17 Ground Level CO (µG/M3) Concentration (1 hours Averaged) due to D.G. sets
Description Maximum 1 Hour GLC
Concentration (g/m3)
NAAQS
CO Contribution from Site 2.21
4000 µg/m3
CO Baseline (Maximum) 1087
Total CO 1089.21
CO Contribution from Site to Maximum CO 0.203 %
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 111.
Figure 5.10: Spatial Distribution of 1 hourly averaged CO GLC (µG/M3)
-2000 -1500 -1000 -500 0 500 1000 1500 2000
-2000
-1500
-1000
-500
0
500
1000
1500
2000
0.3
0.6
0.9
1.2
1.5
5.5 IMPACT ON NOISE ENVIRONMENT
5.5.1 Impact on Noise Environment during Construction Phase
Noise Quality
The noise emission sources during construction phase will include construction machineries/equipments to
be employed at site.
The expected noise levels from the operation of equipment and machineries are provided in Table 5.18.
Table 5:18: Noise levels Generated from Construction Equipment
Name of Source Noise Level at 16 m (50 ft) from source in dB (A)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 112.
Name of Source Noise Level at 16 m (50 ft) from source in dB (A)
Back Hoe/Loader 85
Concrete Mixer Truck 81
Mobile Cranes 81
Dump Truck 89
Generator 75
Pile Driver 101
Jack hammer 90
Prediction Model
For an approximate estimation of propagation of noise in the ambient air from the area or point source, a
standard mathematical model for sound wave propagation has been used which is as follows:
Noise (Receptor) = Noise (Source) - 20 Log [distance (Receptor) / distance (Source)]
The incremental noise level during the construction phase will be predicted using the CPCB approved noise
model DHAWANI, applicable for stationary point sources. For the modeling purposes, worst case scenario
has been considered assuming a flat terrain and absence of sound absorbers.
Results and Discussion
Modeling results indicate that the cumulative noise level is expected to be within the permissible AAQSRN
standards of 55 dB(A) at a distance of about 2000 m. The predicted noise levels are without mitigation
measures and it is assumed that with the adoption of the mitigation measures noise levels will be
further restricted within very short distances from the source.
With respect to occupational exposure, the permissible threshold is 90 dB (A) for 8 hours per day. Thus,
based on the modeling results, it can be concluded that all sensitive receptors (i.e. labour colonies) will be
located beyond 200 meters from the noise generating sources during construction activities. Figure 5.11
shows the spatial variation of incremental noise level during construction phase without any control.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 113.
Figure 5.11: Spatial Variation of Incremental Noise Level during Construction Phase without Control
5.5.2 Impact on Noise Environment during Operation Phase
Impact due to DG sets
The DG sets are proposed to be installed at project site during the construction phase as per the requirment.
However, the DG sets will be provided with acoustic enclosures so as to keep the noise level within the
prescribed standards.
The major noise emissions expected during the operation phase will be due to the operation of DG sets.
Prediction Model
For an approximate estimation of propagation of noise in the ambient environment due to DG set, a
standard mathematical model for sound wave propagation has been used which is as follows:
Noise (Receptor) = Noise (Source) - 20 Log [distance (Receptor) / distance (Source)]
The incremental noise level due to the operation of the DG set installed has been predicted using the CPCB
approved noise model DHAWANI, applicable for stationary point sources. For the modeling purposes,
worst case scenario has been considered assuming a flat terrain and absence of sound absorbers.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 114.
The predicted incremental noise levels without control measures have been presented as noise contours in
an area of 1000m x 1000m as shown in Figure 5.12. Modeling results indicate that the cumulative noise
level is expected to be within the permissible AAQSRN standards of 55 dB(A) at a distance of about 200 m
from the source location.
Figure 5.12: Spatial Variation of DG-set Noise Levels around the Project Site during Operation Phase
without Control
DG sets will be used only in emergency for back up supply. It will be ensured that the DG sets are enclosed
in acoustic enclosures and comply with the prescribed CPCB norms.
5.6 IMPACT ON WATER ENVIRONMENT
5.6.1 Impact on Water Environment during Construction Phase
Water resources
SURFACE WATER RESOURCES
The water requirement during construction phase will mainly comprise of water for construction purposes
and water demand for labourers. The water during construction phase will be sourced through tanker water
supply for drinkable purpose. There will be no extraction of water from surface water resources for using in
the proposed development; hence no impact on surface water resources is envisaged.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 115.
GROUNDWATER RESOURCES
The proposed development would not extract any ground water resources, as the water requirement during
the construction phase will be met through tanker water supply from STP of HUDA for construction
purpose.
Water Requirement
The water requirement during construction phase can be broadly divided into two categories.
Construction activities (180 KLD) which is the peak period demand during construction phase
Domestic water requirement for labourers (70 KLD) (considering 1200 construction labors during the
peak construction period @ 45 lpcd water demand as per CPHEEO and 200 will be residing in labour
camp @ 86 lpcd as per Manual on Construction & large building projects)
Wastewater Generation
Wastewater stream during construction period shall be from transit labour colonies and wastewater from
construction activities. Wastewater generation during construction phase would be around 57 KLD.
Construction activities for the proposed development can have minor impact on hydrology and ground water
quality of the area, should the construction waste leaches into ground. Potential impacts on the hydrology and
ground water quality have been discussed as under.
Soil runoff from the site leading to off-site contamination (particularly during rainy season).
Improper disposal of construction debris leading to off-site contamination of water resources.
Unaccounted disposal of domestic wastewater from temporary labour camps.
Spillage of oil & grease from the vehicles and wastewater stream generated from on-site activities
such as vehicles washing, workshop etc.
Construction & Development of site
Development of the proposed site could lead to stockpiling and excavation activity on site, thereby causing
erosion of base soil. The run off from the site may contain high quantity of suspended solids (SS). The impact
of runoff may not be very significant except during rainy season. Further construction of garland drains will
reduce the runoff from the stockpiles.
Bored piling may be carried out for building structures. Bore piling, if used, requires the use of chemical
lubricants, which generates a wastewater stream requiring treatment before discharge.
Site Workshop
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 116.
The repair and maintenance of equipments/vehicles on site would generate waste containing oil and grease.
The wastewater stream would also be generated from vehicle washing. The impact can be mitigated to a great
extent by installing oil and grease traps during construction phase.
Construction of roads & parking areas
The impact from the road construction depends on both the construction practices and the type of material
used. Construction waste of electrical installation, DG sets, painting and flooring is likely to create significant
impact. This type of waste would be stock piled and disposed properly.
Labour Colony
During construction phase, wastewater shall be generated from labour colony. High levels of BOD, SS,
Nitrogen and E. coli would characterize wastewater generated. Significant water quality impact will occur, if
the sewage is disposed without any prior treatment. It is proposed to deploy local population from nearby
villages to the maximum extent possible.
5.6.2 Impact on Water Environment during Operation Phase
5.6.2.1 Water Requirement
During the operation phase, the ultimate water requirement considering all planned developments is
expected to be 480 KLD. This includes water requirement for domestic purpose, water for landscape
development and for DG set cooling purposes of the entire development, once fully become operational.
The estimates have been worked out on the basis of norms as part of the “Manual on norms and Standards
for Environment Clearance of Large Construction Projects, MoEF”, and CPHEEO manual on “Water
Supply and Treatment”.
The water requirements are planned to be met through public supply and if in case, ground water extraction
is required, due permission will be taken from the CGWA. The project proposes to recycle treated
wastewater for flushing, landscaping thereby reducing the fresh water requirement and is expected to be in
the order of 249 KLD. The ultimate water demand estimated for various activities within the proposed
development, is as shown in Table 5.19.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 117.
Table 5:19: Ultimate Water Requirements for Proposed Project
S. No. Description No. of
Units
Total Population Water
Requirement per
Person
Total Water
Requirement
Total Water
Requirement for
Domestic Use
Total Water
Requirement for
Flushing Use
Waste water
Generation
(80%)
Description Nos. (LPCD) (LPD) (LPD) (LPD) (LPD)
A Water Requirement for Residential
1. Independent Floors 552 Residential 2484
135 345900 223560 111780 276720
Visitors 228
45 6840 3420
Security/ Staff 20
15 100 200
Sub Total 230500 115400
B Water Requirement for Other Uses
1. Landscape 9710 sqm @ 5lit/sqm 48550 - - -
2. Road Maintenance/
Arboriculture
18066 sqm @ 3lit/sqm 54198 - - -
3. Other Construction
Acivities
- - 31000
Total Domestic Water Requirement (A+B) 479648
230500 115400 276720
say in KLD 480 231 115 277
1.1.1.1
1.1.1.1
1.1.1.1
1.1.1.1
1.1.1.1
1.1.1.1
1.1.1.1
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 118.
Total Domestic Water Required (KLD) 480
Net Potable Water Required (KLD) 231
Net Treated Effluent Water Required (KLD) 249
STP
A Wastewater Generation (KL) 277
B Say Proposed Capacity of STP (KL) 320
C Treated Water Available (KLD) after Biological Unit 249
Reuse for Horticulture 49
Reuse for Flushing 115
Reuse for Road Maintenance /Arboriculture 54
Reuse for other construction activities 31
D Total Treated Water Required (KLD) 249
(*Source: MoEF Manual on norms and standards for Environmental Clearance of large construction projects,
CPHEEO Manual on Water Supply & treatment) Wastewater Generation and Characteristics
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 119.
The total sewage generated from the proposed project is expected to be in the order of 277 KLD which will
be treated in STP of capacity 320 KLD to be installed at project site.
The total reclaimed wastewater will be 249 KLD out of which 320 KLD will be used to meet the flushing
requirement, 54 KLD for Road Maintenance/Arboriculture, 49 KLD for horticulture/landscaping
requirement and 31 KLD for Other construction activities.The water balance for the proposed development
is as shown in Figure 5.13.
For optimal management (treatment and reuse), wastewater generation has been categorized under two
sources:
1. Gray water (wastewater generated from various activities, except for the wastewater produced from
the toilet flushing)
2. Black water (wastewater generated from the toilet)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 120.
Figure 5.13: Water Balance for Proposed Project
DOMESTIC WATER REQUIREMENT (346 KLD)
(Fresh Water 231 KLD) + (Recycled Treated Water 115KLD)
Fresh Water Requirement (A) 231 KLD Treated Waste Water Reused (B) 249 KLD
Domestic Other than Flushing
231 KLD Flushing
115 KLD
Road
Maintenance/
Arboriculture
54 KLD
Horticulture
49 KLD
STP Proposed ( Design Capacity= 320KLD)
Horticulture
49 KLD
Flushing
115 KLD
(Sewage Generation 80% of Domestic Water &
Flushing water supply) = 277 KLD
90 % recovery, 249 KLD
TOTAL WATER REQUIREMENT (A + B)= 480 KLD
UV Treatment 249 KLD
Road Maintenance/
Arboriculture 54 KLD
Other
construction
activities
31 KLD
Other construction
activities
31 KLD
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 121.
Treated wastewater is expected to have characteristics as shown in Table 5.20.
Table 5:20: Expected Treated Wastewater Characteristics
Parameters
Treated Effluent Quality
mg/l
pH 6.5-7.5
Biochemical Oxygen Demand (BOD5) < 10 mg/l
Chemical Oxygen Demand (COD) < 30 mg/l
Suspended Solids < 5 mg/l
Oil & Grease Absent
(Source: Manual on Sewerage and Sewage Treatment, CPHEEO)
The waste water will be treated to meet the permissible limits as per CPCB guidelines as given in
Table 5.21 However, the proposed development will ensure zero discharge of treated effluent.
Table 5:21: Standards for Effluent Disposal
S.N Parameter Into inland
surface waters
Into public
sewers, mg/l
On land for
irrigation, mg/l
1 pH 5.5-9.0 5.5-9.0 5.5-9.0
2 BOD for 5 days at 20 oC, mg/L 30 350 100
3 Chemical Oxygen Demand, mg/L 250 - -
4 Suspended Solids, mg/L 100 600 200
5 Total Dissolved Solids, mg/L 2100 2100 2100
6 Temperature, mg/L 40 45 -
7 Oil and grease, mg/L 10 20 10
8 Phenolic compounds, mg/L 1 5 -
9 Cyanides, mg/L 0.2 2 0.2
10 Sulphides, mg/L 2 - -
11 Fluorides, mg/L 2 15 -
12 Total residual chlorine, mg/L 1 - -
13 Pesticides, mg/L - - -
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 122.
14 Arsenic, mg/L 0.2 0.2 0.02
15 Cadmium , mg/L 2 1 -
16 Chromium (Hexavalent) , mg/L 0.2 2 -
17 Copper, mg/L 3 3 -
18 Lead, mg/L 0.1 1 -
19 Mercury , mg/L 0.01 0.01 -
20 Nickel , mg/L 3 3 -
21 Selenium , mg/L 0.05 0.05 -
22 Zinc, mg/L 5 15 -
23 Chlorides, mg/L 1000 1000 600
24 Boron, mg/L 2 2 2
25 Sulphates, mg/L 1000 1000 1000
26 Sodium ( 9%), mg/L - 60 60
27 Ammonical Nitrogen, mg/L 50 50 -
28 Radioactive materials 10-7
10-7
10-8
29 Alpha emitters (milicurie/ml) 10-6
10-6
10-7
The impact on water environment will not be significant as the proposed development would not
extract groundwater resources. However, if in case of any withdrawal from ground water, due
permission will be taken from CGWA.
The proposed development is not likely to have any impact on the water quality of the area as it is
committed not to discharge any effluents outside the developed area and ensured zero discharge of
effluent. Thus, full reutilization of treated effluent will be done on site through landscaping, flushing,
Road maintenance and for other construction activities.
5.7 IMPACT ON LAND ENVIRONMENT
5.7.1 Impact on Land Environment during Construction Phase
The proposed development will not have an impact on soil productivity as the requirement of soil
during construction phase will be met within the said area.
The proposed site is slightly undulating with a variation of about 6.5 m between the highest and
lowest contour level, thereby reducing the leveling requirement. Once the leveling of the land is done,
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 123.
the construction of buildings for various purposes like residential and commercial, It buildings and
social infrastructural facilities will be carried out, which will entail excavation of material.
Total excavated earth = 1,50,000 cum.
The cut and fill will be balanced by volume of earth which would be excavated. No extra earth will be
required and hence no impact on soil productivity.
The proposed development will not have an impact on soil quality as the construction and demolition
waste, chemical waste and municipal solid waste generated during the construction phase will be
handled properly.
The soil of the proposed site may be affected due to improper waste disposal on the site. Wastes
which are likely to be generated during the construction phase include the following:
5.7.1.1 Soil Erosion
Erosion of soil may occur on account of vegetation and large-scale excavation activity for
construction. Site selected for the project has sparse vegetation; hence impact owing to removal of
vegetation would be minimal, however construction and associated activities would expedite erosion
if not managed properly. The following are the major factors determining the soil erosion potential.
Topography /Gradient of Slope: Erosion and gradient have a direct relationship. The steeper the
gradient, higher is the rate of erosion and vice versa. The project site has moderate topography with
slight variation of highest and lowest point. The existing ground levels (EGL) at the time of the
topographical survey varies from RL 237.5 (lowest) to 244.0 m (highest). The site slopes slightly
from east towards west.Hence, the soil erosion potential due to existing topography and due to the
excavation of basement, are almost nil.
Soil Properties: The vulnerability of a piece of land to soil erosion depends on the physical and
chemical characteristics of the soil. The sandy silty texture of the soil at the project site indicate soil
erosion potential of high intensity.
Rainfall Pattern: More precipitation means more surface flow, and more surface flow means more
area vulnerable to erosion by running water. The maximum mean monthly rainfall for the year 2003 is
495.6 mm in the month of July. The soil erosion potential at the site due to the rainfall of the region is
of the medium intensity.
Construction and Demolition Waste
The proposed development will involve generation of construction and demolition (C&D) waste. The
waste generated from various other construction activities contain a mixture of inert and non-inert
material, which include waste timber formwork, spent concrete and cement screening, material and
equipment wrappings.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 124.
Chemical Wastes
Vehicle servicing will likely be the primary source of chemical wastes during the construction period.
The majority of chemical waste will comprise of waste oils and solvents.
Municipal Waste
The municipal waste generated during the construction phase will comprise of waste generated from
the temporary labour camps.
Workers engaged during construction phase will generate municipal solid wastes such as food wastes,
packaging and wastepaper. The waste from labor camps would be mainly household domestic waste
and it is estimated to be 0.170 TPD.
The waste generation during construction phase will not have any impact as the waste generated from
labour camps will be predominantly organic in nature and will be stored within the construction area
for biodegradation and covered with soil layer (daily cover) on regular basis.
5.7.2 Impact on Land Environment during Operation Phase
During the operation phase, carefully designed landscaped areas and plantation will be maintained.
No significant impact is expected on the soils on and around the site, due to the following
management measures:
i. All solid and hazardous wastes from the project will be properly collected, stored and disposed.
An integrated solid waste management plan will be developed as per the details given in
Chapter 6.
ii. Wastewater will be treated and disinfected and reused for various purposes on site and will not
be discharged outside the premises.
iii. Storm water will be used to recharge the aquifer after filtration of silt and sand.
iv. Secondary containment will be provided in fuel, oil and other material storage areas.
v. The entire site area will be well paved and thus there will be no leaching of any substances in
case of spills.
Hence, no negative impact on soil quality in the study area is expected due to the project activities.
Impacts due to Solid Waste Disposal
During operation phase, solid waste will be generated from various activities, which have been
quantified on the basis of Manual for Municipal solid waste management and handling (MSW Rules,
2000) and as per the norms prescribed by Central Public Health and Environmental Engineering
Organization (CPHEEO) for biomedical waste, sewage sludge and industrial waste and is shown in
Table 5.22.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 125.
The generated solid waste will be disposed off and due to the improper disposal of waste the soil of
the proposed site and the surrounding areas is likely to be affected.
Table 5:22: Expected Solid Waste Generation
S. No Description Population
(Nos.)
Area (sq
M)
Rate @ SW
Generation
Total Solid
Waste
Generation (kg)
1 Residential
1.1 Plots (552 Nos du.) 2484
0.4 kg/capita/day 993.6
1.2 Operation & Maintenance Staff 20
0.1 kg/capita/day 2
1.3 Visitors (20% of total
Residential) 228
0.1 kg/capita/day 22.8
2 Landscape Waste
2.1 Landscape Area under
Residential 9710 0.003 kg/m²/day 29.13
3 Sweeping from Road and
Other Hard Paved Area 18066 0.01 kg/m²/day 180.66
4 Sludge Generation from STP
20
Total SW Generation
say
1248.19
or 1.25 TPD
The total waste generated from the proposed project is expected to be about 1.25 TPD comprising of
municipal solid waste, and sewage sludge. Proper segregation, collection, storage, treatment and
disposal facilities for various categories of waste will be provided in accordance with the regulatory
requirements.
MSW including horticulture waste will be generated during the operation phase and will be handled
as per the Municipal Solid Waste Management & Handling Rules, 2000. Segregation at source will be
introduced with bio-degradable and non recyclable/non-biodegradable waste to be stored and
collected separately. The biodegradable waste will be stored and transported to nearest designated
waste storage bins; where as the non recyclable and non biodegradable waste will be disposed off to
authorized recyclers.
The sewage sludge will be generated from the sewage treatment plant and will be disposed off. The
sludge from the water treatment plant could be used in horticulture.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 126.
During this phase, environmental impact from solid waste disposal can typically include
contamination of soil, ground water, surface water and air quality. Solid waste, if disposed improperly
can cause following impact on the environment.
Ground water contamination by leachate generated by non-scientific dumping.
Surface water contamination by the run off from the dumping site
Bad odor, Pests, rodents and wind blown litter in and around the dumping site.
Generation of inflammable gases (e.g. Methane)
Fires within the waste dump.
Bird menace above dumping site which affects flight of air craft
Erosion and stability problem relating to slope of the dumping site
Epidemic through stray animals
Increased concentration of acidity in the surrounding soil
Release of green house gases.
Impacts may also result from improper siting, inadequate design and poor operation. However for the
proposed project, impacts from waste disposal would not be significant, since waste would be
converted to compost at the project site using suitable composting technique. Rejects from compost
along with non-recyclable and non-compostable fraction of waste would be disposed as per the
Municipal Solid Waste (Management and Handling) Rules, 2000.
Impacts due to E-Waste
Approximate 3.59 Tonns per Annum of e-waste will be generated in a worst case scenario from the
proposed development that will be stored at a warehouse to be setup within site and will be sent to
authorized recyclers or e-waste processing plants for treatment as per E-Waste [Management &
Handling] Rules, 2010. Table 5.23 shows the E-waste generated due to the proposed development.
