TABLE OF CONTENTS - KTD
Transcript of TABLE OF CONTENTS - KTD
i
TABLE OF CONTENTS
EXECUTIVE SUMMARY 1
Introduction 1
Environmental Monitoring Works 1
Key Information in the Reporting Month 2
Future Key Issues 2
1 INTRODUCTION 3
Background 3
Project Organizations 3
Construction Activities undertaken during the Reporting Month 4
Summary of EMampA Requirements 10
2 AIR QUALITY 11
Monitoring Requirements 11
Monitoring Locations 11
Monitoring Equipment 11
Monitoring Parameters Frequency and Duration 12
Monitoring Methodology and QAQC Procedure 12
Results and Observations 14
3 NOISE 16
Monitoring Requirements 16
Monitoring Locations 16
Monitoring Equipment 16
Monitoring Parameters Frequency and Duration 17
Monitoring Methodology and QAQC Procedures 17
Maintenance and Calibration 18
Results and Observations 18
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS 20
5 LANDSCAPE OF VISUAL 23
Monitoring Requirements 23
Results and Observations 23
6 ENVIRONMENTAL AUDIT 24
Site Audits 24
Review of Environmental Monitoring Procedures 24
Status of Waste Management 24
Implementation Status of Environmental Mitigation Measures 24
Summary of Mitigation Measures Implemented 25
Implementation Status of Event Action Plans 25
Summary of Complaint Warning Notification of any Summons and Successful Prosecution 25
7 FUTURE KEY ISSUES 26
Key Issues for the Coming Month 29
Monitoring Schedule for the Next Month 30
8 CONCLUSIONS AND RECOMMENDATIONS 31
Conclusions 31
Recommendations 31
ii
LIST OF TABLES
Table I Non-compliance Recorded for the Project in the Reporting Month
Table II Summary Table for Key Information in the Reporting Month
Table 11 Key Project Contacts
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting Month
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Table 21 Locations for Air Quality Monitoring
Table 22 Air Quality Monitoring Equipment
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Table 31 Noise Monitoring Stations
Table 32 Noise Monitoring Equipment
Table 33 Noise Monitoring Parameters Frequency and Duration
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Table 41 Comparison of 1-hr TSP data with EIA predictions
Table 42 Comparison of 24-hr TSP data with EIA predictions
Table 43 Comparison of Noise Monitoring Data with EIA predictions
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Month
LIST OF FIGURES
Figure 1 Layout Plan of the Project Site
Figure 2 Locations of Air Quality Monitoring Stations
Figure 3 Locations of Construction Noise Monitoring Stations
Figure 4 Locations of Wind Anemometer
LIST OF APPENDICES
A Action and Limit Levels for Air Quality and Noise
B Copies of Calibration Certificates
C Weather Information
D Environmental Monitoring Schedules
E 1-hour TSP Monitoring Results Graphical Presentations
F 24-hour TSP Monitoring Results Graphical Presentations
G Noise Monitoring Results and Graphical Presentations
H Summary of Exceedance
I Site Audit Summary
J Event Action Plans
K Environmental Mitigation Implementation Schedule (EMIS)
L Summaries of Environmental Complaint Warning Summon and Notification
of Successful Prosecution
M Summary of Waste Generation and Disposal Records
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 1
EXECUTIVE SUMMARY
Introduction
1 This is the 9th
Environmental Monitoring and Audit (EMampA) Report prepared by Cinotech
Consultants Limited for the ldquoContract No KLN201004 - Environmental Monitoring Works for
Kai Tak Developmentrdquo (hereinafter called ldquothe Projectrdquo) This report documents the findings of
EMampA Works conducted in September 2011
2 During the reporting month the following works contracts were undertaken within Kai Tak Site
bull KL200901 - Site Formation for Kai Tak Cruise Terminal
bull KL200809 - Stage 1 Infrastructure works at North Apron
bull KL200807 - Stage 1 Advance Infrastructure Works
bull KL200902 - Site Investigation for Trunk Road T2 and Infrastructure at South Apron (Stage 1)
bull CV200703 - Development at Anderson Road
bull DC200812 - Sewage Interception Scheme in Kowloon City
bull DC201003 - Kai Tak Nullah Improvement Works at Prince Edward Road East
bull DC200921 - Provision of Interception Facilities at Jordan Valley Box Culvert
bull 20090097 - Public Rental Housing Development at Kai Tak Site 1A
bull 20090006 - Public Rental Housing Development at Kai Tak Site 1B
bull 3WSD08 6WSD08 7WSD08 amp 8WSD08 - Replacement and Rehabilitation of Water
Mains Stages 2 amp 3
bull SS W 303 - Kai Tak Cruise Terminal Building and Ancillary Facilities
bull CKL-KCT circuit 1amp2 - CLPP (132kV cable installation)
bull 1016EM10 - Chilled Water Pipe Laying Works at North Apron Area for District Cooling
System at Kai Tak Development
bull 1017EM10 - Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak
Development
bull KL201002 - Kai Tak Development ndash Kai Tak Approach Channel and Kwun Tong Typhoon
Shelter Improvement Works (Phase 1)
bull KL201003 - Kai Tak Development ndash Stage 2 Infrastructure Works at North Apron Area of
Kai Tak Airport for Residential Development and Government Facilities)
3 Stockpiling of excavated amp construction materials storage of equipments operation of concrete
batching plant sand depot business in the recovery and recycling and car parks etc are the
major activities for short term tenancy (STT) temporary government land allocation (TGLA)
Environmental Monitoring Works
4 Environmental monitoring for the Project was performed in accordance with the EMampA Manual
and the monitoring results were checked and reviewed Site InspectionsAudits were conducted
once per week The implementation of the environmental mitigation measures Event Action
Plans and environmental complaint handling procedures were also checked
5 Summary of the non-compliance in the reporting month for the Project is tabulated in Table I
Table I Non-compliance Record for the Project in the Reporting Month
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 2
Parameter No of Exceedance Action
Taken Action Level Limit Level
1-hr TSP 0 0 NA
24-hr TSP 0 0 NA
Noise 0 0 NA
1-hour amp 24-hour TSP Monitoring
6 All 1-hour amp 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise
7 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Key Information in the Reporting Month
8 Summary of key information in the reporting month is tabulated in Table II
Table II Summary Table for Key Information in the Reporting Month
Event Event Details Action Taken Status Remark
Number Nature
Complaint received 0 --- NA NA ---
Reporting Changes 0 --- NA NA ---
Notifications of any
summons amp
prosecutions received
0 --- NA NA ---
Future Key Issues
9 The future key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 3
1 INTRODUCTION
Background
11 The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula
comprising the apron and runway areas of the former Kai Tak Airport and existing
waterfront areas at To Kwa Wan Ma Tau Kok Kowloon Bay Kwun Tong and Cha Kwo
Ling It covers a land area of about 328 hectares The Project also covers Kowloon Bay and
Kwun Tong Typhoon Shelter and the adjacent water bodies The general layout of the
Project is shown in Figure 1
12 Civil Engineering and Development Department (CEDD) had completed an Environmental
Impact Assessment (EIA) study for KTD under Agreement No CE 352006(CE) Kai Tak
Development Engineering Study cum Design and Construction of Advance Works ndash
Investigation Design and Construction (hereafter called ldquoSchedule 3 EIA Reportrdquo) The
Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance
(EIAO) in March 2009
13 As recommended in the Schedule 3 EIA Report EMampA programme shall be required for
different phases of the KTD as a whole In August 2010 Cinotech Consultants Limited was
commissioned by CEDD to undertake the Environmental Monitoring and Audit (EMampA)
works for KTD Under the Contract Environmental Team (ET(KTD)) shall oversee all the
environmental issues within the Kai Tak Development (KTD) including but not limit to the
Schedule 2 Designated Projects and other work contracts
14 Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental
Monitoring and Audit (EMampA) works for KTD This is the 9th
Monthly EMampA report
summarizing the EMampA works for the Project in September 2011
Project Organizations
15 Different parties with different levels of involvement in the project organization include
bull Environmental Protection Department (The Authority)
bull Project Proponent ndash Civil Engineering and Development Department (CEDD)
bull The Engineer and the Engineerrsquos Representative (ER) ndash AECOM
bull Environmental Team (ET(KTD)) ndash Cinotech Consultants Limited (CCL)
bull Independent Environmental Checker (IEC(KTD)) ndash Allied Environmental Consultants
Limited (AEC)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 4
16 The key contacts of the Project are shown in Table 11
Table 11 Key Project Contacts
Party Role Contact Person Phone No Fax No
CEDD Project Proponent
Mr K Y SHIN 2301 1461 2301 1277
Mr William WONG 3104 2197 2301 1277
AECOM Engineerrsquos
Representative
Ms Anna CHUNG 3922 9437 2317 7609
Cinotech Environmental
Team (KTD)
Dr Priscilla Choy 2151 2089 3107 1388
Ms Ivy Tam 2151 2090
AEC
Independent
Environmental
Checker (KTD)
Ms Grace Kwok
2815 7028 2815 5399
Construction Activities undertaken during the Reporting Month
17 There are several works contracts undertaken within KTD during the reporting month In
order to collect relevant environmental information from the work contracts and incorporate
into this monthly monitoring report a survey form for monthly environmental performance
records was sent to all work contractstenants within KTD on 30 November 2010 The
survey form shall be returned by 5th each month to provide the environmental monthly
information of respective work contracts within KTD
18 Based on the returned survey form from work contracts and site observation for short term
tenancy (STT) temporary government land allocation (TGLA) during the weekly site
inspection the major site activities undertaken within Kai Tak Development (KTD) in the
reporting month are summarized in Table 12
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting month
KDO CEDD projects
Contract No Project Title Site Activities
KL200901 Site Formation for Kai Tak
Cruise Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance system
7) Erection and maintenance of silt curtain
8) Construction of capping beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure
works at North Apron
1) Drainage Works
2) Watermain Works
3) Footbridge Superstructure construction
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
ii
LIST OF TABLES
Table I Non-compliance Recorded for the Project in the Reporting Month
Table II Summary Table for Key Information in the Reporting Month
Table 11 Key Project Contacts
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting Month
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Table 21 Locations for Air Quality Monitoring
Table 22 Air Quality Monitoring Equipment
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Table 31 Noise Monitoring Stations
Table 32 Noise Monitoring Equipment
Table 33 Noise Monitoring Parameters Frequency and Duration
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Table 41 Comparison of 1-hr TSP data with EIA predictions
Table 42 Comparison of 24-hr TSP data with EIA predictions
Table 43 Comparison of Noise Monitoring Data with EIA predictions
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Month
LIST OF FIGURES
Figure 1 Layout Plan of the Project Site
Figure 2 Locations of Air Quality Monitoring Stations
Figure 3 Locations of Construction Noise Monitoring Stations
Figure 4 Locations of Wind Anemometer
LIST OF APPENDICES
A Action and Limit Levels for Air Quality and Noise
B Copies of Calibration Certificates
C Weather Information
D Environmental Monitoring Schedules
E 1-hour TSP Monitoring Results Graphical Presentations
F 24-hour TSP Monitoring Results Graphical Presentations
G Noise Monitoring Results and Graphical Presentations
H Summary of Exceedance
I Site Audit Summary
J Event Action Plans
K Environmental Mitigation Implementation Schedule (EMIS)
L Summaries of Environmental Complaint Warning Summon and Notification
of Successful Prosecution
M Summary of Waste Generation and Disposal Records
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 1
EXECUTIVE SUMMARY
Introduction
1 This is the 9th
Environmental Monitoring and Audit (EMampA) Report prepared by Cinotech
Consultants Limited for the ldquoContract No KLN201004 - Environmental Monitoring Works for
Kai Tak Developmentrdquo (hereinafter called ldquothe Projectrdquo) This report documents the findings of
EMampA Works conducted in September 2011
2 During the reporting month the following works contracts were undertaken within Kai Tak Site
bull KL200901 - Site Formation for Kai Tak Cruise Terminal
bull KL200809 - Stage 1 Infrastructure works at North Apron
bull KL200807 - Stage 1 Advance Infrastructure Works
bull KL200902 - Site Investigation for Trunk Road T2 and Infrastructure at South Apron (Stage 1)
bull CV200703 - Development at Anderson Road
bull DC200812 - Sewage Interception Scheme in Kowloon City
bull DC201003 - Kai Tak Nullah Improvement Works at Prince Edward Road East
bull DC200921 - Provision of Interception Facilities at Jordan Valley Box Culvert
bull 20090097 - Public Rental Housing Development at Kai Tak Site 1A
bull 20090006 - Public Rental Housing Development at Kai Tak Site 1B
bull 3WSD08 6WSD08 7WSD08 amp 8WSD08 - Replacement and Rehabilitation of Water
Mains Stages 2 amp 3
bull SS W 303 - Kai Tak Cruise Terminal Building and Ancillary Facilities
bull CKL-KCT circuit 1amp2 - CLPP (132kV cable installation)
bull 1016EM10 - Chilled Water Pipe Laying Works at North Apron Area for District Cooling
System at Kai Tak Development
bull 1017EM10 - Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak
Development
bull KL201002 - Kai Tak Development ndash Kai Tak Approach Channel and Kwun Tong Typhoon
Shelter Improvement Works (Phase 1)
bull KL201003 - Kai Tak Development ndash Stage 2 Infrastructure Works at North Apron Area of
Kai Tak Airport for Residential Development and Government Facilities)
3 Stockpiling of excavated amp construction materials storage of equipments operation of concrete
batching plant sand depot business in the recovery and recycling and car parks etc are the
major activities for short term tenancy (STT) temporary government land allocation (TGLA)
Environmental Monitoring Works
4 Environmental monitoring for the Project was performed in accordance with the EMampA Manual
and the monitoring results were checked and reviewed Site InspectionsAudits were conducted
once per week The implementation of the environmental mitigation measures Event Action
Plans and environmental complaint handling procedures were also checked
5 Summary of the non-compliance in the reporting month for the Project is tabulated in Table I
Table I Non-compliance Record for the Project in the Reporting Month
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 2
Parameter No of Exceedance Action
Taken Action Level Limit Level
1-hr TSP 0 0 NA
24-hr TSP 0 0 NA
Noise 0 0 NA
1-hour amp 24-hour TSP Monitoring
6 All 1-hour amp 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise
7 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Key Information in the Reporting Month
8 Summary of key information in the reporting month is tabulated in Table II
Table II Summary Table for Key Information in the Reporting Month
Event Event Details Action Taken Status Remark
Number Nature
Complaint received 0 --- NA NA ---
Reporting Changes 0 --- NA NA ---
Notifications of any
summons amp
prosecutions received
0 --- NA NA ---
Future Key Issues
9 The future key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 3
1 INTRODUCTION
Background
11 The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula
comprising the apron and runway areas of the former Kai Tak Airport and existing
waterfront areas at To Kwa Wan Ma Tau Kok Kowloon Bay Kwun Tong and Cha Kwo
Ling It covers a land area of about 328 hectares The Project also covers Kowloon Bay and
Kwun Tong Typhoon Shelter and the adjacent water bodies The general layout of the
Project is shown in Figure 1
12 Civil Engineering and Development Department (CEDD) had completed an Environmental
Impact Assessment (EIA) study for KTD under Agreement No CE 352006(CE) Kai Tak
Development Engineering Study cum Design and Construction of Advance Works ndash
Investigation Design and Construction (hereafter called ldquoSchedule 3 EIA Reportrdquo) The
Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance
(EIAO) in March 2009
13 As recommended in the Schedule 3 EIA Report EMampA programme shall be required for
different phases of the KTD as a whole In August 2010 Cinotech Consultants Limited was
commissioned by CEDD to undertake the Environmental Monitoring and Audit (EMampA)
works for KTD Under the Contract Environmental Team (ET(KTD)) shall oversee all the
environmental issues within the Kai Tak Development (KTD) including but not limit to the
Schedule 2 Designated Projects and other work contracts
14 Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental
Monitoring and Audit (EMampA) works for KTD This is the 9th
Monthly EMampA report
summarizing the EMampA works for the Project in September 2011
Project Organizations
15 Different parties with different levels of involvement in the project organization include
bull Environmental Protection Department (The Authority)
bull Project Proponent ndash Civil Engineering and Development Department (CEDD)
bull The Engineer and the Engineerrsquos Representative (ER) ndash AECOM
bull Environmental Team (ET(KTD)) ndash Cinotech Consultants Limited (CCL)
bull Independent Environmental Checker (IEC(KTD)) ndash Allied Environmental Consultants
Limited (AEC)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 4
16 The key contacts of the Project are shown in Table 11
Table 11 Key Project Contacts
Party Role Contact Person Phone No Fax No
CEDD Project Proponent
Mr K Y SHIN 2301 1461 2301 1277
Mr William WONG 3104 2197 2301 1277
AECOM Engineerrsquos
Representative
Ms Anna CHUNG 3922 9437 2317 7609
Cinotech Environmental
Team (KTD)
Dr Priscilla Choy 2151 2089 3107 1388
Ms Ivy Tam 2151 2090
AEC
Independent
Environmental
Checker (KTD)
Ms Grace Kwok
2815 7028 2815 5399
Construction Activities undertaken during the Reporting Month
17 There are several works contracts undertaken within KTD during the reporting month In
order to collect relevant environmental information from the work contracts and incorporate
into this monthly monitoring report a survey form for monthly environmental performance
records was sent to all work contractstenants within KTD on 30 November 2010 The
survey form shall be returned by 5th each month to provide the environmental monthly
information of respective work contracts within KTD
18 Based on the returned survey form from work contracts and site observation for short term
tenancy (STT) temporary government land allocation (TGLA) during the weekly site
inspection the major site activities undertaken within Kai Tak Development (KTD) in the
reporting month are summarized in Table 12
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting month
KDO CEDD projects
Contract No Project Title Site Activities
KL200901 Site Formation for Kai Tak
Cruise Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance system
7) Erection and maintenance of silt curtain
8) Construction of capping beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure
works at North Apron
1) Drainage Works
2) Watermain Works
3) Footbridge Superstructure construction
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 1
EXECUTIVE SUMMARY
Introduction
1 This is the 9th
Environmental Monitoring and Audit (EMampA) Report prepared by Cinotech
Consultants Limited for the ldquoContract No KLN201004 - Environmental Monitoring Works for
Kai Tak Developmentrdquo (hereinafter called ldquothe Projectrdquo) This report documents the findings of
EMampA Works conducted in September 2011
2 During the reporting month the following works contracts were undertaken within Kai Tak Site
bull KL200901 - Site Formation for Kai Tak Cruise Terminal
bull KL200809 - Stage 1 Infrastructure works at North Apron
bull KL200807 - Stage 1 Advance Infrastructure Works
bull KL200902 - Site Investigation for Trunk Road T2 and Infrastructure at South Apron (Stage 1)
bull CV200703 - Development at Anderson Road
bull DC200812 - Sewage Interception Scheme in Kowloon City
bull DC201003 - Kai Tak Nullah Improvement Works at Prince Edward Road East
bull DC200921 - Provision of Interception Facilities at Jordan Valley Box Culvert
bull 20090097 - Public Rental Housing Development at Kai Tak Site 1A
bull 20090006 - Public Rental Housing Development at Kai Tak Site 1B
bull 3WSD08 6WSD08 7WSD08 amp 8WSD08 - Replacement and Rehabilitation of Water
Mains Stages 2 amp 3
bull SS W 303 - Kai Tak Cruise Terminal Building and Ancillary Facilities
bull CKL-KCT circuit 1amp2 - CLPP (132kV cable installation)
