Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated...

44
London BRT Transit Project Assessment Process – Environmental Project Report 4-i Table of Contents 4 Impact Assessment, Mitigation and Monitoring .......................... 4-1 Transportation and Utilities ............................................................. 4-2 Transit Network ................................................................... 4-2 Traffic Operations ................................................................ 4-3 Cycling and Pedestrian Network.......................................... 4-7 Surface and Subsurface Utilities ........................................ 4-10 Maintenance and Emergency Services ............................. 4-12 Stormwater Management .................................................. 4-12 Natural Environment ....................................................................... 4-13 Source Water Protection.................................................... 4-13 Groundwater and Contaminated Sites ............................... 4-14 Surface Water, Fish and Fish Habitat ................................ 4-14 Vegetation and Vegetation Communities........................... 4-18 Wildlife and Wildlife Habitat ............................................... 4-19 Significant Natural Features and Sensitive Areas.............. 4-21 Air Quality .......................................................................... 4-25 Noise and Vibration ........................................................... 4-26 Socio-Economic Environment ...................................................... 4-28 Land Use and Demographics ............................................ 4-28 Local Economy .................................................................. 4-29 Businesses ........................................................................ 4-31 Recreation, Entertainment and Tourism ............................ 4-35 Cultural Environment ..................................................................... 4-35 Archaeology....................................................................... 4-35 Built and Cultural Heritage ................................................. 4-37 Matters of Provincial Importance ................................................ 4-40

Transcript of Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated...

Page 1: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-i

Table of Contents 4 Impact Assessment, Mitigation and Monitoring .......................... 4-1

Transportation and Utilities ............................................................. 4-2 Transit Network ................................................................... 4-2

Traffic Operations ................................................................ 4-3

Cycling and Pedestrian Network .......................................... 4-7

Surface and Subsurface Utilities ........................................ 4-10

Maintenance and Emergency Services ............................. 4-12

Stormwater Management .................................................. 4-12

Natural Environment ....................................................................... 4-13 Source Water Protection .................................................... 4-13

Groundwater and Contaminated Sites ............................... 4-14

Surface Water, Fish and Fish Habitat ................................ 4-14

Vegetation and Vegetation Communities ........................... 4-18

Wildlife and Wildlife Habitat ............................................... 4-19

Significant Natural Features and Sensitive Areas .............. 4-21

Air Quality .......................................................................... 4-25

Noise and Vibration ........................................................... 4-26

Socio-Economic Environment ...................................................... 4-28 Land Use and Demographics ............................................ 4-28

Local Economy .................................................................. 4-29

Businesses ........................................................................ 4-31

Recreation, Entertainment and Tourism ............................ 4-35

Cultural Environment ..................................................................... 4-35 Archaeology ....................................................................... 4-35

Built and Cultural Heritage ................................................. 4-37

Matters of Provincial Importance ................................................ 4-40

Page 2: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-1

4 IMPACT ASSESSMENT, MITIGATION AND MONITORING Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the existing corridors and has the potential to have impacts beyond the municipal road allowance where road widening to accommodate transit facilities is required. These changes were considered during the review of alternative design options in pre-planning for Transit Project Assessment Process (TPAP) and during TPAP to develop the preliminary engineering design. The following sections provide:

• An assessment and evaluation for potential impacts of the preferred design in Section 4.1. This does not include details on the alternative design options considered during pre-planning;

• A description of proposed measures for mitigating potential negative impacts the transit project might have on the environment; and,

• A description of the proposal for monitoring or verifying the effectiveness of the mitigation measures.

The potential impacts assessed include shorter-term impacts associated with construction activities and longer-term impacts associated with on-going operation and maintenance of the facilities. The evaluation factors are categorized into four themes, building on the objectives of the Rapid Transit Master Plan (RTMP): transportation and utilities, cultural environment, natural environment, and socio-economic factors (Exhibit 4-1). The criteria considered reflect local conditions, best practices, and matters of provincial importance.

This section is structured to parallel Section 3, discussing the impacts of the project in the same contexts: the built, natural, socio-economic, and cultural environments. The supporting technical studies are provided in Appendices E to L.

Exhibit 4-1: Evaluation Factors and Assessment Criteria

Evaluation Factor Assessment Criteria Transportation And Utilities Transit Network • Changes to existing LTC local bus service along the Rapid

Transit corridors • Integrating local service with the Rapid Transit service

Traffic Operations • Changes in traffic circulation • Changes in permitted and prohibited turning movements • Changes to on-street parking • Changes to loading areas

Cycling and Pedestrian Network

• Changes to existing and planned cycling and pedestrian networks • Disruption to existing facilities during construction

Evaluation Factor Assessment Criteria Surface and Subsurface Utilities

• Relocation of existing utilities • Potential for service disruptions during construction

Stormwater Management

• Changes to hard surface areas along the corridors • Changes to stormwater, runoff quantity and quality

Maintenance and Emergency Services

• Changes to existing winter maintenance operations / priorities • Changes to existing waste management operations • Changes to emergency services travel patterns

Natural Environment Groundwater and Contaminated Sites

• Potential for contaminated soils or groundwater during construction

• Potential need for dewatering and related impacts to the groundwater regime

Surface Water, Fish and Fish Habitat

• Changes to existing watercourse crossings with fish habitat, riparian habitat, and aquatic ecosystems

• Potential impacts to designated aquatic species at risk • Potential impacts to the water quality, thermal regime and flow of

watercourse crossings Vegetation and Vegetation Communities

• Potential impacts to existing vegetation communities • Potential impacts to designated vegetation species at risk • Changes to existing tree canopy and street trees

Wildlife and Wildlife Habitat

• Potential impacts to existing wildlife and wildlife habitat • Potential impacts to designated wildlife species at risk

Significant Natural Features and Sensitive Areas

• Potential impacts to designated Environmentally Sensitive Areas, Areas of Natural and Scientific Interest, Provincially Significant Wetlands, Significant Woodlands and Significant Valleylands

Air Quality • Potential impacts to nearby sensitive land uses during construction, and as a result of changing traffic patterns during operation

• Potential impacts related to net reductions in regional emission of critical contaminants including greenhouse gases

Noise and Vibration • Potential for increase in sensitive receptors such as backyards, nursing homes, and other institutions

• Potential noise and vibration impacts to sensitive receptors during construction

• Potential noise and vibration impacts during operations Socio-Economic Environment Land-use and Demographics

• Changes in demographics and population age structure • Ability to achieve The London Plan objectives for land use

including increasing walkable, transit-oriented development Local Economy • Impacts related to construction and operation of the project

• Potential changes in land value

Page 3: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-2

Evaluation Factor Assessment Criteria Businesses • Potential impacts to businesses during construction

• Changes to on-street parking, loading and access Recreation, Entertainment and Tourism

• Improvement to active transportation network (walking, cycling) • Providing transportation choice to access tourism attractions and

recreation areas Cultural Environment Archaeology • Potential to encounter and disturb archaeological resources

adjacent to existing roads that are currently undisturbed and contain archaeological potential.

Built and Cultural Heritage

• Potential direct and indirect impacts to cultural heritage resources that may result in isolation of the resource, premature deterioration of the resource, relocation and/or removal of the resource.

4.1 Transportation and Utilities

4.1.1 Transit Network

4.1.1.1 Potential Impacts The BRT Network has two routes: North-and-East, and South-and-West, with a total of 38 stops. The BRT network is proposed to operate seven days a week from 6 a.m. to 12 a.m. (midnight). The North-and-East route is planned to have five-minute bus frequency to serve forecasted transit ridership demand. The South-and-West route is planned to have 10-minute bus frequency. Riders will be able to transfer between the two routes at the Central Transit Hub, located at the corner of Wellington Street and King Street in downtown London, as well as at the intersection of Queens Avenue and Clarence Street.

For most of the 24 km BRT network, dedicated centre-running transit lanes will be implemented with platforms at signalized intersections, and four general traffic lanes (two per direction). However, in less than 5 km of the system where the right-of-way is constrained and widening is not feasible, such as downtown, one existing traffic or parking lane, per direction, will be converted to a dedicated transit lane. This approach generally maintains existing vehicle capacity of the road network, while increasing the people-carrying capacity of the corridor on higher-occupancy transit vehicles.

With lanes dedicated for transit and reliable, the BRT network will offer improved travel times across the majority of the network. The BRT platforms will be designed to meet Accessibility for Ontarians with Disabilities Act (AODA), (2005) standards to increase mobility for people of all ages and abilities.

BRT stop spacing is generally greater than local transit, which improves travel times once on the Rapid Transit vehicle. However, increased stop spacing can increase walking

distances for passengers to access the BRT network. To mitigate this issue, local bus services are planned to operate along sections of the BRT corridors. For most of the network, local service will operate in the curbside general traffic lane in mixed traffic. These local bus routes will maintain more frequent stop spacing. Local routes which meet or cross the BRT corridors will also be realigned as needed to ensure that they connect directly to BRT stops where feasible.

Fares to use the BRT network are planned to match the London Transit Commission (LTC) fare structure, providing an integrated, easy-to-use rider experience.

During construction, local routes may be temporarily diverted as needed to avoid delayed or disconnected routes. These plans will be developed in the next design phase, as the implementation strategy is refined and construction timing plans are confirmed.

The passenger boardings and alightings at each stop were developed through the travel demand model and adjusted since the RTMP to reflect the 38 total BRT stops, as summarized in Exhibit 4-2 and Exhibit 4-3.

Exhibit 4-2: North-and-East: Projected 2034 P.M. Peak Hour Passenger Boardings and Alightings by Stop: from North to Downtown to East

BRT Stop Boarding (On) Alighting (Off) Passenger Load Masonville Place (Terminus) 200 Not applicable

(start of route) 200

Western Rd at Richmond St 50 10 240 Western Rd at Hospital Driveway 80 10 310 Western Rd at Elgin Rd 570 10 870 Western Rd at Lambton Dr 350 20 1200 Lambton Dr / Perth St at University Dr 220 10 1410 Richmond St at University Dr 70 30 1450 Richmond St at Victoria St 30 60 1420 Richmond St at Grosvenor St 60 50 1430 Richmond St at Oxford St 60 150 1340 Clarence St at Central Ave 50 110 1280 Clarence St at Queens Ave 60 320 1020 King St at Wellington St 150 530 640 King St at Colborne St 30 120 550 King St at Adelaide St 40 170 420 Ontario St at King St 10 20 410 Dundas St at McCormick Blvd 30 40 400 Dundas St at Highbury Ave 30 220 210 Highbury Ave at LPH access 10 60 160 Highbury Ave at Oxford St 30 80 110 Fanshawe College (Terminus) Not applicable

(end of route) 110 0

Page 4: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-3

Exhibit 4-3: South-and-West: Projected 2034 P.M. Peak Hour Passenger Boardings and Alightings by Stop: from West to Downtown to South

BRT Stop Boarding (On)

Alighting (Off)

Passenger Load

Capulet Ln north of Oxford St W (Terminus)

40 Not applicable (start of route)

40

Wonderland Rd and Oxford St W 30 0 70 Oxford St at Beaverbrook Ave 10 0 80 Oxford St at Cherryhill Blvd 30 10 100 Oxford St at Wharncliffe Road 50 10 140 Wharncliffe Rd at Riverside Dr 20 10 150 EB: King St at Talbot St 50 20 180 King St at Wellington St 410 50 540 Wellington St at Horton St 140 30 650 Wellington St at South St 40 60 630 Wellington Rd at Bond St 10 70 570 Wellington Rd at Base Line Rd 10 40 540 Wellington Rd at Commissioners Rd 20 60 500 Wellington Rd at Wilkins St 10 100 410 Wellington Rd at Southdale Rd 10 100 320 Wellington Rd at Montgomery Gate 10 40 290 White Oaks (Terminus) Not applicable

(end of route) 290 0

4.1.1.2 Mitigation The proposed BRT routes will not replace the current LTC bus system. Adding dedicated lanes for Rapid Transit along the designated corridors with integrated local stop locations for convenient connections will make transit more reliable, improve travel times and enhance the user experience. In support of the implementation of Rapid Transit services, the City of London is looking to increase the frequency of local transit services with good connections to and from the Rapid Transit network. The resulting integrated transit system will be a more attractive transportation choice.

The increase in transit service will result from modifications over time to the current local transit network to create more fluid connections and integration with the BRT corridors. The guidelines for integration of local and Rapid Transit are provided in Section 2.3.

Bus Rapid Transit will be integrated with Express Bus and local bus routes to support city-wide increases in transit service. Three Express Bus routes are planned to operate on other corridors. With the implementation of BRT, the 90 Richmond Express will become

redundant and the service hours from this route will be reallocated to improve service on other integrated local routes.

Bus Rapid Transit will be integrated with existing regional transit connections. Inter-regional transit services in London are offered by VIA Rail and Greyhound Canada. VIA Rail offers passenger rail service from the London Station on York Street at Clarence Street. Greyhound Canada offers bus service from the London Bus Depot on York Street at Talbot Street and from the Western University Campus. High-speed passenger rail service between Toronto and London is currently planned to be in operation as early as 2025.

Transit connections to the London International Airport will be maintained through the existing transit route from Oxford Street East near Second Street (Fanshawe College). With future study, dedicated transit lanes could be extended to the east from the East Turnaround to accommodate future BRT service, as it was identified as a corridor for potential future expansion in the RTMP.

4.1.1.3 Net Effects Together, BRT and LTC local buses will provide a 35% increase in transit service hours between 2015 and 2035.

LTC served 22.6 million revenue passengers in 2016, with a total of 24.1 million boardings, which includes transfers. As documented in the RTMP, with the implementation of this BRT project, overall system ridership is projected to reach about 31 million in 2034. The split between Rapid Transit and other transit will depend on the timing of implementation and the local route plan.

4.1.1.4 Monitoring The express and local routes will be reviewed and adjusted leading up to the start of implementation. As the BRT network is constructed in phases, express and local routes will be adjusted accordingly. The BRT service and integration with express and local routes will be monitored as part of the LTC annual service review process.

4.1.2 Traffic Operations Along the BRT corridors, priority is given to reliable transit service, safe and convenient pedestrian access, and access to trip generators and adjacent neighbourhoods. The balance between providing attractive BRT travel times and providing good access to adjacent land use is a key consideration to support growth along the BRT corridors.

A detailed traffic analysis of all signalized intersections in the BRT network is provided in Appendix E, focused on defining: changes to transportation infrastructure, such as new traffic signals; changes to traffic operations including U-turn operations, special signals and traffic impacts; and a queue analysis to inform lane configurations and turn lane lengths in the preliminary engineering design of the project. These elements are reflected in the design provided in Appendix A.

Page 5: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-4

4.1.2.1 Potential Impacts

Short-Term Impacts

Short-term impacts to traffic operations on and across the BRT corridors may be caused during construction activities along BRT corridors, due to lane closures/reductions and work adjacent to traffic. Mitigation strategies are provided in the next section.

Long-Term Impacts

Intersections which are experiencing congestion today are likely to continue to experience congestion with BRT. This is primarily due to background traffic growth, the conversion of main street left-turn movements to fully-protected operations and increases in U-turn demand.

Following the implementation of Rapid Transit, turning movement restrictions will be required at some intersections for general traffic:

• Where dedicated centre-running transit lanes are provided, a centre island will generally be constructed between the BRT lanes. This will restrict left-turns to and from the BRT corridor at unsignalized intersections and driveways. These left-turn movements will occur at the next available signalized intersection, where U-turn movements from the dedicated left-turn / U-turn lane during a fully-protected signal phase will allow drivers to turn around the median and travel in their intended direction. Examples of resulting traffic circulation on centre-running BRT corridors are illustrated in Exhibit 4-4. During the next design phase, the interaction of right-turning vehicles with U-turning vehicles should be examined to confirm intersections where right-turn-on-red should be prohibited due to physical conflict points. Alternatives to inform drivers of right-turn-on-red restrictions can be implemented through static or blank-out signs, illustrated in Exhibit 4-5.

Exhibit 4-4: Typical Changes to Unsignalized Intersections and Driveways

Exhibit 4-5: Signage Options for Right-Turn-on-Red Restrictions

No Right Turn on Red (RB-79) No Right Turn LED Blank Out Sign

Page 6: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-5

• Where the dedicated transit lanes are curbside, there are options for right-turn movements by general traffic, as indicated on the design plates in Appendix A: o At some intersections, general traffic will be permitted to use the dedicated transit

lane to make right turns. To provide clarity to drivers, the transit lane will transition to “right-turn-lane, buses-excepted”, conveyed through the pavement surface, markings and signage;

o At other intersections, in the Downtown and along King Street east of Wellington Street, general traffic will be prohibited from making right-turns from either the general traffic lane or the dedicated transit lane. This is particularly important at BRT platform locations, where the interaction of buses, pedestrians, and right-turning traffic presents a complex series of conflict points. The future traffic analysis accounted for these restrictions by re-routing traffic to the next available intersection where auxiliary right-turn lanes are provided; and,

o In locations where an auxiliary right-turn lane can be provided adjacent to the dedicated curbside transit lane, general traffic will be permitted to cross the dedicated transit lane, indicated by pavement markings and/or signage, to access the right-turn lane.

• To minimize delays to through-traffic, left-turn restrictions are proposed during peak periods, or potentially all-day, at select signalized intersections where auxiliary left-turn/U-turn lanes cannot be accommodated – either due to major constraints, or where deemed to provide little operational benefit relative to their associated costs.

Downtown London and Richmond Row currently have a number of prohibited movements, many of which apply only during a.m. and/or p.m. peak periods. Additional turn restrictions will be introduced at some signalized intersections to accommodate Rapid Transit. Exhibit 4-6 provides a comparison of existing and planned turning movement restrictions that are required with the implementation of the BRT project.

A number of new signalized intersections will be introduced following BRT implementation, particularly along corridors where centre-running transit will be provided:

• All median BRT stops will be located adjacent to a signalized intersection to facilitate safe (protected) pedestrian crossing access to/from the stop. Where a median stop is proposed at an intersection that is currently unsignalized, that intersection will be signalized as part of implementing the BRT system.

• Where routing to/from unsignalized intersections or major driveway access is impeded, and alternative routing options are limited or non-existent, signalized intersections may be introduced to provide U-turn opportunities for inbound/outbound traffic.

The segment of Ridout Street between Queens Avenue and King Street is proposed to be converted from one-way southbound only to two-way traffic operation in response to transportation network changes in downtown London. This connection will provide a new north-south travel corridor for vehicles and bicycles, and connect the cycling network with areas to the southwest.

Exhibit 4-6: Downtown Turning Movement Restrictions (During Peak Periods)

4.1.2.2 Mitigation

Short-term Mitigation

To minimize the potential for traffic delays during construction, the City will coordinate BRT construction with other capital projects. Construction will also be carried out in phases to better manage the temporary impacts to traffic.

Construction impacts can be mitigated with the development of City-wide Transportation Demand Management (TDM) plans. TDM strategies can reduce delays, identify alternative travel options, and help build support for and interest in the new travel choices that will be available after construction. Network Construction Mitigation Plans are common in the United States. Recent examples in Ontario include the Confederation Line Light Rail Transit

Page 7: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-6

(LRT) (Ottawa), Eglinton Crosstown LRT Project (Toronto), Waterloo ION LRT (Waterloo Region), and the Queen Street Hill closure (Hamilton).

Developing localized TDM plans will be an important component in addressing the changing demands placed on RT routes and intersecting roads during construction, in particular at major intersections and BRT stops. TDM plans should address the needs of all modes (pedestrian, cycle, transit and vehicular), as well as managing access to side streets and adjacent properties.