Table 5:23 E-waste Generated – Independent Floors Project
Landuse
No. of
Dwelling
Units
Computer/
Laptop TV Refrigerator
Cell
Phone Telephone CFL
Floors 552 110.4 37 37 276 110.4 276
Weight of Item (Kg.) 10 20 45 0.108 0.25 0.1
Quantity of E-Waste
Generated / Year (Kg.) 1104 740 1665 29.808 27.6 27.6
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 127.
Total Quantity of E-Waste
Generated (Tone/ Year ) 3.594008 or 3.59
5.8 IMPACT ON BIOLOGICAL ENVIRONMENT
Potential primary and secondary impacts from the proposed project on the biological environment
have been identified and noted below:
The significance of ecological impacts is evaluated based on the criteria set forth:
Habitat quality
Species affected
Size/abundance of habits/organisms affected
Duration of impacts
Magnitude of environmental changes
However this being rapid EIA impacts is ranked here as “minor”, “moderate” or “severe”, although in
a few cases a ranking may be minimal. The ranking of a given impact will vary based on the criteria
used. For example, an impact might be ranked as “minor” if it affected only common species and
habitat, or if it affected small number of individuals or small area, whereas it might be ranked as
“severe” if it affected rare species or habitat of large number of individuals or large area.
5.8.1 Impact during Construction Phase
The potential impacts of project on terrestrial ecological may be due to:
Site development.
Noise & disturbance.
Noise, air pollution & other disturbances: Air, noise and visual disturbance may be generated during
the site development that can affect the behavior of fauna of the adjacent habitats. Due to agriculture
nature of surrounding areas, the limited conservation importance of the species recorded, and the
temporary nature of impacts, potential impacts to fauna from this source are ranked minor. These
activities and the resulting impacts on the existing ecology would be mitigated adopting
comprehensive EMP.
Most fauna recorded in the study area are disturbance tolerant. Construction will mainly take place in
project areas, where biodiversity is highly improvised. Fauna inhibiting plantation near construction
site may be temporarily affected by noise and disturbance generated during site formation and
construction. However, as alternative habitats are available in and near this area and disturbance is
going to be confined to construction period. The impacts from noise, air, and other disturbance during
the construction stage on terrestrial fauna are ranked as minor.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 128.
Aquatic
As mentioned earlier, there being no permanent water body of ecological significance within the
immediate impact zone of the study area, therefore there would be no aquatic impact.
5.8.2 Impact during Operation Phase
This section of the report considers the potential impacts (like; air and noise pollution, wastewater and
other disturbances) of project operation phase on terrestrial ecology.
Potential impacts of project operation include long-term air and noise pollution and disturbance
generated by area lighting and traffic. The surrounding study area has limited fauna and flora and is
largely agricultural in nature. Most of the terrestrial fauna in the study area is dweller of typical rural
setting. The impact of project activities on these has been ranked as minimal. In addition, the project
includes development of green areas within the project site.This will provide habitat for the terrestrial
and avifauna of the surrounding area.
5.9 IMPACT ON SOCIO-ECONOMIC ENVIRONMENT
5.9.1 Positive Impacts
Better Physical Infrastructure
At present the Project area is in lack of adequate physical infrastructure. Good quality roads,
communication and transport, and water facilities in the project area are missing. The project will
involve road upgrading and better power and water supply in the area. This would enhance the
existing infrastructure and also encourage further development in the surroundings. It is likely that
with better communication and accessibility infrastructure, there will be increase in the number of
local people indulging in trade, commerce and allied services.
BETTER SOCIAL INFRASTRUCTURE
The design of proposed project has recognised the important role that social infrastructure plays in
the creation of strong, healthy and sustainable communities. Sustainable communities require good
schools, good health services, good parks, transport choices, flourishing businesses as well as a range
of housing types. The design includes Independendent Floors development.
Employment Potential:
During the Construction period, there will be large requirement of workers thus providing
opportunities for employment. The proposed project will provide employment to local residents.
Besides this, local building material industries will supply cement, sand stone and other materials. The
construction of project will increase the movement of workers and people in the area, providing a
greater exchange of technology and business opportunities. Generation of additional economic
activity is expected to create employment opportunities for the local population during operation
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 129.
phase. The service industry will have a corresponding increased market base. Money spent within the
local economies will have a multiplier effect as the money is spent throughout the community. This
will improve the business base in the region and will lead to additional services being provided.
Other Benefits
Benefits to women: The proposed facility would generate jobs for the women laborers during
construction as well as operation phase. The women would also have the opportunities for
administrative or other supervisory jobs, closer to their place of stay.
Increase in land value: With the proposed project coming in the area the prices of the land will
increase considerably. Hence the proposed project will have beneficial impact.
Better health and educational facility: The proposed facility is well planned and would be designed
to incorporate the state of art health facility and therefore would provide emergency services.
Similarly Private educational resources in the study area would provide for the better education.
Wider economic growth: This project will increase the economic activities around the area, creating
avenues for direct/indirect employment in the post project period. There would be a wider economic
impact in terms of generating opportunities for other business like workshops, marketing, repair and
maintenance tasks etc.
Aesthetics Environment: The architectural character of the new building, the vistas and landscaped
areas created would improve the aesthetics of the area.
Additional Revenues: The development of land for any purpose creates both an immediate demand
for services and a flow of revenues to the community from a variety of sources. For example property
tax, licenses and permits fee etc.
5.9.2 Negative Impacts
Traffic and Transport: During the construction phase, truck movement due to construction activities
will take place. In order to minimize any inconvenience that may arise, the movement of trucks would
be allowed during night and non-peak hours. During the operation phase, the traffic in the area is
likely to increase. This may lead to traffic congestion and inconvenience for pedestrians and residents
accessing the localities. The traffic study and Transportation Management Plan being developed for
the project will mitigate these impacts to a large extent
Transit Labour population: Labourers for the project would be from surrounding areas. About 1200
labourers would be working on the site and most of them would be on contract or from the neighbouring
settlements. No significant pressure on local infrastructure is envisaged if a small percentage of
labourers settle in and around the site during construction phase.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 130.
5.9.3 Negligible Impacts
Resettlement & rehabilitation issues: Since there is no existing settlement on the proposed project
area, hence there is no issue of resettlement or rehabilitation.
Demography: During construction and operation phase, some of the work force is likely to be
nonlocal. It is highly unlikely that this will affect or alter the existing demographic profile and
population density.
Impact on historical, archeological & architectural sites: There are no historical or archeological
monuments of significance within 10 kilometers radius of the project and hence no negative impact in
this regard is anticipated.
5.10 IMPACT ON HISTORICAL, ARCHAEOLOGICAL AND ARCHITECTURAL SITES
The proposed site and its surrounding areas do not have archaeological structures, hence no such
demolition of any structures are envisaged due to the proposed development.
5.11 SUMMARY OF IMPACTS
A summary of likely impacts due to proposed project is noted in Table 5.24.
Table 5:24 Summary Matrix of Predicted Impacts due to Proposed Project
S.
No Components Activities Predicted impacts Extent of Impacts
CONSTRUCTION PHASE
1. Ambient Air
Quality
-Dust emissions from
site preparation,
excavation, material
handling and other
construction activities
at Site.
Minor Negative
impact inside the
premises. No
negative impact
outside the site.
Impacts are temporary during
construction phase. Impacts
will be confined to short
distances, as coarse particles
will settle within the short
distance from activities.
2. Noise
-Noise generated from
construction activities
and operation of
construction
equipment
Minor negative
impact near noise
generation sources
inside premises.
No significant
impact on ambient
noise levels at
sensitive receptors.
Temporary impacts during
construction phase. No blasting
or other high intensity noise
activities envisaged. Baseline
noise is already higher than the
standards. Contribution of
noise during the operational
phase will be confined in time
and space
3. Water quality
-Surface runoff from
project site
-Oil/fuel and waste
Minimal due to
effective EMP
proposal
Impact will be temporary.
Local labour will be employed
to reduce size of labour camps.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 131.
S.
No Components Activities Predicted impacts Extent of Impacts
spills.
-Improper debris
disposal
-Discharge of sewage
from labour camp.
No perennial surface water
resource adjacent to site.
Labour colonies shall be
provided potable water for
drinking.
4 Landuse and
Aesthetics
-Land development
Permanent positive
impact
The project has ample open
areas and green spaces, with
sustainable infrastructure plan
that will enhance the visual
appeal of the area.
5 Topography
and Geology
-Existing site is barren
land with undulating
slopes and not highly
productive.
No Significant
Impacts
No impacts on topography and
no deposits of minerals on site
leading to loss of revenue.
Building will be designed as
per IS standards for earthquake
protection.
6. Soil
-Construction activity
leading to topsoil
removal and erosion.
Minor negative
impact Temporary
7
Ecology
Flora and
Fauna
-Habitat disturbance
during construction
activity
Minor negative
impact
The site and adjacent areas do
not have any significant flora
and fauna diversity and
density. No endangered species
recorded on site.
8 Socio-
economy
-Increased job
opportunity for locals.
Economy related to
residential &
commercial real estate
development, material
supply etc. expected to
boom.
Overall positive
impact
9 Traffic
Pattern
-Haul Truck movement
and possibility of
traffic congestion
outside site on the
highway.
Minor negative
Impact
OPERATION PHASE
1. Ambient Air
Quality
-Particulate and
gaseous emissions
from DG sets &
operation of boiler and
Minor negative
impact inside the
premises from
onsite cars.
DG sets will be used only as
back up and would be required
a maximum for 8 hours a day.
A higher stack is
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 132.
S.
No Components Activities Predicted impacts Extent of Impacts
vehicle movement Negative impact
outside site from
DG sets.
recommended for both to DG
and boiler in the EMP.
2. Noise
-Noise from vehicle
movement and
operation of diesel
generator sets during
power failure.
Minor negative
impact inside
premises.
No significant
impact at sensitive
receptors.
Contribution of noise from the
project during operational
phase will be limited to minor
increase.
3. Water
Quality
-Oil/fuel and waste
spills.
-Discharge of sewage.
-Discharge of
contaminated storm
water
No significant
adverse impact
4. Water
Availability
-Use of 231 KLD fresh
water requirement at
peak
Minor negative
impact Public supply
5 Soils
-Storage and disposal
of solid and hazardous
wastes
-Discharge of sewage
-Fuel and material
spills
-Pesticides use
No negative
impact -
6.
Ecology
Flora and
Fauna
-Landuse change
-Discharge of
wastewater to surface
water bodies
No negative
impact
It is open space with sparse
vegetation. In whole study area
no significant flora and fauna
is recorded.
7. Socio-
economy
-Increased job
opportunity for locals
in the site for general
services inside the
project.
-Project will involve
road upgrading, better
power supply, water
Overall positive
impact --
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 133.
S.
No Components Activities Predicted impacts Extent of Impacts
source and other
infrastructure facilities
etc.
8. Traffic
Pattern
-The project is likely to
add to the traffic on
HUDA Sector Road
Moderate Negative
Impact
Traffic management measures
and additional road
infrastructure will be planned
by the developers with the
consent of the concerned
authorities to meet the
increased traffic loads.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 134.
6 ENVIRONMENTAL MANAGEMENT PLAN
6.1 INTRODUCTION
Environmental Management Plan (EMP) is the key to ensure that the environmental quality of the
zone under impact does not deteriorate beyond the expected level due to the construction and
operation of the project. The EMP comprises a set of measures to be taken in different phases of the
project such as construction and operation to reduce adverse environmental impacts to an acceptable
level. Mitigation plans generally evolve around remediation and offsetting.
6.2 CAPACITY BUILDING FOR EMP IMPLEMENTATION
The EMP will be implemented by M/s Commander Pvt. Ltd., through appointment of a team of expert
environmental professionals. All environmental monitoring work will be undertaken by the
contractors through an approved and NABL/ MoEF accredited laboratory.
6.3 IMPLEMENT ARRANGEMENTS FOR EMP
The implementation of the EMP will be initiated by M/s Commander Realtors Pvt. Ltd. The project
proponent (M/s Commander Realtors Pvt. Ltd) will have a multi disciplinary team and will also have
an environmental management cell having a senior level environmental expert supported by a
numbers of middle level environmental experts. This team will ensure compliances of mitigation
measures and all statutory requirements. The team will also implement all EMP provisions and
respective environmental experts will supervise EMP implementation. The senior environmental
expert will mainly report EMP compliances to management and statutory undertakers. The EMP
implementation chart has been given as Figure 6.1.
6.4 ENVIRONMENTAL MANAGEMENT PLAN MATRIX
The Environmental Management Plan is meant for mitigation/management /avoidance of the
negative impacts and the enhancement of the various environmental components of the project. The
measure adopted and /or to be adopted during the different stages of the project have been detailed in
Table 6.1, for pre construction, construction and operation phases respectively.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 135.
Figure 6.1: EMP Implementation Chart
HEAD ENVIRONMENT & SAFETY
MANAGER
HEALTH AND
SAFETY
MANAGER ENVIRONMENT & SAFETY
AGM
ENVIRONMENT.
ARCHITECT
GREEN
BUILDING
DM
ENVIRONMENT
LANDSCAPE
ARCHITECT
CORPORATE LEVEL
HEALTH AND
SAFETY
OFFICER
ENGINEER
ENVIRONMENT
PROJECT SITE
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 136.
Table 6:1 : Environmental Management Plan Matrix
S. No. Environmental
Aspect/Issue Management Measures Responsibility
Planning And Pre-Construction Phase
1. Land Acquisition
The land has already been purchased from the private property holder at prevailing
market prices and hence it does not involve any land related issues. M/s
Commander Realtors Pvt. Ltd will ensure that any additional environmental
impacts resulting in the land will be properly addressed and integrated into the
EMP and other relevant documents.
Project Proponent
2. Preservation of Trees The proposed project is likely to involve cutting of small bushes and ground
vegetation.
Project Proponent through
Contractor
3. Batching Plants
The Contractor will be hired after duly approval of M/s Commander Realtors Pvt.
Ltd. It will also be ensured that the batching plant will comply with the
requirements of the relevant current emission control legislations and
Consent/NOC for the batching plants will be submitted to M/s Commander
Realtors Pvt. Ltd. Arrangements to control dust pollution through provision of
windscreens, sprinklers, and dust encapsulation will also be provided at all such
sites.
Project Proponent through
Contractor
4.
Other Construction
Vehicles, Equipment
and Machinery
All vehicles, equipment and machinery procured for construction will comply with
the Bureau of India Standard (BIS) norms. The discharge standards formulated
under the Environment Protection Act, 1986 will be strictly adhered to.
Noise limits for construction equipments such as compactors, rollers, front loaders
concrete mixers, cranes (moveable), vibrators and saws will not exceed 75 dB (A),
measured at one meter from the edge of the equipment in free field, as specified in
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 137.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
the Environment (Protection) Act, 1986.
6. Arrangement for
Construction Water
Tanker water will be used for fulfilling the water requirement during construction
period. The contractor will not be allowed to use any community water resource,
any irrigation canal or any surface water body for construction activities.
Project Proponent through
Contractor
7. Labor Requirements Unskilled labor from local communities will be given preference so as to provide
maximum benefit to the local community.
Project Proponent through
Contractor
8.
Construction Camp
Locations –
Selection, Design and
Lay-out
Labour camps will be constructed in locations so as to avoid conflicts and stress
over the infrastructure facilities with the local community.
Location for stockyards for construction materials will be made close to the site, so
as to avoid day transportation of raw material.
The waste disposal and sewage system for the labour camps will be designed in a
manner such that there are no adverse impacts on the surrounding areas.
Project Proponent through
Contractor
9.
Orientation of
Implementing Agency
and Contractors
M/s Commander Realtors Pvt. Ltd will organize orientation sessions and regular
on-site training sessions during all stages of the project including training for local
workers as well as for the contractor staff.
Environment Management Cell of
Project Proponent
Construction Phase
Site Clearing
1. Site Clearing
The proposed site will be cleared off all the weeds, shrubs and ground vegetation
prior to commencement of any construction activity
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 138.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
2. Other Construction
Wastes Disposal
Disposal locations will be identified as a part of Comprehensive Solid Waste
Management Plan to be prepared by the Contractor in consultation and with
approval of M/s Commander Realtors Pvt. Ltd.
Contractor will ensure that any spoils of material unsuitable for embankment fill
will not be disposed off near any water course, agricultural land, and natural
habitat like grass lands or pastures. Such spoils from excavation can be used to
reclaim borrow pits and low-lying areas located in barren lands along the project
area.
All waste materials will be completely disposed and the site will be fully cleaned
and certified by Environmental Expert of M/s Commander Realtors Pvt. Ltd before
handing over.
Project Proponent through
Contractor
Procurement of Construction Material
4.
Transporting
Construction Materials
and Haul Road
Management
Contractor will maintain all roads (existing or built for the project), which are used
for transporting construction materials, equipment and machineries as precised. All
vehicles delivering fine materials to the site will be covered to avoid spillage of
materials.
Contractor will arrange for regular water sprinkling as necessary for dust
suppression of all such roads and surfaces.
The unloading of materials at construction sites in/close to settlements will be
restricted to daytime only.
Project Proponent through
Contractor
5. Construction Water The contractor will use tanker water supply and will take all precaution to
minimize the wastage of water in the construction process/ operation.
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 139.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
Construction Work
6. Disruption to Other
Users of Water
It will be ensured by the contractor that only tanker water will be used for
construction purposes and no water is withdrawn from any community water
bodies.
Project Proponent through
Contractor
7. Drainage and Flood
Control
Contractor will ensure that no construction materials like earth, stone, ash will be
disposed off which can block any flow of water.
Contractor will take all necessary measures to prevent the blockage of water flow.
In addition to the design requirements, the contractor will take all required
measures to prevent any temporary or permanent change in the drainage pattern of
the area.
Project Proponent through
Contractor
8. Degradation of Water
Quality
It will be ensured by the contractor that any surface run off during construction
activities will be diverted through garland drains into a collection tank wherein it
will be separated for oil and silt, thereby making it fit to be used for construction
activities or disposal to nearby water bodies.
Project Proponent through
Contractor
Pollution
9. Water Pollution from
Construction Wastes
The Contractor will take all precautionary measures to prevent the wastewater
generated during construction from entering into streams, water bodies or the
irrigation system.
All waste arising from the proposed development will be disposed off as per the
norms of State Pollution Control Board.
Project Proponent through
Contractor
10. Water Pollution from The contractor will ensure that all construction vehicle parking location, Project Proponent through
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 140.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
Fuel and Lubricants fuel/lubricants storage sites, vehicle, machinery and equipment maintenance and
refueling sites will be located close to the project site.
All location and lay-out plans of such sites will be submitted by the Contractor
prior to their establishment and will be approved by M/s Commander Realtors Pvt.
Ltd
Contractor will ensure that all vehicle/machinery and equipment operation,
maintenance and refueling will be carried out in such a way that spillage of fuels
and lubricants does not contaminate the ground. Oil interceptors will be provided
for vehicle parking, wash down and refueling areas as per the design provided.
Contractor will arrange for collection and storing and disposal of oily wastes and
the same will be sold to vendors authorized by MoEF for recycling. All spills and
collected petroleum products will be disposed off in accordance with MoEF and
state PCB guidelines.
Contractor will certify that all arrangements comply with the guidelines of
SPCB/MoEF or any other relevant laws.
Contractor
11. Dust Pollution
It will be ensured by the contractor that the construction equipments conform to
relevant dust emission control legislation and that they are located close to the site,
preferably in downwind direction.
The dust pollution during construction activities will be reduced through water
sprinkling, encapsulation of dust source and by erection of screen/barriers.
The pollution monitoring will be conducted as per the monitoring plan.
Project Proponent through
Contractor
12. Emission from
Construction Vehicles,
Contractor will ensure that all vehicles, equipment and machinery used for
construction are regularly maintained and confirm that pollution emission levels
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 141.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
Equipment and
Machineries
comply with the relevant requirements of SPCB.
The Contractor will submit PUC certificates for all vehicles/ equipment/machinery
used for the project.
13.
Noise Pollution: Noise
from Vehicles, Plants
and Equipments
The Contractor will confirm the following:
All plants and equipment used in construction (including crushing plant) shall
strictly conform to the MoEF/CPCB noise standards.
All vehicles and equipment used in construction will have valid PUC. Servicing of
all construction vehicles and machinery will be done regularly and during routine
servicing operations, the effectiveness of exhaust silencers will be checked and if
found defective will be replaced.
At the construction sites within 250 m of the nearest habitation, noisy construction
work such as concrete mixing, batching will be stopped during the night time
between 10.00 pm to 6.00 am.
Monitoring shall be carried out at the construction sites as per the monitoring
schedule and results will be submitted to M/s Commander Realtors Pvt. Ltd.
M/s Commander Realtors Pvt. Ltd will be required to inspect regularly to ensure
the compliance of EMP.