bull 1016EM10 - Chilled Water Pipe Laying Works at North Apron Area for District Cooling
System at Kai Tak Development
bull 1017EM10 - Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak
Development
bull KL201002 - Kai Tak Development ndash Kai Tak Approach Channel and Kwun Tong Typhoon
Shelter Improvement Works (Phase 1)
bull KL201003 - Kai Tak Development ndash Stage 2 Infrastructure Works at North Apron Area of
Kai Tak Airport for Residential Development and Government Facilities)
3 Stockpiling of excavated amp construction materials storage of equipments operation of concrete
batching plant sand depot business in the recovery and recycling and car parks etc are the
major activities for short term tenancy (STT) temporary government land allocation (TGLA)
Environmental Monitoring Works
4 Environmental monitoring for the Project was performed in accordance with the EMampA Manual
and the monitoring results were checked and reviewed Site InspectionsAudits were conducted
once per week The implementation of the environmental mitigation measures Event Action
Plans and environmental complaint handling procedures were also checked
5 Summary of the non-compliance in the reporting month for the Project is tabulated in Table I
Table I Non-compliance Record for the Project in the Reporting Month
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 2
Parameter No of Exceedance Action
Taken Action Level Limit Level
1-hr TSP 0 0 NA
24-hr TSP 0 0 NA
Noise 0 0 NA
1-hour amp 24-hour TSP Monitoring
6 All 1-hour amp 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise
7 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Key Information in the Reporting Month
8 Summary of key information in the reporting month is tabulated in Table II
Table II Summary Table for Key Information in the Reporting Month
Event Event Details Action Taken Status Remark
Number Nature
Complaint received 0 --- NA NA ---
Reporting Changes 0 --- NA NA ---
Notifications of any
summons amp
prosecutions received
0 --- NA NA ---
Future Key Issues
9 The future key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 3
1 INTRODUCTION
Background
11 The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula
comprising the apron and runway areas of the former Kai Tak Airport and existing
waterfront areas at To Kwa Wan Ma Tau Kok Kowloon Bay Kwun Tong and Cha Kwo
Ling It covers a land area of about 328 hectares The Project also covers Kowloon Bay and
Kwun Tong Typhoon Shelter and the adjacent water bodies The general layout of the
Project is shown in Figure 1
12 Civil Engineering and Development Department (CEDD) had completed an Environmental
Impact Assessment (EIA) study for KTD under Agreement No CE 352006(CE) Kai Tak
Development Engineering Study cum Design and Construction of Advance Works ndash
Investigation Design and Construction (hereafter called ldquoSchedule 3 EIA Reportrdquo) The
Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance
(EIAO) in March 2009
13 As recommended in the Schedule 3 EIA Report EMampA programme shall be required for
different phases of the KTD as a whole In August 2010 Cinotech Consultants Limited was
commissioned by CEDD to undertake the Environmental Monitoring and Audit (EMampA)
works for KTD Under the Contract Environmental Team (ET(KTD)) shall oversee all the
environmental issues within the Kai Tak Development (KTD) including but not limit to the
Schedule 2 Designated Projects and other work contracts
14 Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental
Monitoring and Audit (EMampA) works for KTD This is the 9th
Monthly EMampA report
summarizing the EMampA works for the Project in September 2011
Project Organizations
15 Different parties with different levels of involvement in the project organization include
bull Environmental Protection Department (The Authority)
bull Project Proponent ndash Civil Engineering and Development Department (CEDD)
bull The Engineer and the Engineerrsquos Representative (ER) ndash AECOM
bull Environmental Team (ET(KTD)) ndash Cinotech Consultants Limited (CCL)
bull Independent Environmental Checker (IEC(KTD)) ndash Allied Environmental Consultants
Limited (AEC)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 4
16 The key contacts of the Project are shown in Table 11
Table 11 Key Project Contacts
Party Role Contact Person Phone No Fax No
CEDD Project Proponent
Mr K Y SHIN 2301 1461 2301 1277
Mr William WONG 3104 2197 2301 1277
AECOM Engineerrsquos
Representative
Ms Anna CHUNG 3922 9437 2317 7609
Cinotech Environmental
Team (KTD)
Dr Priscilla Choy 2151 2089 3107 1388
Ms Ivy Tam 2151 2090
AEC
Independent
Environmental
Checker (KTD)
Ms Grace Kwok
2815 7028 2815 5399
Construction Activities undertaken during the Reporting Month
17 There are several works contracts undertaken within KTD during the reporting month In
order to collect relevant environmental information from the work contracts and incorporate
into this monthly monitoring report a survey form for monthly environmental performance
records was sent to all work contractstenants within KTD on 30 November 2010 The
survey form shall be returned by 5th each month to provide the environmental monthly
information of respective work contracts within KTD
18 Based on the returned survey form from work contracts and site observation for short term
tenancy (STT) temporary government land allocation (TGLA) during the weekly site
inspection the major site activities undertaken within Kai Tak Development (KTD) in the
reporting month are summarized in Table 12
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting month
KDO CEDD projects
Contract No Project Title Site Activities
KL200901 Site Formation for Kai Tak
Cruise Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance system
7) Erection and maintenance of silt curtain
8) Construction of capping beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure
works at North Apron
1) Drainage Works
2) Watermain Works
3) Footbridge Superstructure construction
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 2
Parameter No of Exceedance Action
Taken Action Level Limit Level
1-hr TSP 0 0 NA
24-hr TSP 0 0 NA
Noise 0 0 NA
1-hour amp 24-hour TSP Monitoring
6 All 1-hour amp 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise
7 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Key Information in the Reporting Month
8 Summary of key information in the reporting month is tabulated in Table II
Table II Summary Table for Key Information in the Reporting Month
Event Event Details Action Taken Status Remark
Number Nature
Complaint received 0 --- NA NA ---
Reporting Changes 0 --- NA NA ---
Notifications of any
summons amp
prosecutions received
0 --- NA NA ---
Future Key Issues
9 The future key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 3
1 INTRODUCTION
Background
11 The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula
comprising the apron and runway areas of the former Kai Tak Airport and existing
waterfront areas at To Kwa Wan Ma Tau Kok Kowloon Bay Kwun Tong and Cha Kwo
Ling It covers a land area of about 328 hectares The Project also covers Kowloon Bay and
Kwun Tong Typhoon Shelter and the adjacent water bodies The general layout of the
Project is shown in Figure 1
12 Civil Engineering and Development Department (CEDD) had completed an Environmental
Impact Assessment (EIA) study for KTD under Agreement No CE 352006(CE) Kai Tak
Development Engineering Study cum Design and Construction of Advance Works ndash
Investigation Design and Construction (hereafter called ldquoSchedule 3 EIA Reportrdquo) The
Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance
(EIAO) in March 2009
13 As recommended in the Schedule 3 EIA Report EMampA programme shall be required for
different phases of the KTD as a whole In August 2010 Cinotech Consultants Limited was
commissioned by CEDD to undertake the Environmental Monitoring and Audit (EMampA)
works for KTD Under the Contract Environmental Team (ET(KTD)) shall oversee all the
environmental issues within the Kai Tak Development (KTD) including but not limit to the
Schedule 2 Designated Projects and other work contracts
14 Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental
Monitoring and Audit (EMampA) works for KTD This is the 9th
Monthly EMampA report
summarizing the EMampA works for the Project in September 2011
Project Organizations
15 Different parties with different levels of involvement in the project organization include
bull Environmental Protection Department (The Authority)
bull Project Proponent ndash Civil Engineering and Development Department (CEDD)
bull The Engineer and the Engineerrsquos Representative (ER) ndash AECOM
bull Environmental Team (ET(KTD)) ndash Cinotech Consultants Limited (CCL)
bull Independent Environmental Checker (IEC(KTD)) ndash Allied Environmental Consultants
Limited (AEC)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 4
16 The key contacts of the Project are shown in Table 11
Table 11 Key Project Contacts
Party Role Contact Person Phone No Fax No
CEDD Project Proponent
Mr K Y SHIN 2301 1461 2301 1277
Mr William WONG 3104 2197 2301 1277
AECOM Engineerrsquos
Representative
Ms Anna CHUNG 3922 9437 2317 7609
Cinotech Environmental
Team (KTD)
Dr Priscilla Choy 2151 2089 3107 1388
Ms Ivy Tam 2151 2090
AEC
Independent
Environmental
Checker (KTD)
Ms Grace Kwok
2815 7028 2815 5399
Construction Activities undertaken during the Reporting Month
17 There are several works contracts undertaken within KTD during the reporting month In
order to collect relevant environmental information from the work contracts and incorporate
into this monthly monitoring report a survey form for monthly environmental performance
records was sent to all work contractstenants within KTD on 30 November 2010 The
survey form shall be returned by 5th each month to provide the environmental monthly
information of respective work contracts within KTD
18 Based on the returned survey form from work contracts and site observation for short term
tenancy (STT) temporary government land allocation (TGLA) during the weekly site
inspection the major site activities undertaken within Kai Tak Development (KTD) in the
reporting month are summarized in Table 12
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting month
KDO CEDD projects
Contract No Project Title Site Activities
KL200901 Site Formation for Kai Tak
Cruise Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance system
7) Erection and maintenance of silt curtain
8) Construction of capping beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure
works at North Apron
1) Drainage Works
2) Watermain Works
3) Footbridge Superstructure construction
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 3
1 INTRODUCTION
Background
11 The Kai Tak Development (KTD) is located in the south-eastern part of Kowloon Peninsula
comprising the apron and runway areas of the former Kai Tak Airport and existing
waterfront areas at To Kwa Wan Ma Tau Kok Kowloon Bay Kwun Tong and Cha Kwo
Ling It covers a land area of about 328 hectares The Project also covers Kowloon Bay and
Kwun Tong Typhoon Shelter and the adjacent water bodies The general layout of the
Project is shown in Figure 1
12 Civil Engineering and Development Department (CEDD) had completed an Environmental
Impact Assessment (EIA) study for KTD under Agreement No CE 352006(CE) Kai Tak
Development Engineering Study cum Design and Construction of Advance Works ndash
Investigation Design and Construction (hereafter called ldquoSchedule 3 EIA Reportrdquo) The
Schedule 3 EIA Report was approved under Environmental Impact Assessment Ordinance
(EIAO) in March 2009
13 As recommended in the Schedule 3 EIA Report EMampA programme shall be required for
different phases of the KTD as a whole In August 2010 Cinotech Consultants Limited was
commissioned by CEDD to undertake the Environmental Monitoring and Audit (EMampA)
works for KTD Under the Contract Environmental Team (ET(KTD)) shall oversee all the
environmental issues within the Kai Tak Development (KTD) including but not limit to the
Schedule 2 Designated Projects and other work contracts
14 Cinotech Consultants Limited was commissioned by CEDD to undertake the Environmental
Monitoring and Audit (EMampA) works for KTD This is the 9th
Monthly EMampA report
summarizing the EMampA works for the Project in September 2011
Project Organizations
15 Different parties with different levels of involvement in the project organization include
bull Environmental Protection Department (The Authority)
bull Project Proponent ndash Civil Engineering and Development Department (CEDD)
bull The Engineer and the Engineerrsquos Representative (ER) ndash AECOM
bull Environmental Team (ET(KTD)) ndash Cinotech Consultants Limited (CCL)
bull Independent Environmental Checker (IEC(KTD)) ndash Allied Environmental Consultants
Limited (AEC)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 4
16 The key contacts of the Project are shown in Table 11
Table 11 Key Project Contacts
Party Role Contact Person Phone No Fax No
CEDD Project Proponent
Mr K Y SHIN 2301 1461 2301 1277
Mr William WONG 3104 2197 2301 1277
AECOM Engineerrsquos
Representative
Ms Anna CHUNG 3922 9437 2317 7609
Cinotech Environmental
Team (KTD)
Dr Priscilla Choy 2151 2089 3107 1388
Ms Ivy Tam 2151 2090
AEC
Independent
Environmental
Checker (KTD)
Ms Grace Kwok
2815 7028 2815 5399
Construction Activities undertaken during the Reporting Month
17 There are several works contracts undertaken within KTD during the reporting month In
order to collect relevant environmental information from the work contracts and incorporate
into this monthly monitoring report a survey form for monthly environmental performance
records was sent to all work contractstenants within KTD on 30 November 2010 The
survey form shall be returned by 5th each month to provide the environmental monthly
information of respective work contracts within KTD
18 Based on the returned survey form from work contracts and site observation for short term
tenancy (STT) temporary government land allocation (TGLA) during the weekly site
inspection the major site activities undertaken within Kai Tak Development (KTD) in the
reporting month are summarized in Table 12
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting month
KDO CEDD projects
Contract No Project Title Site Activities
KL200901 Site Formation for Kai Tak
Cruise Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance system
7) Erection and maintenance of silt curtain
8) Construction of capping beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure
works at North Apron
1) Drainage Works
2) Watermain Works
3) Footbridge Superstructure construction
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 4
16 The key contacts of the Project are shown in Table 11
Table 11 Key Project Contacts
Party Role Contact Person Phone No Fax No
CEDD Project Proponent
Mr K Y SHIN 2301 1461 2301 1277
Mr William WONG 3104 2197 2301 1277
AECOM Engineerrsquos
Representative
Ms Anna CHUNG 3922 9437 2317 7609
Cinotech Environmental
Team (KTD)
Dr Priscilla Choy 2151 2089 3107 1388
Ms Ivy Tam 2151 2090
AEC
Independent
Environmental
Checker (KTD)
Ms Grace Kwok
2815 7028 2815 5399
Construction Activities undertaken during the Reporting Month
17 There are several works contracts undertaken within KTD during the reporting month In
order to collect relevant environmental information from the work contracts and incorporate
into this monthly monitoring report a survey form for monthly environmental performance
records was sent to all work contractstenants within KTD on 30 November 2010 The
survey form shall be returned by 5th each month to provide the environmental monthly
information of respective work contracts within KTD
18 Based on the returned survey form from work contracts and site observation for short term
tenancy (STT) temporary government land allocation (TGLA) during the weekly site
inspection the major site activities undertaken within Kai Tak Development (KTD) in the
reporting month are summarized in Table 12
Table 12 Summary Table for Major Site Activities undertaken within KTD in the
Reporting month
KDO CEDD projects
Contract No Project Title Site Activities
KL200901 Site Formation for Kai Tak
Cruise Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance system
7) Erection and maintenance of silt curtain
8) Construction of capping beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure
works at North Apron
1) Drainage Works
2) Watermain Works
3) Footbridge Superstructure construction
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 5
4) Construction of subway extension
5) Road Works
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance
Infrastructure Works
1) Filling for public landing steps cum fireboat berth
2) Roadworks at Road TD3 and TL14
3) Construction of utility trough along Taxiway Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu Road
6) EampM works for the sewage pumping station
KL200902 Site Investigation for
Trunk Road T2 and
Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash
Kai Tak Approach
Channel and Kwun Tong
Typhoon Shelter
Improvement Works
(Phase 1)
1) Erection of Site Office
2) Dredging of Type 1 and Type 2 sediment
3) Installation of Silt Curtain
4) Pre-treatment sediment quality survey for bioremediation
KL201003 Kai Tak Development
Stage 2 Infrastructure
Works at North Apron
Area
1) Site Clearance
2) Erection of Hoarding and Fences
3) Site Office Erection
4) Excavation for Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Laying of twin rising mains by open trench
method
3) Construction of chambers manholes etc
4) Trench works pipe laying and backfilling
5) Backfilling works for pumping stations
6) Construction of superstructure of pumping
stations
7) Laying of gravity sewer by trenchless method
8) EampM works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Construction of Box Culvert bay 1A-a
4) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
5) Construction of MHA390
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 6
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
WSD project
Contract No Project Title Site Activities
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 1) Construction material storage (Portion G2)
2) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Construction 1F slab
3) Precast beam fabrication at Area B and C
4) Tree nursery
5) Relocation of hoarding
6) Temporary stockpiling of excavated material at
Area D
CLP projects
Contract No Project Title Site Activities
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation No civil activity
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable laying and jointing
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 7
EMSD projects
Contract No Project Title Site Activities
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
Development
1) Trench excavation
2) Pipe Laying
3) Construction of Jacking Pit
4) Pipe Jacking
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) Steel Sheet-piling
2) 132kV cables diversion works
3) Dewatering wells installation
4) Observation well installation
5) Excavation
6) Trench excavation including strut and waling
installation
7) King post installation
List of Temporary Government Land Allocations (TGLAs)
TGLA No Name of Occupants Site Activities
GLA-TNK 1591 CELW Civil Engineering
amp Development
Department
Works area for maintenance of equipments and
storage
GLA-TNK 1751 Housing Department Works Area and Storage Area
GLA-TNK 1636 Drainage Services
Department
Works Area
GLA-TNK 1560 Slope Maintenance
Section Lands Department
Depot area
GLA-TNK 1801 Housing Department Works and storage area (Site 1B3)
GLA-TNK 1177 Electrical and Mechanical
Services Department
Vehicle maintenance depot next to the existing
HATCL II Building
GLA-TNK 1338 Highways Department Maintenance Depot off Cargo Circuit
GLA-TNK 1635 Drainage Services
Department
Works Area
GLA-TNK 1713 Highways Department Depot Area
GLA-TNK 1709 Water Supplies
Department
Works Area
GLA-TNK 1749 Drainage Services
Department
Additional Works area
GLA-TNK 1568 Fire Services Department Driving training ground
GLA-TNK 1360 HK Police Force Storage of police water barriers and metal gates
GLA-TNK 1675 PM(K) Civil Engineering
amp Development
Department
Works Area in connection with Kai Tak
Development - Advance Infrastructure Works for
Development at the Southern Part of the Former
Runway ndash Stage 1 Works
GLA-TNK 1760 Drainage Services
Department
Site office and storage area
GLA-TNK 1646 CGELPM Civil
Engineering and
Works Area
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 8
Development Department
GLA-TNK 1608 Transport Department Works Area
GLA-TNK 1580 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1581 PM(K) Civil Engineering
amp Development
Department
Works Area
GLA-TNK 1334 Water Supplies
Department
Works Area
GLA-TNK 1144 CEPW Civil Engineering
and Development
Department
Works Area
GLA-TNK 1226
GLA-TNK 1542 Hong Kong Observatory Weather station
List of Short Term Tenancy (STT)
STT No Name of Occupants Site Activities
KX2688 Goldway Parking Ltd Car-park
KX2345 CLP Power Hong Kong
Limited
Storage of construction materials and plant