TDM plans identify the impacts at various stages of construction and define the duration of changes to lane configurations, turn restrictions, transit route changes, sidewalk impacts, or other temporary measures. Strategies can be developed that help manage these changes and capacity restrictions and keep traffic moving, and accesses open, and road users informed. Communication is the most important tool, before, during and after construction, to manage travel demand and help the public understand how to carry out their travel effectively.

As the City’s Intelligent Transportation Systems (ITS) program is implemented on other corridors, this will also assist in the management of traffic diversions during construction of the BRT project.

Long-term Mitigation

The preferred design includes mitigation measures such as maintaining the same number of through lanes at intersections, auxiliary turn lanes at key intersections, and the provision of sufficient storage length for dedicated turn lanes to minimize the spill back of congestion to through lanes.

Traffic signal timing plans along the BRT corridor will be developed prior to construction to provide appropriate pedestrian crossing times. Signal heads for transit, pedestrians, and cyclists will be identified where appropriate during detail design.

Traffic signal phasing changes will be introduced at signalized intersections along the BRT corridors to improve efficiency and reliability of transit service, or to accommodate newly permitted traffic movements, including:

• Transit-only signal phases will be introduced at many signalized intersections to facilitate movement of BRT through the intersection. This type of phasing is used to eliminate potential conflicts between general traffic and BRT vehicles given crossing intersection movements (e.g. between centre-running transit and left-turning traffic), and thus enhance safety and reliability of operation. Transit-only signal phases are also implemented in mixed-use corridors where queue jump lanes are provided, to allow BRT vehicles to move into the receiving lanes ahead of general traffic.

• Transit signal priority (TSP) will be used throughout the BRT network to maintain transit travel times and reliability of service frequency. This can be achieved through either o Passive TSP – where signal timing offsets between adjacent signalized intersections

are determined based on anticipated BRT operating speeds (with consideration of

stops and passenger loading/unloading at stops) rather than to traffic operating speeds, in order to provide a “green wave” for BRT; or,

o Active TSP – where signals are adjusted in real-time, either through early truncation of a red-light phase or early activation of a green-light phase, to ensure green phases are provided to approaching BRT vehicles more quickly.

• U-turn movements will be permitted at many signalized intersections where centre-running transit is present. U-turns will be made from shared auxiliary left-turn/U-turn lanes. Where left-turn/U-turns are permitted, the traffic signal phasing will be altered so that the shared left-turn/U-turn movement operates under fully-protected phasing in order to eliminate conflicts otherwise present with through-travelling BRT and opposing traffic. Existing left turn lanes at signalized intersections are generally maintained and lengthened to accommodate changes in traffic flow, including the additional U-turn movements due to access restrictions resulting from the introduction of the BRT.

In addition, several intersections will be signalized either to provide pedestrian access to centre platforms, or to mitigate the left-turn restrictions by providing a protected location for U-turns. The list of signalized intersections to be introduced to support the BRT system is provided in Exhibit 4-7.

Exhibit 4-7: Intersections to be Signalized to Support the BRT System

Intersections to be Signalized North Corridor Western Road & Ambleside Drive Richmond Street & St. James Street Clarence Street & Angel Street (pedestrian signal) East Corridor King Street & Burwell Street (pedestrian signal) King Street & Ontario Street Dundas Street & Kellogg Lane Dundas Street & McCormick Boulevard Dundas Street & Ashland Street Highbury Avenue & Canada Post / London Psychiatric Hospital (LPH) Secondary Plan Oxford Street & Secondary School / LPH Secondary Plan Oxford Street & London Lane (west-most access) Oxford Street & London Lane (east-most access) West Corridor Oxford Street & 530 Oxford Street West (commercial access) Oxford Street & Beaverbrook Avenue Riverside Drive & Wilson Avenue South Corridor Wellington Street & South Street Wellington Street & Bond Street Wellington Street & Whetter Avenue (replaces existing pedestrian signal at Emery Street)

Page 8: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-7

4.1.2.3 Net Effects Under a future “business-as-usual” scenario (i.e. without BRT), the volume of auto trips in 2035 will grow by more than 20% compared to 2009 volumes. Road improvements required in this scenario are more expensive over their lifecycle as compared to the proposed BRT system, some are infeasible once the roadway is expanded to its limits, and most are inconsistent with the goals of developing a multimodal transportation network.

Recognizing this, the overarching goal of the BRT project is to provide more attractive travel choices for Londoners, thus reducing their collective dependency on the automobile. Rapid Transit is efficient at carrying large volumes of passengers compared to private vehicles, reducing the need for future road widening. Over the long term, this shift in behaviour can reduce the need for costly and disruptive road improvement projects, maintain good roadway level of service, and provide overall environmental benefits.

Intersections currently experiencing congestion are likely to continue to experience congestion into the future. This is primarily due to background traffic growth, as well as the conversion of main street left-turn movements to fully-protected operations; lane reductions and reallocations; and anticipated increases in U-turn demand. However, the future BRT condition includes changes to intersections to mitigate these issues while providing transit service that is fast and reliable, pedestrian access that is safe and convenient, and maintaining mobility and access to trip generators and neighbourhoods.

4.1.2.4 Monitoring Traffic operations are monitored by the City, and this will continue in advance of, during, and after the implementation of BRT. ITS solutions can be applied to manage traffic congestion during and after implementation, through the City’s planned traffic control centre.

4.1.3 Cycling and Pedestrian Network

4.1.3.1 Potential Impacts The BRT system is designed with key consideration given to bicycle and pedestrian modes, in accordance with “complete streets” principles.

Sidewalks will be continuous on both sides of the streets along BRT corridors. To be compliant with AODA (2005), a clear path, called a clearway, which is at least 1.5 m wide, will be provided in constrained areas. In most areas, a clearway of at least 2.0 m will be provided. Other accessible sidewalk design elements include slopes less than 1:20 (5%), a slip-resistant surface, and curb ramps at intersections with tactile warning strips and high tonal colour contrast.

For cycling facilities, there are generally five possible outcomes along the BRT corridors:

• A cycling facility is proposed in the cycling master plan and can be accommodated through the design of the BRT. In these cases, the bundling of the proposed cycling

facility with the BRT corridor is likely to accelerate the delivery of this cycling infrastructure.

• A cycling facility is not proposed in the cycling master plan but has been added to the network as part of the design of the BRT. In these instances, a cycling facility will be added to the overall network that was not previously planned, but provides continuity to a major destinations or to ties into a connecting facility, or delineates a space for cyclists that otherwise would not be provided.

• A cycling facility is existing and can be accommodated through the design of the BRT. In some instances, the existing cycling facility will be upgraded along the BRT corridor, for example by bringing on-road bike lanes into the boulevard to provide separated cycling facilities.

• A cycling facility is existing and must be removed in order to accommodate the BRT. Just as there is a loss of vehicular lanes in some locations to accommodate the BRT, there are locations where the cycling facility has been eliminated through the proposed BRT design. In these cases, mitigation of the impacts of the network removal are needed through the development of network alternatives.

• A cycling facility is proposed in the cycling master plan but cannot be accommodated through the BRT corridors. In these cases, mitigation of the impacts of the removal are needed through the development of network alternatives.

Exhibit 4-8 summarizes the cycling facilities that are proposed along BRT corridors and identifies their relationship with the cycling master plan and current network.

The design also protects for future cycling connections on the majority of intersecting signalized streets. Further consideration is needed to evaluate the appropriateness of these connections in terms of the corresponding intersection upgrades required to provide access to/from the intersecting cycling facility, as well as the proposed facility type relative to roadway motor vehicle volumes and speeds. Exhibit 4-10 details the cycling facilities and connections that are protected for in the design.

In addition to the dedicated and separated cycling facilities, some cyclists may find it convenient and comfortable to use curbside BRT lanes where no alternate cycling facilities are provided. Although not necessarily encouraged through signage or pavement markings, such behavior should not be discouraged or penalized. Although the level of comfort along these corridors may vary depending on the transit frequency and stop configuration, the shared operation of these curb lanes will, at a minimum, provide some network continuity, particularly through the downtown where some cycling facilities were removed to accommodate the BRT.

Page 9: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-8

Exhibit 4-8: Cycling Facilities Proposed along BRT Corridors

BRT Corridor Road Limits Proposed

Facility Type Network Status / Type of Improvement

North Richmond Street

Western Road to Fanshawe Park Road

Raised bike lanes

Upgrade of existing facility (signed bike route with sharrow to raised bike lane)

North Western Road Lambton Drive to Richmond Street

Raised bike lanes

Upgrade of existing facility (on-road bike lane to raised bike lane)

North University Drive

Lambton Drive to Richmond Street

Bike lanes Maintain existing facilities and connection to Thames Valley Parkway

North Clarence Street

Dufferin Street to Central Avenue

MUP (east side)

New cycling network link (not previously proposed in Cycling Master Plan) along Victoria Park

East King Street Wellington Street to Rectory Street

Raised bike lane (eastbound)

Upgrade of existing facility (on-road bike lane to raised bike lane)

East King Street Rectory Street to Ontario Street

Raised bike lane (eastbound)

New cycling network link (not previously proposed in Cycling Master Plan) to improve network connectivity

East Ontario Street King Street to Dundas Street

Raised bike lane (northbound)

New cycling network link (not previously proposed in Cycling Master Plan) to improve network connectivity

East Dundas Street Ontario Street to Egerton Street

MUP (south side)

Upgrade of existing facility (signed bike route to raised MUP)

East Oxford Street Highbury Avenue to Second Street

MUP (south side)

Upgrade of existing facility (in-boulevard facility/bike lanes to MUP)

South Wellington Street / Road

Grand Avenue to South Street

MUP (east side)

New barrier crossing over the Thames River and connections to Thames Valley Parkway

South Wellington Road

Emery Street to Thomas Janes Drive

MUP (west side)

New cycling network link (not previously proposed in Cycling Master Plan) to improve network connectivity

BRT Corridor Road Limits Proposed

Facility Type Network Status / Type of Improvement

South Wellington Road

Commissioners Road to Base Line Road

MUP (east side)

New cycling network link (not proposed in Cycling Master Plan) to improve access to Victoria Hospital & commercial developments in the area

South Wellington Road

Bradley Avenue to Commissioners Road

MUP (east side)

Proposed in cycling master plan

West Ridout Street King Street to Queens Avenue

Bike lane New cycling network link (not proposed in Cycling Master Plan) to improve network connectivity

West Wharncliffe Road

Riverside Drive to Thames River

MUP (east side)

New cycling network link (not proposed in Cycling Master Plan) to improve network connectivity to Thames Valley Parkway

During the next design phase, details for cycling infrastructure will be advanced, including identifying locations for bike boxes, bike signals, and two-stage queue boxes at signalized intersections, conflict zone markings through intersections, bike parking in boulevards at key locations, cycling pavement marking and signage plans. A two-stage queue box detail is provided in Exhibit 4-9.

Page 10: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-9

For pedestrians, the detail design phase should consider signal timing phasing for pedestrians, such as Leading Pedestrian Intervals at higher-volume intersections or intersections near special generators such as schools and hospitals. Leading Pedestrian Intervals give pedestrians a head start of a few seconds to become visible in the crosswalk and establish their right-of-way before the green signal for general traffic is initiated. Wider crosswalks at some signalized intersections may also be appropriate, and should be reviewed in the next design phase.

The City of London is conducting a review of east-west cycling connections in the Downtown and Old East Village. Depending on the findings of this study, the cycling facility shown in Appendix A on King Street between Wellington Street and Ontario Street may not be required. This will be coordinated in detail design.

4.1.3.2 Mitigation As described in Section 4.1.2.2, to minimize the potential for breaks in the cycling network during construction, the City will coordinate BRT construction with other capital projects. Construction will also be carried out in phases to better manage the temporary impacts to the cycling network.

During construction, maintaining pedestrian access will be very important. Pedestrian connections will be maintained and protective fencing will be installed where needed to provide a barrier to traffic and/or road construction. Maintaining pedestrian access to

destinations, especially those with a high rate of pedestrian access, such as commercial properties Downtown, will be an important part of the business impact mitigation strategies.

Post implementation, the BRT corridors will provide a pedestrian-friendly environment with improved sidewalks and intersection crosswalks to enable safe connections to and along the BRT corridors and to BRT stops.

Construction impacts can be mitigated with the development of City-wide TDM plans. TDM strategies can reduce delays, identify alternative travel options, and help build support for and interest in the new travel choices that will be available after construction. Cycling can be a significant part of these plans.

4.1.3.3 Net Effects The City plans to update the cycling master plan to reflect the cycling infrastructure along the BRT corridors, including the new connections at signalized intersections. As part of this process, additional links in the cycling network are likely to be identified. It is recommended that connections to the Thames Valley Parkway will be reviewed in more detail, for example at Wellington Street, Wharncliffe Road, Riverside Drive, and University Drive.

4.1.3.4 Monitoring Walking and cycling provides an important first mile / last mile connections to transit. The City will continue to consult with cycling advocacy groups to monitor the success of the cycling connections to the BRT network once implemented. The City may consider further enhancing first mile / last mile connections with active transportation in support of the BRT project as development occurs. A monitoring program that is based on a combination of the users’ stated experiences (stated preference surveys) and visual monitoring (desire line analysis) will enable an iterative approach to improving design that is reflective of both user perception and behavioral realities.

Exhibit 4-10: Cycling Route Connections Protected for with BRT Design

Location Of Facility Facility Type Cycling Master Plan Status North Corridor Fanshawe Park Road (at Richmond Street)

Bike lane (south side) Existing bike lanes

Hillview Boulevard (at Richmond Street) Bike lanes Future connection to BRT (TBD) Sunnyside Drive (at Richmond Street) Bike lanes Future signed route (6-15 years) Ambleside Drive (at Richmond Street) Bike lanes Existing signed route Windermere Road (at Western Road) Bike lanes Future bike lanes (6-15 years) Huron Street (at Richmond Street) Bike lanes Existing signed route Victoria Street (at Richmond Street) Bike lanes Future connection to BRT (TBD) Cheapside Street (at Richmond Street) Bike lanes Existing/future bike lanes (0-5 years) Grosvenor Street (at Richmond Street) Bike lanes Future connection to BRT (TBD) St James Street (at Richmond Street) Bike lanes Future connection to BRT (TBD) Pall Mall Street (at Richmond Street) Bike lanes Future connection to BRT (TBD)

Exhibit 4-9: Two-Stage Queue Box Detail

Page 11: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-10

Location Of Facility Facility Type Cycling Master Plan Status Central Avenue (crossing Richmond Street) Signed route Existing signed route Dufferin Avenue (at Clarence Street) Bike lanes Existing signed route w/ sharrows East Corridor Waterloo Street (at King Street) Bike lanes Future connection to BRT (TBD) Colborne Street (at King Street) Bike lanes Existing bike lanes Maitland Street (at King Street) Bike lanes Future connection to BRT (TBD) William Street (at King Street) Bike lanes Future connection to BRT (TBD) Adelaide Street (at King Street) Bike lanes Future connection to BRT (TBD) Lyle Street (at King Street) Bike lanes Future connection to BRT (TBD) Rectory Street (at King Street) Bike lanes Future connection to BRT (TBD) Ontario Street (at Dundas Street) Bike lanes (north

and west legs) Future connection to BRT (TBD) Quebec Street (at Dundas Street) Bike lanes Existing bike lanes Egerton Street (at Dundas Street) Bike lanes Existing bike lanes Dorinda Street (at Dundas Street) Bike lanes Future connection to BRT (TBD) McCormick Boulevard (at Dundas Street) Bike lanes Future connection to BRT (TBD) Ashland Avenue (at Dundas Street) Bike lanes Future connection to BRT (TBD) West Corridor Wonderland Road (at Oxford Street) MUP (north leg) Existing MUP Wonderland Road (at Oxford Street) Bike lanes (south

leg) Existing bike lanes Beaverbrook Avenue (at Oxford Street) Bike lanes Future connection to BRT (TBD) Cherryhill Boulevard (at Oxford Street) Bike lanes Future connection to BRT (TBD) Platt's Lane / Woodward Avenue (at Oxford Street) Bike lanes Existing bike lanes Wharncliffe Road (at Oxford Street) Bike lanes Future bike lanes (to north) (0-5 years) Riverside Drive (over Kensington Bridge)

Bike lane (eastbound) Existing bike lane (eastbound)

South Corridor York Street (at Wellington Street) Bike lanes Future connection to BRT (TBD) Horton Street (at Wellington Street) Bike lanes Future connection to BRT (TBD) Grey Street (at Wellington Street) Bike lanes Future connection to BRT (TBD) South Street (at Wellington Street) Bike lanes Future connection to BRT (TBD) Grand Avenue (at Wellington Road) Bike lanes (west

leg) Existing signed bike route (to west) Bond Street (at Wellington Street) Bike lanes Future connection to BRT (TBD) Whetter Street (at Wellington Street) Bike lanes Existing signed bike route

(Emery/Whetter) Base Line Road (at Wellington Road) Bike lanes Future connection to BRT (TBD) Commissioners Road (at Wellington Road) Bike lanes Existing/future bike lanes (0-5 years)

Wilkins Street (at Wellington Road) Sharrows Future signed route w/ sharrows (6-15 years)

Location Of Facility Facility Type Cycling Master Plan Status Southdale Road (at Wellington Road) Bike lanes Future bike lanes (6-15 years) Bradley Avenue (at Wellington Road) Bike lanes Existing signed route

4.1.4 Surface and Subsurface Utilities There are existing utilities within and across the BRT corridors that will require relocation. The utilities are classified as municipal services (such as watermains, storm sewers, sanitary sewers, etc.) and private utilities (telecommunications, gas services, hydro, etc.).

All municipal and private utility owners have been consulted regarding the locations of their existing infrastructure. Where potential relocations were identified, relocation strategies and requirements were further discussed with the owners.

4.1.4.1 Potential Impacts Through coordination with all of the potentially impacted utility providers, utilities found within the proposed platforms will be relocated as needed with the goal to minimize potential disruption to transit during maintenance and repair activities. Underground municipal utilities running through the platform area can remain, but at-grade features such as valve chambers or maintenance holes will be relocated outside the platform area. In general, all private utilities running along the roadway will be required to be relocated outside the proposed BRT dedicated lanes and platform areas, except in areas that are constrained such as the downtown. Private utilities that run perpendicular to the roadway for servicing can be accommodated. Potential impacts to utilities are summarized in Exhibit 4-11.

Exhibit 4-11: Potential Impact to Utilities within the Study Area

Service Owner/Operator Potential Impact Watermains City of London - Water

Division Minor relocations throughout

Storm Sewers City of London - Waste Water & Drainage Engineering

Some upsizing required – refer to stormwater management report.

Sanitary and Combined Sewers

City of London - Waste Water & Drainage Engineering

Maintenance hole relocations outside of BRT stop area

Traffic and Street Lighting

City of London - Parking & Traffic Signals

Relocations due to road widening

Natural Gas Union Gas Relocation outside of BRT lanes Electricity London Hydro Relocations due to road widening

Hydro One Design developed to avoid impacts

Page 12: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-11

Service Owner/Operator Potential Impact District Energy London District Energy Relocations outside of platform area Telecommunications Bell Canada Maintenance hole relocations outside of

BRT stop area Rogers Communications Potential minor relocations throughout Telus Communications Potential minor relocations throughout Execulink Telecom Shared infrastructure with others Start Communications Potential minor relocations throughout Zayo Shared infrastructure with others Allstream Potential minor relocations throughout

Rail Signals Canadian National Railway

No impact to railway corridor

Canadian Pacific Railway No impact to railway corridor Petroleum Enbridge Not within study area

Imperial Oil - Sarnia Products Pipeline

Not within study area

Sun Canadian Pipeline Not within study area Natural Resources Gas Limited (NRG)

Not within study area

Other Western University No impacts anticipated

Due to these relocations, services will be impacted during construction. To install some of the deeper sub-surface infrastructure, trenches will be required with proper shoring.