Project Proponent through
Contractor
Safety
14. Personal Safety
Measures for Labour
Contractor will provide:
Personal Protective Equipments (PPE) will be provided to all the labourers during
construction phase.
Adequate safety measures for workers during handling of materials at site will be
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 142.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
taken up.
The contractor will comply with all the precautions as required for ensuring the
safety of the workmen as per the International Labor Organization (ILO)
Convention No. 62 as far as those are applicable to this contract.
The Contractor will mark ‘hard hat’ and ‘no smoking’ and other ‘high risk’ areas
and enforce non-compliance of use of PPE with zero tolerance. These will be
reflected in the Construction Safety Plan to be prepared by the Contractor during
mobilization and will be approved by M/s Commander Realtors Pvt. Ltd
15. Traffic and Safety
The contractor will take all necessary measures for the safety of traffic during
construction and provide, erect and maintain such barricades, including signs,
markings, flags, lights and flagmen as proposed in the Traffic Control
Plan/Drawings for the information and protection of traffic approaching or passing
through the section of any existing cross roads.
The contractor will ensure that all signs, barricades, pavement markings are
provided as per the MoRTH specifications.
Project Proponent through
Contractor
16. Risk from Electrical
Equipment(s)
The Contractor will take all required precautions to prevent danger from electrical
equipment and ensure that -
No material will be so stacked or placed as to cause danger or inconvenience to
any person or the public.
All necessary fencing and lights will be provided to protect the public in
construction zones.
All machines to be used in the construction will conform to the relevant Indian
Standards (IS) codes, will be free from patent defect, will be kept in good working
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 143.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
order, will be regularly inspected and properly maintained as per IS provision.
17. Risk Force Measure
The contractor will take all reasonable precautions to prevent danger to the
workers and public from fire, flood etc. resulting due to construction activities.
The contractor will make required arrangements so that in case of any mishap all
necessary steps can be taken for prompt first aid treatment. Construction Safety
Plan prepared by the Contractor will identify necessary actions in the event of an
emergency.
Project Proponent through
Contractor
18. First Aid
The contractor will arrange for -
A readily available first aid unit including an adequate supply of sterilized dressing
materials and appliances as per the Factories Rules in every work zone
Availability of suitable transport at all times to take injured or sick person(s) to the
nearest hospital.
Project Proponent through
Contractor
19. Informatory Signs and
Hoardings
The contractor will provide, erect and maintain informatory/safety signs, hoardings
written in English, Hindi and local language, wherever required.
Project Proponent through
Contractor
Flora & Fauna (Plantation, Preservation, Conservation Measures)
20. Flora and Fauna
The contractor will take reasonable precaution to prevent his workmen or any
other persons from removing and damaging any flora (plant/vegetation) and fauna
(animal).
If any carcass of any wild animal/ wetland bird is found near the construction site
at any point of time, the contractor will immediately take necessary actions for
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 144.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
dealing with the same.
Labour Camp Management
21. Accommodation
Contractor will follow all relevant provisions of the Factories Act, 1948 and the
Building and the other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 for construction and maintenance of labor camp.
The contractor will maintain necessary living accommodation and ancillary
facilities in functional and hygienic manner.
It will also be ensured that, local labour will be hired to the maximum extent
possible.
Project Proponent through
Contractor
22. Potable Water
The Contractor will construct and maintain all labor accommodation in such a way
that uncontaminated water is available for drinking, cooking and washing.
The contractor will also guarantee the following:
a) Supply of sufficient quantity of potable water (as per IS) in every
workplace/labor camp site at suitable and regular maintenance of such facilities.
b) If any water storage tank is provided that will be kept such that the bottom of
the tank at least 1m from the surrounding ground level.
c) Testing of water will be done every month as per parameters prescribed in IS
10500:1991.
Project Proponent through
Contractor
23. Sanitation and Sewage
System
The contractor will ensure that
- the sewage system for the camp are designed, built and operated in such a way
that no health hazards occurs and no pollution to the air, ground water or adjacent
Project Proponent through
Contractor
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 145.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
water courses take place
- separate toilets/bathrooms, wherever required, screened from those from men
(marked in vernacular) are to be provided for women
- adequate water supply is to be provided in all toilets and urinals
- all toilets in workplaces are with dry-earth system (receptacles) which are to be
cleaned and kept in a strict sanitary condition
- human excreta is to be disposed of by putting layer of it at the bottom of a
permanent tank prepared for the purpose and covered with 15 cm layer of waste or
refuse and then covered with a layer of earth for a fortnight.
24. Waste Disposal
The contractor will provide garbage bins in the camps and ensure that these are
regularly emptied and disposed off in a hygienic manner as per the Comprehensive
Solid Waste Management Plan, provided by M/s Commander Realtors Pvt. Ltd
Project Proponent through
Contractor
Contractor’s Demobilization
25.
Clean-up Operations,
Restoration and
Rehabilitation
Contractor will prepare site restoration plans. The clean-up and restoration
operations will be implemented by the contractor prior to demobilization. The
contractor will clear all temporary strouctures; dispose all garbage as per
Comprehensive Waste Management Plan, provided by M/s Commander Realtors
Pvt. Ltd.
All disposal pits or trenches will be filled in and effectively sealed off.
All construction zones including road-side areas, camps, hot mix plant sites, ,
batching plant sites and any other area used/affected by the project will be left
clean and tidy, at the contractor's expense, to the entire satisfaction of M/s
Project Proponent through
Contractor.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 146.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
Commander Realtors Pvt. Ltd.
Operation Phase
1. Monitoring Operation
Performance
M/s Commander Realtors Pvt. Ltd will monitor the operational performance of the
various mitigation/ enhancement measures carried out as a part of the project.
The indicators selected for monitoring include the survival rate of trees; status of
rehabilitation of borrows areas; and utility of noise barriers.
Environment Management Cell of
Project Proponent.
2. Maintenance of
Drainage
M/s Commander Realtors Pvt. Ltd will ensure that all drains (side drains, median
drain and all cross drainages) are periodically cleared especially before monsoon
season to facilitate the quick passage of rainwater and avoid flooding.
M/s Commander Realtors Pvt. Ltd will also ensure that all the sediment and oil and
grease traps set up at the water bodies are cleared once in every three months.
Facility Management Team of
Project Proponent
3. Pollution Monitoring
The periodic monitoring of the ambient air quality, noise level, water (both ground
and surface water) quality, soil pollution/contamination in the selected locations as
suggested in pollution monitoring plan will be responsibility of M/s Commander
Realtors Pvt. Ltd, for which approved pollution monitoring agency will be hired.
Environment Management Cell of
Project Proponent through MoEF /
NABL Accredited Laboratory
4. Air Pollution
Ambient air concentrations of various pollutants will be monitored as envisaged in
the pollution-monitoring plan.
Green belt development will be carried out and maintained.
Environment Management Cell of
Project Proponent through MoEF /
NABL Accredited Laboratory
5. Noise Pollution
Noise pollution will be monitored as per monitoring plan at different zones. Noise
control programs will be enforced strictly.
Monitoring the effectiveness of the pollution attenuation barriers, if there is any,
Environment Management Cell of
Project Proponent through MoEF /
NABL Accredited Laboratory
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 147.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
will be taken up thrice in the operation period.
6. Soil Erosion Visual monitoring and inspection of soil erosion will be carried out once in every
three months as suggested in monitoring plan.
Environment Management Cell of
Project Proponent
7. Maintenance of surface
water bodies
M/s Commander Realtors Pvt. Ltd will ensure that no effluent from the proposed
development will be discharged into any surface water bodies. It will ensure that
water conservation measures are being implemented and that the treated effluent is
effectively reused within the site.
Environment Management Cell of
Project Proponent.
8. Energy Conservation
Measures
M/s Commander Realtors Pvt. Ltd will ensure that effective energy conservation
measures are being adopted so as to reduce the power demand.
Environment Management Cell of
Project Proponent
9. Solid waste
Management
M/s Commander Realtors Pvt. Ltd will ensure that the municipal solid waste
generated during the operation phase of the proposed project will be handled as per
the Municipal Solid Waste Management & Handling Rules, 2000. The generated
municipal solid waste will be stored in the bins and then transfer to the centralized
system. From there it will be transported to the outside to an existing SWM
facility. The E-waste generated will be handled as per the E-Waste Management &
Handling Rules, 2010, biomedical waste will be sent to authorize biomedical
recyclers as per notified Biomedical Waste Management Handling (Amendment)
Rules, 1998 and the hazardous waste will be stored within the site and will be
handled as per the Hazardous Waste Management Handling and Transboundary
Movement (Amendment) Rules, 2009.
Environment Management Cell of
Project Proponent
10. Water Sourcing M/s Commander Realtors Pvt. Ltd will ensure that water for the proposed
development, water from the existing public supply will be used; however, in case
of extraction of water from ground water, necessary permission will be taken from
Environment Management Cell of
Project Proponent
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas,
Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 148.
S. No. Environmental
Aspect/Issue Management Measures Responsibility
CGWA and subsequently, the ground water recharge will be done through rain
water harvesting techniques.
11. Wastewater Treatment
M/s Commander Realtors Pvt. Ltd will ensure that no wastewater will be
discharged outside the project premises. It will be ensured that the wastewater
generated is treated in STP and is reused for landscaping, flushing and HVAC
purposes within the development. Care will be taken for zero discharge of treated
effluent outside.
Environment Management Cell of
Project Proponent
12. Water Conservation
M/s Commander Realtors Pvt. Ltd will ensure water recycling for landscaping,
flushing and HVAC & DG cooling purposes within the project premises. Apart
from recycling, rainwater harvesting will also be carried out within the proposed
development in order to recharge groundwater so as to reduce the freshwater
consumption demand and conserve water resources.
Environment Management Cell of
Project Proponent
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 149.
The detailed Environmental Management Plan (EMP) is required to mitigate the adverse
environmental impacts during construction and operation phase of the project are as given below:
6.5 EMP FOR AIR ENVIRONMENT
To minimize the pollutant concentration levels, mitigation measures primarily to minimize the use of
private vehicles would be implemented for further emission reduction as presented in this section. It
is, therefore, assumed that if these measures were implemented, the concentrations of all pollutants as
presented above will be much lower in value and would contribute very less impact on the project site
and at the receptor locations as well.
CONSTRUCTION PHASE
6.5.1 Site Preparation
Environmental impacts during construction phase will mainly arise due to civil works such as site
preparation, RCC foundation, construction etc., material and machinery transportation, fabrication and
erection etc. The construction phase impacts are temporary and localized phenomena except the
permanent change in local landscape and land use pattern at the project site. However, they require
due consideration with importance during project execution and also wherever applicable detailed
procedures shall be implemented to prevent/mitigate adverse impacts and occupational hazards.
To mitigate the impact of dust during the construction phase of the proposed project, the following
measures are recommended for implementation:
A dust control plan; and
Procedural changes to construction activities.
Dust Control Plan
Appropriate measures have been recommended and will be implemented to mitigate the adverse
impacts of dust on health of construction workers and the settlements around the site. The following
measures have been recommended:
Paving: The major access roads to the site will be paved as a part of the overall development
plan. The material storage areas will also be paved for dust control.
Graveling: Locally found gravel will be applied to the other access roads to serve as a
protective layer over the exposed soil.
Water Sprinkling: Water sprinkling will be carried out for the surfaces exposed to high wind
speeds or heavy vehicular movement.
Reducing Vehicle Speed: High vehicle speeds increase the amount of fugitive dust created
from unpaved areas. Speed bumps will be provided to ensure speed reduction on unpaved
areas.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 150.
Material Storage: All material storage areas will be adequately covered and contained so that
they are not exposed to high wind speeds on site leading to dust/particulate emissions. Fabrics
and plastics will be used for covering soils and debris to reduce fugitive dust emissions.
Procedural Changes to Construction Activities
Production and Transportation of Material - The transport of materials such as concrete and asphalt
to the construction sites generate significant amount of road dust, especially for sites that are
relatively far from material manufacturers. Setting up temporary portable concrete plants and/or
asphalt plants at construction sites can eliminate haulage of materials.
Idling Time Reduction - Construction equipment is commonly left idling while the operators are on
break or waiting for the completion of another task. Emissions from idling equipment tend to be high,
since catalytic converters cool down, thus reducing the efficiency of hydrocarbon and carbon
monoxide oxidation. Existing idling control technologies, which automatically shut the engine off
after a preset time can reduce emissions, without intervention from the operators.
Improved Maintenance - Recognizing that significant emission reductions can be achieved through
regular equipment maintenance, contractors will be asked to provide maintenance records for their
fleet as part of the contract bid and at regular intervals throughout the life of the contract.
To mitigate the impacts of DG set operation it will be ensured that the DG set would have sufficient
stack height to disperse the pollutants.
6.5.2 Noise Environment
To mitigate the impact of noise from the construction equipments on site, the following measures are
recommended for implementation:
Time of Operation: Minimum construction activities will be scheduled during night time. Material
transport will be strictly limited to daytime hours to ensure minimum incremental noise during night
hours.
Job Rotation: Workers employed in high noise areas will be engaged in shifts to minimise exposure.
Protective Equipments: Earplugs/muffs or other hearing protective wear will be provided to those
working very close to the noise generating machinery.
Vibration Control: For vibration control, damped tools will be used and the working hours will be
limited. The detailed Noise & Vibration Control Plan is enclosed as Annexure 6.1
To mitigate the impacts of noise generation due to DG sets, it will be ensured that DG set is enclosed
in acoustic enclosure and has adequate stack height so as to disperse the emissions.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 151.
6.5.3 Construction Material Management
The major construction material to be used for construction include bricks, coarse aggregates, cement,
coarse sand, reinforcement steel, structural steel, aluminium doors & windows, granite and vitrified
tiles for flooring and other water supply & sanitary fittings. The material will be loaded and unloaded
by the engaged labour on site.
The duties of the contractor will include monitoring all aspects of construction activities, commencing
with the storing, loading of construction materials and equipment in order to maintain the quality.
The work should be completed as per the final construction schedule. Bricks should be stacked neatly
at designated place of storage yard. Cement should be stored in stacks as shown in Figure 6.2. Other
material like aggregate, reinforcement and consumables should also be tidily stored in place and
released for use without causing litter around.
The contractor shall be responsible for management of such construction material during entire
construction period of the project. Sufficient quantity of materials should be available before starting
the each activity.
The contractor should test the all the materials in the Government labs or Government approved labs
in order to ensure the quality of materials before construction. This is also the responsibility of the
contractor, which would be clearly mentioned in the contractor’s agreement.
As soon as the construction activity is over the surplus earth shall be utilized to fill up the low-lying
areas, if any. All stationary machines shall be inspected weekly for maintenance and will be fitted
with exhaust pollution control devices.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 152.
Figure 6.2 Schematic layout of Cement Godown
OPERATION PHASE
To mitigate the impact of pollutants from vehicular traffic as discussed in Section 6.3 during the
operational phase of the site the following measures are recommended for implementation:
Vehicle emission controls and alternatives; and
Greenbelt development.
6.5.4 Vehicle Emission Controls and Alternatives
Parking Provisions: Adequate parking provisions for 1397 cars are made within the project site. The car
parking facility at the proposed project will be provided only at Stilt level.
Table 6.2 shows the car parking details in the proposed Independent Floors project. Traffic
Circulation and Parking Plan at Stilt is given in Figures 6.3 to Figure 6.5.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 153.
Table 6:2 Parking Details – Independent Floors Project
S.No Details Parking Numbers
1 Parking Requirement as per MoEF Norms
1.1
Residential @ 1 ECS per 2 tenements of BUA 101 to 200 sq m
(Ref: Annexure 6.2 area requirement for car parking, MoEF Manual
on Large Construction Project)
627 ECS
2 Parking Requirement as per HUDA Norms
2.1
Residential @ 1.5 ECS for each Dwelling Units
(Ref: Zoning Plan for Independent Floors 18.138 Acres issued by
DTCP)
828 ECS
3 Total Parking Proposed 1397 ECS
3.3 Stilt 1397 ECS
4 Additional parking over and above the MoEF norms for
future requirement 122.81% ( 770 ECS)
5 Additional parking over and above the HUDA norms for
future requirement 68.72 % (569 ECS)
Proper Road Network: A proper road network shall be constructed within the site boundary for
approach to various equipment/ installations in the site.
Footpaths, and Pedestrian Ways - Adequate footpaths, and pedestrian ways shall be provided at the
site to encourage non-polluting methods of transportation.
Greenbelt Development: Increasing vegetation in the form of greenbelt is one of the preferred
methods to mitigate air pollution. Plants serve as a sink for pollutants, act as a barrier to break the
wind speed as well as allow the dust and other particulates to settle out there. It also helps to reduce
the noise level to some extent. Hence, the project will be so developed that approximately 13% (9,710
sqm) of the area is designated for exclusive green area/landscaping in which 8% of the site area is
designated for peripheral and roadside planting. Details of Greenbelt development are given in
Section 6.10.3. The trees for green belt development that are proposed to be grown as barrier to Air
pollution are given in Table 6.3.
Table 6:3 Trees that can be used as barrier for Air Pollution
Air Pollution Attenuation Dust Barriers
Ficus glomerata (Guler) Azadirachta indica (Neem)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 154.
Peltophorum pterocarpum (Copper Pod)
Polyalthia longifolia (Ashok)
Nerium odorata (Kaner)
Melia azaderach (Mahaneem, Bakain)
Butea monosperma (Palash)
Cassia fistula (Amaltas)
Bauhinia variegata (Kachnar)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 155.
Figure 6.3 Traffic Circulation and Parking Plan
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 156.
Figure 6.4 Traffic Circulation & Parking Plan: Stilt Level (A4 type Typical)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 157.
Figure 6.5 Traffic Circulation & Parking Plan: Stilt Level (A3 type Typical)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. Page | 158
6.6 EMP FOR NOISE ENVIRONMENT
6.6.1 Construction Phase
During the construction phase, there would be a temporary increase in ambient noise levels due to
construction machinery operation and movement of construction vehicles. Though the industrial
countries have specified limits for occupational noise exposure, the permissible noise exposure limit
for industrial workers is primarily concerned with harmful effects of noise and its objective is to
protect the hearing of working people. The American Conference on Government of Industrial
Hygienists (ACGIH), USA, has prescribed the following permissible noise exposure limits for
industrial workers as given in Table 6.4.
Table 6:4 Standards for Occupational Exposure
Exposure time in hours/day Limit in dB(A)
8 90
4 93
2 96
½ 99
¼ 102
1/8 105
1/16 111
1/32 115
Exposure to continuous and intermittent noise levels louder than 115 dB(A) should not be permitted.
Following mitigation / management measures shall be adopted during construction period:
For protection of construction workers, earplugs should be provided to those workers who will be
working very close to noise generation source.
Servicing of all construction vehicles and machinery shall be done regularly and during routine
servicing operations, the effectiveness of exhaust silencers shall be checked and if found defective
will be replaced. Vehicles hired for bringing construction materials at sight shall conform to the
noise emission standards and shall be operated during non peak hours.
Workers employed in high noise areas will be rotated. Earplugs/muffs, or other hearing protective
wear will be provided to those working very close to the noise generating machinery.
Smooth flow of traffic should be ensured on the internal road to avoid idling and honking of
vehicles.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. Page | 159
Ambient Noise level monitoring shall be conducted at suitable locations at periodic intervals
during construction phase to conform to the stipulated standards both during day and night time.
Data shall be reviewed and analysed by the project manager for adhering to any strict measure.
Noise levels will also be monitored at point sources for occupational noise exposure and ensuring
health risk.
6.6.2 Operation Phase
To mitigate the impact of noise due to vehicular movement during the operational phase the greenbelt
development is recommended as per the details mentioned in Section 6.10.3 and proper traffic
management is also proposed to be implemented.
6.7 EMP FOR WATER ENVIRONMENT
6.7.1 Construction Phase
To prevent degradation and maintain the quality of the water source, adequate control measures have
been proposed to check the surface run-off, as well as uncontrolled flow of water into any water body.
Following management measures are suggested to protect the water quality during the construction
phase.
- Avoid excavation during monsoon season.
- Care should be taken to avoid soil erosion.
- Pit latrines and community toilets with temporary septic tanks shall be constructed on the site
during construction phase to prevent wastewater from entering the water bodies.
- To prevent surface and ground water contamination by oil/grease, leak proof containers should be
used for storage and transportation of oil/grease. The floors of oil/grease handling area should be
kept effectively impervious. Any wash off from the oil/grease handling area or workshop shall be
drained through impervious drains, Clarifiers or oil/water separators shall be constructed and
effluent should be treated appropriately before releasing it.