equipments
KX2662 Hong Kong Cricket
Association
Operation of Hong Kong Cricket Association
KX2628 Moral Well International
Enterprise Limited
Car-park
KX2552 Era International
Investment Limited
Car-park
KX2629 Graceful Ocean
Development Limited
Car-park
KX2261 Hong Kong Aviation Club
Ltd
Training for air traffic controllers
KX2574 Future Chinese Limited Car-park
KX2575 Nanjing Limited Car-park
KX2117 Skyhill Resources Ltd Storage of building materials
KX2109 Multi-Light Limited 1) Concrete production
2) Storage of building materials
KX2675 Wang Lee Building
Materials Trading Ltd
Operation of business in the recovery and
recycling
KX2676 Ga Shing Transport Co Operation of business in the recovery and
recycling
KX2677 Chuen Kee Metal Trading
Co Ltd
Operation of business in the recovery and
recycling
KX2678 Kin Xun Environment
Recycle Ltd
Operation of business in the recovery and
recycling
KX2569 Sureguard Logistics
Limited
Open storage of goods and dangerous goods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 9
KX2641 Citybus Limited Parking of buses
KX2642 Goldway Parking Ltd Car-park
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 10
19 The construction programme showing the inter-relationship with environmental
protectionmitigation measures are presented in Table 13
Table 13 Construction Programme Showing the Inter-Relationship with Environmental
ProtectionMitigation Measures
Construction Works Major Environmental Impact Control Measures
As mentioned in Table 12
Noise dust impact water quality
and waste generation
Sufficient watering of the
works site with active dust
emitting activities
Properly cover the
stockpiles
On-site waste sorting and
implementation of trip
ticket system
Appropriate
desiltingsedimentation
devices provided on site for
treatment before discharge
Use of quiet plant and well-
maintained construction
plant
Provide movable noise
barrier
Provide sufficient
mitigation measures as
recommended in Approved
EIA ReportLease
requirement
Summary of EMampA Requirements
110 The EMampA programme requires construction noise monitoring air quality monitoring
landscape and visual monitoring and environmental site audit The EMampA requirements for
each parameter are described in the following sections including
bull All monitoring parameters
bull Action and Limit levels for all environmental parameters
bull Event Action Plans
bull Environmental mitigation measures as recommended in the Schedule 3 EIA Report and
bull Environmental requirements in contract documents under Contract No KLN201004
111 The advice on the implementation status of environmental protection and pollution
controlmitigation measures is summarized in Section 6 of this report
112 This report presents the monitoring results observations locations equipment period
methodology and QAQC procedures of the required monitoring parameters namely air
quality and noise levels and audit works for the Project in September 2011
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 11
2 AIR QUALITY
Monitoring Requirements
21 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 1-hour and 24-hour TSP monitoring were
conducted to monitor the air quality for KTD For regular impact monitoring a sampling
frequency of at least once in every six days at all of the monitoring stations for 24-hour TSP
monitoring For 1-hour TSP monitoring the sampling frequency of at least three times in
every six days shall be undertaken when the highest dust impact occurs Appendix A shows
the established ActionLimit Levels for the environmental monitoring works
Monitoring Locations
22 Six designated monitoring stations were selected for air quality monitoring programme
Impact dust monitoring was conducted at five air quality monitoring stations namely Kai
Tak Operational Base (AM1(A)) Lee Kau Yan Memorial School (AM2) Holy Trinity
Bradbury Centre (AM3(A)) EMSD Workshops (AM4(A)) and Po Leung Kuk Ngan Po Ling
College (AM5(A)) in the reporting month Table 21 describes the air quality monitoring
locations which are also depicted in Figure 2
Table 21 Locations for Air Quality Monitoring
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
23 Table 22 summarizes the equipment used in the impact air monitoring programme Copies
of calibration certificates are attached in Appendix B
Monitoring Stations Locations Location of Measurement
AM1(A) Kai Tak Operational Base Rooftop (about 9F) Area
AM2 Lee Kau Yan Memorial
School
Rooftop (about 8F) Area
AM3(A) Holy Trinity Bradbury
Centre
Rooftop (about 8F) Area
AM4(A) EMSD Workshops Rooftop (about 6F) Area
AM5(A) Po Leung Kuk Ngan Po
Ling College Rooftop (about 10F) Area
AM6 PA 15 Site 1B4 (Planned)
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 12
Table 22 Air Quality Monitoring Equipment
Equipment Model and Make Quantity
Calibrator G25A 1
1-hour TSP Dust Meter Laser Dust Monitor ndash Model LD3B 4
HVS Sampler GMWS 2310 cw of TSP sampling inlet 5
Wind Anemometer Davis Weather Monitor II Model no 7440 1
Monitoring Parameters Frequency and Duration
24 Table 23 summarizes the monitoring parameters and frequencies of impact dust monitoring
for the whole construction period The air quality monitoring schedule for the reporting
month is shown in Appendix D
Table 23 Impact Dust Monitoring Parameters Frequency and Duration
Parameters Frequency
1-hr TSP Three times 6 days
24-hr TSP Once 6 days
Monitoring Methodology and QAQC Procedure
1-hour TSP Monitoring
Measuring Procedures
25 The measuring procedures of the 1-hour dust meters were in accordance with the
Manufacturerrsquos Instruction Manual as follows
bull The 1-hour dust meter is placed at least 13 meters above ground
bull Set POWER to ldquoONrdquo and make sure that the battery level was not flash or in low level
bull Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet
has been released
bull Push the knob at MEASURE position
bull Set timemode setting to [BG] by pushing the time setting switch Then start the
background measurement by pushing the startstop switch once It will take 6 sec to
complete the background measurement
bull Push the time setting switch to change the time setting display to [MANUAL] at the
bottom left of the liquid crystal display Finally push the startstop switch to stop the
measuring after 1 hour sampling
bull Information such as sampling date time count value and site condition were recorded
during the monitoring period
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 13
MaintenanceCalibration
26 The following maintenancecalibration was required for the direct dust meters
bull Check and calibrate the meter by HVS to check the validity and accuracy of the results
measured by direct reading method at 2-month intervals throughout all stages of the air
quality monitoring
24-hour TSP Monitoring
Instrumentation
27 High volume (HVS) samplers (Model GMWS-2310 Accu-Vol) completed with appropriate
sampling inlets were employed for 24-hour TSP monitoring The sampler was composed of
a motor a filter holder a flow controller and a sampling inlet and its performance
specification complied with that required by USEPA Standard Title 40 Code of Federation
Regulations Chapter 1 (Part 50) Moreover the HVS also met all the requirements in section
25 of the updated EMampA Manual
OperatingAnalytical Procedures
28 Operatinganalytical procedures for the operation of HVS were as follows
bull A horizontal platform was provided with appropriate support to secure the samplers
against gusty wind
bull No two samplers were placed less than 2 meters apart
bull The distance between the sampler and an obstacle such as buildings was at least twice
the height that the obstacle protrudes above the sampler
bull A minimum of 2 meters of separation from walls parapets and penthouses was required
for rooftop samples
bull A minimum of 2 meters separation from any supporting structure measured horizontally
was required
bull No furnaces or incineration flues were nearby
bull Airflow around the sampler was unrestricted
bull The sampler was more than 20 meters from the drip line
bull Any wire fence and gate to protect the sampler should not cause any obstruction during
monitoring
29 Prior to the commencement of the dust sampling the flow rate of the high volume sampler
was properly set (between 11 m3min and 14 m
3min) in accordance with the
manufacturers instruction to within the range recommended in USEPA Standard Title 40
CFR Part 50
210 For TSP sampling fiberglass filters have a collection efficiency of gt 99 for particles of 03
microm diameter were used
211 The power supply was checked to ensure the sampler worked properly On sampling the
sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter
media at the designated air monitoring station
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 14
212 The filter holding frame was then removed by loosening the four nuts and a weighted and
conditioned filter was carefully centered with the stamped number upwards on a supporting
screen
213 The filter was aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter Then the filter holding frame was tightened to the filter holder with
swing bolts The applied pressure should be sufficient to avoid air leakage at the edges
214 The shelter lid was closed and secured with the aluminum strip
215 The timer was then programmed Information was recorded on the record sheet which
included the starting time the weather condition and the filter number (the initial weight of
the filter paper can be found out by using the filter number)
216 After sampling the filter was removed and sent to the HOKLAS laboratory (Wellab Ltd) for
weighing The elapsed time was also recorded
217 Before weighing all filters were equilibrated in a conditioning environment for 24 hours
The conditioning environment temperature should be between 25degC and 30degC and not vary
by more than plusmn3degC the relative humidity (RH) should be lt 50 and not vary by more than
plusmn5 A convenient working RH is 40
MaintenanceCalibration
218 The following maintenancecalibration was required for the HVS
bull The high volume motors and their accessories were properly maintained Appropriate
maintenance such as routine motor brushes replacement and electrical wiring checking
were made to ensure that the equipment and necessary power supply are in good working
condition
bull High volume samplers were calibrated at bi-monthly intervals using G25A Calibration
Kit throughout all stages of the air quality monitoring
Results and Observations
219 All 1-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
220 All 24-hour TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
221 The air temperature precipitation and the relative humidity data was obtained from Hong
Kong Observatory where the wind speed and wind direction were recorded by the installed
Wind Anemometer set at rooftop (about 9F) of Kai Tak Operational Base The location is
shown in Figure 4 These weather information for the reporting month is summarized in
Appendix C
222 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring
results are shown in Appendices E and F respectively
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 15
223 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the air quality monitoring
224 According to our field observations the major dust source identified at the designated air
quality monitoring stations are as follows
Station Major Dust Source
AM1(A) ndash Kai Tak Operational Base Road Traffic Dust
Exposed site area
Excavation works
Site vehicle movement
AM2 ndash Lee Kau Yan Memorial School Road Traffic Dust
Exposed site area and open stockpiles
Excavation works
Site vehicle movement
Other construction site (Tung Tau Estate Ph9)
which behind Lee Kau Yan Memorial School
AM3(A) - Holy Trinity Bradbury
Centre
Road Traffic Dust
Exposed site area
Site vehicle movement
AM4(A) ndash EMSD Workshops Sand Depot
Concrete Batching Plant
AM5(A) ndash Po Leung Kuk Ngan Po
Ling College
Road Traffic Dust
Loadingunloading activities and excavation
works at the site (Contract No 1WSD08(K))
facing Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 16
3 NOISE
Monitoring Requirements
31 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 construction noise monitoring was
conducted to monitor the construction noise arising from the construction activities within
KTD The regular monitoring frequency for each monitoring station shall be on a weekly
basis and conduct one set of measurements between 0700 and 1900 hours on normal
weekdays Appendix A shows the established Action and Limit Levels for the
environmental monitoring works
Monitoring Locations
32 Eleven designated monitoring stations were selected for noise monitoring programme Noise
monitoring was conducted at nine designated monitoring stations (M1 M2 M3 M4(A) M5
M6(A) M7 M8 and M9) in the reporting month Figure 3 shows the locations of these
stations
Table 31 Noise Monitoring Stations
Monitoring Stations Locations Location of Measurement
M1 Buddhist Chi King Primary School 7F Sport Area
M2 SKH Kowloon Bay Kei Lok
Primary School 7F Podium
M3 Rhythm Garden 1F Podium
M4(A) Kai Tak Operational Base Rooftop (about 9F) Area
M5 Lee Kau Yan Memorial School Rooftop (about 7F) Area
M6(A) Kowloon City District Kaifong
Association Rooftop (about 6F) Area
M7 Holy Carpenter Primary School Rooftop (about 7F) Area
M8 CCC Kei To Secondary School Rooftop (about 8F) Area
M9 Po Leung Kuk Ngan Po Ling
College Staircase Area (about 9F)
M10 Site 1B1 (Planned) -
M11 Site 1B4 (Planned) -
Remarks BaselineImpact monitoring will be conducted when the premise is occupied or instructed by
Engineer
Monitoring Equipment
33 Table 32 summarizes the noise monitoring equipment Copies of calibration certificates are
provided in Appendix B
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 17
Table 32 Noise Monitoring Equipment
Equipment Model and Make Qty
Integrating Sound Level Meter SVAN 955 amp 957 4
Calibrator SVAN 30A 2
Monitoring Parameters Frequency and Duration
34 Table 33 summarizes the monitoring parameters frequency and total duration of monitoring
The noise monitoring schedule is shown in Appendix D
Table 33 Noise Monitoring Parameters Frequency and Duration
Monitoring
Stations Parameter Period Frequency Measurement
M1
M2
M3
M4(A)
M5
M6(A)
M7
M8
M9
L10(30 min)
dB(A)
L90(30 min)
dB(A)
Leq(30 min)
dB(A)
0700-1900 hrs on normal
weekdays
Once per
week Faccedilade
Monitoring Methodology and QAQC Procedures
bull The Sound Level Meter was set on a tripod at a height of 12 m above the ground
bull The battery condition was checked to ensure the correct functioning of the meter
bull Parameters such as frequency weighting the time weighting and the measurement time
were set as follows
mdash frequency weighting A
mdash time weighting Fast
mdash time measurement 30 minutes
bull Prior to and after each noise measurement the meter was calibrated using a Calibrator
for 940 dB at 1000 Hz If the difference in the calibration level before and after
measurement was more than 10 dB the measurement would be considered invalid and
repeat of noise measurement would be required after re-calibration or repair of the
equipment
bull The wind speed was frequently checked with the portable wind meter
bull At the end of the monitoring period the Leq L90 and L10 were recorded In addition site
conditions and noise sources were recorded on a standard record sheet
bull Noise measurement was paused temporarily during periods of high intrusive noise if
possible and observation was recorded when intrusive noise was not avoided
bull Noise monitoring was cancelled in the presence of fog rain and wind with a steady
speed exceeding 5 ms or wind with gusts exceeding 10 ms
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 18
Maintenance and Calibration
35 The microphone head of the sound level meter and calibrator were cleaned with a soft cloth
at quarterly intervals
36 The sound level meter and calibrator were checked and calibrated at yearly intervals
37 Immediately prior to and following each noise measurement the accuracy of the sound level
meter shall be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency Measurements may be accepted as valid only if the calibration levels
from before and after the noise measurement agree to within 10 dB
Results and Observations
38 Noise monitoring at the nine designated locations was conducted as scheduled in the
reporting month
39 The summary of exceedance record in reporting month is shown in Appendix H No
exceedance was recorded for the noise monitoring
310 All the Corrected Noise Levels (CNLs) reported in this report were adjusted with the
corresponding baseline level (ie Measured Leq ndash Baseline Leq = CNL) in order to facilitate
the interpretation of the noise exceedance The baseline noise level and the Noise Limit
Level at each designated noise monitoring station are presented in Table 34
311 Noise monitoring results and graphical presentations are shown in Appendix G
312 The major noise source identified at the designated noise monitoring stations are as follows
Monitoring
Stations Locations
Major Noise Source
M1 Buddhist Chi King Primary School Traffic Noise
Site vehicle movement
Excavation works M2 SKH Kowloon Bay Kei Lok Primary School
M3 Rhythm Garden Traffic Noise
M4(A) Kai Tak Operational Base
Traffic Noise
Site vehicle movement
Excavation works
M5 Lee Kau Yan Memorial School
Traffic Noise
Site vehicle movement
Excavation works
M6(A) Kowloon City District Kaifong Association Traffic Noise
M7 Holy Carpenter Primary School Road and marine traffic Noise
M8 CCC Kei To Secondary School Road and marine traffic Noise
Excavation work and
loadingunloading activities at the
site (Contract No 1WSD08(K))
facing the schools
M9 Po Leung Kuk Ngan Po Ling College
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 19
Table 34 Baseline Noise Level and Noise Limit Level for Monitoring Stations
Station Baseline Noise Level dB (A) Noise Limit Level
dB (A)
M1 644 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M2
613 (at 0700 ndash 1900 hrs on normal
weekdays)
M3 724 ndash 741 (Background Noise Level
during noise measurement)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M4(A) 658 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M5 767 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M6(A) 705 (at 0700 ndash 1900 hrs on normal
weekdays)
75 (at 0700 ndash 1900 hrs
on normal weekdays)
M7 639 (at 0700 ndash 1900 hrs on normal
weekdays)
70 (at 0700 ndash 1900 hrs
on normal weekdays)
M8 687 (at 0700 ndash 1900 hrs on normal
weekdays)
M9 619 (at 0700 ndash 1900 hrs on normal
weekdays)
() Noise Limit Level is 65 dB(A) during school examination periods
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 20
4 COMPARISON OF EMampA RESULTS WITH EIA PREDICTIONS
41 The EMampA data was compared with the EIA predictions as summarized in 41 to 43
Table 41 Comparison of 1-hr TSP data with EIA predictions
Station Predicted 1-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
192 298 943
AM2 ndash Lee Kau Yan
Memorial School
290 312 1014
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
217 247 965
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
246 258 1035
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
159 221 918
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 21
Table 42 Comparison of 24-hr TSP data with EIA predictions
Station Predicted 24-hr TSP conc
Scenario1 (Mid
2009 to Mid 2013)
microgm3
Scenario2 (Mid
2013 to Late
2016) microgm3
Reporting Month
(Sep 11) microgm3
AM1(A) ndash Kai Tak
Operational Base
(Alternative station for
Rhythm Garden)
121 156 613
AM2 ndash Lee Kau Yan
Memorial School
145 169 966
AM3(A) - Holy Trinity
Bradbury Centre
(Alternative station for
Sky Tower)
106 138 770
AM4(A) ndash EMSD
Workshops
(Alternative station for
Grand Waterfront)
143 152 938
AM5(A) ndash Po Leung
Kuk Ngan Po Ling
College (Alternative
station for CCC Kei
To Secondary School)
103 128 648
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 22
Table 43 Comparison of Noise Monitoring Data with EIA predictions
42 The 1-hour and 24-hour average TSP concentration in the reporting month were well below
the prediction in the approved Environmental Impact Assessment (EIA) Report and no
ActionLimit Level exceedance was recorded
43 The noise monitoring results in the reporting month was also within the range of predicted
mitigated construction noise levels in the EIA report except M5 The noise data at M5
exceeds the prediction of mitigated scenario in EIA report but did not exceed the baseline
level
44 The discrepancy between the EMampA data and EIA predictions is considered due to road
traffic noise from Prince Edward Road East which is the major noise source during the
monitoring
Stations
Predicted Mitigated
Construction Noise Levels
during Normal Working
Hour (Leq (30min) dB(A))
Reporting Month (Sep 11)
Leq (30min) dB(A)
M1 - Buddhist Chi King
Primary School 51 ndash 68 618 ndash 646
M2 - SKH Kowloon
Bay Kei Lok Primary
School
51 ndash 70 663 ndash 676
M3 ndash Rhythm Garden 45 ndash 75 733 ndash 748
M4(A) - Kai Tak
Operational Base
(Alternative station for
Cognitio College)