With the road widening to introduce the dedicated BRT lanes, hydro poles owned by London Hydro are the most widely impacted throughout the entire network. London Hydro has been consulted throughout the project and have identified strategies for the large number of pole relocations.

There may be situations where the cost of the utility relocation needs to be weighed against the disruption to the operations to determine the feasibility of the relocation. To coordinate the works effectively, utilities have been reviewed from an asset management perspective which accounts for upgrades due to growth of the service, as well as non-growth upgrades such infrastructure renewal/replacement.

Potential impacts from surface and sub-surface utilities include service disruptions to both residents and businesses due to construction. Impacts due to the utility relocations can potentially include access restrictions, road closures, sidewalk closures, traffic detours and delays. Depending on the proposed location of the relocated plants, impacts to the public

can be limited and minimized dependent upon available space within the right-of-way (ROW).

4.1.4.2 Mitigation To mitigate the impact of the utility relocations, construction staging must be considered during detail design to minimize potential disruption. The first phase of construction for the BRT network will take place in the downtown couplet. This is being timed to align with other infrastructure and signature projects happening in the core during this time.

The highest level of communication will be required during construction to mitigate the potential impacts of a project of this scale. Robust communications protocols will be established to ensure proactive, accurate information flow to stakeholders, and real-time resources – both online and on-site – will alert stakeholders to project updates as they happen.

A BRT-specific Communications Plan, already underway, will establish communications strategies to support implementation of the project and guide transparent, inclusive, and proactive communications and consultation with affected residents, business owners and the travelling public.

In situations where the roadway will be impacted due to relocation works, traffic management plans will be created to alleviate and minimize disruption as much as possible. In addition to standard mitigation practices for potential construction impacts (identified in 4.1.4.1), such as dust, noise and equipment lay down, other measures will be undertaken, including wayfinding/signage for detours, notification of alternative parking during periods of closed access, and establishing a main point of contact responsible for serving businesses, visitors and property owners.

4.1.4.3 Net Effects Given the short-term nature of the potential impacts on utilities, residents and businesses, and the mitigation strategies proposed, the net effects of utility relocations will be minimal. Since the private utilities will generally be located outside the BRT route, impacts to the operations of transit should be also minimized for most of the BRT network.

In areas where utility relocations are not possible, such as the Downtown, utility servicing may be required to access the utility from the transit lane. This may result in short-duration impacts to traffic and/or transit for utility access. The City will work with private utilities to manage access for non-emergency work to off-peak hours.

4.1.4.4 Monitoring During construction, a traffic management plan will need to be implemented to ensure that the road network is adequately maintained. This plan should be overseen to ensure that transit, cars, cyclists, and pedestrians are able to navigate through the construction and that disruptions are minimized. The Contract Administrator and on site inspectors should monitor the construction activities and adjacent road network, and request that the Contractor make adjustments as necessary to minimize impacts.

Page 13: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-12

4.1.5 Maintenance and Emergency Services

4.1.5.1 Winter Maintenance During the project development, the City of London Roadside Operations staff identified a preference for centre-running transit lanes when considering the most efficient design from a winter maintenance perspective. As snowfall begins, salt trucks with ploughs are first sent out to deal with events accumulating less than 5 cm. Typical ploughing operations work from the centre lane out, and the natural runoff of salt and brine towards the curb will assist in clearing the general traffic lanes as well. Similarly during greater snowfall events, larger ploughs also start with the centre lane, progressively pushing snow to the outside, which is much less conducive to curbside BRT.

The BRT corridors will be designated a “priority” in the City’s Winter Maintenance Program. Winter Maintenance for BRT platforms is expected to require hand work to maintain. Also, consideration for snow storage will be necessary during detail design to avoid triggering the need for removal operations, especially for stop design and areas were the corridors are constrained.

The Rapid Transit Project Team will continue to work with Roadside Operations to establish service standards for RT corridors, with details to be determined through the next phase of the study.

4.1.5.2 Waste Management During the project development, waste management staff identified a preference for centre-running transit lanes when considering curbside waste pick-up for homes and businesses. Centre-running BRT will locate platforms in the middle of the road which will avoid conflicting curbside placement of garbage containers.

Where there are four general traffic lanes (two in each direction), curbside collection can still occur, and the timing along BRT corridors would avoid the am and pm peak periods. Where there are only two lanes of general traffic (one in each direction), such as Richmond Street north of Oxford Street and Dundas Street, alternative service delivery models will be reviewed. Where transit lanes are curbside, such as Downtown and King Street, the City may consider scheduled pick-up outside of peak hours to reduce conflicts between waste management vehicles and transit, such as overnight.

The BRT platforms will have waste receptacles for garbage and recycling and the City will be responsible for cleaning the platform areas and emptying the waste receptacles on a regular basis.

During the detail design stage, consultation will continue with the Waste Management group to develop operational practices and procedures based on corridor configuration and land use and establish service standards for platform maintenance.

4.1.6 Stormwater Management Further details on stormwater management are provided in Appendix L: Stormwater Quality/Quantity Control Strategy.

4.1.6.1 Potential Impacts Within the majority of the proposed Rapid Transit corridors, there will be only a nominal increase in imperviousness, which will in-turn result in a nominal increase in peak storm flows, as the majority of the corridors can already be characterized as having a high level of development. In some locations, such as the fully developed downtown or Old East Village areas, there will be no net increase in impervious areas. In other areas, such as Wharncliffe Road between Oxford Street West and Riverside Drive, no improvements are planned and there will be no increase in imperviousness.

In accordance with City of London standards, areas of re-development or intensification along the corridors will be required to implement Stormwater Management (SWM) quantity and quality controls.

4.1.6.2 Mitigation Although storm sewer replacements are not necessary for increased capacity, there will be some areas where storm sewer work will be required as a result of BRT construction:

• Storm sewers will require relocation if currently located beneath proposed BRT platforms;

• New storm sewers will be required in areas that currently do not have any storm sewers and are required in the future due to the new BRT corridor cross-section. For example, on Wellington Road north of Southdale Road, storm flows currently enter a ditch on the east side of the roadway and flow into the Westminster Ponds. The proposed BRT cross-section will require curb and gutter and a new storm sewer; and,

• In some areas, replacement of storm sewers is required due to age and capacity reasons instead of BRT construction. It is noted that this is the case along Richmond Street from Oxford Street to the Thames River and within the older central parts of the BRT corridor downtown.

The application of low impact development (LID) strategies within the corridors will help to provide some level of both quantity and quality control and provide for water balance conditions. It is expected that going forward, future Ministry guidelines will require the application of these strategies where practical.

Some examples of LID strategies within road rights-of-way include:

• Bio-retention (within planters, curb extensions, bio-retention units); • Swales (Enhanced grass swales, bio-swales); • Perforated pipes;

Page 14: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-13

• Prefabricated Modules (precast tree planters, soil support systems, phosphorus removal, proprietary stormwater treatment devices); and,

• Permeable pavement (pervious concrete, porous asphalt, permeable pavers). It is recommended that the consideration of retention (if feasible) and LID measures be carried forward for consideration as part of detail design.

Examples of stormwater treatment methods include technologies which utilize filtration, hydrodynamic separation and/or sedimentation, such as oil/grit separators and end-of-pipe facilities (detention ponds, etc.).

4.1.6.3 Net Effects Given the nominal increase in imperviousness, and the proposed mitigation strategies to be implemented, the anticipated net effects are expected to be positive, since some areas that currently do not receive treatment will be addressed through BRT implementation.

4.1.6.4 Monitoring A monitoring strategy will be developed as part of detail design to ensure implemented stormwater management infrastructure meet design requirements. This may also be a requirement of the environment compliance approval (ECA).

4.2 Natural Environment There are seven locations along the BRT network corridor where the preferred route intersects or abuts a Natural Heritage Feature or Area. The EIS (Appendix G) assesses the preliminary engineering design for the seven locations in detail and includes recognition of the potential impacts related to the natural features, mitigation measures designed to minimize/eliminate these impacts, net residual effects of the anticipated works on the natural heritage features, and next steps to be considered during the detail design phase of the project.

The potential impacts to source water, groundwater, air quality, and noise and vibration levels in proximity to the BRT network corridors are also assessed in this section, along with the identification of mitigation measures, net effects and monitoring requirements. The, Air Quality Impact Assessment is provided in Appendix H, the Noise and Vibration Assessment is provided in Appendix I, and the Stormwater Quality and Quantity Control Strategy is provided in Appendix L.

4.2.1 Source Water Protection

4.2.1.1 Potential Impacts The Thames-Sydenham & Region Source Protection Plan outlines potential impacts to source water protection areas. Impacts that may apply to this project are listed below by Threat Type along with a brief description of how they may pose a risk to drinking water

sources for this project. It is noted that significant threats to drinking water do not exist in areas designated as highly vulnerable aquifers and significant groundwater recharge areas. Only moderate and low threats to drinking water may exist.

Waste Disposal and Sewage Impacts

Potential impacts exist when establishing, operating or maintaining a system that collects, stores, transmits, treats or disposes of sewage such as Stormwater management facilities designed to discharge stormwater to land or surface water; and sanitary sewers and related pipes.

Chemical Threats

The improper handling and storage of fuel and other chemicals during construction of the BRT corridor can pose a risk to any drinking water sources.

Transportation

The application, handling and storage of road salt and snow storage can pose a risk to any drinking water sources. This impact occurs within all London right-of-way corridors and does not apply solely to the BRT routes.

4.2.1.2 Mitigation Waste Disposal and Sewage

The design of any new storm or sanitary sewers requires approval by the Ministry of Environment, Conservation and Parks (MECP) with an ECA prior to construction. This gives approval under Section 53 of the Ontario Water Resources Act (OWRA). This approval applies for any new sewers or stormwater management facilities proposed as part of the BRT project and will need to be obtained at the detail design stage prior to construction. These approvals ensure the protection of sources of municipal drinking water against existing and potential impacts.

Chemical Threats

During detail design of the BRT routes, potential chemical impacts are to be noted in the tender documents along with appropriate mitigation measures that the contractor is to implement.

Transportation

The City of London maintains best practices in regards to road salt management, snow storage and spill prevention. The City follows legislation that exists to ensure that these items do not become a risk to drinking water sources.

4.2.1.3 Net Effects Waste Disposal and Sewage

The proposed sewage works within the BRT corridor that will require an ECA application are not identified as a drinking water threat in the assessment report for the local source

Page 15: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-14

protection plan under O. Reg. 287/07 of the Clean Water Act. As such, the ECA Applications for this project are not anticipated to include a supplementary report for source protection.

4.2.1.4 Monitoring Chemical Threats

The contract administrator will monitor construction activities to ensure that no intentional discharges occur to the environment. This information is to be included in the Environmental Plan for approvals and should include such items as the following:

• Refueling and cleaning of equipment is to occur away from the watercourse; • Fuel spill equipment should be available for emergency spills of deleterious substances • A contact list for any further required equipment or materials should be prepared and

made available for emergency use.

4.2.2 Groundwater and Contaminated Sites Further details on groundwater are provided in Appendix F: Geotechnical Assessment Report.

4.2.2.1 Potential Impacts There are no areas of significant potential for contamination at BRT stop locations. In general, low to moderate risks related to subsurface conditions are expected at a limited number of sites. The majority of potential contaminates of concern are petroleum hydrocarbon and chlorinated solvents associated with existing and former gas stations and service centres.

4.2.2.2 Mitigation Construction at or near the groundwater level may require treatment of discharge from dewatering activities. It is anticipated that for the majority of BRT stop sites, active remediation is probably not warranted given the relatively minimal depth of excavation at these locations.

4.2.2.3 Net Effects Should contaminated areas be encountered, the potential for net effects are limited, given that localized treatment would be used for discharge from dewatering activities in such cases.

4.2.2.4 Monitoring During construction, a regular program of geotechnical inspections, monitoring and materials testing should be carried out to confirm that the subsurface conditions encountered are consistent with those encountered during design and that contract compliance is achieved.

4.2.3 Surface Water, Fish and Fish Habitat

4.2.3.1 Potential Impacts

Site 1: Oxford Street West at Mud Creek

This site falls within the area that will be modified and enhanced by the City as part of the Mud Creek Subwatershed EA on lands south of Oxford Street West, and by private land development to the north. It is anticipated that the works related to the Subwatershed EA and land development, including realignment of the creek, installation of a new culvert, and enhancement of the valley corridor, are to occur in advance of the Rapid Transit works for the west corridor and protect for the design requirements. As the natural heritage system associated with Mud Creek will largely be altered and restored beyond the anticipated road corridor as part of the Subwatershed EA, direct impacts to the identified natural heritage features are not anticipated as a result of the RT works.

Site 2: North Thames Crossing on Queens Avenue and Riverside Drive

There are no works proposed below the high water mark at the Queens Avenue and Riverside Drive bridges. As such, the potential impacts on fish and fish habitat below the high water mark are limited to indirect or secondary impacts associated with construction.

Site 3: Medway Creek Crossing on Western Road

Additional shading of the Medway Creek will occur as a result of the bridge deck being widened. To support the widening, the new pier will be constructed within the permanently wet portion of the channel to the east of the existing footprint to avoid the sensitive environmental features to the west, resulting in potential impacts to fish and mussels, and their habitat.

This site provides habitat for threatened species (Wavy-rayed Lampmussel, Black Redhorse and Silver Shiner). The proposed works have the potential to directly impact habitat for these species through vegetation removal, habitat loss, alteration to banks and alteration of the channel bed. Passage by aquatic species is unlikely to be impacted by the expanded bridge structure

Site 4: North Thames Crossing on University Drive

A wider deck for the University Drive Bridge will result in an incremental increase in shading of the river; however, the bridge is located at such a height that the shading has nominal effects on fish and fish habitat within the channel. The potential removal of the east pier from the middle of the channel and relocating it to the river’s east bank will open up a portion of the channel bed previously covered by the pier, and allow for enhancement of the bed habitat for aquatic species (including species at risk (SAR)) using the habitat immediately adjacent.

Page 16: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-15

Site 5: Thames Crossing on Wellington Road

An increase to the in-water footprint associated with the potential extension to the pier, and the increase in the permanent footprint below the high water mark, associated with changes to the banks and the recreational trail system, has the potential to impact aquatic SAR that use habitat within and in close proximity to the watercourse. Associated impacts include the loss of habitat within the channel bed for the wider pier, loss of bank habitat for the abutments, and alteration of the bank habitat for the changes to the recreational trail. Widening of the bridge is also likely to result in increased shading of the channel.

Site 6: Westminster Ponds east of Wellington Road

Although the open water portions of the Westminster Ponds support a diverse community of fish species, the London RT works will not impact any of the habitat that supports fish use.

Site 7: Exeter Road Park-and-Ride

There is currently no crossing of Murray Drain, nor is one required to support the proposed construction. As such, it is anticipated that potential impacts to fish and fish habitat within the drain would be limited to indirect, construction-related activities associated with works within the floodplain. The sand and gravel substrates and aquatic vegetation found in riffles within this reach of Murray Drain may provide suitable habitat for Rayed Bean, an Endangered mussel species. Impacts to this species and its habitat are not anticipated.

4.2.3.2 Mitigation

4.2.3.2.1 Site Specific Mitigation A two part Environmental Management and Monitoring Plan (EMMP) is recommended to document the implementation of the mitigation and compensation measures during and after construction.

Part 1 of the EMMP will consist of a Construction Monitoring Plan to monitor construction-related impacts, document success or deficiency of the implemented mitigation measures (e.g., Erosion and Sedimentation Control Plan, Spill Control / Response Plan, etc.), and provide guidance on remedial actions/provisions for when mitigation is not successful. This plan will be developed during the detail design phase.

Part 2 of the EMMP is to consist of a long-term Post-construction Monitoring Plan to evaluate the success of the restoration / compensation efforts and to assess cumulative impacts on the Natural Heritage System. This plan should include contingency/remedial provisions that will be triggered if effects exceed a pre-determined threshold.

The UTRCA will be consulted during the development of the EMMP.

1 During the TPAP, the responsibility for Species at Risk under the Endangered Species Act, 2007, transitioned to MECP from MNRF.

In areas where impacts are anticipated to SAR, a comprehensive assessment of impacts and overall benefits to aquatic species will need to be completed once design details are finalized to ensure that there are no net negative impacts to any of the SAR species. This will require on-going liaison with MNRF staff and the design team.1

Site 1: Oxford Street West at Mud Creek

Re-assessment of habitat conditions should be carried out following the shifting of flows and realignment of the watercourse to the new culvert further east to determine what habitat remains for fish within the existing culvert crossing location. If fish are still using the habitat, then the following mitigation measures should be implemented to protect that habitat:

• Complete in-water works during permissible in-water window for Mud Creek to minimize impacts to the sensitive life cycle functions of the resident species.

• Isolate the construction area from main flow path behind containment measures (i.e., coffer dams or other suitable measures), and carry out fish rescue/relocations in the area supporting water at the time of construction to relocate all aquatic species within construction footprint.

Sediment and erosion control measures will need to be designed to minimize indirect impacts of sediment release to the receiving watercourse downstream during and following construction measures until the construction area has been re-stabilized.

Sites 2, 4 and 5:

Mitigation measures include:

• Overall increases in in-water footprints should be minimized as much as possible. • In-water works occurring during the permissible seasonal window for the Thames River,

to minimize impacts to the sensitive life cycle functions of the resident species. • Construction areas being isolated from main flow path behind containment measures

(i.e., coffer dams or other suitable measures), and fish and mussel rescue/relocations carried out to relocate all aquatic species within construction footprint.

• Additional Schedule B permitting as required for relocation of these species. • Sediment and erosion control measures designed to minimize indirect impacts of

sediment release to the watercourse during and following construction measures until the construction area has been re-stabilized.

Site 3: Medway Creek Crossing on Western Road

The increase of the in-water footprint will be minimized as much as feasible. In-water works will be limited to the permissible seasonal window for Medway Creek to minimize impacts to the sensitive life cycle functions of the resident species. Construction areas should be

Page 17: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-16

isolated from main flow path behind containment measures (i.e., coffer dams or other suitable measures) and fish and mussel rescue/relocations. These rescue/relocations should be carried out to relocate all aquatic species within the construction footprint. Sediment and erosion control measures will need to be designed to minimize indirect impacts of sediment release to the watercourse during and following construction measures until the construction area has been re-stabilized. Efforts should be made during construction to ensure that fish can continue to move safely through the channel to habitats upstream and downstream of the bridge

Site 5: Thames Crossing on Wellington Road

In addition to an ESA permit that will likely be required, it is also possible that a SARA permit will be required due to the potential for critical habitat by a federally at-risk species (Round Pigtoe).

Site 7: Exeter Road Park-and-Ride

Sediment and erosion control measures will need to be designed to minimize indirect impacts of sediment release to the watercourse during and following construction activities, until the construction area has been re-stabilized. Additional hydraulic modelling will be required to identify actions that can reduce the floodplain area at this location in order to address flooding concerns that may result from additional development. In addition, management of surface water flows related to the increase in impervious surfaces and redirection of flows into existing municipal storm sewers or use of LID features should be considered, as discussed in Section 4.1.6.