- Construction activities generate disturbed soil, concrete fines, fertilizer, oils and other wastes. On-
site collection and settling of storm water, prohibition of equipment wash downs, and prevention
of soil loss and toxic releases from the construction site are necessary to minimize water
pollution.
- All stacking and loading areas should be provided with proper garland drains equipped with
baffles to prevent run off from the site to enter any water body.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. Page | 160
OPERATION PHASE
In the operation phase of the project, water conservation and development measures need to be taken
including all possible potential for conservation of water, reuse, harvesting and recycling of water.
These could be in the form of the following:
- Water source Development
- Minimizing water consumption
- Promoting reuse of water after treatment and development of closed loop systems for different
water streams.
6.7.2 Water Source Development
Water source development shall be practiced by installation of scientifically design Rainwater
harvesting system.
Rainwater Harvesting Design
Rainwater harvesting promotes self-sufficiency and fosters an appreciation for water as a resource. It
is proposed to have recharge structures at 8 locations (16 Nos.) within the proposed project. 2 Nos. of
pits are located at each location.
In order to calculate the potential for Artificial Recharge, rainfall intensity of 45 mm per hour has
been considered for Gurgaon. The run-off coefficient parameters considered for calculation of the run-
off are given in Table 6.5.
Table 6:5 Run-Off Coefficient Parameters
S. No. Type of Surface Runoff Coefficient
1. Roof Top 0.9
2. Paved Area 0.65
3. Landscape Area 0.2
However, for the purpose of design of recharge structure, the higher value of runoff coefficient is
being considered in view of unpredictable nature of rainfall for arriving at total storage volumes.
Taking into the consideration the above run off coefficient the total run-off of proposed project is
1051.38 m3/ hour. The details design calculation for rainwater harvesting in proposed project is given
in Annexure 6.3.
The recharge structure is the gravel filled recharge well with sedimentation trap and oil & grease trap.
In the project design, it shall be ensured that no mixing of the storm water with waste effluent takes
place. All the storm water will be diverted to rain water-harvesting pits proposed in the project. The
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. Page | 161
typical section of the rainwater harvesting pit is shown in Figure 6.6 and the location of rainwater
harvesting pits is showing in Figure 6.7
Figure 6.6 Section of RWH Pit Proposed
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 162.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 163.
6.7.3 Provision of Water Body
The provision of about 5.0 % of the net zoned area of the project in green area for the water body for
rainwater harvesting purpose has been made. Approx. 1005 sqm of area has been proposed as
waterbody in the project area and location of water bodies is shown in the Site Plan.
Minimizing Water Consumption
Water consumption will be minimized by a combination of water saving devices such as
implementing fixtures that are low flow and water efficient models together with other water
conservation measures. Furthermore, to ensure ongoing water conservation, an employee education
and awareness programme will be introduced for the residents of the proposed project. Following
section discusses the specific measures, which shall be implemented;
DOMESTIC USAGE
- Use of water efficient plumbing fixtures (low flow toilets and urinals). Water efficient plumbing
fixtures use less water with no marked reduction in quality and service.
- Leak detection and repair techniques.
- Sweep with a broom and pan where possible, rather than hose down for external areas;
- Meter water usage, employ measurement & verification methods. Monitoring water use is a
precursor for management.
- Awareness campaign to disseminate knowledge on strategies and technologies that can be used
for water conservation.
HORTICULTURE
- Plants with similar water requirements shall be grouped on common zones to match precipitation
heads and emitters.
- Use of low-volume, low-angle sprinklers for lawn areas.
- Select controllers with adjustable watering schedules and moisture sensors to account for seasonal
variations, and calibrate them during commissioning.
- Selecting a drought resistant grass, and using lawn chemicals and fertilizer sparingly also reduces
watering needs.
- Place 3 to 5 in. of mulch on planting beds to minimize evaporation.
6.7.4 Promoting Reuse of Water after Treatment
To promote reuse and development of closed loop system for water, segregation of two schemes are
proposed namely:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 164.
(i) Wastewater Treatment scheme
(ii) Storm water management scheme.
WASTEWATER TREATMENT SCHEME:
As explained in Section 5.6.2, the total reclaimed water available from proposed STP is 249 KLD out
of which 115 KLD will be used to meet the flushing requirement; 49 KLD for landscaping purpose,
54 KLD for Road Maintenance and 31 KLD for other construction activities.
Sanitation infrastructure for Wastewater Treatment and its reuse will consist of:
- Wastewater collection & conveyance system.
- Wastewater treatment & disposal arrangement.
Wastewater collection and conveyance system shall be an underground sewer network that the total
wastewater generated from the proposed project is expected to be in the order of 277 KLD which will
be treated in STP of capacity 320 KLD to be installed at project site. The location of STP and dual
plumbing plan for conveyance of fresh water and treated wastewater is given in Figure 6.8
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 165.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 166.
Design Details of STP based on Membrane Bioreactor along with provision of UV treatment.
The wastewater generated will be treated in an on-site sewage treatment plant based on Membrane
Bioreactor along with provision of UV treatment. The characteristics of the wastewater and of the
effluent after treatment are likely to be as given in Table 6.6.
Table 6:6 Wastewater Inlet and Outlet Characteristics
Parameter Inlet (Mg/l)
Treated Effluent from Tertiary
Treatment with Unit (Mg/l)
pH 6.5-8.5 6.5 – 7.5
BOD 300 <5
COD 350 <10
Suspended Solids 250 <5
Oil & Grease 10 < 3
The hydraulic design details of STP based on Membrane Bioreactor with UV treatment of wastewater
generated from proposed project is enclosed as Annexure 6.4.
Storm Water Management:
As discussed earlier (refer section 6.7.2), most of the storm water produced on site will be harvested
for ground water recharge, thus proper management of this resource is must to ensure that it is free of
contamination. Contamination of storm water is possible from the following sources:
Diesel and oil spills in the Diesel Power Generator and fuel storage area
Waste spills in the Solid/ hazardous waste storage area
Oil spills and leaks in vehicle parking lots
Silt from soil erosion in gardens
Spillage of sludge from sludge drying area of sewage treatment plan.
A detailed “Storm Water Management Plan” will be developed which will consider the above sources.
The plan will incorporate best management practices which will include following:
Regular inspection and cleaning of storm drains.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 167.
Cover waste storage areas.
Avoid application of pesticides and herbicides before wet season.
Secondary containment and dykes in fuel/oil storage facilities.
Conducting routine inspections to ensure cleanliness.
Preparation of spill response plans, particularly for fuel and oil storage areas.
Provision of slit traps in storm water drains.
Good housekeeping in the above areas.
6.8 EMP FOR LAND ENVIRONMENT
CONSTRUCTION PHASE
Waste generated from construction activity includes construction debris, biomass from land clearing
activities, waste from the labour camp, and. hazardous waste. Following section discusses
management of each type of waste. Besides management of topsoil is an important area for which
management measures are required
6.8.1 Construction Debris
Construction debris is bulky and heavy and re-utilization and recycling is an important strategy for
management of such waste. As concrete and masonry constitute the majority of waste generated,
recycling of this waste by conversion to aggregate can offer benefits of reduced landfill space and
reduced extraction of raw material for new construction activity. This is particularly applicable to the
proposed project site as the construction is to be completed in a phased manner.
Recycled aggregate will be used for filler application, and as a sub-base for road construction. Mixed
debris with high gypsum, plaster, shall not be used as fill, as they are highly susceptible to
contamination, and will be given to recyclers.
Construction contractors shall remove metal scrap from structural steel, piping, concrete
reinforcement and sheet metal work from the site. A significant portion of wood scrap can be reused
on site. Recyclable wastes such as plastics, glass fiber insulation, roofing etc shall be sold to recyclers.
6.8.2 Waste from Labour Colonies & Biomass
Waste generated from labour camps will mainly comprise of household domestic waste, which shall
be collected and composted on site along with the biomass from the land clearing activities. The non-
compostable and non-recyclable portion of the waste shall be collected and transported to the nearest
solid waste dumping site.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 168.
6.8.3 Topsoil Management
To minimise disruption of soil and for conservation of topsoil, the contractor shall take the topsoil out
separately and stockpile it. After the construction activity is over, topsoil shall be utilised for
landscaping activity. Other measures, which would be followed to prevent soil erosion and
contamination include:
- Maximize use of organic fertilizer for landscaping and green belt development.
- To prevent soil contamination by oil/grease, leak proof containers should be used for storage and
transportation of oil/grease and wash off from the oil/grease handling area shall be drained
through impervious drains and treated appropriately before disposal.
- Removal of as little vegetation as possible during the development, and re-vegetation of bare
areas after the project.
- Working in a small area at a point of time (phase wise construction).
- Construction of erosion prevention troughs / berms.
OPERATIONAL PHASE
6.8.4 Solid Waste Management
The philosophy of solid waste management at the proposed project will be to encourage the four R’s
of waste i.e. waste reduction, reuse, recycling, and recovery (materials & energy). This will result in
lesser reliance on land filling. Regular public awareness meetings will be conducted to involve the
residents in the proper segregation, storage, recycling and composting options and techniques.
The Environmental Management Plan for the solid waste will focus on two major components during
the life cycle of the waste management system i.e. collection & transportation, treatment or disposal
Collection and Transportation
During the collection stage, the bio-degradable and non recyclable/non biodegradable waste will be
stored and collected separately. The segregation, transportation and disposal of wastes will be done by
the project management or may be outsourced to authorized private waste management agency.
To minimize littering and odours, waste will be stored in well-designed containers/bins that will be
located at strategic locations to minimize disturbance in traffic flow.
Care should be taken so that the collection vehicles are well maintained and minimize noise and
emissions. During transporting of the waste, it will be covered to avoid littering.
Treatment & Disposal
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 169.
The waste collected shall be segregated at site into bio-degradable and non-biodegradable. The non-
biodegradable waste shall be disposed off to the recyclers / and inert shall be disposed off at HUDA
waste disposal site. The biodegradable shall be treated on-site. The hazardous waste (used oil from
DG Sets) will be stored in HDPE drums in isolated covered facility and disposed off through
registered recycles only as per the Hazardous Wastes (Management, Handliing and Trans Boundary
Movement) Rules, 2008
The waste management flow diagram is presented in Figure 6.9.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 170.
Figure 6.7 Waste Management Flow Diagram
6.9 EMP FOR E-WASTE MANAGEMENT
The e-waste will be generated from the proposed development which will be stored at a warehouse to
be setup within site and will be sent to authorized recyclers or e-waste processing plants for treatment
as per E- Waste [Management & Handling] Rules, 2010
Household Waste (Segregation and Storage at Source)
1018.4 kg/day (81.47 %)
Primary Collection (from Source to Community Storage)
Road / Hardscape Sweeping 180.66 kg / day (14.45 %)
Segregation Facility
Community Bins for Segregated Waste
DISPOSAL (HUDA Facility)
Organic Inert Recyclable
Sold to Recyclers Compost Plant
Compost Reject
Used as Manure for Horticulture
TOTAL WASTE GENERATED (~1.25 TPD )
Process
Primar y Level C ollec tion / Stor age
Secondar y Level Collecti on / Storag e
Transportation
Segreg ation
Process and Disposal
Process
Disposal
Transportation to Segregation Facility
Horticulture Waste
29.13 kg / day (2.33 %)
Sludge from STP
20 kg / day (1.6 %)
Secure Room (Liquid Hazardous Waste Such as Spent Oil, etc. in
HDPE Drums)
Sold to Authorized Recyclers of HSPCB
Hazardous waste
E Waste
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 171.
6.10 EMP FOR ECOLOGICAL ENVIRONMENT
The proposed site exhibits typical semi-arid landscape. The soil is very sandy, loose and virtually
devoid of humus leading to the poor representation of vegetative cover. It supports thorn scrub of the
dry deciduous type: a sparse cover of drought resistant trees such as Ficus religiosa (pipall),
Azadirachta indica Neem), Albizzia lebbek (Sirin) species interspersed with thorny shrubs, herbs and
wild grasses. The existing land use pattern of the proposed site is not very productive. Hence,
appropriate measures shall be taken during greenbelt development at the site. Increased vegetation in
the form of greenbelt will not only enhance the aesthetics of the site but will also mitigate air
pollution and reduce noise pollution.
6.10.1 Construction Phase
Restrictions on location of labor camps and offices for project staff near the project area to
avoid human induced secondary additional impacts on the left over flora and fauna species of
the surrounding areas.
Cutting, uprooting, of trees or small trees present around the project site for cooking, burning
or heating purposes by the laborers shall be prohibited and suitable alternatives for this
purpose shall be made available.
Along with the major construction work, the multi layered peripheral green belt shall be
developed with native plant species.
6.10.2 Operational Phase
The newly planted site will be especially vulnerable to erosion until the plants have become fully
grown. Temporary stabilization barriers shall be used as required to prevent erosion during plant
growth. These barriers may include hay bales, erosion control blankets, temporary seeding, nurse
crops, and erosion control netting.
During the development of the green belt within the project area, it will be emphasized that the plant
species likely to be planted belong to the existing forest type besides the nitrogen fixing tree species,
species of ornamental values, and species of very fast growth with good canopy cover.
6.10.3 Green Belt Plan
a. General Principles in Greenbelt Design
Plants grown in such a way so as to function as pollutant sinks are collectively referred as greenbelts.
These plants should also provide an aesthetic backdrop for persons using the site and for the
surroundings and the community.
General principles in greenbelt design considered for this study are:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 172.
Type of pollution (air, noise, water and land pollution) likely from the activities at the site.
Agro-climatic zone and sub-zone where the greenbelt is located (and hence the plant species
which can be planted in the area.
Water quantity and quality available in the area
Soil quality in the area.
The plants should exhibit the following desirable characteristic in order to be selected for plantation.
The species should be fast growing and providing optimum penetrability.
The species should be wind-firm and deep rooted.
The species should form a dense canopy.
As far as possible, the species should be indigenous and locally available
Species tolerance to air pollutants like particulate matter, SO2 & NOx should be preferred.
The species should be permeable to help create air turbulence and mixing within the belt.
There should be no large gaps for the air to spill through.
Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces.
Ability to withstand conditions like inundation and drought.
Soil improving plants (Nitrogen fixing, rapidly decomposable leaf litter).
Attractive appearance with good flowering and fruit bearing.
Bird and insect attracting tree species.
Sustainable green cover with minimal maintenance.
Greenbelt is designed to minimize the predicted levels of the possible air and noise pollutants. While
designing the scheme the following facilities are considered:
Site Perimeter and approach road
Along the internal roads
In and around the residential area.
6.10.4 Greenbelt Design for Site
The selection of the trees is based on their phenology (thus roadside trees will not have leaf fall during
summer and rainy seasons when shade is most needed. Trees with more litter fall have been avoided).
The selection criteria of the species are based on pollution mitigation capacity (including particulate
matter), large leaf surface area, deep root system and less litter fall. Faster growing trees with lighter
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 173.
canopy will be planted alternatively with relatively slow growing trees with wider canopy. Trees will
be planted as per CPCB guidelines.
Landscape Plan: The project will have approximately 9710 sq m (~13% of the site area) under
exclusive green area/landscaping in which 5964 sq m (8 % of the site area) is designated for site
peripheral and avenue plantation. Apart from other open area, the site area will also have saucer shape
water body of an area 1005 sq m (5% of net zoned area). The Landscape plan showing the details of
green area for proposed project is enclosed as Figure 6.10.
The plant species proposed for green belt development is specified in Table No. 6.7
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 174.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 175.
Table 6:7: Proposed List of Plant Species
Botanical Name Nos.
Plumeria Alba 12
Azadirachta Indica 46
Ficus Benjamina 76
Cassia Fistula 68
Delonix Regia 42
Bauhinia Blakeana 48
Tabebuia Aurea
28
Tabebuia Rosea
Anthocephalus Cadamba 4
TOTAL 324
6.11 EMP FOR SOCIO-ECONOMIC ENVIRONMENT
The management plan has been designed in order to regularly gauge the social environment in which the
project shall operate, take proactive steps and adopt best practices, which are sensitive to the socio-
cultural setting of the region. Such an approach will not only result in the better management of the
project but also increase its goodwill among the locals. The management plan envisages ongoing
communication with the stakeholders including the public, surrounding areas, pollution control board or
the Ministry of Environment & Forests, etc. Management practices discussed here are pro-active steps to
address potential concerns during the various stages of the project.
A committee shall be formed in order to formalize the community relations of the project proponents.
The committee will address the issues of people as well as ensure that the mitigative measures
mentioned within the Environment Management Plan (EMP) are abided with.
6.11.1 Mitigative Measures
Transport and road safety: Since the project involves the movement of vehicles and machineries in
the area, the health and safety of pedestrians and residents accessing the communities is an issue of
concern. Considering this, the project proponents shall mitigate the impact by drawing traffic
management plans, so that any mishap due to traffic thenceforth can be avoided. Taking this into
concern, following aspects should be kept in mind:
Proper precautionary signage shall be installed.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 176.
Training to the drivers.
Installation of adequate speed breakers at correct locations.
6.11.2 Social Activities Proposed to be undertaken
The following social activities are proposed to be undertaken:
1. Empowerment of Communities, inclusive of Socio-Economic growth
a. Skill development/vocational training (For Men & Women)
2. Community Healthcare
a. General Health camps
b. Specialised Health camps
c. Specialised Medical treatment (Indoor treatment)
d. Health Awareness camps (HIV/AIDS, General Health etc.)
3. Other activities
a. Promotion of Art & Culture
b. Promotion of local Sports & Games
c. Awareness Programs (In-house & External).
The expenditure on the above mentioned CSR activities will be carried out in accordance to the
Companies Act, 2013.
6.12 EMP FOR ENERGY CONSERVATION
Energy conservation program will be implemented through measures taken both on energy demand
and supply.
Supply
Energy
Conservation Demand
Reduce consumption
Use energy-efficient
appliances
Create Guest Awareness
Utilize energy-efficient diesel
generators
Exploring the possibilities of
introducing renewable energy
Energy conservation will be one of the focuses during the project planning and operation stages. The
conservation efforts would consist of the following:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 177.
6.12.1 Solar Passive Techniques
The proposed site plan is designed to capture the positive seasonal climatic forces to mitigate
building’s resource consumption and environmental impacts. The vision for the proposed
development is to minimise its reliance on grid electricity and fossil fuels.
PASSIVE: The project is planned as row of low rise buildings each defining a green space that not
only enhances the visual environment but also contributes to biodiversity and air quality. Strategies
include insulated envelope, solar control glass, air tight construction and design for daylight. The
design ensures that every unit has the potential for passive cross-ventilation. Open spaces at front and
back allow for this and encourage air-flow. Architectural strategies have also been taken to reduce
heat gain by managing window sizes and at the same time, placing the most glazing under balconies
avoiding direct sun exposure to enter living spaces.
The majority of exterior envelope surface will be in a light, reflective color, which ensures that heat
energy is not absorbed by wall surfaces thus reducing cooling costs. Moreover, insulation is added to
the roof composition in order to reduce heat gain. The use of local material is also another initiative to
reduce energy consumption in construction.
The vast majority of the project's parking requirements have been located at stilts and designated off
street parking spaces coupled with the design of the grade level landscaping which includes a large
number of trees, in so reducing the "heat island" effect and migrating overheating of the site. It is
intended to create a landscaped street-scape that is focused on being pedestrian friendly and has
shared surfaces to slow down the traffic, while not compromising on smooth circulation and
aesthetics. Large planting zones along the street and a large central park is planned to be used for
sustainable storm water recharge utilizations.
ACTIVE:. High efficiency lighting with daylight controls to further reduce building’s electric use.
The use of energy-efficient lighting and electronic equipment shall release less energy thus
contributing to less internal heat loads inside the space.
RENEWABLE: Roof top solar thermal system sized to meet part of the service hot water load.
Photovoltaic panels to power external lighting for the site.
Above mentioned provisions have stemmed from fundamental ideas studied in the early concept
stages of the project ensuring the development to be sustainable and responsible to the surrounding
environment.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 178.
6.12.2 Adoption of Lighting Control
The lighting installation will be developed to suit the needs and particular functions of each area
within the residential towers and clubhouse Areas and comply with the recommendations of CIBSE
Lighting Codes.
The lighting will be developed in conjunction with the interior design. Luminaries and lamp sources
will be selected to match the local desired ambiance, where possible the lighting sources will be
selected to be low energy dimmable type, to work in conjunction with the lighting control system.
In the circulation areas including staircases and corridors, high efficacy fluorescent lighting with high
frequency electronic
Lighting Controls
A fully programmable lighting control system will be provided for control of lighting. This will
comprise distributed, networked panels. The panels will be interfaced to local switch plates in public
areas. The system will be programmable centrally and locally. The club house areas will be provided
with dimmable lighting control with daylight and occupancy sensors in the common areas.