47 ndash 75 525 ndash 658
M5 - Lee Kau Yan
Memorial School 47 ndash 74 739 ndash 750
M6(A) - Kowloon City
District Kaifong
Association ( Alternative
station for South
Mansion)
47 ndash 78 651 ndash 676
M7 - Holy Carpenter
Primary School 47 ndash 86 616 ndash 643
M8 - CCC Kei To
Secondary School 45 ndash 68 637 ndash 652
M9 - Po Leung Kuk Ngan
Po Ling College 44 ndash 70 577 ndash 610
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 23
5 LANDSCAPE OF VISUAL
Monitoring Requirements
51 According to EMampA Manual of the Kai Tak Development EIA Study and contract
requirement under Contract No KLN201004 ET(KTD) shall monitor and audit the
contractorrsquos operation during the construction period on a weekly basis and to report on the
contractorrsquos compliance
Results and Observations
52 Site audits were carried out on a weekly basis to monitor and audit the timely
implementation of landscape and visual mitigation measures within KTD The summaries
of site audits are attached in Appendix I
53 No non-compliance of the landscape and visual impact was recorded in the reporting month
54 Should non-compliance of the landscape and visual impact occur action in accordance with
the action plan presented in Appendix J shall be performed
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 24
6 ENVIRONMENTAL AUDIT
Site Audits
61 Site audits were carried out on a weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures in the Project site
The summaries of site audits are attached in Appendix I
62 Site audits were conducted on 2nd
9th
16th
19th
and 30th
September 2011 in the reporting
month Monthly joint site inspection with IEC and the Engineerrsquos Representative was
conducted on 30th
September 2011
Review of Environmental Monitoring Procedures
63 The monitoring works conducted by the monitoring team were inspected regularly The
following observations have been recorded for the monitoring works
Air Quality Monitoring
bull The monitoring team recorded all observations around the monitoring stations within
and outside the construction site
bull The monitoring team recorded the temperature and weather conditions on the monitoring
days
Noise Monitoring
bull The monitoring team recorded all observations around the monitoring stations which
might affect the monitoring result
bull Major noise sources were identified and recorded Other intrusive noise attributing to the
result was trimmed off by pausing the monitoring temporarily
Status of Waste Management
64 The amount of wastes generated by the major site activities of the work contracts within
KTD during the reporting month is shown in Appendix M
65 In respect of the dump truck cover the Contractor of Work Contracts within KTD is advised
to take record photos and inspection to ensure that all dump trucks have fully covered the
skip before leaving the site
Implementation Status of Environmental Mitigation Measures
66 ET (KTD) weekly site inspections were carried out during the reporting month and the
observations of respective works within KTD are shown in Appendix I
67 Based on the major observations recorded during the regular site audit in the reporting
month the Contractor was advised
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 25
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
dust generation works
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source
Summary of Mitigation Measures Implemented
68 An updated summary of the EMIS is provided in Appendix K
Implementation Status of Event Action Plans
69 The Event Action Plans for air quality noise and landscape and visual are presented in
Appendix J
1-hr TSP Monitoring
610 No ActionLimit Level exceedance was recorded in the reporting month
24-hr TSP Monitoring
611 No ActionLimit Level exceedance was recorded in the reporting month
24-hr RSP Monitoring
612 No ActionLimit Level exceedance was recorded in the reporting month
Construction Noise
613 No ActionLimit Level exceedance was recorded for construction noise
Landscape and visual
614 No non-compliance was recorded in the reporting month
Summary of Complaint Warning Notification of any Summons and Successful
Prosecution
615 The summaries of environmental complaint warning summon and notification of successful
prosecution for the Project is presented in Appendix L
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 26
7 FUTURE KEY ISSUES
71 Major site activities undertaken within (KTD) for the coming two month are summarized in
Table 71
Table 71 Summary Table for Site Activities undertaken within KTD for Coming Two
Month
KDO CEDD projects
Contract No Project Title Site Activities
October and November 2011
KL200901 Site Formation for Kai Tak Cruise
Terminal
1) Piling Works
2) Dredging Works
3) Installation of temporary steel bracing
4) Sorting of CampD material from existing seawall
5) Seawall Removal and Reconstruction
6) Impact water quality monitoringsurveillance
system
7) Erection and maintenance of silt curtain
8) Construction of Capping Beam
9) Quay Deck Construction
KL200809 Stage 1 Infrastructure works at
North Apron
1) Drainage Works
2) Road Works
3) Footbridge Superstructure construction
4) Watermain Works
5) Transplanting
6) Enhancement of existing subways
7) Construction of subway extension
KL200807 Stage 1 Advance Infrastructure
Works
1) Filling for public landing steps cum fireboat
berth
2) Pavement works at Road TD3 and TL14
3) Construction of utility trough along Taxiway
Bridge
4) Watermain laying at Hoi Bun Road
5) Junction improvement works at Wang Chiu
Road
6) EampM works for the sewage pumping station
7) Drainage works of the access track road to
public landing steps
KL200902 Site Investigation for Trunk Road
T2 and Infrastructure at South
Apron (Stage 1)
1) Instrument monitoring
KL201002 Kai Tak Development ndash Kai Tak
Approach Channel and Kwun
Tong Typhoon Shelter
Improvement Works (Phase 1)
1) Dredging of Type 1 and Type 2 sediment
2) Site trail for disposal of Type 3 sediment
3) Dredging of Type 3 sediment
4) General water quality monitoring
5) Pre-treatment sediment quality survey for
bioremediation
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 27
6) Optimization trial for bioremediation
7) Odour Patrol
KL201003 Kai Tak Development Stage 2
Infrastructure Works at North
Apron Area
1) Erection of Hoarding and Fences
2) Erection of Site Offices
3) Minor Road Works
4) Box Culvert Construction
CEO CEDD project
Contract No Project Title Site Activities
October and November 2011
CV200703 Development at Anderson Road Disposal of inert CampD material at Kai Tak
DSD project
Contract No Project Title Site Activities
October and November 2011
DC200812 Sewage Interception Scheme in
Kowloon City
1) Construction of substructure of pumping stations
2) Trench works pipe laying and backfilling
3) Laying of gravity sewer by trenchless method
4) Construction of chambers and manholes
5) EampM works for pumping stations
6) Backfilling works for pumping stations
7) Construction of superstructure of pumping
stations
8) Laying of twin rising mains by open trench
method
9) Resurfacing of flexible pavement
10) Finishing works for pumping stations
DC201003
Kai Tak Nullah Improvement
Works at Prince Edward Road
East
1) Maintain Engineerrsquos Principal Office
2) Maintain Contractorrsquos Site Office and Site
Compound
3) Stockpile excavated CampD waste material of
Prince Edward Road East and Choi Hung Road
4) Construction of Box Culvert bay 1A-a
5) Construction of MHA390
6) Pipe jacking at MHA390
DC200921 Provision of Interception
Facilities at Jordan Valley Box
Culvert
1) Excavation
2) Steel Fixing
3) Formworks
4) Concreting
HD projects
Contract No Project Title Site Activities
October and November 2011
20090097 Public Rental Housing
Development at Kai Tak Site 1A
1) Construction of Superstructure (6 blocks)
2) External Works
20090006 Public Rental Housing
Development at Kai Tak Site 1B
1) Construction of Substructure works
2) Construction of Superstructure works
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 28
WSD project
Contract No Project Title Site Activities
October and November 2011
3WSD08 Replacement and Rehabilitation
of Water Mains Stages 2 amp 3
1) Site Office of the Contractor
2) Storage of water works material
3) Storage and sorting of CampD materials
6WSD08 3) Construction material storage (Portion G2)
1) CampD material storage (Portion G4)
7WSD08 1) Transportation and storage of pipe works
material (Portion BX1)
2) Transportation and sorting of construction waste
(Portion BX1)
3) Fabrication of special pipe fittings (Portion B1)
8WSD08 1) CampD materials storage (Portion T1)
2) Pipe materials storage (Portion T2)
ArchSD project
Contract No Project Title Site Activities
October and November 2011
SS W 303 Kai Tak Cruise Terminal Building
and Ancillary Facilities
1) Construction pile caps
2) Testing for Large diameter bored piles
3) ELS excavation and pile caps
4) Mobilization and set up concrete pre-cast yard
5) Tree nursery
6) Precast beam fabrication at Area B and C
7) Welding capping plate amp dowel bar to H-piles
8) Delivery of pre-cast slabs from Mainland China
to Hong Kong
9) Upper floor column construction
10) Temporary stockpiling to excavated material at
area D
11) Construction 1F slab
CLP projects
Contract No Project Title Site Activities
October and November 2011
Kai Tak Cruise Terminal Cable
Tunnel
No civil activity
Eastern Road Substation
CKL-KCT circuit
1amp2
CLPP (132kV cable installation) 132kV cable installation
EMSD projects
Contract No Project Title Site Activities
October and November 2011
1016EM10 Chilled Water Pipe Laying Works
at North Apron Area for District
Cooling System at Kai Tak
1) Trial pit excavation
2) Pipe Laying
3) Construction of Jacking Pit
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 29
Development 4) Construction of Value Chamber
5) Pipe Jacking
6) Pipe Jacking at Portion B amp C
7) Construction of VC1
1017EM10 Design-Build-Operate a District
Cooling System (Phase II Works)
at Kai Tak Development
1) King Posts Installation
2) Dewatering Well installation
3) Pump Test
4) Excavation
5) Steel Sheet-piling works
6) Trench excavation including strut and waling
installation
7) Steel pipe laying and connection
Key Issues for the Coming Month
72 Key environmental issues in the coming month include
bull Runoff from exposed slope
bull Wastewater and runoff discharge from site
bull Regular removal of silt mud and sand along u-channels and sedimentation tanks
bull Review and implementation of temporary drainage system for the surface runoff
bull Noise from operation of the equipment especially for rock-breaking activities piling works
and machinery on-site
bull Dust generation from stockpiles of dusty materials exposed site area excavation works and
rock breaking activities
bull Watering for dust generating activity and on haul road
bull Proper storage of construction materials on site
bull Storage of chemicalsfuel and chemical wastewaste oil on site
bull Accumulation of general and construction waste on site
73 The tentative program of major site activities and the impact prediction and control
measures for the coming two months ie October 2011 to November 2011 are summarized
as follows
Construction Works Major Impact
Prediction
Control Measures
Air quality impact
(dust)
a) Frequent watering of haul road and unpavedexposed
areas
b) Frequent watering or covering stockpiles with tarpaulin or
similar means and
c) Watering of any earth moving activities
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 30
Construction Works Major Impact
Prediction
Control Measures
As mentioned in Table
71
Water quality
impact (surface
run-off)
d) Diversion of the collected effluent to de-silting facilities for
treatment prior to discharge to public storm water drains
e) Provision of adequate de-silting facilities for treating
surface run-off and other collected effluents prior to discharge
f) Provision of perimeter protection such as sealing of
hoarding footings to avoid run-off from entering the
existing storm water drainage system via public road and
g) Provision of measures to prevent discharge into the stream
Noise Impact h) Scheduling of noisy construction activities if necessary to
avoid persistent noisy operation
i) Controlling the number of plants use on site
j) Regular maintenance of machines and
k) Use of acoustic barriers if necessary
Monitoring Schedule for the Next Month
74 The tentative environmental monitoring schedules for the next month are shown in
Appendix D
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 31
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
81 Environmental monitoring works were performed in the reporting month and all monitoring
results were checked and reviewed
1-hr TSP Monitoring
82 All 1-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
24-hr TSP Monitoring
83 All 24-hr TSP monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Construction Noise Monitoring
84 All construction noise monitoring was conducted as scheduled in the reporting month No
ActionLimit Level exceedance was recorded
Landscape and visual
85 No non-compliance was recorded in the reporting month
Complaint and Prosecution
86 No environmental complaints and environmental prosecution were received in the reporting
month
Recommendations
87 According to the environmental audit performed in the reporting month the following
recommendations were made
Air Quality Impact
bull To prohibit any open burning on site
bull To regularly maintain the quality of machinery and vehicles on site
bull To implement dust suppression measures on all haul roads stockpiles dry surfaces and
excavation works
bull To provide hoarding along the entire length of that portion of the site boundary
Noise Impact
bull To inspect the noise sources inside the site
bull To space out noisy equipment and position the equipment as far away as possible from
Civil Engineering and Development Department Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Monthly EMampA Report ndash September 2011
MA0040MonthlyRpt_111019_v10 Cinotech 32
sensitive receivers
bull To provide temporary noise barriers for operations of noisy equipment near the noise
sensitive receivers in an appropriate location
Water Impact
bull To prevent any surface runoff discharge into any stream course
bull To review and implement temporary drainage system
bull To identify any wastewater discharges from site
bull To ensure properly maintenance for de-silting facilities
bull To clear the silt and sediment in the sedimentation tanks
bull To review the capacity of de-silting facilities for discharge
bull To divert all the water generated from construction site to de-silting facilities with enough
handling capacity before discharge
bull To avoid accumulation of stagnant and ponding water on site
WasteChemical Management
bull To check for any accumulation of waste materials or rubbish on site
bull To ensure the performance of sorting of CampD materials at source (during generation)
bull To carry out inspection of dump truck at site exit to ensure inert and non-inert CampD
materials are properly segregated before removing off site
bull To avoid any discharge or accidental spillage of chemical waste or oil directly from the
site
bull To avoid improper handling or storage of oil drum on site
Landscape and Visual
bull To protect the existing trees to be retained
bull To transplant the trees unavoidably affected by the works
bull To control of night-time lighting
bull To provide decorative screen hoarding
bull To complete landscape works at site area as early as possible
FIGURES
Title Scale Project
No
Date Figure
Feb-11 1Site Layout Plan
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM1(A)
AM2
AM3(A)
Title Scale Project
No
Date Figure
Feb-11 2Location of Air Quality Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
AM5(A)
AM4(A)
AM1(A)
AM2
AM3(A)
M1
M2
M3M4(A)
M5
M6(A)
M7
Title Scale Project
No
Date Figure
Feb-11 3Location of Noise Monitoring Stations
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
M1
M2
M3M4(A)
M5
M6(A)
M7
M8
M9
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Title Scale Project
No
Date Figure
Feb-11 4Location of Wind Data Monitoring Equipment
MA0040Environmental Monitoring Works for Kai Tak Development
Contract No KLN201004NTS
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
Wind Data Monitoring Equipment set at
Kai Tak Operational Base
Anemometer Station from The Hong
Kong Observatory
APPENDIX A
ACTION AND LIMIT LEVELS
Appendix A
Appendix A - Action and Limit Levels
Table A-1 Action and Limit Levels for 1-Hour TSP
Table A-2 Action and Limit Levels for 24-Hour TSP
Table A-3 Action and Limit Levels for Construction Noise
Remarks If works are to be carried out during restricted hours the conditions stipulated in the Construction
Noise Permit (CNP) issued by the Noise Control Authority have to be followed 70dB(A) and
65dB(A) for schools during normal teaching periods and school examination periods
respectively
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 342
500
AM2 346
AM3(A) 351
AM4(A) 371
AM5(A) 345
Location Action Level microgm3 Limit Level microgm
3
AM1(A) 159
260
AM2 157
AM3(A) 167
AM4(A) 187
AM5(A) 156
Time Period Action Level Limit Level
0700-1900 hrs on normal weekdays
When one
documented
complaint is received
75 dB(A)
70dB(A)65dB(A)
APPENDIX B
COPIES OF CALIBRATION
CERTIFCATES
APPENDIX C
WEATHER INFORMATION
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 1 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
1 September 2011 274 ndash 301 65 ndash 82 01
2 September 2011 272 ndash 312 63 ndash 84 0
3 September 2011 258 ndash 307 79 ndash 97 226
4 September 2011 266 ndash 315 72 ndash 91 18
5 September 2011 277 ndash 322 71 ndash 88 0
6 September 2011 279 ndash 319 69 ndash 85 0
7 September 2011 270 ndash 320 67 ndash 90 02
8 September 2011 279 ndash 322 69 ndash 87 Trace
9 September 2011 278 ndash 328 60 ndash 82 Trace
10 September 2011 266 ndash 317 58 ndash 94 26
11 September 2011 262 ndash 308 72 ndash 96 204
12 September 2011 259 ndash 324 68 ndash 96 06
13 September 2011 261 ndash 326 57 ndash 94 27
14 September 2011 26 ndash 327 58 ndash 94 27
15 September 2011 241 ndash 320 67 ndash 96 109
16 September 2011 268 ndash 323 69 ndash 92 10
17 September 2011 272 ndash 328 65 ndash 90 02
18 September 2011 274 ndash 299 76 ndash 91 05
19 September 2011 253 ndash 317 69 - 95 161
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
I General Information
MA0040Weather Conditions C - 2 Cinotech
Date Mean Air
Temperature (degdegdegdegC)
Mean Relative
Humidity ()
Precipitation
(mm)
20 September 2011 249 ndash 276 68 ndash 85 Trace
21 September 2011 232 ndash 277 63 ndash 73 0
22 September 2011 239 ndash 269 63 ndash 74 Trace
23 September 2011 234 ndash 275 65 ndash 86 03
24 September 2011 242 ndash 274 65 ndash 78 Trace
25 September 2011 239 ndash 262 69 ndash 96 42
26 September 2011 251 ndash 308 67 ndash 86 02
27 September 2011 262 ndash 308 67 ndash 89 Trace
28 September 2011 262 ndash 313 58 ndash 88 25
29 September 2011 253 ndash 282 81 ndash 95 308
30 September 2011 270 ndash 289 83 ndash 94 27
The above information was extracted from the daily weather summary by Hong Kong Observatory
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 3 Cinotech
Date Time Wind Speed ms Direction
1-Sep-2011 000 23 NE
1-Sep-2011 100 2 NE
1-Sep-2011 200 16 ENE
1-Sep-2011 300 19 ENE
1-Sep-2011 400 17 NE
1-Sep-2011 500 15 ESE
1-Sep-2011 600 16 NE
1-Sep-2011 700 16 NE
1-Sep-2011 800 18 SSE
1-Sep-2011 900 23 ENE
1-Sep-2011 1000 25 NE
1-Sep-2011 1100 31 S
1-Sep-2011 1200 33 NE
1-Sep-2011 1300 32 SW
1-Sep-2011 1400 32 SW
1-Sep-2011 1500 3 WNW
1-Sep-2011 1600 32 SSW
1-Sep-2011 1700 32 SSE
1-Sep-2011 1800 25 W
1-Sep-2011 1900 26 NW
1-Sep-2011 2000 25 NE
1-Sep-2011 2100 24 ENE
1-Sep-2011 2200 22 ESE
1-Sep-2011 2300 2 ESE
2-Sep-2011 000 18 NE
2-Sep-2011 100 2 NE
2-Sep-2011 200 22 NE
2-Sep-2011 300 18 NE
2-Sep-2011 400 19 NE
2-Sep-2011 500 18 ENE
2-Sep-2011 600 16 SE
2-Sep-2011 700 16 ESE
2-Sep-2011 800 13 ESE
2-Sep-2011 900 19 SSE
2-Sep-2011 1000 21 SSE
2-Sep-2011 1100 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 4 Cinotech
2-Sep-2011 1200 31 NNE
2-Sep-2011 1300 29 NNE
2-Sep-2011 1400 34 NNE
2-Sep-2011 1500 31 ESE
2-Sep-2011 1600 25 SSE
2-Sep-2011 1700 21 ENE
2-Sep-2011 1800 23 NE
2-Sep-2011 1900 19 NE
2-Sep-2011 2000 19 NE
2-Sep-2011 2100 23 NE
2-Sep-2011 2200 25 NE
2-Sep-2011 2300 23 ESE
3-Sep-2011 000 24 NNE
3-Sep-2011 100 26 NE
3-Sep-2011 200 23 SE
3-Sep-2011 300 23 SE
3-Sep-2011 400 23 SE
3-Sep-2011 500 23 ENE
3-Sep-2011 600 18 ESE
3-Sep-2011 700 22 NE
3-Sep-2011 800 21 ENE
3-Sep-2011 900 2 ENE
3-Sep-2011 1000 24 ENE
3-Sep-2011 1100 22 NE
3-Sep-2011 1200 26 ENE
3-Sep-2011 1300 29 ENE
3-Sep-2011 1400 32 SW
3-Sep-2011 1500 34 SSW
3-Sep-2011 1600 34 ENE
3-Sep-2011 1700 29 NNE
3-Sep-2011 1800 31 NNE
3-Sep-2011 1900 25 W
3-Sep-2011 2000 25 WNW
3-Sep-2011 2100 23 SW
3-Sep-2011 2200 25 WSW
3-Sep-2011 2300 2 W
4-Sep-2011 000 33 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 5 Cinotech
4-Sep-2011 100 35 W
4-Sep-2011 200 29 WSW
4-Sep-2011 300 26 SW
4-Sep-2011 400 27 SW
4-Sep-2011 500 28 WNW
4-Sep-2011 600 26 WNW