4.2.3.2.2 General Mitigation In addition to the above-noted mitigation measures for the specific sites, the following mitigation measures should be considered as appropriate for each of the sites:

Timing

• To avoid disruption to sensitive fish life stages for all the watercourses, all in- or near-water works will be conducted within the permissible construction period of June 16th to March 14th, as identified by the Ministry of Natural Resources and Forestry (MNRF) through the consultation process. However, it should be noted that a tighter window may be required on those watercourses where Silver Shiner have been confirmed to ensure that bank rehabilitation works have time to take hold and re-vegetate before the spring or fall rainy season, where sedimentation may become a concern for this species and its habitat.

• No equipment should be allowed to ford or otherwise enter the watercourse except as specified in the contract or unless authorized by the appropriate environmental agencies/permits.

Debris Removal

• The removal of material shall be limited to what is necessary for the works and shall be removed by hand or with machinery operating from the banks or a floating barge.

• During structure removal works, suitable mitigation measures will be in place to trap and avoid materials from entering the watercourses (e.g. netting, floating debris barges, etc.).

Land-Based Impacts Through use of Industrial Equipment

• Machinery will be operated on land in a manner that minimizes disturbance to the banks of the watercourses.

• A spill control/response plan (kept on site), will need to be developed and implemented by the contractor to prevent deleterious substances from entering the watercourses. The plan should require that well-maintained machinery, free of fluid leaks, is used for all construction activities. It should also require that washing, refueling and servicing of machinery, along with the storage of fuel, is limited to the construction staging area, which should be a minimum of 30 m away from all watercourses.

Deposition of Deleterious Substances

• Storage and stockpiling of soil and other fill material should be located a minimum of 30 m away from any watercourse(s), drainage features or the tops of steep slopes.

• Appropriate ‘temporary flow passage’ measures should be developed and implemented, and supported by all appropriate erosion and sediment control measures, to isolate the temporary in-stream construction zones required for the in-water works for the pier extensions/replacements.

• Only clean materials free of fine particulate matter should be placed in the water for temporary construction measures (e.g. coffer dams should be constructed of ‘pea gravel’ bags, geotextile fabric, sheet pile or other clean material).

Erosion and Sediment Control

• The installation of Erosion and Sediment Control (ESC) measures around the watercourses and drainage features outletting to watercourses need to be installed prior to the initiation of construction works, to prevent encroachment and the transfer of deleterious substances into the aquatic habitat.

• All ESC measures should be inspected regularly, and maintained by the contractor to ensure they are functioning as intended throughout the construction period, and until such time as the bank areas have been re-stabilized or re-vegetated.

• Sediment-laden water from dewatering activities is to be treated using appropriate settlement (e.g. temporary pond) and/or filtration (e.g. sediment filtration device, filter bags and/or vegetated strips) before being allowed to enter into a watercourse, to ensure that no entrained sediment is released to the watercourses supporting fish habitat.

Restoration of Disturbed Areas

• Minimize removal of vegetation, retain existing vegetation and stabilize exposed soils with vegetation where possible, and as soon as feasible following construction, to

Page 18: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-17

minimize changes to the banks of the watercourses, and shade provided to the local fish community.

• Limit the duration of soil exposure and stage construction on paved surfaces where possible.

• Limit the size of disturbed areas by minimizing non-essential clearing and grading.

4.2.3.3 Net Effects Net effects, categorized by site, may include:

Site 1: Oxford Street West at Mud Creek

Net effects of BRT are assumed to be nominal once all the channel realignment and habitat enhancement elements associated with the Mud Creek Subwatershed Class EA works are completed. If fish and fish habitat exist within the culvert following realignment works, net residual effects may include nominal shading of the habitat as well as an increase in the in-water footprint for the longer culvert length. This extension will occur prior to BRT project implementation.

Site 2: North Thames Crossing on Queens Avenue and Riverside Drive

No net effects are anticipated, as no in-water works are required and appropriate sediment and erosion controls will limit the potential for runoff from construction entering the waterway. Construction-related effects can be avoided through implementation of standard mitigation measures

Site 3: Medway Creek Crossing on Western Road

Increase in permanent in-water footprint associated with longer pier and a loss of habitat potentially used by aquatic SAR species due to the potential encroachment of the increased pier footprint into the permanently wet area of the channel. Works resulting in increases to the permanent in-water footprint may require permitting under the ESA associated with the various aquatic SAR, as well as potential FAA permitting to address impacts to fish and fish habitat generally. It is the aim of such plans to ensure that negative net effects to the species and/or their habitat does not occur.

Site 4: North Thames Crossing on University Drive

A decrease in the permanent in-water footprint may be possible if the bridge is modified to include wider spans and piers on the shores. A comprehensive assessment of impacts and overall benefits to aquatic species will be completed in the development of design alternatives to ensure that there are no net negative impacts to any of the SAR species. This will require on-going liaison with MNRF staff and the bridge owner.

Site 5: Thames Crossing on Wellington Road

An increase in the permanent in-water footprint would be associated with a longer pier.

Due to the number of SAR potentially impacted by the works associated with this bridge, including impacts to both the terrestrial features adjacent the bridge, as well as the channel and banks below the high water mark, an ESA permit will potentially be required for changes to this structure with overall benefit plans developed to address these impacts for each of the SAR. Due to the potential for critical habitat by a federally at-risk species (Round Pigtoe), it is also possible that a SARA permit will be required. Ongoing consultation with MNRF and DFO will be necessary to determine permitting requirements at this site. In addition to these SAR requirements which are to achieve a net positive effect, it is expected that the implementation of mitigation and compensatory mitigation measures as outlined in Appendix G will be sufficient to offset impacts to the natural heritage system at this site.

Site 6: Westminster Ponds east of Wellington Road

No net effects are anticipated to fish and fish habitat. Overall it is anticipated that a positive net environmental effect can be gained at this site through the implementation of a comprehensive enhancement and restoration plan for the thicket and woodland communities adjacent to Wellington Road.

Site 7: Exeter Road Park-and-Ride

There are no net residual effects anticipated for fish and fish habitat within Murray Drain, as there are no direct impacts on the watercourse itself. The UTRCA will be consulted during design of the park-and-ride in detail design to ensure there are no net residual effects resulting from the changes in the floodplain and flooding conditions within the Drain prior to approving the development parcel.

Works resulting in permanent in water footprint increases may require permitting under the ESA associated with the various aquatic SAR, as well as potential FAA permitting to address impacts to fish and fish habitat generally.

4.2.3.4 Monitoring A two part Environmental Management and Monitoring Plan (EMMP) is recommended to document the implementation of the mitigation and compensation measures during and after construction.

Part 1 of the EMMP will consist of a Construction Monitoring Plan to monitor construction-related impacts, document the successes and/or deficiencies of the implemented mitigation measures (e.g., Erosion and Sedimentation Control Plan, Spill Control / Response Plan, etc.), and provide guidance on remedial actions/provisions for when mitigation is not successful. This plan will be developed during the detail design phase.

Part 2 of the EMMP is to consist of a long-term Post-construction Monitoring Plan to evaluate the success of the restoration / compensation efforts and to assess cumulative impacts on the Natural Heritage System. This plan should include contingency/remedial provisions that will be triggered if effects exceed a pre-determined threshold. For example, the need for supplementary plantings would be triggered if survival rates reach a specified percentage (e.g., 50%), or wildlife fencing would be erected to encourage movement

Page 19: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-18

through the valley if there is evidence of increased road mortality at a particular site. Compensation and monitoring requirements for SAR, are to be determined during the detail design phase in consultation with agency staff, and should also be integrated into this plan.

Recommendations for monitoring include, but are not limited to:

• Success of woodland and wetland restoration plantings; • Transplantation success for plants and trees; • Evidence of bank erosion or scouring at or downstream of sites with in-water works; • Success / wildlife use of newly created habitat; • Wildlife monitoring to confirm continued use of known habitat features post-construction

(e.g., basking and nesting sites by turtles); • Evidence of increased road mortality by wildlife at Sites 3, 4, and 5, or effectiveness of

existing or enhanced movement corridors; • Stability of bank restoration areas and success of vegetative growth on banks; and, • Identification of drainage issues associated with increased impermeable surface at Site

7 related to the functioning of Murray Drain. Removal of invasive species as part of the Invasive Species Management Strategy and Ecological Restoration Plans should continue during Part 2 of the EMMP.

4.2.4 Vegetation and Vegetation Communities

4.2.4.1 Potential Impacts

Site 1: Oxford Street West at Mud Creek

As the natural heritage system associated with Mud Creek will largely be altered and restored beyond the anticipated BRT road corridor as part of the Subwatershed EA, direct impacts to the identified natural heritage features are not anticipated as a result of the works. Based on the current design concept, vegetation removal along Oxford Street West is expected to be minor and restricted primarily to previously disturbed areas within the eastern portion of the site where the infrastructure extends beyond the ROW.

Site 2: North Thames Crossing on Queens Avenue and Riverside Drive

Vegetation adjacent to the bridge abutments and roadway is largely manicured or planted, and occurs within parkland or other constructed. The current design concept is expected to result in minor impacts to vegetation adjacent to the Queens Avenue Bridge within a Significant Valleyland.

Site 3: Medway Creek Crossing on Western Road

Since the Medway Creek crossing is to be widened to the east, the works are expected to result in the limited loss of vegetation within the footprint of the proposed road and bridge

abutments, as the area immediately east of the bridge consists primarily of constructed parkland (CGL_2), low density residential (CVR_1) and parking areas associated with the University Hospital (CVS_2). The bank of Medway Creek on the east of the southern abutment had some limited herbaceous vegetation amongst riprap associated with a stormwater outfall from the nearby hospital parking area, with more natural riparian vegetation further east along the bank. To the north, trees adjacent to the constructed valley wall were largely non-native species (Black Locust, Siberian Elm and European Buckthorn). By widening to the east, wooded areas within and adjacent to the Medway Valley Heritage Forest ESA and significant woodlands (unevaluated vegetation patch #3003) on the west side of the bridge beyond the right of way will be maintained.

Site 4: North Thames Crossing on University Drive

To accommodate the wider bridge and new abutment locations, grading will be required to contour and shape the banks of the valleyland, resulting in removal of vegetation within the new footprint. This would likely result in permanent habitat loss associated with the new infrastructure footprint, as well as temporary losses within the construction area. The young Kentucky Coffeetree, located north of the eastern bridge abutment, could be impacted by grading associated with construction of a new bridge abutment.

Site 5: Thames Crossing on Wellington Road

To accommodate the wider bridge concept, grading will be required to contour and shape the banks, resulting in removal of vegetation within the new footprint. This could result in permanent loss associated with the new infrastructure footprint, as well as temporary losses within the construction area. Works on the abutments will likely require removal of localized vegetation on the banks, and potential re-grading of the bank to accommodate the changes to the recreational trail.

Removals associated with mature trees and woodland habitat are expected to be minor as vegetation on the east side of the bridge, within the footprint of the wider bridge, is largely disturbed or manicured parkland.

Site 6: Westminster Ponds east of Wellington Road

The existing four-lane road cross-section is to be expanded to accommodate two dedicated Rapid Transit lanes, four general use lanes, a sidewalk on the west, and a multi-use trail on the east. Within the southern portion of the site, adjacent to the Dry-Fresh Deciduous Woodland (WODM4) and Cattail Mineral Shallow Marsh (MASM1-1) which is part of the PSW, the proposed infrastructure is located within the right of way; but to the north, adjacent to the Buckthorn Deciduous Shrub Thicket (THDM2-8) portions of the multi-use trail will encroach beyond the right of way. Grading is required to achieve a suitable cross-section, and will involve encroachment within the southern and northern portions of the site. Less than 1% of the 250 ha ESA, and 0.7% of the PSW is to be impacted by grading beyond the right of way.

Page 20: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-19

There may experience a short-term reduction in wetland habitat while the replacement wetland vegetation becomes established, and longer-term reduction in woodland cover for a period of 20 to 40 years while trees grow and the community becomes established

Temporary disturbance associated with construction may also occur. Temporary disturbance associated with construction (grading, movement of heavy machinery, etc.) may also occur.

Site 7: Exeter Road Park-and-Ride

The potential infrastructure footprint encroaches into the significant valleyland. The encroachment is into a portion of the valleyland that is characterized by manicured grass and based on the surveys completed as part of this EIS, the area is thought to provide limited ecological function.

4.2.4.2 Mitigation Proposed mitigation measures include:

• Minimize vegetation clearing where possible, and when clearing, delineate vegetation clearing zones and vegetation retention zones (i.e. using silt fencing or tree protection fencing) on both the construction drawings and in the field with the Contractor prior to clearing and grading.

• Stabilize and re-vegetate exposed surfaces as soon as possible upon completion of works.

• Tree and vegetation protection is recommended for trees and vegetation to be retained. • Tree protection should be outlined in a Tree Protection Plan (TPP) to be developed

during detail design. Vegetation protection measures should be detail on contract drawings and implemented to ensure encroachment is limited to the construction footprint.

• Development of an invasive species management strategy, which will include a clean equipment protocol, removal of invasive species using best management practices established by the Ontario Invasive Plant Council, and the development of an ecological restoration plan using appropriate native species.

• A mitigation / compensation strategy to address removal of street trees will be developed through consultation with the City during the detail design phase. There is to be no net loss in tree canopy cover as a result of the project.

For Site 3, the existing Kentucky Coffeetree will be transplanted to avoid harm to the individual.

For Site 6, efforts were made to reduce encroachment into the natural area; however, in order to accommodate utility poles and street-lighting, the landscape strip between the back of curb and the edge of the multi-use pathway could not be reduced to less than 1.5 m. Side slopes associated with the road cross-section were increased from a 3:1 slope to a 2:1 slope to reduce the area of impact. These measures have decreased the overall impacts outside the ROW by 24.8% (from 5,216.8 m2 to 3,854.1 m2).

4.2.4.3 Net Effects Net effects will include:

• A minor loss of disturbed vegetation within the right-of-way • A reduction in tree cover along BRT corridors in areas where road widening is required

for 20 to 40 years until replacement trees mature There is an opportunity for positive net effect where removal of non-native or invasive species is proposed followed by ecological restoration plan incorporating appropriate native species.

Site 6: Westminster Ponds east of Wellington Road

It is anticipated that a positive net environmental effect can be gained at this site through the implementation of a comprehensive enhancement and restoration plan for the thicket and woodland communities adjacent to Wellington Road. This plan would include a focused invasive species management strategy to remove European Buckthorn and Glossy Buckthorn, as well as other invasive species from the thicket (THDM2-8) and woodland (WODM4) communities adjacent to Wellington Road. These vegetation communities were once dominated by native species, and in some cases were considered provincially significant, but have become overwhelmed by these invasive species. This compensatory mitigation would be completed in addition to habitat replacement at a ratio greater than the one-for-one land area required as mitigation.

Site 7: Exeter Road Park-and-Ride

Net effects will include permanent loss of vegetation within the floodplain. Vegetation lost within the floodplain is not considered significant (manicured lawn); however, compensation to address encroachment into natural vegetation within the significant valleyland (if unavoidable) may be offset by enhancing the riparian vegetation to include native shrubs or trees.

4.2.4.4 Monitoring A two part EMMP is recommended to document the implementation of the mitigation and compensation measures during and after construction, as discussed in Section 4.2.3.2.

4.2.5 Wildlife and Wildlife Habitat

4.2.5.1 Potential Impacts Impacts to wildlife are directly associated with impacts to vegetation, which comprises their habitat. Permanent encroachment of infrastructure into woodlands, wetlands and ESAs will result in habitat loss. Noise, dust and vibrations associated with construction activities have the potential to cause short-term disturbance to wildlife and may cause certain wildlife to abandon or avoid the area. Long-term impacts are not expected as the infrastructure is proposed in areas that are already developed and the proposed works do not involve a change in land use.

Page 21: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-20

Site 1: Oxford Street West at Mud Creek

Oxford Street West will be widened through this area by up to 6 m as part of the Rapid Transit works, creating a slightly greater barrier to wildlife movement across the roadway, and increased potential for road mortality. Should mature trees exist within the proposed vegetation removal areas, there could potentially be impacts to bat maternity roost sites (cavity trees) and roosting bats.

Construction of a larger, open-bottom box culvert part of the Mud Creek Subwatershed EA may provide opportunities for movement by amphibians, reptiles and small mammals provided some areas of dry passage are maintained.

Site 2: North Thames Crossing on Queens Avenue and Riverside Drive

No impacts are anticipated.

Site 3: Medway Creek Crossing on Western Road

Though not anticipated, the function of the valleyland as a movement corridor may be impacted during and after construction should expansion of the abutment or valley wall create an obstruction to wildlife. If obstructed, wildlife may attempt to cross the widened roadway in order to reach habitat upstream or downstream of the bridge, increasing the likelihood of road mortality.

This Site provides habitat for endangered and threatened species (Spiny Softshell, Queensnake), and species of conservation concern (Northern Map Turtle and Snapping Turtle). The proposed works have the potential to directly impact habitat for these species through vegetation removal, habitat loss, alteration to banks and alteration of the channel bed.

Construction activities have the potential to cause short-term impacts to resident birds, mammals and amphibians. The greatest threat to avian species is associated with disturbance or destruction of nests during the nesting period.

Site 4: North Thames Crossing on University Drive

The University Drive Bridge will be fully replaced by a wider bridge with new abutment locations, and grading required to contour and shape the banks of the valleyland. This will require the removal of vegetation within the new footprint, likely resulting in permanent habitat loss associated with the new infrastructure footprint, as well as temporary losses within the construction area.

Relocation of the pier to the river bank, will result in the alteration of bank habitat below the high water mark that is potentially used by SAR turtles, as well there are potential short-term impacts to resident birds, mammals and amphibians, due to construction activities. Birds are particularly vulnerable to impacts associated with disturbance or destruction of nests during the nesting period.

Site 5: Thames Crossing on Wellington Road

To accommodate the wider bridge proposed, grading will be required to contour and shape the banks, resulting in removal of vegetation within the new footprint. This could result in permanent habitat loss associated with the new infrastructure footprint, as well as temporary losses within the construction area. An increase to the in-water footprint associated with the proposed extension to the pier, and the increase in the permanent footprint below the high water mark, associated with changes to the banks and the recreational trail system, has the potential to impact terrestrial SAR that use habitat within and in close proximity to the watercourse. Associated impacts include the loss of habitat within the channel bed for the wider pier, loss of bank habitat for the abutments, and alteration of the bank habitat for the changes to the recreational trail. Work in this area also has the potential to impact adjacent turtle nesting areas.

There are potential impacts to wildlife that primarily utilize habitats below the high water mark, as well as potential short-term impacts to resident birds, mammals and amphibians, due to construction activities. Birds are particularly vulnerable to impacts associated with disturbance or destruction of nests during the nesting period.

Site 6: Westminster Ponds east of Wellington Road

There are potential impacts to wildlife and wildlife habitat, as vegetation will be removed due to grading.

Site 7: Exeter Road Park-and-Ride

No impacts are anticipated, as the proposed level of encroachment (9 m) is unlikely to impact the movement of wildlife through the valleyland.

4.2.5.2 Mitigation Mitigation and compensatory areas for removal of natural heritage features will serve to minimize and replace habitat loss, respectively. To avoid disturbance to local wildlife and comply with the Migratory Birds Convention Act, clearing (including grubbing) of trees and vegetation should be completed outside of the bird nesting season (approximately April 1 to August 31).

Maintenance of this movement corridor for terrestrial wildlife should be considered during detailed design, and is to include the creation of an eco-passage and/or erection of fencing to provide safe passage through the valleyland and discourage animals from entering the roadway, if deemed necessary due to an obstruction. Exclusion fencing is recommended to prevent species from entering the construction area. Once work is completed, fencing should be removed to facilitate passage by wildlife.