Automatic Controls
The MEP systems described above for the proposed project will be controlled and monitored by a
dedicated Building Management System (BMS).
The BMS will be based on a series of standalone Strategic Command Centers (SCC) linked via a
LAN network and accessed via a Web Browser to a BMS Head End Command Centre(s). Should the
Landlord prefer this as a solution for the long term management of the Ireo development there will be
a facility allowed for remote monitoring,
The BMS will monitor the operation of each piece of equipment, including raising an alarm should
any one piece of equipment fail and providing a maintenance schedule for each piece of equipment
based on hours run. Specific equipment will be individually monitored for energy consumption, as
will specific distribution points in the different MEP systems, such as each retail unit's power
consumption.
The BMS will control the different MEP systems, such as the operation of the cooling plant. This will
include rotating which of the individual pieces of plant is operant to ensure even wear of equipment,
for example the rotation of the duty standby stair pressurization fans.
Generally the MEP equipment will all derive their power via the SCCs, however larger items of plant,
such as the cooling towers, will derive their electrical power direct from the electrical distribution
switchboards as noted within the electrical services section of this Report.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 179.
6.12.3 Light Power Density (LPD)
Light Power Density (LPD) as per ECBC has been considered in the project so as to reduce Energy
Consumption. The LPD considered for residential towers and clubhouse is given in Table 6.8.
Table 6:8 LPD Levels for the Design of Residential Block
Space LPD (W/m2) Space LPD (W/m2)
Bedroom 15 Master Bedroom 15
Living Room 15 Kitchen 15
Dining Room 15 Study Room 15
Home Theatre 15 Pooja Room 10
Gym 15 Household Help 15
Toilet 15 Common Area 15
Lobbies 20 Communication Corridors 15
Communication Staircases 15 Terrace 10
6.12.4 Use of renewable energy system
- Use of Solar Photovoltaic (SPV) system for direct conversion of sunlight into electricity
for landscape and street lighting.
- Use of solar heating system as per norms of HAREDA
6.12.5 Use of Energy Efficient Building Material
Use of Fly Ash in Road Construction
Fly ash is a lightweight material, as compared to commonly used fill material (local soils), therefore,
causes lesser settlements. It is especially attractive for road construction over a wide range of moisture
content, and therefore, results in less variation in density with changes in moisture content. Fly ash is
easy to handle and compact because the material is light and there are no large lumps.
Use of fly ash in road works results in reduction in construction cost by about 10 to 20 per cent. The
use of fly ash in pavement construction results in significant savings due to savings in cost of road
aggregates. Utilisation of fly ash will not only minimize the disposal problem but will also help in
utilizing precious land in a better way. Construction of road embankments using fly ash, involves
encapsulation of fly ash in earthen core or with RCC facing panels. Since there is no seepage of rain
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 180.
water into the fly ash core, leaching of heavy metals is also prevented. When fly ash is used in
concrete, it chemically reacts with cement and reduces any leaching effect. Even when it is used in
stabilisation work, a similar chemical reaction takes place which binds fly ash particles. Hence
chances of pollution due to use of fly ash in road works are negligible.
Use of Fly Ash Bricks in wall construction
Fly-Ash Bricks are an environment friendly cost saving building product. These bricks are three times
stronger than conventional bricks with consistent strength. These bricks are ideally suited for internal,
external, load bearing and non-load bearing walls. These Bricks with higher strength/weight ratio
(about 3 to 4 times that of burnt clay bricks) aid in designing stronger, yet more economic structures.
Fly Ash Bricks are durable, have Low water absorption, less consumption of mortar, Economical &
eco-friendly, Low energy consumption and No emission of green house gases. These bricks are not
affected by environmental conditions and remain static thus ensuring longer life of the building. Also,
the savings with regard to wastages in fly ash bricks are considerable during unloading and
construction due to true shape and size, consistency in quality, and the workability of the fly ash
bricks unlike traditional clay bricks. These bricks are very economical / cost effective, nil wastage
while transporting and handling.
Features
Some of the attributes of fly ash bricks are as follows:
Eco friendly
Low water absorption
Dimensional accuracy
High compressive strength
Environment friendly- uses by product of thermal power stations.
Advantages:
1. High Strength
Production process of flyash bricks does not involve sintering where as normal burnt clay bricks
onvolve sintering. So there is no burning of fossil fuel required in the manufacturing of Fly ash bricks.
So CO2 emission problem is not there in the manufacturing of Fly ash bricks and contributes to the
reduction of greenhouse gas emissions.
2. Less Water & Energy
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 181.
Use less energy & water – Much energy is onsumed in firing clay bricks in kilns. By using fly ash
bricks instead of clay bricks, much energy is saved in brick manufacturing.
3. Eco-Friendly
Reduce air pollution- Fossil fuel is used in heating clay bricks in kilns. Burning such fuel generates air
pollution and greenhouse gas (CO2), contributing to global warming. Fly ash bricks are manufactured
at room temperature and there is no fossil fuel burning and emission of green house gas (CO2).
4. Accuracy
Due to high strength, there is practically no breakage during transport & use.
Due to uniform size of bricks mortar required for joints and plaster reduces almost by 50%.
Due to lower water penetration, seepage of water through bricks is considerably reduced.
Gypsum plaster (plaster of paris) can be directly applied on these bricks without a backing coat of
lime plaster.
These bricks do not require soaking in water for 24 hours. Sprinkling of water before use is enough.
5. Saves agricultural land which is used for manufacturing clay bricks.
6. Can be manufactured at construction site also.
Use of China Mosaic/ High SRI (Solar Refractive Indiax) Paints in Roof Top
Roofs with high SRI Paints/ china mosaic are capable of delivering high solar reflectance (the ability
to reflect the visible, infrared and ultraviolet wavelengths of the sun, reducing heat transfer to the
building) and high thermal emittance (the ability to radiate absorbed or non-reflected solar energy).
The benefits associated with roofs with High SRI material (Cool roofs) include reduced cooling
energy load, reduced air pollution and greenhouse gas emission, and improved human health and
comfort. They may extend the roof service life and help mitigating the urban heat island effect. It also
achieves cooling energy savings in hot summers.
Use of Materials with Recycled Content
The project will utilize the building materials with recycled content such that the total recycled
content constitutes at least 10% of total civil materials cost (excluding labor & equipment). While the
focus remains on selecting as many materials as possible with high recycled content, it also reduces
the impact produced from the extraction and processing of virgin materials. Table 6.9 shows the list
of the materials with recycled content that are likely to be used during the construction.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 182.
Table 6:9 Used of Material with Recycled Contents
S. No. Name of Material
1 Concrete
a Reinforcement steel
b Cement
c Fly-Ash
2 Masonry
a Hollow Blocks
3 Metals
a MS/SS Works
b Aluminium Work
4 Glass and Glazing
a Glass
5 Finishes
a Ceramic & Vitrified Tiles
6.12.6 Thermal Properties of Building Components
The thermal factor adopted for building design for both Residential Tower and Club house are given
in Table 6.10 & Table 6.11.
Table 6:10 Thermal Factors for Building component
Component U- Factor (W/m2.K)
Exterior Wall Construction 0.44
Roof Construction 0.261
Fenestration U-Value 3.3
Fenestration SHGC 0.25
6.12.7 Thermal Properties of Enhance Building Material
To achieve the minimum heat load (thermal stresses) in the building occupancy, Table 6.11 shows the
specify the building design features and list of enhanced building materials proposed to be adopted in
the project with reference to thermal conductivity (k- value), density (d-value), specific heat(), surface
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 183.
resistance®, and solar heat gain factor(SHGF), projection factor (PF), M—factor (orientation factor),
minimum visible transmission of glazing for vertical projection (VT) as per MOEF GI guidelines
Table 6:11 Thermal Properties of Enhance Building Material
S.N
o.
Description
Densi
ty
Conductiv
ityb
Conducta
nce
Resistance (R) Specific
Heat 1/k, For
kg/m
3
(K),W/(m
K)
(C)2,K
m2/W
Km2
/w
Thickn
ess
Listed
(1/C)
Km2
/W
kJ/(kg K)
1 BUILDING BOARD
1a Gypsum or plaster board. 800 — 17.6 — 0.056 1.09
1b Hardboard 880 0.82 — 8.46 — 1.34
2 FINISH FLOORING MATERIALS
2a
Tile-asphalt, linoleum,
vinyl,rubber — — 113.6 — 0.009 1.26
2b ceramic — — — — — 0.8
3 INSULATING MATERIAL
3a Expanded polystyrene 29-56 0.029 — 34.7 — 1.21
3b
Reflective material — — 1.76 — 0.57 —
4 SIDING MATERIALS
4a Wood — — 6.53 — 0.15 1.3
5 PLASTERING MATERIALS
5a
Cement plaster, sand
aggregate 1860 0.72 — 1.39 — 0.84
5b
Gypsum plaster:Lightweight
aggregate 720 — 17.7 — 0.056 —
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 184.
6 MASONRY MATERIALS
6a Concrete blocks — — 5.1-5.8 —
0.20-
0.17 0.92
6b
Concretes- Sand and gravel
or stone aggregate
concretes 2400 1.4-2.9 —
0.69-
0.35 — —
6c
Lightweight aggregate
concretes 1920 0.9-1.3 —
1.08-
0.76 — —
6.13 ENERGY BALANCE
The Energy (Power) balance plan takes in account of various aspects like total energy required,
sources of energy inputs and outputs. Energy calculations are done for the different building i.e.
residential towers and EWS along with club house, School and retail to calculate the total power
consumption of the project. During construction phase, power will be met through DG sets and during
the operation phase will be sourced from Dakshin Haryana Bijlee Vitran Nigam Limited (DHBVNL),
with back-up power supply during operation phase of the proposed development.
The calculations are done with Whole Building Compliance Method. The energy consumption is
calculated by taking into account various Energy Conservation Measures and enhanced specification
of the materials. To calculate the energy savings in the project, buildings (Independent Floors) are
compared with a Base case building model which is based on stringent ECBC specifications.
The design criteria for the proposed residential towers are set to meet and exceed the minimum
requirements of the code. The following energy conservation measures have been incorporated in the
design of the proposed residential towers:
Energy Conservation Measures
Building Parameter Description
External Fenestration High performance insulating glass compared to base case glass
resulting is reduced heat gain and loss in the perimeter spaces.
External Shading
Staggering floor plates and balconies on the west facade are
designed to shade the floors below during summers. Louvers and
screens are provided on the western facade to block out afternoon
sun. Opaque insulated panels provide the required opacity on the
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 185.
Energy Conservation Measures
Building Parameter Description
east and south facade to further reduce the solar gains.
Natural ventilation
Operable windows to allow for free cooling during shoulder
months and night time.
PV powered lighting
Photovoltaic panels will be provided for external lamps to provide
common external lighting load.
6.13.1 Shadow Analysis
A shadow study provides an understanding of how the building mass in relation to the position of sun
will determine the amount of light that a space will receive. This analysis will inform the landscape
programme as well as the planting character of the space. The different relationships between the
towers and the adjacent outdoor spaces help create a range of spaces in full or partial shade.
Therefore, the shadow analysis has been carried out for the proposed group hosuing and the same is
shown below:
Sun Path Analysis: 21st March – 08 am.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 186.
Sun Path Analysis: 21st March – 12 noon.
Sun Path Analysis: 21st March – 5 pm.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 187.
Sun Path Analysis: 21st June – 08 am.
Sun Path Analysis: 21st June – 12 noon.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 188.
Sun Path Analysis: 21st June – 5 pm.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 189.
Sun Path Analysis: 23rd
September – 08 am.
Sun Path Analysis: 23rd
September – 12 noon.
Sun Path Analysis: 23rd
September – 5 pm.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 190.
Sun Path Analysis: 23rd
December – 08 am.
Sun Path Analysis: 23rd
December – 12 noon.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 191.
Sun Path Analysis: 23rd
December – 5 pm.
6.13.2 Ventilation
Ventilation Plan of a building takes into account various aspects of a building which includes various
ventilation techniques and building design features. As the project comprise of Residential and
Clubhouse which has Mechanical Ventilation defined as zones. The Ventilation Plan for basement
and ventilation calculations is attached in Annexure 6.5.
6.13.3 Energy Consumption
42.45 Watt per sqm of built-up area. Energy saving devices/policies will be pursued during
construction and operation phases to achieve energy savings. Alternate sources of energy i.e. solar and
recycling of waste will be promoted to enhance savings of conventional energy.
The electrical line diagarns showing the energy distribution in the project is shown in the Figure 6.11
6.13.4 Energy Saving in the Project
Total of about 460 kW-h energy saving is being estimated using non-conventional sources of energy
(solar heating). The energy saving calculation for Solar Water Heating for proposed project is
enclosed as Annexure 6.6.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 192.
Apart from this 27.05 % energy saving has been achieved using energy efficient appliances. The
energy saving calculation through energy efficient appliances in proposed Independent Floors project
enclosed as Annexure 6.7.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 193.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 194.
6.14 STRUCTURAL SAFETY MEASURES
The project falls in the category of zone-4, specify the standards and codes used in building
construction to minimize the risk of natural calamities like wind, load, seismic load (earthquake),
thunder storm/lightning etc. as per NBC 2005
Table 6:12 List of Codes Adopted for Structural Safety
S.No Strtured Design Codes Adopted
1 National Building Code SP 7:2005
2 Design Aids for Reinforced Concrete – to IS 456 Sp16:1980
3 Code of practice for plain and reinforced concrete IS 456:2000
4 Code of practice for general construction in steel IS 800:2007
5
Code of practice for design loads (other than
earthquake) for buildings and structures – Dead
Loads
IS 875:Part 1:1987
6
Code of practice for design loads (other than
earthquake) for buildings and structures – Wind
Loads
IS 875:Part 3:1987
7 Criteria for Earthquake Resistance Design of
Structures – General Provisions and Buidings IS1893:2002
6.15 ELECTRICAL HAZARDOUS AND SAFETY MEASURE PLAN
Following Guidelines have been followed for implementation of Electrical Hazard / Safety
precautions at the construction Site and thereafter at the Premises during operations.
Definition Electrical Hazard – A dangerous condition such that contact or equipment failure can
result in Electric shock, arc-flash burn, thermal burn, or blast. Electrical hazard includes ‘dangerous’
meaning ‘able or likely to inflict injury’; there are high voltage, low current sources that are not
intrinsically dangerous, and there are low-voltage, high-current sources that are not ‘safe’. A
‘harmless’ static electricity shock could cause sufficient startle reaction to make a worker fall off a
ladder. A hazard analysis is necessary to identify electrical hazards and determine the degree of risk.
Measures for preventing Electrical Hazards
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 195.
1. Safe Electrical Installation
Installation of new electrical systems to a suitable IS standard. Requirements for electrical
installations, and then maintain them in a safe condition;
Provision of enough socket-outlets - overloading socket-outlets by using adaptors which can cause
fire.
2. Provision of safe and suitable equipment
There will be proper selection of equipment that will suit our working environment;
Electrical risks will be eliminated by using air, hydraulic or hand powered tools. These will be
especially used only in harsh conditions;
There will be provision of an accessible and clearly identified switch near each fixed machine
to cut off power in an emergency;
For portable equipment, there will be use of socket-outlets which are close by so that
equipment will be easily disconnected in an emergency;
The ends of flexible cables will always have the outer sheath of the cable firmly clamped to
stop the wires (particularly the earth) pulling out of the terminals;
Damaged sections of cable will be replaced completely;
There will be use of proper connectors or cable couplers to join lengths of cable;
There will be proper protection of light bulbs and other equipment which could easily be
damaged in use. And also creates risk of electric shock if they are broken;
Electrical equipment used in flammable/explosive atmospheres will be designed to stop it
from causing ignition.
i) Reduction of Voltage
One of the best ways of reducing the risk of injury when using electrical equipment is to limit the
supply voltage to the lowest needed to get the job done, such as: Temporary lighting can be run at
lower voltages, e.g. 12, 25, 50 or 110 volts; Where electrically powered tools are used, battery
operated will be safest; Portable tools are readily available which are designed to be run from a 110
volts centre-tapped-to-earth supply.
ii) Provision of safety device
If equipment will be operated at 230 volts or on higher, then the provision of an RCD (residual current
device) will be provided as an additional safety. An RCD is a device which detects some, but not all,
faults in the electrical system and rapidly switches off the supply. RCD will be built into the main
switchboard or the socket-outlet, as this means that the supply cables will be permanently protected.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 196.
Additionally a plug incorporating an RCD, or a plug-in RCD adaptor, will also be provided for an
additional safety. RCDs for protecting people have a rated tripping current (sensitivity) of not more
than 30 milliamps (MA).
An RCD is a valuable safety device, never bypass it;
If the RCD trips, it is a sign there is a fault;
The RCD will have a test button to check that its mechanism is free and functioning.
iii) Work safely
We will make sure that people who are working with electricity are competent to do the
job. Even simple tasks such as wiring a plug can lead to danger – we will ensure that
people know what they are doing before they start.
We must not allow work on or near exposed live parts of equipment unless it is absolutely
unavoidable and suitable precautions will be taken to prevent injury, both to the workers
and to anyone else who may be in the area.
iv) Underground Power Cables
Always assume cables will be present when digging in the street, pavement or near
buildings. The usage will be up-to-date service plans, cable avoidance tools and safe
digging practice to avoid danger.
v) Overhead Power Lines
When working near overhead lines, it may be possible to have them switched off. So, we
will keep the safe working distance from the cables.
6.15.1.1 Basic Precautions
There are various ways of protecting people from the hazards caused by electricity, including
insulation, guarding, grounding and electrical protective devices. We will significantly reduce
electrical hazards by following some basic precautions.
i) Insulation
All electrical cords will have sufficient insulation to prevent direct contact with wires. All
cords will be checked before each use, since corrosive chemicals or solvent vapors may
erode the insulation. Damaged cords will be repaired or taken out of service immediately,
especially in wet environments such as cold rooms
ii) Guarding
Live parts of electric equipment operating at 50 volts or more
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 197.
will be guarded against accidental contact. Plexiglas shields may be used to protect
against exposed live parts.
iii) Grounding
Only equipment with three-prong plugs will be used. The third prong provides a path to
ground that helps prevent the buildup of voltages that may result in an electrical shock or
spark.
iv) Circuit Protection Devices
Circuit protection devices will be designed to automatically limit
or shut off the flow of electricity in the event of a ground-fault,
overload, or short circuit in the wiring system. Fuses, circuit
breakers, and ground-fault circuit interrupters are three well-
known examples of such devices.
Fuses and circuit breakers prevent over-heating of wires and
components that might otherwise create hazards for operators.
They disconnect the circuit when it becomes overloaded. The
ground-fault circuit interrupter or GFCI, will be used to shutoff electric power if a ground
fault is detected. The GFCI will be particularly used near sinks and wet locations. Since
GFCIs will cause equipment to shutdown unexpectedly, they may not be appropriate for
certain apparatus. Portable GFCI adapters (available in most safety supply catalogs) may
be used with a non-GFCI outlet.
v) Safe Work Practices
The following practices will be used to reduce the risk of injury or fire when working with electrical
equipment:
Avoid contact with energized electrical circuits.
Disconnect the power source before servicing or repairing electrical equipment.
When it is necessary to handle equipment that is plugged in, be sure hands are dry and,
when possible, wear nonconductive gloves and shoes with insulated soles.
If it is not unsafe to do so, work with only one hand, keeping the other hand at your side
or in your pocket, away from all conductive material. This precaution reduces the
likelihood of accidents that result in current passing through the chest cavity.
If water or a chemical is spilled onto equipment, shut off power at the main switch or
circuit breaker and unplug the equipment.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 198.
If an individual comes in contact with a live electrical conductor, do not touch the
equipment, cord or person. Disconnect the power source from the circuit breaker or pull
out the plug using a leather belt.
vi) High Voltage or Current
Repairs of high voltage or high current equipment will be performed by trained electricians.
Individuals who are experienced in such tasks and would like to perform such work on their own
equipment must first receive specialized electrical safety related work practices training by EHS staff.
The following additional precautions will be taken:
Always assume a high voltage potential exists within a device while servicing it, even if it is
de-energized and disconnected from its power source.
Avoid becoming grounded by staying at least 6 inches away from walls, water, and all metal
materials, including pipes.
Use of voltmeters and test equipment with ratings and leads sufficient to measure the highest
potential voltage expected to be found inside the equipment being serviced.
After servicing, check equipment with a multi-meter or appropriate device to ensure it is
grounded before reconnecting to the power source.
Earthing Pits layout Plan and Lighting Arrestors Layout Plan are given in Figure 6.12and Figure
6.13 respectively. The list of electrical codes and standards considered are enclosed as Annexure 6.8
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 199.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 200.
Figure 6.8 Location of Lightning Arrestors in Proposed Project (TYPICAL UNIT)
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 201.