4-Sep-2011 700 25 SSW
4-Sep-2011 800 29 W
4-Sep-2011 900 32 SW
4-Sep-2011 1000 36 WNW
4-Sep-2011 1100 43 WNW
4-Sep-2011 1200 41 WSW
4-Sep-2011 1300 42 SW
4-Sep-2011 1400 4 WSW
4-Sep-2011 1500 41 WSW
4-Sep-2011 1600 32 SSW
4-Sep-2011 1700 32 WSW
4-Sep-2011 1800 27 WSW
4-Sep-2011 1900 23 SW
4-Sep-2011 2000 21 W
4-Sep-2011 2100 18 SW
4-Sep-2011 2200 23 SW
4-Sep-2011 2300 22 SW
5-Sep-2011 000 25 WSW
5-Sep-2011 100 28 SW
5-Sep-2011 200 29 SW
5-Sep-2011 300 25 SSW
5-Sep-2011 400 3 WNW
5-Sep-2011 500 3 SSW
5-Sep-2011 600 29 WSW
5-Sep-2011 700 29 WSW
5-Sep-2011 800 32 SW
5-Sep-2011 900 36 NW
5-Sep-2011 1000 37 SW
5-Sep-2011 1100 32 WSW
5-Sep-2011 1200 38 S
5-Sep-2011 1300 41 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 6 Cinotech
5-Sep-2011 1400 38 SW
5-Sep-2011 1500 4 WSW
5-Sep-2011 1600 4 SSW
5-Sep-2011 1700 4 WSW
5-Sep-2011 1800 38 SSW
5-Sep-2011 1900 32 SW
5-Sep-2011 2000 34 SSW
5-Sep-2011 2100 35 W
5-Sep-2011 2200 34 WSW
5-Sep-2011 2300 32 W
6-Sep-2011 000 32 WSW
6-Sep-2011 100 36 SW
6-Sep-2011 200 37 WSW
6-Sep-2011 300 38 SSW
6-Sep-2011 400 36 WSW
6-Sep-2011 500 32 WSW
6-Sep-2011 600 29 WSW
6-Sep-2011 700 29 SW
6-Sep-2011 800 3 SW
6-Sep-2011 900 31 SW
6-Sep-2011 1000 3 WSW
6-Sep-2011 1100 37 SSE
6-Sep-2011 1200 36 SW
6-Sep-2011 1300 4 SW
6-Sep-2011 1400 34 SW
6-Sep-2011 1500 36 SSW
6-Sep-2011 1600 36 WSW
6-Sep-2011 1700 34 SW
6-Sep-2011 1800 3 SSW
6-Sep-2011 1900 32 SSW
6-Sep-2011 2000 32 SSW
6-Sep-2011 2100 29 SW
6-Sep-2011 2200 34 SW
6-Sep-2011 2300 32 SSW
7-Sep-2011 000 31 SSW
7-Sep-2011 100 34 SW
7-Sep-2011 200 31 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 7 Cinotech
7-Sep-2011 300 31 W
7-Sep-2011 400 29 SSW
7-Sep-2011 500 29 W
7-Sep-2011 600 26 W
7-Sep-2011 700 2 N
7-Sep-2011 800 23 WNW
7-Sep-2011 900 23 WNW
7-Sep-2011 1000 25 SW
7-Sep-2011 1100 24 SW
7-Sep-2011 1200 23 WSW
7-Sep-2011 1300 2 SSW
7-Sep-2011 1400 2 SW
7-Sep-2011 1500 24 W
7-Sep-2011 1600 27 WSW
7-Sep-2011 1700 27 NE
7-Sep-2011 1800 25 N
7-Sep-2011 1900 25 W
7-Sep-2011 2000 17 W
7-Sep-2011 2100 16 SSW
7-Sep-2011 2200 18 W
7-Sep-2011 2300 16 WSW
8-Sep-2011 000 12 WSW
8-Sep-2011 100 13 WSW
8-Sep-2011 200 14 WSW
8-Sep-2011 300 13 NNW
8-Sep-2011 400 11 NW
8-Sep-2011 500 11 WSW
8-Sep-2011 600 14 WNW
8-Sep-2011 700 16 WNW
8-Sep-2011 800 18 WSW
8-Sep-2011 900 21 WNW
8-Sep-2011 1000 29 WSW
8-Sep-2011 1100 24 SW
8-Sep-2011 1200 25 W
8-Sep-2011 1300 26 W
8-Sep-2011 1400 3 SSW
8-Sep-2011 1500 31 SW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 8 Cinotech
8-Sep-2011 1600 27 NW
8-Sep-2011 1700 2 SW
8-Sep-2011 1800 2 NW
8-Sep-2011 1900 2 WSW
8-Sep-2011 2000 18 WNW
8-Sep-2011 2100 2 SSW
8-Sep-2011 2200 16 SW
8-Sep-2011 2300 13 SW
9-Sep-2011 000 16 SSW
9-Sep-2011 100 17 W
9-Sep-2011 200 14 W
9-Sep-2011 300 15 W
9-Sep-2011 400 14 ENE
9-Sep-2011 500 12 NE
9-Sep-2011 600 11 W
9-Sep-2011 700 12 WNW
9-Sep-2011 800 14 ESE
9-Sep-2011 900 22 NW
9-Sep-2011 1000 3 WNW
9-Sep-2011 1100 32 W
9-Sep-2011 1200 27 WSW
9-Sep-2011 1300 28 W
9-Sep-2011 1400 22 N
9-Sep-2011 1500 23 NW
9-Sep-2011 1600 19 NNE
9-Sep-2011 1700 21 WNW
9-Sep-2011 1800 19 WNW
9-Sep-2011 1900 15 W
9-Sep-2011 2000 1 W
9-Sep-2011 2100 08 NNE
9-Sep-2011 2200 08 ESE
9-Sep-2011 2300 07 NE
10-Sep-2011 000 07 WNW
10-Sep-2011 100 09 WNW
10-Sep-2011 200 14 WNW
10-Sep-2011 300 1 ESE
10-Sep-2011 400 1 ESE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 9 Cinotech
10-Sep-2011 500 12 WNW
10-Sep-2011 600 16 ENE
10-Sep-2011 700 15 ENE
10-Sep-2011 800 14 NNE
10-Sep-2011 900 17 NNE
10-Sep-2011 1000 2 N
10-Sep-2011 1100 27 ENE
10-Sep-2011 1200 28 ENE
10-Sep-2011 1300 33 ENE
10-Sep-2011 1400 34 ENE
10-Sep-2011 1500 32 ENE
10-Sep-2011 1600 32 NE
10-Sep-2011 1700 38 ENE
10-Sep-2011 1800 26 NE
10-Sep-2011 1900 25 E
10-Sep-2011 2000 28 NE
10-Sep-2011 2100 2 N
10-Sep-2011 2200 3 ENE
10-Sep-2011 2300 22 E
11-Sep-2011 000 27 ENE
11-Sep-2011 100 21 NNW
11-Sep-2011 200 28 ESE
11-Sep-2011 300 22 NE
11-Sep-2011 400 2 NE
11-Sep-2011 500 24 NNE
11-Sep-2011 600 26 NNE
11-Sep-2011 700 2 NE
11-Sep-2011 800 2 N
11-Sep-2011 900 25 NE
11-Sep-2011 1000 31 N
11-Sep-2011 1100 34 N
11-Sep-2011 1200 4 NE
11-Sep-2011 1300 37 NE
11-Sep-2011 1400 38 N
11-Sep-2011 1500 45 ENE
11-Sep-2011 1600 42 N
11-Sep-2011 1700 38 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 10 Cinotech
11-Sep-2011 1800 31 NE
11-Sep-2011 1900 27 N
11-Sep-2011 2000 29 NE
11-Sep-2011 2100 29 NNE
11-Sep-2011 2200 3 NNE
11-Sep-2011 2300 27 N
12-Sep-2011 000 24 N
12-Sep-2011 100 23 N
12-Sep-2011 200 23 NE
12-Sep-2011 300 25 N
12-Sep-2011 400 22 N
12-Sep-2011 500 24 NNE
12-Sep-2011 600 21 ENE
12-Sep-2011 700 21 NNE
12-Sep-2011 800 22 E
12-Sep-2011 900 27 N
12-Sep-2011 1000 27 NNE
12-Sep-2011 1100 35 NNE
12-Sep-2011 1200 37 NE
12-Sep-2011 1300 38 NE
12-Sep-2011 1400 43 NNE
12-Sep-2011 1500 41 N
12-Sep-2011 1600 36 N
12-Sep-2011 1700 34 NE
12-Sep-2011 1800 32 N
12-Sep-2011 1900 26 N
12-Sep-2011 2000 23 N
12-Sep-2011 2100 19 NE
12-Sep-2011 2200 19 N
12-Sep-2011 2300 2 NNE
13-Sep-2011 000 2 ESE
13-Sep-2011 100 22 E
13-Sep-2011 200 23 NE
13-Sep-2011 300 26 NE
13-Sep-2011 400 26 ENE
13-Sep-2011 500 21 ENE
13-Sep-2011 600 25 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 11 Cinotech
13-Sep-2011 700 25 ENE
13-Sep-2011 800 26 E
13-Sep-2011 900 24 ENE
13-Sep-2011 1000 31 NNE
13-Sep-2011 1100 34 NNE
13-Sep-2011 1200 4 NE
13-Sep-2011 1300 4 ENE
13-Sep-2011 1400 38 E
13-Sep-2011 1500 38 ENE
13-Sep-2011 1600 35 ENE
13-Sep-2011 1700 35 NNE
13-Sep-2011 1800 31 E
13-Sep-2011 1900 25 NNE
13-Sep-2011 2000 16 ENE
13-Sep-2011 2100 16 E
13-Sep-2011 2200 16 E
13-Sep-2011 2300 17 ENE
14-Sep-2011 000 18 N
14-Sep-2011 100 2 NE
14-Sep-2011 200 19 NNE
14-Sep-2011 300 2 ENE
14-Sep-2011 400 19 ENE
14-Sep-2011 500 18 ENE
14-Sep-2011 600 2 ENE
14-Sep-2011 700 23 NNE
14-Sep-2011 800 25 NNE
14-Sep-2011 900 28 ENE
14-Sep-2011 1000 36 ENE
14-Sep-2011 1100 45 ENE
14-Sep-2011 1200 36 ENE
14-Sep-2011 1300 34 E
14-Sep-2011 1400 35 NNE
14-Sep-2011 1500 36 ENE
14-Sep-2011 1600 34 ENE
14-Sep-2011 1700 31 ENE
14-Sep-2011 1800 31 ENE
14-Sep-2011 1900 42 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 12 Cinotech
14-Sep-2011 2000 4 ENE
14-Sep-2011 2100 34 ENE
14-Sep-2011 2200 32 ENE
14-Sep-2011 2300 25 ENE
15-Sep-2011 000 46 ENE
15-Sep-2011 100 24 ENE
15-Sep-2011 200 35 NE
15-Sep-2011 300 35 NNE
15-Sep-2011 400 24 NE
15-Sep-2011 500 24 NE
15-Sep-2011 600 21 NNE
15-Sep-2011 700 41 ENE
15-Sep-2011 800 22 NE
15-Sep-2011 900 24 NNE
15-Sep-2011 1000 36 NNE
15-Sep-2011 1100 39 W
15-Sep-2011 1200 43 N
15-Sep-2011 1300 46 ENE
15-Sep-2011 1400 44 NE
15-Sep-2011 1500 33 NNE
15-Sep-2011 1600 46 NE
15-Sep-2011 1700 43 ENE
15-Sep-2011 1800 44 NE
15-Sep-2011 1900 36 NNE
15-Sep-2011 2000 31 N
15-Sep-2011 2100 33 ENE
15-Sep-2011 2200 29 E
15-Sep-2011 2300 27 SSE
16-Sep-2011 000 29 N
16-Sep-2011 100 27 ENE
16-Sep-2011 200 28 NE
16-Sep-2011 300 25 NE
16-Sep-2011 400 26 ENE
16-Sep-2011 500 29 NNE
16-Sep-2011 600 25 ENE
16-Sep-2011 700 32 NNE
16-Sep-2011 800 29 NNE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 13 Cinotech
16-Sep-2011 900 34 NE
16-Sep-2011 1000 38 NNE
16-Sep-2011 1100 41 NE
16-Sep-2011 1200 42 ENE
16-Sep-2011 1300 47 NNE
16-Sep-2011 1400 47 N
16-Sep-2011 1500 48 N
16-Sep-2011 1600 37 ENE
16-Sep-2011 1700 36 NE
16-Sep-2011 1800 27 ENE
16-Sep-2011 1900 23 ENE
16-Sep-2011 2000 18 ESE
16-Sep-2011 2100 19 ESE
16-Sep-2011 2200 15 ENE
16-Sep-2011 2300 12 SSE
17-Sep-2011 000 18 ENE
17-Sep-2011 100 16 NNE
17-Sep-2011 200 14 ENE
17-Sep-2011 300 2 ENE
17-Sep-2011 400 1 NE
17-Sep-2011 500 14 NNE
17-Sep-2011 600 25 NNE
17-Sep-2011 700 12 NNE
17-Sep-2011 800 16 ENE
17-Sep-2011 900 18 SSE
17-Sep-2011 1000 19 SSE
17-Sep-2011 1100 31 NNE
17-Sep-2011 1200 28 NE
17-Sep-2011 1300 26 ENE
17-Sep-2011 1400 26 ENE
17-Sep-2011 1500 3 NE
17-Sep-2011 1600 36 NE
17-Sep-2011 1700 23 NE
17-Sep-2011 1800 23 NNE
17-Sep-2011 1900 2 NE
17-Sep-2011 2000 15 ENE
17-Sep-2011 2100 14 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 14 Cinotech
17-Sep-2011 2200 15 ENE
17-Sep-2011 2300 14 E
18-Sep-2011 000 13 NNE
18-Sep-2011 100 17 NNE
18-Sep-2011 200 1 ENE
18-Sep-2011 300 1 ENE
18-Sep-2011 400 11 ENE
18-Sep-2011 500 13 NNE
18-Sep-2011 600 06 E
18-Sep-2011 700 06 NE
18-Sep-2011 800 13 ENE
18-Sep-2011 900 22 ESE
18-Sep-2011 1000 3 ESE
18-Sep-2011 1100 3 E
18-Sep-2011 1200 34 ENE
18-Sep-2011 1300 32 ENE
18-Sep-2011 1400 3 SE
18-Sep-2011 1500 34 NE
18-Sep-2011 1600 31 ESE
18-Sep-2011 1700 27 ENE
18-Sep-2011 1800 25 ENE
18-Sep-2011 1900 2 ENE
18-Sep-2011 2000 24 ENE
18-Sep-2011 2100 22 ENE
18-Sep-2011 2200 2 ENE
18-Sep-2011 2300 24 NE
19-Sep-2011 000 29 SE
19-Sep-2011 100 21 NNE
19-Sep-2011 200 28 NNE
19-Sep-2011 300 24 NNE
19-Sep-2011 400 22 SE
19-Sep-2011 500 23 NNE
19-Sep-2011 600 22 NNE
19-Sep-2011 700 17 NNW
19-Sep-2011 800 23 N
19-Sep-2011 900 29 N
19-Sep-2011 1000 28 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 15 Cinotech
19-Sep-2011 1100 3 NNE
19-Sep-2011 1200 38 ENE
19-Sep-2011 1300 25 E
19-Sep-2011 1400 25 NNE
19-Sep-2011 1500 27 ENE
19-Sep-2011 1600 29 ESE
19-Sep-2011 1700 25 SSE
19-Sep-2011 1800 23 ENE
19-Sep-2011 1900 21 ENE
19-Sep-2011 2000 2 ENE
19-Sep-2011 2100 11 NW
19-Sep-2011 2200 2 SSE
19-Sep-2011 2300 22 NNE
20-Sep-2011 000 2 ESE
20-Sep-2011 100 17 NNE
20-Sep-2011 200 21 ESE
20-Sep-2011 300 21 ENE
20-Sep-2011 400 23 NE
20-Sep-2011 500 25 ESE
20-Sep-2011 600 25 ENE
20-Sep-2011 700 18 SSE
20-Sep-2011 800 18 ESE
20-Sep-2011 900 23 NNE
20-Sep-2011 1000 25 ENE
20-Sep-2011 1100 28 NNE
20-Sep-2011 1200 24 NNE
20-Sep-2011 1300 26 N
20-Sep-2011 1400 3 S
20-Sep-2011 1500 33 ENE
20-Sep-2011 1600 33 ENE
20-Sep-2011 1700 34 SE
20-Sep-2011 1800 23 NE
20-Sep-2011 1900 18 ENE
20-Sep-2011 2000 16 NNE
20-Sep-2011 2100 17 NNE
20-Sep-2011 2200 21 ESE
20-Sep-2011 2300 27 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 16 Cinotech
21-Sep-2011 000 18 NE
21-Sep-2011 100 16 NE
21-Sep-2011 200 17 NE
21-Sep-2011 300 23 NE
21-Sep-2011 400 19 NE
21-Sep-2011 500 21 E
21-Sep-2011 600 16 ESE
21-Sep-2011 700 12 ESE
21-Sep-2011 800 12 E
21-Sep-2011 900 21 SE
21-Sep-2011 1000 31 ESE
21-Sep-2011 1100 33 SE
21-Sep-2011 1200 34 SE
21-Sep-2011 1300 33 NE
21-Sep-2011 1400 29 NE
21-Sep-2011 1500 24 SW
21-Sep-2011 1600 27 WNW
21-Sep-2011 1700 28 WNW
21-Sep-2011 1800 29 WNW
21-Sep-2011 1900 29 WNW
21-Sep-2011 2000 23 SW
21-Sep-2011 2100 27 WSW
21-Sep-2011 2200 24 W
21-Sep-2011 2300 31 W
22-Sep-2011 000 32 SW
22-Sep-2011 100 22 W
22-Sep-2011 200 23 W
22-Sep-2011 300 18 E
22-Sep-2011 400 23 W
22-Sep-2011 500 21 W
22-Sep-2011 600 21 W
22-Sep-2011 700 21 SW
22-Sep-2011 800 29 SSW
22-Sep-2011 900 26 WSW
22-Sep-2011 1000 29 NE
22-Sep-2011 1100 31 ENE
22-Sep-2011 1200 29 ENE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 17 Cinotech
22-Sep-2011 1300 29 ESE
22-Sep-2011 1400 33 SW
22-Sep-2011 1500 35 WSW
22-Sep-2011 1600 35 WSW
22-Sep-2011 1700 31 SW
22-Sep-2011 1800 34 SW
22-Sep-2011 1900 31 W
22-Sep-2011 2000 29 SSW
22-Sep-2011 2100 29 S
22-Sep-2011 2200 21 W
22-Sep-2011 2300 23 W
23-Sep-2011 000 23 W
23-Sep-2011 100 2 N
23-Sep-2011 200 22 N
23-Sep-2011 300 21 NW
23-Sep-2011 400 17 N
23-Sep-2011 500 16 ESE
23-Sep-2011 600 16 W
23-Sep-2011 700 21 W
23-Sep-2011 800 21 WNW
23-Sep-2011 900 24 S
23-Sep-2011 1000 34 SSW
23-Sep-2011 1100 34 S
23-Sep-2011 1200 35 SW
23-Sep-2011 1300 37 WSW
23-Sep-2011 1400 39 NE
23-Sep-2011 1500 38 S
23-Sep-2011 1600 39 SSW
23-Sep-2011 1700 34 SW
23-Sep-2011 1800 27 ESE
23-Sep-2011 1900 27 WNW
23-Sep-2011 2000 23 SW
23-Sep-2011 2100 2 SW
23-Sep-2011 2200 18 W
23-Sep-2011 2300 16 N
24-Sep-2011 000 14 WNW
24-Sep-2011 100 18 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 18 Cinotech
24-Sep-2011 200 14 ENE
24-Sep-2011 300 12 ENE
24-Sep-2011 400 14 ENE
24-Sep-2011 500 19 ENE
24-Sep-2011 600 17 SSW
24-Sep-2011 700 15 WSW
24-Sep-2011 800 22 SSW
24-Sep-2011 900 25 S
24-Sep-2011 1000 27 W
24-Sep-2011 1100 27 ENE
24-Sep-2011 1200 29 ESE
24-Sep-2011 1300 32 NE
24-Sep-2011 1400 34 WNW
24-Sep-2011 1500 33 NE
24-Sep-2011 1600 33 NW
24-Sep-2011 1700 26 NNE
24-Sep-2011 1800 18 NE
24-Sep-2011 1900 17 WSW
24-Sep-2011 2000 15 SW
24-Sep-2011 2100 16 SW
24-Sep-2011 2200 17 WNW
24-Sep-2011 2300 18 NE
25-Sep-2011 000 16 ENE
25-Sep-2011 100 16 NE
25-Sep-2011 200 16 NNE
25-Sep-2011 300 12 WNW
25-Sep-2011 400 11 W
25-Sep-2011 500 14 SSW
25-Sep-2011 600 13 NE
25-Sep-2011 700 14 W
25-Sep-2011 800 18 SW
25-Sep-2011 900 26 ENE
25-Sep-2011 1000 27 NNE
25-Sep-2011 1100 32 NNE
25-Sep-2011 1200 33 W
25-Sep-2011 1300 36 SSW
25-Sep-2011 1400 39 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 19 Cinotech
25-Sep-2011 1500 39 W
25-Sep-2011 1600 39 E
25-Sep-2011 1700 32 WNW
25-Sep-2011 1800 27 WNW
25-Sep-2011 1900 23 WNW
25-Sep-2011 2000 23 NE
25-Sep-2011 2100 21 N
25-Sep-2011 2200 2 NNE
25-Sep-2011 2300 2 NNE
26-Sep-2011 000 17 SSE
26-Sep-2011 100 16 N
26-Sep-2011 200 16 NNE
26-Sep-2011 300 17 N
26-Sep-2011 400 07 NE
26-Sep-2011 500 09 SW
26-Sep-2011 600 11 N
26-Sep-2011 700 14 NE
26-Sep-2011 800 19 SW
26-Sep-2011 900 22 SW
26-Sep-2011 1000 23 NE
26-Sep-2011 1100 28 SW
26-Sep-2011 1200 31 SW
26-Sep-2011 1300 3 NE
26-Sep-2011 1400 32 WNW
26-Sep-2011 1500 3 SW
26-Sep-2011 1600 32 W
26-Sep-2011 1700 25 W
26-Sep-2011 1800 2 W
26-Sep-2011 1900 18 WSW
26-Sep-2011 2000 17 WSW
26-Sep-2011 2100 32 WNW
26-Sep-2011 2200 3 SE
26-Sep-2011 2300 3 SW
27-Sep-2011 000 29 WNW
27-Sep-2011 100 23 SSW
27-Sep-2011 200 23 NNE
27-Sep-2011 300 18 WSW
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 20 Cinotech
27-Sep-2011 400 15 NW
27-Sep-2011 500 14 WNW
27-Sep-2011 600 14 W
27-Sep-2011 700 14 WNW
27-Sep-2011 800 16 WSW
27-Sep-2011 900 21 WSW
27-Sep-2011 1000 25 W
27-Sep-2011 1100 24 NE
27-Sep-2011 1200 32 NNE
27-Sep-2011 1300 29 WSW
27-Sep-2011 1400 32 NNE
27-Sep-2011 1500 32 SSW
27-Sep-2011 1600 25 N
27-Sep-2011 1700 29 NNE
27-Sep-2011 1800 23 ENE
27-Sep-2011 1900 18 WNW
27-Sep-2011 2000 17 WSW
27-Sep-2011 2100 18 SSE
27-Sep-2011 2200 14 WSW
27-Sep-2011 2300 21 NNE
28-Sep-2011 000 22 N
28-Sep-2011 100 2 ESE
28-Sep-2011 200 2 W
28-Sep-2011 300 16 W
28-Sep-2011 400 18 S
28-Sep-2011 500 15 WSW
28-Sep-2011 600 13 WNW
28-Sep-2011 700 14 W
28-Sep-2011 800 16 WNW
28-Sep-2011 900 2 W
28-Sep-2011 1000 29 W
28-Sep-2011 1100 41 SSW
28-Sep-2011 1200 42 SSW
28-Sep-2011 1300 57 NW
28-Sep-2011 1400 46 SW
28-Sep-2011 1500 46 WSW
28-Sep-2011 1600 42 W
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 21 Cinotech
28-Sep-2011 1700 35 W
28-Sep-2011 1800 44 WNW
28-Sep-2011 1900 52 W
28-Sep-2011 2000 53 WNW
28-Sep-2011 2100 53 WSW
28-Sep-2011 2200 54 ENE
28-Sep-2011 2300 55 ENE
29-Sep-2011 000 55 N
29-Sep-2011 100 59 NE
29-Sep-2011 200 6 ENE
29-Sep-2011 300 57 NNE
29-Sep-2011 400 54 ENE
29-Sep-2011 500 54 ENE
29-Sep-2011 600 53 N
29-Sep-2011 700 52 NE
29-Sep-2011 800 53 ENE
29-Sep-2011 900 55 ENE
29-Sep-2011 1000 64 NNE
29-Sep-2011 1100 64 ENE
29-Sep-2011 1200 61 NNE
29-Sep-2011 1300 61 WNW
29-Sep-2011 1400 59 NNE
29-Sep-2011 1500 66 SW
29-Sep-2011 1600 63 S
29-Sep-2011 1700 61 WNW
29-Sep-2011 1800 55 ENE
29-Sep-2011 1900 52 ENE
29-Sep-2011 2000 52 W
29-Sep-2011 2100 53 E
29-Sep-2011 2200 56 S
29-Sep-2011 2300 51 ENE
30-Sep-2011 000 51 ENE
30-Sep-2011 100 46 NNE
30-Sep-2011 200 28 ENE
30-Sep-2011 300 29 SSW
30-Sep-2011 400 35 NNE
30-Sep-2011 500 18 NE
APPENDIX C ndash
WEATHER CONDITIONS DURING THE MONITORING PERIOD
II Mean Wind Speed and Wind Direction
MA0040Weather Conditions C - 22 Cinotech
30-Sep-2011 600 12 NE
30-Sep-2011 700 11 N
30-Sep-2011 800 17 WNW
30-Sep-2011 900 27 NNE
30-Sep-2011 1000 28 SSW
30-Sep-2011 1100 29 W
30-Sep-2011 1200 38 NW
30-Sep-2011 1300 32 ESE
30-Sep-2011 1400 34 N
30-Sep-2011 1500 35 N
30-Sep-2011 1600 33 SE
30-Sep-2011 1700 27 W
30-Sep-2011 1800 25 E
30-Sep-2011 1900 25 WSW
30-Sep-2011 2000 24 E
30-Sep-2011 2100 22 N
30-Sep-2011 2200 23 W
30-Sep-2011 2300 21 NE
APPENDIX D
ENVIRONMENTAL MONITORING
SCHEDULES
1-Sep 2-Sep 3-Sep
4-Sep 5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep
11-Sep 12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep
18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep
25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Impact Air and Noise Monitoring Schedule for September 2011
Sunday Monday Tuesday Wednesday Thursday Friday
Noise(M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
1 hr TSP X3 NoiseNoise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
24 hr TSP
1-Oct
2-Oct 3-Oct 4-Oct 5-Oct 6-Oct 7-Oct 8-Oct
9-Oct 10-Oct 11-Oct 12-Oct 13-Oct 14-Oct 15-Oct
16-Oct 17-Oct 18-Oct 19-Oct 20-Oct 21-Oct 22-Oct
23-Oct 24-Oct 25-Oct 26-Oct 27-Oct 28-Oct 29-Oct
30-Oct 31-Oct
The schedule may be changed due to unforeseen circumstances (adverse weather etc)
Air Quality Monitoring Station Noise Monitoring Station
AM1(A) - Kai Tak Operational Base M1 - Buddhist Chi King Primary School
AM2 - Lee Kau Yan Memorial School M2 - SKH Kowloon Bay Kei Lok Primary School
AM3(A) - Holy Trinity Bradbury Centre M3 - Rhythm Garden
AM4(A) - EMSD Workshops M4(A) - Kai Tak Operational Base
AM5(A) - Po Leung Kuk Ngan Po Ling College M5 - Lee Kau Yan Memorial School
M6(A) - Kowloon City District Kaifong Association
M7 - Holy Carpenter Primary School
M8 - CCC Kei To Secondary School
M9 - Po Leung Kuk Ngan Po Ling College
24 hr TSP
24 hr TSP
Noise 1 hr TSP X3(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
24 hr TSP
(M1 M2 M6(A) M7 and M8) Noise (M3 M4(A) M5 and M9)
Noise 1 hr TSP X3
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3
24 hr TSP
1 hr TSP X3 Noise
24 hr TSP
Noise (M3 M4(A) M5 and M9) (M1 M2 M6(A) M7 and M8)
1 hr TSP X3 Noise
24 hr TSP
Saturday
Contract No KLN201004
Environmental Monitoring Works at Kai Tak Development
Tentative Impact Air and Noise Monitoring Schedule for October 2011
Sunday Monday Tuesday Wednesday Thursday Friday
APPENDIX E
1-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix E - 1-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 7406-Sep-11 1500 Sunny 8726-Sep-11 1600 Sunny 795
12-Sep-11 1400 Sunny 99712-Sep-11 1500 Sunny 130612-Sep-11 1600 Sunny 145916-Sep-11 1400 Cloudy 94216-Sep-11 1500 Cloudy 88216-Sep-11 1600 Cloudy 99722-Sep-11 1400 Cloudy 132522-Sep-11 1500 Cloudy 119022-Sep-11 1600 Cloudy 113628-Sep-11 1400 Cloudy 61928-Sep-11 1500 Cloudy 41928-Sep-11 1600 Cloudy 460
Average 943Maximum 1459Minimum 419
Location AM2 - Lee Kau Yan Memorial School
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 7486-Sep-11 1600 Sunny 879
12-Sep-11 1400 Sunny 121112-Sep-11 1500 Sunny 136812-Sep-11 1600 Sunny 153316-Sep-11 1400 Cloudy 93716-Sep-11 1500 Cloudy 101516-Sep-11 1600 Cloudy 85622-Sep-11 1400 Cloudy 138022-Sep-11 1500 Cloudy 108522-Sep-11 1600 Cloudy 112028-Sep-11 1400 Cloudy 78628-Sep-11 1500 Cloudy 64128-Sep-11 1600 Cloudy 696
Average 1014Maximum 1533Minimum 641
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM3(A) - Holy Trinity Bradbury Centre
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9216-Sep-11 1000 Sunny 8606-Sep-11 1100 Sunny 995
12-Sep-11 900 Sunny 91112-Sep-11 1000 Sunny 86012-Sep-11 1100 Sunny 99416-Sep-11 900 Cloudy 108216-Sep-11 1000 Cloudy 101616-Sep-11 1100 Cloudy 104622-Sep-11 900 Cloudy 120822-Sep-11 1000 Cloudy 142522-Sep-11 1100 Cloudy 106928-Sep-11 900 Cloudy 65628-Sep-11 1000 Cloudy 87528-Sep-11 1100 Cloudy 554
Average 965Maximum 1425Minimum 554
Location AM4(A) - EMSD Workshops
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 1400 Sunny 9516-Sep-11 1500 Sunny 10256-Sep-11 1600 Sunny 729
12-Sep-11 1400 Sunny 131412-Sep-11 1500 Sunny 114312-Sep-11 1600 Sunny 137316-Sep-11 1400 Cloudy 121416-Sep-11 1500 Cloudy 111316-Sep-11 1600 Cloudy 102522-Sep-11 1400 Cloudy 121322-Sep-11 1500 Cloudy 113722-Sep-11 1600 Cloudy 138028-Sep-11 1400 Cloudy 49228-Sep-11 1500 Cloudy 55028-Sep-11 1600 Cloudy 863
Average 1035Maximum 1380Minimum 492
MA0040App E - 1hr TSP Cinotech
Appendix E - 1-hour TSP Monitoring Results
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Date Time Weather Particulate Concentration ( microgm3)
6-Sep-11 900 Sunny 9026-Sep-11 1000 Sunny 9406-Sep-11 1100 Sunny 821
12-Sep-11 900 Sunny 66912-Sep-11 1000 Sunny 76612-Sep-11 1100 Sunny 82616-Sep-11 900 Cloudy 106716-Sep-11 1000 Cloudy 118116-Sep-11 1100 Cloudy 97422-Sep-11 900 Cloudy 120322-Sep-11 1000 Cloudy 127922-Sep-11 1100 Cloudy 141928-Sep-11 900 Cloudy 63528-Sep-11 1000 Cloudy 50628-Sep-11 1100 Cloudy 583
Average 918Maximum 1419Minimum 506
MA0040App E - 1hr TSP Cinotech
1-hr TSP Concentration Levels
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - Kai Tak Operational Base1-hour TSP
Action Level 342 microgm3
Limit Level 500 microgm3
300
400
500
600
ratio
n micro
gm
3
AM2 - Lee Kau Yan Memorial School1-hour TSP
Action Level 346 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre1-hour TSP
Action Level 351 microgm3
Limit Level 500 microgm3
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
1-hr TSP Concentration Levels
300
400
500
600
ratio
n micro
gm
3
AM5(A) - Po Leung Kuk Ngan Po Ling College1-hour TSP
Action Level 345 microgm3
Limit Level 500 microgm3
0
100
200
300
400
500
600
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops1-hour TSP
Action Level 371 microgm3
Limit Level 500 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
100
200
Con
cent
r
Date
Date AppendixSep 11 EGraphical Presentation of 1-hour TSP Monitoring Results
APPENDIX F
24-HOUR TSP MONITORING RESULTS
AND GRAPHICAL PRESENTATION
Appendix F - 24-hour TSP Monitoring Results