In the event an animal is found within the construction area, it should remain undisturbed and be allowed to leave on its own. Photos for identification should be taken of animals observed onsite, if possible. If Threatened or Endangered species are discovered during site preparation or construction, activities will stop, or be modified to avoid negative impacts

Page 22: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-21

to Species at Risk until further direction is provided by the MNRF. In the event of such a discovery, MNRF Aylmer District office should be contacted promptly.

In areas where endangered and threatened species, a comprehensive assessment of impacts and overall benefits to terrestrial species will need to be completed once design details are finalized to ensure that there are no net negative impacts to any SAR species. This will require on-going liaison with MNRF staff and the design team.

Confirmation of nest presence/absence is recommended prior to commencement of works so that appropriate measures can be taken to ensure compliance with the ESA.

Specific mitigation measures to reduce disturbance to nesting turtles and long-term impacts to substrates at Site 5 is included in Appendix G.

4.2.5.3 Net Effects Net effects may include:

• Nominal long-term negative impacts associated with a potential increase in wildlife road mortality due to the wider road cross-section required for the RT infrastructure along Oxford Street West. These impacts are expected to be nominal given the existing fragmentation of the valleyland and the nature of the resident wildlife. The new culvert may also serve to improve habitat connectivity and wildlife passage between portions of the valleyland north and south of Oxford Street West.

• Habitat associated with woodland replacement will be reduced for 20 to 40 years, while newly planted trees grow.

• Replacement of wetland area is expected to result in short-term (1 to 3 years) reduction of habitat.

• A permanent increase in the footprint impacts on the valley and its associated habitat. • Compensatory mitigation for removal of natural features may provide additional benefit

through habitat enhancements for wildlife. • For sites that will require an ESA Overall Benefit Permit, overall benefit plans will be

developed to address impacts for each of the SAR. It is the aim of such plans to ensure that negative net effects to the species and/or their habitat does not occur.

4.2.5.4 Monitoring A two part EMMP is recommended to document the implementation of the mitigation and compensation measures during and after construction, as discussed in Section 4.2.3.2.

4.2.6 Significant Natural Features and Sensitive Areas

4.2.6.1 Potential Impacts Potential impacts are categorized by site for each significant and/or sensitive natural feature identified within the Study Area:

Sites 1, 3, 4 and 5: Significant Woodlands

Potential indirect impacts to woodlands include damage to vegetation outside the work zone, sedimentation, spills of contaminants / fuel, root pruning, and soil compaction.

Site 1: Oxford Street West at Mud Creek

There are woodlands north (unnumbered Patch: FODM4-11) and south (Patch 6007: FODM1-4) of Oxford Street West adjacent to the proposed works. However, the woodlands to the north have been removed by a private developer and realignment/enhancement of the Mud Creek corridor is expected to occur in advance of the RT works. As such, direct impacts from the edge encroachment beyond the ROW to the north are not anticipated. There is no encroachment into the woodland to the south anticipated.

Common Evening Primrose, a regionally rare plant species (UTRCA, 2003), was noted at this Site. There is potential for impacts to this species if it occurs within the area to be disturbed.

Site 3: Medway Creek Crossing on Western Road

Direct impacts to woodlands (FODM3-1 and WODM4-4) on the west side of Western Road are not anticipated as a result of the proposed road alignment and widening. Minor impacts to wooded areas east of the existing bridge may occur to accommodate the widened bridge abutments.

Site 4: North Thames Crossing on University Drive

Woodlands (FODM7) on both sides of the North Thames, including patch #3001 to the northwest, which was assumed to be significant as part of this study, may be impacted by the replacement of the University Drive Bridge. A Kentucky Coffeetree within the wooded area adjacent to the northeast abutment may need to be transplanted to avoid impacts.

Site 5: Thames Crossing on Wellington Road

Woodlands (FODM4-5) on the east side of the Wellington Road crossing may experience minor impacts as a result of the proposed bridge widening and alterations to the grade of the northeast Thames Valley trail access to meet accessibility standard. The extent to which these vegetation communities will be impacted will need to be assessed once the grading limits and extent of disturbance is confirmed during detail design.

Removals associated with mature trees and woodland habitat are expected to be minor as vegetation on the east side of the bridge, within the footprint of the wider bridge, is largely disturbed or manicured parkland.

Sites, 1, 2, 3, 4, 5, and 7: Significant Valleylands

Existing infrastructure (roads and bridges) occur within the Significant Valleylands at Sites 1, 2, 3, 4 and 5. Modifications to the Mud Creek corridor at Site 1 are expected to occur in advance of the BRT works. As such, potential impacts to the valleyland are not anticipated.

Page 23: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-22

Alterations to bridges and contouring of banks to improve hydraulic capacity at Sites 3 and 4 have the potential to improve flood and hazard conditions within the valleyland and associated floodplain.

The current configuration for the infrastructure at Site 7 encroaches into the significant valleyland of the Murray Drain, defined as a 30 m wide corridor on either side of the drain. The infrastructure is proposed within a manicured area, where impacts to ecological functions are not anticipated. Efforts should be made during detail design to modify the infrastructure footprint at Site 7 to achieve a minimum setback of 30 m from the high water mark of Murray Drain, if possible.

Sites 3 and 6: Environmentally Significant Areas

An edge encroachment to accommodate road widening and/or modifications to the crossings may occur at Sites 3 and 6.

Site 3: Medway Creek Crossing on Western Road

Medway Valley Heritage Forest ESA is located adjacent to the southwest corner of the Medway Creek crossing on Western Road. Works may result in minor impacts to disturbed vegetation within the ROW, however encroachment beyond the ROW into the ESA is not anticipated. The extent of grading within this area will be determined during the detail design phase, at which time further assessment will be necessary.

Site 6: Westminster Ponds east of Wellington Road

Westminster Ponds / Pond Mills ESA / PSW / ANSI is located on the east side of Wellington Road in this area. Encroachment beyond the ROW into the edge of thicket, woodland, and wetland communities is anticipated under the current configuration. The thicket and woodland communities contain a high proportion of non-native and invasive species, namely European and Glossy Buckthorn. Indirect impacts to wildlife may occur during construction, however long-term impacts are not anticipated given the infrastructure is proposed in areas that are already developed and does not involve a change in land use.

Efforts were made to reduce encroachment into the natural area. Side slopes associated with the road cross-section were increased from a 3:1 slope to a 2:1 slope to reduce the area of impact. These measures have decreased the overall impacts outside the ROW by 24.8% (from 5,216.8 m2 to 3,854.1 m2). Less than 1% of the 250 ha ESA, and 0.7% of the PSW is to be impacted by grading beyond the ROW.

Site 6: Provincially Significant Wetlands

Under the current design concept, an encroachment into the edge of the Cattail Mineral Shallow Marsh (MASM1-1) is expected. In order to accommodate utility poles and street-lighting, the landscape strip could not be reduced to less than 1.5 m between the back of curb and the edge of the multi-use pathway. A similar landscape strip (1.0 m in width) is proposed on the east side of the multi-use trail and is intended for street furniture and/or utilities.

The merits and drawbacks of graded side slopes and retaining walls were also considered in attempts to further reduce the area of encroachment into the Westminster Ponds area. It was determined that construction impacts, costs, and ongoing maintenance needs made a retaining wall a less desirable solution to reduce the width of the road cross-section in this area. By changing side slopes from a 3:1 slope to a 2:1 slope, the area of impact has been reduced within the PSW by 120.4 m2, and by 1,272.7 m2 in the woodland/thickets.

Temporary disturbance associated with construction (grading, movement of heavy machinery, etc.) may occur.

Direct impacts may include loss of habitat, removal of wetland vegetation, and temporary construction related effects (erosion and sedimentation, noise, dust, etc.)

Regionally rare plant species including Sweetflag, Watershield, and Buffalo Berry have been observed within the vicinity. Although vegetation removal is expected to be largely restricted to the more disturbed area adjacent to the road, there is potential for impacts to these regionally rare species if they occur within the area to be disturbed.

Hybrid or Blue Cattail (Typha x glauca) was observed within the MASM1-1 vegetation community, along with the parent species, Narrow leaved Cattail and Broad-leaved Cattail. Blue Cattail is listed as rare within Middlesex County (UTRCA, 2003). Given its hybrid status, and the co-occurrence of the parent species, transplantation may not be warranted. Discussion with UTRCA during detail design will be completed to verify relocation needs, if any.

Indirect or long-term effects include potential impacts associated with increased input of road salts into the PSW and potential alteration to drainage patterns (groundwater and/or surface water flows).

4.2.6.2 Mitigation Potential mitigation measures are categorized by site for each significant and sensitive natural feature identified within the Study Area:

Sites 1, 3, 4 and 5: Significant Woodlands

• Clearing should be minimized where possible. Vegetation clearing zones and vegetation retention zones should be clearly delineated (i.e. using silt fencing or tree protection fencing) on both the construction drawings and in the field with the Contractor prior to clearing and grading.

• Survey vegetation within the clearing zone prior to the commencement of works to identify regionally rare plant species. Surveys should be completed during appropriate timing windows when the plant species is readily identified (e.g., flowering stage, leaf on). A ‘best effort’ approach should be taken to relocate affected individuals to suitable habitat beyond the area of disturbance.

• Tree and vegetation protection is recommended for trees and vegetation to be retained. Tree protection should be outlined in a Tree Protection Plan (TPP) to be developed at

Page 24: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-23

detail design. Vegetation protection measures should be detail on contract drawings and implemented to ensure encroachment is limited to the construction footprint.

• Equipment, materials and other construction activities should not be permitted in vegetation retention zones.

• Unnecessary traffic, dumping and storage of materials over tree root zones adjacent to the proposed works should be avoided.

• Exposed surfaces should be stabilized and re-vegetated as soon as possible, upon completion of works.

• To offset for the removal of vegetation communities / habitat associated with significant natural features within the Natural Heritage System, mitigation in the form of habitat replacement at a ratio greater than 1:1 land area is required through plantings of appropriate native species.

• Where feasible, creation of replacement habitat should occur adjacent to the impacted feature. If not possible, replacement habitat should be created as close to the site of impact as possible, and preferably within the same subwatershed. Plantings should strive to meet woodland densities for trees and shrubs, and should include establishment of a healthy understory.

• At all sites there is an opportunity to provide additional compensatory mitigation through the implementation of an invasive species removal and management plan, and/or feature enhancement through plantings of appropriate native species. Due to the sensitive nature of the Natural Heritage System at Sites 3, 4, and 5, compensatory mitigation is recommended to offset impacts to the natural features and functions.

• Comprehensive compensation plans are to be developed during detail design through consultation with the City and relevant agencies.

Sites, 1, 2, 3, 4, 5, and 7: Significant Valleylands

• Alterations to banks and crossings must be supported by hydraulic modelling to ensure that there is a balance between improved hydraulic capacity, and avoidance of potential downstream issues associated with increased erosion and scouring.

• The extent of grading along the banks and around the bridge abutments, and the need for scour protection of the pier footings will be determined at later design phases.

• Maintenance of natural vegetation along the Murray Drain will provide protection to the valley feature and associated wildlife and fish habitat. If grading results in the temporary encroachment into natural vegetation communities within the significant valleyland, appropriate mitigation and compensation measures should be determined through consultation with the City and UTRCA.

• Implementation of a Spills Management Plan, and ESC Plan should be completed to address construction related impacts at each site.

• Permanent changes to the significant valleyland can be offset by implementing a comprehensive compensation plan. To be most effective, this plan may be drafted in conjunction with an overall benefit plans for SAR, to ensure that there is no net negative

impact on the features or various species at this site. It is recommended that the compensation plan include an Invasive Species Management Strategy to help remove invasive plant species, and increase native diversity through appropriate plantings within the adjacent natural heritage system.

Sites 3 and 6: Environmentally Significant Areas

• Encroachment into the ESAs should be limited as much as possible. • Opportunities to further reduce the area of impact should be investigated during the

detail design phase (e.g. increased side slopes to reduce grading requirements, relocation of multi-use trail, etc.).

• General recommendations for Significant Woodlands and PSWs should be implemented to reduce the potential for impacts to these significant areas, as appropriate.

• To offset for the removal of vegetation / habitat, mitigation in the form of habitat replacement at a minimum ratio of 1:1 land area is required through plantings of appropriate native species. Where feasible, creation of replacement habitat should occur adjacent to the impacted feature. If not possible, replacement habitat should be created as close to the site of impact as possible.

• Due to the significant and sensitive nature of these features, compensatory mitigation is required to offset impacts to the features and their functions. Opportunities include, replacement of habitat at a ratio greater than 1:1 land area, implementation of an invasive species removal and management plan, and enhancement of other areas within the ESAs.

• At site 6, mitigation in the form of habitat replacement at a ratio greater than a one-for-one land area will be required for the loss of approximately 3,826.7 m2 of woodland/thicket habitats within the ESA. Further, due to the significance of this area, additional compensation is recommended to offset impacts to the function of this natural area.

Site 6: Provincially Significant Wetlands

• Mitigation in the form of habitat replacement at a ratio greater than a one-for-one land area will be required for the loss of approximately 27.4 m2 of wetland. Further, due to the significance of this area, additional compensation is recommended to offset impacts to the function of this natural area.

• Opportunities to further reduce the area of impact should be investigated during detail design.

• Vegetation clearing should be minimized as much as possible. • Use of heavy machinery within the PSW should be avoided. If unavoidable, swamp

mats or similar materials should be used to avoid soil compaction. • Vegetation clearing zones and vegetation retention zones should be clearly delineated

(i.e. using silt fencing or tree protection fencing) on both the construction drawings and in the field with the Contractor prior to clearing and grading.

Page 25: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-24

• Vegetation within the clearing zone prior to the commencement of works should be surveyed to identify regionally rare plant species. Surveys should be completed during appropriate timing windows when the plant species are readily identified (e.g., flowering stage, leaf on). A best effort approach should be taken to relocate affected plants to suitable habitat beyond the area of disturbance.

• Changes to drainage patterns should be minimized to reduce/eliminate potential for changes to the existing wetland moisture regime and site hydrology.

• Stormwater Management Plans should include strategies to balance surface water and/or ground water inputs to the PSW between pre- and post-construction. Preliminary analysis indicates that water balance at this site can be achieved; thereby maintaining the existing moisture regime within the PSW.

• A Spills Management Plan should be developed and used for the construction area. • An Erosion and Sedimentation Control Plan should be developed and used to minimize

the risk of potential impacts from sedimentation on the water quality and quantity within wetlands and surface water features.

• The use of alternative de-icing products / application methods should be considered to reduce the input of road salts into the wetlands and ponds. There are no stormwater management techniques that capture road salts or reduce road salt water pollution.

• To offset for the removal of wetland communities / habitat, mitigation in the form of habitat replacement at a ratio greater than 1:1 land area is required through plantings of appropriate native species. Where feasible, creation of replacement habitat should occur adjacent to the impacted feature. If not possible, replacement habitat should be created as close to the site of impact as possible (i.e., elsewhere within the Westminster Ponds / Ponds Mills ESA).

• Due to the significant and sensitive nature of this feature, additional compensatory mitigation is recommended to offset impacts to the feature and its functions. An Invasive Species Removal and Management Plan should be developed and used, in conjunction with Enhancement Planting Plans for other areas within the ESA to provide a net environmental benefit to the area. Vegetation communities in proximity to Wellington Road contain a high proportion of undesirable invasive species (fifteen species including European Buckthorn and Glossy Buckthorn) which are outcompeting native species; thereby decreasing native diversity and degrading associated habitat. Comprehensive compensation plans are to be developed through consultation with the City and relevant agencies.

4.2.6.3 Net Effects Potential net effects are grouped by the significant and sensitive natural feature identified within the Study Area:

Sites 1, 3, 4 and 5: Significant Woodlands

• Minor vegetation removal in woodland communities outside of the ROW may occur at Sites 1, 3, 4, and 5.

• The degree of encroachment is not anticipated to alter the designation of these woodlands as significant.

• Minor vegetation removals are not anticipated to affect resident significant flora or fauna species (following transplantation, if necessary, of Kentucky Coffeetree and Common Evening Primrose individuals, at Sites 4 and 1, respectively)

• Resident wildlife will be displaced to adjacent natural areas • A reduction in tree cover along BRT corridors in areas where road widening is required

for 20 to 40 years until replacement trees reach maturity.

Sites, 1, 2, 3, 4, 5, and 7: Significant Valleylands

• Potential gains may be achieved at Sites 3 and 4 by increasing hydraulic capacity, and improving protection from flooding and other hazard processes.

• Minor encroachment into other natural heritage features and habitat within the valleylands at Sites 3, 4 and 5 will be offset through mitigation and compensatory mitigation measures for woodlands, and/or overall benefit permits for species at risk, if required at those sites.

• Net effects are not anticipated at Sites 1, 2, or 7

Sites 3 and 6: Environmentally Significant Areas

There are no net effects anticipated at Site 3.

Net environmental gains can be achieved at Site 6 through the implementation of an invasive species management plan focusing on removal of invasive species and replacement and enhancement with appropriate native species. Encroachment into the edge of the ESA can be offset through mitigation and compensatory mitigation measures. Impacts will not affect the designation of this area as an ESA. While limited, where mature trees are to be removed, reduction in tree cover for 20 to 40 years may occur while newly planted woodland replacement areas grow.

Site 6: Provincially Significant Wetlands

• Vegetation removal within the PSW adjacent to the ROW is to be mitigated at a replacement ratio greater than 1:1 land area.

• Encroachment is not anticipated to affect the designation of this wetland as significant. • Proposed removals are not anticipated to affect significant flora or fauna species. • Resident wildlife will be displaced to adjacent natural areas. • Wetland area will temporarily be reduced for 1 to 3 years while wetland replacement

area(s) grow. • Gains in botanical diversity and quality can be obtained by enhancing adjacent

terrestrial portions of the Westminster Ponds / Pond Mills ESA through removal and

Page 26: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-25

management of invasive species (European and Glossy Buckthorn) and planting of native species.

• There may be short-term reduction in wetland habitat while the replacement wetland vegetation becomes established, and longer-term reduction in woodland cover for a period of 20 to 40 years while trees grow and the community becomes established; however, overall it is anticipated that a positive net environmental effect can be gained at this site through the implementation of a comprehensive enhancement and restoration plan for the thicket and woodland communities adjacent to Wellington Road.

4.2.6.4 Monitoring A two part EMMP is recommended to document the implementation of the mitigation and compensation measures during and after construction, as discussed in Section 4.2.3.2.

4.2.7 Air Quality Further details on air quality are provided in Appendix H: Air Quality Impact Assessment Report.

4.2.7.1 Potential Impacts To identify the potential impact of the project on air quality, future Full Build and No-Build scenarios were compared for the horizon year of 2034 using the methodology described in Appendix H.

The cumulative impacts were calculated by aggregating the project specific modelling results with the 90th percentile background ambient concentrations. The cumulative impacts were compared to air quality thresholds and the percentage is presented can be found in Appendix H. The cumulative air quality impacts of the project are predicted to be below the air quality thresholds, with the exception of annual NO2, PM2.5, benzene, and annual and 24 h benzo(a)pyrene, which already exceed the air quality thresholds from 90th percentile background ambient concentrations,

The air dispersion modelling results for the selected Contaminants of Concern (COCs) for the most impacted sensitive receptor for each scenario are provided in Appendix H.

4.2.7.2 Net Effects The cumulative impacts were compared with air quality thresholds and no additional exceedances of the thresholds were identified, other than 1 h NO2, for the No-Build Scenario within the Oxford study area. With the exception of annual PM2.5, the contribution of the project to pre-existing exceedances from ambient background concentrations is a net improvement. Comparison of the cumulative concentrations shows the COCs associated with the Project are below the air quality thresholds, or result in a net improvement, or no change to existing condition exceedances.