6.16 EMP FOR GREEN HOUSE EFFECTS, RADIATION EFFECTS, OZONE DEPLETION
EFFECTS AND ACID RAIN EFFECTS
Particular Source Impact of Project Mitigation Measures
Green House Effect -Emission of green
house gases like Cox,
Nox due to combustion
of fuel during
vehicular traffic.
-Running of DG sets
also cause emission of
green house gas like
Nox etc
-Add pollutant load in
the baseline
environment of the
project area
-Impact on the health
of construction workers
during the construction
phase
-Impact on flora and
fauna of the area
-Greenbelt
development to
mitigate air pollution
-Ensuring proper stack
height of DG sets to
disperse the pollutant
properly which in turn
reduce the ground
level conc. near the
project site.
-Water sprinkling will
be adopted
-Use of scrubbers
which trap pollutants
before they are
released into the
atmosphere
– use of catalytic
converters in cars to
reduce the emissions
of pollutant
Radiation Effect Depletion of ozone
layer due to ozone
depletion substance
cause entry of UV rays
on earth, which further
cause skin cancer and
other harmful effect on
human health.
-Impact on
construction workers
health during the
construction phase
-Impact on flora and
fauna of the area
The construction
workers shall be
provided with
adequate safety
equipments during the
cutting, welding and
other activities of
construction phase and
the same has been
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 202.
Particular Source Impact of Project Mitigation Measures
Source-Construction
work, metal cutting,
welding operation etc
are the different source
of ozone gas and
nitrous gas emission
discussed below :-
Welding shall be done
only in designated
areas
Protective clothes shall
be provided during
welding activities
Flame proof gauntlet
gloves,
leather apron and high
top shoes shall be
provided to the
construction labours
Specifically designed,
leak proof helmet
equipped with filter
plates shall be
provided to protect
against ultraviolet,
infrared and visible
radiation.
Ozone Depletion
Effect
-Emission of CFCs
from air conditioners
and refrigerators
-The destruction of the
ozone layer means the
loss of the natural
barrier against the sun's
harmful ultraviolet
rays, particularly UV-
B, which can harm the
eyes (cataracts) and
contribute to skin
cancer (melanoma) and
suppress the efficiency
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 203.
Particular Source Impact of Project Mitigation Measures
of the body's immune
system.
-UV-B also produces
changes in the
chemical makeup of
plant species.
Acid Rain Effect -Acid rain is caused by
emissions of sulphur
dioxide and nitrogen
oxides from running of
DG sets and Vehicular
emission, which react
with the water
molecules in the
atmosphere to and
produce acids.
-It can have harmful
effects on plants, and
proposed
infrastructure.
-Use of scrubbers
which trap pollutants
before they are
released into the
atmosphere
– use catalytic
converters in cars to
reduce their emissions
6.17 EMP FOR FIRE FIGHTING
The fire protection system will be generally designed based on Part IV, Group I of National Building
Code (NBC) of India (2001), Tariff Advisory Committee’s TAC, fire protection manual (1998) and
the latest Indian and International standards/codes. The fire protection system will cover external as
well as internal premises of the building
Following systems are planned to be provided within the entire Independent Floors:
Wet riser cum down comer system
Portable Fire Extinguisher
The proposed fire tender plan is shown in Figure 6.14.
The fire escape route plans for proposed project are shown in Figure 6.15.
2 nos. of fire fighting water tanks having capacity of 150 m3 each is provided for fire fighting
purpose.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 204.
Figure 6.9 Fire Tender Plan for Proposed Independent Floors Project
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 205.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 206.
6.18 HEALTH AND WELFARE PLAN
The health, safety and welfare plan for the building workers has been prepared as per the clauses of
the Haryana Building and Other construction Workers (Regulation of Employment (RE) &
Condition of Service (CS)) Act, 1996 and Rules 2005 and such other Rules, Regulations and Laws
as may be applicable.
The detailed provisions regarding Health, Safety and Welfare are as follows:-
6.18.1 Fixation of Hours of Work and Interval of Rest & Spread Over
a. No building worker employed shall be required or allowed to work more than nine hours a
day or forty eight hours a week
b. No building worker hall be required or allowed to work continuously for more than five hours
unless he had an interval of rest of not less than half an hour
c. The working day of the building workers employed in the construction shall be so arranged
that inclusive of the interval of rest shall not be spread over than 12 hours on any day
d. When a building worker work for more than 9 hours on any day or for more than 48 hours in
any week, he shall, in respect of over time work, be entitiles to wages at double the ordinary
rate of wages.
6.18.2 Weekly rest, payment of work dones on the day of rest at overtime rate, etc.
a. Workers employed in construction work shall be allowed a day rest in every seven days for all
building workers
b. No worker shall allowed to work on rest day unless he already had or will have substituted
rest day for whole day on one of the five days immediately before or after such rest day
6.18.3 Notice of Wage Period
a. Provision of display board to the conspicuous place at the work site showing the rates of
wages, hour of working, wage period, date of payment of wages, name and address of
grievance redressal officer.
b. The display board shall be in english and local language understood by majority of workers
c. Muster roll, wages register, deduction register and overtime register shall be maintained as
per the provision of Clause 88, Part III, Chapter VI, B. The Haryana Building and Other
construction Workers (RE & CS) Rules 2005
6.18.4 Accommodation
a. The contractor shall provide, free of charge temporary living accommodation to all workers
employed by him till the construction work is in progress.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 207.
b. The temporary accommodation shall have separate cooking place, bathing, washing and
lavatory facilities.
c. Incase, more than fifty female building workers are ordinarily employed, there shall provide
and maintain suitable room for the use of children under the age of six of such female.
d. All room shall have adequate light & ventilation and will be maintained
6.18.5 Latrine and Urinal
a. Effective arrangement to provide and maintain at suitable points sufficient supply of
wholesome drinking water as per IS 10500. All such points will be situated within six meter
of any washing place, urinal or latrine
b. Provision of urinal and latrine at conveniently located such that may be accessible to workers
at all times while they are in such place.
c. Every latrine shall be under cover and so partitioned off as to secure privacy and shall have a
proper door and fastening.
d. Where in both male and female building workers are employed, there shall be displayed
outside each block of latrines and urinals, written in the landuage understood by the majority
of workers
e. Every latrine or urinal shall be adequately lighted with energy efficient lighting and shall be
maintained in a clean and sanitary condition at all the time.
f. Water shall be provided by means of a tap or otherwise so as to be conveniently accessible in
or near by every latrine or urinal
g. The walls, ceiling and partitions of very latrine or urinal shall be white washed once in every
period of four months.
h. Every latrine and urinal shall be connected to flush system and shall wastewater shall be
disposed off through mobile STP.
6.18.6 Canteens
a. Provision of canteen which shall accommodate building workers, kitchen, store room, pantry
and washing places separately for building workers and utensils
b. The canteen shall be sufficiently lighted with energy efficient lights.
c. The floor of the canteen should be made smooth and impervious and shall be lime washed or
color washed atleast once in six months.
d. The precincts of canteen shall be maintained in a clean and sanitary condition
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 208.
e. Wastewater from the canteen shall be carried away in covered drain and shall not be allowed
to accumulate in the surrounding of canteen
f. Adequate number of bins shall be provided at kitchen, dining area, utensil washing area and
hand washing area. Arrangement shall be made for daily collection
g. The canteen should not be situated at the distance not less than 15.2 meters from any latrine or
urinal or any source of dust, smoke or obnoxious fumes
h. At the location where the canteen is located more than 2 km from the work place, provision of
place for serving tea and light refreshment shall be made for the building workers.
6.18.7 Medical Facilities
a. The Project Proponent shall ensure that the Contractor shall provide full fledged First Aid
Centre (24 hours facility available) with one full time medical officer including once nurse,
once dresser-cum-compounder.
b. There shall be Ambulance 24 hours available at project site
c. The medical examination for all building workers shall be carried out before employing, after
illness or injury.
d. If it appears that the illness or injury might have affected workers fitness and thereafter,
medical examination once in every two years upto age of forty and once in a year there after
shall be done.
e. Complete and confidential record of medical examination shall be maintained by the
employers or the authorized physician
f. The medical examination shall include:
Full medical and occupational history
Vision
Hearing
Breathing
Upper Limbs (adequate arm function and grip)
Lower Limbs (adequate leg and foot function
Spine
General mental alertness and stability with good eye, hand and foot coordination.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 209.
6.18.8 Emergency Care Services or Emergency Treatment
a. Project Proponent shall ensure that the provision for essential life saving aides and required to
handle following shall be made:
Head injuries and spinal injuries
Bleeding
Fractures and dislocations of bones and joints
Crush injuries
Shock including electric shocks
Dehydration due to any cause
Snake bite, insect bite, scorpion and bee sting
Burns including chemical burns
Sunstroke and frost bite
The above shall be provided and maintained under the supervision of Medical Officer,
appointed by the contractor
6.19 SAFETY MEASURES
6.19.1 General Safety Measures
a. The proponent shall form safety committee consisting of members of project proponent,
contractor, and workers.
b. The project proponent shall appoint a safety officer who shall possess such qualification and
perform such duties as may be prescribe
c. The project proponent shall ensure that the contractor shall provide safe access and safety to
any work place, including the provision of suitable and sufficient scaffolding at various stage
where work cannot be done from the ground or from any part of a building or from a ladder.
d. The erection, installation, use and maintenance of transporting equipment such as
locomotives, trucks, wagons and other vehicles and trailers shall be done by appointing
competent persons to drive or operate such equipment.
e. The project proponent shall ensure adequate and suitable energy efficient lighting to every
work place and approach.
f. The precautions to be taken to prevent inhalation of dust, fumes, gases during any grinding,
cleaning, spraying of any material and steps to be taken to secure and maintain adequate
ventilation of every working place or confined space.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 210.
g. The project proponent shall ensure that the contractor shall take all precautions to prevent
danger to workers from live electric wire or apparatus including electrical machinery and
tools and from overhead wires
h. The project proponent shall ensure that the contractor shall provide safety nets, safety sheets
and safety belts where specific nature or circumstance of work render then necessary for the
safety of the workers.
i. The project proponent shall ensure that the contractor shall abide by and follow EHS policy of
M/s Faithbuildtech Realtors Pvt. Ltd.
j. The project proponent shall appoint of Inspecting Staff as per the directives of Chapter VIII,
Inspecting Staff & Chapter IX Special Provisions, The Haryana Building and Other
construction Workers (RE & CS) Act, 1996.
k. The project proponent will penalize contractor for contravention of provision of safety
measures.
6.19.2 Safety for Welding & Cutting
1. Welding and gas cutting operations shall be done only by qualified and authorized persons
and as per IS Specifications and code of Practice.
2. Welding and gas cutting shall not be carried out in places where flammable or combustible
materials are kept and where there is danger of explosion due to presence of gaseous
mixtures.
3. Welding and gas cutting equipment including hoses and cables shall be maintained in good
condition.
4. Barriers shall be erected to protect other persons from harmful rays from the work. When
welding or gas cutting is done in elevated positions, precautions shall be taken to prevent
sparks or hot metal falling on persons or flammable materials.
5. Suitable type of protective clothing consisting of fire resistant gauntlet gloves, leggings, boots
and aprons shall be provided to workers as protection from heat and hot metal splashes.
Welding shields with filter glasses of appropriate shade shall be worn as face protection.
6. Adequate ventilation shall be provided while welding in confined space or while brazing,
cutting or welding zinc, brass, bronze, galvanized or lead coated materials.
7. Welding and gas cutting shall not be done on drums, barrels, tanks or other containers unless
they have been emptied, cleaned thoroughly and it is made certain that no flammable material
is present.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 211.
8. Fire extinguisher shall be available near the location of welding operations. Fire safety permit
shall be obtained for working at volnearable areas and operating areas before flame
cutting/welding is taken up.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61, Village
Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 212.
7 ENVIRONMENTAL MONITORING PLAN
7.1 GENERAL
An environmental monitoring plan provides feedback about the actual environmental impacts of a
project and helps to judge the adequacy of the mitigation measures in protecting the environment. The
purpose of environmental monitoring is to evaluate the effectiveness of implementation of
Environmental Management Plan (EMP) by periodically monitoring the important environmental
parameters within the impact area, so that any adverse effects are detected and timely action can be
taken.
7.2 OBJECTIVES OF ENVIRONMENTAL MONITORING PLAN
The key objective of the environment monitoring program will be as follows:
1 Ensure compliance with the mitigation measures as identified in the EIA;
2 Determine the project’s actual environmental impacts so that modifications can be made to the
project’s mitigation measures;
3 Describe the extent of environmental effects and resource losses;
4 Provide scientific information about the response of an ecosystem to a given set of human
activities and mitigation measures;
7.3 SUGGESTED ENVIRONMENTAL MONITORING PLAN
The environmental monitoring plan for the proposed Independent Floors development has been
conceptualized in view of the institutional, scientific and fiscal issues pertaining to the project. The
monitoring plan aims to collect data on the environmental indicator to provide information about the
environmental impacts. For developing the monitoring plan, appropriate components which are likely
to be affected have been identified. For each component, suitable measurable environmental
indicators which are appropriate to the impact mechanism and scale of disturbance and which have a
low natural variability, broad applicability and an existing data series have been defined.
The monitoring plan has been designed for the construction and the operation phase of the project and
the details of the plan have been presented in Table 7.1.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 213.
Table 7:1: Recommended Environmental Monitoring Plan
S.N Performance
Indicator
Component Parameters Locations Frequency Measurement
methodology
Preconstruction Phase
1 Concentration
of SPM to
assess the
effectiveness
of dust
control
measures
Ambient Air
Quality
PM2.5 and
PM10
Project site Quarterly
IS 5182 ( Part –
IV), 1973
IS 5182 ( Part –
XXIII), 1973
Emissions
from DG
sets
Quarterly
2 Equivalent
noise level
Ambient
Noise
Quality
Noise
emissions
from DG set
Project site Quarterly Operational
manual of noise
level meter
Construction Phase
1 Oil and
grease, heavy
metal
concentration
Soil Quality pH,
electrical
conductance,
cation
exchange
capacity,
Sodium
Absorption
Ratio (SAR),
water
holding
capacity,
phosphorous,
Copper,
Zinc, iron,
calcium,
One location
within
project site
Annually Practical methods
in Ecology and
Environmental
Sciences
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 214.
S.N Performance
Indicator
Component Parameters Locations Frequency Measurement
methodology
magnesium,
sodium,
potassium,
boron,
Nitrogen,
porosity,
permeability,
infiltration
capacity,
bulk density,
organic
content
texture, etc.,
2 Concentration
of SPM to
assess the
`effectiveness
of Dust
control plan
Ambient Air
Quality
PM2.5 and
PM10
Project site Quarterly
IS 5182 ( Part –
IV), 1973
IS 5182 ( Part –
XXIII), 1973
Emissions
from DG set
of admin
block
Quarterly
3 Equivalent
noise level
Ambient
Noise
Quality
Hourly Leq Project site Monthly Operational
manual of noise
level meter Noise
emissions
from DG set
operation
during
construction
work
Monthly
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 215.
S.N Performance
Indicator
Component Parameters Locations Frequency Measurement
methodology
Operation Phase
1 Ground water
table level
Rainwater
harvesting
and ground
water
recharge
plan
Ground
water table
Near the
ground
water
recharge pit
Twice in a
year
As per standard
practice
2 Greenbelt
survival rate
Greenbelt
development
plan
Greenbelt At the
greenbelt
development
corridor
Twice in a
year
3 % Savings of
energy
Energy
conservation
measure
Rating of
energy
consumption
At all
installation
Monthly As per standard
practice of BEE
4 Potability,
taste, odour
Groundwater
Quality
Parameters
as listed in
IS
10500:1991
Water intake
structure
Half
Yearly
Standard method
for the
examination of
water and
wastewater, 21st
Edition, edited by
Lenore S.
Clesceri, Arnold
E. Greenberg,
Andre D. Eton
5 Efficiency of
the STP (%)
Treated
effluent
Quality
pH, Color,
Odor,
Turbidity,
EC,
Alkalinity ,
Hardness,
STP Outlet Twice a
month for
1st three
months,
monthly
for next
Standard method
for the
examination of
water and
wastewater, 21st
Edition, edited by
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-61,
Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 216.
S.N Performance
Indicator
Component Parameters Locations Frequency Measurement
methodology
BOD, COD,
Total
Dissolved
Solids,
Suspended
Solids, Total
Coliform,
Volatile
solids ,
Heavy
Metals
three
months
and
quarterly
Lenore S.
Clesceri, Arnold
E. Greenberg,
Andre D. Eton
# - The performance of the proposed STP will be evaluated on a regular basis by the operator, in terms of quick
check of different physical and physicochemical parameters
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 217.
7.3.1 Data Analysis
The monitored data will be analyzed and compared with the baseline levels as established in the EIA
study and the regulatory standards specified by different government agencies. The standards against
which the different environmental components will be compared are as per Table 7.2.
Table 7:2: Applicable Standards for different Environmental Components
S.N Component Applicable Standards
1 Ambient Air Quality National Ambient Air Quality standards, CPCB
2 Noise Quality Ambient Air Quality Standards with Respect to Noise,
CPCB
3 Surface water quality Water Standards, CPCB
4 Groundwater quality IS: 10500 Standards, BIS
5 Soil Quality --
6 Treated sewage water quality IS 2490(1974) – Discharge into surface water, IS
3306(1974) – Discharge on land, IS 3307(1974)- Discharge
for agricultural use
7.3.2 Reporting Schedule
The monitoring results of the different environmental components will be analyzed and compiled
every six months during the construction phase and every twelve months during the operation phase.
The report will also list the project activities along with the environmental mitigation measures and
will evaluate the efficacy of the Environmental Management Plan.
7.3.3 Emergency Procedures/Corrective Measures
Corrective measures will be adopted if the review of the monitoring report reveals that the
environmental management plan is inadequate or has not been implemented properly. A detailed
review will be carried out by the interdisciplinary team of experts in the Environment Management
Cell for assessing the gaps in the EMP and the addressal of EMP. A corrective action plan will be
worked out for the environmental component and a rigorous follow up of environmental monitoring
plan will be carried out.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 218.
8 RISK ASSESSMENT & DISASTER MANAGEMENT PLAN
8.1 INTRODUCTION
A disaster is a natural or man-made (or technological) hazard resulting in an event of substantial
extent causing significant physical damage or destruction, loss of life, or drastic change to the
environment. A disaster can be ostensively defined as any tragic event stemming from events such as
earthquakes, floods, catastrophic accidents, fires, or explosions. It is a phenomenon that disasters can
cause damage to life, property and destroy the economic, social and cultural life of people. Disasters
in general, can broadly be grouped under three categories viz. (i) Water and Climate related (ii)
Geology / Geomorphology related and (iii) Accident related. On project site, accident related disasters
from fire, oil spills, and chemical induced and vehicular / operational accidents are quite possible. In
the context of the proposed project it thus becomes imperative to identify the type, pattern and the
potential severity of the hazards, which can cause loss of life, damage to property and environment,
and to assess the vulnerability and risks there from with a view to outlining an appropriate response
mechanism.
The proposed project site is located in Gurgaon district which is the sixth largest city of Haryana
State. For the last two decades, it has been on the faster pace of the development and emerged as the
industrial and financial hub of Haryana. Hazard Risk in Gurgaon are compounded by increasing
vulnerabilities related to the high population growth, rapid-urbanization, increasing Industrialization,
rapid development within high risk seismic zone (Zone IV), environmental degradation, climate
change etc.
Therefore, the Disaster Management Plan is required to encompass all the administrative and
operational programmes and responses to reduce the risk of emergencies of hazardous events likely to
occur at any point of time during construction and operational phases of the project.
8.2 HAZARD
Risk assessment is the systematic identification of the hazards associated with construction work and
the evaluation of the risks associated with those hazards. A hazard - risk assessment shall take account
of all the work activities and consideration shall also be given to anyone else who could be affected
by the work activities.
8.3 RISK
Risk is the “the combination of the frequency, or probability of occurrence, and consequence of a
specified hazardous event”. Where frequency of exposure is an issue then duration of exposure is also
considered. Risk is the level to which a hazard poses a threat to life, limb or property. This will vary
from a minor laceration to a permanent disability, an illness such as cancer, or death.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 219.
8.4 HAZARD IDENTIFICATION AND RISK ASSESSMENT DURING THE
CONSTRUCTION PHASE
The purpose of Hazard Identification and Risk Assessment is to identify all the significant hazards,
which may occur during the construction phase, and to rank them according to their severity. Having
ranked the risks by severity the measures shall be introduced to mitigate the effects of that risk.