Location AM1(A) - Kai Tak Operational Base
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33889 34745 00856 14410 14650 240 122 122 122 17503 4898-Sep-11 Sunny 3016 7588 33462 34766 01304 14650 14890 240 122 122 122 17573 74214-Sep-11 Cloudy 3021 7591 33811 34827 01016 15370 15610 240 122 122 122 17562 57920-Sep-11 Sunny 2965 7627 33362 34157 00795 15610 15850 240 123 123 123 17756 44826-Sep-11 Fine 2991 7604 33189 34617 01428 15850 16090 240 123 123 123 17659 809
Min 448Max 809
Average 613
Location AM2 - Lee Kau Yan Memorial School
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33369 34937 01568 13450 13690 240 121 121 121 17469 8988-Sep-11 Sunny 3016 7588 33582 35591 02009 13690 13930 240 122 122 122 17537 114614-Sep-11 Cloudy 3021 7591 33987 34975 00988 14410 14650 240 122 122 122 17527 56420-Sep-11 Sunny 2965 7627 33575 35125 01550 14650 14890 240 123 123 123 17715 87526-Sep-11 Fine 2991 7604 33517 35889 02372 14890 15130 240 122 122 122 17621 1346
Min 564Max 1346
Average 966
Location AM3(A) - Holy Trinity Bradbury Centre
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33228 34409 01181 41282 41522 240 122 122 122 17537 6738-Sep-11 Sunny 3016 7588 34445 35917 01472 41522 41762 240 122 122 122 17602 83614-Sep-11 Cloudy 3021 7591 33308 34309 01001 41762 42002 240 122 122 122 17593 56920-Sep-11 Sunny 2965 7627 33387 34725 01338 42002 42242 240 123 123 123 17771 75326-Sep-11 Fine 2991 7604 33124 34925 01801 42242 42482 240 123 123 123 17682 1019
Min 569Max 1019
Average 770
Start Date
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
Appendix F - 24-hour TSP Monitoring Results
Location AM4(A) - EMSD Workshops
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33447 34956 01509 11280 11520 240 121 120 121 17355 8698-Sep-11 Sunny 3016 7588 33828 35654 01826 11520 11760 240 121 121 121 17420 104814-Sep-11 Cloudy 3021 7591 33428 34764 01336 11760 12000 240 121 121 121 17410 76720-Sep-11 Sunny 2965 7627 33640 35156 01516 12000 12240 240 122 122 122 17588 86226-Sep-11 Fine 2991 7604 33374 35372 01998 12240 12480 240 122 121 122 17499 1142
Min 767Max 1142
Average 938
Location AM5(A) - Po Leung Kuk Ngan Po Ling College
Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3min) Av flow Total vol ConcCondition Temp (K) Pressure Pa (mmHg) Initial Final weight (g) Initial Final Time(hrs) Initial Final (m3min) (m3) (microgm3)
2-Sep-11 Sunny 3034 7569 33504 34519 01015 13450 13690 240 121 121 121 17459 5818-Sep-11 Sunny 3016 7588 33711 34950 01239 13690 13930 240 122 122 122 17522 70714-Sep-11 Cloudy 3021 7591 33300 34146 00846 13930 14170 240 122 122 122 17513 48320-Sep-11 Sunny 2965 7627 34200 35202 01002 14170 14410 240 123 123 123 17688 56626-Sep-11 Fine 2991 7604 33910 35494 01584 14410 14650 240 122 122 122 17600 900
Min 483Max 900
Average 648
Start Date
Start Date
MA0040App F - 24hr TSP Cinotech
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM1(A) - kai Tak Operational Base24-hour TSP
Action Level 159 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM2 - Lee Kau Yan Memorial School24-hour TSP
Action Level 157 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cen
Date
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM3(A) - Holy Trinity Bradbury Centre24-hour TSP
Action Level 167 microgm3
Limit Level 260 microgm3
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
24-hr TSP Concentration Levels
0
50
100
150
200
250
300
Con
cent
ratio
n micro
gm
3
Date
AM4(A) - EMSD Workshops24-hour TSP
Action Level 187 microgm3
Limit Level 260 microgm3
150
200
250
300
trat
ion
microg
m3
AM5(A) - Po Leung Kuk Ngan Po Ling College24-hour TSP
Action Level 156 microgm3
Limit Level 260 microgm3
Title Scale ProjectNTS No MA0040
Date Appendix
Contract No KLN201004Environmental Monitoring Works for Kai Tak
0
50
100
Con
cent
Date
Date AppendixSep 11 FGraphical Presentation of 24-hour TSP Monitoring Results
APPENDIX G
NOISE MONITORING RESULTS AND
GRAPHICAL PRESENTATION
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1400 Sunny 675 705 635 646
8-Sep-11 1400 Sunny 663 690 621 618
15-Sep-11 1400 Cloudy 669 692 637 633
20-Sep-11 1400 Fine 672 705 645 640
30-Sep-11 1400 Cloudy 671 707 649 638
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1500 Sunny 675 704 651 663
8-Sep-11 1500 Sunny 681 726 666 671
15-Sep-11 1500 Cloudy 679 715 656 668
20-Sep-11 1500 Fine 677 710 651 666
30-Sep-11 1500 Cloudy 685 725 665 676
L eq L10 L 90
6-Sep-11 1400 Sunny 739 754 683
12-Sep-11 1400 Sunny 748 773 693
22-Sep-11 1400 Cloudy 746 770 694
28-Sep-11 1400 Cloudy 733 753 680
732
741
741
724
613
Location M3 - Rhythm Garden
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level Background Noise Level during Noise Measurement
L eq
644
Location M2 - SKH Kowloon Bay Kei Lok Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M1 - Buddhist Chi King Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1400 Sunny 658 678 618 658 Measured ≦ Baseline
12-Sep-11 1400 Sunny 664 686 649 575
22-Sep-11 1400 Cloudy 650 673 611 650 Measured ≦ Baseline
28-Sep-11 1400 Cloudy 660 684 645 525
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 1500 Sunny 744 762 704 744 Measured ≦ Baseline
12-Sep-11 1500 Sunny 750 769 712 750 Measured ≦ Baseline
22-Sep-11 1500 Cloudy 739 756 698 739 Measured ≦ Baseline
28-Sep-11 1500 Cloudy 745 768 705 745 Measured ≦ Baseline
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0900 Sunny 721 742 697 670
8-Sep-11 0900 Sunny 716 748 683 651
15-Sep-11 0900 Cloudy 720 743 706 667
20-Sep-11 0900 Fine 723 755 704 676
30-Sep-11 0900 Cloudy 719 745 699 663
705
767
Location M6(A) - Kowloon City District Kaifong Association
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
658
Location M5 - Lee Kau Yan Memorial School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M4(A) - Kai Tak Operational Base
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Appendix G - Noise Monitoring Results
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 0910 Sunny 666 694 637 633
8-Sep-11 0910 Sunny 671 705 645 643
15-Sep-11 0910 Cloudy 660 692 637 618
20-Sep-11 0910 Fine 667 699 627 635
30-Sep-11 0910 Cloudy 659 686 620 616
Location M8 - CCC Kei To Secondary School
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
1-Sep-11 1015 Sunny 648 671 619 648 Measured ≦ Baseline
8-Sep-11 1015 Sunny 640 667 608 640 Measured ≦ Baseline
15-Sep-11 1015 Cloudy 652 685 620 652 Measured ≦ Baseline
20-Sep-11 1015 Fine 637 665 605 637 Measured ≦ Baseline
30-Sep-11 1015 Cloudy 646 679 613 646 Measured ≦ Baseline
Location M9 - Po Leung Kuk Ngan Po Ling College
Baseline Level Construction Noise Level
L eq L10 L 90 L eq L eq
6-Sep-11 0900 Sunny 645 675 608 610
12-Sep-11 0900 Sunny 638 667 603 593
22-Sep-11 0900 Cloudy 633 665 596 577
28-Sep-11 0900 Cloudy 640 676 607 598
619
687
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
639
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
Location M7 - Holy Carpenter Primary School
Date Time Weather
Unit dB (A) (30-min)
Measured Noise Level
MA0040App G - Noise CinotechMA0040App G - Noise Cinotech
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M1 - Buddhist Chi King Primary School M1
Baseline NL 644 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M2 - SKH Kowloon Bay Kei Lok Primary School M2
Baseline NL 613 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
30
40
50
60
70
80
Me
as
ure
d N
ois
e L
eve
l d
B(A
)
Date
M3 - Rhythm GardenM3
Limit Level 75 dB(A)
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M5 - Lee Kau Yan Memorial School M5
Baseline NL 767 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M4(A) - Kai Tak Operational Base M4(A)
Baseline NL 658 dB(A)
Limit Level 75 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M6(A) - Kowloon City District Kaifong Association M6(A)
Baseline NL 705 dB(A)
Limit Level 75 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
Noise Levels
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
M8 - CCC Kei To Secondary School M8
Baseline NL 687 dB(A)
Limit Level 70 dB(A)
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M7 - Holy Carpenter Primary School M7
Baseline NL 639 dB(A)
Limit Level 70 dB(A)
Title Scale Project
NTSNo
MA0040Date Appendix
Sep 11 G
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Graphical Presentation of Construction Noise MonitoringResults
30
40
50
60
70
80
Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
M9 - Po Leung Kuk Ngan Po Ling College M9
Baseline NL 619 dB(A)
Limit Level 70 dB(A)
30Co
ns
tru
cti
on
No
ise
Le
ve
l d
B(A
)
Date
APPENDIX H
SUMMARY OF EXCEEDANCE
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix H ndash Summary of Exceedance
MA0040ExceedanceApp H - Exceedance 1109 1
Exceedance Report for Contract No KLN201004
(A) Exceedance Report for Air Quality
(NIL in the reporting month)
(B) Exceedance Report for Construction Noise
(NIL in the reporting month)
(C) Exceedance Report for Landscape and Visual
(NIL in the reporting month)
APPENDIX I
SITE AUDIT SUMMARY
Appendix I - Summary of Site Audit
Date Contract No Observation Follow-up
09092011 DC200921 The grouting works is not fully coveredRectificationimprovement was observed during the
follow-up audit session on 16 September 2011
16092011 Stockpile of dusty material were not covered properlyRectificationimprovement was observed during the
follow-up audit session on 19 September 2011
19092011 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
19092011 6WSD08 Construction materials were disposed at unoccupied areaRectificationimprovement was observed during the
follow-up audit session on 30 September 2011
DateSTT NoTGLA NoUnoccupied Area (Lands
Department)Observation Follow-up
02092011 Accumulation of rubbish at the access road
09092011 Accumulation of rubbish at the access road
16092011 Accumulation of rubbish at the access road
19092011 Accumulation of rubbish at the access road
30092011 Accumulation of rubbish at the access road
02092011 Stockpile of dusty material were not covered properly
02092011 Stockpile of dusty material were not covered properly
02092011 Deposited of dusty material at seawall
09092011 Deposited of dusty material at seawall
16092011 Deposited of dusty material at seawall
16092011 Stockpile of dusty material were not covered properly
19092011 Deposited of dusty material at seawall
19092011 Stockpile of dusty material were not covered properly
30092011 Deposited of dusty material at seawall
30092011 Stockpile of dusty material were not covered properly
02092011 Dust generation from loadingunloading works
09092011 Dust generation from loadingunloading works
16092011 Dust generation from loadingunloading works
16092011 Dark smoke emitted from excavator
19092011 Dust generation from loadingunloading works
19092011 Dark smoke emitted from excavator
30092011 Dark smoke emitted from excavator
30092011 Dust generation from loadingunloading works
8WSD08
STT No KX2678
STT No KX2117
Access Road to STT No KX2117 Follow-up action was needed for the item
Follow-up action was needed for the item
Follow-up action was needed for the item
App I -1
APPENDIX J
EVENT ACTION PLANS
Appendix J - Event Action Plans
J-1
EventAction Plan for Air Quality
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contactor IEC and ER
3 Repeat measurement to confirm finding
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
1 Notify Contractor 1 Rectify any unacceptable practice
2 Amend working methods if
appropriate
Action Level being
exceeded by
two or more
consecutive
sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC and ER
3 Increase monitoring frequency to daily
4 Discuss with IEC and Contractor on
remedial actions required
5 Assess the effectiveness of
Contractorrsquos remedial actions
6 If exceedance continues arrange
meeting with IEC and ER
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
4 Advise the ER on the effectiveness
of the proposed remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
1 Discuss with ET and IEC on proper
remedial actions
2 Submit proposals for remedial
actions to ER and IEC within three
working days of notification
3 Implement the agreed proposals
4 Amend proposal if appropriate
Limit Level being
exceeded by
one sampling
1 Identify source and investigate the
causes of exceedance
2 Inform Contractor IEC ER and EPD
3 Repeat measurement to confirm finding
4 Assess effectiveness of
Contractorrsquos remedial actions and keep
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss with ET and Contractor on
possible remedial measures
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
1 Take immediate action to avoid
further exceedance
2 Discuss with ET and IEC on proper
remedial actions
3 Submit proposals for remedial
actions to ER and IEC within three
Appendix J - Event Action Plans
J-2
EPD IEC and ER informed of
the results
4 Advise the ER on the
effectiveness of the proposed
remedial measures
implemented
4 Supervise implementation of
remedial measures
5 Conduct meeting with ET and
IEC if exceedance continues
working days of notification
4 Implement the agreed proposals
Limit Level being
exceeded by
two or more
consecutive
sampling
1 Notify IEC ER Contractor and
EPD
2 Repeat measurement to confirm
findings
3 Carry out analysis of Contractorrsquos
working procedures to identify source and
investigate the causes of exceedance
4 Increase monitoring frequency to
daily
5 Arrange meeting with IEC ER
and Contractor to discuss the
remedial actions to be taken
6 Assess effectiveness of
Contractorrsquos remedial actions and
keep EPD IEC and ER informed
of the results
7 If exceedance stops cease additional
monitoring
1 Check monitoring data submitted
by ET
2 Check Contractorrsquos working
method
3 Discuss amongst ER ET and
Contractor on the potential remedial
actions
4 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of notification
of exceedance in writing
2 Notify Contractor
3 In consolidation with the IEC
agree with the Contractor on the
remedial measures to be
implemented
4 Supervise implementation of
remedial measures
5 If exceedance continues
consider stopping the Contractor
to continue working on that
portion of work which causes the
exceedance until the
exceedance is abated
1 Take immediate action to avoid
further exceedance
2 Discuss with ET ER and IEC on
proper remedial actions
3 Submit proposals for remedial
actions to IEC within three working
days of notification
4 Implement the agreed proposals
5 Submit further remedial actions if
problem still not under control
6 Stop the relevant portion of works
as instructed by the ER until the
exceedance is abated
Appendix J - Event Action Plans
J-3
EventAction Plan for Construction Noise
EVENT ACTION
ET IEC ER CONTRACTOR
Action Level
being
exceeded
1 Notify ER IEC and Contractor
2 Carry out investigation
3 Report the results of investigation
to the IEC ER and Contractor
4 Discuss with the IEC and
Contractor on remedial measures
required
5 Increase monitoring frequency to
check mitigation effectiveness
(The above actions should be taken
within 2 working days after the
exceedance is identified)
1 Review the investigation
results submitted by the ET
2 Review the proposed remedial
measures by the Contractor and
advise the ER accordingly
3 Advise the ER on the
effectiveness of the proposed
remedial measures
(The above actions should be
taken within 2 working days after
the exceedance is identified)
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
measures to be implemented
4 Supervise the
implementation of remedial
measures
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
1 Submit noise mitigation
proposals to IEC and ER
2 Implement noise mitigation
proposals
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Limit Level
being
exceeded
1 Inform IEC ER Contractor and
EPD
2 Repeat measurements to confirm
findings
3 Increase monitoring frequency
4 Identify source and investigate the
cause of exceedance
1 Discuss amongst ER ET and
Contractor on the potential
remedial actions
2 Review Contractorrsquos remedial
actions whenever necessary to
assure their effectiveness and
advise the ER accordingly
1 Confirm receipt of
notification of failure in
writing
2 Notify Contractor
3 In consolidation with the
IEC agree with the
Contractor on the remedial
1 Take immediate action to
avoid further exceedance
2 Submit proposals for remedial
actions to IEC and ER within 3
working days of notification
3 Implement the agreed
proposals
Appendix J - Event Action Plans
J-4
5 Carry out analysis of Contractorrsquos
working procedures
6 Discuss with the IEC Contractor
and ER on remedial measures
required
7 Assess effectiveness of
Contractorrsquos remedial actions and
keep IEC EPD and ER informed of
the results
8 If exceedance stops cease
additional monitoring
(The above actions should be taken
within 2 working days after the
exceedance is identified)
(The above actions should be
taken within 2 working days after
the exceedance is identified)
measures to be implemented
4 Supervise the
implementation of remedial
measures
5 If exceedance continues
consider stopping the
Contractor to continue
working on that portion of
work which causes the
exceedance until the
exceedance is abated
(The above actions should be
taken within 2 working days
after the exceedance is
identified)
4 Submit further proposal if
problem still not under control
5 Stop the relevant portion of
works as instructed by the ER
until the exceedance is abated
(The above actions should be
taken within 2 working days after
the exceedance is identified)
Appendix J - Event Action Plans
J-5
EventAction Plan for Landscape and Visual
EVENT
ACTION
LEVEL
ACTION
ET
IEC
ER
CONTRACTOR
Design Check 1 Check final
design conforms to
the requirements
of EP and prepare
report
1 Check report
2 Recommend
remedial design if
necessary
1 Undertake remedial design if necessary
Non-conformity on one occasion 1 Identify Source
2 Inform IEC and
ER
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
1 Check report
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Check implementation
of remedial measures
1 Notify Contractor
2 Ensure remedial measures are properly
implemented
1 Amend working methods
2 Rectify damage and
undertake any necessary
replacement
Repeated Non-conformity 1 Identify Source
Inform IEC and
1 Check monitoring
report
1 Notify Contractor
2 Ensure remedial measures are properly
1 Amend working methods
2 Rectify damage and
Appendix J - Event Action Plans
J-6
ER
2 Increase
monitoring
frequency
3 Discuss remedial
actions with IEC
ER and Contractor
4 Monitor remedial
actions until
rectification has
been completed
5 If non-conformity
stops cease
additional
monitoring
2 Check Contractors
working method
3 Discuss with ET and
Contractor on possible
remedial measures
4 Advise ER on
effectiveness of
proposed remedial
measures
5 Supervise
implementation of
remedial measures
implemented undertake any necessary
replacement
APPENDIX K
ENVIRONMENTAL MITIGATION
IMPLEMENTATION SCHEDULE (EMIS)
K-1
Appendix K - Summary of Implementation Schedule of Mitigation Measures for Construction Phase
Types of Impacts Mitigation Measures
Status
Construction Dust
^
^
^
K-2
^
^
^
NA
K-3
NA
NA
K-4
^
NA
NA
K-5
Construction Noise
^
^
NA(1)
^
^
^
^
^
NA
NA
K-6
NA
NA
NA
NA
NA
NA
NA
NA
NA
NA
K-7
NA
NA
NA
NA
NA
K-8
Construction Water
Quality
NA
NA
NA
NA
^
K-9
^
^
NA (1)
^
K-10
K-11
^
^
^
^
K-12
^
^
^
^
K-13
^
^
^
^
K-14
^
^
^
^
^
K-15
^
^
^
K-16
^
^
K-17
^
^
K-18
^
K-19
^
^
^
K-20
^
^
^
^
K-21
^
^
K-22
Landscape and Visual
^
^
NA(1)
^
Remarks
^ Compliance of mitigation measure
X Non-compliance of mitigation measure
NA Not Applicable at this stage
NA(1) Not observed bull Non-compliance but rectified by the contractor
Recommendation was made during site audit
but improvedrectified by the contractor
APPENDIX L
SUMMARIES OF ENVIRONMENTAL
COMPLAINT WARNING SUMMON
AND NOTIFICATION OF SUCCESSFUL
PROSECUTION
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 1
Reporting Month September 2011
Contract No KLN201004
Log
Ref Location
Received
Date
Details of
Complaintwarningsummon
and prosecution
InvestigationMitigation
Action Status
NA NA NA NA NA NA
Remarks No environmental complaintwarningsummon and prosecution were received in the reporting period
Works Contract within KTD
KDO CEDD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
KL200901 No No No
KL200809 No No No
KL200807 No No No
KL200902 No No No
KL201002 No No No
KL201003 No No No
CEO CEDD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
CV200703 No No No
DSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful
Prosecutions(YesNo)
DC200812 No No No
DC201003 No No No
DC200921 No No No
HD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
20090097 No No No
20090006 No No No
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix L ndash Summary of environmental complaint warning summon and notification of
successful prosecution
MA0040App L 2
WSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
3WSD08 No No No
6WSD08 No No No
7WSD08 No No No
8WSD08 No No No
ArchSD project
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
SS W 303 No information provided by
the Contract
No No
CLP projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
Kai Tak Cruise