4.2.7.3 Mitigation To mitigate construction activities an Air Quality Management Plan will be developed to address construction equipment and vehicle exhaust, potential traffic disruption and congestion, fugitive dust and odour. The Air Quality Management Plan will be submitted to the City of London and MECP for review prior to construction, to ensure the plan is adequate to control fugitive releases caused by construction. Potential mitigation measures that may be included in the Air Quality Management Plan include:

• Dust suppression measures (e.g., application of water wherever appropriate, or the use of approved non-chloride chemical dust suppressants, where the application of water is not suitable) will conform to recognized standard specifications such as the Cheminfo Services Inc. March 2005 publication “Best Practices for the Reduction of Air Emissions from Construction and Demolition Activities” prepared for Environment Canada;

• Use of dump trucks with retractable covers for the transport of soils and other friable materials;

• Minimize the number of loadings and unloading of soils and other friable materials; • Minimize drop heights, use enclosed chutes, and cover bins for debris associated with

deconstruction of affected structures; • Washing of equipment and use of mud mats where practical at construction site exits to

limit the migration of soil and dust off-site; • Dust monitoring in locations where it has been determined that a particulate bound

contaminant of concern exists in native soil; • Stockpiling of soil and other friable materials in locations that are less exposed to wind

(e.g., protected from the wind by suitable barriers or wind fences/screens, or covered when long-term storage is required) and away from sensitive receptors to the extent possible;

• Reduction of unnecessary traffic and implementation of speed limits; • Permanent stabilization of exposed soil areas with non-erodible material (e.g., stone or

vegetation) as soon as practicably possible after construction in the affected area is completed;

• Ensuring that all construction vehicles, machinery, and equipment are equipped with current emission controls, which are in a state of good repair; and,

• Dust-generating activities should be minimized during conditions of high wind.

4.2.7.4 Monitoring In addition to the Air Quality Management Plan, construction activities should be monitored by a qualified Environmental Inspector who will frequently review the efficacy of the mitigation measures and construction best management practices to confirm they are functioning as intended. In the event that mitigation is found to not be effective, revised mitigation measures designed to improve effectiveness will be implemented. Dust levels should be monitored daily by the Contractor and frequently by the Environmental Inspector

Page 27: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-26

to assess the effectiveness of dust suppression measures, and adjust as required. Monitoring should continue throughout the construction phase until activities are complete, all exposed soils have been stabilized, and all construction waste has been removed from site.

A complaint response protocol will be established for nuisance effects, such as dust, for local residents to provide feedback. Regular inspections of dust emissions will be carried out by the Contractor (frequency to be defined prior to project construction) to confirm dust control watering frequency and rates are adequate for control. Competent Site Supervisors should monitor the site for wind direction and weather conditions to ensure that high-risk dust generating activities are reduced when the wind is blowing consistently towards nearby sensitive receptors. The Site Supervisor should also monitor for visible fugitive dust and take action to determine and correct the cause.

4.2.7.5 Fuel Source for Buses The potential fuel sources BRT buses, considered in terms of relative change to air quality, are diesel, CNG, or electric. The Air Quality Impact Assessment was conducted for the worst-case fuel source which is diesel. Electric buses would not emit any COCs within the study areas, with the exception of particulate matter from brakewear, tirewear, and re-suspension. The remainder of the COCs generated by electric buses do not occur locally, but rather nationally/regionally depending on the source of power to generate the required electricity. Impacts associated with electric buses would need further information to assess, such as the type of electric bus, energy demand, and source of electricity generation. Regardless of vehicle type, this project is projected to have a positive impact on air quality and lead to a reduction in greenhouse gas emissions. However, the use of Electric vehicles would result in the greatest net benefit to air quality.

4.2.7.6 Greenhouse Gases and Climate Change Greenhouse gases (GHGs) are contributors to the radiative warming effect of the environment that results in global climate change. The major GHGs include carbon dioxide (CO2), methane (CH4), and nitrous oxide (N2O), which are emitted from fuel combustion as well as other anthropogenic and natural sources. Carbon dioxide is the main product of combustion, while the other two gases are by-products of incomplete combustion. Methane and nitrous oxide have lower concentrations in the atmosphere than carbon dioxide, but their potential impact on global warming per molecule is larger than for carbon dioxide.

Start-up emissions have little impact to greenhouse gas emissions, as the buses will be running continuously for long periods, without stopping or starting their engines within the study areas.

Idling emissions are important to the study area as buses will idle at stop lights and at bus stops. The purpose of the BRT system is to minimize idling at stop lights by timing the signals to maintain BRT traffic movement whenever possible. When idling, CNG buses have the greatest reduction to GHG emissions compared to current fleet vehicles.

For electric buses, there is no local impact within the study areas from greenhouse gases as the creation of power (i.e., electrical generation plants) is located outside of the study

area; however, there will be an impact nationally/regionally from these plants, which is not assessed due to a lack of knowledge of the total power demand requirement of the BRT fleet should it be all electric.

For travelling emissions, both future diesel engines and CNG engines yield a reduction of GHG generation. Future diesel buses offer the greatest decrease, but both options produce a net decrease that would assist in meeting Ontario’s 2007 Action Plan on Climate Change. Once the fuel source of the fleet is known, the GHG study will be updated and provided to the MECP for review.

4.2.8 Noise and Vibration

4.2.8.1 Potential Impacts To assess how future roadway noise levels will be impacted by BRT implementation, future sound levels following full build-out of the BRT were estimated and compared to existing conditions, using the methodology described in Appendix I. The sound levels for Outdoor Living Areas given road conditions and traffic volumes identified for these two scenarios are summarized in Exhibit 4-12. The Noise and Vibration Assessment is provided in Appendix I. The conservative scenario of a full diesel BRT fleet was assumed.

Exhibit 4-12: Future Roadway Noise Levels

Receptor ID Existing Noise

Levels (dBA)

Future Noise Levels with BRT (dBA)

Change in Noise Levels (dBA)

North Corridor N1 62 69 7 N2 57 64 7 N3 58 64 6 N4 61 63 2 N5 54 54 0 N6 54 54 0 N7 59 64 5 N8 52 53 1 N9 63 62 -1

N10 53 53 0 N11 63 63 0

East Corridor E1 58 58 0 E2 69 70 1 E3 69 70 1 E4 65 66 1

West Corridor W1 53 56 3 W2 65 66 1

Page 28: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-27

Receptor ID Existing Noise

Levels (dBA)

Future Noise Levels with BRT (dBA)

Change in Noise Levels (dBA)

W3 50 57 7 W4 62 62 0 W5 57 57 0 W6 56 56 0 W7 62 62 0

South Corridor S1 58 67 9 S2 55 59 4 S3 54 58 4 S4 60 59 -1 S5 57 56 -1 S6 48 53 5 S7 54 62 8 S8 64 66 2 S9 50 57 7 S10 51 56 5 S11 56 59 3 S12 60 60 0 S13 56 61 5 S14 59 60 1 S15 66 67 1 S16 60 61 1 S17 61 61 0 S18 61 61 0 S19 62 62 0 S20 67 67 0

A stationary noise assessment was undertaken at the south turnaround to investigate the impact of idling buses on the nearby houses located on Holiday Avenue. The south turnaround was considered the most critical of the four turnarounds as the proximity to noise sensitive receptors was the least and this location is expected to have the most buses. The sound levels at the two nearest dwellings were assessed at two receptor locations each. For each property, one receptor was located 1.5 metres high near the property line, and the other receptor was located 1.5 metres high on the building façade to be representative of the nearest window. The outdoor receptor was used to evaluate daytime noise levels as they were nearer to the source and therefore louder and the plane of window receptor was used for nighttime levels. A summary is provided in Exhibit 4-13.

Exhibit 4-13: Receptors for Bus Idling Noise

Noise Receptor Address Type of Residential Unit

Outdoor 1 25 Holiday Avenue Detached House

Façade 1 25 Holiday Avenue Detached House

Outdoor 2 29 Holiday Avenue Detached House

Façade 2 29 Holiday Avenue Detached House

In addition to existing residential units, impacts to future development was also considered. A list of site plan applications on the BRT corridor was obtained from the City of London. There are five site plans, and of the five, two were determined to be at risk of excessive noise exposure. These sites were added to the list of receptors and evaluated.

4.2.8.2 Mitigation Most receptors experience a small increase in sound levels, however noise impacts are limited and mitigation is not required along the majority of the 24 km BRT corridor. Although noise barrier walls are not required along the majority of the BRT corridor, noise barrier walls will be installed in some areas to ensure that existing residential backyards backing onto arterial roads, which are widened to four vehicles lanes or greater, are not subjected to significant noise level increases, as per City of London policy.

Noise increases greater than 5 decibels are predicted only to occur at select locations due to the removal of existing buildings to accommodate the design. In total, seven locations were identified as having potential noise increases in excess of 5 decibels. Recommended barrier heights and lengths are summarized in Exhibit 4-14.

Exhibit 4-14: Recommended Noise Mitigation

Receptor ID Approximate Location

Recommended Noise Barrier Height

Recommended Barrier Length

North Corridor N1 106 Bees Court 1.8 metres 211 metres N2 38 St Bees Place 1.8 metres 211 metres N3 1 Ambleside Drive 1.8 metres 29 metres

West Corridor W3 226 Cooper Street 1.8 metres 91 metres

South Corridor S1 2 Kennon Place 2.4 metres 41 metres S7 13 Bond Street 2.3 metres 65 metres S9 484 Moore Street 1.8 metres 48 metres

Page 29: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-28

Schematic locations of the sound barriers, as well as the lengths and heights of the barriers, are provided in Appendix I, and are also indicated on the design plates in Appendix A.

4.2.8.3 Net Effects Attenuated future sound levels following BRT implemented and with recommended noise barriers constructed are summarized in Exhibit 4-15.

Note that to ensure such noise attenuation is achieved, barriers must be continuous and without gaps. All fence material must have a minimum surface density of 20 kg/m2.

Exhibit 4-15: Future Attenuated Noise Levels

Receptor ID Future Noise Levels (dBA)

Attenuated Noise Levels with Barrier (dBA)

Mitigation Provided (dBA)

North Corridor N1 69 64 -5 N2 64 59 -5 N3 64 60 -4

West Corridor W3 57 52 -5

South Corridor S1 67 58 -9 S7 62 55 -7 S9 57 52 -5

4.2.8.4 Construction Considerations The following should be specified during the preparation of detail design drawings and adhered to during construction:

• The Contractor will be required to comply with the City of London’s noise by-law (Noise By-Law, PW-12) regarding noise emission standards for construction equipment that may be in place at the time of construction.

• General noise control measures (not sound level criteria) will be referred to, or placed into the City of London contract documents.

• Any initial complaint from the public will require verification by the City of London to determine if the general noise control measures agreed to, are in effect. The City of London will investigate any noise concerns, warn the Contractor of any problems and enforce its contract.

• Nighttime construction activities should be avoided to reduce the potential impact of construction noise. Construction should be planned to minimize the number of nights where noisy nighttime construction activities may be required.

• All construction equipment used should be in good repair and properly maintained to limit noise emissions. All construction equipment should be operated with effective muffling devices that are in good working order and idling of construction equipment kept to a minimum to reduce noise from construction activities. Unnecessary noise caused by faulty or non-operating components shall be addressed by regularly maintaining all equipment.

• Noise emissions from construction equipment are to be in compliance with the limits set out in NPC-115 and NPC-118.

• The concurrent use of high impact construction equipment such as pile driving should be avoided. The feasibility of augur pile driving should be investigated if pile driving is required.

• Construction activities should be kept as far as possible from nearby structures and the duration of construction activities near structures should be kept to a minimum.

• Construction activities should comply with the requirements of MOE Publication NPC-207.

• Consideration should be given to minimizing construction-related vibration levels, while balancing construction schedules and expediting construction activity.

• During detail design, the Zone of Influence should be confirmed to determine which structures will fall within it. If a structure falls within the Zone of Influence, the following is recommended: o Pre-construction consultations between the applicant and owners/occupants; o Pre-construction measurements of background vibration levels; and o Pre-construction survey by means of a photographic record of potentially affected

structure façades and all surfaces, including visible sections of building foundations, building cladding, doors, windows, interior wall finishes, surface pavement, sidewalks, signs and trees. Each of the elements should be rated on their general condition (new, good, fair, poor, severe), and visible defects should be photographed.

4.3 Socio-Economic Environment

4.3.1 Land Use and Demographics Once the Bus Rapid Transit system is implemented, the Rapid Transit Corridors are envisioned to become vibrant, mixed-use, mid-rise communities that border the length of Rapid Transit route. The land uses along the corridors will vary depending on the character, uses and intensity of the surrounding areas. Some will be primarily residential with small-scale, street-facing commercial uses, while others may feature stand-alone commercial uses or mixed-use development. The corridors will have easy access to Downtown and Transit Villages via Rapid Transit, and will be fundamentally walkable and transit-oriented.

Page 30: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-29

Areas closer to Rapid Transit stops may be more appropriate for greater density and height to support transit usage for a larger number of residents and workers.

Looking at projected demographic changes over the next 20 years, a major shift in age group structure is expected. Exhibit 4-16 shows the current and projected population age structure for Middlesex County. Some key observations include:

• The proportion of seniors (65 years and older) changes from 15% of total population in 2011 to 23% in 2030. This represents an additional 43,100 potential transit users in London.

• The 14-29 young adult age group makes up 22% of the current population. This group will age into the 35 to 49 cohort over the next 20 years and make up a large part of the commuting population.

• The current 14-29 age cohort has well-documented lower auto ownership rates across North America and higher public transit use than previous generations. If these generational lifestyle preferences are continued in the future, this has the possibility to increase demand for future Rapid Transit services.

The young adult age group is the largest, and typically more flexible with respect to transportation mode choice. Providing Rapid Transit service to this group soon could make them into choice riders, with this behaviour continuing throughout their lives. The shift towards an older population will also have major implications regarding the need to provide high quality multi-modal mobility options to many parts of the city. As people age, they begin to choose to stop driving, or may lose their ability, and convenient transit must be made available to maintain a high quality of life. Having higher quality transit will allow London to continue to attract many types of residents including students, young professionals, and seniors.

The impact on London’s rental housing units will be among the issues considered during the next phase of the project. Consultation with stakeholders interested in maintaining affordable housing stock will assist in identifying impacts and appropriate mitigation measures, such as opportunities to integrate affordable housing with future transit-oriented development.

2 Ontario Population Projections Update, 2012-2036, Ontario Ministry of Finance

Exhibit 4-16 Middlesex County Population Age Structure, 2011 and 20302

4.3.2 Local Economy

4.3.2.1 Potential Impacts

Short Term Economic Benefits

The economic benefits associated with the construction of BRT network can be quantified in terms of the estimated number of direct and indirect person-years of employment, wages and additional GDP. It should be noted that GDP, by definition, includes wages and salaries as a sub-component and therefore the estimates of GDP and income cannot be added together. During construction, the project is expected to generate 4,389 employment years and increase GDP by $262 million.

The magnitude of short-term impacts is directly based on the capital cost of the project. Larger construction costs means greater person-years of employment, wages and increase in GDP.

Long Term Economic Benefits

The economic benefits associated with the ongoing operations of Rapid Transit can also be quantified in terms of the estimated number of direct and indirect person-years of

Page 31: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-30

employment, income (i.e. wages/salaries) and additional GDP. These long-term economic benefits are directly tied to the annual operating costs and can be impacted by changes in ridership, operational subsidy, and service standards. The estimated operating costs, and consequently the long-term economic impacts, reflect a minimum level of service to accommodate projected ridership demand.

Salary information from the London Transit Commission and Statistics Canada was used to generate estimates of direct person-years of employment and wages over the operating period of 2025 to 2050. The Rapid Transit service could generate 148 direct person-years of employment annually and $8.1 million in direct wage income annually.

During the life cycle of the project (up until 2050), the project is expected to generate 225 employment years and contribute an additional $9 million in GDP per year3.

Land Value

Investment in transit often results in changes in land value. Case study research has shown, for the most part, these changes are positive (i.e. increased property values) as lands become more desirable in their existing form and/or redevelop into higher density, higher order uses. Over the past few decades, construction of transit systems in Canada, the United States and Australia has been seen to result in property value increases ranging from 2% to over 60%. The larger increases in property values are generally tied to heavy rail and subway systems, but the introduction of high quality BRT can also result in increased interest and demand for land and uplift in land value.

A number of other factors play an important role in the impact transit investment can have on property values, intensification and economic development. For example:

• Uplift in land value is closely tied with the levels of population and employment growth and market demand for various types of housing (e.g. lower density suburban vs higher density urban).

• Higher levels of ridership and passenger usage of stops results in greater impact on the value of retail, commercial and institutional lands and lease rates.

• Studies have found that transit investment tends to have a larger impact on land values in lower and middle-income areas, or neighbourhoods with high proportions of students, seniors and young adults.

• Research suggests that the greatest uplift in land value has been realized in areas where transit service is being introduced (opposed to an upgrade to existing service) or in situations where a Rapid Transit line is serving either a very dense urban area or a large geographic area and has particularly high daily ridership levels.

• Based on The London Plan, London is projected to reach a population of 458,000 by 2035. The ReThink London Land Needs Background Study forecasts that 42,375 new residential units will be required to accommodate this population growth, with 39% (16,738) of the new units to be constructed within the ‘Built Area’ of municipality:

3 London Rapid Transit Business Case, 2017

• 88% high-density (11,581 units); • 21% medium-density (3,596 units); and, • 9% low-density (1,561 units). Based on population forecasts prepared by the City of London, it is estimated that over the period of 2011 to 2034 (horizon for which detailed forecasts by traffic zone are available), of the growth that will be constructed in the existing “Built Area”, between 60% and 70% of this growth could occur within 800 m of the proposed Rapid Transit corridors. This would translate into the need for thousands of new residential units. The City of London has a large supply of vacant or underutilized lands within 500 m of the proposed Rapid Transit corridors, which could accommodate transit-oriented development.

Following a review of The London Plan and the land designations (Place Types) and density permissions along the proposed Rapid Transit corridors, estimates of the amount of land which will be required to accommodate the anticipated population growth (i.e. new buildings and units) were prepared. Residential developments which have been recently built or are planned and underway were taken into consideration.

The City of London’s economy is currently heavily dominated by information technology, medical research, manufacturing and insurance. Higher education facilities such as Western University and Fanshawe College play a major role in London’s economy, adding close to 1.5 billion dollars annually.

In past years, the City has struggled with high vacancy rates specifically in the downtown core area. The Canadian Market Outlook (2015) conducted by CBRE suggests that the vacancy rates seen in recent years in London will continue, with marginal gains, but acknowledged that the City’s attempt to revitalize the downtown core by waiving development charges for certain types of developments is a positive way to stimulate growth.

The introduction of Rapid Transit should also help stimulate economic development and growth, as it will help connect people to jobs and establish clusters of industry in proximity to Rapid Transit stops. Businesses and major institutions within close proximity to the Rapid Transit corridors can be expected to benefit from improved access to skilled workers and customers, and increased productivity and competitiveness resulting from a reduction in travel times and transportation costs. The City anticipates its employment base will grow by 43,000 jobs between 2015 and 2035 and that millions of square feet of new commercial, institutional and industrial space will be required. It is estimated that when complete, the majority of London’s jobs will be within walking distance of Rapid Transit.