Risk assessment analysis process shall identify certain activities for which detailed written method
statement or safe systems of work are required to ensure that the activities are properly controlled and
executed safely and without risk to health and the environment. All such written safe systems of work
shall clearly identify the objective, the sequence of operations, foreseeable hazards, precautionary and
protective measures required and shall be easily understood by the personnel who are to supervise and
carry out the work.
8.5 METHOD STATEMENTS
As a result of the Hazard Identification and Risk Assessment detailed method statements shall need to
be produced for medium and high risk activities including amongst others the following:
Concreting.
Scaffolding erection/dismantling.
Excavations.
Work in confined spaces
Temporary Works
Chemical Cleaning
Work on Energized Electrical Equipment
Craneage of items in excess of 1 tonne
Inflammable materials – the use and storage
Use and storage of explosives
8.6 SAFE WORK METHOD STATEMENT STEP BY STEP
A method statement should contain sufficient information to enable the task to be undertaken safely
and should contain as a minimum the following information
Company Name;
A description of the work activity or task to be undertaken;
The date the SWMS was developed;
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 220.
The name and signature of the person who developed the SWMS;
The project name/number and the name of the Principal Contractor;
The job steps involved in doing the work;
Potential Class 1 and Class 2 hazards associated with the job task to be undertaken;
The controls that will be put in place to eliminate or minimise the potential hazards identified;
Controls as high as practicable on the “best” to “worst” control guide; and
The name of the person/s responsible for ensuring that the control/s is in place.
a description of the work to be undertaken
the step by step sequence in doing the work
the potential hazards associated with the work and with each of its steps
the safety controls that will be used to minimise these hazards
all precautions to be taken to protect health and safety
identification of all health and safety law, standards or codes applicable to the work, and
where these are kept on the worksite
the names and qualifications of those who will supervise the work and inspect and approve
work
description of work area, work methods, protective measures, plant, equipment and power
tools
a description of what training is given to people doing the work
identification of plant and equipment needed on site to do the job eg ladders, scaffolds,
electrical leads, welding machines etc
details of the inspection and maintenance checks that will be, or have been, carried out on the
equipment listed
Site Safety Rules.
Where contractors and or sub-contractors are employed on the project, shall provide similar
assessments covering their respective operations and all Hazard / risk assessments shall be reviewed
and necessary revised as circumstance change.
8.7 PERMITS TO WORK
The Contractor shall develop a permit-to-work system, which is a formal written system used to
control certain types of work that are potentially hazardous. A permit-to-work is a document, which
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 221.
specifies the work to be done, and the precautions to be taken. Permits-to-work form an essential part
of safe systems of work for many construction activities. They allow work to start only after safe
procedures have been defined and they provide a clear record that all foreseeable hazards have been
considered. Permits to Work are usually required in high-risk areas as identified by the Risk
Assessments.
A permit is needed when construction work can only be carried out if normal safeguards are dropped
or when new hazards are introduced by the work. Examples of high risk activities include but are not
limited to:
a) Work close to 25kV overhead Catenery
b) Entry into Confined Spaces. (SAF 010)
c) Work In Close Proximity to Overhead Power lines and Telecommunication Cables.
d) Hot Work.
e) To dig—where underground services may be located.
f) Work with moving construction locomotives.
g) Working On Electrical Apparatus.
h) The permit-to-work system should be fully documented, laying down:
i) how the system works;
j) the jobs it is to be used for;
k) the responsibilities and training of those involved; and
l) how to check its operation;
The permit-to-work form must help communication between everyone involved. It should be designed
by the Contractor issuing the permit, taking into account individual site conditions and requirements.
Separate permit forms may be required for different tasks, such as hot work and entry into confined
spaces, so that sufficient emphasis can be given to the particular hazards present and precautions
required.
The permit to work form should contain:
a) clear identification of who may authorise particular jobs (and any limits to their authority);
b) clear identification of who is responsible for specifying the necessary precautions (e.g.
c) isolation, emergency arrangements, etc);
d) a detailed description of the task clearly identifying the work to be done and the associated
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 222.
hazards;
e) plans and diagrams be used if appropriate to assist in the description of the work to be done,
its location and limitations;
f) identity of the hazards and the precautions to be taken;
g) clear rules about how the job should be controlled or abandoned in the case of an emergency;
h) the time limitations should be stated;
i) job specific toolbox talk conducted by the supervisor
A Permit to Work authorisation form shall be completed with the maximum duration period not
exceeding twenty four hours.
A copy of each Permit to Work shall be displayed, during its validity, in a conspicuous location in
close proximity to the actual works location to which it applies.
A pre-permit activation job specific toolbox talk shall be conducted by the supervisor including
amongst others the following.
a) All identified hazards are explained;
b) Risk mitigation process clarified;
c) Method of work explained stressing points (a) and (b) above;
d) Emergency response procedure is clarified and persons assigned tasks in the event of an
emergency;
e) PPE requirements including PPE serviceability checks and training if required;
All workers and supervision shall attend the toolbox talk and sign the toolbox attendance register.
Any person/s coming late to the work site shall be given the toolbox talk and sign the attendance
register
8.8 RISK ASSESSMENT DURING THE OPERATION PHASE
8.8.1 Earthquake Hazard
The entire region of Gurgaon falls in high risk seismic zone IV and corresponds to MSK intensity
VIII making it highly vulnerable to Earthquakes. The major tectonics features affecting Gurgaon are
as follows:
The Sohna Fault
Junction of Aravali and Alluvium near Delhi
Moradabad Fault
Delhi Moradabad Fault
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 223.
Delhi-Haridwar Fault
Although no major earthquake have occurred in Gurgaon in recent year, yet tremors have been felt
whenever there is an earthquake in the Himalayan foothills. The NCR has fairly high seismicity with
general occurrence of earthquakes of 5-6 magnitude, a few of magnitude 6-7 and occasional incident
of 7.5-8.0 magnitude shocks. Subsequent traumatic events have occurred in 1803, 1819, 1905, 1924,
1937, 1945, 1949, 1958, 1960, 1966, 1975, 1980 and 1994 during which the intensities level on
Richter scale between VII and IX are believed to have been experienced as indicated by the damage
pattern. The most important earthquake which affected Gurgaon was on 27th August, 1960 with the
magnitude of 6.0. The epicentre of this earthquake was between Delhi cantonment and Gurgaon.
8.8.2 Drought
Rapid industrialization, urbanization and withdrawal of huge ground water are leading factors for the
occurrence of drought in Gurgaon district. The droughts in 1987 & 2001 were worst droughts in the
state of Haryana. Gurgaon receives most of its rainfall from the ‘summer’ monsoon and continuous up
to the middle of August. The summer monsoon sets during the month of July and starts withdrawing
from the end of August or first week of September. Due to this uncertain rainfall pattern the entire
district receive less than one month of rainy session. Hence the department of agriculture and
cooperation, ministry of agriculture and government of India has categorized Gurgaon in chronically
in drought affected area.
8.8.3 Flood
The main cause of flood in the Gurgaon district can be attributed to the heterogeneous topography. As
such there is no perennial river in the district, on the other hand a number of Barsati Nallahs/Hills
torrent are found, which criss cross the entire region and become the cause of floods during rainy
season. Besides this, rapid urbanization in the district also leads to floods because heavy pressure of
the existing infrastructure development over the natural drainage system. Low lying areas of Gurgaon
are under the threat of water logging even if there is a minor rain.
8.8.4 Fire
The short circuits, LPG blasts and chemical industrial fire are the major reasons to worry in the
district. Most of the reported accidents are in the city of Gurgaon, mainly due to the inadequate safety
measures in the electrical installation and chemical and LPG blasts, as well as careless practices while
handling and storage of inflammable materials. However, a broad identification of the types of
locations where there is a positional threat of fire is possible. These are:
Storage area of flammable/explosive material in the vicinity of populated area;
Multi storey buildings especially in the cities, with inadequate fire safety measures;
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 224.
Narrow lanes, congested and overcrowded buildings, and old building with poor internal
wiring.
The facilities in each fire station are appropriate to the municipality’s financial position. However,
due to the paucity of funds in most municipalities, except in Gurgaon city in the district, the fire-
stations are poorly equipped. In addition to combating fire related hazards, fire frightening services
are also required during building collapse, road accidents, and industrial hazards and earthquake etc
Therefore, the need for a well equipped, well maintained, and adequate fire station cannot be under
estimated.
8.9 DISASTER MANAGEMENT PLAN FOR CONSTRUCTION PHASE
Disaster management plan prepared to avoid any risk assessed during the construction phase has been
discussed below
Scaffolding at site is considered as one of the major hazards at a construction site and can be
mitigated by following measures
a. Inspection and certification (tagging) of the erection.
b. Intermediate guard rails,
c. Barrier and warning notices,
d. Regular inspection of the scaffold.
e. Provision of toe guards to prevent items from rolling over the edge
Power access equipment causes hazards and should be managed by using good quality tools as
well as regular maintenance.
Hazard of ladder can be mitigated by proper erection and regular check up and vigilance during
use of ladders.
a. Secure fixing
b. ladder condition,
c. position and foundation,
d. suitability
e. Slippery sideways.
Plant and machinery hazards are very major and can be mitigated by using proper pre-approved
and certified equipment with regular periodic maintenance.
Fire and Emergency is one of the most common hazards at construction site, this can be
mitigated by
a. availability of extinguishers,
b. reducing the possibility of ignition sources,
c. provision of exit alarms,
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 225.
d. personnel awareness of the risks
e. emergency procedures
f. regular training of responsible “fire marshals”
Hazardous Substance is considered as a low risk hazard but should be taken care by preserving
the material at right place and in approved conditions.
8.10 DISASTER MANAGEMENT PLAN FOR OPERATION PHASE
8.10.1 On Site Emergency Management Plan
Earthquake
Spatial and temporal impacts of earthquake are large. Resource requirements are both intensive and
extensive for management of earthquake. Though the project impact area comes under seismic zone-
IV, the probability of occurrence of earthquake in future is not ruled out. In the case earthquake occur,
following management plan will be adopted:
Since earthquake is the most uncertain natural occurrence giving birth to massive calamities on
both life and property, adequate care has been taken into account while designing the
infrastructure facilities for the proposed site as per seismic zone.
Extensive rescue operations are required to shift the injured persons to the nearest medical units
and evacuate the trapped individuals to safer places. Appropriate medical services are necessary
to control epidemics in the post earthquake period.
Suitable steps on war footing basis need to be adopted to restore all the essential services like,
electricity, water and food supply, telecommunication, transportation, etc. Proper steps should
also ensure the protection and safeguard of properties.
Damage to road access due to landslides/land subsidence would need immediate clearing for
which operations in close coordination with the concerned departments/agencies in the district
will have to be made.
Areas indicating signs of liquefaction should be declared out of bounds and district vigil should
be kept to prohibit trespassing.
Foundations of the structures prone to liquefaction will require technical assessment.
Alteration in the river, creek and canal water flow that may inundate the site areas would
require immediate evacuation of people and properties in coordination with the district
authorities.
Fire
Though fire in general is a localized problem it may assume unmanageable proportions if immediate
care is not taken. Following management plan shall be adopted:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 226.
Storage of fuel will be as per the rules and guidelines as laid down in the relevant statutes.
Adequate fire safety equipments e.g. extinguishers, dry chemicals, carbon dioxide, foam spray;
water spray should be kept in the complex.
IS codes for cables to be applied for preventing short circuits in wiring.
Adequate Immediate actions call for the extinguishing of fire by using proper devices
necessary, depending on the nature of the fire keeping in consideration that the fires are not
spread further to cause greater loss of life and properties.
Immediate rescue operations will be initiated for which assistance of the local fire service
authorities to be sought.
Emergency medical attention will be extended to the affected / injured persons immediately.
Serious burn cases should be transported to General hospital in town or private health care units
in the vicinity.
Despite all efforts and the measures provided for, it is within the realm of possibility that emergencies
and accidents can take place. The primary objective of Emergency Management Plan is to defend the
men, material and property against such hazards and restore normalcy as soon as possible. An
Emergency Management Group (EMG) is thus constituted with such objective and to provide help to
those in need in the times of disaster. The EMG constitutes of personnel having various duties and
responsibilities which work in tandem with each other and proper hierarchy to mitigate the adverse
impacts of disasters and return to normalcy with immediate effect. All the personnel of EMG operate
through Emergency Control Centre (ECC) that is a nodal point for all communications and record of
observations and data logging.
8.11 KEY PERSONS AND RESPONSIBILITIES
For effective handling of the emergency, there will be a designated Site Main Controller (SMC),
Work Incident Controller (WIC) and various other key persons. The key responsibilities of all the
personnel that form the part of EMG are as follows:
8.11.1 Site Main Controller
He will report to the Emergency Control Center and will assume overall responsibility of the site and
its personnel. The main duties of SMC comprises of:
Assessing the magnitude of the situation and decide whether a major emergency exists or is
likely to develop, requiring external assistance.
Inform District emergency chief (i.e. District Collector) accordingly.
Ensure that the key personnel are called in promptly.
Maintain a continuous review of possible developments and assess these to determine most
probable course of events.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 227.
Assume the head of ECC and oversee all the functions are performed as planned.
8.11.2 Work Incident Controller
The WIC will report to the SMC and would act in such a manner as to manage the hazardous
situation, put in control and mitigate. The main duties of WIC comprises of:
Exercise direct operational control of the affected area.
Ensure the accounting for personnel and arrange for non essential workers to be sent to
assembly point.
Arrange for a chronological record of the emergency to be maintained.
Establish communication link with the ECC (through phone or messenger) and keep the SMC
informed about the developments at the incident site
8.11.3 Safety Coordinator
The Safety Coordinator would assist the WIC in removal of unsafe situations and act as overseer to
monitor that all the activities for emergency management are performed safely and will not escalate
the situation.
8.11.4 Medical Officer
The M.O. will rush to the scene of emergency on receipt of information and ensure that casualties are
receiving adequate help. The WIC is to be informed of the steps taken and seek advice for further
mobilization of medical resources from within and outside the site.
8.11.5 Maintenance Support Officer
He will provide assistance as per the demand of WIC / Safety Officer and will be responsible for
electrical supply cut-off / restoration and other mechanical and workshop help.
8.11.6 Civil Support Officer
His responsibility is to provide fabrication/construction manpower for any demolition/ construction as
per the emergent situation and provide temporary barricade to the affected location.
8.11.7 Material Support Officer
He has to ensure that the stores remain open through out the period of emergency for providing
material assistance together with providing assistance to the Maintenance Support officer and Civil
Support officer for receiving adequate supplies of machinery spares and material.
8.11.8 Area Staff
They will ensure removal of non essential workers to the assembly points and will facilitate Roll
Caller to verify the causality.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 228.
8.11.9 Running Messengers
Running messengers will act as per the direction of respective key personnel.
8.11.10 Employees
All the employees are responsible to inform their section in charge about the mishap. The employees
of the emergency area except involved in the emergency handling must assemble at the designated
assembly points.
8.11.11 Technical Coordinator
The persons in charge of the respective sections are designated as Technical Coordinators. They will
ensure that all operations are put in safe and standby condition.
8.11.12 Utilities Coordinator
The utilities coordinator will hold the responsibility of examining and assessing the requirement of
water for the purpose of fire fighting and other requirements like drinking and processing water. If
required, he will shut down the main power supply to the site and arrange for safe backup power in
the affected area and the emergency control center.
8.11.13 Liaison and Public Relations Coordinator
The liaison and Public Relations coordinator may be a separate person or the duties may be performed
by SMC only. He will liaise with local police/ law enforcing authority, District Collector, Chief
Medical Officer, District Fire Officer, etc. for possible help, if needed.
8.11.14 Transportation Coordinator
The transportation coordinator will have the responsibility of ensuring that all vehicles are in good
state of repair and maintain a log of all vehicle movement and remain standby for any immediate
situation.
8.11.15 Communication Coordinator
Communications officer will provide information to the emergency services as directed by SMC and
shall have all available means and messengers to communicate.
8.12 EMERGENCY PREPAREDNESS
In addition to planning and delegating responsibilities to the identified key persons, the proposed land
parcel will be adequately equipped in terms of safety equipment and facilities in order to be
completely prepared for combating emergencies.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 229.
8.12.1 Fire Detection and Fire Fighting
All the fire risks in the site like electrical substation, etc. will be adequately armed with fire detection
systems and will be equipped with fire extinguishers.
8.12.2 Personal Protective Equipment
The PPEs act as last line of defense and provide physical protection to the personnel. Sufficient
supplies of PPEs like helmets, gloves, ear muffs/plugs, face mask, fire escape masks, water gel
blankets, goggles etc. will be maintained at the proposed site.
8.12.3 Communication System
Communication facilities play a key role in notification, coordination and even for calling external
help during emergency situations. In view of this, adequate communication arrangements shall be
made as given below:
External telephones
Facsimile
Internal telephones in all sections
Public Address System
Walkie-talkies
In addition to the above, a siren with adequate audible range to cover the entire site will be available.
8.12.4 Training
Workers will be trained in fire-fighting and safety aspects through demonstration exercises and mock-
drills.
8.12.5 Emergency Control Center
It is necessary that the emergency is controlled from one specific point so that all the inputs are
available at the Emergency Control Center (ECC). At ECC a list of emergency telephone numbers,
communication facilities & necessary documents for emergency management will be available.
8.13 EMERGENCY MANAGEMENT PROCEDURE
It has been observed that pre-planned and practiced procedures for management of emergency
substantially reduce the damage potential of an accident. Thus, for any facility it is necessary to have
clear-cut procedures for different functions of emergency planning and management.
All occupants within the land parcel will be authorized to report the emergency. If the incident is of a
serious nature, the security in-charge of the shift will contact the site in-charge to report the situation
who will then mobilize suitable personnel to asses the situation and declare the emergency
accordingly. The SMC shall perform the following broad duties:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 230.
Emergency Shut-Down
Accounting of Personnel
Evacuation
Rehabilitation
Inform relatives of the affected people
Terminate the emergency procedures
These will be followed by:
Head count of all the individuals at the assembly point.
Constitution of the committee to investigate the cause of disaster, which will submit a detailed
report of the findings.
Based on the findings and lessons learned during emergency, the on-site plan will be suitably
modified to make it more effective.
Mock-drills will be carried out on the on-site plan to check its effectiveness and for
identification of areas for improvement.
Regular training programs through audio-visual aides will be conducted to enhance the
preparedness of all workers, specially the emergency combat personnel.
8.14 OFF-SITE EMERGENCY PREPAREDNESS PLAN
Off-site emergency plan follows the on-site emergency plan. When the consequences of an emergency
situation go beyond the site boundaries, an off-site emergency comes into play. Off-site emergency is
essentially the responsibility of the public administration however; the site management will provide
public administration along with technical information relating to the nature, quantum and probable
consequences on the neighboring population.
The off-site plan in detail will be based on those events which are most likely to occur, but other less
likely events which have severe consequence will also be considered. Incidents which have very
severe consequences yet have a small probability of occurrence should also be considered during the
preparation of the plan. However, the key feature of a good off-site emergency plan is flexibility in its
application to emergencies other than those specifically included in the formation of the plan.
The main aspects which should be included in the off-site emergency plan are:
Organization/ hierarchy
Communication systems
Specialized knowledge experts or agencies
Voluntary organizations
Meteorological information
Humanitarian arrangements
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 231.
Public information
Assessment of emergency plan
8.14.1 Emergency Code of Practices
The following are the code of practices (COP) that will be followed by IREO during the disasters
from natural hazards which can affect the proposed land parcel:
Objective
To provide relief to the affected people in quick and efficient manner
Earthquake Preparedness
The earthquake susceptibility in the proposed land parcel will be studied and the earthquake
protection measures will be accordingly incorporated in the building design stage itself.
Line of Action
Earthquakes are situations that do not affect a particular identified location. Thus, after the earthquake
the SMC will perform the following duties-
Patrolling of sensitive locations and the entire facility
Instruct communication officer to contact all department heads to give status of their respective
areas, men and machinery.
If any help is sought at some place, mobilize the resources accordingly
Immediate attendance of all the staff and visitors
8.14.2 Fire fighting COP
Objective
The main objective of this Code of Practice is to detect the source and location of the fire and
extinguish followed by the evacuation of victims and goods to a safe area.
Fire fighting Preparedness
The critical areas should be provided with fire alarm, extinguisher and automatic fire hydrant system.
Caution and awareness signage shall be strategically installed at regular interval in those areas.
Line of Action
Immediately on the breakout of the fire, the following line of action shall be adopted:
To reach the location of crisis at the earliest
To identify the source of fire and take necessary action to diminish the cause
To make sure all the fire automatic fire hydrants are operational
To evacuate the area as early as possible
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 232.
Instruct communication officer to contact all department heads to give status of their respective
areas, men and machinery.