Terminal Cable
Tunnel
No No No
Eastern Road
Substation
No No No
CLPP (132kV
cable installation)
No No No
EMSD projects
Contract No Record of Complaint
(YesNo)
Record of Warning
(YesNo)
Notification of Summons and
Successful Prosecutions
(YesNo)
1016EM10 No No No
1017EM10 No No No
APPENDIX M
WASTE GENERATED QUANTITY
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 1
KDO CEDD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
KL200901 No Yes
KL200809 No Yes
KL200807 No Yes
KL200902 No No
KL201002 No Yes
KL201003 No No
CEO CEDD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
CV200703 No No
DSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
DC200812 No Yes
DC201003 Yes (2 load inert material to TKO137
overloaded not exceeding 105)
Yes
DC200921 Yes (2 nos of overloading) Yes
HD projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
20090097 No No
20090006 No Yes
WSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
3WSD08 No Yes
6WSD08 No Yes
7WSD08 No Yes
8WSD08 No Yes
ArchSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
SS W 303 No information provided from the Contract
CLP projects
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
Kai Tak Cruise
Terminal Cable
Tunnel
No No
Eastern Road
Contract No KLN201004
Environmental Monitoring Works for Kai Tak Development
Appendix M ndash Summary of Waste Generation and Disposal Records
MA0040App M - Summary of Waste Records 2
Substation
CLPP (132kV
cable installation)
EMSD project
Contract No Overloading record in the reporting month
(YesNo)
Waste flow tableDisposal Records
Yes(as attached)No
1016EM10 No Yes 1017EM10 No No
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 1)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 15422 0000 0000 0000 2791 0000 275465 0225 0044 0000 0025
February 14688 0000 0000 6930 6701 0000 180414 0075 0036 0000 0015
March 20552 0000 0000 5952 12590 0000 91963 0090 0086 0234 0025
April 48733 0000 0300 19217 20402 0000 142244 0084 0032 0000 0035
May 49397 0000 3117 28494 9211 0000 11504 0060 0020 0000 0025
June 40022 0000 16203 7473 15606 0000 26665 0087 0335 0000 0030
Sub-total 188814 0000 19620 68066 67301 0000 728255 0621 0553 0234 0155
July 46563 0000 11087 2060 19131 0000 13024 0057 0022 0000 0025
August 46591 0000 3295 30659 12283 0000 0005 0050 0018 0000 0020
September 53595 0000 5398 39646 1047 0000 18193 0060 0022 0000 0040
October
November
December
Total 335563 0000 39400 140431 99762 0000 759476 0788 0615 0234 0240
Notes
Monthly Summary Waste Flow Table for _ 2011_ (year)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Waste Generated Monthly
Month
Name of Department CEDD Contract No Site Formation for Kai Tak Cruise Terminal Development (KL200901 )
Total Quantity
Generated
Hard Rocks
and Large
Broken
Concrete
Reused in the
Contract
Reused in
Other Projects
Disposed as
Public FillImported Fill Metal
Paper
cardboard
packaging
Plastics
(see Note 3)
Chemical
Waste
Others eg
general refuse
(in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000m3) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
6556 unknown 1765 600 4861 7 1000 2 05 05 2
Notes
(1) The performance targets are given in PS clause 6(14) above
(2) The waste flow table shall also include CampD materials that are specified in the Contractor to be imported for use at the Site
(3) Plastic refer to plastic bottlescontainers plastic sheetsfoam from packaging material
(4) The Contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the nature
where the total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000 m3 (PS clause 5(4)(b) above refers)
- Total Quantity Generated = (Materials obtained from removal of existing seawall 644000m3 [322300m3 by dredging] + from general excavation 11600m3)= 655600m3
- Hard Rocks and Large Broken Concrete = Cannot be defined at this stage
- Reused in the Contract = (Armour Rock 68500m3 + Rock Fill 97400m3 + General Fill 10600m3) = 176500m3
- Reused in Other Projects = As much as possible (unknown at this stage)
- Disposed as Public Fill = (Total Quantity Generated 655600m3 - Reused in the Contract 176500m3 + Imported Fill 7000m3) = 4861m3
- Imported Fill = (According to PS 684) = 7000cm3
- Metal = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor (Spent lubricating oil assume density 09kgL)
- Other eg general refuse = Estimated by the Contractor
- Papercardboard packaging = Estimated by the Contractor
- Plastics = Estimated by the Contractor
- Chemical Waste = Estimated by the Contractor
- Other eg general refuse = Estimated by the Contractor
Forecast of Total Quantities of CampD Materials to be Generated from the Contract (see Note 4)
Monthly Summary Waste Flow Table for _ 2011_ (year)
Name of Department Civil Engineering and Development Department Kowloon Development Office Contract No ________________KL200809
JAN 0
FEB 0
MAR 0
APR 0
MAY 0
JUNE 304
SUB-
TOTAL304
JULY 0283
AUG 0
SEPT 0
OCT
NOV
DEC
TOTAL 3323
Notes (1) The performance targets are given in PS Clause 6(14)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the site
(3) Plastics refer to plastic bottles containers plastic sheets foam from packaging material
(4) The contractor shall also submit the latest forecast of the total amount of CampD materials expected to be generated from the Works together with a breakdown of the
nature where to total amount of CampD materials expected to be generated from the Works is equal to or exceeding 50000m3 (PS Clause 5(4)(b) referes)
[Delete Note (4) and the table above on the forecast where inapplicable]
00946
00534
01933
00264
00189
00094
00135
00208
00227
00197
00085
0 12
03
0
0
045
0
0
045
0
0
0
075
0
0
0
0005 0608
0
0
0
0
0
0
0263
0
0
0
0345
0
0608
0
0
0
0
0
0
0
0005
0
0005
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0 0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
35163
0
0
0
0
0
0
0
0
00189
03368
00208
00227
00197
00264
31342
30481
[in 000kg][in 000m3]
00094
00135
Chemical
Waste
[in 000kg]
0
0
0
0
Month
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg]
Disposal as
Public Fill
[in 000m3]
APPENDIX E MONTHLY SUMMARY WASTE FLOW TABLE FOR 2011 (YEAR)
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total
Quantity
Generated
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Projects
Import Fill Metals
Paper
Cardboard
Packaging
Total
Quantity
Borken
Concrete (4)
Reused in the
Contract
Reused in
other
Disposal as
Public Fill
Forecast of Total Quantities of CampD materials to be Generated from the Contracts
Other eg
general
refuse
Plastics (3)
Import Fill MetalsPaper
Cardboard Plastics (3)
Chemical
Waste
Other eg
general
[in 000m3][in 000kg]
[in 000m3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000m
3] [in 000kg] [in 000kg] [in 000kg] [in 000kg] [in 000m
3]
27972 26472 0 0 0 0 09 0 18 150
KL200807 Kai Tak Development - Advance Infrastructure Works for Developments at the Southern Part of the Former Runway Stage 1
Inert C amp D
Materials (Soft
Public Fill)
Good Quality Rock
(with break - down)Low Quality Rock Broken Concrete
Bituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
200907 (Actual) 000 000 000 000 000 000 000 000 000
200908 (Actual) 000 000 000 000 000 000 000 000 000
200909 (Actual) 000 000 000 000 000 000 000 000 000
200910 (Actual) 000 000 000 000 000 24581 000 000 000
200911 (Actual) 413949 000 000 000 000 37743 000 000 000
200912 (Actual) 175115 000 000 000 000 330 000 000 000
Sub-total 589064 000 000 000 000 62654 000 000 000
201001 (Actual) 293161 000 000 000 000 266 000 000 000
201002 (Actual) 000 000 000 000 000 178 000 000 000
201003 (Actual) 000 000 000 000 000 2239 000 000 000
201004 (Actual) 000 000 000 000 000 142 000 000 000
201005 (Actual) 2854 000 000 000 000 599 000 000 000
201006 (Actual) 000 000 000 000 000 722 000 000 000
Sub-total 296015 000 000 000 000 4146 000 000 000
201007 (Actual) 8310 000 000 000 000 5595 000 000 000
201008 (Actual) 1948 000 000 000 000 2568 000 000 000
201009 (Actual) 5825 000 000 000 000 837 000 000 000
201010 (Actual) 49259 000 000 000 000 2134 000 000 000
201011 (Actual) 32753 000 000 000 000 2580 000 000 000
201012 (Actual) 58766 000 000 000 000 2321 000 000 000
Sub-total 156861 000 000 000 000 16035 000 000 000
201101 (Actual) 69703 000 000 000 000 3122 000 000 000
201102 (Actual) 8755 000 000 000 000 1082 000 000 000
201103 (Actual) II 195087 000 000 000 000 6269 000 1680000 000
201104 (Actual) I II 2040129 870000 000 000 000 2143 000 940000 000
201105 (Actual) 21399 000 000 000 000 2144 000 000 000
201106 (Actual) 000 000 000 000 000 4627 000 000 000
Sub-total 2335073 870000 000 000 000 19387 000 2620000 000
201107 (Actual) 8571 000 000 000 000 2007 000 000 000
201108 (Actual) 45432 000 000 000 000 1977 000 000 000
201109 (Actual) 000 000 000 000 000 3342 000 000 000
201110 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201111 (Forecast) 400000 000 000 400000 200000 700 000 000 000
201112 (Forecast) 1545997 000 000 1300000 200000 274 000 180000 000
Sub-total 2400000 000 000 2100000 600000 9000 000 180000 000
201201 (Forecast) 400000 000 000 300000 000 1000 000 000 000
201202 (Forecast) 175187 000 000 300000 000 1000 000 000 000
201203 (Forecast) 7600 000 000 300000 000 500 000 000 000
201204 (Forecast) 000 000 000 300000 000 500 000 000 000
201205 (Forecast) 000 000 000 300000 000 500 000 000 000
201206 (Forecast) 000 000 000 114800 000 078 000 000 000
Sub-total 582787 000 000 1614800 000 3578 000 000 000
201207 (Forecast) 000 000 000 000 000 000 000 000 000
201208 (Forecast) 000 000 000 000 000 000 000 000 000
201209 (Forecast) 000 000 000 000 000 000 000 000 000
201210 (Forecast) 000 000 000 000 000 000 000 000 000
201211 (Forecast) 000 000 000 000 000 000 000 000 000
201212 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
201301 (Forecast) 000 000 000 000 000 000 000 000 000
201302 (Forecast) 000 000 000 000 000 000 000 000 000
201303 (Forecast) 000 000 000 000 000 000 000 000 000
201304 (Forecast) 000 000 000 000 000 000 000 000 000
201305 (Forecast) 000 000 000 000 000 000 000 000 000
201306 (Forecast) 000 000 000 000 000 000 000 000 000
Sub-total 000 000 000 000 000 000 000 000 000
Overall Total (t) 6359800 870000 000 3714800 600000 114800 000 2800000 000
Overall Total (m3) 3179900 348000 000 1485920 300000 459200 000 1400000 000
Remark I) 20000 tonne soft fill and 8700 tonne good quality rock generated was disposed of at HyD Contract No HY200911
II) Rock fill of 16800 tonne in March 11 and 9400 tonne in April 11 were imported from MTRC Conract 704 site and Zhu Hai Mainland
Footnote 10300 tonne surplus good quality rock stockpiled on site for re-use in Kai Tak Nullah Improvement Works
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
KL201002 Kai Tak development ndash Kai Tak approach channel and Kwun Tong typhoon shelter improvement works (Phase 1)
Inert C amp D
Materials (Soft
Public Fill)
Good Quality
Rock (with break -
down)
Low Quality Rock Broken ConcreteBituminous
MaterialC amp D Waste
Inert C amp D
Materials (Soft
Public Fill)
Rock Sand Fill
2 25 25 25 2 025 18 2 2
(t) (t) (t) (t) (t) (t) (t) (t) (t)
201107 (Actual) 000 000 000 000 000 000 000 000 000
201108 (Actual) 000 000 000 000 000 8860 000 000 000
201109 (Actual) 000 000 000 000 000 1047 000 000 000
Overall Total (t) 000 000 000 000 000 9907 000 000 000
Overall Total (m3) 000 000 000 000 000 39628 000 000 000
Latest Programme
for Geneation of
Materials in each
Reporting Period
Programmed Quantity for Generation of Surpus C amp D Materials
Density (tm3)
Programmed Quantity for Imported of Fill
Department DSD
Contract No DC200812
Project Sewage Interception Scheme in Kowloon City - Pumping Stations Rising Mains and Trunk Sewers
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Jan2009
to
Jun2009
Jul2009 0 0 0 0 0 0 0 0 0 0 0 0
Aug2009 8645 0 0 0 8645 0 0 0 0 0 0 3835
Sep2009 33475 0 0 0 33475 0 50390 400 0 0 0 52
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Quarter
Ending
Total
Quantity
Generated
Actual Quantities Inert C amp D Materials Generated Quarterly
NA
Waste Flow Table As at 30 Sep 2011
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Penta-Ocean - Concentric Joint Venture
Appendix 2Appendix 2Appendix 2Appendix 2
Oct2009 2743 0 0 13 2730 0 0 0 0 0 0 455
Nov2009 23075 0 0 0 23075 0 0 0 0 0 0 845
Dec2009 25881 0 0 176 23999 0 0 0 0 0 0 122
Jan2010 32624 0 0 182 30541 0 0 0 0 0 1000 263
Feb2010 10917 0 0 286 8037 0 0 0 0 0 0 2
Mar2010 12276 0 0 579 6331 0 0 0 0 0 0 155
Apr2010 18351 0 0 573 12541 0 0 0 0 0 0 8
May2010 17639 0 300 281 11744 0 0 0 0 0 0 85
June2010 43635 0 80 250 4023 0 0 100 0 0 0 105
July2010 20385 0 0 60 1968 0 310 0 0 100 428 105
Aug2010 59985 0 0 3220 2768 0 0 0 0 0 0 105
Sep2010 31635 0 0 875 2272 0 0 0 0 0 0 165
Oct2010 54725 0 0 340 5113 0 0 0 0 0 0 195
Nov2010 39765 0 0 880 3085 0 0 0 0 0 0 115
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Broken
Concrete
(See Note 3)
Reused in
the Contract
Reused in
other
Projects
Disposed as
Public Fill
Imported
FillMetals
Paper
Cardboar
d
Plastics
(see Note
2)
Others eg
general
refuse
(in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in msup3) (in kg) (in kg) (in kg) Battery(No) Oil(in L) (in msup3)
Dec2010 26985 0 0 2215 473 0 0 0 0 0 0 105
Jan2011 523 0 0 0 514 0 0 0 0 0 0 9
Feb2011 440 0 0 0 431 0 0 0 0 0 0 9
Mar2011 1673 0 1055 0 603 0 0 0 0 0 0 15
Apr2011 1199 0 982 0 202 0 0 0 0 0 0 15
May2011 6745 0 0 0 652 0 0 0 0 0 0 225
Jun2011 708 0 0 0 693 0 0 0 0 0 0 15
Jul2011 781 0 0 340 429 0 0 0 0 0 0 12
Aug2011 5685 0 0 0 552 0 0 0 0 0 0 165
Sep2011 1258 0 0 20 530 0 510 150 30 0 0 18
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Actual Quantities of C amp D Wastes Generated Quarterly
Chemical Waste
Actual Quantities Inert C amp D Materials Generated Quarterly
Quarter
Ending
Total
Quantity
Generated
As at 30 Sep 2011
Appendix 2Appendix 2Appendix 2Appendix 2
Total 56568 0 2417 10290 42877 0 51210 650 30 100 1428 860
Notes 1 The waste flow table shall also include C amp D materials that are specified in the Contract to be imported for use at the Site
2 Plastics refer to plastic bottles containers plastic sheets foam from packaging material
3 Broken concrete for recycling into aggregates
Appendix 2Appendix 2Appendix 2Appendix 2
Hsin Chong Construction Co Ltd
12
Name of Department ArchSDCEDDDSDEMSDHyDWSD Contract No DC200921
Monthly Summary Waste Flow Table for 201109 (YearMonth)
Month
Actual Quantities of Inert CampD Materials Generated Monthly Actual Quantities of CampD Wastes Generated Monthly
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
Jan 5183 1374 0 0 3809 0 0 0 0 0 28
Feb 14014 1593 0 0 12421 0 0 0 0 0 0
Mar 25439 3828 0 0 21611 0 0 0 0 0 94
Apr 21663 2103 0 0 1956 0 0 0 0 0 766
May 7465 20085 0 0 54565 0 0 0 0 0 39
June 2179 1143 0 0 1036 0 0 0 0 0 571
Sub-total 143128 30126 0 0 113002 0 0 0 0 0 2947
July 43764 20143 0 0 23621 0 0 0 0 0 1384
Aug 12573 3945 0 0 8628 0 0 0 0 0 293
Sept 9215 3985 0 0 523 0 0 0 0 0 445
Oct
Nov
Dec
Total 208680 58199 00 00 150481 00 00 00 00 00 507
Hsin Chong Construction Co Ltd
22
Forecast of Total Quantities of CampD Materials to be Generated from the Contract
Total Quantity
Generated
Hard Rock and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
Disposed as
Public Fill Imported Fill Metals
Paper cardboard
packaging
Plastics
(see Note 3) Chemical Waste
Others eg
general refuse
(in m3) (in m3) (in m3) (in m3) (in m3) (in m3) (in kg) (in kg) (in kg) (in kg) (in m3)
23180
7200 7700 0 8280 0 0 0 0 0 50
Notes (1) The performance targets are given in PS Clause 134A5(4)
(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site
(3) Plastics refer to plastic bottlescontainers plastic sheetsfoam from packaging material
Title Summary Waste Flow Table
Contract Title and No The Integrated Contract for Construction of Public Rental Housing Development at Kai Tak Site 1B (20090006)
Name of Department Hong Kong Housing Authority Appendix III
Rev 19
Monthly Summary Waste Flow Table for Year 2011 [to be submitted not later than the 5th day of each month for the past month report]
(All quantities shall be rounded off to 2 decimal places)
Month
Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act Est Act
Jan 800000 250610 000 000 150000 000 150000 000 500000 250610 1000 11117 000 016 000 000 000 050 20000 2618Feb 1600000 161392 000 000 150000 62694 250000 000 1200000 98698 000 9607 000 075 000 000 000 000 20000 3117Mar 1600000 4551085 000 000 200000 737812 250000 000 1150000 3813273 000 60910 100 085 000 000 050 000 20000 3909
Apr 1600000 1744895 000 000 200000 520462 250000 000 1150000 1224433 5000 28299 000 058 000 000 000 000 30000 6966
May 800000 954322 000 000 200000 895220 150000 000 450000 59102 000 36755 000 145 000 000 000 000 30000 15211
June 600000 1523974 000 000 200000 1325967 50000 74100 350000 123907 000 2143 100 070 000 000 050 000 30000 14247
Sub-total 7000000 9186278 000 000 1100000 3542155 1100000 74100 4800000 5570023 6000 148831 200 449 000 000 100 050 150000 46068
July 1250000 1093990 000 000 1000000 999590 000 000 250000 94400 5000 1560 100 055 000 000 000 000 40000 19600
Aug 510000 365821 000 000 500000 360868 000 000 10000 4953 5000 9291 100 110 000 000 000 000 30000 27579
Sept 55000 41288 000 000 50000 41288 000 000 5000 000 5000 6898 100 080 000 000 050 000 30000 24772
Oct 30000 000 20000 000 10000 5000 300 000 000 30000
Nov 30000 000 10000 000 20000 5000 300 000 000 50000
Dec 50000 000 10000 000 40000 5000 400 000 050 50000
Total 8925000 10687377 000 000 2690000 4943901 1100000 74100 5135000 5669376 36000 166580 1500 694 000 000 200 050 380000 118019
Notes (1) The waste reduction targets are stated in PREB819955(2) The waste flow table shall also include CampD materials that are specified in the Contract to be imported for use at the Site(3) Plastics refer to plastic bottlescontainers plastic sheetsforam from packaging material
(in 000 kg) (in 000 kg)
Chemical WasteOthers
eg general refuse
(a) (b) (c) (d) (e) (in 000 kg) (in 000 kg) (in 000 kg)
(i) (j)
Total Quantity Generated
Broken Concrete
suitable for
recycling Reused in the Contract
Marine Mud Reused in
the ContractDisposed as
Public Fill MetalsPaper cardboard
Packaging
Plastics
(see Note 3)
Estimate Actual Quantities of Inert CampD Materials Generated Monthly (in 000kg) Estimated Actual Quantities of CampD Wastes Generated Monthly
(a) (b) (c) (d) (e=a-b-c-d) (f) (g) (h)
3 of 5
Monthly WFT(revised July 2005)
3WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0995 0000 0000 0000 0995 0172 1350 0000 0000 0000 0002
February 0543 0000 0035 0000 0508 0069 0000 0000 0000 0000 0004
March 1274 0000 0113 0000 1161 0302 1090 0000 0000 0000 0000
April 0789 0000 0000 0000 0789 0158 0000 0205 0000 0000 0010
May 0698 0000 0000 0000 0698 0265 0000 0000 0000 0000 0005
June 0634 0000 0000 0000 0634 0216 1730 0000 0000 0000 0007
Half-year total 4933 0000 0148 0000 4785 1182 4170 0205 0000 0000 0028
July 0706 0000 0000 0000 0706 0216 0000 0000 0000 0000 0013
August 0740 0000 0223 0000 0517 0300 0000 0000 0000 0000 0006
September 0606 0000 0531 0000 0075 0531 0000 0000 0000 0000 0011
October 0000
November 0000
December 0000
Yearly Total 6985 0000 0902 0000 6083 2229 4170 0205 0000 0000 0058
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
6WSD08
Total Quantities
Generated
Broken Concrete(including rock for
recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic(bottlescontainers
plastic sheets foams
from package
material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) 0 (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 0149 0003 0000 0000 0145 0008 0001 0002 0003 2534 0036
February 0052 0003 0000 0000 0049 0000 0002 0003 0002 1322 0005
March 0200 0003 0000 0000 0197 0008 0003 0003 0003 0005 0005
April 0136 0003 0000 0000 0133 0007 0003 0004 0004 0006 0007
May 0152 0005 0000 0000 0147 0047 0003 0005 0004 0006 0005
June 0096 0000 0000 0000 0096 0006 0003 0005 0003 0006 0047
Half-year total 0785 0018 0000 0000 0766 0076 0015 0022 0019 3879 0105
July 0191 0003 0000 0000 0187 0000 0004 0006 0003 0005 0016
August 0318 0003 0000 0000 0315 0062 0003 0004 0003 0006 0011
September 0197 0000 0000 0000 0197 0008 0004 0005 0004 0005 0003
October 0000
November 0000
December 0000
Yearly Total 1490 0025 0000 0000 1466 0146 0026 0037 0029 3895 0135
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
Monthly WFT(revised July 2005)
7WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 05752 00065 00200 00000 05487 00000 00000 00010 00010 00005 00035
February 04164 00045 00150 00000 03969 00000 00000 00010 00010 00005 00045
March 08517 00043 00180 00000 08294 00000 00000 00010 00010 00005 00044
April 10909 00089 00320 00000 10500 00000 00000 00010 00010 00005 00213
May 02444 00056 00195 00000 02193 00000 00000 00010 00010 00005 00146
June 04393 00048 00361 00000 03984 00000 00000 00010 00010 00005 00077
Half-year total 36179 00346 01406 00000 34427 00000 00000 00060 00060 00030 00560
July 10778 00078 00430 00000 10270 00000 00000 00010 00010 00005 00286
August 09390 00072 00243 00000 09075 00000 00000 00010 00010 00005 00253
September 08039 00039 00352 00000 07648 00000 00000 00010 00010 00005 00165
October 00000
November 00000
December 00000
Yearly Total 64386 00535 02431 00000 61420 00000 00000 00090 00090 00045 01264