Overall, it is estimated that an uplift in land value of $90 million could be realized along the proposed BRT corridors if London grows as anticipated or achieves even greater levels of population and employment growth4. Some vacant or largely underutilized properties will

4 London Rapid Transit Business Case, 2017

Page 32: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-31

see a major uplift in value and others will see little to none. The average uplift in land value along the corridors is anticipated to range from 2% to 10%5.

4.3.3 Businesses

4.3.3.1 Potential Impacts

Businesses during Construction

Businesses typically experience impacts with urban road construction in the form of the removal/lack of street parking, road closures, signage and visibility issues, noise and vibration, garbage pickup, snow removal and/or sidewalk closures.

The level of impact will depend on the level of disruption, as well as the nature of businesses that are affected by construction. The level of disruption would depend on factors such as duration of construction and the extent/level of road closure, etc.

Certain types of businesses in certain areas of the City will be more affected by construction than others. For example, the impact of construction on office uses along Oxford Street West is likely less severe than that on retail uses downtown, since office uses are generally less dependent on customer visits. Similarly, retail/service uses that cater to specific purposes, e.g., a special item of clothing, are likely less affected by construction than retail/service uses that meet daily local needs.

The businesses in London have been categorized using the NAICS industry classification system. These categories were then assessed according to their tolerance toward business interruptions, typical of urban transportation projects. A “low tolerance” level indicates that a businesses in this category are generally more sensitive to the impacts of construction compared to those of “high tolerance”. The tolerance level for each business category is identified below.

While most areas along the BRT corridors will have very few impacts due to having large setbacks from the roadway and off-street parking, there are some areas along the BRT corridor that have a high concentration of businesses that have lower tolerance levels, have street front facades, and rely on street parking for loading and customer parking. These areas are Downtown, including Richmond Row and Wellington Street between South Street and Horton Street. A more detailed analysis of these areas is provided below.

Downtown and Richmond Row Based on an inventory conducted in 2017, there were 239 downtown businesses that fronted onto the BRT corridors in Downtown London. This included sections of the RT

5 London Rapid Transit Business Case, 2017

bound by Ridout Street to the west, Oxford Street to the North, Wellington Street to the East and King Street to the South. Retail stores and restaurant establishments make up the majority with 130 businesses. The proportional distribution of businesses based on construction tolerance level is summarized in Exhibit 4-17, with businesses of a “medium” tolerance level making up the largest share at 35%.

Exhibit 4-17: Proportional Distribution of Businesses Based on Construction Tolerance Level – Downtown and Richmond Row

These businesses will be impacted during construction due to limitations on access from the temporary removal of on-street parking and temporary road closures, as well as disruption from construction activity such as dust, noise and vibrations.

Wellington Street between South Street and Horton Street Based on the business inventory conducted on Wellington Street between South Street and Horton Street, there are approximately 53 businesses fronting the BRT corridor. A majority (34) of these businesses are offices and are considered to have a high tolerance for construction disruption, with another two considered to have moderate tolerance for construction disruption. 17 of the businesses are either retail food stores or services (entertainment/food/drink) establishments and considered to have low or medium-low tolerance for construction disruption. The proportional distribution of businesses based on construction tolerance level is summarized in Exhibit 4-18.

Page 33: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-32

Exhibit 4-18: Proportional Distribution of Businesses Based on Construction Tolerance Level - Wellington Street (Between South and Horton)

On-Street Parking, Loading and Access

The implementation of Rapid Transit will have both positive and negative impacts on businesses in the longer term, once this system is in place and operational. Rapid Transit will improve access to businesses for existing and new transit users and it will facilitate residential intensification in the corridors, which could increase the local customer base, encourage walkability, and incentivize localized shopping patterns. However, changes to the road corridors will reduce the amount of on-street parking and on-street loading in some areas along the corridor where it currently exists and will impact off-street parking in some locations as well.

On-Street Parking Along the 4 BRT Corridors (North, East, South, West) and Downtown there are currently a total of 295 on-street parking spaces. The majority of these spaces are located Downtown, where there are 204, 24-hour parking spaces along the BRT corridors.

As it is a goal to implement the BRT system with few impacts, on-street parking spaces in several locations were compromised in order to limit the widening of the existing road right-of-way to preserve adjacent property and maintain the existing building fabric. This is especially the case Downtown, where road rights-of-way are tight to the building faces and it is a priority to maintain the existing built form.

The removal of all bus service from Dundas Street between Wellington Street and Ridout Street involves the realignment of 10 routes (2, 5, 7, 9, 11, 12, 19, 20, 23, &102), which currently use Dundas Street in the Downtown area.

The net parking loss in Downtown as a result of the rerouting of buses off Dundas Street in Spring 2018 was 29 parking spaces. Business owners fronting the specific areas were notified of the changes. A total of eight additional on-street parking spaces will be added along Clarence Street and Talbot Street due to the removal of transit from those streets. Some of these spaces may transitionally serve as business loading zones coordinated with the closure of Dundas Street during construction of the Dundas Place project.

Less than half of the all-day on-street parking spaces have been removed as part of the design of the BRT network. Along the BRT corridors Downtown, a total of 84 all-day on-street parking spaces will be removed, bringing the total from 204 to 120.

The total number of all-day on-street parking spaces that exist today and that will existing after the BRT system is implemented are summarized by city block in Exhibit 4-19.

Loading Downtown has specified on-street loading zones for businesses that don’t have off-street loading facilities. On-street parking is also often used for loading and parcel delivery of adjacent businesses. The removal of on-street parking and some loading areas will therefore have an impact on loading in areas where on-street parking is compromised.

4.3.3.2 Mitigation

Businesses During Construction

The highest level of communication will be required prior to, and during, BRT construction to mitigate the potential impacts of a project of this scale. Encouraging people to continue coming to these areas during construction will be a crucial component of limiting the impacts that construction will have. It will also be important to provide timely, accurate and proactive information to stakeholders, as well as real-time, on-site resources and robust communications protocols.

The first stage of construction for the BRT network is expected to take place in the Downtown couplet. This work is being timed to align with other infrastructure and signature projects happening in the core.

With multiple projects being timed for completion either in close sequence or simultaneously across the BRT network, it is necessary for the Rapid Transit Implementation Office to work closely with other project teams to coordinate on communications across projects, share best practices, and ensure a consistent and holistic approach to activities and messages, building upon proven strategies and tools used for other signature projects.

Page 34: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-33

Exhibit 4-19: Changes to All-day On-Street Parking

Block Existing On-Street Parking (2018)

On-Street Parking with BRT

Block Existing On-Street Parking (2018)

On-Street Parking with BRT

South Corridor Downtown Wellington Street

Clarence Street

Horton to Simcoe

5 0 King to Dundas 14 15

Simcoe to Grey 11 11 Dundas to Queens 21 13 Grey to Hill 5 5 Queens to Dufferin 18 0 Hill to South 7 3 King Street South Corridor Total

28 19 Ridout to Talbot 14 4

North Corridor Talbot to Richmond 8 3 Richmond Street

Richmond to Clarence 20 11

Central to Hyman

5 5 Clarence to Wellington 8 0

Hyman to Piccadilly

20 9 Wellington to Waterloo 25 10

North Corridor Total

25 14 Wellington Street

East Corridor King to Dundas 6 9 King Street Dundas to Queens 3 8 Waterloo to Colborne

19 0 Queens Ave.

Colborne to Burwell

7 0 Wellington to Clarence 15 16

Dundas Street Clarence to Richmond 8 15 Ontario to Quebec

12 0 Richmond to Talbot 12 0

East Corridor Total

38 0 Talbot to Ridout 10 10

Ridout Street Queens to Dundas 16 6 Dundas to King 6 0 Downtown Total 204 120

Page 35: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-34

A successful mitigation strategy should include the following elements:

1. Signage for local businesses during construction;

2. Communication strategy to routinely update shoppers, employees and visitors/clients, with real-time information, for example, through website updates, area signage and social media;

3. Parking strategies (e.g., increase availability of on-street parking proximate to study area, reduced rates for downtown parking; wayfinding signage identifying alternative parking options);

4. Promotion of Study area businesses in collaboration with BIAs;

5. Pedestrian safety and wayfinding measures (e.g., clear paths to businesses); and,

6. Promoting active transportation options (e.g., bike share program).

On-Street Parking, Loading and Access

On-Street Parking As of 2015, there were 13,000 parking spaces available in Downtown. The removal of 84 all-day on-street spaces will not have a significant impact on the total available parking stock. With a high vacancy rate (verified by the 2018 Downtown Parking Study) in municipal parking garages, these garages will be able to take on the burden of the removed on-street supply.

In order to promote the use of the off-street parking supply, the City can implement pricing programs and provide adequate signage to increase awareness of the availability of parking at off-street locations. Using technology to monitor parking supply and demand that is relayed to people looking for parking can also help distribute demand to off-street parking garages with adequate supply.

The demand for on-street parking Downtown will also be mitigated with the promotion of active transportation and transit for getting Downtown.

Outside of Downtown, the on-street parking supply is not relied on as heavily as there are more free off-street parking opportunities.

A more detailed strategy and analysis of Downtown parking supply and demand will be provided in the 2018 Downtown Parking Plan.

Loading The loss of on-street loading space for businesses Downtown and on Wellington Street between Horton and South can be mitigated by designating new on-street loading spaces on nearby side streets or other nearby loading areas. This can also be complimented by improving maintenance on public alleyways and having access to abutting commercial parcels.

A mitigation strategy for relocating loading activity along each block that is affected is provided in the Exhibit 4-20 below.

Exhibit 4-20: Downtown Parking and Loading Strategy

Page 36: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-35

4.3.3.3 Net Effects In total, 106 parking spots will be removed due to the implementation of the BRT system. Parking spots on side streets adjacent to the BRT corridors will not be impacted.

4.3.3.4 Monitoring The City will continue to work with impacted property owners, residents and businesses to mitigate the effects associated with the removal of parking, loading and access.

4.3.4 Recreation, Entertainment and Tourism Recreation and Entertainment

In 2009, the City published a Parks and Recreation Master Plan, guiding the sustainable growth of City’s recreation facilities. The first of the guiding principles that are identified is Accessibility and Affordability, indicating that the City should “seek to provide fair, accessible and affordable recreation and leisure opportunities that encourage participation by a diverse community”. The recommendations for achieving this include locating recreation facilities so that the largest number of persons can reach the facility by foot, by bicycle, and by public transit.

The development of the Bus Rapid Transit system will also help improve upon the existing network of sidewalks, trails, and off-street bike paths. As part of the project, cycling facilities will be constructed along Wellington Road from Bradley Avenue to Base Line Road East, Western Road from Lambton Drive to Richmond Street, Richmond Street to Fanshawe Park Road, King Street from Waterloo to Ontario Street, Dundas Street from Ontario Street to Egerton, and on Oxford Street East from Highbury Avenue to First Street. In addition to multi-use paths, bike lanes will be added along the Rapid Transit where space allows, and facilities will be developed along parallel streets in constrained areas.

As indicated in Exhibit 3-23, several of the City’s significant recreation and entertainment attractions are located along the BRT corridors Londoners will have improved access to these facilities with the implementation of BRT, which will help achieve the guiding principles set out in the Parks and Recreation Master Plan and provide Londoners with improved access to leisure opportunities, helping to solidify London as an attractive place to live, work and play.

Tourism

When visiting a city, the ability to navigate and get to your desired destination conveniently can be a defining element of the visitor experience. Rapid Transit serves as a definitive spine in the public transit network with routes that provide fast and reliable service to major destinations and that are intuitive and easy to navigate. Rapid Transit stops can also provide information on places of interest around the local area that they serve, and they can serve as points of reference for navigating.

The BRT corridor will also provide connections to inter-city bus and rail connections, as well as the proposed future high-speed rail station, and has the potential to service connections

to the London International Airport, providing high quality transit connections from these points of entry to the rest of the City.

As indicated in Exhibit 3-24, there are several tourist destinations along the BRT corridors as well as many of the City’s hotels. These destinations and the visitors that are trying to get to and from them will be better served by the BRT system.

4.4 Cultural Environment Further details on cultural heritage and archaeological findings, impacts and mitigations can be found in the Cultural Heritage Screening Report (Appendix K) and the Stage 1-2 Archaeological Assessment Report (Appendix J), respectively.

4.4.1 Archaeology

4.4.1.1 Potential Impacts The BRT network was designed to stay within the existing road allowance wherever possible to minimize or avoid impacts to potential archaeological resources.

Within the Study Area, there is the potential for impacts to four registered archaeological sites, three of which require further archaeological assessment (Exhibit 4-21), 10 historic cemeteries (Exhibit 4-22), and seven additional areas that that have the potential for deeply buried resources.

Exhibit 4-21: Registered Archaeological Sites Requiring Further Assessment

Borden Number

Name Cultural Affiliation

Location Description

AFHH-244 Victoria Park Pre-contact; Post-contact

Clarence Street

1864 barrack structure with resources; pre-contact resources within the park away from the project

AFHH-182 O’Brien Block Post-contact West of Ridout Street

Line of structures; human remains also found in the area.

AGHH-72 Unnamed Post-contact Western University campus

Site identified during construction, potentially former tavern or hotel.

Page 37: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-36

Exhibit 4-22: Potentially Impacted Historical Cemeteries

Cemetery Location Year Established Restmount Oxford Street West and Proudfoot Lane 1933 Or Shalom Oxford Street West and Proudfoot Lane 1888 Oakland Oxford Street West 1882 Mount Pleasant Cemetery Oxford Street West 1874 Anglican Cemetery Dundas Street and Ridout Street 19th Century St. Peter’s Basilica Richmond Street and Dufferin Street 1830s St. Paul’s Anglican Cathedral Cemetery

Queens Avenue and Clarence Street 1934

St. Paul’s Anglican Cemetery

Bound by Rectory Street, Florence Street, Dundas Street and Ontario Street

1852

Potter’s Field Richmond and Kent Street Prior to 1889 Middlesex County Courthouse

399 Ridout Street North 19th Century

4.4.1.2 Mitigation A Stage 3 Test Excavation and Deeply Buried Resource survey is to be completed within the boundaries of AfHh-244, Victoria Park. The test excavation is to entail the excavation of test units within the areas of impact, within the lawn areas of the site, at 5 m intervals to provide a sample of the site area. Addition infill units amounting to 20% of the total grid are to be completed within the site area, targeting notable areas as identified by a Licensed Archaeologist. Where the project is located within the site area, but the area is presently covered by asphalt or other modern structures, the investigation is to proceed directly to deeply buried investigations. Deeply buried investigations are to entail the excavation of the upper layers of fill down to the level of undisturbed soil horizons at 5 to 10 m intervals. Should intact archaeological deposits be found, hand excavation may be employed at the discretion of the site archaeologist. All trenched areas within the Stage 3 investigation with intact archaeological deposits should be fully excavated to Stage 4 standards prior to backfilling the trenches. Stage 4 mitigations through avoidance or excavation are to follow the results of the Stage 3 investigations.

Stage 2 Test pit survey is recommended in association with AGHh-72 to entail the completion of three 1 m by 1 m test units at 5 m intervals along the edge of the parking lot or roadway in close association to the site coordinates, to determine whether further remains associated with the archaeological site are present within the project footprint at this location. This strategy is employed because of the limited information available for the site.

Consultation with the Ministry of Tourism, Culture and Sport (MTCS), and Museum of Ontario Archaeology will be undertaken to determine the extent of the original investigations into AfHh-182. Subsequent to the consultation, Stage 2 and/or 3 investigations will be completed for the project footprint within the registered site area.

Discovery of Human Remains

In the event that human remains are encountered at any point, the following response protocol will be implemented:

• All site alteration activities must cease immediately and the Quality Assurance / Environmental Administrator and Construction Manager will be contacted;

• The Construction Manager will contact the Owner and the Environmental Manager; • Notification of the remains will be undertaken in accordance with the Funeral, Burial and

Cremation Services Act, 2002, S.O. 2002, C.33, which requires that any person who discovers human remains notify the police or coroner, and the Registrar of Cemeteries at the Ministry of Government and Consumer Services;

• The site will be secured until such time that the Police or Coroner’s Office assume control of the site;

• Should it be determined that the remains are Indigenous, the Indigenous community with cultural affiliation to the remains will be notified; and,

• Site alternation activities will not be reinstated at the site until clearance from the above noted authorities has been provided.

4.4.1.3 Net Effects The Stage 1 Archaeological Assessment identified a number of historic and active cemeteries in close association with the project works. These cemeteries will be addressed within the archaeological assessments for the project. Each active cemetery will have consultation with the current owner/operator to garner further information on the potential for burials within the project area. All areas of impact from the project within 10 m of the identified cemeteries will have a Stage 3 Cemetery Investigation completed to determine the presence of grave shafts. Should grave shafts be identified, Stage 4 Mitigation options will be discussed with the affected parties including the City of London, the Registrar of Cemeteries, MTCS, and the cemetery owners.

Areas with potential for the discovery of deeply buried resources are to undergo Stage 2 Deeply Buried investigations, with mechanical excavation of test trenches at intervals no greater than 10 m, targeting potential features visible on the historic mapping of the area. If the area of potential identified is located within lawn or other undeveloped areas, a test pit survey is to be completed prior to the test trenching to confirm the depth of fill and disturbance over the area.

Page 38: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-37

4.4.1.4 Monitoring

Chance Discovery of Undocumented Archaeological Resources

Should previously undocumented archaeological resources be discovered during the course of site investigations or construction, they may be deemed to be a new archaeological site and therefore subject to Section 48 (1) of the Ontario Heritage Act. The following protocol will be implemented:

• All site alteration activities will cease immediately and the Quality Assurance / Environmental Administrator and Construction Manager will be contacted;

• The Construction Manager will contact the Owner and the Environmental Manager; • Instruction will be provided not to move or collect the uncovered archaeological or

historical materials; • The locations of actual or suspected archaeological finds will be secured against theft or

trespass by unauthorized individuals; • A Licensed Archaeologist will be engaged to carry out archaeological fieldwork, in

compliance with sec. 48 (1) of the Ontario Heritage Act; • A Licensed Archaeologist will be contacted/brought on site immediately upon discovery

of a new archaeological resource, to provide recommendations for impact avoidance or further investigation;

• Results of any Archaeological Assessments will be submitted/reviewed by MTCS to confirm recommendations; and,

• Additional Archaeological Assessments (Stage 2, 3 and/or Stage 4), will be undertaken as required.

4.4.2 Built and Cultural Heritage

4.4.2.1 Potential Impacts While design refinements were made to avoid impacting cultural heritage features, the Cultural Heritage Screening Report (CHSR) identified that there is the potential for the project to result in direct or indirect impacts to properties with confirmed and potential cultural heritage status. Potential impacts are identified and defined by the MTCS’ Ontario Heritage Toolkit. These impacts include direct and indirect impacts such as destruction, alteration, shadows, isolation, direct or indirect obstruction, and a change in land use. As the project is planned along pre-existing roadways within the City of London, shadows, isolation, direct or indirect obstruction, or change in land use impacts are not anticipated.

Impacts may be minimized during the detail design process. More details are available in the CHSR, which is included in Appendix K. The CHSR found that the following impacts are anticipated:

• 204 properties were screened out as having no potential cultural heritage value and do not require further cultural heritage study.

• 449 properties were identified as having potential cultural heritage value or interest (CHVI), but have no anticipated direct or indirect impacts. These properties do not require further cultural heritage study under the scope of this project.

• 96 properties with potential CHVI were identified with impacts limited to minor landscape alterations. These impacts will be mitigated by alterations to project design during detailed design, construction planning, and project controls (e.g. vibration reduction, dust suppression, or other measures). Where possible, sidewalk widths should be planned to provide a buffer between heritage buildings and construction. These properties do not require further study under the scope of this project.