Immediate attendance of all the staff and visitors
Providing of medical on site aid to affected people
Call ambulance on immediate basis for the affected people and send them to nearest hospital
8.15 MANAGEMENT FRAMEWORKS AND CONCLUSION
The overarching objective of the project is the economic development of the region / State/ country
and improvement in the quality of life of the local population in general. It therefore becomes
necessary to develop an appropriate response mechanism, which would act in close coordination with
the District Collector / DDMA of the district. For this purpose, the authority should set up a Disaster
Management Cell with a small team of dedicated personnel trained in relief and rescue operations
required for the anticipated emergencies. In addition to the above the following should be undertaken
by the authority.
Extensive afforestation programme will be undertaken with appropriate native species as per
guidelines of CPCB.
Timely warning to the local residents will be made through an effective communication system.
Timely alerting the key personnel in Disaster Management Cell of the district for taking
emergency action.
A Disaster Management Committee will be set up involving all the stakeholders particularly the
local community and NGOs and a list of personnel with allocated responsibilities will be kept at
the office and in all the concerned local body offices.
All power supply lines and connections, public address systems, etc. will be thoroughly checked
before onset of the monsoon months and special mock drills should be will be organised to put
all concerned on alert.
The administrative machinery of the project along with local NGOs will organize regular
awareness campaigns with the help of the local authorities where women and school children
from the community should be involved. Involvement of NGOs is necessary in mobilizing
community efforts for the control of epidemics by ensuring standards of environmental
sanitation, disposal of waste and personal hygiene.
The buildings in the project site will be allowed to be used as safe shelters during emergencies.
Volunteers’ Handbook for Disaster Preparedness of the UNDP will be circulated during
awareness campaigns.
8.15.1 Coordination with Concerned Authorities
The policy of the Govt. of India emphasizes on sustainable disaster/risk reduction in all states/UTs by
building capacities at all levels to institutionalize disaster risk management in the country. For
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 233.
strengthening the overall capacities for emergency/disaster response in the country, the Govt. of India
is systematically assessing the existing systems at the national, state and district levels. Mock drills
with the community should be carried out regularly which may be helpful while formulating the
disaster response mechanism by the authorities.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 234.
9 CORPORATE ENVIROMENT RESPONSIBILITY
9.1 ENVIRONMENT POLICY
As mentioned earlier in Chapter 1, M/s Commander Realtors Pvt. Ltd. is one of the subsidiary
companies of Ireo Pvt. Ltd (IREO). All the policies and standard operating procedures followed by
Ireo Pvt. Ltd. are applicable to and are abide by all its subsidiary companies.
The IREO, along with its all subsidiary companies, has its own Environment, Occupational, Health
and Safety (EHS) Policy that focuses on the commitment to excellence in Environmental,
Occupational Health and Safety stewardship of all its activities and services. The Policy shows the
organization commitments towards:
1. Compliance to all applicable EHS legislation, statutory and regulatory requirements
2. Continual enhancement of EHS performance through sound practices.
3. Design, build and operate its facilities in an environmentally responsible manner, conserving
energy, water, other natural resources; minimizing waste generation and preventing pollution
thereby contributing to environmentally sustainable growth.
4. Accountability for ensuring a safe and healthy environment.
5. Providing training, awareness and resources to accomplish above mentioned EHS
commitments.
The commitment made under the above said policy is applicable to M/s Commander Realtors Pvt. Ltd
and is being followed as it is.
9.2 STANDARD OPERATING PROCEDURES
As said above M/s Commander Realtors Pvt. Ltd will strictly abide by the IREO’s standardized
operating procedures for project planning and execution phase of the project. The standard operating
procedures (SOP’s) have been divided under five heads based on project stages as follows:
Stage 1. Project Concept and Definition
Stage 2. Feasibility Study
Stage 3. Design Brief and Appointment of Consultants
Stage 4. Design Development and Production of Good for Construction (GFC’s) Drawings
Stage 5. Project Execution
The Annexure 9.1 Shows the process flow of above mentioned stages along with the inter-linkages of
various department s and inputs to be provided at all five stages.
9.3 HIERARCHICAL SYSTEM OF THE ORGANIZATION
The hierarchical system of the M/s Commander Realtors Pvt. Ltd is presented in Figure 9.1.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 235.
Figure 9.1 Hierarchical System of the Organisation
9.4 REPORTING MECHANISM OF NON-COMPLIANCE
M/s Commander Realtors Pvt. Ltd has team of qualified environmental experts personals to ensure the
implementation of environmental requirements. The environmental team proposes to conduct site
inspections as site requirements. Any non-compliance during the site inspections will be reported /
closed as per the reporting mechanism given in Figure 9.2.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 236.
Figure 9.2 Reporting Mechanism of Non-Compliance
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 237.
10 DISCLOSURE OF EIA PREPARES
The EIA report has been prepared as per approved ToR by the experts of :
1. The Project Proponent – M/s Commander Realtors Pvt. Ltd
2. EIA Consultants – GreenC India Consulting Pvt. Ltd.
10.1 THE PROJECT PROPONENT - M/S COMMANDER REALTORS PVT. LTD.
The name of experts of Project Proponent and there brief resume are as given below:
S.No Expert Name Education Qualification Area of Expertise Experience
1. Dr Asha Sharma Ph.D, M.Sc. Hons (Gold
Medalist) and B.Sc. Hons
EIA Cordinator & Team
Leader
+30 Years
2. Arijit Das B. Arch & BEM Architect/ Planning 18 years
3. Mukut Sharma B.E. (BITS Pilani) - Hons Infrastructure Planning 28 Years
4. Rajiv Piparia B. Tech – Civil Engg, IIT-
Kanpur Structure 27 Years
5. Geetha Manoj B.Tech (Civil) Plumbing & Fire Fighting 21 Years
6. Santosh A George B.Tech (Agriculture), M.
Arch (Landscape) Landscape 23 Years
7. Ashok Chaudhary B. Arch Land & Revenue 16 Years
8. Abhishek Sharma B. Arch Architect/ Planning 16 years
9. Richa Sharma B. Arch & PGDPM (CM-
NICMAR) Architect/ Planning 7 Years
10. Prashant Jain B.E. (Civil), PGD
(NICMAR) & MBA (IMI) Infrastructure planning 12 Years
11. Pankaj Jain M.E. (Env. Engg.) B.E.
(Civil) Infrastructure planning 18 Years
12. Vikas Chand
Sharma
M.Plan (Env. Planning) &
BE (Env Engg.), IGBC
EIA study & Green
Building 13 Years
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 238.
S.No Expert Name Education Qualification Area of Expertise Experience
(AP)
13. Saket Verma M.SC (Env. Science) &
B.SC (PCM)
EIA study & Env.
Monitoring Coordinator 12 Years
14. Kamal kant Ujinwal M Tech (Env. Engg.) &
BE (Agriculture)
Environment Monitoring
& Survey 6 Years
15. Renu Singh
B.Arch, IGBC (AP),
GRIHA Trainer,
LEED Green Associate
Green Building & Energy
Simulation 8 Years
16. Neha Prakash M.BEM & B.Arch, IGBC
(AP)
Green Building & Energy
Simulation 3.5 Years
17. Varidhi Sharma
M.Tech (Energy & Env.
Mgt) & B.Tech (Bio-
Technology)
Env. Baseline Study 3 years
18. Environment Monitoring Laboratory ITL Labs Pvt. Ltd.
(NABL/MoEF Accredited)
19. Architect Consultant SCDA Architect Pte. Ltd.
20. MEP Consultant CP Vidya & Associates.
21. EIA Consultant GreenC India Consulting Pvt.Ltd.
10.2 EIA CONSULTANTS – GREENC INDIA CONSULTING PRIVATE LIMITED
GreenC India Consulting Private Limited (Formerly known as GIS Enabled Environment & Neo-
Graphic Centre) (hereinafter referred to as "GCPL") is an ISO 9001:2008, 14001:2004, OHSAS
18001 and NABET certified company with a vision to take up paradigm of development planning in
sustainable economic development and environment protection. The primary aim of the company is to
sensitize policy planner and local people about their development needs through capacity building
process. The main objects of the Company are as follows:
To carry on the business of providing all types of consultancy services not limited to social and
environmental assessment, environment action plan, tribal development plan, resettlement and
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 239.
rehabilitation action plan, project information report, Detailed project report, Need Assessment
Report, Corporate Social Responsibility, Forest Diversion Plan, Wildlife Conservation Plan,
Environment, Social & Land related legal services and any other consultancy services & Studies
related to Urban Development, Rural Development, Environment, Forest and Legal aspects.
To provide consultancy services in environment monitoring, sample collection of Air, Water, Soil,
meteorological data’s and publish testing results for the collected samples
To Undertake research study not limited to the field of Environment, Social, legal, agriculture,
Urban Planning, Rural Planning, Alternate Sources of Energy etc and provide
consultancy/advisory/Training services in these field to Government, Quasi-Government, Non-
government and private institutions.
To providing consultancy services not limited to social and environmental standards, grievance
Mechanism, action plan and management system, review and categorization of the project and
independent review and monitoring of all the acts and things necessary for the attainment of above
objects.
To provide IFC performance standard not limited to labour and working conditions, EPFI reporting,
Drainage Plan and Hydrogeology, environmental and social impact Assessment according to IFC
guidelines and equator principles.
To provide consultancy services to Government, Quasi-Government, Non-government, private
institutions etc in field no limited to Environment, Social, legal, agriculture, Urban Planning, Rural
Planning, Alternate Sources of Energy etc. in all stages of project cycle i.e Project
conceptualization, Project planning, Project execution, Project operation.
The technical resources within GCPL include many engineering disciplines, physical and natural
sciences, mathematics, statistics, and computer sciences. One of our strengths is our desire to
continually build upon our abilities in our areas of technical expertise, providing exceptional
knowledge and insight into our clients needs. This concentrated technical effort is looked upon
favorably by our clients that continually uses our services and retain us as technical experts.
10.3 AREA OF EXPERTISE (GCPL)
Environmental Impact Assessment: GCPL have done many EIA studies and clearances for
Building Construction Sector, Thermal Power Plant; Road & highways; Special Economic Zones
(SEZs); Urban Infrastructure Projects etc. The areas of specialization are as follows:
Environmental Management Plan
Disaster Management Plan
Risk Assessment
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 240.
Rehabilitation & Resettlement Plan
Pre-feasibility Report
Detailed Project Report
Geo-Technical Investigation
National, Regional and Urban Plans
Management Information System and Geographic Information system
Urban Infrastructure Development including Water Supply and Solid Waste Management
Environmental Monitoring and Assessments
Impact Assessment Formulate Policies & Mitigation Measures R&R
Natural Resource Management
Terminal Planning and Design
Institutional Strengthening
Development, Functional and Strategic Planning and Design
Preparation of Manuals
Conduct of Training Programmes
10.4 QCI/NABET ACCREDITATION STATUS OF THE EIA CONSULTANT
As on date, Greencindia Consulting Pvt. Ltd. has been granted accreditation by the Quality Council of
India / National Accreditation Board for Education & Training (QCI / NABET) in 9 sectors vide
Certificate No. NABET/EIA/RA014/041 valid up to February 18, 2017. The certificate of
accreditation is enclosed below:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 241.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 242.
10.5 BRIEF RESUME OF TEAM MEMBERS
GCPL comprises of group of professionals drawn from development related fields. The core
members of GCPL team hold experiences in Developmental Planning, Pollution Control, Economic
Analysis, Social Work and Information Technologies. In addition there is a panel of senior associates
and young voluntaries facilitating the various programmes. The brief resume of the Environment
Coordinator and Functional Area experts are discussed below:-
Rahul Singh (EC): Mr. Singh is the EIA coordinator of the Infrastructure projects and has an
experience of 12 years. He is a coordinator with rich experience in city planning, site planning,
terminal designs and preparation of environment reports and management plant. He has numerous
national and international projects related in his credit. He has in depth understanding of environment
legislations applicable in India and has also undertaken an assessment of legislative framework on the
development projects.
Ankur Agarwal (AFAE-LU): Mr. Agrawal has an experience of 7 years in field of Landuse
Planning and is Planner with rich experience in site planning, and preparation of Map. He has in depth
understanding of environment legislations applicable in India and has also undertaken an assessment
of legislative framework on the development projects.
AP Singh (FAE- WP & RH): Mr. Singh has a rich experience of 42 years in field of environment
and safety. He has conducted Environment Impact Assessment , study for greenfield as well as
expansion/modernization of Nitrogenous and Phosphoric Fertilizers Plants and Power Plants w.r.t to
fly ash/grit re-firing, fly ash & grate ash handling & disposal system & implementation of its
mitigation measures & to introduce surplus Coke Oven Gas to minimize dust pollution in Power
plant.
He has co-ordinate work related to HSE for IFFCO Fertiliser plants & was Technical advisor,
National Safety Council (UP Chapter). Mr. Singh has conducted studies related to Hazard
Identification & Risk Analysis of Nitrogenus and Phosphatic Fertiliser Plants, Petroleum Storages,
Gas pipelines, chlorine storage & handling etc using “ Building Block Principle”, Dow/ Mond Index
etc using mathematical analysis, TNO, ALOHA models & Conducted Risk Analysis and HAZOP
studies for Ammonia Storage, Petroleum Storage tanks and LPG storages, including Preparation &
mock drill of Onsite Plan, Safety Audits, Safety Reports, Compliances of Factories Acts & Rules.
Delivered talk on “Quantitative Methods of Risk Assessment at National Level Seminar conducted by
FAI.
Nilanjan Das (FAE-SE): Mr. Das has 17 years of experience and acquired expertise in rural habitat
planning through understanding people’s perception. He has worked on various rural development
projects in villages of Orissa, West Bengal and Gujarat. His area of expertise includes Socio-
Economic Study, R&R Plan, Participatory Rural Appraisal Technique, forestry and rural development
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 243.
planning principles. As part of EIA activity, Mr. Das has been involved in more than 25 EIA Studies
and has prepared Socio-economic Studies, Social Impact Assessment and Management Plan. He has
also been actively involved for more than 15 R&R Reports.
Sanjay Singh (FAE-NV): Mr. Singh has an experience of more than 20 Years in field of
Environment Impact Studies. He has working experience on more than 50 projects in the field of
Environment Impact Assessment Studies. He is having NABET Accreditation for NV. His primary
strength is the quantitative assessment of noise and vibration study in the field of mining, railway and
construction projects. He is well versed with the Indian Legislative Framework for Environment.
Dr. PC Kuniyal (FAE-EB&SC): Dr. Kuniyal has 7years of experience in study of ecology in
himalayan and sub-himalayan region. He has in-depth insight in study and interpretation of flora and
fauna species across various climatic zone of country. He has specific training in field of impact
assessment and ecological monitoring. He also has working experience of the application of
taxonomy in resource inventory in numerous projects across country. Dr. Kuniyal also have
experience in assessment of fertility and characterization of soil and assess the impact of gaseous,
liquid and solid pollutants on the soil in large and medium size projects.
Dr. Manoj Kumar (FAE-HG & GEO): Mr. Manoj has 20 years of National & International
experience in the field of geology and involved in more than fifty projects across country to study the
geology and hydrogeology of the area with respect to aquifer characteristics, determination of impact
of ground water withdrawal of groundwater and suggested mitigation measures. He has also
developed geological maps by undertaking geology & geo-morphological analysis in the projects
undertaken by him. He has also involved in mining development incorporating environmental aspects
like top soil preservation, waste dump management, reclamation/rehabilitation of mined out areas in
various states of country.
Dipannita Das (AFAE-AP, AQ & SHW): Ms. Das has 3 years experience in the study of Air
Quality Assessment & Air Pollution Assessment and was involved in several EIA project as well as in
construction project. She has also experience in the field of Solid & Hazardous Waste Management.
10.6 ENVIRONMENTAL MONITORING LABORATORY
M/s ITL Labs Pvt. Ltd. has been hired for the environmental baseline monitoring carried out for the
proposed project. M/s ITL Labs Private Limited is a recognized and approved laboratory by Ministry
of Environment and Forests, Govt. of India for specialized testing and analysis of samples from their
laboratory. It is well equipped with the sophisticated & versatile analytical instruments & having
updated technology for various analytical applications in the field of environment. It provides a wide
range of services in the following area of environment:
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 244.
Monitoring & testing of Atmospheric Air; Process Emissions; Water; Wastewater; Solid
Waste; Toxic & Hazardous Wastes; Noise & Vibration etc.
Complete Arrangement for Testing of Industrial Gases.
Site Survey & Industrial Risk Assessment including Disaster Management; Hazardous
Management etc.
Biological & Socio - economic studies.
Environmental Impact Assessment.
Environmental Management Plan (EMP) & Environmental Audits.
Micro meteorological Data.
Dispersion Modeling.
Estimation of Priority Pollutants in Environment
Soil Characterization
The copy of MoEF accreditation of ITL Labs Private Limited is enclosed as Annexure 10.1.
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 245.
11 SUMMARY & CONCLUSIONS
11.1 INTRODUCTION
M/s Commander Realtors Pvt. Ltd., proposing to develop Independent Floors at Sector 61, Village
Ullawas, Tehsil Sohna, Dist. Gurgaon, in the State of Haryana as a part of its vision to develop state-
of-the-art infrastructure for the Nation. The establishment of the project will bring more
developmental activities in the area and there will be an enhancement in the living standards of local
people.
An Environmental Impact Assessment (EIA) study report has been prepared for this project based on
baseline environmental quality data in the project area. Identification & prediction of significant
environmental impacts due to proposed project along with Environmental Impact Statement followed
by delineation of appropriate Environmental Management Plan are included in EIA Report.
The Summary and Conclusions summarize the findings of the EIA study undertaken in accordance
with the EIA guidelines on similar developmental projects.
11.2 PROJECT DESCRIPTION
11.2.1 Salient Features of the Project
The salient features of the project are discussed below:
Total land requirement : 18.138 acres (73,401.77 sq m)
Major facilities : Independent Floors (S+3) along with basic
infrastructure.
Common facilities : STP, storm water network, Electric sub-station &
Waste Treatment plant
Water Requirement :
Construction phase 80 KLD for construction activities (Treated Water
from HUDA STP)
70 KLD domestic consumption for construction
labors (tanker water)
Operation phase : Total water requirement is 480 KLD.
Fresh water requirement is 231 KLD to be met from
municipal public supply,
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 246.
Remaining water requirement will be met from
treated effluent obtained from STP
Waste water generation :
Construction phase 57 KLD (construction phase) from labour camps
Operation phase 277 KLD (operation phase)
STP Capacity : STP capacity : 320 KLD
STP Technology : Membrane Bioreactor along with provision of UV
treatment
Solid Waste generation :
Construction phase 0.170 TPD MSW (labor camp)
Operation phase Approximately 1.25 TPD of Municipal solid waste
will be generated from the proposed project
Parking Facilities : Total parking: 1379 Nos.
Stilt Parking – 1379 Nos.
Power Requirement
Construction phase : 1000 kVA during construction phase through DG sets
Operation phase : The total demand load is 6.4 MW which will be
sourced from Dakshin Haryana Bijlee Vitran Nigam
Limited (DHBVNL).
Power Back up :
Construction phase : DG set will be installed to provide power supply
Operation phase : 5 DG sets of (4 nos. x 1500 kVA + 1 nos. x 500)
Project Cost 237.17 Crores
[24.16 (Land Cost) + 213.01 (Constrcution Cost)]
Environment Impact Assessment Report Proposed Independent Floor Development (18.138 Acres), Sector-
61, Village Ullawas, Gurgaon
M/s Commander Realtors Pvt. Ltd. P a g e | 247.
11.3 CONCLUSIONS
Based on the environmental assessment, all possible environment aspects have been adequately
assessed and necessary control measures have been formulated to meet with statutory requirements, in
the preparation of the EIA-EMP.
The proposed project is aimed at the infrastructural development of the area. The project will provide
impetus to further future growth of the concerned area and its surroundings. Thus implementing this
project will not have any significant negative impacts, thereby encourage acceptance in terms of
regional development and may be facilitate with environmental clearance.
11.4 OVERALL JUSTIFICATION FOR IMPLEMENTATION OF THE PROJECT
The proposed project will entail development of physical and social infrastructure in the region which
includes all utility services, overhead and underground, as well as all telecommunication facilities and
roads. The proposed land use pattern for this development envisages residential, commercial, IT
sectors’ development and emergence of social infrastructure in the region. Depending upon these
different land use patterns, the development would be envisaged in housing facilities, transportation
and communication, recreational and business opportunities.
The associated benefit from this development could be summarized as below:
1 Improvement in Physical Infrastructure
2 Improvement in Social Infrastructure
3 Employment Potential-Skilled, Semi-Skilled and Unskilled
4 Trigger growth in the district and of the region due to increased land requirement;
5 Other Tangible benefits - Improvement in quality of life of the local population;