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Actual Quantities of Other CampD Materials Wastes Generated
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
Contract No
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3)
Month
8WSD08
Total Quantities
Generated
Broken Concrete
(including rock
for recycling into
aggregates)
Reused in the
Contract
Reused in Other
Projects
Disposed as
Public Fill
Imported Fill
MaterialMetal
Paper Cardboard
Packaging
Plastic
(bottlescontainer
s plastic sheets
foams from
package material)
Chemical Waste
Others (eg
General Refuse
etc)
[a+b+c+d) (a) (b) (c) (d) (in 000kg) (in 000kg) (in 000kg) (in 000kg) (in 000m3)
January 02255 00000 00000 00000 02255 00000 00010 00300 00010 00000 00011
February 00664 00000 00000 00000 00664 00000 00000 00000 00000 03000 00000
March 04084 00000 00000 00000 04084 00000 00000 01270 00000 00000 00000
April 03760 00000 00000 00000 03760 00000 00000 00000 00000 00000 00000
May 04874 00000 00000 00000 04874 00000 00000 00000 00000 00000 00079
June 03937 00000 00000 00000 03937 00000 13000 01010 00000 00000 00036
Half-year total 19575 00000 00000 00000 19575 00000 13010 02580 00010 03000 00125
July 00290 00000 00000 00000 00290 00000 00000 00670 00000 00000 00026
August 00000 00000 00000 00000 00000 00000 00000 00090 00010 00000 00022
September 08401 00000 00000 00000 08401 00000 00000 00000 00000 00000 00025
October
November
December
Yearly Total 28266 00000 00000 00000 28266 00000 13010 03340 00020 03000 00198
Month
Actual Quantities of Inert CampD Materials Generated Imported (in 000 m3) Actual Quantities of Other CampD Materials Wastes Generated
Water Supplies Department
Monthly Summary Waste Flow Table
for Contract with Waste Management Plan under ETWB TCW No 152003
Reporting Year 2011
Contract No
(To be submitted to CampD MM Coordinator of Respective DivisionRegion via Engineers Representative before 15th of the following month)
1016EM10 - Chilled Water Pipe Laying Works at North Apron Area
for District Cooling System at Kai Tak Development
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
07666356 NA 05-Sep-11 HH7577 1323 Mixed rock and soil 1348 08-Sep-11 2368 1110 29970
07666357 NA 05-Sep-11 FC3995 1340 Mixed rock and soil 1408 08-Sep-11 2294 1020 27540
07666358 NA 05-Sep-11 HH7577 1426 Mixed rock and soil 1454 08-Sep-11 2380 1130 30510
07666359 NA 05-Sep-11 HH7577 1529 Soil 1553 08-Sep-11 2348 1110 29970
07666360 NA 05-Sep-11 FC3995 1616 Mixed rock and soil 1646 08-Sep-11 2264 1000 27000
07666361 NA 05-Sep-11 HH7577 1628 Mixed rock and soil 1654 08-Sep-11 2323 1070 28890
07808960 0003792001 09-Sep-11 HH7577 817 Mixed rock and soil 849 15-Sep-11 2346 1090 29430
07808961 0003792002 09-Sep-11 LS2926 830 Mixed rock and soil 900 15-Sep-11 2322 1070 28890
07808962 0003792003 09-Sep-11 GB3193 845 Soil 912 15-Sep-11 2209 910 24570
07808963 0003792004 09-Sep-11 EP408 850 Soil 925 15-Sep-11 2267 990 26730
07808964 0003792005 09-Sep-11 LS2926 935 Mixed rock and soil 1013 15-Sep-11 2315 1070 28890
07808965 0003792006 09-Sep-11 GB3193 1000 Mixed rock and soil 1028 15-Sep-11 2262 950 25650
07808966 0003792007 09-Sep-11 PD2592 1005 Mixed rock and soil 1039 15-Sep-11 2241 950 25650
07808967 0003792008 09-Sep-11 GB3193 1100 Mixed rock and soil 1136 15-Sep-11 2261 960 25920
07808968 0003792009 09-Sep-11 HH7577 1115 Mixed rock and soil 1148 15-Sep-11 2416 1150 31050
07808970 0003792011 09-Sep-11 MR7288 1408 Broken Concrete 1432 15-Sep-11 2080 660 17820
07808971 0003792012 14-Sep-11 GH1190 910 Mixed rock and soil 941 19-Sep-11 2266 990 26730
07808972 0003792013 14-Sep-11 GH1190 1055 Broken Concrete 1123 19-Sep-11 2270 1020 27540
07808973 0003792014 14-Sep-11 GH1190 1318 Broken Concrete 1346 19-Sep-11 2156 900 24300
07808974 0003792015 14-Sep-11 GH1190 1250 Mixed rock and soil 1514 19-Sep-11 2171 910 24570
07808975 0003792016 14-Sep-11 GH1190 1607 Broken Concrete 1637 19-Sep-11 2066 800 21600
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808976 0003792017 10-Sep-11 MR7288 1610 Broken Concrete 1640 16-Sep-11 2309 900 24300
07808977 0003792018 10-Sep-11 MR7288 1350 Mixed rock and soil 1417 16-Sep-11 2276 870 23490
07808978 0003792019 10-Sep-11 MR7288 1112 Mixed rock and soil 1134 16-Sep-11 2231 810 21870
07808979 0003792020 10-Sep-11 MR7288 913 Broken Concrete 940 16-Sep-11 2380 960 25920
07808980 0003792021 14-Sep-11 EP408 1345 Mixed rock and soil 1409 19-Sep-11 2325 1060 28620
07808981 0003792022 14-Sep-11 CG1498 1342 Mixed rock and soil 1410 19-Sep-11 2270 1040 28080
07808982 0003792023 14-Sep-11 EP408 1444 Mixed rock and soil 1504 19-Sep-11 2227 960 25920
07808983 0003792024 14-Sep-11 CG1498 1440 Mixed rock and soil 1511 19-Sep-11 2265 1040 28080
07808984 0003792025 14-Sep-11 EP408 1530 Mixed rock and soil 1559 19-Sep-11 2308 1050 28350
07808985 0003792026 14-Sep-11 CG1498 1543 Mixed rock and soil 1608 19-Sep-11 2252 1020 27540
07808986 0003792027 14-Sep-11 EP408 1630 Mixed rock and soil 1658 19-Sep-11 2322 1060 28620
07808987 0003792028 14-Sep-11 CG1498 1640 Mixed rock and soil 1706 19-Sep-11 2236 1010 27270
07808988 0003792029 15-Sep-11 CG1498 825 Mixed rock and soil 852 20-Sep-11 2184 950 25650
07808989 0003792030 15-Sep-11 CG1498 930 Mixed rock and soil 953 20-Sep-11 2295 1060 28620
07808990 0003792031 15-Sep-11 GH1190 850 Broken Concrete 921 20-Sep-11 2294 1030 27810
07808991 0003792032 15-Sep-11 GH1190 1040 Broken Concrete 1113 20-Sep-11 2215 940 25380
07808992 0003792033 15-Sep-11 GH1190 1335 Broken Concrete 1406 20-Sep-11 2166 920 24840
07808993 0003792034 15-Sep-11 GH1190 1500 Broken Concrete 1529 20-Sep-11 2180 920 24840
07808994 0003792035 15-Sep-11 GH1190 1632 Broken Concrete 1701 20-Sep-11 2160 900 24300
07808995 0003792036 16-Sep-11 GH1190 850 Broken Concrete 917 21-Sep-11 2265 1020 27540
07808996 0003792037 16-Sep-11 GH1190 1100 Mixed rock and soil 1130 21-Sep-11 2344 1100 29700
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07808997 0003792038 16-Sep-11 GH1190 1415 Mixed rock and soil 1445 21-Sep-11 2297 1040 28080
07808998 0003792039 16-Sep-11 GH1190 1600 Mixed rock and soil 1629 21-Sep-11 2266 1020 27540
07808999 0003792040 17-Sep-11 GH1190 915 Mixed rock and soil 947 22-Sep-11 2266 1000 27000
07809000 0003792041 15-Sep-11 PD2592 1025 Mixed rock and soil 1055 20-Sep-11 2334 1050 28350
07809001 0003792042 15-Sep-11 CG1498 1020 Mixed rock and soil 1055 20-Sep-11 2346 1120 30240
07809002 0003792043 15-Sep-11 EP408 1038 Mixed rock and soil 1105 20-Sep-11 2315 1070 28890
07809003 0003792044 15-Sep-11 CL9989 1220 Mixed rock and soil 1247 20-Sep-11 2217 910 24570
07809004 0003792045 15-Sep-11 GL1498 1215 Mixed rock and soil 1246 20-Sep-11 2348 1120 30240
07809005 0003792046 15-Sep-11 EP408 1217 Mixed rock and soil 1247 20-Sep-11 2260 1000 27000
07809006 0003792047 15-Sep-11 EP408 1625 Mixed rock and soil 1657 20-Sep-11 2386 1140 30780
07809007 0003792048 15-Sep-11 CG1498 1320 Mixed rock and soil 1349 20-Sep-11 2265 1040 28080
07809008 0003792049 16-Sep-11 EP408 825 Broken Concrete 825 20-Sep-11 2290 1020 27540
07809009 0003792050 15-Sep-11 CG1498 1555 Mixed rock and soil 1622 20-Sep-11 2214 980 26460
07809010 0003792051 15-Sep-11 FG3995 950 Soil 1021 20-Sep-11 2244 970 26190
07809011 0003792052 15-Sep-11 DH6986 1000 Mixed rock and soil 1027 20-Sep-11 2241 990 26730
07809012 0003792053 15-Sep-11 FC3995 1100 Mixed rock and soil 1129 20-Sep-11 2258 980 26460
07809013 0003792054 15-Sep-11 DH6986 1110 Mixed rock and soil 1141 20-Sep-11 2323 1070 28890
07809014 0003792055 15-Sep-11 FC3995 1310 Mixed rock and soil 1336 20-Sep-11 2359 1090 29430
07809015 0003792057 15-Sep-11 PJ165 1215 Mixed rock and soil 1345 20-Sep-11 2174 910 24570
07809016 0003792060 15-Sep-11 FC3995 1515 Mixed rock and soil 1546 20-Sep-11 2251 980 26460
07809017 0003792058 15-Sep-11 FC3995 1620 Mixed rock and soil 1652 20-Sep-11 2328 1050 28350
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809018 0003792059 16-Sep-11 FC3995 810 Mixed rock and soil 845 21-Sep-11 2300 1030 27810
07809019 0003792060 15-Sep-11 PJ165 1130 Mixed rock and soil 1207 20-Sep-11 2168 910 24570
07809020 0003792061 16-Sep-11 BL3661 830 Broken Concrete 906 20-Sep-11 2205 980 26460
07809021 0003792063 16-Sep-11 BL3661 1400 Mixed rock and soil 1435 20-Sep-11 2297 1070 28890
07809022 0003792062 16-Sep-11 BL3661 1043 Mixed rock and soil 1117 20-Sep-11 2232 1000 27000
07809023 0003792070 16-Sep-11 BL3661 1600 Mixed rock and soil 1626 20-Sep-11 2232 1010 27270
07809024 0003792068 17-Sep-11 DJ9133 1340 Mixed rock and soil 1408 21-Sep-11 2233 910 24570
07809025 0003792069 17-Sep-11 DJ9133 900 Broken Concrete 938 21-Sep-11 2158 820 22140
07809026 0003792067 17-Sep-11 DJ9133 1110 Broken Concrete 1148 21-Sep-11 2254 930 25110
07809027 0003792064 17-Sep-11 FN8993 908 Mixed rock and soil 938 21-Sep-11 2291 1030 27810
07809028 0003792065 17-Sep-11 FN8993 1110 Mixed rock and soil 1145 21-Sep-11 2219 970 26190
07809029 0003792066 17-Sep-11 FN8993 1403 Mixed rock and soil 1436 21-Sep-11 2298 1040 28080
07809030 0003792072 16-Sep-11 FC3995 919 Mixed rock and soil 955 21-Sep-11 2320 1060 28620
07809031 0003792075 16-Sep-11 FC3995 1310 Mixed rock and soil 1345 21-Sep-11 2255 990 26730
07809032 0003792074 16-Sep-11 FC3995 1420 Mixed rock and soil 1453 21-Sep-11 2325 1070 28890
07809033 0003792071 16-Sep-11 FC3995 1530 Soil 1604 21-Sep-11 2250 980 26460
07809034 0003792073 16-Sep-11 FC3995 1040 Mixed rock and soil 1106 21-Sep-11 2271 1000 27000
07809035 0003792076 20-Sep-11 GH1190 910 Mixed rock and soil 939 24-Sep-11 2183 930 25110
07809036 0003792077 20-Sep-11 DJ9133 1030 Soil 1102 24-Sep-11 2272 950 25650
07809037 0003792078 19-Sep-11 GH1190 1040 Mixed rock and soil 1118 23-Sep-11 2274 1010 27270
07809038 0003792079 19-Sep-11 GH1190 1630 Soil 1702 23-Sep-11 2362 1110 29970
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07809039 0003792080 17-Sep-11 GH1190 1600 Soil 1627 22-Sep-11 2360 1090 29430
07809040 0003792081 19-Sep-11 GH1190 900 Mixed rock and soil 939 23-Sep-11 2301 1040 28080
07809041 0003792082 17-Sep-11 DJ9133 1540 Soil 1610 22-Sep-11 2308 980 26460
07809042 0003792083 17-Sep-11 FN8993 1600 Broken Concrete 1632 22-Sep-11 2203 950 25650
07809043 0003792084 19-Sep-11 FN8993 830 Mixed rock and soil 900 23-Sep-11 2347 1080 29160
07809044 0003792085 19-Sep-11 FN8993 1030 Soil 1107 23-Sep-11 2249 990 26730
07809045 0003792086 19-Sep-11 FN8993 1615 Mixed rock and soil 1652 23-Sep-11 2255 1000 27000
07809046 0003792087 20-Sep-11 FN8993 900 Soil 926 24-Sep-11 2162 900 24300
07809047 0003792089 20-Sep-11 FN8993 1355 Mixed rock and soil 1422 24-Sep-11 2315 1050 28350
07809048 0003792090 20-Sep-11 FN8993 1030 Mixed rock and soil 1102 24-Sep-11 2301 1040 28080
07809049 0003792091 20-Sep-11 GH1190 1036 Mixed rock and soil 1107 24-Sep-11 2226 970 26190
07809050 0003792092 20-Sep-11 GH1190 1400 Mixed rock and soil 1434 24-Sep-11 2265 1010 27270
07809051 0003792093 20-Sep-11 DJ9133 1600 Soil 1621 24-Sep-11 2264 950 25650
07809052 0003792094 20-Sep-11 FN8993 1540 Soil 1613 24-Sep-11 2269 1020 27540
07809053 0003792095 19-Sep-11 DJ9133 1040 Soil 1111 23-Sep-11 2316 990 26730
07809054 0003792096 20-Sep-11 DJ9133 900 Mixed rock and soil 927 24-Sep-11 2328 1020 27540
07809055 0003792097 19-Sep-11 DJ9133 1605 Mixed rock and soil 1639 23-Sep-11 2286 960 25920
07809056 0003792098 19-Sep-11 DJ9133 900 Mixed rock and soil 929 23-Sep-11 2349 1040 28080
07809057 0003792099 17-Sep-11 GH1190 1110 Mixed rock and soil 1147 22-Sep-11 2316 1060 28620
07809058 0003792088 20-Sep-11 DJ9133 1355 Mixed rock and soil 1425 24-Sep-11 2257 940 25380
07809059 0003792100 17-Sep-11 GH1190 1410 Mixed rock and soil 1442 22-Sep-11 2308 1040 28080
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892951 0003792101 23-Sep-11 FN8993 1640 Mixed rock and soil 1715 28-Sep-11 2225 960 25920
07892952 0003792102 23-Sep-11 DJ9133 1635 Mixed rock and soil 1714 28-Sep-11 2272 940 25380
07892953 0003792103 23-Sep-11 GH1190 1645 Mixed rock and soil 1714 28-Sep-11 2208 960 25920
07892954 0003792104 24-Sep-11 DJ9133 900 Mixed rock and soil 934 28-Sep-11 2261 930 25110
07892955 0003792105 24-Sep-11 DJ9133 1040 Mixed rock and soil 1107 28-Sep-11 2311 980 26460
07892956 0003792106 24-Sep-11 GH1190 905 Broken Concrete 938 28-Sep-11 2226 960 25920
07892957 0003792107 24-Sep-11 DJ9133 1330 Mixed rock and soil 1402 28-Sep-11 2289 960 25920
07892958 0003792108 24-Sep-11 DJ9133 1500 Broken Concrete 1529 28-Sep-11 2310 980 26460
07892959 0003792109 24-Sep-11 GH1190 1050 Mixed rock and soil 1122 28-Sep-11 2342 1090 29430
07892960 0003792110 24-Sep-11 GH1190 1345 Mixed rock and soil 1407 28-Sep-11 2232 980 26460
07892961 0003792111 24-Sep-11 GH1190 1500 Mixed rock and soil 1538 28-Sep-11 2263 1010 27270
07892962 0003792112 24-Sep-11 DJ9133 1600 Mixed rock and soil 1700 28-Sep-11 2307 980 26460
07892963 0003792113 24-Sep-11 GH1190 1630 Mixed rock and soil 1707 28-Sep-11 2261 1010 27270
07892964 0003792114 26-Sep-11 FN8993 1025 Mixed rock and soil 1055 29-Sep-11 2239 980 26460
07892965 0003792115 26-Sep-11 FN8993 1330 Soil 1400 29-Sep-11 2343 1080 29160
07892966 0003792116 26-Sep-11 FN8993 1500 Mixed rock and soil 1526 29-Sep-11 2279 1020 27540
07892967 0003792117 26-Sep-11 FN8993 1620 Soil 1651 29-Sep-11 2316 1060 28620
07892968 0003792118 26-Sep-11 GH1190 1030 Mixed rock and soil 1102 29-Sep-11 2240 990 26730
07892969 0003792119 26-Sep-11 GH1190 1325 Soil 1357 29-Sep-11 2231 970 26190
07892970 0003792120 26-Sep-11 GH1190 1450 Mixed rock and soil 1523 29-Sep-11 2338 1090 29430
07892971 0003792121 24-Sep-11 GV8482 1225 Mixed rock and soil 1256 27-Sep-11 2275 890 24030
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892972 0003792122 24-Sep-11 MH1788 1220 Mixed rock and soil 1256 27-Sep-11 2318 870 23490
07892973 0003792123 24-Sep-11 MH1788 1410 Mixed rock and soil 1444 27-Sep-11 2376 910 24570
07892974 0003792124 26-Sep-11 MH1788 1120 Mixed rock and soil 1156 29-Sep-11 2373 910 24570
07892975 0003792125 26-Sep-11 MH1788 1315 Mixed rock and soil 1348 29-Sep-11 2244 790 21330
07892976 0003792126 26-Sep-11 MH1788 1430 Soil 1501 29-Sep-11 2283 830 22410
07892977 0003792127 26-Sep-11 MH1788 1540 Soil 1615 29-Sep-11 2258 800 21600
07892978 0003792128 27-Sep-11 GV8482 1035 Soil 1108 30-Sep-11 2349 890 24030
07892979 0003792129 27-Sep-11 MH1788 1040 Soil 1114 30-Sep-11 2300 850 22950
07892980 0003792130 27-Sep-11 GV8482 1155 Soil 1224 30-Sep-11 2410 950 25650
07892981 0003792131 27-Sep-11 MH1788 1230 Mixed rock and soil 1259 30-Sep-11 2294 840 22680
07892982 0003792132 27-Sep-11 MH1788 1340 Mixed rock and soil 1414 30-Sep-11 2264 810 21870
07892983 0003792133 28-Sep-11 GV8482 1000 Mixed rock and soil 1033 30-Sep-11 2345 940 25380
07892984 0003792134 28-Sep-11 MH1788 1005 Soil 1044 30-Sep-11 2296 840 22680
07892985 0003792135 28-Sep-11 GV8482 1135 Soil 1203 30-Sep-11 2256 840 22680
07892986 0003792136 28-Sep-11 MH1788 1140 Soil 1213 30-Sep-11 2245 800 21600
07892987 0003792137 28-Sep-11 MH1788 1400 Mixed rock and soil 1426 30-Sep-11 2292 840 22680
07892988 0003792138 28-Sep-11 GV8482 1355 Mixed rock and soil 1428 30-Sep-11 2216 810 21870
07892989 0003792139 28-Sep-11 MH1788 1510 Mixed rock and soil 1549 30-Sep-11 2347 890 24030
07892991 0003792141 28-Sep-11 GH1190 1340 Soil 1412 30-Sep-11 2334 1080 29160
07892992 0003792142 28-Sep-11 GH1190 1510 Mixed rock and soil 1545 30-Sep-11 2249 1000 27000
07892993 0003792143 26-Sep-11 GH1190 1610 Soil 1649 29-Sep-11 2235 980 26460
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07892994 0003792144 27-Sep-11 FN8993 910 Soil 942 30-Sep-11 2303 1040 28080
07892995 0003792145 27-Sep-11 FN8993 1030 Soil 1104 30-Sep-11 2274 1010 27270
07892996 0003792146 27-Sep-11 FN8993 1325 Mixed rock and soil 1357 30-Sep-11 2235 980 26460
07892997 0003792147 27-Sep-11 FN8993 1610 Mixed rock and soil 1647 30-Sep-11 2272 1020 27540
07892998 0003792148 27-Sep-11 DJ9133 1330 Mixed rock and soil 1401 30-Sep-11 2264 940 25380
07892999 0003792149 27-Sep-11 DJ9133 1620 Soil 1651 30-Sep-11 2236 910 24570
07893000 0003792150 27-Sep-11 DJ9133 1030 Soil 1104 30-Sep-11 2216 900 24300
07893001 0003792151 27-Sep-11 DJ9133 910 Soil 943 30-Sep-11 2420 1110 29970
07893002 0003792152 27-Sep-11 GH1190 915 Soil 949 30-Sep-11 2309 1070 28890
07893003 0003792153 27-Sep-11 GH1190 1040 Soil 1112 30-Sep-11 2196 950 25650
07893004 0003792154 27-Sep-11 GH1190 1340 Mixed rock and soil 1409 30-Sep-11 2195 930 25110
07893005 0003792155 27-Sep-11 GH1190 1633 Soil 1700 30-Sep-11 2296 1030 27810
07893006 0003792156 28-Sep-11 GH1190 910 Mixed rock and soil 945 30-Sep-11 2301 1040 28080
07893007 0003792157 28-Sep-11 DJ9133 1030 Soil 1059 30-Sep-11 2309 970 26190
07893008 0003792158 28-Sep-11 FN8993 910 Mixed rock and soil 937 30-Sep-11 2256 1000 27000
07893009 0003792159 28-Sep-11 HA5295 835 Broken Concrete 918 30-Sep-11 2190 920 24840
07893010 0003792160 28-Sep-11 GH1190 1040 Soil 1113 30-Sep-11 2274 1020 27540
07893011 0003792161 28-Sep-11 PD2592 810 Mixed rock and soil 848 30-Sep-11 2208 930 25110
07893012 0003792162 28-Sep-11 LA9970 825 Mixed rock and soil 856 30-Sep-11 2195 980 26460
07893013 0003792163 28-Sep-11 DH6986 830 Mixed rock and soil 905 30-Sep-11 2223 990 26730
07893014 0003792164 28-Sep-11 PD2592 920 Mixed rock and soil 957 30-Sep-11 2204 920 24840
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893015 0003792165 28-Sep-11 LA9970 935 Mixed rock and soil 1005 30-Sep-11 2351 1140 30780
07893016 0003792166 28-Sep-11 DH6986 950 Mixed rock and soil 1018 30-Sep-11 2341 1090 29430
07893017 0003792167 28-Sep-11 PD2592 1021 Mixed rock and soil 1054 30-Sep-11 2226 950 25650
07893018 0003792168 28-Sep-11 LA9970 1030 Mixed rock and soil 1109 30-Sep-11 2184 970 26190
07893019 0003792169 28-Sep-11 DH6986 1100 Mixed rock and soil 1130 30-Sep-11 2267 1030 27810
07893020 0003792170 28-Sep-11 PD2592 1110 Mixed rock and soil 1149 30-Sep-11 2227 940 25380
07893021 0003792171 28-Sep-11 LA9970 1300 Mixed rock and soil 1335 30-Sep-11 2378 1170 31590
07893022 0003792172 28-Sep-11 DH6986 1310 Mixed rock and soil 1345 30-Sep-11 2290 1050 28350
07893023 0003792173 28-Sep-11 PD2592 1315 Mixed rock and soil 1349 30-Sep-11 2313 1030 27810
07893024 0003792174 28-Sep-11 LA9970 1415 Mixed rock and soil 1436 30-Sep-11 2280 1070 28890
07893025 0003792175 28-Sep-11 DH6986 1420 Soil 1451 30-Sep-11 2233 1000 27000
07893026 0003792176 28-Sep-11 PD2592 1420 Mixed rock and soil 1454 30-Sep-11 2354 1070 28890
07893027 0003792177 30-Sep-11 GH1190 910 Mixed rock and soil 948 03-Oct-11 2265 1010 27270
07893028 0003792178 30-Sep-11 GH1190 1040 Mixed rock and soil 1110 03-Oct-11 2270 1020 27540
07893029 0003792179 30-Sep-11 GH1190 1340 Mixed rock and soil 1412 03-Oct-11 2293 1040 28080
07893030 0003792180 30-Sep-11 DJ9133 1505 Soil 1539 03-Oct-11 2304 980 26460
07893031 0003792181 28-Sep-11 HA5295 1355 Broken Concrete 1423 30-Sep-11 2249 970 26190
07893032 0003792182 28-Sep-11 HA5295 1200 Broken Concrete 1226 30-Sep-11 2180 920 24840
07893033 0003792183 28-Sep-11 HA5295 1010 Broken Concrete 1042 30-Sep-11 2289 1020 27540
07893034 0003792184 28-Sep-11 HA5295 1640 Broken Concrete 1708 30-Sep-11 2228 950 25650
07893035 0003792185 28-Sep-11 DJ9133 1335 Soil 1404 30-Sep-11 2245 910 24570
Chit No記帳單號
DDF Serial No運載記錄票編號
Disposal Date卸置日期
Vehicle No車輛登記號
碼
DepartureTime from
Site出泥時間
Type of Material物料類別
Arrival Time atDisposalGround到達時間
Received Date收回單日期
Weight In (tonne)入載重量(公噸)
Charged Load(tonne)收費重
量 (公噸)
Amount (HK$)總數 (港幣)
Construction and Demdition Material Disposal Delivery Form
拆建物料運載記錄
07893036 0003792186 28-Sep-11 DJ9133 1510 Mixed rock and soil 1540 30-Sep-11 2273 950 25650
07893037 0003792187 28-Sep-11 DJ9133 1630 Mixed rock and soil 1701 30-Sep-11 2314 980 26460
07893038 0003792188 28-Sep-11 DJ9133 910 Mixed rock and soil 940 30-Sep-11 2321 980 26460
07893039 0003792189 28-Sep-11 FN8993 1015 Mixed rock and soil 1057 30-Sep-11 2273 1010 27270
07893040 0003792190 28-Sep-11 FN8993 1330 Mixed rock and soil 1401 30-Sep-11 2319 1050 28350
07893041 0003792191 28-Sep-11 FN8993 1510 Soil 1540 30-Sep-11 2288 1030 27810
07893042 0003792192 28-Sep-11 FN8993 1630 Soil 1700 30-Sep-11 2276 1030 27810
07893043 0003792193 28-Sep-11 HA5295 1505 Broken Concrete 1538 30-Sep-11 2041 770 20790
07893044 0003792194 28-Sep-11 GH1190 1635 Soil 1708 30-Sep-11 2235 980 26460
07893045 0003792195 30-Sep-11 DJ9133 1330 Soil 1357 03-Oct-11 2246 920 24840
07893046 0003792196 30-Sep-11 FN8993 910 Mixed rock and soil 940 03-Oct-11 2264 1010 27270
07893047 0003792197 30-Sep-11 FN8993 1035 Soil 1100 03-Oct-11 2288 1030 27810
07893048 0003792198 30-Sep-11 FN8993 1340 Soil 1405 03-Oct-11 2304 1040 28080
07893049 0003792199 30-Sep-11 DJ9133 910 Mixed rock and soil 939 03-Oct-11 2289 950 25650
07893050 0003792200 30-Sep-11 DJ9133 1030 Soil 1100 03-Oct-11 2305 970 26190
07893051 0003792201 30-Sep-11 DJ9133 1610 Mixed rock and soil 1647 03-Oct-11 2344 1010 27270
07893052 0003792202 30-Sep-11 FN8993 1510 Mixed rock and soil 1548 03-Oct-11 2276 1020 27540
07893053 0003792203 30-Sep-11 FN8993 1640 Soil 1706 03-Oct-11 2273 1020 27540
07893054 0003792204 30-Sep-11 GH1190 1520 Soil 1558 03-Oct-11 2224 970 26190
07893055 0003792205 30-Sep-11 GH1190 1650 Soil 1719 03-Oct-11 2284 1030 27810