• 51 properties and structures were identified as having potential cultural heritage value or interest, and may be directly impacted by demolition, removal or relocation. Cultural Heritage Evaluation Reports (CHERs) were completed for these properties prior to the completion of TPAP. The results of the CHERs are included in Exhibit 4-23.

• 12 properties were identified as having potential cultural heritage value or interest and may be directly or indirectly impacted. There is an opportunity to mitigate the direct impacts to these properties. CHERs are recommended for these properties following the completion of TPAP (Exhibit 4-24).

• 10 properties were identified as having known cultural heritage value or interest, and may be directly or indirectly impacted. Heritage Impact Assessments (HIAs) are recommended for these properties, including Victoria Park and one Ontario Heritage Trust easement property, following the completion of TPAP (Exhibit 4-25).

• 32 properties were identified as being located within an HCD and may be directly or indirectly impacted. HIAs are recommended for these properties, following the completion of TPAP (Exhibit 4-26). Specific information related to HCD-level impacts is included in Exhibit 4-27.

As mentioned above, CHERs were completed during TPAP for 51 properties and structures determined to be directly impacted by the project. The CHERs were submitted to LACH for review and approval at their regularly scheduled meetings on December 14, 2018 and February 13, 2019. The CHERs are included in Appendix K1.

Exhibit 4-23: Results of the CHERs Completed During TPAP

PROPERTY CHVI PROPERTY CHVI

1 Kennon Place No cultural heritage value 251 Wellington Road

No cultural heritage value

16 Wellington Road CHVI 253-255 Wellington

Road No cultural heritage value

26 Wellington Road CHVI

261 Wellington Road No cultural heritage value

Page 39: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-38

PROPERTY CHVI PROPERTY CHVI

28 Wellington Road CHVI

263 Wellington Road No cultural heritage value

30 Wellington Road CHVI

265 Wellington Road No cultural heritage value

32 Wellington Road No cultural heritage value 267 Wellington Road

No cultural heritage value

34 Wellington Road No cultural heritage value 269 Wellington Road

No cultural heritage value

74 Wellington Road No cultural heritage value 271 Wellington Road

No cultural heritage value

78 Wellington Road No cultural heritage value 273 Wellington Road

No cultural heritage value

88 Wellington Road No cultural heritage value 275 Wellington Road

No cultural heritage value

98 Wellington Road No cultural heritage value 285 Wellington Road

No cultural heritage value

118 Wellington Road No cultural heritage value 287 Wellington Road

No cultural heritage value

122 Wellington Road No cultural heritage value 289 Wellington Road

No cultural heritage value

126 Wellington Road No cultural heritage value 297 Wellington Road

No cultural heritage value

134 Wellington Road No cultural heritage value 301 Wellington Road

No cultural heritage value

136 Wellington Road No cultural heritage value 736 Richmond Street

CHVI

138 Wellington Road No cultural heritage value 740 Richmond Street

No cultural heritage value

140 Wellington Road No cultural heritage value 742 Richmond Street

CHVI

142 Wellington Road No cultural heritage value 744 Richmond Street

No cultural heritage value

166 Wellington Road No cultural heritage value 746 Richmond Street

No cultural heritage value

174 Wellington Road CHVI 1110 Richmond

Street CHVI

220 Wellington Road No cultural heritage value 44 Wharncliffe Road

No cultural heritage value

PROPERTY CHVI PROPERTY CHVI

19 Raywood Avenue No cultural heritage value Queens Ave Bridge

No cultural heritage value

243 Wellington Road CHVI

Highbury Bridge No cultural heritage value

247 Wellington Road No cultural heritage value University Bridge

CHVI

249 Wellington Road No cultural heritage value

Exhibit 4-24: Properties Recommended for CHERs Post-TPAP

MUNICIPAL ADDRESS MUNICIPAL ADDRESS 1111 Richmond Street 120 Wellington Street 1151 Richmond Street (University Gates on Western University property)

327 Wellington Street

1033 Dundas Street 331 Wellington Street

72 Wellington Street 333 Wellington Street 90 Wellington Street 127 Oxford Street West 92 Wellington Street 100 Kellogg Lane

Exhibit 4-25: Properties Recommended for Heritage Impact Assessments Post-TPAP

MUNICIPAL ADDRESS MUNICIPAL ADDRESS 1156 Dundas Street 1132 Richmond Street 871 Dundas Street Victoria Park 850 Highbury Avenue North 75 Riverside Drive 1603 Richmond Street 77 Riverside Drive 531 Ridout Street, 481 Ridout Street 163 Oxford Street West

Exhibit 4-26: Properties within HCDs Recommended for HIAs Post-TPAP

MUNICIPAL ADDRESS

HCD MUNICIPAL ADDRESS

HCD

568 Richmond Street Downtown 63 Riverside Drive Blackfriars-Petersville 472 Richmond Street Downtown 65 Riverside Drive Blackfriars-Petersville 120 Queens Avenue Downtown 67 Riverside Drive Blackfriars-Petersville 100 Queens Avenue Downtown 69 Riverside Drive Blackfriars-Petersville

Page 40: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-39

MUNICIPAL ADDRESS

HCD MUNICIPAL ADDRESS

HCD

421 Ridout Street North

Downtown 70 Riverside Drive Blackfriars-Petersville

99 Dundas Street Downtown 71 Riverside Drive Blackfriars-Petersville 130 King Street Downtown 73 Riverside Drive Blackfriars-Petersville 195 Dundas Street West Woodfield 78 Riverside Drive Blackfriars-Petersville 320 King Street West Woodfield 232 Wharncliffe Road

North Blackfriars-Petersville

25 Wilson Avenue (2 parcels requiring HIAs)

Blackfriars-Petersville 230 Wharncliffe Road North

Blackfriars-Petersville

12 Wilson Avenue Blackfriars-Petersville 227 Wharncliffe Road North

Blackfriars-Petersville

10 Riverside Drive (3 parcels requiring HIAs)

Blackfriars-Petersville 46 Oxford Street West

Blackfriars-Petersville

53 Riverside Drive Blackfriars-Petersville 42 Oxford Street West

Blackfriars-Petersville

59 Riverside Drive Blackfriars-Petersville 40 Oxford Street West

Blackfriars-Petersville

61 Riverside Drive Blackfriars-Petersville Exhibit 4-27: Impacts to HCDs

HCD IMPACTS Blackfriars-Petersville Two properties have been identified within Blackfriars-Petersville HCD

which will be directly impacted by alteration and/or demolition. 23 properties have been identified within Blackfriars-Petersville HCD which will be indirectly impacted by the proposed development. Of the indirectly impacted properties, Labatt Park, St. George Anglican Church, and the Empress Avenue School are considered key heritage landmarks to the Blackfriars-Petersville HCD.

West Woodfield Three properties identified within this HCD will be indirectly impacted, including the First Baptist Church, St. Peter’s Cathedral Basilica and Parish Office, and Victoria Park. These are considered key properties within West Woodfield HCD.

Downtown Ontario Heritage Trust has two easement properties, 399 Ridout Street North and 481 Ridout Street North, which are within the boundaries of the Downtown HCD. No impact is anticipated for these easement properties.

HCD IMPACTS Old East No properties within the Old East HCD are anticipated to be directly or

indirectly impacted.

There are no provincially significant cultural heritage properties either directly or indirectly impacted by the project.

4.4.2.2 Mitigation During detail design, it is recommended that design elements be reviewed and refined to minimize or avoid property impacts to properties with identified or potential cultural heritage value or interest.

Developing a Terms of Reference for the Heritage Impact Assessment (HIA) studies is recommended to begin immediately after the TPAP, in consultation with the London Advisory Committee on Heritage (LACH).

Due to the number of properties with potential cultural heritage value or interest, it is recommended that the Rapid Transit Implementation Office work with the City of London Heritage Planners and LACH to prioritize the heritage studies.

Potential mitigation measures have been determined for each property that has the potential to be directly or indirectly impacted. These mitigation measures are included in Table 2 within Appendix K. Mitigation measures specific to HCD are included in Exhibit 4-28.

Exhibit 4-28: Mitigation Measures for HCDs

HCD MITIGATION Blackfriars-Petersville A detailed analysis of the streetscape and lot alignments should be

further considered in an HIA. It is recommended that the Blackfriars-Petersville HCD plan be reviewed and that the impacted properties undergo an HIA.

West Woodfield A more detailed analysis of the streetscape and land use should be further considered in an HIA. It is recommended that the West Woodfield HCD plan be reviewed and the directly and indirectly impacted properties undergo an HIA.

Downtown Ontario Heritage Trust has two easement properties, 399 Ridout Street North and 481 Ridout Street North, which are within the boundaries of the Downtown HCD. No impact is anticipated for these easement properties, however, ongoing consultation with the Ontario Heritage Trust is recommended. The Downtown HCD is comprised of buildings related to the development of the downtown area, during the nineteenth century and into the early twentieth century. Several of the structures are considered to be contributing (as defined in the HCD Plan) and a more detailed analysis of the streetscape and land use

Page 41: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

London BRT Transit Project Assessment Process – Environmental Project Report

4-40

HCD MITIGATION should be further considered in an HIA assessment of the impacts to the HCD. It is recommended that the Downtown HCD plan be reviewed and the contributing and non-contributing properties undergo an HIA.

Old East No properties within the Old East HCD are anticipated to be directly or indirectly impacted, and therefore no further cultural heritage study is recommended in the Old East HCD.

Where indirect or direct impacts are anticipated and avoidance is not possible, mitigation measures to be considered in detail design include: context sensitive design (sidewalk placement, street trees, decorative walls and fences, front yards), stop and shelter design to reflect cultural heritage resources, and documentation of resources in advance of alteration. Best practice approaches to such impacts could include a tree reinstatement plan to redevelop the mature tree canopy along the streetscape and altering design elements to reduce or remove impacts to areas were heritage attributes are identified near the roadway. Built heritage resources in close proximity to the project should undergo a pre-construction building condition survey and be monitored during heavy construction activity.

Design principles and branding strategies for the BRT network can be developed that compliment adjacent cultural heritage resources and are sensitive to contextual values and character. There are opportunities to integrate the proposed infrastructure into London’s heritage resources, including stop infrastructure, shelters, platforms, signage, lighting, art and seating, resulting in a project that compliments existing cultural heritage resources.

Prior to construction, identified cultural heritage resources should be documented and archived in advance of landscape alteration. This work should be conducted in consultation with LACH, and include photographic documentation of individual resources with representative views, histories, mapping, and historic photographs where available and appropriate.

During construction or excavation adjacent to known or potential cultural heritage resources, vibration impact will be monitored and work will stop immediately if vibration thresholds are exceeded. This applies to potential, listed, and designated properties.

4.4.2.3 Net Effects Property-specific recommendations have been provided for properties that may be directly or indirectly impacted by the project. These recommendations, which are detailed in Table 2 within Appendix K, have been made to confirm that impacts from project implementation will be mitigated during detail design.

In instances where direct impacts to properties with CHVI are unavoidable, the project will result in the permanent alteration or attrition of irreplaceable cultural heritage resources. Further studies such as HIAs and conservation plans are recommended during detail design to identify measures for long-term conservation of the cultural heritage resources and reduce negative impacts.

4.4.2.4 Monitoring During the detail design process, if modifications to intersecting streets are identified, cultural heritage elements should be reviewed to identify any additional potential impacts.

If additional bus rapid transit infrastructure is identified during detail design, which was not contemplated as part of this report, a qualified heritage consultant should be retained to confirm impacts of such infrastructure and develop appropriate recommendations to mitigate and/or avoid impacts.

For the properties located within or directly adjacent to the study area that have potential CHVI, listed in Exhibit 4-24, it is recommended that CHERs be completed post-TPAP to determine the extent of the CHVI. All completed CHERs will be reviewed by the City of London Heritage Planning staff and LACH.

Once all technical cultural heritage studies (CHERs, HIAs) are complete and the project design has been finalized, the project team will provide the MTCS with a summary update on which properties were confirmed to have CHVI and how cultural heritage resources will be conserved, for MTCS records.

4.5 Matters of Provincial Importance Under the TPAP, the MECP considers whether a transit project may have negative impacts on matters of provincial importance and constitutionally protected Indigenous or treaty rights.

The following table summarizes the findings of the analysis of potential impacts, net effects, and mitigation measures for relevant matters of provincial importance.

A series of comprehensive plans for mitigation and monitoring will be developed during detail design and prior to project implementation, described further in Section 7. These plans will be based on the recommendations provided in the technical reports to produce net positive effects on matters of provincial importance. Plans will be developed specifically related to the natural environment, cultural heritage resources, hydrology, or constitutionally protected Indigenous or Treaty Rights. The plans will identify and address potential environmental impacts, approval and permit requirements, and monitoring processes to be completed during construction.

Page 42: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

4-41

Exhibit 4-29: Matters of Provincial Importance

Matters of Provincial Importance1 Definition2 Applicability to the Project A park, conservation reserve or protected area

A provincial park, conservation reserve or provincially protected area designated by the province.

There are no provincial parks or conservation reserves within the Study Area.

Extirpated, Endangered, Threatened, or species of special concern and their habitat

A species at risk (SAR): Extirpated, Endangered, or Threatened species and their habitat. A Species of Conservation Concern (SCC): Rare or substantially declining species that have a high percentage of their global population in Ontario Special concern species identified on the Species at Risk in Ontario (SARO) List that were formally referred to as “vulnerable” in the Significant Wildlife Habitat Technical Guide (SWHTG) (MNRF, 2000). Species identified as nationally endangered or Threatened by the Committee on the Status of Endangered Wildlife in Canada (COSEWIC), which are not protected in regulation under Ontario’s Endangered Species Act, 2007.

There are a number of species protected under the Endangered Species Act that have the potential to be impacted by the project. The net effects, mitigation and monitoring measures are identified and will be updated during TPAP as required.

A wetland, woodland, habitat of wildlife or other natural heritage feature

A significant Wetland, Significant Woodland, Significant Valleyland or Significant Wildlife Habitat as defined in Section 2.1.5 of the Provincial Policy Statement (2014).

There are portions of a Significant Wetland, Significant Woodlands, Significant Valleylands and Significant Wildlife Habitat within the Study Area.

An area of natural or scientific interest (ANSI)

A Significant ANSI as defined in Section 2.1.5 of the PPS (2014) The Westminster Ponds/Pond Mills Area of Natural or Scientific Interest is located within the Study Area and has the potential to be impacted by the project.

A stream, creek, river, or lake containing fish and their habitats

A stream, creek, river or lake containing fish and their habitats. The Rapid Transit route crosses the Thames River, the North Thames River, Medway Creek and Mud Creek.

An area or region of surface water or groundwater or other important hydrological feature

An area or region of surface water or groundwater or other important hydrological feature.

There are no areas or regions of surface water or groundwater or other important hydrological features within the Study Area.

Areas that may be impacted by a known or suspected on-site or off-site source of contamination such as a spill, a gasoline outlet, an open or closed landfill site, etc.

Areas that may be impacted by a known or suspected on-site or off-site source of contamination such as a spill, a gasoline outlet, an open or closed landfill site, etc.

29 areas with low or low-to-moderate risk ratings were identified within the Study Area. No areas with significant potential for contamination were identified within the Study Area.

Protected heritage property Property designated under Parts IV, V or VI, of the Ontario Heritage Act; property subject to a heritage conservation easement under Parts II or IV of the Ontario Heritage Act; property identified by the Province and prescribed public bodies as provincial heritage property under the Standards and Guidelines for Conservation of Provincial Heritage Properties; property protected under federal legislation, and United Nations Educational, Scientific and Cultural Organization (UNESCO) World Heritage Sites.

There are 10 properties that have known CHVI and may be directly or indirectly impacted by the project. Further, 32 properties have been identified as being within a HCD and may be directly or indirectly impacted by the project. These properties and HCDs will be subject to Heritage Impact Assessments following TPAP and early in the detail design process. During detail design, opportunities to avoid or minimize impacts to properties will be investigated.

Page 43: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

4-42

Matters of Provincial Importance1 Definition2 Applicability to the Project Built heritage resources A building, structure, monument, installation or any manufactured remnant

that contributes to a property’s cultural heritage value or interest as identified by a community, including an Indigenous community. Built heritage resources are generally located on property that has been designated under Parts IV or V of the Ontario Heritage Act, or included on the local, provincial and/or federal registers.

CHERs were completed during TPAP for 51 properties with potential CHVI that may be directly impacted by the project. The CHERs completed during the TPAP confirmed that 10 properties have CHVI. Further, 12 properties were identified as having potential CHVI and may be directly or indirectly impacted by the project. Cultural Heritage Evaluation Reports will be prioritized and completed for these properties following TPAP in consultation with LACH and early in the detail design process. During detail design, opportunities to avoid or minimize impacts to properties will be investigated.

Cultural heritage landscapes A defined geographical area that may have been modified by human activity and is identified as having cultural heritage value or interest by a community, including an Indigenous community. The area may involve features such as structures, spaces, archaeological sites or natural elements that are valued together for their interrelationship, meaning or association.

There are two cultural heritage landscapes within one kilometre of the project footprint. No impacts are anticipated.

Archaeological resources and areas of potential archaeological interest

Includes artifacts, archaeological sites, and marine archaeological sites, as defined under the Ontario Heritage Act. The identification and evaluation of such resources are based upon archaeological fieldwork undertaken in accordance with the Ontario Heritage Act.

There are four registered archaeological sites, of which three are required to undergo additional archaeological assessments, 10 historic cemeteries and seven areas with the potential for deeply buried deposits within the Study Area.

An area designated as an escarpment natural area or an escarpment protection area by the Niagara Escarpment Plan under the Niagara Escarpment Planning and Development Act

An area designated as an escarpment natural area or an escarpment protection area by the Niagara Escarpment Plan under the Niagara Escarpment Planning and Development Act.

The study area is located outside of the Niagara Escarpment Plan area.

Property within an area designated as a natural core area or natural linkage area within the area to which the Oak Ridges Moraine Conservation Plan (ORMCP) under the Oak Ridges Moraine Conservation Act, 2001 applies

Property within an area designated as a natural core area or natural linkage area within the area to which the ORMCP under the Oak Ridges Moraine Conservation Act, 2001 applies.

The study area is located outside of the Oak Ridges Moraine Conservation Plan area.

Property within an area described as a key natural heritage feature or a key hydrologic feature in the Protected Countryside by the Greenbelt Plan under the Greenbelt Act, 2005

Property within an area described as a key natural features or a key hydrological features in the Protected Countryside by the Greenbelt Plan under the Greenbelt Act, 2005.

The study area is located outside of the Greenbelt Plan’s area.

Constitutionally protected Indigenous or treaty rights and areas of concern3

Specific protected rights as recognized by Section 35 of the Constitution Act (1982), including treaty rights for present and future modern land claims agreements.

The Ministry of the Environment, Conservation and Parks provided a comprehensive list of Indigenous Communities to consult through the study process.

Notes: 1. (Examples from) Guide to Environmental Assessment Requirements for Transit Projects, Ministry of the Environment, Conservation and Parks, January 2014

2. Definition based on Guide to Ontario’s Transit Project Assessment Process (MECP, January 2014) and other applicable Acts or Guides as noted.

3. Library of Parliament, Aboriginal and Treaty Rights, https://lop.parl.ca/Content/LOP/ResearchPublications/tips/tip96-e.htm, Parliament of Canada.

Page 44: Table of Contents - London, Ontario · Creating a Bus Rapid Transit (BRT) network of dedicated lanes for transit will change the ... The BRT network is proposed to operate seven days

4-43